bridge strengthening paper

Upload: viet-duc-dang

Post on 03-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Bridge Strengthening Paper

    1/18

    Strengthening of Bridges

    David Coe - Pitt and Sherry

    1.0 INTRODUCTION

    Understanding the load capacity of bridges should be the fundamental requirement of

    all road authorities. This knowledge is essential for proper management of traffic on

    any transport network. It is surprising how many authorities have a poor

    understanding of bridge load capacity and hence, by inference, little appreciation of a

    major risk on their road network.

    There is pressure for road authorities to increase legal loads of vehicles across theirnetworks. The transportation industry has invested heavily in vehicles with increased

    axle mass with road friendly suspensions. While access for a number of years has

    been limited to designated routes, road authorities are being pressured to provide

    increased access so that the great economic benefits highlighted in the 1996 National

    Road Transport Commission report on Mass Limits Review (MLR) can be realised.

    Figure 1 illustrates the new vehicle loads following the MLR process.

    Figure 1 Mass Limit Review Loads

    As a result of these needs to improve bridge management processes and to provide

    access to heavy axle mass vehicles, road authorities are under increasing pressure to:

    Determine, and further refine, the load rating of bridges

    Develop cost effective strengthening solutions

  • 7/28/2019 Bridge Strengthening Paper

    2/18

    2.0 LOAD RATING

    Following acceptance of the recommendations of the Mass Limits Review, Austroads

    developed Guidelines for Bridge Load Capacity Assessment, through a Bridge

    Assessment Group, comprising representatives from the state road authorities. These

    guidelines focused on assessing bridges for the live load configurations shown inFigure 1, which represented the increased axle mass vehicles.

    The Bridge Assessment Group collected, summarised and distributed bridge rating

    information and produced guidelines such as that shown in Table 1 below.

    Design load Comments

    T44 bridges

    (1976-NAASRA Bridge Design

    Specification)

    < 25m spans are generally adequate except

    for some road trains

    > 25m spans are generally adequate exceptfor road trains and multiple B doubles

    MS18 bridges

    (1953 NAASRA Bridge Design

    Specification)

    < 20m simply supported spans are generally

    adequate except for U-slab bridges without

    concrete overlays

    Pre MS18 bridges Review all bridges

    Table 1 Bridge Rating Guidelines

    This table demonstrates that, in general, many bridges constructed after 1953 should

    be adequate for the higher mass vehicles. However, many bridges located on lowclassification routes were only designed for 75% of the full design load.

    In 2004 the Australian Bridge Design Code was superseded by AS5100 Bridge

    Design, including Part 7: Rating of Existing Bridges. The methodology used to assess

    the load capacity of a bridge in the code is based on ensuring the same level of risk in

    a specific case as required for the general case.

    Where the Mass Limits Review process has identified understrength bridge

    substructures and isolated superstructure components it has generally proved to be

    cost effective to proceed with strengthening. Where analysis shows majorsuperstructure elements, such as bridge girders, to be understrength the cost of

    practical strengthening measures is greatly increased. In these cases, the costs of

    undertaking further investigation and analysis, including bridge load testing is often

    warranted in order to obtain more refined load capacity information. It is frequently

    proved through load testing that a bridge has more capacity than originally calculated

    in a simple desk top analysis.

    With significant constraints on available funds, the process of assessing the priority

    for further investigation and strengthening needs to be aligned with the communities

    demands for improved level of service with regard to load capacity of designated

  • 7/28/2019 Bridge Strengthening Paper

    3/18

    routes, or road hierarchies. The criteria for determining the priority of selecting

    structures may include:

    Existing load capacity of structure;

    Strategic heavy load route designation;

    Traffic intensity;

    Specific heavy load access requirements;

    Funding sources.

    2 STRENGTHENING DESIGN METHODOLOGY

    When a structure has been identified through a desktop assessment to be understrength

    and is required to be capable of carrying the higher loads in accordance with the

    priorities described above, it is important to undertake an extensive engineering designprocess to achieve an optimised solution. This process should involve the following

    stages:

    i) The detailed structural assessment of the structures;

    ii) Development of alternative concept strengthening solutions;

    iii) Detailed design and documentation of the preferred solution and preparation of

    tender specification.

