    BishopsgateGoods Yard

    Development Brief

    DPU_BUDD_2010_BU1

  • 8/3/2019 Bishops Gate Report

    2/76

  • 8/3/2019 Bishops Gate Report

    3/76

    01

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    1.0_Introduction1.1_Terms of Reference

    1.2_Setting out the physical and socio-economic context1.3_Summary of policy and planning framework

    2.0_Area Analysis2.1_Urban Design Characteristics

    2.2_Constraints and Opportunities

    3.0_Objectives, vision and design principles3.1_Vision

    3.2_Objectives

    3.3_Design Principles

    4.0_Detailed development strategy: Identication of development sites4.0_Identication of Development Site

    4.1_Urban Structure

    4.2_Access

    4.3_Public Realm

    5.0_Phasing5.1_Phasing Plan

    5.2_Cost Analysis

    6.0_Conclusions

  • 8/3/2019 Bishops Gate Report

    4/76

  • 8/3/2019 Bishops Gate Report

    5/76

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    1.0Introduction

  • 8/3/2019 Bishops Gate Report

    6/76

    04

    London has remnants and fragments of a rich

    historical past which has helped to build a grandmegalopolis. Today London has its place as a

    global city. Mixing the old with new, London has

    a peculiar character where people from every part

    of the world, race, ethnicity and age group, nd a

    place and identify themselves from it.

    This Development Brief has been formulated for

    the Bishopsgate Goods Yard (BGY) site which

    is within both boroughs of Tower Hamlets and

    Hackney and bordering the City of London. Bish-

    opsgate Goods Yard was used as a logistics node

    until 1964 and has been lying disused awaiting theconstruction of the East London Line (ELL) exten-

    sion. The linear form of the site along with the rail-

    way lines acts as a dividing line running east-west.

    Over the years, adjoining areas have turned their

    back on the goods yard leading to a number of

    derelict sites.

    London Olympics 2012 and the ELL has brought

    a much needed attention and connectivity to the

    area. In response to raising interest in the local ar-

    eas within the real estate market, the council has

    developed the Bishopsgate Planning Guidance,which aggressively targets integrating the goods

    yard into the mainstream. This Brief positions it-

    self as both a critical assessment of the Planning

    Guidance and an alternative vision.

    This Brief is informed by a previous stage of Urban

    Analysis dealing with aspects related to Accessi-

    bility, Building Typology, Urban Grain, Open Spac-

    es, Density and the Socio-economic context. It

    also looked at the site within the broader context

    of London.

    The report is primarily divided into two sections.

    The rst section builds on the previous stage work

    and outlines the vision, objectives and design

    principles of the Brief. The second section deals

    with guidelines for Urban Structure, Access and

    Public Realm, with a the Phasing Plan for each

    and concluding remarks.

  • 8/3/2019 Bishops Gate Report

    7/76

    05

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    The Terms of Reference of this Brief are dened

    as follows:

    1. To draw upon the ndings of the Urban Analysis

    stage to inform strategic objectives, vision and de-

    sign principles for the site, simultaneously identify-

    ing areas of intervention and acupuncture.

    2. To identify and prioritize characteristics within

    the site and study area with the theme of crime

    prevention as outlined by ODPM.

    3. To develop guidelines based on the elementsof Urban Structure, Access and Public Realm in-

    tegrating the urban analysis and crime prevention

    characteristics.

    4. To develop long-term strategies and short-term

    tactics for development based on the guidelines

    with key temporal considerations outlining a logi-

    cal, responsive and dynamic transformation pro-

    cess.

    5. To develop a phasing strategy that would ad-dress broader goals of the city and the site itself

    and provide a pragmatic framework that is re-

    sponsive to new stimuli.

    1.2_Setting out the physical and socio-economic context

    1.1_Terms of Reference

    Bishopsgate Goods Yard is located on the cusp

    of a number of boroughs including the LondonBorough of Tower Hamets, LB of Hackney, LB of

    Islington and the City of London. Currently, the site

    is undergoing a transformation with the construc-

    tion of the ELL and the opening of the Shoreditch

    High Street Station, opening up the area to in-

    creased transportation routes linking residential

    areas to the City. Public space in the area divided

    into hard and soft spaces with use varying not

    only from one day to the next, but also at different

    times throughout the day demonstrating the sites

    dynamic character.The socio-economic situation in the area is com-

    plex and reects sharp contrasts in density, eth-

    nicity, education and employment of its residents.

