  • 7/30/2019 BOQ Food Court

    1/36

    GENERAL SUMMARY

    SECTIONSAMOUNT

    (US$)

    AMOUNT

    (S$)

    Carried from

    Page

    SECTION NO. 1 - PRELIMINARIES SR 1/3 -

    SECTION NO. 2 - M&E INSTALLATIONS SR 2/2 -

    SECTION NO. 3 - SEATINGS AREA SR 3/8 #REF!

    SECTION NO. 4 - SUB TENANT KIOSKS AREA SR 4/6

    SECTION NO. 5 - BACK OF HOUSE AND COMMON AREA SR 5/4

    SECTION NO. 6 - PELMET AND COLUMNS SR 6/3

    SECTION NO. 8 - SUPPLY OF LIGHT FIXTURES

    SECTION NO. 9 - SUPPLY OF LOOSE FURNITURES SR 8/1 -

    Note : Compulsory 10% VAT has not be included into the BOQ

    TOTAL SUM CARRIED : #REF! -

    Prepared by : Sebrina Tan, Kingsmen GS Page 1

  • 7/30/2019 BOQ Food Court

    2/36

    167765240.xlsx.ms_office

    Bill of Quantities

    ITEM DESCRIPTION QTY UNIT RATE

    Section NO. 1 PRELIMINARIES

    GENERAL NOTES

    A The Contractor shall refer to the "Preliminaries Specification" when

    pricing this Schedule.

    Note

    B All variations and additional works shall not be adjusted for

    Preliminaries and the Contractor shall make allowance in this

    regard.

    Note

    PRELIMINARIES

    1 Site Management, Site Survey, Supervision and Setting Out 1 Sum

    2 Attendance on and Coordination with all Nominated and/or Direct/

    Separate Contractors, Sub-Contractors and Suppliers

    1 Sum

    3 Insurance (CAR and Third Party Liability) 1 Sum

    4 Hoarding - including all staged hoarding where necessary. 1 Sum

    5 Dismantle of existing structures and removal of debris 1 Sum

    6 Working Hours Limitation and Site Constraints 1 Sum

    7 Permits, Fees and Charges (If applicable) 1 Sum

    8 Safety equipment 1 Sum

    9 Temporary Light, Power, Water and Facilities 1 Sum

    10 Storage and Delivery for procurement items (If applicable) 1 Sum

    11 Staging, scaffoldding, temporary railing 1 Sum

    12 Site Security 1 Sum

    13 Daily site cleaning during construction 1 Sum

    14 Finished floor protection 1 Sum

    15 Final Cleaning Sessions 1 Sum

    16 Samples and Mock-up 1 Sum

    17 Shop Drawings 1 Sum

    18 As Build Drawings and Operation & Maintenance Manuals 1 Sum

    20 Structural Calculation and Submission 1 Sum

    21 Warranties and Guarantees 1 Sum

    Carried to Collection :

    SR1-Prelim Page 2

  • 7/30/2019 BOQ Food Court

    3/36

    167765240.xlsx.ms_office

    Bill of Quantities

    ITEM DESCRIPTION QTY UNIT RATE

    SECTION NO. 1 PRELIMINARIES (CONT'D)

    23 Maintenance Crew within DLP 1 Sum

    24 Government and Building Permit Submission 1 Sum

    25 Other Employer's and Landlord's Requirements 1 Sum

    Carried to Collection :

    SR1-Prelim Page 3

  • 7/30/2019 BOQ Food Court

    4/36

    167765240.xlsx.ms_office

    Bill of Quantities

    ITEM DESCRIPTION QTY UNIT RATE

    SCHEDULE NO. 1 PRELIMINARIES (CONT'D)

    COLLECTION

    Page: SR 1/1

    Page: SR 1/2

    Total Carried To GENERAL SUMMARY :

    SR1-Prelim Page 4

  • 7/30/2019 BOQ Food Court

    5/36

    167765240.xlsx.ms_office

    AMOUNT (US$)

    0

    SR1-Prelim Page 5

  • 7/30/2019 BOQ Food Court

    6/36

    167765240.xlsx.ms_office

    AMOUNT (US$)

    By others

    0

    SR1-Prelim Page 6

  • 7/30/2019 BOQ Food Court

    7/36

    167765240.xlsx.ms_office

    AMOUNT (US$)

    0

    0

    0

    SR1-Prelim Page 7

  • 7/30/2019 BOQ Food Court

    8/36

    167765240.xlsx.ms_office

    ITEMDESCRIPTION

    QTY UNIT RATE AMOUNT (US$)

    Section NO. 2 M&E INSTALLATIONS

    GENERAL NOTES

    A The Contractor shall refer to the M&E Specification

    Documents and all relevant drawings for the full extent

    of works and pricing of this Schedule.

    Note

    B The Contractor must refer to the Fit-Out Guide for any

    Landlord's Approved/ Nominated Contractors for

    carrying out below works, where appropriate. The

    Contractor shall direct contract with these Landlord

    Contractors as his own sub-contractors and fully

    responsible for their works under this Contract. The

    Contractor shall include and price all these works under

    this Contract.

    Note

    C All other M&E sub-contractors shall be subject to thefinal approval by the Project Manager prior to

    commencement of the Works.

    Note

    D Total sum build up for each individual system shall be

    brought forward from Part 1 of Schedules under

    Appendice section of the M&E Specification. The

    Contractor shall also fill in Part 2 - Sectional Costs and

    Part 3 - Schedule of Unit Rates.

