building and managing the right pmo_06feb2010v2

Upload: mohd-aqel-abo-karam

Post on 06-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    1/199

    PROJECT MANAGEMENT INSTITUTE - AGC

    06 10 February 2010

    Crowne Plaza Hotel

    Jeddah, Saudi Arabia

    Building & Managing the Right

    PMO

    By

    Ibrahim Mahmoud Ibrahim, PMP, MBA

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    2/199

    2 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Introduction

    The Instructor

    The Participants

    Name

    Job Information

    Seminar Expectations

    Starting Time, Breaks, and Adjourn

    Class Rules

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    3/199

    3 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Course Objectives

    Learn the key concepts related to Project Management Offices asper the PMI standards

    Understand the different PMO Models

    Determine the right PMO model based on your organizationalneeds

    Understand where the PMO fits in the organizational context

    Design the right PMO Organization

    Learn how to define the PMO value proposition & PMO services

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    4/199

    4 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Course Objectives

    Understand the concepts of portfolio management and programmanagement as per the PMI standards

    Discuss and learn in a workshop environment how to build theright PMO (Case Study)

    Understand the Organizational Project Management MaturityModel

    Learn the secrets for maintaining a successful PMO

    Get an overview of the current PMO tools in the market

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    5/199

    5 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Course Contents at a Glance

    Understanding Key PMO Concepts1

    The PMO Environment2

    Implementing the Right PMO3

    Conclusion

    4 Understanding Program Management

    Conclusion

    5 Understanding Portfolio Management

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    6/199

    6 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Course Contents at a Glance

    Conclusion

    6 Introduction to OPM3

    PMO Software Tools

    7

    Sustaining a Successful PMO8

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    7/199

    7 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Chapter 1

    UNDERSTANDING KEY PMOCONCEPTS

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    8/199

    8 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    What is a PMO?

    Pfor Project or Program

    M for Management

    O for Office

    Other interpretations

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    9/199

    9 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    What is a Project?

    PMI PMBOK defines a project as a temporary endeavorundertaken to create a unique product, service, or result

    Temporary means have definite time frame

    Unique means the deliverables are somehow unique

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    10/199

    10 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Characteristics of Projects

    What are the general characteristics of a project?

    Projects are non-routine (one-time)

    Have specific products (physical or intangible)

    Normally used as instrument of change

    Have limited time frame

    Involves a sequence of activities demanding different resources andskills

    Resources are grouped to achieve a particular aim

    Requires professional commitment (some one/agency is fullyresponsible for the project single point of responsibility)

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    11/199

    11 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    What is Project Management?

    Project management is the application of knowledge, skills,tools, and techniques to project activities to meet projectrequirements

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    12/199

    12 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Project Management Process Groups

    Initiating Planning

    Monitoring&

    Controlling

    Executing

    Closing

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    13/199

    13 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Project ManagementKnowledge Areas

    TimeManagement

    HRManagement

    ScopeManagement

    Communication

    Management

    RiskManagement

    IntegrationManagement

    CostManagement

    QualityManagement

    ProcurementManagement

    AS per the PMI PMBOK(2004)

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    14/199

    14 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    SEQ SCOPE MANAGEMENT

    PROCESSES

    PM PROCESS GROUP

    1 Collect Requirements Planning

    2 Define Scope Planning

    3 Create WBS Planning

    4 Verify Scope Monitoring & Controlling

    5 Control Scope Monitoring & Controlling

    PROJECT SCOPE MANAGEMENT

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    15/199

    15 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    SEQ TIME MANAGEMENT PROCESSES PM PROCESS GROUP

    1 Define Activities Planning

    2 Sequence Activities Planning

    3 Estimate Activity Resources Planning

    4 Estimate Activity Duration Planning

    5 Develop Schedule Planning

    6 Control Schedule Monitoring & Controlling

    PROJECT TIME MANAGEMENT

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    16/199

    16 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PROJECT COST MANAGEMENT

    SEQ COST MANAGEMENT PROCESSES PM PROCESS GROUP

    1 Estimate Cost Planning

    2 Determine Budget Planning

    3 Control Cost Monitoring & Controlling

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    17/199

    17 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PROJECT QUALITY MANAGEMENT

    SEQ QUALITY MANAGEMENT

    PROCESSES

    PM PROCESS GROUP

    1 Plan Quality Planning

    2 Perform Quality Assurance Executing

    3 Perform Quality Control Monitoring & Controlling

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    18/199

    18 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PROJECT HR MANAGEMENT

    SEQ HR MANAGEMENT PROCESSES PM PROCESS GROUP

    1 Develop Human Resource Plan Planning

    2 Acquire Project Team Executing

    3 Develop Project Team Executing

    4 Manage Project Team Executing

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    19/199

    19 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PROJECT COMMUNICATION MANAGEMENT

    SEQ COMMUNICATION MANAGEMENT

    PROCESSES

    PM PROCESS GROUP

    1 Identify Stakeholders Initiating

    2 Plan Communications Planning

    3 Distribute Information Executing

    4 Manage Stakeholders Executing

    5 Report Performance Monitoring & Controlling

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    20/199

    20 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PROJECT RISK MANAGEMENT

    SEQ RISK MANAGEMENT PROCESSES PM PROCESS GROUP

    1 Plan Risk Management Planning

    2 Identify Risks Planning

    3 Perform Qualitative Risk Analysis Planning

    4 Perform Quantitative Risk Analysis Planning

    5 Plan Risk Responses Planning

    6 Monitor & Control Risks Monitoring & Controlling

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    21/199

    21 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PROJECT PROCUREMENT MANAGEMENT

    SEQ PROCUREMENT MANAGEMENT

    PROCESSES

    PM PROCESS GROUP

    1 Plan Procurements Planning

    2 Conduct Procurements Executing

    3 Administer Procurements Monitoring & Controlling

    4 Close Procurements Closing

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    22/199

    22 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    SEQ INTEGRATION MANAGEMENT

    PROCESSES

    PM PROCESS GROUP

    1 Develop Project Charter Initiating

    2 Develop Project Management Plan Planning

    3 Direct and Manage Project Execution Executing

    4 Monitor & Control Project Work Monitoring & Controlling

    5 Perform Integrated Change Control Monitoring & Controlling

    6 Close Project or Phase Closing

    PROJECT INTEGRATION MANAGEMENT

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    23/199

    23 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Defining Project Management Office

    Project Management Office (PMO) is an organizational body orentity assigned various responsibilities related to the centralized andcoordinated management of those projects under its domain

    The responsibilities of a PMO can range from providing projectmanagement support functions to actually being responsible for thedirect management of a project

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    24/199

    24 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    What is a Program?

    A programs is a group ofrelated projects managed in acoordinated way to obtainbenefits and control notavailable from managing them

    individually. Programs mayinclude elements of related

    work outside the scope of thediscrete projects in theprogram.

    Examples of other Work?

    Program

    Programs Projects Other Work

    Project Projects

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    25/199

    25 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    What is Program Management?

