burundi-kenya-rwanda-tanzania-uganda - building … · capacity building component of the project...

32
AFRICAN DEVELOPMENT FUND MULTINATIONAL - EAST AFRICAN COMMUNITY (EAC) Payment and Settlement Systems Integration Project COUNTRIES: Burundi, Kenya, Rwanda, Tanzania, and Uganda __________________________________________________ PROJECT APPRAISAL REPORT October 2012 OSGE DEPARTMENT Appraisal Team Sector Director: I. LOBE NDOUMBE, Director, OSGE Regional Director: G. NEGATU, Director, EARC Sector Manager: J. MUKETE Manager , OSGE.2 Team Leader: C. IJEH, Chief Financial Economist OSGE.2

Upload: dangthu

Post on 06-May-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

AFRICAN DEVELOPMENT FUND

MULTINATIONAL - EAST AFRICAN COMMUNITY (EAC)

Payment and Settlement Systems Integration Project

COUNTRIES: Burundi, Kenya, Rwanda, Tanzania, and Uganda

__________________________________________________

PROJECT APPRAISAL REPORT

October 2012

OSGE DEPARTMENT

Appraisal Team

Sector Director: I. LOBE NDOUMBE, Director, OSGE

Regional Director: G. NEGATU, Director, EARC

Sector Manager: J. MUKETE Manager , OSGE.2

Team Leader: C. IJEH, Chief Financial Economist OSGE.2

TABLE OF CONTENTS

Acronyms and Abbreviations

Currency Equivalents

Fiscal Year

Weights and Measurement

Client’s Information

Project Summary

Results-based Logical Framework

Project Timeframe

I - STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Regional Strategy Objectives

1.2 Rationale for Bank’s Involvement

1.3 Donor Coordination

II – PROJECT DESCRIPTION

2.1 Project Components

2.2 Technical Solution Retained and other Alternative Explored

2.3 Project Type

2.4 Project Cost and Financing Arrangements

2.5 Project’s Target Area and Beneficiaries

2.6 Participatory Process for Project Identification, Design and Implementation

2.7 Bank Group Experience, and Lessons Reflected in Project Design

2.8 Key Performance Indicators

III – PROJECT FEASIBILITY

3.1 Economic and Financial Performance

3.2 Environmental, Social and Other Impacts

IV - IMPLEMENTATION

4.1 Implementation Arrangements

4.2 Monitoring Arrangements

4.3 Project Governance

4.4 Project Sustainability

4.5 Key Risks and Mitigation Measures

4.6 Knowledge Management

V – LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal Instrument

5.2 Conditions Associated with Bank’s Intervention

5.3 Compliance with Bank’s Policies

VI – CONCLUSIONS AND RECOMMENDATIONS

i

iii

iii

iii

iv

v

vi

viii

1

1

2

3

4

4

5

6

6

7

7

8

8

9

9

10

10

10

13

14

14

15

15

16

16

16

17

17

Appendices

Appendix 1. EAC: Selected Macroeconomic Indicators

Appendix 2. Bank Public Sector Portfolio in EAC Partner States

Appendix 3. Map of the East African Community Region

i

ABBREVIATIONS AND ACRONYMS

ACH Automated Clearing House

ACP Automated Check Processing

ADB African Development Bank

ADF African Development Fund

AML Anti-Money Laundering

ATM Automated Teller Machine

BCEAO Central Bank of West African States

BIS Bank for International Settlements

CBA Core Banking Applications

CFAA Country Financial Accountability Assessment

CMIPC Capital Markets, Insurance and Pension Committee

CPAR Country Procurement Assessment Review

CPIA Country Policy and Institutional Assessment

CPPR Country Portfolio Performance Review

CPSIPS Core Principles for Systemically Important Payment Systems

CPT Core Project Team

CSD Central Securities Depository

CSP Country Strategy Paper

DFID Department for International Development

DNS Deferred Net Settlement

DPs Development Partners

DS Development Strategy

EAC East African Community

EAC-FSDRP East African Community Financial Sector Development and Regionalization

Project

EACJ East African Court of Justice

EALA East African Legislative Assembly

EAC-PSSIP EAC Payment and Settlement Systems Integration Project

EAPS East Africa Payment System

EFT Electronic Funds Transfer

EU European Union

FDI Foreign Direct Investment

FPAC Finance and Public Accounts Standing Committee

FSVC Financial Services Volunteer Corps

GDP Gross Domestic Product

GFS Government Financial Statistics

IFAD International Fund for Agricultural Development

IFMIS Integrated Financial Management Information System

IGOs Inter-Governmental Organizations

IMF International Monetary Fund

IOSCO International Organization of Securities Commissions

IPSAS Institute for International Public Sector Accounting Standards

JAS Joint Assistance Strategy

KYC Know Your Customer

LAN Local Area Network

MAC Monetary Affairs Committee

MFI Microfinance Institution

ii

Mobile Money Mobile (cell phone) money transfer system

MOU Memorandum of Understanding

MTR Mid-Term Review

NBFI Non-Bank Financial Institution

NPS National Payment Systems

OMO Open Market Operations

PAD Project Appraisal Document

PAR Project Appraisal Report

PCR Project Completion Report

PCN Project Concept Note

PCU Project Coordinating Unit

PD Presidential Directive

PIU Project Implementation Unit

POS Point Of Sale

PRSP Poverty Reduction Strategy Paper

PSS Payment and Settlement Systems

RECs Regional Economic Communities

RISP Regional Integration Strategy Paper

ROs Regional Operations

RPG Regional Public Good

RTGS Real Time Gross Settlement

SBD Standard Bidding Document

SIDA Swedish International Development Cooperation Agency

TA Technical Assistance

UA Unit of Account

UEMOA Economique et Monétaire Ouest Africaine

USAID United States Agency for International Development

USD United States Dollars

SIDA Swedish International Development Agency

SMEs Small and Medium Size Enterprises

SWITCH Computer system for the management of cards (ATM / POS)

WAEMU West Africa Economic and Monetary Union

WAMZ West Africa Monetary Zone

WB World Bank

iii

Currency Equivalents

As of October 2012

Currency Unit = Burundi (BIF)

Kenya (KES)

Rwanda (RWF)

Tanzania (TZS)

Uganda (UGX)

1 Unit of Account (UA) = 2239.70 BIF

1 Unit of Account (UA) = 128.337 KES

1 Unit of Account (UA) = 935.258 RWF

1 Unit of Account (UA) = 2385.30 TZS

1 Unit of Account (UA) = 3818.00 UGX

1 Unit of Account (UA) = 1.54219 USD

EAC Fiscal Year

1 July – June 30

Weights and Measures

1metric tonne = 2204 pounds (lbs)

1 kilogramme (kg) = 2.200 lbs

1 meter (m) = 3.28 feet (ft)

1 millimeter (mm) = 0.03937 inch (“)

1 kilometer (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

iv

Client’s information

BENEFICIARY: EAC - Burundi, Kenya, Rwanda, Tanzania, and Uganda

EXECUTING AGENCY: EAC Secretariat (Core Project Team)

Financing plan

Source Amount (UA) Instrument

ADF (Regional Operation)

15.0 million

Grant

Timeframe - Main Milestones (expected)

Preparation

May/June 2011

Appraisal May 2012

Negotiation 30 October 2012

Project approval 05 December 2012

Effectiveness December 2012

/January 2013

Mid-term Review November 2014

Project Completion Date December 2016

Last Disbursement June 2017

Project Completion Report December 2017

v

PROJECT SUMMARY

Paragraph Topics covered

Project Overview

Program Name: EAC Payment and Settlement Systems Integration Project

Geographic Scope: The following five East African Countries constituting the “East African

Community” (EAC): Burundi, Kenya, Rwanda, Tanzania and Uganda.

Expected Project Outputs: Well-functioning and integrated Real Time Gross Settlement (RTGS) systems

and retail payment and settlement systems, Central Securities Depositories and Core Banking Platforms

in the region; Supporting infrastructure including business continuity and disaster recovery platforms

that function satisfactorily; Harmonized national legislation; regulations and policies that ensure

adequate supporting pillars for the payment and settlement systems to be integrated throughout the EAC

in order to protect payment flows. Including, but not limited to; adoption of common “Failure to Settle”

arrangements, “Oversight Framework and Policy”, on site-inspection format in line with BIS CPSIPS,

regulatory arrangements for payment instruments and collateral levels; enhance capacity and supporting

skill sets for specific areas of payment and settlement systems for the EAC-CPT, the National Central

Banks, the Commercial Banks, Judges and other stakeholders and regulators.

Expected Project Outcomes: Sound national and Integrated Regional wholesale and retail payment and

settlement systems that will strengthen the efficiency of cross-border funds transfers within the five EAC

countries; together with strengthening of the financial sector regulatory and legislative capacity in the

EAC Partner States.

Implementation Timeframe: January 2013 to December 2016

Grant Amount: UA 15 million

Project Direct Beneficiaries: The EAC will be the recipient of the grant. The direct beneficiaries of the

project will include the National Central Banks of the EAC Partner States, Commercial Banks, other

financial institutions, and the judiciary, including the East African Court of Justice (EACJ) and members

of the East African Legislative Assembly (EALA). This will also include the Office of the Counsel to the

Community. This is the EAC Secretariat Legal Office

Needs Assessment

The EAC Partner States have identified the integration of their payments and settlement systems as a

priority in order to create a firm foundation that will ensure that payment obligations, throughout the

EAC, are settled effectively and with certainty. The need to mitigate risks associated with payment and

settlement systems is a high priority with the mitigation of systemic risk paramount. A technological

platform is desired that will not only accommodate existing payment systems streams but also provide a

common foundation for the introduction and development of additional financial products and services

in the future. This project is an integral element of the overall infrastructure, and technological platform

required to support the proposed East African Monetary Union to function effectively and will contribute

to managing the convertibility of the EAC Partner States’ currencies in the region. The Project will also

contribute to implementation of the Common Market Protocol, particularly the free movement of capital.

The proposed project will provide a sound platform aimed at enhancing payment and settlement systems

in the EAC Partner States as a prelude to the successful introduction of the East African Monetary

Union.

Bank’s Added Value

The Bank’s intervention will catalyze the process of financial integration in the EAC leading to the

effective introduction of the proposed East African Monetary Union by ensuring that there is

coordination of the process through the EAC Secretariat. The Bank has comparative experience of a

similar regional payment and settlement integration project which contributed to the design of the

proposed EAC project. The Bank’s cumulative experience in the implementation of other payment and

settlement systems projects would therefore, be valuable to the beneficiaries in the establishment and,

implementation of the proposed project.

Knowledge

Management

The implementation of the PSSIP will result in the development of skills and knowledge in specific areas

of payment and settlement systems operations and functions for the EAC Secretariat, National Central

Banks, and Commercial Banks. This knowledge will be disseminated through seminars and workshops

organized by the National Central Banks and Bankers’ Associations. Also, the implementation of the

capacity building component of the project will result in knowledge building for Judges and judicial

officers at the EACJ and national courts, as well as members of the EALA. This knowledge will be

disseminated through applications of the knowledge, law of precedence, and seminars and workshops.

vi

RESULTS BASED LOGICAL FRAMEWORK Country and project name: EAC - Payment and Settlement Systems Integration Project Purpose of the project: To contribute to the modernization, harmonization and regional integration of payment and settlement systems; ensure common standards for the

instruments together with appropriate regulatory practices.