    While the BGY site has an extremely low popula-

    tion density, surrounding areas including Bethnal

    Green North and South, Spitalelds and Bangla-

    town have the cities highest. The high population

    density of the surrounding area contrasted by the

    low built density for housing must be considered

    in the planning guidance and particularly with re-

    spect to adequate housing in the area.The ethnic diversity is much greater in the site area

    compared to London and has the largest Bangla-

    deshi population in the UK. The diversity of the

    area creates a vibrant and culturally driven com-

    munity.

    The proportion of young people of working age

    (26-45) in the area accounts for almost half of the

    population. The potential for job creation, educa-

    tion and training should be realised and exploited

    when developing the site.

  • 8/3/2019 Bishops Gate Report

    8/76

    06

    Signicant London and borough planning policies

    for the development of the site are indicated in

    the table below..

    1.3_Summary of policy and planning framework

  • 8/3/2019 Bishops Gate Report

    9/76

    07

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    Headline policies that relate directly to the site in-

    clude:

    London Plan

    The site falls within an Opportunity Area: the

    capitals major reservoir of browneld land with

    signicant capacity to accommodate new hous-

    ing, commercial and other development linked to

    existing or potential improvements to public trans-

    port accessibility.(GLA, 2009)

    Hackneys South Shoreditch / City FringeArea Action Plan

    Identies the area as suitable for intensication of

    urban form and economic performance. The west-

    ern portion of the site falls within the Tall Buildings

    Opportunity Area. Other keys aspects denoted in

    the document include conservation areas to the

    west of the site and the importance of retaining

    local character. As well as ighlights a local open

    space deciency and the need for improved pe-

    destrian connectivity.

    Hackney Tall Buildings Strategy

    Identies the western portion of the site as a rec-

    ommended area for a tall buildings cluster.

    Tower Hamlets City Fringe Area Action Plan

    Recommends retaining and intensifying the cur-

    rent mixed use and character of the Brick Lane

    area, restricting heights to 4-5 oors, restricting

    set-backs and maintaining ne grain, improving

    connectivity of and access to open space and

    providing new affordable homes, including family

    homes.

    Hackney and Tower Hamlets Housing Strate-

    gies

    Identify the need for more affordable housing,

    specically for family homes (3 or more bedrooms)

    and see developments such as Bishopsgate

    Goods Yard critical to securing this growth.

    Bishopsgate Goods Yard Planning Guidelines

    Situates the site in the context of constraints, sur-

    rounding conservation areas and listed structures

    on site. Contains recommendations for: a taller

    building cluster on the west of the site reducing

    in height to the east, opportunities to build above

    the East London Line, sustainable design, pub-

    lic space including new green open space above

    the viaduct, enhanced local connectivity, a site

    integrated with the surrounding character areas,re-use of historic structures, a mix of employ-

    ment opportunities and housing types and tenure,

    healthcare and community facilities.

    It is proposed that the site could support approxi-

    mately:

    350,000 sq.m. of overall development;

    1000-2000 new homes;

    75,000 150,000 sq.m. of non residential oor

    space;

    1.8 ha of publicly accessible open space.

  • 8/3/2019 Bishops Gate Report

    10/76

  • 8/3/2019 Bishops Gate Report

    11/76

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    2.0Area Analysis

  • 8/3/2019 Bishops Gate Report

    12/76

    10

    The urban and spatial analysis of the local area

    surrounding the Bishopsgate Goods Yard site wasundertaken by six different areas of analysis:

    Socio-economic prole

    Urban grain/block structure and use/ mix

    Open Space system

    Access

    Massing/Density

    Building typology, landmarks, signicant build-

    ings and view corridors.

    Throughout this section, we summarize the nd-ings of these areas of analysis focussing on how

    they affect the particular urban characteristics (ie.

    block structure, access, public realm) which will

    inform the detailed development strategy.

    Socio economic prole

    The population of the area surrounding BGY ispredominantly young (Fig. 1) and is characterised

    by a diversity in terms of income, education (Fig.

    2) and ethnicity and relatively high rates of unem-

    ployment (6%).

    The degree of socio-economic complexity in the

    area, in particular the amount of working age pop-

    ulation and young people, should be taken into

    account in terms of proposed economic activities.