    Program Management is the centralized coordinatedmanagement of a program to achieve the programs strategic

    objectives and benefits

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    26/199

    26 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    What is Program Management Office?

    Program Management Office (PMO) is the centralizedmanagement of a particular program or programs such thatcorporate benefit is realized by the sharing of resources,methodologies, tools & techniques, and related high-level project

    management focus.

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    27/199

    27 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Dont Judge a Book by its Title

    Other names given to the PMO entity includes: Project Support Office

    Project Office

    Enterprise Project Office

    Project Management Center of Excellence

    Strategic Project Office

    Project Management Competency Center

    Studies show that existing PMOs vary significantly in theirstructure, roles assumed, and the perceived value

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    28/199

    28 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    When Do We Need a PMO?

    Large number of projects performed but few are completed

    Projects are not aligned with business strategy

    We celebrate project completion and reward project teammembers even if the project did not deliver the full scope,exceeded the budget, exceeded the deadlines, and compromisedthe quality

    Same problems recur in most projects

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    29/199

    29 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    When Do We Need a PMO?

    Difficulty in tracking project progress

    Poor project documentation

    Lack of unified project management methodology

    Fire fighting mode and management by crisis approach (i.e.urgent issues takes priority over important issues)

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    30/199

    30 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Is PMO a Panacea?

    According to a Forrester report (2003), PMOs are on the rise buttheir effectiveness is dubious

    Studies show that departmental PMOs has little acceptanceoutside their span of influence

    A PWC survey (2004) conducted on 10640 projects valued at $7.2 billion across a range of industries showed that only 2.5% ofglobal businesses achieved 100% project success and over 50% of

    the projects fail

    The relevance or even the existence of the PMO has beenseriously questioned in recent years in 42% of organizationssurveyed by PMI in 2006

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    31/199

    31 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Models

    Models allow us to envision, in advance, what the final outcomewill be. It also allow us to exchange ideas, conversations, anddebate if the model is suitable for usage or not

    The PMO literature is full of high level PMO classifications orcategorizations called PMO models

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    32/199

    32 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Models

    Full Control PMO

    PM reports to PMO

    Full responsibility of

    deliverables Assign resources

    Enforce discipline

    Advisory PMO

    Awareness

    Training

    NewslettersGuidelines

    Full Control

    versusAdvisory Board

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    33/199

    33 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Models

    The easy to visualize model Control Tower

    Establish standards

    Educate Standards

    Enforce Standards

    Improve Standards

    Weather StationReport progress status to the executives (budget, risk, issues,progress)

    Track events without influencing them

    Resource PoolSupply of project managers

    Experts are hired in the pool

    Internal clients normally pay for the service

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    34/199

    34 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Models

    The How Good Can We Be ModelBased on number of project management processes applied and level of

    sophistication

    Basic PMO

    Advanced PMO

    Center of Excellence PMO

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    35/199

    35 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Models

    The Where to Focus Model Strategic

    Tactical

    How We Do Things Model Supportive: Train, Coach, and Rescue

    Controlling: Monitor, Audit, and Report

    Directive: Share some responsibility (plan, manage, and provideresources)

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    36/199

    36 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Models

    The Organizational Chart Model Enterprise Level PMO

    Departmental PMO

    Project Control Office

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    37/199

    37 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Gartner PMO Models

    The Repository Model Serves as a repository for information on project management

    methodology and standards

    Some staff are assigned formal, part-time roles for maintaining therepository

    Suitable for organizations with weak central governance orempower distributed, business-centric project ownership

    Does not provide project oversight within organization

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    38/199

    38 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Gartner PMO Models

    The Coach Approach Builds on the repository approach

    Best practices are documented and shared by the PMO

    Project performance is actively monitored. Poor performing projectmanagers are trained and coached

    The office is permanently staffed.

    The office has some supervisory & reporting responsibility for mostof the projects

    The office act as a trainer, consultant, and information provider onproject processes

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    39/199

    39 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Gartner PMO Models

    The Enterprise Approach (Manager Model) Builds on the repository and coach models

    Concentrates project management capabilities and responsibilitieswithin the PMO. Project managers are staffed within the sharedservices and assigned to projects as needed

    May provide direct management of selected projects (act as acontracted project manager)

    Sometimes called PM Center of Excellence

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    40/199

    40 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Gartner PMO Models

    What are the perceived advantages & disadvantages of each ofthe three Gartner PMO models?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    41/199

    41 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Competency Continuum

    Stage 1Project Office

    Achieve projectdeliverables andobjectives for cost,schedule &

    resources. 1 or moreprojects 1 ProjectManager

    Stage 2Basic PMO

    Provide standardand repeatable PMmethodology Multiple Projects Multiple ProjectManagers Program Manager Part time PMOSupport Staff

    Stage 3Standard PMO

    Establish capabilityand infrastructureto support andgovern a cohesiveprojectenvironment Multiple Projects Multiple PMs Program Mngrs Full time& parttime PMO SupportStaff

    Stage 4Advanced PMO

    Apply integrated &

    comprehensiveproject managementcapabilities toachieve businessobjectives PMO Director Dedicated PMOtechnical & supportstaff

    Stage 5Center of

    Excellence

    Manage continuousimprovement andcross departmentalcollaboration toachieve strategicbusiness goals Multiple programs VP or Director ofProject Management Enterprise widesupport staff

    Project Oversight

    Process Control

    Process Support

    Business Maturity

    Strategic Alignment

    Source: Hill (2008)

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    42/199

    42 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Models

    Which is the best model for your organization?

    What are the factors that help in deciding the right PMO model?

    What if my organizational needs are not covered by the generalPMO models?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    43/199

    43 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Which Model is the Best?

    Model Selection tips Who is the main customer of the PMO?

    What is the maturity level of the project management community?

    What is the level of cooperation and teamwork at the executiveslevel?

    Where is the greatest pain?

    Will the PMO be funded and sourced sufficiently by the executivesto address opportunities and threats?

    What is the level of support for a strong PMO role?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    44/199

    44 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Chapter 2

    THE PMO ENVIRONMENT

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    45/199

    45 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The PMO Stakeholders

    A stakeholder is any one whose interests may be positively ornegatively impacted by the PMO establishment project (i.e. hassomething to gain or lose by implementing the PMO)

    Key stakeholders include CEO, CIO, CFO and other corporateexecutives, project managers, customers, PMO project sponsor,PMO team members, project team members, vendors, owners,fund providers, and sellers

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    46/199

    46 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The PMO Stakeholder Expectations

    Stakeholder Expectations

    Executives

    Accurate, relevant & timely reports and views on projects andportfolios to support the decision making process and to facilitatethe selection of the right investments (projects) that give sustainedcompetitive advantage or improve the market share

    ProjectManagers

    More advanced and stable processes for planning and managingprojects.

    Team MembersImproved methods to track their project participation and lower

    conflict between projects & their operational duties.