    Note

    E The Contractor is required to complete the Schedule of

    Delivery Period and Proposed Manufacturers for Major

    Equipment/ Materials as attached in Part 4 of Schedules

    under Appendice section of the M&E Specification.

    Note

    F Please note that Supply ONLY of all light fixtures toCeiling and BOH/ Stock/ Office areas shall be priced

    under Schedule No. 6 - Supply of Light Fixtures.

    Note

    G Please note that Supply and Install of all light fixtures

    and M&E Installations to External and Internal Shop

    Front Faade System are carried out by others and not

    forming part of this Contract.

    Note

    1 M&E INSTALLATIONS

    1.1 Electrical Services Installations Sum

    1.1.1 Take down and remove all existing installations that are

    not required for the works. (If applicable)

    lot

    1.1.2 Supply and installation of L.V. distribution system from

    landlord switch room to retail shop, including:

    lot -

    - 200 main distribution system.

    - Trunking, cable tray, conduit and accessories for

    - Main distribution MCCB board and MCCB units.

    - Main cable from Landlord switch room to the shop:

    a Switch 200A TPN pcs

    b Main distribution board DB-M panel- MCCB 200A TPN pcs- MCCB 80A TPN pcs- MCCB 63A TPN pcs

    - 6 way MCCB board & Accessories lot

    c 4x120 sqmm 1/c PVC Cu Cable + E m

    Bill of Quantities

    SR2-M&E Installations Page 8

  • 7/30/2019 BOQ Food Court

    9/36

    167765240.xlsx.ms_office

    ITEMDESCRIPTION

    QTY UNIT RATE AMOUNT (US$)

    Bill of Quantities

    d Trunking 100x100x1.5 mm m

    e Hanger, Support & Accessories lot

    Carried to Collection : -

    SCHEDULE NO. 2 M&E INSTALLATIONS (CONT'D)

    Electrical Services Installations (cont'd)

    1.1.3 Supply and installation of LV distribution system for lot -- Main distribution system.

    - Trunking, cable tray, conduit and accessories for

    - Main distribution MCCB board and MCCB units.

    - Emergency cut-off power control system.

    a Distribution board DB-1L panel- MCCB 80A TPN pcs

    - MCB 10A SP pcs- Contactor 3P-16A pcs

    - Timer 24h pcs

    - Switch & Button lot- 16 way MCCB board & Accessories lot

    b Distribution board DB-1P panel- MCCB 63A TPN pcs

    - MCB 16A SP pcs- MCB 20A SP pcs- RCB 20A DP pcs- MCB 16A TP lot

    - 12 way MCCB board & Accessories lot

    c Distribution board DB-2L panel- MCCB 63A TPN pcs

    - MCB 10A SP pcs- Contactor 3P-16A pcs

    - Timer 24h pcs- Switch & Button lot

    - 12 way MCCB board & Accessories lotd Distribution board DB-2P panel

    - MCCB 63A TPN pcs

    - MCB 16A SP pcs

    - MCB 20A SP pcs

    - RCB 20A DP pcs

    - MCB 16A TP lot

    - 12 way MCCB board & Accessories lot

    e 4x35 sqmm 1/c PVC Cu Cable + E m

    f 4x25 sqmm 1/c PVC Cu Cable + E m

    g Trunking 100x100x1.5 mm m

    h Hanger, Support & Accessories lot

    1.1.4 Supply and installation of final circuit power installation

    for retail shop, including:lot -

    - MCB boards and accessories.

    - Trunking and accessories.

    - Cable, conduit and accessories.

    - Socket outlets.

    - Connection units.

    - Power point as specified on the drawings:

    13A 1 gang flush mounted switch socket outlet nos13A 1 gang flush mounted switch socket outlet nos13A 2 gang flush mounted switch socket outlet nos13A 2 gang flush mounted switch socket outlet nos

    13A 1 gang floor mounted switch socket outlet c/w nos13A 2 gang floor mounted switch socket outlet c/w nos

    Recessed Wall / Ceiling / Flush Floor mounted nosRecessed Wall / Ceiling / Flush Floor mounted nos

    SR2-M&E Installations Page 9

  • 7/30/2019 BOQ Food Court

    10/36

    167765240.xlsx.ms_office

    ITEMDESCRIPTION

    QTY UNIT RATE AMOUNT (US$)

    Bill of Quantities

    Junction Box for Showcase Light Switch nos

    Carried to Collection : -

    SCHEDULE NO. 2 M&E INSTALLATIONS (CONT'D)

    Electrical Services Installations (cont'd)

    1.1.4 Supply and installation of final circuit power installation

    for retail shop, including:lot Incl.

    13A switched fused connection unit with DP switch nosFused connection unit with DP switch and Pilot lamp nos

    20A Double Pole Switch nos16A TPN Isolator nos

    GI Conduit D25 mCu/PVC (1x4.0) sqmm m

    Cu/XLPE/PVC (5x4.0) sqmm mAccessories lot

    1.1.5 Supply and installation of final circuit lighting installation

    for retail shop, including:

    lot -

    - Switches. -

    - Lighting points for all lighting fittings as shown on nos -

    - Timer and contactors.

    - Trunking, cable, conduit and accessories:Lighting Switch pcs

    Trunking 100x100x1.5 mm mGI Conduit D25 m

    Cu/PVC (1x2.5) sqmm mAccessories lot

    1.1.6 Supply and installation of final circuit lighting installation

    for internal facade, including:lot -

    - Switches. -- Lighting points for all lighting fittings as shown on nos -

    - Timer and contactors.