    A wider range of employment opportunities, train-

    ing and education and improved services targeted

    towards the local population should be a priority in

    redevelopment schemes. The gap between levels

    of education and employment is great in the area

    with the majority of highly paid and highly skilled

    employment concentrated in the City of London.

    Improvement of green spaces including educa-

    tional programmes could tackle issues of sustain-

    ability, crime, mental health and community cohe-

    sion. The incidence of robbery and theft related

    crime in the area could also be tackled by imple-

    menting CPTED principles in areas missing natu-

    ral surveillance, active frontages, etc.

    2.1_Urban Design Characteristics

  • 8/3/2019 Bishops Gate Report

    13/76

    11

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    Urban grain/block structure and use/ mix

    The urban fabric of the area is typied by adapt-

    able mixes of coarse and ne grain plots around

    the site supporting a variety of uses, with a ow

    of activity at different times. The encroachment of

    the coarse, mono-use City grain into these areas

    has been prevented by their designation as con-

    servation areas despite enormous economic pres-

    sure. Exceptions to this typical form are the more

    homogenous areas to the south east (corporate

    commercial) and south west (social housing).

    The area involves a large and varied mixed use

    covering a wide range of activities which dene

    certain areas of similar character (image districts)bordered by zones of transition (edges). The va-

    riety in these image districts and the adaptability

    of uses evident in some ne mix uses buildings (ie.

    Tea Building , old Truman Brewery) suggest a wide

    range of potential options for the site to adopt in

    relation to the mixture and adaptability between

    multiple grains and uses. (p.31)

    The built mass is shaping both internal and ex-

    ternal spaces, and has mostly been adapted to

    suit function. The building use then determinespedestrian ows and access as well as inuence

    the character of the public realm.

  • 8/3/2019 Bishops Gate Report

    14/76

    12

    Open Space system

    The open space system of the area is character-

    ized by its exibility and transitory character; by a

    constantly changing atmosphere that varies from

    day to night and weekday to weekend. The di-

    verse nature of open space is further categorized

    by public and private, hard and soft, temporary

    and permanent and high and low intensity among

    others.

    The built environment shapes the voids that cre-

    ate open spaces. Within the site, there is not alack of open spaces per se but a lack of green

    spaces. The challenge for the planned framework

    is to make connections between green spaces,

    markets and other hardscapes in the area that are

    disrupted so that these spaces can be enjoyed by

    residents and visitors.

    The site serves as a backdrop for informal activities

    that nourish the temporal uses of its open space

    boundaries. The challenge is to encourage inter-

    action within the open spaces around the site andto increase permeability without destroying the

    existing network. The activities proposed through

    temporary or long-term use might be adaptive

    and exible to the continuous contextual changes.

    Access

    The area is generally well served by public trans-

    port, and has a PTAL index 6b. Currently, the

    North-East part of the site area is less served by

    bus networks in comparison to the West. Opening

    of the Shoreditch Station will improve accessibility

    in the North-East area.

    The site is bound by networks of strategic routes,

    streets and cycle paths, which allows for sufcient

    access to surrounding Boroughs.

    The area provides several points for improvement

    of pedestrian movement. Conicts of use be-

    tween pedestrians, cyclists and drivers emerge in

    certain sites such as Brick Lane. Accessibility is

    also inuenced by building density, as high-mass

    buildings in the area cut off alternative routes and

    decrease sense of security. Inappropriate use of

    street furniture occasionally diminishes the quality

    of pedestrian use and safety and disrupts ows

    of pedestrian movement. Design of pedestrian

    crossings should contribute to ow without de-lays.

  • 8/3/2019 Bishops Gate Report

    15/76

    13

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    Massing/Density

    Due to various factors such as plot size, family

    size, and building heights the inconsistency be-

    tween population and physical density is ubiq-

    uitous. The disconnection between population

    and physical density is shown in the contrast

    between Shoreditch High Street and Brick Lane.

    While Brick Lane has a higher population then

    Shoreditch High Street, it has a drastically lower

    physical net density.

    The study area can be divided into clusters de-ned by trends in building mass. The design and

    formation of mass provides an identity for the

    area and also plays a role in vulnerability to crime.