    2.1 Detailed Structural Assessment

    A desktop analysis that initially identifies a structure as being understrength is usually

    based on the existing drawings, making the same assumptions for the analysis as an

    engineer would make for a new design. This tends to be a conservative approach

    where:

    The elastic model is usually relatively simplistic,

    The material properties are based on lower bound characteristic values code based

    values, and

    Factors are adopted from the design code tend to be conservative.

    It is important to review where the desktop analysis is showing deficiencies anddetermine if further investigation will improve the understanding of the actual load

    capacity of a structure. It is usually warranted to undertake further detailed

    investigation and assessment including:

    Inspection of the structure to identify elements of the structure that may affect the

    structural performance of the bridge. For example, the barriers on a structure will

    often attract load and improve the capacity of a structure. Similarly, there is

    usually some form of fixity at a support which will frequently enhance the

    structural performance of a structure.

  • 7/28/2019 Bridge Strengthening Paper

    4/18

    In many cases it will be difficult to identify the extent such items may contribute

    to the structural performance of a bridge. Depending on the areas where the

    structure is understrength, a load test may be warranted.

    It is usually worthwhile undertaking testing to better understand the properties of

    the material actually used in the structure, particularly for older structures

    By undertaking a detailed investigation, the dimensions for a structure will be

    better understood and it should be possible to reduce factors in the load assessment

    process.

    2.2 Alternative concept strengthening solutionsDuring the design development process there needs to be a close liaison between the

    client and designer in order to deliver practical, cost effective solutions. As it usually

    impossible to close any structure for any significant period, the constraints to install

    any proposed strengthening work will usually drive the strengthening design solution.

    It is likely there will be pressure for further mass increases to be introduced in future.

    As a result it is advisable to assess structures for the current standard traffic design

    loading and the SM1600 loads specified in AS5100.2. Strengthening options should

    be developed based on the principle that structures should be strengthened to current

    standard traffic design loading as a minimum but where practical and justifiable within

    the funding available to Load Group B.

    During design development, it is advisable for the proposed strengthening measures to

    be reviewed by an experienced bridge construction engineer to assess potential

    buildability issues and also provide guidance on cost estimates, where the cost ofaccess and labour usually far outweighs the cost of materials.

    2.3 Detailed design

    During the detailed design process, a thorough risk assessment should be undertaken

    of the proposed works. It will often be more economic to accept that some issues will

    need to be finally resolved during the construction work, rather than fully appraising

    and eliminating all risks during the design process. However, it is important for

    authorities to include reasonable contingencies when undertaking strengthening, or

    rehabilitation work.

    3.0 STRENGTHENING SOLUTIONS

    In Tasmania and Victoria there has been a campaign by road authorities to strengthen

    a significant number of bridges. A number of unique methods have been developed for

    strengthening bridge components.

    Methods for strengthening substructures include:

    External post-tensioning of pier crossheads;

    Widening of blade piers;

    Bonding of steel plates to crossheads. Infill walls between pier columns;

  • 7/28/2019 Bridge Strengthening Paper

    5/18

    Widening of pier crosshead.

    For superstructures strengthening methods include:

    Carbon fibre strengthening;

    Strengthening of halving joints;

    Reinforced concrete U-Beam Overlay

    External Post Tensioning

    Strengthening of wrought iron structures

    The strengthening solutions have been developed to address deficiencies identified

    from the detailed assessment to suit each structure and site constraints. Most of the

    adopted solutions have proved successful and can be transferred to bridges with

    similar deficiencies. The following section provides further details on the

    strengthening methods listed above.

    3.1 Strengthening of Substructure Elements

    3.1.1 External post tensioni ng of pier crossheads

    At Hellyer River Bridge the hammerhead pier crosshead to the 2 span steel girder

    superstructure was identified to be understrength in flexure for MLR vehicles and in

    shear and torsion for MS1600 vehicles.

    The strengthening works involved external post tensioning consisting of high strength

    Macalloy bars stressed against prefabricated steel stressing heads located at either end

    of the crosshead, as shown in the Figure 2. Although located in a benign environment

    all steelwork, including the Macalloy bars, were coated with two coats of epoxy

    primer. Due to a lack of depth in the crosshead, the moment capacity could only be

    increased to accommodate MLR design vehicles.