    BusinessManagers

    Enhanced project delivery, improved quality, lower project budgets,and gain competitive advantage

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    47/199

    47 Building & Managing the Right PMO

    IBRAHIM MAHMOUD IBRAHIM

    PMO & the Organizational Context

    CEO

    CIO COOVP

    Marketing

    GM ITSolutions

    GMProduction

    MarketingPMO

    Operation Mgr Logistics Mgr

    EPMO

    Product APMO

    Product BPMO

    GM ITOperations

    IT PMO

    ERP PMOMission CriticalProject Level

    Golden Rule: The PMO should be located nearthe main customer of the PMO

    Corporate Level

    Business Unit orRegional Office

    Level

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    48/199

    48 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO & the Organizational Context

    The closer the PMO to the top, the higher its level of autonomy,authority, and responsibility

    Lower resistance

    Strategic nature

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    49/199

    49 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Exercise 1

    Who are the major stakeholders in your organization?

    Where should the PMO be placed in your organization? Why?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    50/199

    50 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Important Environmental Factors

    Sponsorship

    CultureOrganization Structure

    Personalities

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    51/199

    51 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Factors to Consider: Sponsorship

    Dont start a PMO initiative without executive sponsorship

    Does management provide tangible support or just some lip-services? (talk the talk but do not walk the walk)

    The higher the level of the sponsor, the less work required toovercome obstacles

    Again: Dont start a PMO without a strong executive

    sponsorship

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    52/199

    52 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Factors to Consider: Culture

    What is the organizational culture? How success is defined in theorganization?

    Does it reward team work or the super heroes?

    Does it promote cooperation? Or does it encouragecompetition?

    Does it support process-oriented initiatives?

    dont tell me how to do my job environment requires extracommunication effort from the PMO

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    53/199

    53 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Factors to Consider: Culture

    The culture the PMO should promote is one of Cooperation

    Teamwork

    Shared success

    Process orientation

    Doing it right the first time, rather than doing it over

    A research by BIA conducted on 750 PMO organizations showed

    that 60% of the PMOs are not supported by their corporateculture

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    54/199

    54 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Factors to Consider: Organization

    What is the organizational structure? Weak Matrix or Functional

    Strong Matrix

    Projectized

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    55/199

    55 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PROJECTIZED

    FUNCTIONAL

    STRONG

    MATRIX

    BALANCED

    MATRIX

    WEAK

    MATRIX

    PROJECTMAN

    AGER

    FUNCT

    IONAL

    MANAGER

    AUTHORITY

    AUTHORITYORGANIZATION STRUCTURE TYPE

    Factors to Consider: Organization

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    56/199

    56 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Factors to Consider: Organization

    PMO placement

    PMO leadership

    Project management maturity of the organization

    Where do all the project managers go?

    Ability to move towards a strong matrix or projectized

    organization

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    57/199

    57 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Factors to Consider: Personalities

    What are some of the dominant personalities of both thepeople leading the effort of creating the PMO and of the keystakeholders?

    Start with your self

    Diversity is not only dealing with people of different cultures,ethnic backgrounds, religions, but also with people withdifferent styles, skills and strengths

    If you want to get out of the box thinking, you might need tohave people who are not in the box

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    58/199

    58 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The Purpose of the PMO

    Speed up project deliverytime without impactingquality (doing projects right)

    Facilitate choosing the right

    project mix (doing the rightprojects)

    Track & report progress tothe executives

    Provide project managementmethodology

    Provide technical support forproject management tools

    Focus efforts on correctiveactions

    Provide or manage projectmanagement training

    Manage project portfolios

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    59/199

    59 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The Purpose of the PMO

    Mentor project managers

    Help projects in trouble

    Keep project archives in one place (i.e. maintains lessons learned)

    Help desk services

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    60/199

    60 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The Purpose of the PMO

    Asurvey on PMO implementation varieties - Hobbs (2006) -published at PMI website revealed the following:

    PMO Function % of PMOs where

    important

    Report status to upper management 83%

    Develop & implement standard methodology 76%

    Monitor & control project performance 65%

    Develop competency of personnel including training 65%

    Implement & operate Project Information System 60%

    Provide advice to upper management 60%Coordinate between projects 59%

    Develop & maintain project scorecard 58%

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    61/199

    61 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The Purpose of the PMO

    PMO Function % of PMOs whereimportant

    Promote PM within organization 55%

    Monitor & control performance of PMO 50%

    Participate in strategic planning 49%

    Provide mentoring for project managers 49%

    Manage one or more portfolios 49%

    Identify, select & prioritize new projects 48%

    Manage archives of project documentations 48%

    Manage one or more programs 48%

    Conduct project audits 45%

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    62/199

    62 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Exercise 2

    What are the main purposes of the PMO in your organization &why?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    63/199

    63 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The PMO Environment

    ProjectPortfolio

    Processes /Methodologies

    ResourcePortfolio

    AssetPortfolio

    Scorecards /Dashboards

    Knowledge /Change Mgmt

    VendorManagement

    ProjectDelivery

    Support FunctionsHR Legal

    Purchase Training

    Admin Program / ProjectManagers

    SolutionVendors

    GovernanceBoard

    SeniorManagement

    Data

    Feedback/Direction

    InformationInformation Direction(Strategy)

    Direction(Governance)

    MentoringData

    FeedbackRequest

    Support

    PMO

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    64/199

    64 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The PMO Environment

    What information the PMO delivers to the Governance Board?

    What type of support Legal, Purchasing, and HR provide toPMO?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    65/199

    65 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Chapter 3

    IMPLEMENTING THE RIGHT

    PMO

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    66/199

    66 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    High Level Implementation Roadmap

    Business Case

    Project Selection

    Project Charter

    Assess Current Situation

    PMO Value Proposition

    PMO Services

    PMO Team Setup

    PMO Tool ImplementationBuild the PMO (phase 1)

    PMO Organization

    Operate to achieve the

    required maturity level

    Specify Priorities

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    67/199

    67 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Maturity Takes Time

    Manage

    Enhance

    TransitionManage

    Manage

    PMO: Stage 4

    PMO: Stage 3

    PMO: Stage 2

    PMO: Stage 1

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    68/199

    68 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Example: Phased Implementation

    High Level Implementation Plan

    PMProcesses

    ToolSupport

    SkillsDevelopment

    PortfolioManagement

    Stage

    1

    Stage2

    - Define standardmethodology tomanage scope,

    time, HR,communications,and risk

    - Install MS EPM

    - Automate forms,

    templates, andsome processes

    - Define standardmethodology tomanage

    procurement,quality, cost, andintegration

    - Conduct ProjectmanagementConcepts

    Training

    - Conduct PMOawarenesssessions

    - Conduct ProjectmanagementConceptsTraining

    - Conduct PMOawarenesssessions

    - Conducts MSEPM Training

    - MS EPMCoaching

    - MS EPM first levelSupport

    - Establish electronicproject repository

    - Design initial

    dashboard & web-based reporting

    - Design repositoryupdate mechanism

    - Maintain projectrepository

    - Finalize dashboard& web-basedreporting

    - Design resourceportfolio analysis &reporting

    GovernanceSetup&Proj

    ect

    Manag

    ementMaturityPla

    ns

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    69/199

    69 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Phased PMO Implementation

    Q: Which approach is better: implement the PMO tool beforeoperating the first phase of the PMO or at a later stage when thePMO role is accepted by all parties and automation requirementsare more precise?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    70/199

    70 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The PMO Project Charter

    The charter should include the following elements: PMO objectives

    High level business justification

    High Level Business Requirements

    High level deliverables

    Major Stakeholders

    Assumptions & Constraints

    Summary Milestones

    Summary Budget

    Name of the Assigned Project Manager

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    71/199

    71 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Assess the Current Situation

    Where are the major pain areas?