    Building mass shapes the edges that create prop-

    erty demarcation, accessibility, and visibility, which

    form areas of safety or vulnerability to crime. In

    addition, changing week activities, such as week-

    end markets and business people from The City

    create an ebb and ow of population density on

    the street. Therefore, the areas redevelopment

    must be sensitive to the existing context by incor-porating cluster identity into new developments,

    design mass to create spaces of perceived safety

    and decreased crime risk, and generate continu-

    ous activity to evade street voids.

    Building typology, landmarks, signicant

    buildings and view corridors.

    The built environment of the BGY has been under-

    going urban change for years. The building uses in

    the area are quite diverse and range from creative

    industries to high nance. The image and reality of

    the site is dened by striking contrasts of vibrant

    areas and high rise buildings to areas of urban de-

    cay, and derelict infrastructure.

    The sense of insecurity in some areas is quite

    prominent, exasperated by the blighted built envi-ronment. Derelict buildings in the area lead to de-

    creased sense of pedestrian safety. Lack of active

    frontages and natural surveillance such as Sclater

    Street also decrease pedestrian safety. Thus, re-

    development schemes in the site area must take

    into consideration the transformation of derelict

    buildings, while staying true to the existing urban

    fabric ad historical signicance of the area.

  • 8/3/2019 Bishops Gate Report

    16/76

    Strengths

    (to be defended and built on through the

    development)

    Weaknesses

    (to be addressed through the development)

    High levels of connectivity by public transport

    Transformation and adaptability of local building useallow for a constant evolution of neighbourhoodidentity

    Diversity and vibrancy of local economic activity

    Adaptable existing spaces and structures within thesite

    Overall high population density of local areas ascompared with the rest of London

    Site serves as a bridge from residential to morecommercial areas and The City of London

    Diverse commercial spaces attract a range of usesand users at different times of the day / week

    Good lighting on major streets

    Markets attract people from surrounding areas andextend active frontages around the site on weekends

    Disconnection between built form and population

    density leading to overcrowding in some residentialareas and signicantly lower population densities inothers.

    Coarse-grain/mono-use housing and commercialareas restrict adaptability and integration with otheractivities

    Derelict buildings and construction sites disrupt cityfabric and increase fear of crime

    There is less than half of the recommended greenspace in Hackney and Tower Hamlets

    Limited and fragmented open space, with poorlydemarcated public/private space

    Poor East/West public transport and pedestrianconnections

    Street clutter prevents seamless pedestrian ow andcreates confusing street intersections

    Lack of street furniture, especially benches andbicycle stands

    Opportunities

    (to be maximised through the development)

    Threats

    (to be mitigated through the development)

    Build additional affordable family housing and reduce

    local overcrowding

    Connect the variety of community and structuralidentities surrounding the site

    Prioritise neighbourhoods needs through communityuses / services and economic opportunities for youngpeople

    Create a space that draws strengths from individualneighborhood characteristics

    New multi-use buildings unlock potential of coarsegrain buildings to incorporate varied activities atdifferent times. The same ideology can be used formixed use open spaces.

    Encourage temporary uses that reect local interestsand needs from the site, and contribute to thedevelopment of uses and form over time.

    Use strong existing local community organizationsand institutions to attract interest in temporary usesfrom the community

    Connect fragmented open space, improve pedestrianconnectivity and provide additional green space.

    Bridge Goods Yard with Eastern Yards

    Site will remain unused as development is reliant on

    economic climate

    Economic pressures will mandate what is built on andaround the site and will lead to high mass commercialbuildings that do not add signicantly to housingneed and generate a character in great contrast tolocal conservation areasPromotion of high-income housing and high-valueuses leads to indirect exclusion of local populationsfrom the site

    Risk of crime on streets of irregular activity

    Developers will disregard community identity andcreate a generic space

    Public Space on the Goods Yard site will de factobelong to those living on the site and will isolate thesurrounding community

    Poorly designed open space can correlate toincreased crime rates

    Redevelopment of the area can cause an increasein density thus making the affects of the additionalhousing provision in the area negligible

    2.2_Constrains and Opportunities

  • 8/3/2019 Bishops Gate Report

    17/76

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    3.0Objectives,

    vision anddesign

    principles

  • 8/3/2019 Bishops Gate Report

    18/76

    16

    The Bishopsgate Goods Yard has the potential

    to be an inclusive spatial node by harnessing thestrengths of the surrounding area, both social

    and physical, and exploiting its opportunities. Its

    future development should respect local charac-

    ter and livelihoods, create non-fragmented open

    spaces and approach structural development in a

    way that compliments existing urban grains. Be-

    yond the short-term temporary uses of the site,

    the long-term design parameters must answer to

    a comprehensive vision, where land-use, scale

    and social impact are coordinated under the um-

    brella of community building.