    Figure 2 Post Tensioned Pier Crosshead

  • 7/28/2019 Bridge Strengthening Paper

    6/18

    Photograph 1 Post Tensioned Crosshead - Hellyer River Bridge.

    The approximate cost of the work was $57,000. The work proceeded smoothly with

    minimal disruption to traffic using the bridge. During post tensioning, traffic was

    limited to a single central lane with a 10km/hr speed restriction enforced. The as

    constructed strengthening on Hellyer River Bridge is shown in Photograph 1.

    3.1.2 Widening of blade pier

    Stitt River Bridge is a 2 span steel girder structure, with a hammerhead pier. The piercrosshead, which is supported on a blade type column, was found to be understrength

    for MLR vehicles in flexure and shear, and failure for combined shear/torsion.

    Photograph 2 Blade Pier Widening Stitt River Bridge

  • 7/28/2019 Bridge Strengthening Paper

    7/18

    Photograph 2 shows the adopted strengthening solution of widening the blade pier to

    improve the bending and shear properties of the crosshead and also remove the

    problem of torsion. Dowels were grouted into the existing crosshead and pier at

    300mm spacing, alternately located to both faces of the wall. The design considered

    concrete shrinkage effects against the existing pier, with the specification detailing

    requirements for casting sequences and programming. A gap was left between the top

    of the widening and the underside of the crosshead. After a reasonable period to allow

    for further shrinkage effects, the gap was filled under pressure with a non-shrink grout.

    The approximate cost for undertaking this work was $86,000. During construction the

    majority of the work was able to proceed without traffic restrictions on the bridge.

    Prior to grouting the traffic lane on the side of the bridge to which grouting was to

    occur was closed. It remained closed until the strength of the grout was 20MPa. A

    speed restriction of 10km/hr was applied to the open lane during this period.

    3.1.3 Bonding of steel plates to pier crossheads

    The piers to Little Forester River Bridge consist of three hexagonal concrete columns

    supporting an 800mm deep crosshead. The crosshead, which supports a precast

    concrete inverted U-beam superstructure, was identified as having inadequate shear

    capacity.

    In addition to a standard deck overlay to strengthen the superstructure, steel plates

    were bonded to the crosshead to increase the shear capacity for Load Group A

    vehicles, as shown in Photograph 3. Steel angles were fixed to the top and bottom

    corners of the crosshead and the vertical steel plates were fixed to the sides at regular

    spacing. The steelwork, which was galvanised, was fixed to the crosshead with an

    epoxy bonding agent.

    The approximate construction cost was $35,000. The bridge was closed to traffic

    while undertaking the remedial work as there was insufficient width to install the deck

    overlay by keeping one lane open to traffic. As a result a bypass was constructed and

    remained in place while work to the piers was carried out.

    3.1.4 I nf il l walls between columns

    The steel girder bridges forming the on and off ramps to the Bass Highway on the

    western side of the Mersey River in Devonport are relatively complex with varying

    span lengths, widths and skews along the length of both bridges. The piers consist of

    675mm square reinforced concrete columns supporting 1050mm deep reinforced

    concrete crossheads. For MLR loads, the crossheads were deficient in flexure and

    shear.

  • 7/28/2019 Bridge Strengthening Paper

    8/18

    Photograph 3 Shear Capacity Strengthening - Little Forester River Bridge

    Photograph 4 Infill Walls Bass Highway Off-ramp

  • 7/28/2019 Bridge Strengthening Paper

    9/18

    It was decided to strengthen the piers by constructing a new 300mm thick concrete

    wall between the columns. The new wall is dowelled into the existing column and

    pile cap to develop monolithic behaviour. The gap between the top of the infill wall

    and the underside of the crosshead is grouted under pressure injection after a suitable

    curing period. The strengthening increases the capacity of the piers to include MS

    1600 loads.

    3.5 Widening of pier crossheads

    Treehawke Creek Bridge has a precast concrete inverted U-Beam superstructure with

    a hammerhead pier. The pier crosshead, which is supported on a blade type column,

    was found to be understrength for MLR vehicles in flexure, shear and torsion.

