by daniel govender (amsaice) project manager in training (are)
DESCRIPTION
CONTENTS SANRAL Projects N2 Project Update (current) N2 & R22 Project Update (future) Community Development ProjectsTRANSCRIPT
![Page 1: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/1.jpg)
PRESENTATION TO SARF ZULULAND SUB-
REGIONUPDATE ON SANRAL PROJECTS
21 OCTOBER 2015
by Daniel Govender (AMSAICE)Project Manager in Training (ARE)Eastern Region
![Page 2: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/2.jpg)
CONTENTSSANRAL ProjectsN2 Project Update (current)N2 & R22 Project Update (future)Community Development Projects
![Page 3: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/3.jpg)
SANRAL PROJECTS Routine Road Maintenance (RRM) / Repairs Periodic Maintenance & Rehabilitation Capacity Upgrades Community Development Incident Management Traffic Control Toll Projects
![Page 4: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/4.jpg)
N2 PROJECT UPDATE Mtunzini to Empangeni
![Page 5: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/5.jpg)
MTUNZINI TOLL PLAZA TO EMPANGENI T-JUNCTION N2 Section 28 Km 42.7 To 29 Km 13.0 Scope
Upgrade to four lane dual carriagewayExtension of structures to
accommodate new cross-section Consulting Engineer: UWP Tender adjudication is ongoing
![Page 6: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/6.jpg)
N2 PROJECT UPDATE Mtunzini to Empangeni
Kwabhoboza Interchange
![Page 7: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/7.jpg)
KWABHOBOZA INTERCHANGE N2 Section 30 Km 5.6 Scope
New interchange Consulting Engineer: Mott Macdonald PDNA Construction start: June 2014 Construction duration: 25 months
![Page 8: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/8.jpg)
N2 PROJECT UPDATE Mtunzini to Empangeni
Kwabhoboza Interchange Eteza TCC
![Page 9: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/9.jpg)
ETEZA TRAFFIC CONTROL CENTRE N2 Section 29 Km 44 To Km 48 Scope
New interchange and TCCNew screener lanesDual carriageway for 4km
Consulting Engineer: WP Contractor: Raubex Construction Construction start: October 2014 Construction duration: 26 months
![Page 10: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/10.jpg)
ETEZA PROJECT SCOPE OF WORKS
![Page 11: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/11.jpg)
N2 PROJECT UPDATE Mtunzini to Empangeni
Kwabhoboza Interchange Eteza TCC Pongola Reseal
![Page 12: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/12.jpg)
RESEAL PONGOLA RIVER TO PONGOLA TOWN N2 Section 32 Resurfacing from Pongola
River to Pongola town Consulting Engineer: Gibb Contractor: KPMM Construction start: November 2014 Construction duration: 8 months Status: Project Complete
![Page 13: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/13.jpg)
N2 PROJECT UPDATE Mtunzini to Empangeni
Kwabhoboza Interchange Eteza TCC Pongola Reseal Phelandaba to
Mozambique
![Page 14: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/14.jpg)
2 RESEAL contracts on R22 Section 4 and 5 Phelandaba to Manguzi (8 months)
Consulting Engineer: Ingerope SA Contractor: Raubex Construction
Manguzi to Mozambique Border (7 months) Consulting Engineer: Nathoo Mbenyana and Associates Contractor: Raubex Construction
Both projects to be completed in 2015
![Page 15: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/15.jpg)
N2 & R22 PROJECT UPDATE
Empangeni to Kangela KwaMsane & Mkuze Crawler Lanes (N2/32) R22 Railway Line Manguzi Bypass
![Page 16: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/16.jpg)
FUTURE PROJECTS
N2 Section 29 Km 13 To 30 Km 14 Upgrade to dual carriageway from
Empangeni intersection to Kangela (design only)
KwaMsane Interchange N2 Section 30 km 2.5 (south of KwaBhoboza)
Mkuze Interchange
![Page 17: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/17.jpg)
FUTURE PROJECTS
N2 Section 32 Crawler lanes (due to go to tender for consulting engineers)
R22 Hluhluwe railway line crossing elimination (design has commenced)
Manguzi Bypass (design is complete)
![Page 18: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/18.jpg)
COMMUNITY DEVELOPMENT PROJECTS Umhlabuyalingana Pongola
![Page 19: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/19.jpg)
COMMUNITY DEVELOPMENT PROJECTS Umhlabuyalingana
R22 Road Safety & Public Transport Project Status: Contracts re-tendered due to termination
for both Contractors Pongola
Road Safety & Public Transport facilities on N2/32Consulting Engineer: UWP/TLS (JV) Contractor: Chapps ConstructionStatus: Contract Complete
![Page 20: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)](https://reader035.vdocuments.site/reader035/viewer/2022062306/5a4d1ad67f8b9ab0599730ab/html5/thumbnails/20.jpg)
THANK YOU…