    - Trunking, cable, conduit and accessories:

    Lighting Switch pcsTrunking 100x100x1.5 mm m

    GI Conduit D25 mCu/PVC (1x2.5) sqmm m

    Accessories lot

    1.1.7 Installation of all light fittings for retail shop, either

    supplied by the Client or the Contractor, including

    wiring, conduit / trunking, switch points and battery pack

    for light fittings of emergency purpose.

    set -

    1.1.8 Supply and installation of trunking and conduit

    installation for extra low voltage systems, such as A/V

    system, computer system, POS system and telephone

    system:

    lot -

    - Recessed Speaker Point nos- Video Outlet Conduit Point nos- Data & Tel Conduit Point nos- Trunking 100x100 mm m- GI Conduit D25 m- Accessories lot

    SR2-M&E Installations Page 10

  • 7/30/2019 BOQ Food Court

    11/36

    167765240.xlsx.ms_office

    ITEMDESCRIPTION

    QTY UNIT RATE AMOUNT (US$)

    Bill of Quantities

    Carried to Collection : -

    SCHEDULE NO. 2 M&E INSTALLATIONS (CONT'D)

    Electrical Services Installations (cont'd)

    1.1.9 Supply and installation of trunking and conduit

    installation for security system. Conduit and power point

    shall be allowed as follows.

    lot -

    - 50 conduit points

    - 20 power points

    Dome type colour camera with wide angle lens point nosAlarm Key Pad Point nos

    Door Lock Point nosSecurity Motion Detector Point nos

    Traffic People Counter Point nosGI Conduit D25 m

    Accessories lot

    1.1.10 Supply and installation of the earthing protection

    including protective conductor for the low voltage

    distr ibut ion system and equipotential bonding to all

    extraneous conductive parts in the site area.

    lot -

    1.1.11 Supply and installation of all fluorescent fittings, with

    necessary ballast and all light box. (T5 type)

    set -

    1.1.12Supply and installation of lighting dimming panel

    lot -

    - Dimming Panel - Lutron GRX-3504-T-AU-WH set- 8 button control panel - EGRX-8S-WH set

    - 2 button control panel - EGRX-2B-SL-WH set- GRX-TVI pcs

    1.1.13Provision of miscellaneous items such as

    lot -

    - Testing and commissioning

    - Liaison and applications for approval to utility

    - Provision of completion certificates to suit the

    - Instructing employers staff,

    - Provision of Operating and Maintenance manuals,

    - Maintenance during the Defects Liability Period,

    - As-fitted drawings,

    - Painting and labelling,

    - any other incidentals not specifically listed and which

    1.1.14Other items if any (to be stated by Tenderer)

    lot NA

    SR2-M&E Installations Page 11

  • 7/30/2019 BOQ Food Court

    12/36

    167765240.xlsx.ms_office

    ITEMDESCRIPTION

    QTY UNIT RATE AMOUNT (US$)

    Bill of Quantities

    Carried to Collection : -

    SCHEDULE NO. 2 M&E INSTALLATIONS (CONT'D)

    1.2 Fire Services Installations Sum

    1.2.1 Alteration and addition to the existing sprinkler system

    for retail shop, including supply and installation of

    sprinklers, pipeworks and all necessary fittings.

    lot -

    - Galvanized mild steel pipe f40 m- Galvanized mild steel pipe f32 m- Pipe fittings lot- Sprinkler head

    - Supply & installation

    Concealed type, 68oC, K8.0 nosStainless steel conceal type, 68oC, K8.0 nos

    - Relocation

    Concealed type

    - Hanger, support lot- Testing lot- Accessiries lot

    1.2.2 lteration and addition to the existing automatic and

    manual fire alarm system for retail shop, including

    supply and installation of alarm bells, smoke detectors,

    extended indicating lights, conduits, wir ings and all

    necessary accessories.

    lot -

    Smoke Detector nosFire Alarm Panel 4 zones nos

    Alarm belts nosStrobe light nos

    Fire alarm manual call point nos2x1.5 mm2 FR Cu/PVC mGI Conduit DN 25 mFlexible GI Conduit DN 20 m

    Accessories lotT&C lot

    1.2.3 Supply and installation of all electr ical works for fire

    services systems including conduit, trunking, wiring and

    all necessary equipment.

    lot -

    Galvanized mild steel pipe f50 mPIpe fitting lotFire hose reel box 1000x600 set

    Angle valve DN 50 setHose reel 30m , DN 50 setNozzle DN 50 setHanger support lot

    Accessiries lotTesting lot

    1.2.4 Supply and installation of portable fire extinguishers c/w

    mounting bracket.

    lot -

    Powder Fire Extinguisher ABC 4 kg nosCo2 Fire Extinguisher 4kg nos

    SR2-M&E Installations Page 12

  • 7/30/2019 BOQ Food Court

    13/36

    167765240.xlsx.ms_office

    ITEMDESCRIPTION

    QTY UNIT RATE AMOUNT (US$)

    Bill of Quantities

    Carried to Collection : -

    SCHEDULE NO. 2 M&E INSTALLATIONS (CONT'D)

    Fire Services Installations (cont'd)

    1.2.5 Provision of miscellaneous items such as: lot -- Testing and commissioning

    - Liaison and applications for approval to utility

    companies, regulatory and licensing authorities,

    - Provision of completion certificates to suit the

    requirements of utility companies, regulatory and

    licensing authorities,

    - Instructing employers staff,

    - Provision of Operating and Maintenance manuals,

    - Maintenance during the Defects Liability Period,

    - As-fitted drawings,- Painting and labelling,

    - any other incidentals not specifically listed and which

    may be required for the completion of the whole works.