    Figure 3 Crosshead widening Treehawke Creek Bridge

    The bridge is located in an environmentally sensitive area with the pier being partially

    submerged. It was decided to strengthen the crosshead for MLR vehicles by wideningto both sides in order to minimise the site disturbance, as shown in Figure 3. The

    widening process involved drilling and grouting dowels into the existing crosshead,

    preparing the existing concrete surface and casting new reinforced concrete bolsters to

    the side of the crosshead. The concrete mix included a super plasticiser to facilitate

    concrete placement and reduce shrinkage.

    The approximate cost of the crosshead widening works was $64,000. During

    construction, the Contractor proposed to anchor the dowels in epoxy mortar instead of

    the detail shown in Figure 3. Difficulty was experienced with fixing the reinforcement

    in the confined space and applying the specified bonding agent to the surface of the

    existing concrete crosshead with the reinforcement for the widening in position.

  • 7/28/2019 Bridge Strengthening Paper

    10/18

    3.2 Strengthening of Substructure Elements

    3.2.1 Carbon fi bre strengthening

    Carbon fibre is being used increasingly to improve the load capacity of reinforced

    concrete bridge superstructures. It is predominantly used to improve the flexural

    capacity of beams and decks. For example, the reinforced concrete deck to the Bass

    Highway on-ramp on the western side of the Mersey River in Devonport was found

    to be deficient in sagging moment by up to 47%.

    Carbon fibre laminates were specified to be adhered to the underside of the deck to

    improve the flexural capacity of the slab by supplementing the existing steel

    reinforcement. The 2.0m long laminate strips span between the steel girders. The

    80mm wide, 1.2mm thick strips are installed at a spacing of 650mm along the deck.

    Prior to installation, the substrate must be carefully prepared by patch repairing any

    unsound areas and removing concrete laitance. The preparation of the substrate must

    be verified by undertaking pull-off tests as the substrate integrity is critical to the

    success of the process. The structure must be closed to traffic during placement of the

    carbon fibre laminates and during curing of the adhesive. The curing time can be

    reduced by applying heat to the adhesive.

    The approximate construction cost for the strengthening was $150,000. As the bridge

    forms an integral part of the link between East and West Devonport, severerestrictions were imposed in the contract regarding when the bridge could be shut to

    traffic.

    Difficulties were experienced during construction with irregularities in the deck soffit

    because the as-constructed detail varied from that shown on the drawings. As a result

    the pull-off tests failed and it was necessary to apply an epoxy grout to the underside

    of the deck in order to achieve an adequate surface for adhering the carbon fibre

    laminates.

  • 7/28/2019 Bridge Strengthening Paper

    11/18

    Photograph 5 Carbon Fibre Strengthening Bass Highway Off-ramp

    Arden Street Bridge forms a critical part of Melbournes road network connecting the

    Central Business District to the inner suburban and industrial areas of Kensington. The

    bridge crosses the Moonee Ponds Creek. The 47m long, 7 span structure was

    constructed in 1923. It consists of an in-situ reinforced concrete deck with 5

    downstand beams. Each beam is cast integrally into a reinforced concrete pier.

    The bridge was found to have inadequate capacity in flexure and both vertical and

    longitudinal shear in the regions close to and over the piers. Plastic Analysis allowing

    moment re-distribution at supports did not provide any significant benefits. The low

    rating in the region of the supports was exacerbated by reinforcement detailing which

    is no longer considered acceptable.

    A critical constraint during the development of bridge strengthening options was that

    there should be minimal disruption to the traffic using the bridge. In effect, this

    required all strengthening proposals to be installed under the bridge.

    It was proposed to install a folded steel plate to the underside of the deck and the side

    of the downstand beam. To ensure structural continuity the folded plate was epoxy

    bonded to the concrete substrate along with chemical anchors. The combination of the

    plate and the anchors provided increased capacity for both flexure and longitudinal

    shear over the supports.