    Assess the project environment

    Organization & People Assessment

    Process Assessment Delivery Assessment

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    72/199

    72 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Organizational assessment

    Organization type (projectized, strong matrix, weak matrix,functional)

    What resources are working in what projects?

    Which business unit has more projects, which region, & whichtime of the year?

    What resources can work as PMO champions?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    73/199

    73 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Process Assessment

    Identify the organizational processes that are in place for projectselection, initiation, planning, monitoring & controlling, andcloseout

    Identify gaps in project management knowledge areas

    Plan to achieve targeted project management maturity usingphased approach

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    74/199

    74

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Process Assessment

    Statement 1 2 3 4 5

    1 A Project Scope Statement is created for every project.

    2 Project Scope Statements are prepared with customer

    input throughout the development process.

    3 Management and the customer reviews all projectprogression alternatives and recommendations.

    4 Potential changes to the SOWs are processed accordingto a documented Change Control Procedure.

    5 Approved changes to the Scope Statement arecommunicated to the project team and the customer.

    6 The Statement of Work (SOW) contains all deliverablesand is reflected in the Project Plan.

    Example: Assessing Scope Management Processes

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    75/199

    75

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Process Assessment

    Statement 1 2 3 4 5

    1 The projects WBS and resource estimate areused to develop the projects baseline schedule.

    2 The project schedule identifies scheduleconstraints driven by the customer, technology,

    suppliers, or management.3 Project schedules are updated on a regular basis

    with progress status updates, which are measuredagainst the baseline plan.

    4 All project schedule work elements havedependencies, effort, and resources assigned.

    5 A critical path analysis is performed on theproject schedule during each progress updatecycle.

    6 Schedules are optimized to conform to contractrequirements.

    Example: Assessing Time Management Processes

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    76/199

    76

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Delivery Assessment

    CostAre we delivering on budget?

    TimeAre we delivering on time?

    Customer SatisfactionHow satisfied are our customers? Are wemeasuring their satisfaction level regularly? How?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    77/199

    77

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Getting Executive Approval

    Face to Face presentation Distribute the slides a head of time to allow for constructivediscussions

    Set the right expectations The PMO Setup will follow a phased implementation approach

    All deliverables & business objectives will not be delivered in phase- 1

    Explain current project management challenges

    Present the PMO opportunities

    What resources required to do the job & when do you need them (high level)

    Initial Budget

    High level milestones and project duration

    Present the PMO value proposition

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    78/199

    78

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The PMO Value Proposition

    Clearly specify the expected benefits by establishing the PMO Life before and after the PMO

    What problems and pain areas will be addressed by the PMO

    How the PMO will expedite the delivery process

    Be realistic, show how the PMO will function to meet its obligation Specify the timeframe required for building the PMO

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    79/199

    79

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Services: Defining the Right Mix

    Provide Standardization Develop a unified project management methodology based on PMI

    PMBOK

    Process Standardization (templates, policies, procedures)

    Document best business practices

    Benchmarking

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    80/199

    80

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Services: Defining the Right Mix

    Report Status to Management Provide insight / analysis on resource utilization , availability, and

    performance in all projects

    Project Scorecards at periodic executive meetings

    Detailed performance analysis at major milestones

    Monthly Resource Utilization Analysis Report

    Project Health Check

    O S i fi i h i h i

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    81/199

    81

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Services: Defining the Right Mix

    Participate in Resource Management Monitor resource performance

    Ensure proper staffing in all projects

    Re-assignment

    External Scanning / Sourcing

    Outsourcing versus In-sourcing criteria

    Project selection and project funding

    PMO S i D fi i th Ri ht Mi

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    82/199

    82

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Services: Defining the Right Mix

    Participate in Cost Management Vendor Management

    Purchasing

    Monitor and report on project cost performance

    PMO S i D fi i th Ri ht Mi

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    83/199

    83

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Services: Defining the Right Mix

    Project Portfolio Management Participate in project selection process to ensure alignment with

    business strategy

    Provide key stakeholders with timely assessment of portfolio andcomponents performance

    Participate in program and project reviews

    Measure the value of the portfolio through ROI, NPV, or any otherquantitative or qualitative technique

    PMO S i D fi i th Ri ht Mi

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    84/199

    84

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Services: Defining the Right Mix

    Training & Mentoring - Leverage the skills of the staff in projectmanagement through

    Training

    Coaching

    Certification Project Reviews

    PMO S i D fi i th Ri ht Mi

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    85/199

    85

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PMO Services: Defining the Right Mix

    PMO Tools Support Ensures the integrity of all data captured through the PMO tool

    Ensures that all staff involved in project management are capable ofutilizing the PMO tool to the maximum through coaching and formaltraining

    Trouble-shooting (first level support) Dashboard & Reporting Support

    Maintain corporate-wide project repository (project documentation)

    Tool Administrator

    Th PMO T

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    86/199

    86

    Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The PMO Team

    PMO Director

    Project Portfolio Administrator

    Project Management MethodologyConsultant

    Project planners/Schedulers

    Project Administrators/Coordinators

    Technical PMO Tool Support

    Resource Analyst

    Th PMO T

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    87/199

    87 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The PMO Team

    Project Management Training

    Officer

    Contract Management Administrator

    Legal Advisor

    Financial Analyst

    Librarian / Documentation Specialist

    S lli th PMO V l P iti

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    88/199

    88 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Selling the PMO Value Proposition

    Awareness & Marketing Sessions (why should everybody supportthe PMO?)

    Which group should be addressed first & Why?

    Executives

    Project ManagersTeam Members

    Business Managers

    Be a spokesman

    Selling the PMO Val e Proposition

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    89/199

    89 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Selling the PMO Value Proposition

    Be passionate about the potential

    Engage upper level management

    Show examples of successful PMO implementations

    Exercise 3

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    90/199

    90 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Exercise 3

    Read the case study then work on groups to identify thefollowing:

    The most suitable PMO model

    The PMO value proposition

    PMO position in the organization structure The PMO organization structure (roles & responsibilities)

    The PMO Services to be delivered

    Implementation Phases (PMO stages) and what to be delivered ineach phase

    Do we need more than one PMO? Where?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    91/199

    91 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Chapter 4

    Program Management

    Role of the Program Manager

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    92/199

    92 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Role of the Program Manager

    Responsible for the coordinated planning, management, and execution of aprogram which is defined as multiple, related projects directed towards strategicbusiness benefits & objectives

    Ensure program management processes enable the component teams tosuccessfully complete their work

    Ensure proper integration of project deliverables into programs end product.