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS/MITIGATION

MEASURES Indicator

(including CSI) Baseline

Target Indicator (including CSI)

2014 2016

I

M

P

A

C

T

Impact

Financial

Inclusion and

Improved trade and Deeper

financial sector

integration in the EAC region.

1. Financial Depth

as measured by broad money supply

(M2) as a

percentage of GDP

2. The share of

intra-regional trade to total trade among

EAC Countries.

3. Proportion of

regional

population’s access to formal banking

services

Level of

financial depth as measured by

broad money

supply (M2) as a percentage of

GDP was 30% in

2010

7.9% in 2010

22% in 2010

Level of

financial depth as measured by

broad money

supply (M2) as a percentage of

GDP increases to

35% in 2014

9% in 2014

27% in 2014

Level of

financial depth as measured by

broad money

supply (M2) as a percentage of

GDP increases to

40% in 2016

12% in 2016

35% in 2016

1.EAC Economic Surveillance

Reports

2. Reports of

National Central Banks and EAC

Secretariat

O

U

T

C

O

M

E

S

Outcome 1

Improved and

Integrated Regional

payment and

settlement systems and

Improved

efficiency of funds transfer

across the five

EAC countries

1. Growth in inter-bank fund transfers

2. Longest clearing

cycle in number of days of local and

upcountry cheques.

The volume of high value funds

transfers in the

five EAC countries in 2010

was US$279

billion

T+10 days in 2011.

The volume of high value funds

transfers in the

five EAC countries in 2014

should grow to

US$340 billion

T+5 days in 2014

The volume of high value funds

transfers in the

five EAC countries in 2016

should grow to

US$420 billion

T+3 days in 2016

1. EAC Economic

Surveillance Reports

2. Reports of National Central

Banks and EAC

Secretariat

Risk 1: Full functionality of the integrated systems if the new

systems are not fully implemented

at national levels.

Mitigation: This risk is mitigated

by continued commitment and ownership of the new systems by

the Central Banks. In fact, they

have also initiated investments that are complementary to the

components being provided by the

proposed project. The proposed project is therefore intended to fill

the gap.

Risk 2: Possible lack of

commitment of the Commercial

Banks to the new payment systems.

Mitigation: This risk is mitigated given the commercial benefits that

the new systems would provide to

the Commercial Banks. The Commercial Banks have been

placing demands on the NCBs

regarding the need to modernize and integrate the national payment

systems. They have also initiated

investments to upgrade their

infrastructure in anticipation of

new payment systems. The

arrangements for project implementation also ensure that

the Commercial Banks are fully

involved in its implementation as members of the NPSCs.

Outcome 2

Adequate and harmonized

legislation and

policy supporting payment and

settlement

systems.

1. Adequate

legislative support

and harmonized rules and

regulations for

payment and settlement systems

Very limited

support and no

harmonization of payment and

settlement

systems rules and regulations in

2011

Promulgated

legislative

support for National

Payment

Systems, CSD laws and ACH

in Uganda,

Burundi and Tanzania,

respectively by

2014

Harmonized

rules and

regulations for RTGS and

National

Payment Systems approved by the

Monetary Affairs

Committee and promulgated by

the EAC

Assembly by the end of 2016

1. Progress reports

from NCBs and

EAC.

2. Structured

promulgation by EAC Assembly

vii

RESULTS BASED LOGICAL FRAMEWORK Country and project name: EAC - Payment and Settlement Systems Integration Project Purpose of the project: To contribute to the modernization, harmonization and regional integration of payment and settlement systems; ensure common standards for the

instruments together with appropriate regulatory practices.

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS/MITIGATION

MEASURES Indicator

(including CSI) Baseline

Target Indicator (including CSI)

2014 2016

O

U

T

P

U

T

S

Component 1

Integration of

RTGS

Centralized

database for

capturing payment flows

within the region

1. Number of EAC

Partner States with inter-operable and

integrated RTGS

2. Technological

platform to deliver full regional

integration

Three (3)

countries currently

implementing the

East African Payment System

(EAPS) Project.

2011 - Full

integration not in

place.

2011 platform

not in place

At least, 4

countries having implemented the

East African

Payment System (EAPS) Project

by 2014

All 5 countries

having implemented the

East African

Payment System (EAPS) Project

by 2016

2016 - Full

integration

completed

Regional

technological platform in place

2016.

Payment system and settlement

systems

integration established

Risk 3: Systems failure and

systemic risk posed by having EAC Partner States with mixed

levels of readiness and payment

systems automation and standards.

Mitigation: Business continuity

and disaster recovery plans are in place in all the NCBs. Also, as a

further mitigation measure, the

business continuity arrangements in Burundi and Kenya and disaster

recovery arrangements in

Tanzania and Rwanda would be further strengthened.

Risk 4: Technical Solutions may not be sustained

Mitigation: This risk is mitigated because the technologies to be

employed for component 1 of the

project are standard industry technologies that have been well

tested and deployed worldwide.

Moreover, Capacity building is a key component of the project, and

will ensure that participant’s staff

is adequately trained and that they receive regular skills upgrades

when necessary.

Risk 5: Possible constraints of

required project implementation capacity which could delay project

implementation.

Mitigation: The project has

provided for the recruitment of a

“Payment and Settlement Systems Specialist, a Procurement Expert

and an Accountant to strengthen

the implementation capacity of the EAC Core Project Team. In

addition, the NCBs shall provide

the necessary technical expertise throughout the procurement

process thereby reducing any

residual risk. The project also provides for trainings and

workshops.

Component 2

Drafting and

adoption of regulations of

corporate

governance for banking

institutions

1. Casting of overarching

legislation.

2. Drafting of

“Directives and

Determinations”

No regional legislation in

place 2011

Limited national

legislation in place

In place by- 2016

In place 2016

Submission of Bills to the

Assembly or

Council Directives.

“Directives and Determinations”

adopted

Component 3

Capacity

Building for

Structured implementation

and coordination

of project

activities, and

Strengthened Judicial Capacity

in PSS.

1. Number of EAC

Secretariat, NCBs and other

stakeholders

Trained in PSS.

2. Number of

Judges and Legal Officers Trained in

PSS

3. Progress reports

and audits of

projects produced in a timely manner

Limited expertise

in PSS in the EAC region 2011

None in 2011

Core Project

Team established

in 2011

Raise levels of

expertise by training at least

50, of which at

least 15 should be women, by

2014

At least 50, of

which at least 15 should be

women, by 2014

Progress reports

and financial

statements submitted to the

Bank on a

quarterly basis.

Raise levels of

expertise by training at least

120, of which at

least 45 should be women, by

2016

At least 100, of

which at least 35 should be

women, by 2016

Progress reports

and financial

statements submitted to the

Bank on a

quarterly basis.

Workshops,

trainings, and assessment.

Workshops,

trainings, and

assessment.

Structured

reporting to EAC and the Bank of

progress and

impediments

K

E

Y

A

C

T

I

V

I

T

I

E

S

COMPONENTS INPUTS

Component 1: Support for Integration of Financial Market Infrastructure

Component 2 : Support for Harmonization of financial laws and regulations

Component 3: Support for Capacity Building for member states and EAC in PSS; Support for establishment, support for effective project implementation and management, capacity building for key

legal, judicial and financial institutions.

ADF Grant = UA 15 million; Central Banks =

UA 3.5 million; Commercial Banks = UA 1.5 million

Missions: Appraisal, supervision, MTR and donor coordination

Capacity building by ADB and other DPs (i.e. World

Bank)

viii

PROJECT TIMEFRAME

EAC: PAYMENT AND SETTLEMENT SYSTEMS INTEGRATION PROJECT

Activities/Years

2012 2013 2014 2015 2016 2017 Action by

Q3/4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Project Processing and Management

Grant approval AfDB

Signing Protocol of Grant Agreement AfDB/EAC

Project Effectiveness and Launching AfDB /EAC/NCBs

Procurement of Goods and Services

Training Programmes

Supervision and Monitoring AfDB /EAC/NCBs

Submission of Annual Audit Reports

Mid-term Review AfDB /EAC/NCBs

Project Completion Date AfDB /EAC/NCBs

Last Disbursement

Project Completion Report AfDB /EAC/NCBs

1

Report And Recommendation Of The Management Of The ADB Group To The Board Of

Directors For A Proposed Grant To The EAC - Burundi, Kenya, Rwanda, Tanzania, And

Uganda In Support Of The EAC Regional Payment And Settlement Systems Integration

Project

Management submits the following Report and Recommendation for a proposed Grant of UA

15.0 million to the EAC – Burundi, Kenya, Rwanda, Tanzania, and Uganda from the Regional

Operations envelop for ADF-12 to finance the EAC Regional Payment and Settlement Systems

Integration Project (EAC-PSSIP).

I. STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Regional Strategy and Objectives

1.1.1 This proposed project is closely aligned with Bank’s Eastern Africa Regional

Integration Strategy Paper (EA-RISP) 2011-2015 pillars 1 and 2, on Regional Infrastructure and

Capacity Building respectively. The proposed EAC-Payment and Settlement Systems

Integration Project (EAC-PSSIP) is also closely aligned with the Fourth EAC Development

Strategy, 2011/12-2015/16, and the EAC Common Market Protocol, which emphasizes trade

facilitation, establishment of a single market in financial services, establishment of the EAC

Monetary Union, and integration of Information and Communication Technology (ICT) into

regional development initiatives, amongst others. Table 1.1 illustrates the alignment of the EAC

Payment and Settlement Integration Project with both the Fourth EAC Development Strategy

and the Bank’s EA-RISP, 2011-2015.

Table 1.1: Linkage of the EAC-PSSIP with the 4TH

EAC DEVELOPMENT STRATEGY and AfDB - EA RISP

4TH EAC DEVELOPMENT STRATEGY AfDB – EA RISP EAC PSSIP Strategic Objective

The 4th EAC Development Strategy focuses on

consolidating the benefits of a fully-fledged Customs

Union, full implementation of the Common Market and laying the foundation for the Monetary Union and

the Political Federation

Strategic Objective

To create a well-connected, economically prosperous

and peaceful region by providing support to: (a) the

public sector to implement measures that facilitate the flow of capital, goods, and services across the East

African Market; and (b) to the private sector, which

invests in and finances economic activities and infrastructure across the region.

Program objective

To contribute to the modernization, harmonization

and regional integration of payment and settlement

systems; and ensure common standards for the instruments together with appropriate regulatory

practices.