    Increasing the shear capacity of the downstand beams in the vicinity of the piers was

    more of a problem. The use of carbon fibre strengthening for shear strengthening has

    been very limited, because it is very difficult to mobilise the full shear planes in thesection unless the beams can be fully wrapped. On Arden Street Bridge, as the

  • 7/28/2019 Bridge Strengthening Paper

    12/18

    downstand beams were cast integrally into the deck it was not possible to wrap the

    carbon fibre around the beam to provide the necessary anchorage lengths.

    Nevertheless, the folded steel plates that were proposed for strengthening the beams

    for flexure, provided the opportunity to fully anchor carbon fibre shear strengthening

    at the deck/beam interface. As a result, the carbon fibre strengthening detail shown in

    Figure 4 was proposed. A high modulus carbon fibre was chosen in this case, so that

    the minimum movement in shear would mobilize the most resistance force within the

    fibre, maximising the benefit to the bridge beams.

    Figure 4 Arden Street Bridge Strengthening Detail

    Once the Contractor had thoroughly cleaned the bridge and provided access for closer

    inspection there was a significant crack identified at the interface between the

    underside of the deck and the beam, forming a structural discontinuity between the

    deck and the beam. For the strengthening work to be fully effective, it was essential

    that the continuity between the downstand beam and the reinforced concrete deck was

    reinstated. Extensive crack injection was undertaken along the length of the bridge toreinstate the connection between the beam and the deck.

  • 7/28/2019 Bridge Strengthening Paper

    13/18

    Photograph 6 Carbon Fibre Installation Arden Street Bridge

    3.2.2 Strengthening of Halving Join ts

    With increased vehicle loads, the increase in shear force at supports often causes

    capacity problems. For example, Mersey River bridge is a 186m long, 5 span steelcomposite plate girder bridge. At the piers, the girders to both spans have a halving

    joint, as shown in Figure 5. The analysis showed the halving joints were overstressed

    in the following areas for MLR vehicles:

    Halving joint web panel;

    First full depth web panel;

    Lower halving joint load bearing stiffener.

    It was decided to strengthen the halving joints by providing:

    Additional web panel plating;

    Additional vertical intermediate web stiffeners to reduce effective panel sizes;

    Increased bearing stiffener thickness in the lower halving joint.

    Details of the strengthening measures are shown in Figure 5.

    The approximate cost of the works was $170,000. The bridge forms part of the

    National Highway and it was required that one lane should remain open at all times.

    Traffic was restricted to a single 3m wide lane immediately adjacent to the kerblocated on the side of the bridge away from the girder undergoing strengthening. A

  • 7/28/2019 Bridge Strengthening Paper

    14/18

    speed restriction of 20km/hr was also applied immediately prior to welding

    commencing until 15 minutes after completion of the weld. Extensive weld

    inspections demonstrated the required quality of the welds was achieved even though

    the Contractor had difficulty slowing the traffic to 20km/hr.

    F igure 5 Steel Gi rder H alving Joints - Mersey River Br idge

    3.2.3 Rein forced Concrete U-Beam Overlay

    There have been a significant number of bridges constructed from precast reinforced

    concrete U-beams. The beams are usually bolted together, with a grouted shear key at

    deck level. The poor connection details between the beams means that there is very

    little distribution of load between the beams. As a result most U-Beam bridges do not

    have sufficient capacity for MLR vehicles.

    A common method of strengthening these bridges is to provide a reinforced concrete

    deck overlay, as shown in Figure 6 below. The deck overlay not only increase the

    structural depth of the superstructure, but provides good load distribution between thebeams. It can also be seen in Figure 6, that provision of new kerbs provides an

    excellent opportunity to upgrade the bridge barriers as the existing barriers will rarely

    meet current code requirements.

  • 7/28/2019 Bridge Strengthening Paper

    15/18

    F igure 6 Typical Deck Overlay Detail

    3.2.4 External Post Tensioning

    Following the accident on the Tasman Bridge, in addition to the replacement of the

    damaged spans and piers, the number traffic lanes on the bridge were increased. This

    resulted in additional traffic loading on the outer beams, for which it had not been

    designed. As a result external post tensioning was provided to the outside beams to

    increase the structural capacity, as shown in Photograph 7 below.