    Ensure projects are organized and executed in a consistent manner fulfilling

    established standards

    Important Program Management Themes

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    93/199

    93 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Important Program Management Themes

    Benefits Management

    Program Stakeholder Management

    Program Governance

    Benefits Management

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    94/199

    94 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Benefits Management

    The definition and formalization of the expected benefits aprogram is intended to deliver

    The benefits are normally identified & formalized at portfolio level beforebeing delegated to the program for realization

    Some programs deliver incremental benefits to the organization. Others

    deliver all of the benefits at the very end of the program. Examples?

    Benefits Management includes

    Definition of each benefit and how to realize it

    Mapping of benefits to program outcomes

    Metrics and procedures to measure benefits

    Roles, responsibilities, and Communication plan for benefit management

    How to sustain the benefit at the end of the program (on-going operation)

    Program Stakeholders Management

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    95/199

    95 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Program Stakeholders Management

    Defines the individuals and organizations whose interests may beaffected by the program outcome

    Stakeholders can either help or hinder the program depending onthe opportunity or threat they see

    Proper communication skills are required to manage stakeholders

    Stakeholders include Program Director, Program Managers,Program Sponsor, PMO, Program Team Members, ProgramGovernance Board, Suppliers, and Consumers

    Program Governance

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    96/199

    96 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Program Governance

    The process of developing, communicating, implementing,monitoring, and assuring the policies, procedures, organizationalstructures, and practices associated with a specific program

    Program governance should fit within the wider picture

    (corporate governance)

    A governance board (or Steering Committee) is the forum whereissues related to the program are discussed.

    The Governance Board controls the investment and monitor thedelivery of benefits as the program progresses

    Program Governance

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    97/199

    97 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Program Governance

    Functions of the Governance Board include: Initiating the program

    Approvals of program plans and authorizes deviation from the plans(when needed)

    Review programs progress, benefits delivery, and cost

    Problem solving in issues the Program Manager cannot solve.

    Ensure compliance with corporate and legal policies, procedures,and requirements

    Program Lifecycle

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    98/199

    98 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Program Lifecycle

    1.Pre-

    ProgramPreparation

    2.ProgramInitiation

    3.Program

    Setup

    4.Delivery ofProgramBenefits

    GR1 GR2 GR3

    GR45.

    ProgramClosure

    GR: Gate Review

    Program Lifecycle & Benefits Management

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    99/199

    99 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Program Lifecycle & Benefits Management

    Pre-Program

    Preparation

    ProgramInitiation

    ProgramSetup

    Delivery ofProgramBenefits

    ProgramClosure

    BenefitIdentification

    BenefitsAnalysis &Planning

    BenefitRealization

    BenefitsTransition

    Identify &qualify business

    benefits

    Derive & prioritizecomponents

    Define benefit metrics Define benefitrealization plan &monitoring Map benefits toprogram plan

    Monitorcomponents

    Maintainbenefits register Report benefits

    Consolidatebenefits

    Transfer theongoingresponsibilities

    Program Governance

    Phase 1: Pre-Program Preparations

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    100/199

    100 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Phase 1: Pre-Program Preparations

    The main objective of this phase is to establish a firm foundationof support and approval for the program

    Activities include:

    Understanding the strategic value of the proposed business change

    Study expectations of the key decision makers and stakeholders

    Define program objectives and their alignment with business strategicobjectives

    Conduct feasibility / justification study (also answer the question: whyprogram approach is better than individual projects)

    Passing the selection process by the portfolio review board

    Developing Program initial Plan including check points to ensure theprogram is on track

    Phase 2: Program Initiation

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    101/199

    101 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Phase 2: Program Initiation

    Defines detailed program roadmap on how the program is to bestructured & managed and defines program key deliverablesi.e.the focus is on program-level planning processes

    The main outcome is an approval authorizing execution of the

    program charter

    Justification Vision Strategic Fit Outcomes Scope Benefit Strategy Assumptions & Constraints

    Components Risks & Issues Timeframe Resources Stakeholders Program Governance High-level Roadmap

    Phase 3: Program Setup

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    102/199

    102 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Phase 3: Program Setup

    The purpose of this phase is to progressively elaborate theprogram charter and establish an infrastructure that will supportthe program and its constituent projects

    The desired outcome is approval authorizing execution of the

    program plan

    The program management plan should answer the following:

    What are the deliverables and when they will be ready

    How much will it cost? What are the risks and issues?

    What are the dependencies, assumptions, and constraintsincluded?

    How will the program be managed? What are the other servicesrequired?

    Phase 4: Delivery of Program Benefits

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    103/199

    103 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Phase 4: Delivery of Program Benefits

    The purpose of this phase is to initiate the component projects ofthe program and manage the development of program benefits

    This phase is iterative in natureends only when all plannedbenefits of the program have been achieved

    Activities at this phase include:

    Ensure program governance is in action

    Initiate projects

    Ensure project deliverables meet the program requirement

    Measure benefits realization Analyze progress to the plan

    Phase 4: Delivery of Program Benefits

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    104/199

    104 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Phase 4: Delivery of Program Benefits

    Activities at this phase include (Cont.): Communicate with stakeholders

    Manage dependencies and shared resources

    Manage program level risks and issues

    Ensure adherence to methodologies, polices, and procedures

    Manage transition from current as-is state to required to-be state

    Review change requests and approve as appropriate

    Phase 5: Program Closure

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    105/199

    105 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Phase 5: Program Closure

    Ensure proper closing of program organization and infrastructurewhen all work is completed and benefits are realized.

    Activities include:

    Document lessons learned

    Archive program repository

    Manage transition to operations

    Disband the program organization

    Provide feedback and recommendations on changes identifiedduring the program lifecycle

    Program Management Knowledge Areas

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    106/199

    106 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Program Management Knowledge Areas

    Program IntegrationManagement

    Program Scope Management

    Program Time Management

    Program Cost Management

    Program Quality Management

    Program Human ResourceManagement

    Program CommunicationManagement

    Program Risk Management

    Program Procurement

    Management

    Program Financial Management

    Program Stakeholder

    Management

    Program Governance

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    107/199

    Initiating Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    108/199

    108 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Initiating Process Group