Regional Priorities/Pillars

i. Consolidation of the benefits of a fully-fledged

Customs Union ii. Full Implementation of the Common Market

iii. Establishment of the EAC Monetary Union

iv. Laying the foundation of a Political Federation v. Development of Regional Infrastructure

vi. Development and Strengthening of the Regional Productive Sectors

vii. Strengthening of EAC Organs and Institutions

viii. Wide stakeholder participation

AfDB – EA RISP Strategic Pillars

i). Regional Infrastructure:

(a) Regional Transport/Trade Facilitation Infrastructure

(b) Regional Energy Development

(c) Information and Communications Technology Development of Shared Water Resources

ii) Capacity Building: (a) Support to the CES Tripartite Arrangement

(b) Support to trade facilitation, statistical and

regulatory and institutional framework (c) Strengthening institutions (RECs/IGOs, continental

organizations, special utilities and national

implementation units (d) Enhancing financial and technical capacity of

regional multilateral institutions and agencies that

invest in infrastructure and private enterprises RPGs/Cross-cutting Issues:

(i) Regional Public Goods, Climate Change,

Management of Shared Water Resources and Trans-boundary Animal Diseases Control, political risk

mitigation services, (ii) Cross-cutting Issues: Gender

and Environment, and (iii) Knowledge Management and Networking

1. EAC PSSIP Components:

(i). Support for Integration of Financial Market

Infrastructure (ii) Support for Harmonization of financial laws

and regulations

(iii) Support for Capacity Building for member states and EAC in PSS.

2. Linkages with EAC and AfDB Strategies: (i) Financial Inclusion and improved trade

facilitation

(ii) Deeper financial sector integration in the EAC region.

(iii) Integration of RTGS systems, together with

retail payment streams, and Centralized database for capturing payment flows which is critical for the

effective operation of the proposed East African

Monetary Union (iv) Improved and Integrated Regional payment and

settlement systems

(v) Improved efficiency of funds transfer across the five EAC countries.

(vi) Adequate and harmonized legislation and policy

supporting payment and settlement systems. (vii) Capacity Building for Structured

implementation and coordination of project

activities. (viii) Strengthening Institutions (RECs/IGOs,

continental organizations, special utilities and

national implementation units) through the strengthening of capacity at the EAC Secretariat,

strengthening of capacity of oversight institutions,

harmonization of financial laws and regulations.

Priority Areas Relevant to the EAC PSSIP

i. Trade Facilitation

ii. Establishment of a Single Market in Financial Services

iii. Establishment of the EAC Monetary Union

iv. Support to integration of ICT into regional development initiatives.

Focus Areas Relevant to the EAC PSSIP

(i) Trade Facilitation Infrastructure

(ii) Information and Communication Technology (iii) Support to trade facilitation, statistical and

regulatory and institutional framework

(iv) Strengthening Institutions (RECs/IGOs, etc.)

2

1.2 Rationale for Bank’s Involvement

1.2.1 The EAC region is comprised of five Partner States1 that currently maintain mixed

levels of payment systems automation and standards with implications on the ability to integrate

the payment and settlement systems at a regional level. The requirement to maintain a secure

and accessible payment and settlement systems infrastructure remains an important element in

the overall ability to effectively integrate the payment systems within the EAC. However, the

continued expansion of the EAC communications “backbone” proves a valuable element in the

regional payment and settlement systems integration. Those member states having RTGS

systems, namely Tanzania, Kenya and Uganda, have started the process of integrating their

RTGS systems as the initial project toward a comprehensive EAC regional payments and

settlement systems integration. The first phase of this process commenced live operations in

May 2012.2 Table D.1 in the Technical Annexes provides a broad overview of the national

payments systems (NPS) currently in place in the EAC Partner States. Also, NPS legislation and

regulations remain variable and inconsistent with the desire to establish an integrated regional

payments system. Examples include, in some cases, no NPS Legislation that acts as a supporting

pillar for the NPS; the Law of Evidence is mixed, and does not provide for the submission of

electronically stored data to be accepted as “Prime Facie” evidence in a court of law; and clear

“Oversight” regulatory frameworks are not complete in all member states.

1.2.2 The EAC Partner States have identified the integration of their payments and

settlement systems as a priority in order to create a sound foundation that will ensure that

payment obligations throughout the EAC are settled effectively and with certainty. The need to

manage risks associated with payment and settlement systems is a high priority with the

mitigation of systemic risk paramount. A technological platform is required that will not only

accommodate existing payment and settlement systems streams but also provide a common

foundation for the introduction and development of additional financial products and services in

the future. The overriding objective is to develop a sound payments and settlement mechanism

that will facilitate the integration of member states national economies into a single monetary

area and efficient means of undertaking payments within the EAC region. Details of the

Regional, Sectoral and Institutional Context are presented in the Technical Annexes A, while

the identified issues, constraints and challenges of the current payment and settlement systems

landscape in the EAC region are presented in the Technical Annexes, D.1 to D.6.

1.2.3 This project is considered a Regional Public Good (RPG) as it will yield direct utility

by accelerating the convergence and regional integration of payment and settlement systems.

The project, which was selected by OpsCom during the July 2011 Selection and Prioritization

exercise for ROs, will strengthen commercial activities within the region by contributing to

more secure, efficient, safe and timely transfer of funds among the EAC Partner States thereby

stimulating trade in goods and services and the free movement of capital within the region.

Furthermore, the technological platform which the project will provide will encourage more

people within the region to enter the formal banking system to undertake retail funds transfers. It

will also provide expanded financial inclusion. In the period leading to the desired state of full

financial sector integration and Monetary Union, there is a need to ensure that integrated

payment and settlement systems are adequately supported throughout the EAC Partner States

with a view to accelerating convergence and regional integration of payments and settlement

systems thereby contributing to facilitating the conduct of centralized monetary policy within

the Union. The project is also expected to have a positive impact on the private sector,

1 Kenya, Tanzania, Uganda, Rwanda and Burundi.

2 Kenya, Tanzania and Uganda

3

especially the SMEs, which would benefit from an integrated and sound regional payment and

settlement systems.

1.2.4 The project is of broad public regional interest and benefit that would promote greater

trade facilitation and financial inclusion. It engenders both national and regional benefits. The

project components are well distributed over all the EAC Partner States with the implication that

all EAC Partner States will share its costs and benefits. The project requires effective cross-

border collective and cooperative action. The missing elements identified for Burundi, Uganda

and Rwanda under component 1, are critical and indispensable for the successful realization of

the project. Without the commitment and participation of all EAC Partner States, the objectives

of the project of ensuring regional interoperability of RTGS systems, ACHs, ATM/POS

switches at national and regional levels together with the establishment of a sound technological

platform to deliver regionally integrated payment and settlement systems cannot be realized.

The proposed EAC-PSSIP is a pivotal part of the infrastructure required by the proposed East

African Monetary Union to operate effectively and manage the convertibility of the EAC

Partner States’ currencies. Each participating country will contribute, proportionately, to the

financing of the project through their respective National Central Banks and Commercial Banks.

The commercial banks’ contribution represents the investments that they have to make to

interface with the new payment systems in order for the systems to operate effectively and

ensures they do not get a free-ride. The Bank’s intervention will therefore, catalyze the process

of financial integration and inclusion in the EAC and support the effective operations of the

proposed East African Monetary Union by ensuring that there is coordination in the process

through the EAC Secretariat. The Bank’s intervention will also ensure that the free-rider

problem is eliminated. See Technical Annex B for a detailed check-list of criteria for financing

Regional Public Goods (RPGs).

1.2.5 The Bank has comparative advantage and experience in similar operations which has

been useful in the design of the proposed project. The Bank’s cumulative experience in the

implementation of other payment and settlement systems projects would therefore, be valuable

to the beneficiaries in the establishment and implementation of the proposed project. Examples

include; a Bank financed project to reform systems and means of payment in WAEMU

countries through an ADF loan of UA6.20 million to BCEAO which has been successfully

completed. Also, implementation of the WAMZ Payment and Settlement Development System

Project3 financed by the Bank, with an ADF grant of UA 19 million which remains on-going.

See Table 2.9, for a summary of lessons learnt from previous regional operations. The Bank’s

cumulative experience in the implementation of payment and settlement systems projects would

therefore, provide significant benefits to the beneficiaries in the implementation of the proposed

EAC project.

1.3 Donors Coordination

1.3.1 The proposed EAC-PSSIP is an integral part of the objective of the East African

Community Financial Sector Development and Regionalization Project (EAC-FSDRP) which is

being funded by the World Bank. The overarching objective of the EAC-FSDRP is to establish a

single market for financial services among EAC Partner States. The EAC-FSDRP seeks to build

the foundation for financial sector integration among EAC Partner States upon the six following

pillars: (i) Financial Inclusion and Strengthening of Market Participation; (ii) Harmonization of

Financial Laws and Regulations Against Common Standards; (iii) Mutual Recognition of

Supervisory Agencies; (iv) Integration of Financial market Infrastructure; (v) Development of

the Regional Bond Market; and (vi) Capacity Building

3 The Gambia, Guinea, Liberia and Sierra Leone

4

1.3.2 The proposed EAC Payment and Settlement Systems Integration Project (EAC-

PSSIP) being an integral part of the objectives of the EAC-FSDRP, is aimed at complementing

the integration of the regional Financial Market Infrastructure to facilitate the undertaking of

cross border funds transfers in support of the economies of the region as a whole, together with

providing outreach to rural areas, to encourage greater participation in the formal financial

sector. The Bank’s support will focus on the provision of funding in pillars 2, 4, and 6, of the

EAC-FSDRP where it is felt, and agreed, that strengthening of these component areas would

prove to be the most beneficial in the overall progression of the payment and settlement systems

(PSS) in the EAC under Phase I (2011-2014) of the EAC-FSDRP. All the donor activities will

be coordinated by the EAC Secretariat. This will strengthen client ownership of the project. In

view of the foregoing, the preparation and appraisal of the proposed project was coordinated

with the World Bank with a view to ensuring that activities that are currently funded under the

EAC - FSDRP are not duplicated in the proposed project. It was also agreed that during

implementation, coordination between the two institutions will continue and that the project

documents for both the EAC-FSDRP and the proposed EAC-PSSIP should be seen as living

documents to accommodate the changing needs of the Partner States and to ensure that

activities, especially in the areas of capacity building and harmonization of financial laws and

regulations, are not duplicated.

II. PROJECT DESCRIPTION

2.1 Project Components

2.1.1 Project Objectives: The objective of the proposed project is to develop a robust

environment for both, wholesale and retail payment and settlement systems and to facilitate

market integration, support effective application of monetary policy and financial markets aimed

at enhancing safety and efficiency in the overall payment and settlement systems. This will

contribute to the pursuit of sound macroeconomic policies and improved functioning of regional

integrated financial markets. The project would support, through integrated Payment and

Settlement Systems (PSS), the broadening and deepening of the financial sector by establishing

a single market in financial services among EAC Partner States, with a view to providing a wide

range of financial products and services to all, at competitive prices. The project aims

specifically to: (i) contribute to establishing an infrastructure that is sound, efficient and

compatible at the regional level; (ii) assist the EAC to redress weaknesses in the legal and

regulatory arrangements in banking and PSS which are critical to achieving the effective

functioning of a single common market in financial services; and (iii) provide capacity building

in the area of payment and settlement systems at both the national and regional level.

2.1.2 Project Components: The proposed project includes the following components: (i)

integration of financial market infrastructure - to achieve its objective this component is

expected to realize the integration of RTGS systems and retail systems across the region; (ii)

harmonization of financial laws and regulations; and (iii) capacity building. It is expected that

integration of existing systems will be substantially completed by 2014 and that the regional

technological platform will be in place by 2016. The major activities are summarized in table

2.1 while the detailed description of project components and costs is presented in the Technical

Annex C1.

