PROGRESS REPORT FEBRUARY 2012. Published March 20, 2012. The Banks Project. Master Development Plan. Executive Summary. Summary: Construction. February 2012: Close-out BP#9—Mehring Way guardrail installation complete. BP#11—Outstanding punch list items being addressed. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PROGRESS REPORT FEBRUARY  2012

PROGRESS REPORT FEBRUARY 2012

Published March 20, 2012

Page 2: PROGRESS REPORT FEBRUARY  2012

The Banks Project

Page 3: PROGRESS REPORT FEBRUARY  2012

Master Development Plan

3

Page 4: PROGRESS REPORT FEBRUARY  2012

Executive Summary

Page 5: PROGRESS REPORT FEBRUARY  2012

Summary: Construction

•February 2012: Close-out•BP#9—Mehring Way guardrail installation complete.•BP#11—Outstanding punch list items being addressed.

•All that’s left is the paperwork!

•Public Safety Technologies work ramping up•BP#12—Contract awarded to ESI; work already underway

Page 6: PROGRESS REPORT FEBRUARY  2012

Bid Package #12Street Grid/Pedestrian Improvements Design

•Pedestrian walkway and street improvements planned•Part 2 of BP#12 to be bid Fall 2012—sidewalk upstream side of Roebling Bridge, pedestrian bring over Pete Rose Way, construction of Ohio River Trail segment•Part 1 of BP#12 to be bid Spring 2013—widening of Second Street sidewalk, removal of Race Street Bridge, reconstruction of portion of Freedom Way, completion of Public Safety technology

Page 7: PROGRESS REPORT FEBRUARY  2012

Summary: Budget

• All public parties construction (Phases 1 and 2a) work have operated continuously within budget.

• Approx. $1M Phase 1 contingency can be moved to Phase 2a

• http://www.thebankspublicpartnership.com/sites/default/files/budget-detail-feb2012.pdf

Page 8: PROGRESS REPORT FEBRUARY  2012

Summary: DeveloperCarter-Dawson: • Phase 1a residential is 99% leased • Retail is 80% leased

Page 9: PROGRESS REPORT FEBRUARY  2012

Developer’s Leasing Activity

Holy Grail, Johnny Rockets, Toby Keith, and Police Welcome Center open and operating.

The Tin Roof and Crave are finalizing permits and preparing to start construction.

Mahogany’s lease is executed; project is in design phase.

Lease executed with The Wine Guy; design is underway.

Ruth’s Chris is designing their space; construction anticipated to begin second quarter 2012.

Page 10: PROGRESS REPORT FEBRUARY  2012

Economic Inclusion

Page 11: PROGRESS REPORT FEBRUARY  2012

Summary: Economic Inclusion

• The Project maintained the 36% SBE participation commitment (goal for Construction is 30%) as of 1/25/12.• SBE: 36%• MBE: 15.9%• WBE: 2.8%

• Professional Services (SBE goal is 10%)• SBE: 8.1%

Page 12: PROGRESS REPORT FEBRUARY  2012

Economic Inclusion

Bid Packages #5, #6, and #7 are closed out. Substantial work was completed this month by the DBE contractors on Bid Packages #9 & #11; final billings are projected to meet ODOT goals.

Click here for Economic Inclusion reports: http://www.thebankspublicpartnership.com/sites/default/files/economic-inclusion-feb2012.pdf

.

Bid Package No.

ODOT DBE Goal

Contractor Commitment

Actual DBE Participation

9 4% 4.9% 2.8%

11 8% 8.4% 7.6%f

Page 13: PROGRESS REPORT FEBRUARY  2012

• Combined Minority/Female Workforce participation is 17.44% as of 1/25/12.

• Minority Workforce (female and male) is 16.14%

• For the one-month period ending 1/25/12, a total of 89.3% of workers lived within the 15-County Cincinnati-Middletown MSA

• Local residency analysis 1,406 workers (through 12/25/11)• Tri-State

97.7%• Cincinnati-Middletown MSA 77%• Hamilton County 25.5%• City of Cincinnati 9.2%

There are no local residency participation goals.

Economic Inclusion

Page 14: PROGRESS REPORT FEBRUARY  2012

Summary: Safety

• The Project has logged over 416,000 hours worked without a lost-time accident for both Public Parties construction phases through Bid Package #11.

Page 15: PROGRESS REPORT FEBRUARY  2012

Cincinnati Parks

Page 16: PROGRESS REPORT FEBRUARY  2012

Cincinnati Parks

• Phase 1 Walnut Street Fountain and Grand Stairway to open in early Spring.• Bike Center design completed in

February; scheduled to open in early Spring.• Schmidlapp Event Lawn and Stage

canopy will be completed late March.• Work at Smale Riverfront Park Phase 3

continued.• Moerlein Lager House opened 2/27/12.

Page 17: PROGRESS REPORT FEBRUARY  2012

Cincinnati ParksWork South of Mehring Way

Page 18: PROGRESS REPORT FEBRUARY  2012

Cincinnati Parks

Page 19: PROGRESS REPORT FEBRUARY  2012

Communications

The Banks Project in the News

• Over 20 articles mentioning The Banks in February and two progress update presentations delivered.

http://www.thebankspublicpartnership.com/sites/default/files/media-summary.pdf

Page 20: PROGRESS REPORT FEBRUARY  2012

Progress: February 2012

For more information:John F. Deatrick

The Banks Project Executive(513) 946-4434