cable trench design

Upload: irshad-khan

Post on 04-Jun-2018

428 views

Category:

Documents


5 download

TRANSCRIPT

  • 8/13/2019 Cable Trench Design

    1/24

    DRN. NAME SIGN DATEPRPD A.K. 20.12.12CHKD S.A 20.12.12 APPD S.A 20.12.12

    OWNER M/S GAIL (INDIA) LTD.

    CONSULTANTENGINEERS INDIA LTD.

    PROJECT:

    SWITCHYARDGAIL PETROCHEMICAL COMPLEX-II, PATA

    TITLE :-CABLE TRENCH - DESIGN

    CALCULATIONSDOC NO:

    M2011EP008A-091REV. NO.

    0

    CONTRACTORS STERLING AND WILSON LIMITED

    ALIF ENGINEERS & PLANNERSMUMBAI

  • 8/13/2019 Cable Trench Design

    2/24

  • 8/13/2019 Cable Trench Design

    3/24

  • 8/13/2019 Cable Trench Design

    4/24

  • 8/13/2019 Cable Trench Design

    5/24

    A) Input Data

    1 Internal Width of the cable Trench = mm2 Thikness of the wall = mm3 Thikness of the Raft = mm4 Depth of the cable trench below the FFL = mm5 Grade of concrete = N/mm26 Density of concrete = = kn/m37 Grade of steel = N/mm28 Density of the soil(DENS) = kN/m39 Surcharge = Kg/m2

    10 Angle of internal friction (f) f

    B) Design of wall

    200

    Coeff of active earth pressure Ka = (1-sin f )/(1+sin f )= 0.33

    Height of Wall H = 2125 mmMaximum pressure at the Base Pa = Ka x DENS x H

    = 12.74Pressure per meter of run = 12.74 kN/mMaximum pressure due to ps = 0.33 x 20 = 6.66

    surcharge/MPressure per meter of run = 6.66 kN/m

    Moment Due to Surcharge + due to soil pressure = 0.50 x 12.74 x 2.125 x 2.125 +3

    6.66 x 2.1252

    = 9.591 + 7.080 = 16.671 Kn-mtr

    Total Moment = 16.671 = 16.671 Kn-mtr

    2125

    23252025

    Fe 500

    DESIGN OF CABLE TRENCH TYPE -A-A

    1500200200

    15006.66

    182000

    30

    kN/m2

    kN/m2

    12.74

    kN/m2 kN/m2Pressure Diagram

    5 Alif Engineers PlannersSterling Wilson Ltd

  • 8/13/2019 Cable Trench Design

    6/24

    -Main Reinforcement( At Face of wall):Let thickness of Wall = 200 mmEffective Depth = 200 - 20 - 5.00 = 175.00 mm

    Mu/bd^2 = 1.5 x 16.67 x 10^6 = 0.81651000 x 175.00 ^2

    Corresponding reinforcement % = pt = 0.297983

    Area of steel=Ast=ptxBd/100 = 0.297983 x 1000 x 175.001 x 100

    = 521.47 mmMin area of steel = 0.12 x 1000 x 200

    1 x 100= 240 mm^2

    Spacing of steel required = 151 mm C/CProvide Main reinforcement fo dia 10 @ 150 mm C/C At face

    Provide Ast = 523 mm

    - Distribution Reinforcement;secondary reinforcement = 0.12 x 1000 X 20015% for MS and 12% for tor steel 1 x 100

    = 240 mmCorresponding reinforcementspacing = ast*100/Ast = = 0.785 x 8 ^2 x 1000

    240= 209 mm

    Minimum clear spacing=3xdeff = 3 x 175.00= 525 mm

    Provide Sec reinforcement of dia 8 @ 200 mm C/CProvide Ast = 251 mm

    C) Design of the BaseSlab:Load calculationWall load = 0.200 x 2.125 x 1 x 25 = 10.625 KnSecond wall = = 10.625 KnSelf wt of slab = 0.200 x 1.9 x 1 x 25 = 9.5 KnLoad due to cable SAND FILLING