5

Table 2.1: EAC Payment and Settlement Systems Integration Project-Project Components

Components Est. Cost

(UA mil)4

Component Description

Component 1:

Integration of

Financial

Market

Infrastructure

13.50

(i) Supporting the integration and upgrading of Real Time Gross Settlement (RTGS) systems including:

(a) Purchase of a Real Time Gross Settlement System (RTGS) and Central Securities Depository (CSD) for Burundi and

Integration of the Burundi RTGS with EAPS;

(b) Upgrade of the Uganda RTGS to interface with the accounting system; and

(c) Support to Uganda to complete the interface between RTGS and the Core Banking System.

(ii) Support to Retail Payment System Automation in Uganda and Rwanda through the upgrade of their clearing systems;

(ACHs) to accommodate cheque truncation and ATM/POS reciprocity;

(iii) Support for SWIFT Connectivity to integrate to the EAPS for Rwanda;

(iv) Support for Business Continuity arrangements for Kenya and Burundi;

(v) Support for Systems Upgrade and Disaster Recovery arrangements for Tanzania5; and

(vi) Support for Network Upgrade and Disaster Recovery arrangements for Rwanda6.

Component 2:

Harmonization

of financial

laws and

regulations.

3.50

(i) The proposed project will provide consultancy support to the EAC Secretariat in the drafting of legislation and policy

to ensure that the payment and settlement systems are adequately supported and integrated throughout the EAC in order

to protect payment flows. More specifically, the project will, amongst others, help to: (a) adopt common “Failure to

Settle” arrangements; (b) agree “Oversight Framework and Policy”, on site-inspection format in line with BIS CPSIPS;

(c) agree regulatory arrangements for payment instruments and collateral levels; (d) drafting of regional payment systems

legislation; and (e) Support for the development of an EAC oversight framework.

(ii) At the national level, support is required for, but not limited to: (a) Development of rules, regulations and procedures

to enable the National Payments Systems (NPS) Act in all EAC Partner States; (b) Drafting of the Central Securities

Depository7 (CSD) law and enabling regulations in Burundi; (c) Support for the development of enabling regulations and

the NPS Act in Uganda; and (d) Drafting and implementation of rules and regulations for ACH for Tanzania.

Component 3: 8

Capacity

Building

2.00

(a) Training and skills improvement support to strengthen the capacity of the EAC Core Project Team (CPT), National

Central Banks, Commercial Banks and other stakeholders in the area of Payment and Settlement Systems;

(b) Training judges and judicial officers at the EACJ and members of the EALA in the legislative support required for

payment and settlement systems, commercial law, enforcement of collateral, acceptance of electronic evidence as “prima

facie” evidence, and the resolution of contractual disputes, especially in relation to payment and settlement;

(c) Training of legal officers at the National Central Banks and Commercial Banks in the legal aspects of payment and

settlement systems;

(d) Sensitization of the population on retail payment systems and use of electronic means of payment, by means of

seminars and workshops and media to explain the new payment systems to stakeholders;

(e) Study tour for Payment Systems Experts in the EAC Secretariat and the region to strengthen their capacity in

payments systems oversight, including exchange programs between the NCBs to exchange expertise and experience; and

(f) Support to the Regional Association of Bankers.

Project

Management

1.00

(a) Support to the EAC Core Project Team by providing:

(i) Payment Systems Specialist/Project Manager

(ii) Procurement Specialist

(iii) Accountant

(iv) Project Administration Assistant

(b)Project operational costs for the Core Project Teams in the EAC and the NCBs

(c) Logistical support for the National Payment Systems Committees

(d) Cost of the annual audits during project implementation

Total Cost 20.00

2.2 Technical Solution Retained and other Alternatives Explored

2.2.1 Large value/time critical systems are not in place in all EAC Partner States. There is a

need to implement and integrate national RTGS systems in Partner States to develop a regional

cross-border large value/time critical funds transfer system. Integration to the SWIFT network is

a prerequisite for all member states to access the EAPS “high value” system. While Tanzania,

Uganda and Kenya have integrated their RTGS systems to establish the foundation of the “East

African Payment System” (EAPS), Rwanda and Burundi are yet to do so, with Burundi

requiring the acquisition and implementation of an RTGS system. The solution retained

therefore is a regional RTGS system with interface to SWIFT, using the SWIFT “FIN-Y” copy

4 All figures include price and physical contingencies.

5 See technical annexes Table C.3.11 (A) for details.

6 See technical annexes Table C.3.11 (B) for details.

7 Securities Act

8 The Commercial Banks will be required to sponsor their staff and cover the full cost of their participation in

the training programs to be provided under this component.

6

platform which utilizes sound SWIFT “Closed User Group” (CUG) conventions. This would

ensure an efficient and secured funds transfer mechanism within the region. This could be

extended, in the future, to accommodate the settlement of cross-border clearing house and

ATM/POS Switch operations for retail payments, enhance financial inclusion, and stimulate

trade among the EAC Partner States.

2.2.2 An alternative solution considered during the design of the project and reasons for its

rejection is presented in the table below.

Table 2.2: Project Alternatives Considered Alternative Brief Description Reasons for Rejection

Interface of

Regional RTGS to

an Independent

Virtual Private

Network (VPN)

Establishment of

an EAC centric

VPN

The establishment of an EAC centric VPN would not be cost effective and efficient.

Global best practice for such systems would be the SWIFT service as the “de facto” global

standard for such systems.

Any other alternative to SWIFT could create further delays in the transfer of funds and

integration of payment and settlement systems among the EAC Partner States.

2.3 Project Type

2.3.1 The proposed operation is a technical and institutional support project, financed by a

grant under the Regional Operations Envelope of ADF-12. The project involves the

improvement and integration of the payment systems in Burundi, Kenya, Rwanda, Tanzania,

and Uganda. It focuses on three areas: (a) Integration of Financial Market Infrastructure; (b)

Harmonization of financial laws and regulations; and (c) Capacity Building. The project will

contribute to the modernization, harmonization and regional integration of payment and

settlement systems in the EAC Partner States, and develop common standards for instruments

together with appropriate regulatory and legislative practices.

2.4 Project Cost and Financing Arrangements

2.4.1 The total cost, net of taxes and duties, of financing the implementation of the Payment

and Settlement Systems within National Central Banks, covering regional dimensions for the

first four years (2013-2016) is estimated at UA 20 million. Of this amount, UA 15 million,

representing 75.0 percent of the cost of the project, is the proposed ADF Grant to the EAC. The

countries collectively, will contribute UA3.5 million, representing 17.5 percent of the cost of the

project through their respective National Central Banks (NCBs). The contribution of each

participating NCB will be proportionate to the financing it is receiving under component 1 of

the project. The Commercial Banks will be required to contribute UA1.5 million representing

7.5 percent of the project. The commercial banks’ contribution represents the investments that

they would be required to make in their respective offices in order for the new payment systems

to operate effectively. In addition, for the Commercial Banks to benefit from the training

programs, which shall be undertaken under component 3 of this project, they will be required to

sponsor their staff and cover the full cost of their participation in the programs. Details of the

fees for participation of Commercial Banks would be determined by the EAC-CPT in

conjunction with the training providers. The contribution of the Commercial Banks ensures their

commitment and involvement. Incorporated in the cost estimates is a 4 percent physical

contingency factor and 4 percent for price escalation on local and foreign currency. At the end

of this investment and the initial operation period, the systems will become fully sustainable.

2.4.2 Tables 2.3 and 2.4 below present estimated project costs by category of expenditure

and component while Tables 2.5 (a and b) and 2.6 show financing by source and schedule of

expenditure. Costs have been estimated on the basis of data obtained during the Appraisal

Mission. Details of the project cost by component and expenditure category are presented in

Technical Annex C1.

7

Table 2.3: Project Cost by Category of Expenditure (in million UA)9

CATEGORIES OF EXPENDITURE (USD$ Million) (UA Million) % Total Cost

Local Foreign Total Local Foreign Total

A. Goods 2.87 9.44 12.31 1.85 6.09 7.94 39.7%

B. Services 0.46 10.48 10.94 0.30 6.76 7.06 35.3%

C. Operating Costs 6.86 0.89 7.75 4.43 0.57 5.00 25.0%

Total Cost 10.20 20.80 31.00 6.58 13.42 20.00 39.7%

Table 2.4: Project Cost Estimates by Component (in million UA)10

(USD$ Million) (UA Million)

COMPONENT Local Foreign Total Local Foreign Total

Integration of financial market infrastructure 9.02 10.36 19.38 5.82 6.68 12.5

Harmonization of financial laws and

regulations 0.00 5.02 5.02 0.00 3.24 3.24

Capacity building 0.14 2.73 2.87 0.09 1.76 1.85

Sub-total 9.16 18.11 27.27 5.91 11.69 17.60

Project Management 0.29 1.15 1.44 0.19 0.74 0.93

Total Base Cost 9.45 19.26 28.71 6.09 12.43 18.52

Physical contingencies 0.38 0.77 1.15 0.24 0.50 0.74

Price contingencies 0.38 0.77 1.15 0.24 0.50 0.74

Total Project Cost 10.20 20.80 31.00 6.58 13.42 20.00

Table 2.5 (a): Sources of Financing (in million UA)

Sources of Financing Foreign Currency costs Local Currency cost Total % of total

ADF 12.85 2.15 15.00 75.00%

Central Banks 0.57 2.93 3.50 17.50%

Commercial Banks 1.50 1.50 7.50%

Total Cost 13.42 6.58 20.00 100.00%

Table 2.6: Expenditure Schedule by Component (in million UA) (ADF financing)

COMPONENTS 2013 2014 2015 2016 Total

Integration of Financial Market Infrastructure 9.45 2.02 1.35 0.67 13.50

Harmonization of Financial Laws and Regulations 0.88 0.88 0.88 0.88 3.50

Capacity Building 0.50 0.50 0.50 0.50 2.00

Sub-total 10.82 3.40 2.72 2.05 19.00

Project Management 0.25 0.25 0.25 0.25 1.00

Total Cost 11.07 3.65 2.97 2.30 20.00

2.5 Project’s Target Area and Beneficiaries

2.5.1 While the EAC will be the recipient of the grant, the project will be implemented in

the territories of the five EAC Partner States. The direct beneficiaries of the project will include

the NCBs of the five countries, the Commercial Banks, other financial institutions and the

judiciary, including the EACJ and members of the EALA. However, given the expected

improvements to the efficiency of payments processing and funds transfers in the countries, the

ultimate beneficiaries would be businesses (especially SMEs) and all users of banking services

(including women which constitute the majority of the population) through increased

participation and inclusion in the formal financial sector. The efficiency and reliability to be

delivered, and expanded financial intermediation, will result in the strengthening and integration

of the national payment systems in the five countries designed to encourage a greater proportion

of the population to migrate into the formal financial sector. The project would also create an

enabling environment for the private sector. As a Regional Public Good, the strengthening of the

payment and settlement systems will enhance regional integration and financial governance.

9 Including contingencies

10 1UA = 155USD as of May 20th 2012

8

2.6 Participatory Process for Project Identification, Design and Implementation

2.6.1 The Bank and the EAC Secretariat, in collaboration with the Central Bank of Rwanda and

other development partners, held a workshop on Payments and Settlement Systems Development

and Integration in the EAC in Kigali in December 2010. The objective of the workshop was to

review the requirements to establish regional payment clearing and settlement systems in the EAC.

