bridge preservation update wade f. casey, p.e. bridge management engineer federal highway...
TRANSCRIPT
Bridge Preservation Update
Wade F. Casey, P.E.Bridge Management Engineer
Federal Highway Administration
AASHTO SCOM MeetingLouisville, KY
July 20, 2011
Presentation Outline
• National Bridge Preservation Efforts
• FHWA Bridge Preservation Guide
• National Bridge Management, Inspection and Preservation Conference
National Bridge Preservation Efforts
• FHWA Bridge Preservation Expert Task Group (ETG)
• AASHTO (TSP.2), Bridge Preservation Regional Partnerships
• Bridge Preservation Association
• AASHTO SCOBS, T-9 Committee
• TRB, AHD-30, AHD-00 Committee
DC
No East
PR
Western So East
Hartford, CT
Orlando, FL
Sacramento, CA
Detroit, MI
Midwest
2010 AASHTO TSP2 Bridge Preservation Partnership Meetings
Western So East Midwest No East
ETG - Objectives1. Promote the development and
implementation of clear and consistent bridge preservation terminology
2. Promote nationwide understanding and acceptance of bridge preservation as a component of asset management.
3. Streamline the analysis and presentation of bridge data to support the needs of decision makers, management, technical staff and other stakeholders to advance bridge preservation.
ETG - Objectives4. Promote the development and
implementation of bridge preservation related performance measures
5. Promote the continued development of a technically competent workforce in bridge preservation
6. Promote and support access to research results
ETG - Objectives7. Provide the needed leadership to ensure the
continuous management of the bridge component of the TSP2 Research Roadmap
8. Monitor changes to laws, regulations, policies and guidance that impacts bridge preservation and identify impediments to advancing and improving the state of the practice
9. Foster an environment that promotes agency and industry innovation in products, processes, technologies, and specifications
BRIDGE PRESERVATION ACTION ITEMSAction Items Organization
SEBPP NEBPP MWBPP WBPP BPETG Performance Measures P P P Public Awareness/Marketing P P P Research P P P P Specifications & Materials P P Toolbox, & Best Practices P P P P Website Development P P P Definitions P P P P Maintenance Contracting P 2011 Meeting Planning P P P P Local Agency Outreach P Monitor BP Laws, Regs, & Policies P BP as Applied Asset Management P Streamline Analysis & Data Presentation
P
Work Force Training & Development P
Bridge Preservation Guide• FHWA bridge preservation guide published in
May, 2011.• The guide can be found at the following web
link: http://wwwdev.fhwa.dot.gov/bridge/preservation/guide/index.cfm
Bridge Preservation Guide
Bridge Preservation
Preventive Maintenance
Cyclical (Non- Condition Based)
Activities
Condition Based Activities
Rehabilitation
Bridge Replacement
Bridge Preservation Definition
Actions or strategies that prevent, delay or reduce deterioration of bridges or bridge elements, restore the function of existing bridges, keep bridges in good condition and extend their useful life. Preservation actions may be preventive or condition-driven.
Systematic Preventive MaintenanceGoals &
Measures
Inventory & Condition
Assessment
Needs Assessment
Budgeting & Alternatives Evaluation
Work Plan
Plan Implementation
Performance Evaluation
Systematic Process
7 . Demonstrate Cost
Effectiveness ?
8 . Demonstrate
extension of life ?
YES
Implement Systematic Process for Preventive
Maintenance ( PM )
NO
NO 1 .
Define How the Needs are
ID ?
2 . Prioritize the
Need ?
3 . Program Remedy
to address the Need ?
4 . Define Outcome
?
5 . ID Resources
to achieve goal ?
6 . Define Timelines
and / or timeframes ?
9 . Dedicate adequate
resources ?
Application does not meet the systematic
process criteria
NO
YES
YES
YES
YES
YES
YES
YES
YES
NO
NO
NO
NO
NO
NO
Track the Progress
Review Application for Systematic Process. :
Does it
Use of Federal-aid funds not appropriate
for PM activities
Adjust as necessary to reach goal
And/or Goal
Examples of PM Activities
• Seal or replace leaking joints or elimination of deck joints
• Deck overlays
• Spot, zone, and complete coating of structural steel elements
• Installation of Cathodic Protection (CP) Systems.
• Electrochemical Chloride Extraction (ECE) Treatment for decks and substructure elements
• Installations of scour countermeasures.
Examples of PM Activities
• Removing large debris from channels.
• Retrofit of fracture critical members
• Retrofit of fatigue prone details
• Application of concrete sealants, coatings, and membranes.
• Bridge cleaning and/or washing service.
Bridge Management, Inspection, and Preservation National Conference
• October 31 – November 2, 2011, at the Millennium Hotel - Downtown St. Louis
• Three focus areas – Management, Inspection, and Preservation
• Hosted by FHWA, TSP-2, and Midwest Bridge Working Group
• Preconference Workshops on October 31• Technical presentations and Breakout
sessions
Closing Thoughts• FHWA will continue to emphasize and
support bridge preservation initiatives through:– Regional Bridge Preservation Partnerships,– AASHTO TSP2,– National Workshops, Conferences– Bridge Management Peer Exchanges, – Bridge Preservation Expert Task Group– Research– AASHTO SCOM and SCOBS– Bridge Preservation Association– TRB AHD30 and 00
Thank you!
Anwar S. Ahmad, P.E.Bridge Preservation Engineer
Federal Highway AdministrationTelephone: (202) 366-8501
Email: [email protected]