    1 = 2.125 x 2 x 1 x 19 = 60.563 Kn

    Total 91.313 Kn

    Pmax = P = = 48.06 KN/m^2 A 1.9 x 1

    Moment calculation at base slab48.059 kn/mtr

    1.7

    91.3125

    6 Alif Engineers PlannersSterling Wilson Ltd

  • 8/13/2019 Cable Trench Design

    7/24

    Maximum Moment at the Mid = = 48.059 x 1.425^28

    = 17.361 Kn-mtr -Main Reinforcement( at center):Let thickness of Wall = 200 mmEffective Depth = 200 - 100 - 5.00 = 95.00 mm

    Mu/bd^2 = 1.5 x 17.36 x 10^6 = 2.88551000 x 95.00 ^2

    Corresponding reinforcement % = pt = 0.874

    Area of steel=Ast=ptxBd/100 = 0.873504 x 1000 x 95.001 x 100

    = 829.8287 mmMin area of steel = 0.12 x 1000 x 200

    1 x 100= 240 mm^2

    Spacing of steel required = 95 mm C/CProvide Main reinforcement fo dia 10 @ 150 mm C/C at Bottom of slabProvide Ast = 523 mm

    - Distribution Reinforcement;secondary reinforcement = 0.12 x 1000 X 20015% for MS and 12% for tor steel 1 x 100

    = 240 mmCorresponding reinforcementspacing = ast*100/Ast = = 0.785 x 8 ^2 x 1000

    240= 209 mm

    Minimum clear spacing=3xdeff = 3 x 95.00= 285 mm

    Provide secondary reinforcementat spacing = 170 mmProvide Sec reinforcement of dia 8 @ 200 mm C/CProvide Ast = 251 mm

    7 Alif Engineers PlannersSterling Wilson Ltd

  • 8/13/2019 Cable Trench Design

    8/24

    A) Input Data

    1 Internal Width of the cable Trench = mm2 Thikness of the wall = mm

    3 Thikness of the Raft = mm4 Depth of the cable trench below the FFL = mm5 Grade of concrete = N/mm26 Density of concrete = = kn/m37 Grade of steel = N/mm28 Density of the soil(DENS) = kN/m39 Surcharge = Kg/m2

    10 Angle of internal friction (f) f11 Live load due to the cable = kg/mtr

    B) Design of wall

    1075

    200

    800

    150

    Fe 50018

    2000

    30

    800150

    2001275

    DESIGN OF CABLE TRENCH TYPE -B-B

    25

    Pressure Diagram

    6.456.66kN/m2 kN/m2

    20

    8 Alif Engineers PlannersSterling Wilson Ltd

  • 8/13/2019 Cable Trench Design

    9/24

    Coeff of active earth pressure Ka = (1-sin f )/(1+sin f )= 0.33

    Height of Wall H = 1075 mmMaximum pressure at the Base Pa = Ka x DENS x H

    = 6.45Pressure per meter of run = 6.45 kN/m

    Maximum pressure due to ps = 0.33 x 20 = 6.66surcharge/MPressure per meter of run = 6.66 kN/m

    Moment Due to Surcharge + due to soil pressure = 0.50 x 6.45 x 1.075 x 1.075 +3

    6.66 x 1.0752

    = 1.242 + 3.582 = 4.823 Kn-mtr

    Total Moment = 4.823 = 4.823 Kn-mtr

    -Main Reinforcement( At face of wall):

    Let thickness of Wall = 150 mmEffective Depth = 150 - 20 - 5.00 = 125.00 mm

    Mu/bd^2 = 1.5 x 4.82 x 10^6 = 0.4631000 x 125.00 ^2

    Corresponding reinforcement % = pt = 0.164722

    Area of steel=Ast=ptxBd/100 = 0.164722 x 1000 x 125.001 x 100

    = 205.90 mmMin area of steel = 0.12 x 1000 x 150

    1 x 100= 180 mm^2

    Spacing of steel required = 244 mm C/C

    Provide Main reinforcement fo dia 8 @ 200 mm C/C At Each Face

    Provide Ast = 251 mm

    - Distribution Reinforcement;secondary reinforcement = 0.12 x 1000 X 15015% for MS and 12% for tor steel 1 x 100

    = 180 mmCorresponding reinforcementspacing = ast*100/Ast = = 0.785 x 8 ^2 x 1000

    180= 279 mm

    Minimum clear spacing=3xdeff = 3 x 125.00= 375 mm

    Provide Sec reinforcement of dia 8 @ 200 mm C/CProvide Ast = 251 mm

    C) Design of the BaseSlab:Load calculationWall load = 0.150 x 1.075 x 1 x 25 = 4.0313 KnSecond wall = = 4.0313 KnSelf wt of slab = 0.200 x 1.1 x 1 x 25 = 5.5 Kn