It brought together policy-makers, central bankers, bankers associations, regulators, and private

sector mobile network operators, technology companies, and independent service providers and

other experts to discuss key payment and settlement systems issues facing the EAC. The Conference

developed a draft “Road Map” that the EAC Governments, NCBs and Regulators will follow to

undertake the development and subsequent integration of their respective payment and settlement

systems. The Road Map was presented to, and adopted by, the Monetary Affairs Committee (MAC)

of the EAC during its 13th Meeting held in Zanzibar on 16th December 2010. The Bank undertook a

preparation mission jointly with the EAC in May/June 2011, to objectively review the road map and

propose areas where the Bank could consider providing support and assistance in the development

and integration of payment and settlement systems and a “mapping” exercise that highlighted the

areas that the Bank could offer support was undertaken. In addition, the Appraisal Mission, which

took place in May 2012, consulted with all the National Central Banks of the five EAC Partner

States, representatives of the Commercial Banks in all EAC Partner States (including Bankers

Associations), selected private sector ICT and mobile service providers, as well as the World Bank

which is currently implementing the FSDRP in the region. As part of the implementation of the

project, sensitization of the population on retail payment systems and use of electronic means of

payment would be undertaken by means of seminars and workshops and media to explain the new

payment systems to stakeholders.

2.7 Bank Group Experience, and Lessons Reflected in Project Design

Table 2.9: Lessons learned from the previous Payment Systems and other Regional Projects

Lessons learned Actions taken to integrate lessons into the PAR

1. Regional Economic Community Secretariats lack experience

as the executing agency for payment and settlement systems

projects. Moreover, payment and settlement systems integration

projects are complex and multifaceted, due to the number of sub-

components/sub-projects that are commonly implemented

concurrently. Given these factors, the timeframe proposed for the

implementation of the UEMOA project which addressed the

reform of the payment systems turned out not to be feasible.

The appraisal team for the proposed project took all necessary steps to

ensure, as much as possible, that prior to the signing of loan agreements,

the conditions precedent to first disbursement would be met to ensure that

the timeframe agreed with the client for the implementation of the project

would be feasible. The EAC Secretariat will also initiate the process of

recruiting the Payment and Settlement Systems Specialist and other skills

required ahead of project approval.

2. In the case of the Union Economique et Monétaire Ouest

Africaine (UEMOA) project, there was weak collaboration

between the implementing agency, the project beneficiaries and

users. For instance, after the completion of the RTGS component

of the project it took a long time before it was launched thereby

delaying the use of the systems.

In the case of the proposed project effort would be made to ensure close

collaboration between the implementing agency and the beneficiaries of

the project. During the appraisal mission extensive consultations were held

with the beneficiaries of the project that include both National Central

Banks and Commercial Banks. The role of the NPSCs which would be

established as part of the project would also ensure sustained consultations

with stakeholders throughout the implementation of the project.

Component 3 of the project provides for sensitization of the population on

retail payment systems and use of electronic means of payment, by means

of seminars, media awareness and workshops to explain the new payment

systems to stakeholders.

3. In many cases, there is a lack of or insufficient capacity of

local contractors and service providers to implement projects of

regional dimensions. This has been found to be a limiting factor

which has subsequently proved difficult to correct during project

implementation.

During the appraisal mission consultations were held with local service

providers to assess their capacity to provide the requisite goods and

services. While in two the capacity was weak, there was adequate capacity

in the remaining three countries. The mission therefore concluded that, on

a regional basis, there is adequate capacity to provide the required goods

and services.

4. In many instances, regional organizations are not familiar with

Bank rules and procedures which caused undue delays to project

start-up and implementation.

The Bank will undertake training on its rules and procedures to build the

required capacity at the EAC Secretariat, the EAC-CPT and the CPT at the

National Central Banks in the application of the Bank’s rules and

procedures.

5. It is important that in the formulation of conditions that the

Bank ensures that the conditions are realistic and achievable

within a reasonable time. This will help to avoid lengthy delays

in fulfilling effectiveness and first disbursement conditions.

The appraisal team has taken all steps to ensure that the conditions

precedent to first disbursement specific in this report is achievable within a

reasonable timeframe.

9

2.8 Key Performance Indicators

2.8.1 The key performance indicators identified and the expected outcomes, at project

completion, are presented in the results-based logical framework (page vi). The first expected

outcome is an improved and integrated regional payment and settlement system and improved

efficiency of funds transfer across the five EAC countries. The performance indicators under

this outcome are:

(i) Growth in inter-bank high-value funds transfers growing from US$279 billion in 2010 to

US$ 340 billion in 2014 and US$420 billion in 2016; and

(ii) Improvement in the longest clearing and settlement cycle for local and upcountry

cheques within the region from T+10 days in 2011 to T+5 days in 2014 and T+3 days in

2016.

2.8.2 The second expected outcome is; Adequate and harmonized legislation and policy

supporting payment and settlement systems. The main performance indicator under this

outcome is:

(i) Improvement from the current state of, very limited regional legislative support for

payment and settlement systems to the promulgated legislative support for National

Payment Systems, CSD laws and ACH in Uganda, Burundi and Tanzania, respectively

by 2014 and the approval of harmonized rules and regulations for RTGS and National

Payment Systems by the Monetary Affairs Committee and promulgation of the laws by

the National Assembly by the end of 2016.

III. PROJECT FEASIBILITY

3.1 Economic and Financial Performance

3.1.1 The proposed project is an Institutional Support Operation and, as such, is not

amenable to credible and rigorous cost-benefit and financial analyses. While the costs of the

proposed project are quantifiable (section 2.4), the benefits are indirect and realizable through

the integration of the region’s wholesale and retail payment and settlement systems which will

provide seamless transmission of funds at both the commercial and individual level throughout

the EAC Partner States thereby providing an enhanced platform to facilitate expansion of intra-

regional trade and attract greater local and foreign direct investments. The economic

justification of the proposed project includes its contribution to the facilitation of the migration

to a common currency and the facilitation of the progress to EAC monetary union resulting in an

expanded regional market. In addition, the project is expected to improve financial security of

inter-bank flows, within the region, by reducing the use of cash. It will also contribute to

increasing financial system stability as “float” at all levels can be reduced, together with the

mitigation of systemic risk. Furthermore, fraud associated with high value sums paid through

cheques is mitigated by encouraging the use of RTGS systems. It will also contribute to the

reduction of clearing and settlement delays by banks to their customers thus making funds

transfer more efficient. The consequent efficiency gains that would result from the above

benefits and the accelerated means of undertaking payment for goods and services would

contribute to an expansion of the regional economy and GDP growth within the region. In

general, it is expected that the economic and financial benefits from the proposed project will be

much higher than UA 15.0 million. Other economic and social benefits of the project are

discussed in section 3.2 below.

10

3.2 Environmental, Social and Other Impacts

3.2.1 Environment: The project has been classified as Category 3 by ORQR and will

therefore have no adverse effect on the environment.

3.2.2 Gender: As indicated above, the proposed project would promote cross-border trade;

and since women are the most active participants in cross-border trade, particularly at the retail

level, the project will have positive social impact on women in the EAC. The project will

promote gender inclusiveness through other benefits that it will confer on the population of the

region, the majority of which are women. Some of these benefits include, the potential for the

project to play a key role in facilitating greater access to finance to the population, contribute

significantly in facilitating financial inclusion and expansion of financial services “access

points” to the citizens of the EAC region, within a well regulated and legislative framework. The

provision of extended “access points” coupled with “agency banking” arrangements that are

“bank-driven” which will result from the project is also expected to provide outreach to the un-

banked, and improve financial deepening as more people are encouraged to move from the

informal economy to the formal sector as financial services become less complex, more

accessible and more reliable specifically reaching the female population.

3.2.3 Social: The availability of modern and harmonized payment systems among the

countries of EAC would ease interbank fund transfers within the region, thereby reducing the

necessity for carrying large amounts of physical cash by traders, which exposes them to risks of

theft and harm. The expected increase in regional trade that would be facilitated by the project

together with the consequent expansion of the regional economy and GDP growth is also

expected to lead to increased income for the poor, especially women active in cross-border

trade, thereby improving their economic and social well-being.

3.2.4 Regional Integration: Through its impact on the acceleration of convergence of

payments and settlement systems, and the strengthening of regional Common Market

commercial activities, the project will contribute to the attainment of EAC’s regional integration

objectives. Moreover, the negotiations of all the provisions of the EAC Monetary Union

Protocol have been completed and awaiting signature by the Summit. The project is a critical

element that would contribute to its effective operation.

3.2.5 Private Sector Development: The project is expected to lead to a reduction in funds

transfer costs for SMEs, the economy and the public in general. The integration and

management of sound payment and settlement systems would contribute to the overall

landscape of the EAC while also encouraging FDI and the presence of multinational enterprises

that are evaluating investment in the region which would benefit from an integrated and sound

regional payment and settlement systems.

IV. IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 Executing Agency: The main organs of the EAC are (i) the “Summit of the Heads of

States and Governments of Partner States” which gives broad direction towards the realization

of the goals and objectives of the community; (ii) the “Council of Ministers”; (iii) the “Co-

ordination Committee” which is made up of Permanent Secretaries and reports to the “Council

of Ministers” and co-ordinates the activities of the sectoral committees; (iv) the “East African

Legislative Assembly” (EALA); (v) the East African Court of Justice (EACJ); and (vi) the

“EAC Secretariat” which is the executive organ of the Community. The EAC would be the

recipient of the grant. The EAC Secretariat will be the “Executing Agency” of the EAC-PSSIP

and will be responsible for the overall implementation of the project. The EAC Secretariat will

11

be the operational link between the Bank and the five EAC Partner States. In this regard, the

project will be implemented by an EAC “Core Project Team” (EAC-CPT) to be established at

the EAC Secretariat. The EAC-CPT would be assisted in this assignment by a Payment System

Specialist who would serve as the Project Manager, a Procurement Specialist and an

Accountant. The Payment Systems Specialist, Procurement Specialist and Accountant would be

recruited by the EAC using resources provided by the Grant. The project will also require a

Project Administrative Assistance. In addition the EAC would be required to assign an M&E

Specialist and an Information and Technology Expert to the project as part of the EAC-CPT.

4.1.2 As agreed with the EAC and NCBs, the project implementation will be delivered at

two levels: the regional level and country level. At the regional level, a Regional Core Project

Team (CPT) would be constituted at the EAC Secretariat. The EAC-CPT would maintain

responsibility for the overall coordination of project implementation. The EAC-CPT will consist

of, at least, three (3) EAC staff from relevant departments/units (including technical staff from

the ICT department and an M&E Specialist) and would be headed by the EAC Director of

Planning. He or She would be the “Project Director” and would be responsible for providing

general oversight of project implementation activities, and effective interface with the senior

management of EAC and the NCBs. The Payment Systems Specialist would serve as the Project

Manager with responsibilities for managing day-to-day project activities.