    -

    SR2-M&E Installations Page 13

  • 7/30/2019 BOQ Food Court

    14/36

    167765240.xlsx.ms_office

    ITEMDESCRIPTION

    QTY UNIT RATE AMOUNT (US$)

    Bill of Quantities

    Carried to Collection : -

    SCHEDULE NO. 2 M&E INSTALLATIONS (CONT'D)

    1.3 MVAC Services Installations Sum -

    1.3.1 Dismantle, and modify the existing A/C supply system to

    suit the interior decoration.

    lot - -

    1.3.2 Supply and installation of electrical and control system

    for the shop including main switchboard, motor control

    panels, and control devices and necessary accessories,

    conduit and wiring, etc.

    lot -

    Duct type temperrature sensor nosProbe type smoke detector nosDifferential Presure switch nos

    HVAC control panel setDisplay Panel setVSD 3 KW nosVSD 1.5 KW nosChilled water meter flow rate setCu/PVC/PVC 3x4mm3+1x2.5mm2 mCu/PVC/PVC 2x2.5mm3+1x2.5mm2 mCu/PVC 1x1.5mm2 mSielded Cu/PVC/PVC 2x1.5mm2 mConduit GI D20 mConduit GI D25 mTrunking 100x50x1.5 mm m

    Accessories lot

    1.3.3 Supply and installation of air conditioning and fresh air

    duct work system including insulation, dampers, airgrilles and all necessary fittings.

    lot -

    Duct 0,8mm m2Fiber glass insulation 32kg/m3, 25mm m3

    Attennuator nosVCD 200 nosFlexible canvas connector nosFlexible duct cw insulation 200 m

    Air distribution device

    * Plenum box for with 50(H) & 40(H) outlet nos* 100(W) Al. linear air diffuser w/30 deflection nosHanger and support lot

    Accessories lot

    1.3.4 Supply and installation of AHUs and exhaust air fan lot -Air Handling Unit

    - 2000l/s nos- 1500l/s nosExhaust air fan, ceiling mounted type, 15L/s pcsHanger, support lot

    Antivibrator lotSUS mainternance platform lot

    Accessories lot

    SR2-M&E Installations Page 14

  • 7/30/2019 BOQ Food Court

    15/36

    167765240.xlsx.ms_office

    ITEMDESCRIPTION

    QTY UNIT RATE AMOUNT (US$)

    Bill of Quantities

    Carried to Collection : -

    SCHEDULE NO. 2 M&E INSTALLATIONS (CONT'D)

    MVAC Services Installations (cont'd)

    1.3.5 Supply and installation of chilled water pipes and

    condensate drain pipe system including gate valves,

    insulation and all necessary fittings.

    lot -

    Chilled water pipe c/w insulation PU 50 mm

    * 40 mm m* 50 mm m* 65 mm m* 80 mm mCondensation drain pipe c/w insulation 25mm

    * 32 mm m

    * 40mm m* 50mm mPipe fitting lotGate valve

    * 40 mm nos* 50 mm nos* 65 mm nos* 80 mm nos

    Auto Air Vent

    * 20 mm nosStrainers

    * 40 mm nos* 50 mm nosTwo- way on/off control valve actuator

    * 25mm nosTwo- way modulating control valve with actuator

    * 40 mm nos* 50 mm nosBalancing valve with commissioning set

    * 40 mm nos* 50 mm nosFlexible joint

    * 25 mm nos* 40 mm nos* 50 mm nosDrain cock nosTemperature gauge nosPressure gauge nosSecondary drain pan nosHanger and support lot

    Accessories lot

    1.3.6 Provision of miscellaneous items such as: lot -

    - Testing and commissioning

    - Liaison and applications for approval to utility

    companies, regulatory and licensing authorities,

    - Provision of completion certificates to suit the

    requirements of utility companies, regulatory and

    licensing authorities,

    - Instructing employers staff,

    - Provision of Operating and Maintenance manuals,

    - Maintenance during the Defects Liability Period,

    - As-fitted drawings,

    - Painting and labelling,

    SR2-M&E Installations Page 15

  • 7/30/2019 BOQ Food Court

    16/36

    167765240.xlsx.ms_office

    ITEMDESCRIPTION

    QTY UNIT RATE AMOUNT (US$)

    Bill of Quantities

    - any other incidentals not specifically listed and which

    may be required for the completion of the whole works.

    Carried to Collection : -

    SCHEDULE NO. 2 M&E INSTALLATIONS (CONT'D)

    MVAC Services Installations (cont'd)

    1.3.7 Other items if any (to be stated by Tenderer) lot -Chilled water pipe c/w insulation PU 50 mm

    * 80 mm m

    1.4 Audio Visual System Installation

    Allowance for supply and install new AV System:-

    a) DVD player No. -

    b) Conceal ceiling speaker No. -

    c) Multi -Channel Power Amplifier No. -

    d) Equalizer No. -

    e) Samsung 40 OUTn-UD, LCD (RTW) c/w brackets. No. -

    f) Samsung ME 40B, LED Screen (Staircase Screen &

    Screen Vitrine) c/w Wall mount bracket

    No. -

    g) Magic Info Video wall (Software for LED Video wall) Lot -

    h) Testing and commissioning of AV system Sum -

    1.5 Security System Installation

    a) Allowance for supply and install new Security System - - By Other

    2 BUILDER'S WORKS IN CONNECTION WITH M&E

    INSTALLATIONS

    2.1 Allowance for all builder's works in connection with M&EServices installations Sum

    SR2-M&E Installations Page 16

  • 7/30/2019 BOQ Food Court

    17/36

    167765240.xlsx.ms_office

    ITEMDESCRIPTION

    QTY UNIT RATE AMOUNT (US$)