    3.1_Vision 3.2_Objectives

    1. Development of the Bishopsgate Goods Yard is

    well integrated with the surrounding areas, takinginto consideration the unique character of the site;

    2. Foster local diversity and interaction by sup-

    porting a community driven development in order

    to achieve a strong social cohesion and to reduce

    crime.

    3. Improve the permeability of the site, by support-

    ing a development strategy that not only improves

    north-south/east-west connectivity but that ad-

    dresses the needs of pedestrians and cyclists;

    4. Improve the existing and fragmented open

    spaces in and around to the site to allow greater

    accessibility of these areas by residents and visi-

    tors;

    5. Ensure that any new building developments in

    the BGY site are sensitive to the historical and cul-

    tural fabric of the existing area, taking into consid-

    eration conservation areas, listed and locally listed

    buildings;

    6. Promote multi-use buildings to unlock the po-

    tential of coarse grain buildings in the area and to

    incorporate varied activities at different times

  • 8/3/2019 Bishops Gate Report

    19/76

    17

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    3.3_Design principles

    The following design principles have been shaped

    and inuenced by the previous urban analysis andact as a guide to the forthcoming development

    proposals for the Goods Yard.

    1. Improve the permeability to the site at different

    levels (ground and upper) in the east-west and

    north-south directions.

    2. Create a clear hierarchy of movement which

    puts pedestrians at the top: pedestrian paths

    and cycling routes should be clearly divided in the

    site; as well, pedestrian paths, cycling and vehicleroutes, should be clearly divided outside the site.

    3. Create recognizable and exible paths inside

    the site.

    4. Improve cycle and public transport networks

    and their interaction with the pedestrian one (bus

    stops, bike racks etc.).

    5. Improve nodes and signage through traditional

    tools and through use of art.

    6. Network already existing columns of activity

    into an integrated public realm fabric.

    7. Develop a strategy to create a public realm

    language that ows uently between the three

    councils around the site.

    8. Establish a balanced public-private partnership

    with council leadership to ensure equal access to

    public realm benets.

    9. Foster landmark spaces from public to private,

    from open to enclosed.

    10. Balance the private requirements of land use

    with the existing local needs regarding health

    issues and space pressures.

    11. Utilize existing viaduct and archways

    as a connecting element from east to west,an opportunity for temporary uses and as a

    boulevard for permanent use.

    12. Respond to the existing urban grains to the

    north of the site, allow for north-south permeability

    through the site, both at multiple levels and also

    connecting multiple levels.

    13. Integrating existing and new structures through

    advanced structural engineering.

    14. High-rise buildings should provide public

    and semi public facilities for temporary densities

    (work time densities, residential and weekends

    activities) - that ensure a constant use of the of

    ground oors and upper oor levels. the where

    use is not a linear purely an extrusion vertically,

    from public-transitional-private.

    15. Enhance visual connection across the site

    while maintaining clear security boundaries.

  • 8/3/2019 Bishops Gate Report

    20/76

  • 8/3/2019 Bishops Gate Report

    21/76

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    4.0Detailed

    developmentstrategy:

    Identication of

    development sites

  • 8/3/2019 Bishops Gate Report

    22/76

    20

    The BGY site is situated in a dynamic context of

    urban development and transition. Because of itsstrategic position linking the north/south axes of

    activity and movement of Shoreditch High Street

    and Brick Lane, and proximity to the expanding

    City, any development of the site must take into

    account impact on and inuences from develop-

    ment opportunities and pressures in the surround-

    ing urban fabric.