4.1.3 Actual implementation shall be done at the country level by the National Central

Banks, which shall be designated as the Implementing Agencies. The NCBs would be required

to establish National Core Project Teams (NCB-CPT) with the head of the department

responsible for payment systems at the National Central Bank as the “National Project

Coordinator”, and including experts for each of the project components, including an M&E

Specialist. The NCBs’ project teams would be responsible for all project implementations at the

national level. Furthermore, if not already in place, the NCBs will be required to facilitate the

establishment of “National Payment Systems Committees” (NPSC), comprised of

representatives of the NCBs, Commercial Banks, and other relevant stakeholders. The NPSC

would be regularly consulted during the course of project implementation, and would provide

inputs from the users’ perspective. The establishment of the EAC-CPT and NCB-CPT by EAC

and the NCBs respectively, is a condition of first disbursement of the grant resources, while the

establishment of the NPSC is also a condition of the grant.

4.1.4 The NCBs will be required to establish a Steering Committee at the country level that

would be chaired by the Deputy Governor, who will also serve as the Project Sponsor. The

Steering Committee, which will have oversight over the NCB-CPT, would include management

level stakeholders that will be directly impacted by the outcome of the project, including heads

of payment and settlement systems, information management systems, financial markets,

banking operations, banking supervision, research, finance, and legal. During the

implementation, the Steering Committee will provide policy direction, and resolve cross-

functional and other matters pertaining to the project. The “Project Coordinator”, as a member

of the Steering Committee, would provide the required interface between the project and the

committee. Representatives of the EAC and solution providers may be invited to participate in

the Steering Committee meetings as need arise. In addition, there shall be an Executive

Committee, chaired by the Deputy Secretary General Planning and Infrastructure (EAC

Secretariat), and composed of representatives of the EAC Secretariat and the NCBs at Deputy

Director or Director level which will be responsible for supervising Project operations, in

particular overseeing the execution of financial management, procurement, accounting, and

monitoring and evaluation (M&E) functions of the EAC-CPT and NCB-CPT. The Executive

Committee will be required to meet, at least once in each quarter, to deliberate on the direction

of implementation of the project and to take remedial measures where necessary. Members of

12

the EAC-CPT and NCB-CPT may be invited to participate in the Executive Committee

meetings as need arise.

4.1.5 Financial Management, Reporting and Audit: The EAC-CPT will be responsible for

the financial management of the project. Under the guidance of the Director of Planning, the

EAC-CPT, will manage; the budgeting, financial accounting and financial reporting aspects of

the project. The accounting will utilize the EAC Computerized Accounting system. All projects

in EAC use the same “Chart of Accounts” which are GFS based and they will not therefore, be

required to revise their “Chart of Accounts”. The EAC’s financial systems comply with IPSAS

Accrual basis of Accounting and operate under the Sun system.

4.1.6 The project will follow the financial year of the EAC which runs from 1st July to 30th

June. The EAC-CPT would be required to produce quarterly interim financial reports for the

project which will be submitted to the Bank no later than 45 days after the end of each quarter.

The EAC Internal Audit Department will audit the project at least once annually. The internal

audit reports will be shared with the Bank. Annually, the EAC will produce project specific

annual financial statements. An annual external audit will be carried out by a competent auditor

acceptable to the Bank, selected by the EAC, using the EAC systems. The EAC is currently

being audited by an Audit Commission made up of the Auditor Generals’ of the member states.

The Bank recognizes The Audit Commission as an acceptable auditor. However, the EAC

Secretariat has the option to recruit an international private audit firm for the purpose of

expediting the audit process. To that end, the funds have been appropriately allocated to the cost

of the audit in the project budget. The last three entity audit reports of EAC had unqualified

audit opinions. The audit report, complete with a Management Letter will be submitted to the

Bank not later than six months after the end of the financial year. A detailed audit arrangement

is set out in Technical Annex C3.

4.1.7 Procurement: All procurement of goods and acquisition of consulting services

financed by the Bank will be in accordance with the Bank's Rules and Procedures for

Procurement of Goods and Works or, as appropriate, Rules and Procedures for the Use of

Consultants, May 2008 edition and as amended from time to time, using the relevant Bank

Standard Bidding Documents. The East Africa Community (EAC) Secretariat will be the

Executing Agency responsible for coordinating the procurement of goods, services and

miscellaneous items while the National Central Banks will be the Implementing Agencies

responsible for providing the technical inputs and implementation of the activities at national

level. An assessment of the EAC Secretariat, Procurement Unit to undertake procurement under

ADF financing was undertaken and it was concluded that the unit will need further

strengthening in order to effectively support the project. In this regard, a Senior Procurement

Specialist will be recruited as part of the Regional Core Project Team to be responsible for

procurement under the project, support the Procurement Unit in its regular activities and mentor

staff. Detailed procurement arrangements are presented in Technical Annex C4.

4.1.8 Disbursement: Disbursement to the project will be undertaken in line with the Bank’s

procedure. The Bank’s four disbursement methods will be available to be used during project

implementation. Disbursement of funds for consulting and non-consulting services and the

payment of goods and equipment will be by direct payment in accordance with the Bank’s

Handbook on Disbursement. For purposes of the project, the EAC will open a “Special

Account” (in US Dollars) at a Bank acceptable to the African Development Bank to receive

funds designated for financing project implementation activities such as capacity building and

training activities as well as smaller payments. The size of the initial advance into the Special

Account shall be as per the Bank’s disbursement rules. The opening of the Special Account will

be a condition precedent of first disbursement of the grant. The Bank’s Disbursement Letter will

be issued stipulating key disbursement procedures and practices. The Bank will have the right,

13

as reflected in the General Conditions to suspend disbursement of the Funds if reporting

requirements are not complied with.

4.1.9 While the Special Account would be opened and managed by the EAC, it might be

necessary, for ease of project implementation, for sub-accounts to be opened in the recipient

countries by each of the NCBs. The EAC would be authorized to transfer reasonable amounts of

money, based on estimated project requirements, to the sub-accounts opened in the countries.

All payments into the special account together with any transfers to the sub-accounts must be

fully justified before the replenishment of the Special Account. The Special Account, opened by

the EAC will be replenished on condition that at least 50 percent of the most recent advance and

100 percent of all older advances have been justified. Transfers to the sub-accounts, opened in

the countries, will not be considered as justifications and the EAC will be responsible for

ensuring that the sub-account holders submit to the EAC the relevant documentation to account

for the transfers received from EAC.

4.2 Monitoring Arrangements

4.2.1 Monitoring and evaluation (M&E) activities remain crucial for the successful

implementation of the project. In addition to the regular dialogue between the Governance

Expert based in EARC and the EAC-CPT, the Bank will undertake supervision missions, at

least, twice annually. The EARC and Field Offices in Bujumbura, Kampala, Kigali and Dar es

Salaam will also assist in on-going monitoring of project implementation. The EAC will

maintain constant communication with the Bank on the progress of implementation. A mid-term

progress review to assess achievements, discuss constraints and make necessary adjustments,

where needed, would be undertaken after two years of implementation. At the end of project

implementation, the Bank would prepare a Project Completion Report (PCR) to evaluate the

achievements of the project and the lessons learned from its implementation.

4.2.2 The EAC will submit quarterly progress reports’ in a form and substance satisfactory

to the Bank, on the implementation of the respective components. The reports will review

progress made in light of the project’s “Results-Based Logical Framework” and include a clear

presentation description of activities undertaken during the period under review. The reports

will also analyze; to what extent the activities undertaken have contributed to the realization of

the anticipated results/outputs and project objectives, make recommendations to address any

issues encountered, and present “time-bound” actions/work plans for the following quarter. The

EAC will also be required to prepare and submit, to the Bank, a Project Completion Report

(PCR) within three months of the final disbursement that will provide an overview of the

project’s implementation, the project outputs achieved vis-à-vis the estimates and the lessons

learned from the implementation in accordance with the Bank’s General Rules and Procedures.

The indicative implementation schedule is summarized as follows:

Table 4.1: Project Implementation Schedule

Task Responsible Party Dates/Period

Preparation Bank May/June 2011

Appraisal Bank May 2012

Grant Approval Bank December 2012

Grant Effectiveness Bank and EAC/NCBs December 2012/January 2013

Procurement of goods and services EAC/NCBs March 2013 – June 2015

Training programmes EAC/NCBs June 2013 – June 2016

Submission of Annual Audit Report EAC Annually from 2014 to 2017

Supervision Mission Bank June, and December 2013, 2014, 2015, and 2016

Mid-term Progress Review Bank November 2014

Project Completion Bank and EAC/NCBs December 2016

Last Disbursement Bank June 2017

Project Completion Report Bank and EAC December 2017

14

4.3 Project Governance

4.3.1 Article 4 of the EAC Treaty which provides for legal capacity of the Community,

states that the Community, as a corporate body shall be represented by the Secretary General.

Consequently, funding for all projects and programmes of the EAC is negotiated, agreement

signed and managed by the EAC Secretariat. This is founded on the provisions of Article 4 read

together with Article 71 of the EAC Treaty which provides for, inter-alia, the Secretariat’s

function envisaging: 71 (1) (b) the initiation of studies and research related to the

implementation of programmes for the most appropriate, expeditious and effective ways of

achieving the objectives of the community; (c) the strategic planning , management and

monitoring of programmes for the development of the Community; (h) the general

administration and financial management of the Community; (i) the mobilization of funds from

the development partners and other sources for the implementation of projects for the

Community. It is clear from these provisions that the EAC Secretariat has the mandate to deal

with the Bank on EAC related projects/programmes requiring funding. The implementation of

this project shall therefore, be similar to the implementation of any other EAC project or

programme.

4.4 Project Sustainability

4.4.1 The key stakeholders to the project, including the EAC, NCBs and Commercial Banks

have indicated strong commitment to the overall sustainability of the project. In particular, the

NCBs and Commercial Banks have been in the forefront of the efforts to improve the payment

systems in the EAC Partner States. The National Payment Systems Committees, proposed in

this report, would be charged with the responsibility of monitoring and supporting the

investments made under the project. Also, the EAC has committed to mainstreaming the

Payment System Specialist, Procurement Specialist, Accountant, and Project Administrative

Assistant to be recruited for the project after the implementation of the project. This will ensure

that core capacity for payment and settlement systems is established at the EAC. In addition,

since the five countries are at different levels of implementation of payment and settlement

systems, provision has been made under the capacity building component for study tours,

including exchange programs between the NCBs to exchange expertise and experience.

4.4.2 In terms of availability of resources for project operational and recurrent costs, post-

implementation, “cost recovery” charges, which are already in place in some of the EAC Partner

States, would contribute to the sustainability of the associated payment and settlement systems.

The arrangement involves user-charges by the NCBs (owners of the systems) on the commercial

banks and other participants, on a pro rata basis, for the use of the systems. The participants, in

turn, recover the resulting charges through the banking fees charged to their customers.

Additional charges to customers are usually limited, given the large volume of transactions. It is

also expected that the increased efficiency delivered by the new systems will encourage further

reduction in charges. As part of the harmonization process, consideration must be given to the

harmonization of the “cost recovery charges” currently in place in the countries to ensure that

they are equitable across the EAC region.

4.4.3 With regard to technical sustainability, the technologies to be employed for

component 1 of the project are standard industry technologies that have been well tested and

deployed worldwide. For instance, SWIFT is a proven “message carrying” service available on a

global basis. In addition, the service providers for the new systems will be required to provide

extensive training for the personnel of the NCBs and the Commercial Banks that would operate

the systems. Capacity building is a key component of the project, and will ensure that

participant’s staff is adequately trained and that they receive regular skills upgrades when

15

necessary. An assessment of the appraisal team shows that business continuity and disaster

recovery arrangements are in place in EAC countries. However, business continuity in Burundi

and Kenya, and disaster recovery arrangements in Tanzania and Rwanda would be further

strengthened. This is provided for under component 1 of the project (see table 2.1).