    Bill of Quantities

    Carried to Collection : -

    SCHEDULE NO.2 M&E INSTALLATIONS (CONT'D)

    COLLECTION

    Page: SR 2/1 -

    Page: SR 2/2 -

    Page: SR 2/3 -

    Page: SR 2/4 -

    Page: SR 2/5 -

    Page: SR 2/6 -

    Page: SR 2/7 -

    Page: SR 2/8 -

    Page: SR 2/9 -

    Total Carried To GENERAL SUMMARY : -

    SR2-M&E Installations Page 17

  • 7/30/2019 BOQ Food Court

    18/36

    167765240.xlsx.ms_office

    Bill of Quantities

    ITEM DESCRIPTION QTY UNIT RATE AMOUNT (US$)

    Section NO. 3 SEATINGS AREAS

    GENERAL NOTES

    A This Section is for the fit-out works to Seating

    Areas Only. Sub-Tenant Kiosks and Back of House/

    Stock/ Office areas shall be priced under Schedule

    No.4 and 5 respectively.

    Note

    B The Contractor shall allow for design calculation duly

    endorsed by Registered Engineer and submit to the

    Project Manager where appropriate.

    Note

    C The Contractor must liaise and co-ordinate closely with

    all Employer's/ Landlord's Direct Contractors for

    necessary staging and programme of the fit out works.

    Note

    1 MODIFICATION AND ALTERATION WORKS TO

    1.1 Allowance for calculation and safe loading check on

    base building slab for Safe Installation

    1 Sum

    1.2 Allowance for installation of Safe 1 Sum

    (Safe to be supplied by others)

    2 FLOORING

    2.1 Preparation of floor level and apply floor screeding to

    receive new floor finishes

    530 m2

    2.2To supply and install 900x150mm White Horse Tile

    (HD95014)

    583 m2

    2.3 To supply and install 5mm stainless steel inlay 166.9 ml

    3 WALL AND PARTITIONS

    3.1 Make good existing brick wall to receive new wall

    finishes

    318.1 m2

    3.2 Supply and install timber structure backing to receive

    Groove Line Panel

    83.4 m2

    3.3 Supply and install 200x100mm HT. selected metal in

    powdered coat finishing (Color to be selected) to

    receive existing glass wall by owner

    50.8 ml

    3.2 Wall Finishing3.2.1 Supply and install Groove Line Panel as specified 83.4 m2

    3.2.2 Selected 1/P paint finish 183.2 m2

    3.2.3 Bare brick wall in lacquor finish 96.7 m2

    3.2.4 Supply and install 150mm stainless steel skirting in hair-

    line finish

    139.5 ml

    3.2.5 Supply and install selected black sticker 3.2 m2

    SR3-Seatings Page 18

  • 7/30/2019 BOQ Food Court

    19/36

    167765240.xlsx.ms_office

    Bill of Quantities

    ITEM DESCRIPTION QTY UNIT RATE AMOUNT (US$)

    SECTION NO. 3 SEATINGS AREA (CONT'D)

    3.2.6 Supply and install selected sticker with cut-out lettering 7 sets

    4 CEILING

    4.1 Exposed ceiling in selected spray paint finish 530 m2

    4.2 To supply and install plaster ceiling at 3500mm in

    selected paint finish

    756.6 m2

    4.3 Provide labor to install recess light coves 1 sum

    4.4 To supply and install hollow steel support structure for

    recessed light coves

    141.4 ml

    4.5 To supply and install 8mm metal rods support forlightings

    TBC ml

    4.6 Allowance for access panel, forming openings for M&E

    services etc.

    1 Sum

    5 HAND RAILS

    5.1 To supply and install stainless steel hand rail frame in

    hair-line finishing

    25.5 ml

    5.2 To supply and install 850x850x12mm thk tempered

    glass (incl. aluminium U channel to receive glass)

    12 pcs

    6 PLAYGROUND

    6.1 Playground mats by specialist

    SECTION NO. 3 SEATINGS AREA (CONT'D)COLLECTION

    Page: SR 3/1 #REF!

    Page: SR 3/2 -

    Total Carried To GENERAL SUMMARY : #REF!

    SR3-Seatings Page 19

  • 7/30/2019 BOQ Food Court

    20/36

    167765240.xlsx.ms_office

    Bill of Quantities

    ITEM DESCRIPTIONQTY UNIT RATE AMOUNT (US$)

    SCHEDULE NO. 4 KIOSK AREA

    GENERAL NOTES

    A This Schedule is for the fit-out works to Kiosk Area

    Only. Seatings Area and Back of House/ Stock/

    Office areas shall be priced under Schedule No. 3

    and 6 respectively.

    Note

    B The Contractor shall allow for design calculation duly

    endorsed by Registered Engineer and submit to the

    Project Manager where appropriate.

    Note

    C The Contractor must liaise and co-ordinate closely with

    all Employer's/ Landlord's Direct Contractors for

    necessary staging and programme of the fit out works.

