Page 1: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Board of County Commissioners

2007-1 Regular Cycle Amendments to CPP

Settlement with the Florida Department of Community Affairs

March 4, 2008

Board of County Commissioners

2007-1 Regular Cycle Amendments to CPP

Settlement with the Florida Department of Community Affairs

March 4, 2008

Page 2: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Overview of 2007-1 Regular Cycle Non-Compliance determination Stipulated Settlement Agreement Action Requested

Overview of 2007-1 Regular Cycle Non-Compliance determination Stipulated Settlement Agreement Action Requested

Presentation OutlinePresentation Outline

Page 3: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Overview of 2007-1 Regular Cycle Non-Compliance determination Stipulated Settlement Agreement Action Requested

Overview of 2007-1 Regular Cycle Non-Compliance determination Stipulated Settlement Agreement Action Requested

Presentation OutlinePresentation Outline

Page 4: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Overview of 2007-1 CycleOverview of 2007-1 Cycle

BCC transmittal hearing - February 13, 2007 ORC report received - April 27, 2007 Adoption hearing - June 26, 2007 Notice of Intent issued - August 27, 2007

BCC transmittal hearing - February 13, 2007 ORC report received - April 27, 2007 Adoption hearing - June 26, 2007 Notice of Intent issued - August 27, 2007

Page 5: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Overview of 2007-1 Regular Cycle Non-Compliance determination Stipulated Settlement Agreement Action Requested

Overview of 2007-1 Regular Cycle Non-Compliance determination Stipulated Settlement Agreement Action Requested

Presentation OutlinePresentation Outline

Page 6: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Land Use Amendments Density and intensity issues related to PD

land use designation Text Amendment to the Transportation Element

Policy 1.4.2 of the Transportation Element

Land Use Amendments Density and intensity issues related to PD

land use designation Text Amendment to the Transportation Element

Policy 1.4.2 of the Transportation Element

Non-compliance determinationNon-compliance determination

Page 7: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Overview of 2007-1 Regular Cycle Non-Compliance determination Stipulated Settlement Agreement Action Requested

Overview of 2007-1 Regular Cycle Non-Compliance determination Stipulated Settlement Agreement Action Requested

Presentation OutlinePresentation Outline

Page 8: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Creation of new policy: FLUE Policy 1.1.12.1.1 Includes densities and intensities for all PD land use amendments

Transportation Policy 1.4.2 For projects that degrade the roadway level-of-service below the

adopted level-of-service standard, development permits shall not be issued unless (1) the facility impacted is on the County’s five-year capital improvement schedule; or (2) scheduled for construction within the fourth or fifth year of the County’s 5-year capital improvements schedule, in which case the County will calculate and approve a proportionate fair share contribution based on the formula in the Orange County Code; or (3) if the facility is scheduled for completion within years 6 through 10 of the County’s 10-year roadway program, then the County at its discretion may approve a proportionate fair share contribution based on the formula in the Orange County Code.

Creation of new policy: FLUE Policy 1.1.12.1.1 Includes densities and intensities for all PD land use amendments

Transportation Policy 1.4.2 For projects that degrade the roadway level-of-service below the

adopted level-of-service standard, development permits shall not be issued unless (1) the facility impacted is on the County’s five-year capital improvement schedule; or (2) scheduled for construction within the fourth or fifth year of the County’s 5-year capital improvements schedule, in which case the County will calculate and approve a proportionate fair share contribution based on the formula in the Orange County Code; or (3) if the facility is scheduled for completion within years 6 through 10 of the County’s 10-year roadway program, then the County at its discretion may approve a proportionate fair share contribution based on the formula in the Orange County Code.

Stipulated Settlement AgreementStipulated Settlement Agreement

Page 9: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Amendment 2007-1-A-5-2 (Wedgefield) Applicant requested to withdraw amendment Necessitates change to the Stipulated

Settlement Agreement

Amendment 2007-1-A-5-2 (Wedgefield) Applicant requested to withdraw amendment Necessitates change to the Stipulated

Settlement Agreement

Stipulated Settlement AgreementStipulated Settlement Agreement

Page 10: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Overview of 2007-1 Regular Cycle Non-Compliance determination Stipulated Settlement Agreement Action Requested

Overview of 2007-1 Regular Cycle Non-Compliance determination Stipulated Settlement Agreement Action Requested

Presentation OutlinePresentation Outline

Page 11: Board of County Commissioners 2007-1 Regular Cycle Amendments to CPP Settlement with the Florida Department of Community Affairs March 4, 2008 Board of

Approve Stipulated Settlement Agreement

Approve Amendment to the Stipulated Settlement Agreement

Adopt Ordinance

Approve Stipulated Settlement Agreement

Approve Amendment to the Stipulated Settlement Agreement

Adopt Ordinance

Requested ActionRequested Action