4.4.4 With regard to the responsibility for coordination, after the implementation stage of

the project, the proper functioning of the proposed EAC Monetary Union would require the

establishment of the East African Central Bank (EACB) whose primary objective shall be to

achieve and maintain price stability in the single currency area. The EACB shall, together with

the NCBs, form a functionally integrated region-wide system of Central Banks that shall

perform the Central Bank functions in the Monetary Union. However, in the transition period,

there will be an Institution, as a precursor to the establishment of the EACB, to coordinate the

monetary and exchange rate policy and all the preparatory work towards the Single Currency.

The responsibility for coordination and maintenance of the proposed EAC Payment and

Settlement Systems Integration Project will be transferred to this organ as soon as it is

established.

4.5 Key Risks and Mitigation Measures11

Table 4.2: Risks and Mitigation Measure

Risks Mitigation Measures

Risk 1: Full functionality of the integrated systems if the new

systems are not fully implemented at national levels.

This risk is mitigated by continued commitment and ownership of the new systems

by the Central Banks. In fact, they have also initiated investments that are

complementary to the components being provided by the proposed project. The

proposed project is therefore intended to fill the gap.

Risk 2: Possible lack of commitment of the Commercial Banks

to the new payment systems.

This risk is mitigated given the commercial benefits that the new systems would

provide to the Commercial Banks. The Commercial Banks have been placing

demands on the NCBs regarding the need to modernize and integrate the national

payment systems. They have also initiated investments to upgrade their

infrastructure in anticipation of new payment systems. The arrangements for

implementing the project also ensure that the Commercial Banks are fully involved

in its implementation as members of the NPSCs.

Risk 3: Systems failure and systemic risk posed by having EAC

Partner States with mixed levels of readiness and payment

systems automation and standards.

Business continuity and disaster recovery plans are in place in all the NCBs. These

plans were assessed during the appraisal mission and found acceptable. However, as

a further mitigation measure, the business continuity arrangements in Burundi and

Kenya and disaster recovery arrangements in Tanzania and Rwanda would be

further strengthened.

Risk 4: Technical Solutions may not be sustained

This risk is mitigated because the technologies to be employed for component 1 of

the project are standard industry technologies that have been well tested and

deployed worldwide. Moreover, Capacity building is a key component of the

project, and will ensure that participant’s staff is adequately trained and that they

receive regular skills upgrades when necessary.

Risk 5: Possible constraints of required project implementation

capacity which could delay project implementation.

The project has provided for the recruitment of a “Payment and Settlement

Specialist, a Procurement Expert and an Accountant to strengthen the

implementation capacity of the EAC CPT. In addition, the NCBs, shall provide the

necessary technical expertise throughout the procurement process thereby reducing

any residual risk. The project provides for trainings and workshops.

4.6 Knowledge Management

4.6.1 The implementation of the PSSIP will result in the development of skills and

knowledge in specific areas of payment and settlement systems operations and functions for the

EAC Secretariat, National Central Banks, and Commercial Banks. This knowledge will be

disseminated through seminars and workshops organized by the National Central Banks and

Bankers’ Associations. Also, the implementation of the capacity building component of the

project will result in knowledge building for Judges and judicial officers at the EACJ and

national courts, as well as members of the EALA. This knowledge will be disseminated through

applications of the knowledge, law of precedence, and seminars and workshops. The EAC-

PSSIP will contribute to knowledge building and development of skills in specific areas of

payment and settlement systems for the EAC Secretariat (including the EAC-CPT), National

11

Risks relating to Financial Management are discussed in Technical Annex C3

16

Central Banks, Commercial Banks, Judges and other stakeholders who would be trained in, but

not limited to, such disciplines as; the requirement for adequate legislation to support both

national and regional payment systems that are in-line with the BIS CPSIPS; settlement finality;

legality of electronic payment instruments; soundness of computer records/image’s etc. as prima

facie evidence; commercial law and enforcement of collateral requirements, the resolution of

contractual disputes, especially in relation to payment and settlement systems. This will

contribute significantly to the legislative capacity in the region in the regulatory and legal

elements of payment and settlement systems together with; dispute resolution in the area of

payment and settlement systems so as to effectively address the concerns of the business

community and the public and build the professional capacity to effectively manage the

increasing national and cross-border complex commercial and personal transactions. Legal

officers at the National Central Banks and Commercial Banks would also be trained in legal

aspects of payment and settlement systems. Other groups that would be targeted by the training

programmes under the project will include; Ministries of Finance, Capital Market Authorities,

Stock Exchanges, Revenue Authorities, and Customs.

V. LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal Instrument

5.1.1 The Grant Protocol of Agreement between the East African Community and the

African Development Bank for an amount of ADF Grant of UA 15.0 million from the Regional

Operation Envelope.

5.2 Conditions Associated with Bank’s Intervention

5.2.1 The ADF Grant Protocol of Agreement shall enter into force on the date of signature

by the East African Community and the African Development Fund. The first disbursement of

the grant shall be subject to effectiveness of the Grant Protocol of Agreement and fulfillment by

the Grantee, to the satisfaction of the Bank of the following specific conditions:

A. Conditions Precedent to First Disbursement: The obligations of the Fund to make the first

disbursement of the Grant shall be conditional upon the entry into force of the Protocol of

Agreement and the Recipient having provided evidence satisfactory to the Fund of the

fulfillment of the following conditions.

(i) The Recipient shall submit a commitment letter jointly signed by all the Central Bank

Governors of the respective Partner States endorsing the Project;

(ii) The Recipient shall open a foreign currency account for the deposit of the proceeds of

the Grant;

(iii) The signing of Implementation Agreements between the Recipient and Partner States for

the implementation of the Project at the national level of the respective Partner States;

(iv) The designation of a Regional Core Project Team by the Recipient with the EAC

Director of Planning as the Regional Project Coordinator , Monitoring and Evaluation

Expert and an Information and Technology Expert, whose terms of reference are

acceptable to the Fund; and

(v) The constitution of National Core Project Teams at the Central Banks of Burundi,

Kenya, Rwanda, Tanzania and Uganda, with the respective heads of departments

responsible for Payment Systems as the National Project Coordinator, whose terms of

reference are acceptable to the Fund.

17

B. Other Conditions: The Recipient shall provide evidence, in form and substance satisfactory to

the Fund, that National Payment System Committees (NPSC) in Burundi, Kenya, Rwanda,

Tanzania and Uganda have been established with members and terms of reference acceptable to

the Fund.

5.3 Compliance with Bank Policies

5.3.1 This project complies with all applicable Bank policies.

VI. RECOMMENDATION

6.1 Recommendations: Management recommends that the Board of Directors approve the

proposed Grant, not exceeding UA 15.0 million, to the East African Community from the ADF

(Regional Operations envelop) to finance the activities discussed in this report.

I

APPENDIX 1: EAC - SELECTED MACROECONOMIC INDICATORS

Macroeconomic Indicators 2000 2005 2006 2007 2008 2009 2010 2011 2012

( e ) (p) (p)

Real GDP Growth Rate (%) 7.9 7.3 6.8 7.3 6.1 4.3 6.3 5.3 5.7

GDP Per Capita (US $) 301 388 422 492 561 551 578 630 667

Real per Capita GDP Growth Rate (annual %) 4.9 4.4 3.8 4.3 3.1 1.4 3.3 2.3 2.7

Inflation (%) ... 8.2 6.8 5.9 13.5 11.6 4.8 14.0 9.9

Fiscal Balance (% of GDP) -1.5 -1.0 -3.2 -1.9 -2.1 -3.7 -6.1 -6.6 -7.2

Gross Domestic Investment (% of GDP) 17.4 20.2 21.1 22.7 22.8 23.0 23.8 23.8 23.8

Gross National Savings (% of GDP) 14.1 18.8 17.1 16.6 15.9 15.6 16.7 18.1 17.6

Real Export Growth, Goods (%) 1.5 19.8 -3.9 12.0 9.3 -2.6 3.0 -1.1 12.1

Real Import Growth, Goods (%) -4.2 16.2 10.5 15.9 6.6 16.4 3.8 6.3 3.7

Terms of Trade, Goods (%) -8.1 -4.3 -5.1 4.0 -7.1 16.4 10.4 5.3 -8.6

Trade balance (As % of GDP) -8.4 -9.8 -13.3 -13.9 -16.1 -15.6 -14.9 -17.3 -16.6

Current Account (% GDP) -4.0 -2.5 -4.9 -5.4 -8.7 -7.4 -7.7 -8.5 -9.6

Remittances inflows (USD Billion) 0.79 1.17 1.58 2.11 2.51 2.61 2.84 ... ...

FDI Inflows (USD Billion) 0.59 0.91 1.32 2.25 1.62 1.73 1.74 ... ...

Net total ODA (USD Million) 2.84 4.39 5.45 7.09 6.79 7.99 7.97 ... ...

Total External Debt (% GDP) 58.4 46.4 40.6 23.6 24.5 25.8 27.4 28.8 30.3

Debt Service (% of Exports) 25.1 9.7 11.6 64.1 3.6 4.1 3.6 3.8 3.4

Source: AfDB Statistics Department, UNCTAD and IMF.

II

APPENDIX 2: BANK PUBLIC SECTOR PORTFOLIO IN EAC COUNTRIES

Updated : 31-May-12

Sector Project Title

Fin Source

/Inst

Bank

Financing

(UA mil)

Approval

Date

Completio

n Date

KENYA

Agriculture ASAL-Based Livestock and Rural Livelihoods Support Project ADF-Loan 18.4 17/Dec/03 30/Dec/12

ADF-Grant 3.2 17/Dec/03 30/Dec/12

Kimira- Oluch Smallholder Farm Improvement Project ADF-Loan 23.0 31/May/06 30/Sep/13

ADF-Grant 1.2 31/May/06 30/Sep/13

Small-Scale Horticulture Development Project ADF-Loan 17.0 5/Sep/07 31/Dec/14

Restoration of Farm Infrastructure (Rural Livelihood Rehab. & Recon.) ADF-Loan 15.0 29/Apr/09 30/Jun/13

Green Zones Developmemt Support Project ADF-Loan 25.0 12/Oct/05 31/Dec/13

Environment Ewaso Ng'ïro North Natural Resources Conservation Project ADF-Loan 13.6 22/Apr/05 31/Dec/12

ADF-Grant 2.9 22/Apr/05 31/Dec/12

Power Mombassa Nairobi Transmission Line ADF-Loan 50.0 6/May/09 31/Dec/13

Kenya Elec Transmission Project ADF-Loan 46.7 6/Dec/10 30/Jun/15

Menengai Geothermal Development project ADF-Loan 80.0 14/Dec/11 31/Dec/17

Social Community Empowerment Project (CEISP) ADF-Loan 17.0 17/Dec/07 31/Jul/14

Technical Industrial Vocational and Entrepreneurship Training (TIVET) ADF-Loan 25.0 16/Dec/08 31/Dec/13