    Total 13.563 Kn

    kN/m2

    kN/m2

    9 Alif Engineers PlannersSterling Wilson Ltd

  • 8/13/2019 Cable Trench Design

    10/24

    Pmax = P = = 12.33 KN/m^2 A 1.1 x 1

    Moment calculation at base slab12.330 kn/mtr

    0.95

    Maximum Moment at the Mid = = 12.330 x 0.7^28

    = 1.391 Kn-mtr -Main Reinforcement( At face):Let thickness of Wall = 200 mmEffective Depth = 200 - 100 - 5.00 = 95.00 mm

    Mu/bd^2 = 1.5 x 1.39 x 10^6 = 0.23121000 x 95.00 ^2

    Corresponding reinforcement % = pt = 0.054

    Area of steel=Ast=ptxBd/100 = 0.053972 x 1000 x 95.001 x 100

    = 51.27363mm

    Min area of steel = 0.12 x 1000 x 2001 x 100

    = 240 mm^2Spacing of steel required = 209 mm C/CProvide Main reinforcement fo dia 8 @ 200 mm C/C at center of wallProvide Ast = 251 mm- Distribution Reinforcement;secondary reinforcement = 0.12 x 1000 X 20015% for MS and 12% for tor steel 1 x 100

    = 240 mmCorresponding reinforcementspacing = ast*100/Ast = = 0.785 x 8 ^2 x 1000

    240

    = 209 mmMinimum clear spacing=3xdeff = 3 x 95.00= 285 mm

    Provide secondary reinforcementat spacing = 170 mmProvide Sec reinforcement of dia 8 @ 200 mm C/CProvide Ast = 251 mm

    13.5625

    10 Alif Engineers PlannersSterling Wilson Ltd

  • 8/13/2019 Cable Trench Design

    11/24

    Design of Cable trench Cover Slab For Type B-B

    In put data

    1 Width of the slab(Ly) = 300 mm2 Length of the slab(Lx) = 940 mm

    C/c of support = 840 mm3 Thikness of the slab = 75 mm4 Live load = 1000 kg/mm25 Density of concrete = = 25 kn/m36 Grade of concrete = 20 N/mm27 Grade of steel = Fe 500 N/mm28 Clear cover = 15 mm

    Load calculation

    Dead Load = 0.075 x 25 = 1.875 Kn/m2Live load = = 10 Kn/m2

    Total 11.875 Kn/m2

    ultimate Load = 1.5 x 11.875 = 17.8125 Kn/m^2

    Ultimate Moment (Mu) = WxL^28

    = 17.8125 x 0.84 x 0.848

    = Kn-m

    Mu = = 0.50b x d^2 1000 x 56 x 56

    0.14189= 0.14189 x 1000 x 56.00

    1 x 100= 79.5 mm= 0.12 x 1000 x 75

    1 x 100= 90 mm

    Spacing of steel required = 558 mm C/CProvide Main reinf. dia 8 @ 150 mm C/C ( 3 Y 8)Provide Ast = 334.933 mm

    - Distribution Reinforcement;= 0.12 x 1000 x 100

    15% for MS and 12% for tor steel 1 x 100= = 120 mm

    Spacing of steel required = 419 mm C/C

    = 5 x 56.00= 280 mmProvide Dist reinforcement fo 8 @ 200 mm C/CProvide Ast = 251.2 mm

    Check for the Deflection :

    Fs = 0.58 x Fy X Area of cross section of steel required Area of cross section of steel Provided

    = 0.58 x 415 X

    = N/mm2pt provided = 0.5981Modification Factor = 2

    L = 0.840 = 15 < 40 Safed 0.056

    334.957.10

    Min area of steel

    secondary reinforcement

    1.57

    1.57

    Corresponding reinforcement % = pt Area of steel=Ast

    req=ptxBd/100

    Minimum clear spacing=3xdeff

    79.5

  • 8/13/2019 Cable Trench Design

    12/24

    Sterling Wilson Ltd. 12 Alif Engineers Planners

    A) Input Data

    1 Internal Width of the cable Trench = mm2 Thikness of the wall = mm3 Thikness of the Raft = mm4 Depth of the cable trench below the FFL = mm5 Grade of concrete = N/mm26 Density of concrete = = kn/m37 Grade of steel = N/mm28 Density of the soil(DENS) = kN/m39 Surcharge = Kg/m2