    Photograph 7 External Post Tensioning Tasman Bridge

  • 7/28/2019 Bridge Strengthening Paper

    16/18

    3.2.5 Wrought I ron Structures

    Strengthening of wrought iron bridges is particularly difficult and significant problems

    are frequently encountered including:

    High cost access is usually expensive and the strengthening work inherently

    slow and labour intensive. Material compatibility wrought iron has a laminar structure that provides high

    strength in the longitudinal direction but is weak in the transverse direction.

    Strengthening of components by means of welding is potentially dangerous.

    Disruption to the community any extensive strengthening proposals require

    prolonged lane closures and possibly closure of the bridge for considerable

    periods.

    Heritage issues developing a strengthening solution sympathetic with the

    heritage values of the bridge would be difficult.

    Princes Bridge is Melbournes grandest bridge linking the southern commercial and

    art centres to the commercial heart of the City. It is one of the busiest bridges in

    Australia servicing vehicular, trams and extensive pedestrian traffic. Built in 1888 it

    has significant heritage value.

    A desktop analysis of the bridge load capacity showed the bridge required extensive

    strengthening to meet current legal loads. Pitt & Sherry and Van Ek Contracting

    offered an alternative proposal to carry out a performance load test on the bridge with

    the objective undertaking a more rigorous analysis by developing a calibrated

    structural model to optimise strengthening requirements to meet current legal loads.

    The Performance Load Test involved attaching strain gauges to critical structural

    members to measure the response of the structure under a test vehicle, developing an

    elastic model in a structural analysis program, as shown in Figure 7, and modifying

    the parameters in the model so that it has a similar response to that measured in the

    actual structure in the field, refer Figure 8.

    F igu re 7 Elastic Model F igure 8 Comparison of Model andF ield Test Resul ts.

  • 7/28/2019 Bridge Strengthening Paper

    17/18

    The analysis using the calibrated model showed that the bridge acted in a significantly

    different way to the original desktop analysis and the vast majority was deemed to

    have adequate strength for the new design loads. As a result the strengthening work

    comprised predominantly of replacing wrought iron rivets with high strength bolts.

    It is quite common for rehabilitation work on such structures that additional work is

    required once access is provided and the extent of damage is understood. It was

    recognised there was a high risk of repair work being required once access was

    provided and the pigeon guano removed to allow detailed inspection of the structure

    and there was a reasonable contingency for the repair of these different deteriorated

    members.

    The calibrated structural model was used to determine the extent of degradation that

    was permissible before intervention was required. In this way the extent of repair work

    was optimised.

    Photograph 8 Structural Repair Princes Bridge 4.0 CONCLUSIONS

    Following the introduction of MLR vehicles, a significant number of bridges have

    been identified as understrength. With limited funds available, road authorities have

    initiated programs of strengthening or further investigation by focussing on structures

    located on the strategic road network.

    In general it has proved more cost effective to strengthen bridge substructures andisolated superstructure components. Strengthening options have been developed based

  • 7/28/2019 Bridge Strengthening Paper

    18/18

    on the principle that structures should be strengthened to current design loads,

    including MLR vehicles, as a minimum. In recognition of the pressure for further

    design load increases, where economically justifiable the strengthening measures were

    increased to accommodate the actions from proposed higher design loads.

    Pitt and Sherry has developed a number of effective strengthening solutions to suit a

    wide range of structural deficiencies and site constraints. The majority of the solutions

    have proved to be successful and will be transferred to other structures with similar

    deficiencies.

    The construction issues need to be carefully assessed for all proposed strengthening

    works and in particular for relatively new techniques, such as carbon fibre

    strengthening. In addition to the construction methodology, management of traffic on

    the bridges while the work is being carried out is a critical issue.

    5.0 REFERENCES

    1. NRTC, National Road Transport Commission (1996)

    Mass Limits Review, Report and Recommendations, Melbourne, Victoria.

    2. STANDARDS AUSTRALIA, AS5100.7 Bridge Design Rating of Existing

    Structures, Standards Australia, New South Wales, 2004

    3. AUSTROADS BRIDGE ASSESSMENT GROUP, Guidelines for Bridge Load

    Capacity Assessment, AUSTROADS, Sydney New South Wales, 1997