Education III Project ADF-Loan 24.3 17/Dec/03 30/Dec/12

ADF-Grant 6.8 17/Dec/03 30/Dec/12

Rural Health Project III ADF-Loan 17.2 7/Jul/04 30/Aug/12

ADF-Grant 6.0 7/Jul/04 30/Aug/12

Nairobi - Thika Highway Improvement Project ADF-Loan 117.9 21/Nov/07 31/Dec/12

ADF-Loan 3.2 21/Nov/07 31/Dec/12

Timboroa - Eldoret Road Project ADF-Loan 35.0 24/Nov/10 29/Feb/16

Water

Sup/Sanitation Integrated Land & Water Management (AWTF) ADF-Loan 1.6 13/Jan/09 31/Dec/12

Water Services Boards Support Project ADF-Loan 35.2 21/Nov/07 31/Dec/12

RWSSI-Grant 9.2 5/Dec/07 31/Dec/12

Nairobi River Basin Restoration ADF-Loan 35.0 6/Dec/10 31/Dec/15

Small Towns Water and Sanitation ADF-Loan 70.0 3/Nov/09 31/Dec/14

BURUNDI

Power Réhabil. et Exten. infrastructures élec ADF-Grant 7.3 5/Jul/07 30/Sep/12

Social Projet multisectoriel de réinsertion (Loan) ADF-Grant 9.8 13/Dec/04 30/Nov/12

Projet de Creation d'Emplois ADF-Grant 10.0 24/Jun/09 31/Dec/13

Transport Projet Gitega- Nyangungu-Ngozi Phase 1 FSF-Grant 24.1 27/Sep/10 31/Dec/13

Projet Gitega-Ngozi Phase 2 FSF-Grant 32.0 29/Jun/11 31/Dec/15

ADF-Grant 10.0 29/Jun/11 31/Dec/15

Route Nyamitanga-Ruhwa-Ntendezi-Mwityazo ADF-Grant 49.4 16/Dec/08 31/Dec/13

Water

Sup/Sanit Projet de Rehabilitation et d'Extension des Infrast. Hydrauliques en Milieu Rural ADF-Grant 12.0 14/Dec/05 30/Dec/12

Réhabil. et Exten. infrastructures élec ADF-Grant 7.3 5/Jul/07 30/Sep/12

RWANDA

Agriculture Inland Lakes Int Development & Managementt Support Project (PAIGELAC) ADF-Loan 13.8 6/Oct/04 31/Dec/12

ADF-Grant 1.0 6/Oct/04 31/Dec/12

Bugesera Agricultural Development Support Project (PADAB) ADF-Grant 10.0 24/Jul/06 31/Dec/13

PPF LISP ADF-Grant 0.5 20/Nov/10 31/Dec/12

Livestock Infrastructure Support Program (LISP) - SBS ADF-Loan 21.8 29/Jun/11 31/Dec/15

Transport Butare-Kitabi-Ntendezi Road ADF-Grant 16.0 25/Mar/09 31/Dec/13

Rwanda-(Nyamitanga-Ruhwa-Ntendezi-Mwityazo Rd) ADF-Grant 50.6 16/Dec/08 31/Dec/13

Sustainable management of woodlands and restoration of natural forests of Rwanda CBFF-Grant 3.0 29/Nov/11 31/Dec/15

Water

Sup/Sanit Rural Water and Sanitation-Phase II (AEPA) ADF-Grant 10.0 1/Jul/09 31/Dec/13

Social Support to Skills Development in Science & Tech ADF-Grant 6.0 11/Nov/08 31/Dec/13

Regional ICT Centre of Excellence ADF-Loan 8.6 14/Dec/10 30/Jun/16

Multisector Competitiveness & Enterprise Development ADF-Grant 5.0 29/Dec/08 31/May/13

Support for Policy and Strategy Development ADF-Grant 1.0 18/Sep/09 31/Dec/12

TANZANIA

Agriculture District Agricultural Sector Investment Project ADF-Loan 36.00 24/Nov/04 31/Dec/13

ADF-Grant 7.00 24/Nov/04 30/Jun/12

Support the Lake Tanganyika Integrated Regional Development Programme

(PRODAP) ADF-Loan 4.99 17/Nov/04 31/Dec/13

Marketing Infrastructure, Value addition and Rural Finance Program (MIVARFP) ADF-Loan 40.00 29/Jun/11 31/Dec/16

Transport Zanzibar Roads Upgrading Project (ZNZ only) ADF-Loan 16.22 9/Jun/04 30/Sep/12

ADF-Grant 2.60 9/Jun/04 31/Dec/07

Singida-Babati-Minjingu Road Project ADF-Loan 60.00 17/Sep/07 31/Dec/14

III

Tanzania Road Sector Support I ADF-Loan 152.00 2/Dec/09 31/Dec/15

Tanzania Road Sector Support II ADF-Loan 120.00 4/Apr/12

Water

Sup/Sanit Rural Water Supply and Sanitation Programme II ADF-Loan 59.00 15/Sep/10 31/Dec/15

AWTF-Grant 5.46 15/Sep/10 31/Dec/15

Zanzibar Water & Sanitation Project (ZNZ only) ADF-Loan 25.00 11/Nov/08 31/Dec/13

AWTF-Grant 2.76 11/Nov/08 31/Dec/13

Power Electricity V Project ADF-Loan 28.68

14-De-

2007 31/Dec/12

ADF-Grant 1.32

14-De-

2007 31/Dec/12

Iringa-Shinyanga Transmission Line ADF-Loan 45.36 26/Oct/10 31/Dec/14

Social Support to SAP for Vocational Ed & Training ADF-Loan 14.22 9/Jul/03 30/Jun/12

ADF-Grant 1.60 9/Jul/03 30/Jun/12

Support to Maternal Mortality Reduction Project ADF-Loan 40.00 11/Oct/06 31/Dec/12

Small Entrepreneurs Loan Facility II ADF-Loan 20.00 10/May/10 31/Dec/15

Alternative Learning and Skills Development II (ZNZ only) ADF-Loan 15.00 29/Jun/11 31/Dec/16

Multisector Institutional Support for Good Governance II ADF-Loan 5.20 20/Sep/10 31/Dec/14

Poverty Reduction Support Loan IV ADF-Loan 100.00 16/Dec/11 31/Dec/13

UGANDA

Agriculture Farm Income Enhancement& Forestry Conservation project ADF-Loan 31.6 29/Sep/04 30/Dec/12

ADF-Grant 9.9 29/Sep/04 30/Dec/12

Community Agricultural Infrastructure Improvement Programme- Project I ADF-Loan 30.0 31/Jan/07 31/Dec/13

Community Agricultural Infrastructure Improvement Programme- Project II ADF-Loan 45.0 17/Sep/08 31/Dec/14

Markets and Agricultural Trade Improvement (MATIIP) ADF-Loan 38.0 25/Mar/09 30/Sep/15

Community Agricultural Trade Improvement Programme III ADF-Loan 40.0 3/May/11 31/Dec/16

Transport Road Sector Support Project 1 (Kabale Kisoro Bunagana Rd) ADF-Loan 27.0 27/Apr/05 29/Dec/12

ADF-Grant 1.5 27/Apr/05 29/Dec/12

Road Sector Support Project 1 supplementary Loan ADF-Loan 33.0 20/Dec/06 29/Dec/12

Road Sector Support Project 2 (Fort portal Bundibugyo Rd) ADF-Loan 56.7 17/Dec/07 31/Dec/13

ADF-Grant 1.4 17/Dec/07 31/Dec/13

Road Sector Support Project 3( Nyakahaita Ibanda Rd) ADF-Loan 80.0 25/Sep/09 31/Dec/14

Water Sup/Sanit Kampala Water Sanitation Project ADF-Loan 35.0 16/Dec/08 31/Dec/14

Water Supply and sanitation program ADF-Loan 40.0 10/May/11 30/Jun/16

ADF-Grant 3.6 10/May/11 30/Jun/16

Social Support to Post Primary Education and Training Project (Education III) ADF-Grant 20.0 19/Dec/05 30/Apr/12

Support to the Health Sector Strategic Plan II ADF-Loan 20.0 8/Nov/06 31/Dec/12

Rehabilitation of Mulago and KCC Clinics ADF-Loan 46.0 6/Jul/11 31/Dec/16

Support to Post Primary Education and Training Project (Education IV) ADF-Loan 52.0 25/Nov/08 31/Dec/14

Rural Income and Employment Enhancement Project ADF-Loan 10.2 17/Nov/09 31/Jul/15

Industry/Mine Mineral Resources Management & Capacity Building Project ADF-Grant 5.4 29/Sep/04 31/May/12

Power Bujagali Transmission Interconnection Project ADF-Loan 19.2 28/Jun/07 31/Dec/13

Mbarara-Nkenda/Tororo-LiraTransmission Lines Project ADF-Loan 52.5 16/Dec/08 31/Dec/13

MULTINATIONAL

Agriculture Programme d'Amenagement Lac Tanganyika - Burundi ADF-Loan 5.0 17/Nov/04 31/Dec/13

Projet Developpement Rural du Bugesera (Burundi, Rwanda) ADF-Grant 30.0 25/Sep/09 31/Dec/15

Strengthening Institutions for Risk Management of Transboundary Animal Diseases

in the SADC Region Project (TZ Comp: 3.69 mill UA)

(Tan/Malawi/Angola/Moz/Zam) ADF-Grant 3.69 5/Jul/06 31/Dec/12

Transport East Africa Trade & Transport (EAC, NCTTCA, TTFA) ADF-Grant 9.20 29/Nov/06 31/Dec/12

Mombasa-Nairobi-Addis Corridor II (Kenya, Ethiopia) ADF-Loan 125.0 1/Jul/09 31/Dec/15

Mombasa-Nairobi-Addis Corridor III (Kenya, Ethiopia) ADF-Loan 120.0 30/Nov/11 31/Dec/17

Arusha- Namanga-Athi River Road Development-Kenya (Kenya, Tanzania) ADF-Loan 49.78 13/Dec/06 31/Dec/12

ADF-Grant 3.50 13/Dec/06 31/Dec/12

Phase 2 Chemin Fer DSM/Isaka-Kiga/Keza-Musongati ADF-Grant 3.34 17/Nov/09 31/Dec/12

Social African Virtual University (Phase II) ADF-Loan 10.00 16/Dec/11 30/Jun/17

Power

Interconnection of Electric Grids of Nile Equatorial Lakes Countries (NELSAP) -

(Burundi, Kenya, Uganda, Dr Congo, Rwanda) ADF-Loan 47.36 27/Nov/08 31/Dec/14

ADF-Grant 74.45 16/Jun/10 31/Dec/14

Water

Sup/Sanit Lake Victoria Water and Sanitation Programme ADF-Grant 72.98 17/Dec/10 31/Dec/15

Songwe River Basin Development Programme (Malawi and Tanzania) AWTF-Grant 2.93 25/May/10 31/Dec/14

NEPAD/IPPF-

Grant 1.04 25/May/10 31/Dec/14

SADC Shared Watercourses Support Project (Tan/Zim/Moz) ADF-Grant 9.38 1/Jan/06 30/Dec/12

ADF-Loan 1.66 17/Dec/09 31/Dec/12

IV

APPENDIX 3