    10 Angle of internal friction (f) f11 Live load due to the cable = kg/mtr

    B) Design of wall

    825

    150

    Coeff of active earth pressure Ka = (1-sin f )/(1+sin f )= 0.33

    Height of Wall H = 825 mmMaximum pressure at the Base Pa = Ka x DENS x H

    = 4.95Pressure per meter of run = 4.95 kN/mMaximum pressure due to ps = 0.33 x 20 = 6.66

    surcharge/MPressure per meter of run = 6.66 kN/m

    Moment Due to Surcharge + due to soil pressure = 0.50 x 4.95 x 0.825 x 0.825 +3

    6.66 x 0.8252

    = 0.561 + 2.749 = 3.310 Kn-mtr

    Total Moment = 3.310 = 3.310 Kn-mtr

    9752025

    Fe 500

    DESIGN OF CABLE TRENCH TYPE C-C

    800150150

    150

    800

    182000

    30

    Pressure Diagram

    kN/m2

    kN/m2

    6.66 4.95kN/m2 kN/m2

    12 Alif Engineers PlannersSterling Wilson Ltd.

  • 8/13/2019 Cable Trench Design

    13/24

    Sterling Wilson Ltd. 13 Alif Engineers Planners

    -Main Reinforcement( at center of wall):Let thickness of Wall = 150 mmEffective Depth = 150 - 75 - 5.00 = 70.00 mm

    Mu/bd^2 = 1.5 x 3.31 x 10^6 = 1.01321000 x 70.00 ^2

    Corresponding reinforcement % = pt = 0.375403

    Area of steel=Ast=ptxBd/100 = 0.375403 x 1000 x 70.001 x 100

    = 262.78 mmMin area of steel = 0.12 x 1000 x 150

    1 x 100= 180 mm^2

    Spacing of steel required = 299 mm C/CProvide Main reinforcement fo dia 8 @ 150 mm C/C at center

    Provide Ast = 335 mm

    - Distribution Reinforcement;

    secondary reinforcement = 0.12 x 1000 X 15015% for MS and 12% for tor steel 1 x 100

    = 180 mmCorresponding reinforcementspacing = ast*100/Ast = = 0.785 x 8 ^2 x 1000

    180= 279 mm

    Minimum clear spacing=3xdeff = 3 x 70.00= 210 mm

    Provide Sec reinforcement of dia 8 @ 250 mm C/CProvide Ast = 201 mm

    C) Design of the BaseSlab:Load calculationWall load = 0.150 x 0.825 x 1 x 25 = 3.0938Second wall = = 3.0938Self wt of slab = 0.150 x 1.1 x 1 x 25 = 4.125Load due to cable SAND FILLING

    1 = 0.825 x 1 x 1 x 17 = 11.22

    Total 21.533

    Pmax = P = = 19.58 KN/m^2 A 1.1 x 1

    21.5325

    13 Alif Engineers PlannersSterling Wilson Ltd.

  • 8/13/2019 Cable Trench Design

    14/24

  • 8/13/2019 Cable Trench Design

    15/24

    Sterling Wilson Ltd. 15 Alif Engineers Planners

    15 Alif Engineers PlannersSterling Wilson Ltd.

  • 8/13/2019 Cable Trench Design

    16/24

    Sterling Wilson Ltd. 16 Alif Engineers Planners

    KnKnKn

    Kn

    Kn

    16 Alif Engineers PlannersSterling Wilson Ltd.

  • 8/13/2019 Cable Trench Design

    17/24

    Sterling Wilson Ltd. 17 Alif Engineers Planners

    17 Alif Engineers PlannersSterling Wilson Ltd.

  • 8/13/2019 Cable Trench Design

    18/24

    Design of Cable trench Cover Slab For Type C-CIn put data

    1 Width of the slab(Ly) = 300 mm2 Length of the slab(Lx) = 950 mm

    C/c of support = 850 mm3 Thikness of the slab = 75 mm4 Live load = 1000 kg/mm25 Density of concrete = = 25 kn/m36 Grade of concrete = 20 N/mm27 Grade of steel = Fe 500 N/mm28 Clear cover = 15 mm