    Note

    1 MODIFICATION AND ALTERATION WORKS TO

    1.1 Allowance for calculation and safe loading check on

    base building slab for Safe Installation

    1 Sum

    1.2 Allowance for installation of Safe 1 Sum

    (Safe to be supplied by others)

    2 FLOORING

    2.1 Preparation of floor level and apply floor screeding to

    receive new floor finishes

    322.3 m2

    2.2 Supply and apply 3 layers water proof in wet works area 136.9 m2

    2.3To supply and install 300mm SQ Ceramics Tiles

    Seasera 20A rough surface

    354 m2

    2.4 To supply and install 5mm stainless steel inlay 65.6 ml

    3 WALLS AND PARTITIONS

    3.1 Make good existing brick wall to receive new wall

    finishes

    358.7 m2

    3.2Supply and install timber structure backing to receive

    Groove Line Panel

    69.9 m2

    3.2 To supply and build:3.2.1 Full height brick wall (4000mm) 267.5 m2 -

    3.2.2 1200mm height brick wall 61.8 m2

    3.2.3 RC Kerb

    3.3 To supply and install3.3.1 1200x12mm thick clear glass 28.3 m2

    3.3.2 300x12mm thick clear glass 6.3 m2

    3.3.3 Support system to hold signage 7 set

    SR4-Kiosks Page 20

  • 7/30/2019 BOQ Food Court

    21/36

    167765240.xlsx.ms_office

    Bill of Quantities

    ITEM DESCRIPTIONQTY UNIT RATE AMOUNT (US$)

    3.4 Wall Finishing3.4.1 To supply and install 300x300 selected Ceramic wall tile 781.3 m2

    3.4.2 Supply and install Groove Line Panel as specified 69.9 m2

    3.4.3 Selected spray paint finish 93.2 m2

    3.4.4 Selected tile finish (1/T) 1.8 m2

    3.4.5Supply and install 150mm stainless steel skirting in hair-

    line finish

    23.3 ml

    4 CEILING

    4.1 Exposed ceiling in selected spray paint finish 82.11 m2

    4.2 2'x4' HCCP Ceiling at 2700mm 182.9 m2

    4.3 Allowance for access panel, forming openings for M&Eservices etc.

    1 Sum

    4.4To supply and install 8mm metal rods support for

    lightings

    TBC ml

    5 FRONT COUNTER

    DETAILS MISSING

    Carried to Collection : -

    SECTION NO. 4 KIOSK AREA (CONT'D)

    7 DOORS

    Supply and Install the following doors including finishes,

    ironmongeries, fittings and accessories as specified:-

    DETAILS MISSING 9 sets

    Carried to Collection : #REF!

    SECTION NO. 4 KIOSK AREA (CONT'D)

    COLLECTION

    Page: SR 4/1 -

    Page: SR 4/2 #REF!

    Page: SR 4/3 #REF!

    Page: SR 4/4 #REF!

    Page: SR 4/5 #REF!

    SR4-Kiosks Page 21

  • 7/30/2019 BOQ Food Court

    22/36

    167765240.xlsx.ms_office

    Bill of Quantities

    ITEM DESCRIPTIONQTY UNIT RATE AMOUNT (US$)

    Total Carried To GENERAL SUMMARY : #REF!

    SR4-Kiosks Page 22

  • 7/30/2019 BOQ Food Court

    23/36

    167765240.xlsx.ms_office

    Bill of Quantities

    ITEM DESCRIPTIONQTY

    UNITRATE AMOUNT (US$)

    SECTION NO. 5 BACK OF HOUSE AREA

    GENERAL NOTES

    A This Schedule is for the fit-out works to Back of

    House/Service Corridor and Common Area only.

    Note

    B The Contractor shall allow for design calculation duly

    endorsed by Registered Engineer and submit to the

    Project Manager where appropriate.

    Note

    C The Contractor must liaise and co-ordinate closely with

    all Employer's/ Landlord's Direct Contractors for

    necessary staging and programme of the fit out works.

    Note

    1 FLOOR FINISHES

    1.1 Preparation of floor level and apply floor screeding to

    receive new floor finishes

    252.5 m2 0

    1.2 To supply and install 300mm SQ Ceramics Tiles

    Seasera 20A rough surface

    74.2 m2

    1.3 To supply and install Cemkrete S-Crete HF MF Light

    Grey

    179.3 m2

    1.4 To supply and install 5mm stainless steel inlay 15.4 ml

    2 WALL AND PARTITION

    2.1 Make good existing brick wall to receive new wall

    finishes

    318.5 m2 0

    2.2 Supply and build full height brick wall (4000mm) 53.4 m2

    2.3 Wall Finishing

    2.3.1 Selected 1/P paint Finish 45.2 m2

    2.3.3 To supply and install 300x300 selected Ceramic wall tile 134.3 m2

    2.3.4 Bare brick wall in lacquor finish 123.3 m2

    2.3.5 Supply and install 150mm stainless steel skirting in hair-

    line finish

    45.2 ml

    3 CEILING

    3.1 Exposed ceiling in selected spray paint finish 535.2 m2 0

    3.2 To supply and install 8mm metal rods support for

    lightings

    TBC ml #VALUE!

    4 DOORS

    4.1 DETAILS MISSING 3 set

    SR5-BOH Page 23

  • 7/30/2019 BOQ Food Court

    24/36

    167765240.xlsx.ms_office

    Bill of Quantities

    ITEM DESCRIPTIONQTY

    UNITRATE AMOUNT (US$)

    Carried to Collection : 0

    SCHEDULE NO. 5 BACK OF HOUSE AREA (G/F & B/F) (CONT'D)

    COLLECTION

    Page: SR 5/1 #REF!

    Page: SR 5/2 0

    Total Carried To GENERAL SUMMARY : #REF!

    SR5-BOH Page 24

  • 7/30/2019 BOQ Food Court

    25/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEMDESCRIPTION

    QTYUNIT

    RATE AMOUNT (HK$)

    SECTION NO. 6 PELMET AND COLUMNS

    GENERAL NOTES

    A The Contractor shall refer to all relevant Drawings &

    Specification for the standard of quality, workmanship

    and pricing the Faade Works.

