building for learning project photo progress report 5 december 2009 – february 2010
DESCRIPTION
Building for Learning Project Photo Progress Report 5 December 2009 – February 2010 Project commencement 21 st September 2009. Mid January – more minor demolition and framing. Fire services installed and stairway brickwork. Hooray - Admin completed!!!!!!. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/1.jpg)
Building for Learning ProjectPhoto Progress Report 5
December 2009 – February 2010
Project commencement 21st September 2009
![Page 2: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/2.jpg)
Mid January – more minor demolition and framing
![Page 3: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/3.jpg)
Fire services installed and stairway brickwork
![Page 4: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/4.jpg)
Hooray - Admin completed!!!!!!
![Page 5: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/5.jpg)
Former student work (maths and French) dating back to 1922 found in building cavities from demolition
![Page 6: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/6.jpg)
1st Storey wall frames going up
![Page 7: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/7.jpg)
Ground floor ceiling struts and power box installed
![Page 8: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/8.jpg)
1st Storey Wall Framing – well underway
![Page 9: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/9.jpg)
While the photos don’t show it – several days of +40c
![Page 10: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/10.jpg)
Final part of old roof replaced with addition of new 1st Storey roof – February 2010
Finally the last of the timber singles!!!
![Page 11: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/11.jpg)
With the final part of the roof replaced, the last big cleanup of all the 100+ years of accumulated dust, possum poo,
birds nests, etc from the classroom below
![Page 12: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/12.jpg)
More scaffolding as the stairway and lift get built.
![Page 13: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/13.jpg)
Sisalation being added, under black plastic is plaster boards ready for March construction.
![Page 14: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/14.jpg)
Roof, spouts, drainage and sisalation February 2010
![Page 15: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/15.jpg)
1st Floor data, electrical, phone installation Solar panels on roof - February 2010
![Page 16: Building for Learning Project Photo Progress Report 5 December 2009 – February 2010](https://reader035.vdocuments.site/reader035/viewer/2022062422/56813207550346895d985c1e/html5/thumbnails/16.jpg)
Plumbing, air conditioning February 2010 Kos installing ducting.