    Load calculation

    Dead Load = 0.075 x 25 = 1.875 Kn/m2Live load = = 10 Kn/m2

    Total 11.875 Kn/m2

    ultimate Load = 1.5 x 11.875 = 17.8125 Kn/m^2

    Ultimate Moment (Mu) = WxL^28

    = 17.8125 x 0.85 x 0.858

    = Kn-m

    Mu = = 0.51b x d^2 1000 x 56 x 56

    0.14537= 0.14537 x 1000 x 56.00

    1 x 100= 81.4 mm

    = 0.12 x 1000 x 751 x 100

    = 90 mmSpacing of steel required = 872 mm C/CProvide Main reinforcement 8 @ 200 mm C/C (3 Y 8)Provide Ast = 251.2 mm- Distribution Reinforcement;

    = 0.12 x 1000 x 10015% for MS and 12% for tor steel 1 x 100

    = = 120 mmSpacing of steel required = 419 mm C/C

    = 5 x 56.00= 280 mm

    Provide Dist reinforcement fo 8 @ 250 mm C/C

    Provide Ast = 200.96 mmCheck for the Deflection :

    Fs = 0.58 x Fy X Area of cross section of steel required Area of cross section of steel Provided

    = 0.58 x 415 X

    = N/mm2pt provided = 0.44857Modification Factor = 1.8

    L = 0.850 = 15 < 36 Safed 0.056

    1.61

    1.61

    Corresponding reinforcement % = pt Area of steel=Ast

    req=ptxBd/100

    251.278.00

    Min area of steel

    secondary reinforcement

    Minimum clear spacing=3xdeff

    81.4

    18 Alif Engineers PlannersSterling Wilson Ltd.

  • 8/13/2019 Cable Trench Design

    19/24

    A) Input Data

    1 Internal Width of the cable Trench = mm2 Thikness of the wall = mm

    3 Thikness of the Raft = mm4 Depth of the cable trench below the FFL = mm5 Grade of concrete = N/mm26 Density of concrete = = kn/m37 Grade of steel = N/mm28 Density of the soil(DENS) = kN/m39 Surcharge = Kg/m2

    10 Angle of internal friction (f) f

    B) Design of wall

    200

    Coeff of active earth pressure Ka = (1-sin f )/(1+sin f )= 0.33

    Height of Wall H = 2125 mmMaximum pressure at the Base Pa = Ka x DENS x H

    = 12.74Pressure per meter of run = 12.74 kN/mMaximum pressure due to ps = 0.33 x 20 = 6.66

    surcharge/MPressure per meter of run = 6.66 kN/m

    Moment Due to Surcharge + due to soil pressure = 0.50 x 12.74 x 2.125 x 2.125 +

    36.66 x 2.1252

    = 9.591 + 7.080 = 16.671 Kn-mtr

    Total Moment = 16.671 = 16.671 Kn-mtr

    -Main Reinforcement( At Face of wall):Let thickness of Wall = 200 mmEffective Depth = 200 - 20 - 5.00 = 175.00 mm

    kN/m2 kN/m2Pressure Diagram

    kN/m2

    kN/m2

    2125

    15006.66 12.74

    25Fe 500

    182000

    30

    DESIGN OF CABLE TRENCH TYPE -A-A

    1500200

    2002325

    20

  • 8/13/2019 Cable Trench Design

    20/24

  • 8/13/2019 Cable Trench Design

    21/24

    = 240 mm^2Spacing of steel required = 95 mm C/CProvide Main reinforcement fo dia 10 @ 150 mm C/C at Bottom of slabProvide Ast = 523 mm- Distribution Reinforcement;secondary reinforcement = 0.12 x 1000 X 20015% for MS and 12% for tor steel 1 x 100

    = 240 mm

    Corresponding reinforcementspacing = ast*100/Ast = = 0.785 x 8 ^2 x 1000240

    = 209 mmMinimum clear spacing=3xdeff = 3 x 95.00

    = 285 mmProvide secondary reinforcementat spacing = 170 mmProvide Sec reinforcement of dia 8 @ 200 mm C/CProvide Ast = 251 mm

  • 8/13/2019 Cable Trench Design

    22/24

    A) Input Data

    1 Internal Width of the cable Trench = mm2 Thikness of the wall = mm

    3 Thikness of the Raft = mm4 Depth of the cable trench below the FFL = mm5 Grade of concrete = N/mm26 Density of concrete = = kn/m37 Grade of steel = N/mm28 Density of the soil(DENS) = kN/m39 Surcharge = Kg/m2