    The image below illustrates some of the most sig-

    nicant of these potentialities and their relationship

    to the BGY site. While this development brief fo-

    4.0_Identication of development sites

    Transitional area around

    Redchurch St can besupported and enhancedthrough increased N-S

    connectivity on BGY site

    G+ 25 development

    Potential for Eastern Yards

    development following ELL

    completion

    Pedley Street development

    site

    Brick Lane activity corridorcan be enhanced throughincreased W-E connectivity

    on BGY site, intensified nodeat eastern end of BGY

    connecting to Allen Gardens

    Fragmented transitional area

    mostly residential,permeability and activity in

    area can be enhancedresponding to increased N-S

    connectivity on BGY site

    BGY site and focus of development brief

    Future development site identified by HackneyLDF

    G+50

    develop-ment

    proposed

    Fragmented

    mixed usearea, identity

    can be

    consolidatedto complement

    and enhanceactivity and

    connectivity on Reference sites for high density, tall building clusters setting precedents in proximity to BGY

    cuses predominately on the BGY itself, it is devel-

    oped in the context of the urban analysis of thewider area and expected to contribute a catalytic

    role on the integrated development of the indicat-

    ed areas.

  • 8/3/2019 Bishops Gate Report

    23/76

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    4.1Urban Structure

  • 8/3/2019 Bishops Gate Report

    24/76

    22

    Development of the urban structure of Bishopsgate

    Goods Yard must be integrated with publicrealm and access developments under a holistic

    approach that responds to the complexity of site

    and surrounding context as revealed through the

    urban analysis phase. Guidelines are structured to

    allow multiple proposal options which recognise

    and are conscious of the trade-offs between

    the sites economic potential, the needs of the

    surrounding communities and the context of the

    local urban fabric. Responses should promote a

    phased and incremental development of the site

    allowing emergent uses and transitions betweentemporary and permanent activities.

    3.1.1_Vision 3.1.2_Objectives

    1. Address neighbourhoods needs through uses,

    facilities and services (including affordable familyhousing, green space and a health facility) that

    meet identied local need and provide economic

    opportunities for young people.

    2. Include diverse commercial spaces of varied

    grain to attract a range of uses and users at differ-

    ent times of the day / week.

    3. Create a legible built form that is not an amal-

    gamation and blending of identities, but draws

    strengths from individual neighbourhood charac-teristics.

    4. Implement an approach to massing and density

    that is sensitive to the character of and impact on

    surrounding conservation areas.

    5. Implement an approach to permeability and

    movement in the urban structure that reects the

    complexity of the vertical and horizontal layering

    of the site.

    6. Encourage temporary uses that reect local

    interests and needs from the site, engage local

    people and institutions and contribute to the de-

    velopment of uses and form over time.

    7. Retain existing structures (full length of the via-

    duct, remaining perimeter wall, weavers cottages

    etc) for adaptive use wherever possible.

  • 8/3/2019 Bishops Gate Report

    25/76

    23

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    3.1.3_Design Principles 3.1.3_Long Term Framework

    1. Utilize existing viaduct and archways as a con-

    necting element from east to west, an opportunityfor temporary uses and as a boulevard for per-

    manent use

    2. Respond to the existing urban grains to the

    north of the site, allow for north-south permeabil-

    ity through the site, both at multiple levels and also

    connecting multiple levels

    3. Integrating existing and new structures through

    advanced structural engineering.

    4. High-rise buildings should provide public and

    semi public facilities for temporary densities (work

    time densities, residential and weekends activi-

    ties) - that ensure a constant use of the of ground

    oors and upper oor levels. the where use is not

    a linear purely an extrusion vertically, from public-

    transitional-private

    5. Enhance visual connection across the site while

    maintaining clear security boundaries.

    The Bishopsgate Goods Yard is the site of many

    overlapping, interdependent and interconnectinginuences. These inuences come from all as-

    pects, primarily the commercial forces in the City

    to the south-west, the contextual characteristics

    of the Brick Lane and Banglatown communities to

    the south-east and residential areas to the north of

    the site, and the aspirations and obligations of the

    local authority and city which are to be provided

    for its citizens.

    Surrounding Inuences

    Each of these key inuences bring with them

    strong and complex characteristics, which need

    to be considered within the development prin-

    ciples in order for future permanent development

    to reach the sites full potential and to support the

    needs of the surrounding communities; primarily

    with respect to housing, local and city economy,

    open space, and transport and movement, while

    maintaining an integrated urban fabric within the

    city as a whole.

