building for learning project photo progress report 5 december 2009 – february 2010

16
Building for Learning Project Photo Progress Report 5 December 2009 – February 2010 Project commencement 21 st September 2009

Upload: chase-lyons

Post on 01-Jan-2016

26 views

Category:

Documents


2 download

DESCRIPTION

Building for Learning Project Photo Progress Report 5 December 2009 – February 2010 Project commencement 21 st September 2009. Mid January – more minor demolition and framing. Fire services installed and stairway brickwork. Hooray - Admin completed!!!!!!. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

Building for Learning ProjectPhoto Progress Report 5

December 2009 – February 2010

Project commencement 21st September 2009

Page 2: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

Mid January – more minor demolition and framing

Page 3: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

Fire services installed and stairway brickwork

Page 4: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

Hooray - Admin completed!!!!!!

Page 5: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

Former student work (maths and French) dating back to 1922 found in building cavities from demolition

Page 6: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

1st Storey wall frames going up

Page 7: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

Ground floor ceiling struts and power box installed

Page 8: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

1st Storey Wall Framing – well underway

Page 9: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

While the photos don’t show it – several days of +40c

Page 10: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

Final part of old roof replaced with addition of new 1st Storey roof – February 2010

Finally the last of the timber singles!!!

Page 11: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

With the final part of the roof replaced, the last big cleanup of all the 100+ years of accumulated dust, possum poo,

birds nests, etc from the classroom below

Page 12: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

More scaffolding as the stairway and lift get built.

Page 13: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

Sisalation being added, under black plastic is plaster boards ready for March construction.

Page 14: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

Roof, spouts, drainage and sisalation February 2010

Page 15: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

1st Floor data, electrical, phone installation Solar panels on roof - February 2010

Page 16: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010

Plumbing, air conditioning February 2010 Kos installing ducting.