    10 Angle of internal friction (f) f

    B) Design of wall

    200

    Coeff of active earth pressure Ka = (1-sin f )/(1+sin f )= 0.33

    Height of Wall H = 2125 mmMaximum pressure at the Base Pa = Ka x DENS x H

    = 12.74Pressure per meter of run = 12.74 kN/mMaximum pressure due to ps = 0.33 x 20 = 6.66

    surcharge/MPressure per meter of run = 6.66 kN/m

    Moment Due to Surcharge + due to soil pressure = 0.50 x 12.74 x 2.125 x 2.125 +

    36.66 x 2.1252

    = 9.591 + 7.080 = 16.671 Kn-mtr

    Total Moment = 16.671 = 16.671 Kn-mtr

    -Main Reinforcement( At Face of wall):Let thickness of Wall = 200 mmEffective Depth = 200 - 20 - 5.00 = 175.00 mm

    DESIGN OF CABLE TRENCH TYPE -A-A

    1500200

    2002325

    2025

    Fe 50018

    2000

    30

    2125

    15006.66 12.74

    kN/m2 kN/m2Pressure Diagram

    kN/m2

    kN/m2

  • 8/13/2019 Cable Trench Design

    23/24

    Mu/bd^2 = 1.5 x 16.67 x 10^6 = 0.81651000 x 175.00 ^2

    Corresponding reinforcement % = pt = 0.297983

    Area of steel=Ast=ptxBd/100 = 0.297983 x 1000 x 175.001 x 100

    = 521.47 mmMin area of steel = 0.12 x 1000 x 200

    1 x 100= 240 mm^2Spacing of steel required = 151 mm C/CProvide Main reinforcement fo dia 10 @ 150 mm C/C At face

    Provide Ast = 523 mm

    - Distribution Reinforcement;secondary reinforcement = 0.12 x 1000 X 20015% for MS and 12% for tor steel 1 x 100

    = 240 mmCorresponding reinforcementspacing = ast*100/Ast = = 0.785 x 8 ^2 x 1000

    240

    = 209 mmMinimum clear spacing=3xdeff = 3 x 175.00

    = 525 mmProvide Sec reinforcement of dia 8 @ 200 mm C/CProvide Ast = 251 mm

    C) Design of the BaseSlab:Load calculationWall load = 0.200 x 2.125 x 1 x 25 = 10.625 KnSecond wall = = 10.625 KnSelf wt of slab = 0.200 x 1.9 x 1 x 25 = 9.5 KnLoad due to cable SAND FILLING

    1 = 2.125 x 2 x 1 x 19 = 60.563 Kn

    Total 91.313 Kn

    Pmax = P = = 48.06 KN/m^2 A 1.9 x 1

    Moment calculation at base slab48.059 kn/mtr

    1.7

    Maximum Moment at the Mid = = 48.059 x 1.425^28

    = 17.361 Kn-mtr -Main Reinforcement( at center):Let thickness of Wall = 200 mmEffective Depth = 200 - 100 - 5.00 = 95.00 mm

    Mu/bd^2 = 1.5 x 17.36 x 10^6 = 2.88551000 x 95.00 ^2

    Corresponding reinforcement % = pt = 0.874

    Area of steel=Ast=ptxBd/100 = 0.873504 x 1000 x 95.001 x 100

    = 829.8287 mmMin area of steel = 0.12 x 1000 x 200

    1 x 100

    91.3125

  • 8/13/2019 Cable Trench Design

    24/24

    = 240 mm^2Spacing of steel required = 95 mm C/CProvide Main reinforcement fo dia 10 @ 150 mm C/C at Bottom of slabProvide Ast = 523 mm- Distribution Reinforcement;secondary reinforcement = 0.12 x 1000 X 20015% for MS and 12% for tor steel 1 x 100

    = 240 mm

    Corresponding reinforcementspacing = ast*100/Ast = = 0.785 x 8 ^2 x 1000240

    = 209 mmMinimum clear spacing=3xdeff = 3 x 95.00

    = 285 mmProvide secondary reinforcementat spacing = 170 mmProvide Sec reinforcement of dia 8 @ 200 mm C/CProvide Ast = 251 mm