    Note

    B All proposed faade contractors shall be subject to the

    final approval by the Project Manager prior to the

    commencement of the Works.

    Note

    C The Contractor is required to refer to the Specification

    Preliminaries of the Tender Documents for all

    Guarantee/ Warranty requirements for the Faade

    Works.

    Note

    D The Contractor shall allow for all FRP provisions and

    associated Landlord's requirements applicable to the

    Works.

    Note

    E The Contractor shall allow for design calculation duly

    endorsed by Registered Engineer and submit to the

    Project Manager where appropriate.

    Note

    F The Contractor must liaise and co-ordinate closely with

    all Employer's/ Landlord's Direct Contractors for

    necessary staging and programme of the Faade

    Works.

    Note

    1 FAADE PELMET

    1.1 Entrance Pelmet

    1.1.1 To supply and install 40x40mm steel hollow sections for

    reinforcement to concrete slab

    21 ml -

    1.1.2 To supply and install 275x45x5mm 'U' profile in selected

    metal (4/MF) to receive 20mm thk glass

    6.2 m2

    1.1.3 To supply and install 12mm MDF backing to receive

    20mm thk glass

    4.1 m2

    1.1.4 To supply and install 20mm thk clear tempered glass 9.6 m2

    1.2 Kiosk and Seatings Area Pelmet

    1.2.1 Hol low Sect ion Pelmet

    1.2.1a Supply and install 40x40mm selected metal hollow

    section in powder coat finish (Color to be selected) to

    form pelmet structure as specified

    398.4 ml

    1.2.1b Supply and install 10mm thk. metal plates in powder

    coat finish

    11.1 m2

    1.2.1c Supply and install 6mm thk mirror (3/G) 8.2 m2

    1.2.1d Supply and install 12mm thk clear glass (1/G) 10.7 m2

    1.2.2 Timber Str ips Pelmet

    SR6-Pelmet and Columns Page 25

  • 7/30/2019 BOQ Food Court

    26/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEMDESCRIPTION

    QTYUNIT

    RATE AMOUNT (HK$)

    1.2.2a Supply and install 8mm metal rods support to hang

    pelmet system

    18 m

    1.2.2b Supply and install 150x50mm Timber Strips in Lacquor

    finish

    101.3 ml

    1.2.2c Supply and install 50x25mm Timber Strips in Lacquor

    finish

    20.2 ml

    1.2.2d Supply and install Decorative nuts & bolts 1 lot

    1.2.3 Metal Str ips Pelmet

    1.2.3a Supply and install 18mm thk MDF backing, reinforced

    by 50x100mm steel hollow section dropped down from

    concrete slab @ 500mm/each

    107.3 m2

    1.2.3b Supply and install 1600x150x30mm thk Decorative

    Metal Strips in powder coat finish (Color to be selected)

    105.7 m2

    Carried to Collection : -

    SECTION NO. 6 PELMET AND COLUMNS (CONT'D)

    2 COLUMNS

    2.1 To supply and install metal stud Box-Up with 9mm

    Gypsum Board in selected white Jotun paint finish (2/P)

    111.9 m2

    2.2 To supply and install 90x180mm timber strips to receive

    selected LED light finish and metal strips

    38.2 ml

    2.3 To supply and install 300x9mm thk selected metal strips

    (3/MF) in Chrome finish

    38.7 ml

    2.4 To supply and install 150x5mm stainless steel in hair-

    line finish. C/w MDF backing.

    30.8 ml

    2.5 To supply and install timber backing to receive Photo

    Frame by others

    1 Sum

    3 SIGNAGE

    3.1 To supply and install 350mm HT. cut-out lettering in

    Clear Acrylic finish (1/AC). C/w 8mm metal rods support

    1 set

    3.2 To supply and install 350mm HT. x 50mm THK.

    stainless steel Signage Frame in hair-line finish, with cut

    out lettering. C/w Clear Acrylic backing and LED

    lightings. (For 20mm thk glass pelmet)

    1 set

    SR6-Pelmet and Columns Page 26

  • 7/30/2019 BOQ Food Court

    27/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEMDESCRIPTION

    QTYUNIT

    RATE AMOUNT (HK$)

    Carried to Collection : -

    SCHEDULE NO. 7 SHOP FRONT FAADE SYSTEM (CONT'D)

    COLLECTION

    Page: SR 7/1 -

    Page: SR 7/2 #REF!

    Page: SR 7/2 -

    SR6-Pelmet and Columns Page 27

  • 7/30/2019 BOQ Food Court

    28/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEMDESCRIPTION

    QTYUNIT

    RATE AMOUNT (HK$)

    Total Carried To GENERAL SUMMARY: #REF!

    SR6-Pelmet and Columns Page 28

  • 7/30/2019 BOQ Food Court

    29/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEM DESCRIPTION QTY UNIT RATE AMOUNT (US$)

    SECTION NO. 6 SUPPLY OF LIGHT FIXTURES

    GENERAL NOTES

    A Unless otherwise stated, the Contractor shall price theinstallation ONLY of light fixtures under Schedule No. 3 - M&E

    Installations, Schedule No. 3 - Retail Area (1/F), Schedule No. 4 -

    Retail Area (2/F) and Schedule No. 5 - Back of House Area

    respectively.

    Note

    B Reference shall be made to the M&E Specification Documents and all

    relevant drawings for the specification of light fixtures and its

    requirement.