    Initiate Program

    Establish Program FinancialFramework

    Planning ProcessGroup

    Planning Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    109/199

    109 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    g p

    Initiate Program

    Define Goals & Objectives

    Develop Management Plan

    Plan for Audits

    Plan Program Quality

    Plan Risk Management

    Identify Program Risks

    Analyze Risks

    Plan Risk Responses

    Plan Program ProcurementDevelop Program Schedule

    Estimate Program Costs Budget Program Costs

    Plan & Establish GovernanceStructure Identify Program Stakeholders

    Develop Program Infrastructure

    Develop Program Requirements

    Develop Program Architecture

    Develop Program WBS

    Develop Program Financial Plan

    Plan Stakeholders Management

    Plan Communications

    Initiating Process Group

    Executing Process Group

    Closing Process Group

    Monitoring & ControllingProcess Group

    Executing Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    110/199

    110 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Executing Process Group

    Direct & Manage ProgramExecution

    Planning Process Group

    Manage ProgramResources

    Manage ProgramArchitecture

    Manage ComponentInterfaces

    Engage ProgramStakeholders

    Distributeinformation

    Conduct ProgramProcurements

    ApproveComponent

    Initiation

    Monitoring & ControllingProcess Group

    Monitoring & Controlling Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    111/199

    111 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    o o g & Co o g ocess G oup

    Initiating ProcessGroup

    Monitor & ControlProgram Performance

    Monitor & ControlProgram Scope

    Monitor & ControlProgram Schedule

    Closing Process Group

    Monitor & ControlProgram Financials

    Manage StakeholderExpectations

    Monitor & ControlProgram Risks

    Administer ProgramProcurement

    Report ProgramPerformance

    Monitor & ControlProgram Changes

    Manage Program Issues

    Provide GovernanceOversight

    Manage ProgramBenefits

    Planning ProcessGroup

    Executing ProcessGroup

    Closing Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    112/199

    112 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    g p

    Close Program

    Planning Process Group

    Executing Process Group

    Approve ComponentTransition

    Close ProgramProcurements

    Monitoring & ControllingProcess Group

    Skills of the Effective Program Manager

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    113/199

    113 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    g g

    High communication and relationship-building skills

    Excellent risk and conflict management

    Has strategic vision and broad organizational management skills

    Political

    People

    Leadership

    Has excellent project management skills

    Ability to conduct effective questioning

    Project Management & Program Management

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    114/199

    114 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    j g g g

    What are the similarities and differences between programmanagement and project management?

    Program Management Project Management

    Business & Technical in nature Technical in nature

    Aligned to strategic objectives of thebusiness Aligned to program objectives

    Focuses on interdependencies amongprojects and feasibility of delivery

    Focus on milestone, deliverables of asingle project

    Handle program level risks Focus on project level risks

    Broad range of business, leadership,and management skills required

    In-depth project management skillsrequired

    Focus on consistent usage of commonprocesses among projects

    Focus on effective usage of processesin a single project

    Role of the PMO in Program Management

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    115/199

    115 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    g g

    The role of the PMO in program management variesdepending on several factors. What are these factors?

    A standard PMO supports the Program Manager by

    Providing the Program Manager with accurate and timelyinformation to make the right decisions

    Providing administrative support in managing schedules, budgets,risks, issues, procurement and human resource

    Exercise 4

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    116/199

    116 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Q: What type of services a Program Management Office (PMO)can provide to the Program Manager?

    Define the program management processes that will be followed

    Manage schedule and budget at the program level

    Define the quality standards for the program and its components Provide document configuration management

    Provide centralized support for managing changes and tracking risks andissues

    Provide central repository for all program deliverables

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    117/199

    117 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Chapter 5

    Project Portfolio Management

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    118/199

    118 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Q: Have you ever cancelled a project that is on-timeand on-budget? Why?

    Defining Project Portfolio

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    119/199

    119 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    g j

    A collection of projects and/or programs and other work that aregrouped together to facilitate the effective management of thatwork to meet strategic business objectives.

    The projects and programs within a portfolio may not be

    interdependent or directly related

    Defining Project Portfolio

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    120/199

    120 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    A portfolio represents a view the organizations set of activeprograms, projects, sub-portfolios, and other work at a specificpoint of time

    A portfolio represents the work selected to be done, but not

    necessarily the work that should be done

    Common features of portfolio components include:

    They represent investments made or planned by the organization

    They are aligned with the strategic goals of the organization

    They can be measured, ranked, and prioritized

    Are portfolios temporary like projects and programs?

    Defining Project Portfolio

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    121/199

    121 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Portfolio

    Portfolio Projects Programs

    Program Projects Program Projects Other Work

    Projects Projects Projects

    Defining Project Portfolio

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    122/199

    122 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PortfolioName

    Give an exampleof a portfolio ?

    Defining Project Portfolio Management

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    123/199

    123 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The centralized management of one or more portfolios, whichincludes identifying, prioritizing, authorizing, managing, andcontrolling projects, programs, and other related work to achievespecific strategic business objectives.

    The focus of portfolio management is to ensure that theorganization is doing the right work rather than doing work

    right

    The Organizational Context of PPM

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    124/199

    124 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Management of AuthorizedPrograms & Projects

    (Increasing value production capabilities)

    Management ofOn-going Operations

    (Producing Value)

    Project PortfolioPlanning & Management

    High-Level OperationsPlanning & Management

    Organizational Strategy & Objectives

    Mission

    Vision

    Organizational Resources

    The Organizational Context of PPM

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    125/199

    125 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Vision, Mission, Strategy, and Objectives help definingorganizations performance targets

    Portfolio Planning & Management establishdistinctinitiatives required to achieve the organizations

    performance targets

    PPM ensures that the critical organizational resourcesare consumed in achieving high priority initiatives.

    PPM & Organizational resources

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    126/199

    126 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Some project managers are frustrated by lack of resources or byother groups stealing their resources

    These frustrations are symptoms of an unbalanced (orunacknowledged) project portfolio.

    The frequent complaint of "not enough resources," is simply anotherway of saying that there are too many projects!

    Someone should be sorting them out, prioritizing them, and "killing"the projects that aren't high priority.

    PPM can help project managers have enough resources toaccomplish projects that are perceived to be valuable and enjoyplenty of support throughout the organization

    Exercise 5

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    127/199

    127 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Compare project management, program management, andportfolio management.

    Portfolio Management Process Groups

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    128/199

    128 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Aligning ProcessGroup

    1. Identify components2. Categorize components3. Evaluate components4. Select components

    5. Identify portfolio risks6. Analyze portfolio risks7. Prioritize components8. Develop portfolio risk

    responses9. Balance portfolio10. Communicate portfolio

    adjustment11. Authorize components

    Monitoring &Controlling

    Process Group

    1. Monitor & control portfoliorisks

    2. Review & report portfolioperformance

    3. Monitor business strategychanges

    Portfolio Management Process Groups

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    129/199

    129 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    StrategicChange

    No

    Yes

    Current strategicPlan

    Goals Definition Key performancecriteria CapacityDefinition

    Strategic PlanningProcess Output

    Aligning Process Group

    IdentifyComponents

    CategorizeComponents

    EvaluateComponents

    SelectComponents

    PortfolioReporting &

    Review

    Monitoring &Controlling Process

    Group

    ComponentExecution &Reporting

    ComponentProcesses

    Identify

    Portfolio Risks

    AnalyzePortfolio Risks

    PrioritizeComponents

    DevelopPortfolio Risk

    Responses

    BalancePortfolio

    CommunicatePortfolio

    Adjustment

    AuthorizeComponents

    Monitor Bus.StrategyChanges

    Monitor &Control

    Portfolio Risks

    Aligning Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    130/199

    130 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Identify ComponentsTo create an up-to-date list, withsufficient information, of ongoing and new components that willbe managed through portfolio management

    Categorize ComponentsTo group identified components

    into relevant business groups to which a common set of decisionfilters and criteria can be applied for evaluation, selection,prioritization, and balancing.

