Page 1: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Broyhill Wind Project4 March 2008 Presentation

Page 2: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Topics to cover

• REI background• Broyhill Wind Project• Visual analysis

– Photo simulation– Shadow analysis

• Sound analysis• Other topics• Discussion

Page 3: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Renewable Energy Initiative

Mission StatementReduce the environmental impact of Appalachian State University by replacing the university’s existing sources of energy with cleaner forms of renewable energy technology on campus and serve as a resource for students and faculty by identifying and investing in the most appropriate renewable energy projects.

Page 4: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Last Year’s Vote on the REI Fee

• Student referendum for additional fee of $5/student/semester

• 1,352 votes– more than the presidential issue (1070)

• 93% of voters (1258) voted yes! • Compared with 2004 vote

– 500 more votes this year– 82% mandate in 2004

Page 5: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Completed REI projects

• Biodiesel Collaborative Solar Thermal

• ASU & AppalCART Biodiesel Tank

• Biodiesel Collaborative Photovoltaic Array

Page 6: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Current REI projects

• Raley Hall Photovoltaic Array

• Plemmons Student Union Solar Thermal System

• Plemmons Kiosk• Education Building Solar• No examples of wind energy

Page 7: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Broyhill is the windiest place at ASU

Wind Power density map

Annual Average wind speed map

Page 8: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Other benefits Broyhill site

• School property• Close to infrastructure

– Short run to utility interconnect– No additional roads needed

• Showcase ASU– Environmental leader– Student activity– Serves as an attraction

Page 9: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Where

• Next to water tank– Highest place has the best wind– Extend water tank fence

• Well within ASU property– Satisfies setbacks– ASU regulations not Boone or Watauga

Page 10: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Site dimensions

Page 11: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 12: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Size of proposed REI Wind Turbine

• Dictated by annual budget: $135,000• Can afford about 100kW

– Diameter of 20m (66ft)– Tower height of 35m (115ft)– Total height of 45m (148ft)

• Monopole, 3-blade, upwind modern– Modeled as Vestas V-20 on 35m tower– Annual output of 150,000 to 200,000kWh, enough for 10 to 15 homes

Page 13: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 14: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Photo Simulations• WindPRO, actual photos

– snowy March 1st

– sunny March 2nd

• ArcGIS, actual data, CG world

– wind turbine = 45m– trees = 60ft– The Broyhill Inn & Conference Center = 40ft– water tank = 30ft– other building = 20ft, regardless of their actual height

Page 15: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 16: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 17: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Bodenheimer Dr.

Page 18: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 19: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Broyhill dining room

Page 20: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 21: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 22: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 23: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 24: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 25: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Animations in ArcGIS

Page 26: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

What will it sound like?• Same noise level as a “quiet office”

– Rear carport– Outside dining room window

• Will not be above ambient sound levels– loading dock– Upper dining room patio

Page 27: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Sound Analysis

• Decibel chart• Ambient sound measurements on:

– March 2nd, windy day– March 3rd, calm day with birds chirping

• WindPRO analysis

Page 28: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Ambient noise level

Pink dB from 1st March, windy day –see rightBlue dB from 2nd March, calm day

Page 29: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Ambient Noise ResultsdB

Common reference

Calm day Windy day V-20 noiseEquivalent Location

more walk by idling SUV

60 Noisey office Loading dock Loading dock @ tower base

55 Upper patio Upper patio @ 35mMiddle of paved service road

50 Quiet officewindow AC in northwest cornerservice area picknic table

front carportservice area picknic tablerear parking lot

@ 85mOutside dining room window

45transformer boxlower patiorear carport

@ 140m Front carport

less

transformer boxlower patiorear carportfront carport

WindPRO calculations on noise level and distances from turbine

dB [ft] [m]55 56 1750 200 6145 404 12340 623 19035 945 288

Page 30: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Shadow AnalysisAstronomical worst case

– Always sunny, and therefore always a shadow– Always windy, so the blades are moving

– Always blowing inline with the turbine and the observer; making the blades perpendicular to the observer, and giving the largest possible shadow area

This way not this

Page 31: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Rear carport

Page 32: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Dining room window

Page 33: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Dining room shadow

• An awning– Need to shade when sun is at first shadow on

winter solstice –the worst case• Azimuth of 167• Elevation of 29

– Broyhill faces 86– Apply trigonometry

• 5.5ft overhang provides full shading for 10ft tall window

Page 34: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Chancellor’s house

Page 35: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Other items• Radio

– No. Asynchronous, brushless motors do not cause the same RF interference

– Turbines as antenna towers• Construction

– Relatively small crane• Birds

• Typically not an issue– Monopole does not allow for roosting– Broyhill not a known migratory path for endangered

birds

Page 36: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Animations in ArcGIS

Page 37: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Questions&

Discussion

Page 38: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

THANK YOU

Page 39: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 40: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 41: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Output

Page 42: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis

Comparison of output

Page 43: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 44: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis
Page 45: Broyhill Wind Project 4 March 2008 Presentation. Topics to cover REI background Broyhill Wind Project Visual analysis – Photo simulation – Shadow analysis