    Note

    C The Contractor shall refer to the Approved Quotation given by the

    Employer and inserted under Specification Section for pricing the

    supply of specified light fixtures. All quantities in the quotation are for

    reference ONLY and it is the sole responsibility for the Contractor to

    check and verify the quantities according to the drawings and

    specification requirements in the tender.

    Note

    The Contractor is deemed to include due allowance in the Contract

    Sum for all the exclusion items & qualification offered in these

    quotations by respective nominated suppliers. No adjustment to the

    Contract Sum is allowed resulting from his ignorance of this

    requirement.

    Note

    D When pricing the supply of light fixtures, the "supply rates" shall,

    unless otherwise excluded in the Approved Quotation, include cost of

    packing, carriage and delivery to Site, contractor's warehouse or

    factory, where further production is required. The Contractor shall

    allow all other costs for installation under Schedule No. 3, 4, 5 & 6

    respectively.

    Note

    E Supply and installation of light fixtures for External and InternalShop Front Faade (including Light Boxes, Window Displays

    and Backlit Logo) are carried out by others and not forming part

    of this Contract.

    Note

    1 Supply and install the following light fixtures including all

    necessary bulbs, transformers, accessories and spares as

    specified (Unless otherwise supplied direct by the Employer) :-

    1.1 Light Fixtures to CEILING (1F & 2F)

    a) C3 Halogen lights for ceiling to all BOH/ Stock/ Office areas Set 0

    Carried to Collection : 0

    SR6 Li ht Fi t P 29

  • 7/30/2019 BOQ Food Court

    30/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEM DESCRIPTION QTY UNIT RATE AMOUNT (US$)

    SCHEDULE NO. 6 SUPPLY OF LIGHT FIXTURES (CONT'D)

    1 Supply and install the following light fixtures including all

    necessary bulbs, transformers, accessories and spares as

    specified (Unless otherwise supplied direct by the Employer) :-(CONT'D)

    1.2

    a)

    1.3

    a)

    2 Delivery and Handling Charges (PROVISIONAL)

    2.1 Logistic for delivery, handling and all associated expense etc. for alllight fixtures supplied by Nominated Suppliers above 1 Sum Refer to Prelim

    [Note: Warranty and maintenance for all fluorescent tube within

    Defect Liability Period and LED lights with supplier's warranty

    are deemed to be included as per Preliminaries Specification

    requirement.]

    Carried to Collection : 0

    SR6-Light Fixtures Page 30

  • 7/30/2019 BOQ Food Court

    31/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEM DESCRIPTION QTY UNIT RATE AMOUNT (US$)

    SCHEDULE NO. 6 SUPPLY OF LIGHT FIXTURES (CONT'D)

    COLLECTION

    Page: SR 6/1 0

    Page: SR 6/2 0

    Total Carried To GENERAL SUMMARY : 0

    SR6-Light Fixtures Page 31

  • 7/30/2019 BOQ Food Court

    32/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEM DESCRIPTION QTY UNIT RATE AMOUNT (US$)

    SCHEDULE NO. 8 - PC SUM FOR MATERIAL SUPPLY

    1 Allowance for PC SUM for SUPPLY ONLY of the

    following materials:-

    Carried to Collection :

    SR8-PC Sum Page 32

  • 7/30/2019 BOQ Food Court

    33/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEM DESCRIPTION QTY UNIT RATE AMOUNT (US$)

    SCHEDULE NO. 8 - PC SUM FOR MATERIAL SUPPLY (CONT'D)8a

    8b

    8c

    9a

    9b

    9c

    10a

    10b

    10c

    11a

    11b

    11c

    12a

    12b

    12c

    13a

    13b

    13c

    14a

    14b

    14c

    15a

    15b

    15c

    16a

    16b

    16c

    17a

    17b

    17c

    Carried to Collection : 0.00

    SR8-PC Sum Page 33

  • 7/30/2019 BOQ Food Court

    34/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEM DESCRIPTION QTY UNIT RATE AMOUNT (US$)

    SCHEDULE NO. 8 - PC SUM FOR MATERIAL SUPPLY (CONT'D)

    18a

    18b

    18c

    19a

    19b

    19c

    20a

    20b

    20c

    21a21b

    22a

    22b

    23a

    23b

    23c

    24a

    24b

    24c

    25a

    25b

    25c

    26a

    26b

    26c

    Carried to Collection : 0.00

    SR8-PC Sum Page 34

  • 7/30/2019 BOQ Food Court

    35/36

    167765240.xlsx.ms_office

    SCHEDULE OF RATES

    ITEM DESCRIPTION QTY UNIT RATE AMOUNT (US$)

    SCHEDULE NO. 8 - PC SUM FOR MATERIAL SUPPLY (CONT'D)

    COLLECTION

    Page: SR 8/1 0

    Page: SR 8/2 0

    Page: SR 8/3 0

    Total Carried To GENERAL SUMMARY: 0

    SR8-PC Sum Page 35

  • 7/30/2019 BOQ Food Court

    36/36

    SCHEDULE OF RATES

    ITEM DESCRIPTION QTY UNIT RATE AMOUNT (US$)

    SCHEDULE NO. 8 DAYWORK SCHEDULE

    GENERAL NOTES

    A The Contractor shall submit a set of daily wages rates for the

    following types of workers:

    1 General labour (skilled) 1 Day

    2 General labour (non-skilled) 1 Day

    3 Carpenter 1 Day

    4 Plasterer 1 Day

    5 Painter 1 Day

    6 Decorator 1 Day

    7 Metal worker 1 Day

    8 Electrician 1 Day

    9 M&E worker 1 Day

    10 Plumber 1 Day