    Hint: Components in each group relate to a common strategic goal

    Aligning Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    131/199

    131 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Evaluate ComponentsTo gather necessary information toevaluate components with the purpose of comparing them inorder to facilitate the selection process

    Qualitative & quantitative information

    Iterative process until you reach the required accuracy and

    coverage level Graphs, charts, documents, and recommendations are produced to

    support the selection process

    Aligning Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    132/199

    132 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Select ComponentsTo select components based on theevaluation process. Produces a list of categorized, evaluated, andselected components. Also recommendation report of acceptedand rejected components is produced

    Identify Portfolio RisksTo identify portfolio risks anddetermine which risks could affect the portfolio and documenttheir characteristics. The impact of a risk on different portfoliocategories vary

    Analyze Portfolio RisksTo prioritize the identified risks forfurther action based on their probability of occurrence and theirimpact on portfolio performance or objectives such as ROI

    Aligning Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    133/199

    133 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Prioritize ComponentsRank components within eachstrategic or funding category, investment time frame, risk versusreturn, and organizational focus according to established criteria

    Develop Portfolio Risk ResponsesTo develop options and

    determine action to enhance the opportunities and reduce threatsto the portfolio objectives. Risk response planning includesassigning risk owners and inserting resources and activities intothe budget, schedule, and portfolio management plan.

    Aligning Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    134/199

    134 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Portfolio BalancingDevelop the portfolio component mixwith the greatest potential to collectively support the strategicinitiatives and achieve strategic objectives

    includes the following activities:

    Add new components that have been selected and prioritizedfor authorization

    Eliminating components to be suspended, reprioritized, orterminated based on the review process

    Identifying components that are not authorized based on thereview process

    Selecting the right mix to achieve the desired returns should take into

    consideration: interdependencies, similarities, and synergies that existbetween components

    Aligning Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    135/199

    135 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Communicate Portfolio AdjustmentsCommunicateportfolio changes to the stakeholders to provide clearunderstanding of the impact of the change on portfolioperformance goals and the larger business strategies

    AuthorizationTo formally allocate financial and humanresources to either develop business case or execute selectedcomponents and to formally communicate portfolio-balancingdecisions to stakeholders

    Starting and / or terminating decisions Budget and resource reallocation for inactive and terminated

    components

    Monitoring & Controlling Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    136/199

    136 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Monitor & Control Portfolio RisksTo determine if:

    Portfolio assumptions are still valid

    Risk, as assessed, has changed from its prior state

    Proper risk management policies and procedures are beingfollowed

    Contingency reserves of cost or schedule are modified in line withthe risks

    Monitoring & Controlling Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    137/199

    137 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Review & Report Portfolio PerformanceGather and reportperformance indicators and review the portfolio at an appropriatepredetermined frequency to ensure alignment with theorganizations strategy and effective resource utilization

    Each review cycle may contain several reviews with a different

    focus and depth of analysis.

    What is the ultimate purpose of the reviews?

    Portfolio contains only the components required to supportachieving the strategic objectives

    What elements to be reviewed?

    Scope, Risks, Resource Utilization, Financial Performance,policies &Standards, etc.

    Monitoring & Controlling Process Group

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    138/199

    138 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Monitor Business Strategy ChangesTo enable portfoliomanagement to respond to changes in business strategy. Asignificant change in business strategic direction will impactcomponent categorization or prioritization and this will require re-

    balancing the portfolio

    Portfolio Management Knowledge Areas

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    139/199

    139 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    PORTFOLIO MANAGEMENT PROCESS GROUPS

    Monitoring & Controlling

    Process GroupAligning Process

    GroupProcess Knowledge

    Area

    Review & Report PortfolioPerformance

    Identify Components

    PortfolioGovernance

    Monitor Business Strategy ChangesCategorize Components

    Communicate Portfolio AdjustmentsEvaluate Components

    Select Components

    Prioritize Components

    Authorize Components

    Monitor & Control Portfolio RisksIdentify Portfolio RisksPortfolio RiskManagement

    Analyze Portfolio Risks

    Develop Portfolio RiskResponses

    Pipeline Management

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    140/199

    140 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The process of determining if and how a set of projects in theportfolio can be executed by a company in a specified time, givenfinite development resources in the company.

    The organization should have the tools to estimate the efforts planned foreach project

    Role of the Portfolio Manager

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    141/199

    141 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Typically a senior manager or senior management team

    Provide stakeholders with timely assessment & timelycommunication of portfolio and component performance

    Participate in program and project support to reflect senior levelsupport and leadership

    Re-evaluate portfolio components on regular basis

    Performance review

    Benefit realization

    Strategic direction & priorities

    The PMO as a Portfolio Manager

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    142/199

    142 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Project Portfolio Management is the responsibility of senior executives in the

    organization. PMO facilitates and coordinates the involvement of theexecutives in the project oversight

    Develop and implement processes and procedures for each project portfoliomanagement activity based on the organizational maturity level

    Furnish executive management with reports indicating the organizationportfolio overall health

    How each component is performing against predefined KPIs

    Level of contribution of each component to achieving strategic objectives

    Composite risk level of the portfolio

    Resource capabilities and utilization

    Financial Performance

    Example: Defining Business Priorities

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    143/199

    143 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Defining Business Priorities

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    144/199

    144 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Assess Competing Investments

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    145/199

    145 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Measure Strategic fit (how?)

    Financial Return (how?)

    Risks (how?)

    Architectural fit (how?)

    Operational Performance (how?)

    Example: Measuring the Strategic Fit

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    146/199

    146 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Portfolio Management Success Factors

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    147/199

    147 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Does your organization have clear, communicated strategic goals& objectives?

    Does your organizations have the following symptoms?

    No formal process to define goals & objectives

    Long-term planning is not as important as fire-fighting

    There is no measurement process to validate status

    Only those at the top know about the goals & objectives

    Goals & objectives are not qualified or quantifiable

    Accountability to achieve the goals doesnt exist

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    148/199

    148 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Chapter 6

    INTRODUCTION TO OPM3

    Maturity Models

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    149/199

    149 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The term Maturity Model has become widely recognized withthe advent of CMM (Capability Maturity Model) for softwareengineering in the late 1980s

    Maturity indicates capabilities grow over time to produce

    repeatable success

    Without existence of mature processes, organizations are forcedto use talent and heroic efforts alone to accomplish tasks

    Defining OPM3

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    150/199

    150 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Organizational Project Management (OPM) is the alignment of

    an organizations projects, programs, and portfolios to its stated

    strategic goals

    Organizational Project Management Maturity Model (OPM3)is a

    standard developed by PMI designed to help organizations translatestrategy into successful outcomes, consistently and predictably(PMI, 2003,p. ix)

    Defining OPM3

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    151/199

    151 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    OPM3 standard has three key elements:

    Knowledge: Describes the organizational project managementmaturity

    Assessment: Methods, processes, & procedures that anorganization can use to self-assess its maturity

    Improvement: A process for moving from current maturity toincreased maturity

    Defining OPM3

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    152/199

    152 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    OPM3 focuses on alignment of projects, programs, andportfolio resultswith the organizational strategicobjectivesachieved by continuous improvement through the adoption andenhancement ofbest practices

    Other maturity models such as CMM focus on producingconsistent products and consistent support for products

    OPM3 defines a continuum of maturity as opposed to discrete

    maturity levels

    The OPM3 Cycle

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    153/199

    153 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    1

    The OPM3 Cycle

    2 3 4 5

    OPM3 Vs CMM

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    154/199

    154 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    CMM model has five levels

    Level 1: Initial ad-hoc processes employed based on the strengthof individual team leaders

    Level 2: Repeatable basic processes are informally established

    Level 3: Defined documented processes are standardized and

    integrated into daily operations

    OPM3 Vs CMM

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    155/199

    155 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Level 4: Managed process adherence is measured through

    established metrics and evolutions are based on these metrics Level 5: Optimizing continuous process improvement is

    practiced and documented; organization culture is continuousimprovement

    OPM3 Domains

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    156/199

    156 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    OPM3 model has three different domains

    Project Domain

    Program Domain

    Portfolio Domain

    Project Domain

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    157/199

    157 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The main responsibilities of the project manager in the projectdomain are:

    Managing stakeholder expectations at a project level

    Managing project constraints

    Identifying inter-project contentions

    Prioritizing Tasks

    Ensure project objectives support program strategies

    Program Domain

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    158/199

    158 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The main responsibilities of the program manager in the programdomain are:

    Managing stakeholder expectations at a program level

    Coordinating activities of multiple project managers & teams

    Managing conflicts among projects to achieve organizational goals

    Prioritizing projects

    Ensure program objectives support portfolio strategies

    Portfolio Domain

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    159/199

    159 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The main responsibilities of the portfolio manager in theportfolio domain are:

    Translating organizational strategies into specific initiatives orbusiness cases that become the foundation for programs & projects

    Identifying and initiating programs and projects

    Providing, allocating, and reallocating resources to programs,projects, and other activities

    Maintaining a balanced project portfolio

    Supporting the OPM environment

    Process Improvement Stages

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    160/199

    160 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    S = Standardize: The organization uses the process acrossfunctional boundaries

    M = Measure: The process is standardized and measurements aretaken

    C = Control: A process is in control if all measurements arewithin the upper and lower boundaries

    I = Improved: If the process is controlled and data is collected &used to improve the process

    Best Practices

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    161/199

    161 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    An optimal way currently recognized by industry to achieve a stated goal or

    objective. Best practices are incorporated into mature project managementcapabilities in organizations

    All BPs are categorized by stage & domain dimensions. OPM3 has around 586OPM BPs

    BP

    Number

    BP Name BP

    Description

    Domain Stage Process Process

    Group

    1030

    Project Scope

    Planning

    ProcessStandardization

    Project Standardize 5.1 Planning

    Capability

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    162/199

    162 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    CapabilityA specific competency that must exist in anorganization in order to execute project management processesand deliver project management services and products.

    Capability is an element of BP. Every BP has several Caps.

    OPM3 has around 3000 capabilities

    Best Practices & Capabilities

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    163/199

    163 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    BP 1030 with constituent and pre-requisiteCapsBP Diagram with constituent and pre-requisite Caps

    Best Practice 1030 Project ScopePlanning Standardization

    Constituent Cap 1030.10 ProcessManagement Governing Body

    Prerequisite Cap 1000.10 EstablishedStandardization Policies

    Constituent Cap 1030.20 Project ScopePlanning Process Development

    Constituent Cap 1030.30 StandardizedProject Scope Planning Process

    BP 1030 BP 1000

    Cap1030.030

    Cap1000.030

    Cap1000.020Cap

    1030.020

    Cap1030.010

    Cap1000.010

    Other Important OPM3 Terms

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    164/199

    164 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    OutcomeA tangible or intangible result of applying a capability.

    A capability may have one or more outcomes

    Key Performance Indicator (KPI)A criterion by which anorganization can determine, quantitatively or qualitatively, whetherthe outcome associated with the Capability exists or the degree to

    which it exists.

    The difference between a Cap and an Outcome of a Cap is ademonstrated competency in the organization

    Other Important OPM3 Terms

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    165/199

    165 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    BP 1030 Caps & OutcomesBP Diagram with Outcome and KPI

    Best Practice 1030 Project ScopePlanning Standardization

    Constituent Cap 1030.020 ProjectScope Planning Process Development

    Outcome 1030.020.10 DocumentedProject Scope Planning Process

    BP 1030

    Cap1030.030

    Cap1030.020

    Cap1030.010

    Outcome1030.020.10 KPI

    How Does OPM3 Work?

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    166/199

    166 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    1. Standardize

    2. Measure

    3. Control

    4. Improve

    Standardize

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    167/199

    167 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    The process is implemented and standardized in the organization

    Documented (Caps, outcomes, policies, checklist, templates, guidelines,tools, etc.)

    Communicated

    Implemented consistently

    Governing body established

    Use a formal process model for documentation such as:

    SIPOC (Suppliers-Inputs-Process-Outputs-Customers)

    ETVX (Entry Criteria, Task, Verification, and Exit Criteria)

    IDEF (Integrated Definition) CIMOSA (Computer Integrated Manufacturing Open System Architecture)

    Measure

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    168/199

    168 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    Critical steps of the process and all inputs to the process are identified,

    mapped, and measured

    Variations are identified

    Quality Audit group measures performance of the process (attributemeasurement & variable measurement)

    Did the project team conduct kick-off meeting? Did the kick-off meeting had a clear agenda and minutes?

    Number of scope changes

    Cost Performance Index

    QA produces Non Compliance Report (NCR) that PMO will investigate

    Metrics dashboards might be used in some organizations to highlight vitalmeasurements

    Control

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    169/199

    169 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    A process is controlled when it stays within process specifications

    A controlled process has predictable future performance basedon past performance

    A process is controlled in the organization if acontrol plan for the process has been developed, in action, and

    describes how it address variations

    The process has upper and lower limitations

    Control tools include: control charts, Standard deviations

    Who controls the processes?

    Improve

  • 8/3/2019 Building and Managing the Right PMO_06Feb2010v2

    170/199

    170 Building & Managing the Right PMO IBRAHIM MAHMOUD IBRAHIM

    A series of actions taken to identify, analyze, and improve existingprocesses within an organization to meet new goals and objectives

    A process in control is the primary target for improvement

    An improved process has the following characteristics Root causes for problems within the process are documented

    All parties participate in the improvement process

    The improvement is sustainable (enforced by PMO, training,