    Surrounding inuences are not a snapshot intime, but need to capture the historic character,

    respond to the current conditions, as well as ac-

    knowledge the anticipated development plans

    for the future. When responding to the City it

    will be imperative to understand the planned fu-

    ture development of the city fringe, while on the

    contrary when responding to the residential areas

    to the north, the development needs to pay re-

    spect to the existing conservation areas, in par-

    ticular considering their building typologies, densi-

    ties, heights etc. The character and atmosphere

    of Brick Lane and the surrounding market areas

    are a unique phenomenon, which will require very

    sensitive considerations in order to support and

    nurture those conditions into the future. Part of the

    local authoritys responsibilities is to ensure suf-

    cient social provisions such as educational facili-

    ties, affordable housing, public open space, trans-

    portation etc which will be carried out through

    new development within the local area including

    the Bishopsgate Goods Yard site.

  • 8/3/2019 Bishops Gate Report

    26/76

    24

    Site Complexity

    In addition to the surrounding inuences the Bish-

    opsgate Goods Yard site itself is far from being a

    blank canvas browneld site. On the contrary the

    remnants of layering of past life and activity of the

    sites history, in conjunction with the current de-

    velopments on site, namely the new East London

    Line railway, provide a rich and changing starting

    point for future development. The main physical

    elements for consideration include the following:

    The 260m long Grade II listed Braithwaite Via-duct, with respect to historical and structural val-

    ue, and also the internal and external spaces it

    creates at both ground and upper levels

    The other unlisted arches connecting to the

    Braithwaite Viaduct, which together create the

    covered pedestrian boulevard along London

    Road

    The listed forecourt wall and gates, which cre-

    ate a frontage to Shoreditch High Street at ground

    level only

    The elevated box of the new East London Linerailway, which in the next few months will not only

    provide a transport connection to other parts of

    the city, but will create a node and intersection

    for transfer between vertical and horizontal move-

    ment around the site

    The lower ground level barrier to north-south

    circulation, which is the mainline rail network to

    and from Liverpool Street Station

    The other non-visiblebelow ground infrastruc-

    ture such as the BT telecommunications and cen-

    tral line tunnels

    Framework for Development of the Urban

    Structure

    The common approach to development relating

    to Urban Structure is to create development prin-

    ciples along the lines of discreet topics; where the

    most widely used topics include Form, Typology,

    Grain, Height, Use Mix, Density, and Environmen-

    tal Impact. On straightforward browneld devel-

    opment sites it is possible to assess development

    potential using each of these topics in isolation,

    but on complicated sites such as the BishopsgateGoods Yard site this approach could be consid-

    ered an over-simplication of the development

    opportunities and parameters. The itemized ap-

    proach also misses the opportunity to understand

    the nuances which are only apparent when as-

    sessing the site in a collective manner; it is im-

    perative that the development outcomes amount

    to more than the sum of the parts.

    Our approach to the long-term development of

    the Bishopsgate Goods Yard is two-fold.

    Firstly, we establish a set ofoverarching develop-

    ment principles which are intended to guide or

    steer the development priorities and act as a tool

    for achieving successful and sustainable develop-

    ment on the site.

    The following are the key development principles:

    1. Existing Viaduct and Archways

    as a connecting element from east to west opportunity for temporary uses

    boulevard for permanent use

    2. Footprint at ground and upper levels

    built form to explore extrusions other than

    purely vertical extrusions

    in particular, respond to the existing urban

    grains to the north of the site

    allow for north-south permeability through the

    site, both at multiple levels and also connecting

    multiple levels

    3. Integrating Existing and New

    through advanced structural engineering pro-

    vide solutions on the south-west corner of the

    site which integrate the existing and new struc-

    tures for a collective benet

    4. Interconnected and overlapping uses

    where use is not a purely related to verticality,

    from public-transitional-private

    high-rise buildings should provide public and

    semi public facilities for temporary densities

    (work time densities, residential and weekends

    activities) - that ensure a constant use of the of

  • 8/3/2019 Bishops Gate Report

    27/76

    25

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    *Existing Planning

    Guidance

    Commercial

    Drivers

    *Context

    West side East side

    Overall development 350,000 sq.m.

    Density

    Population 425-851 person/ha1.88-83.44

    person/ha

    131.31-150.04

    person/ha

    Household 213-426 household/ha

    1-36.39household/ha

    45.86-60.45household/ha

    Built 74468 sq.m./ha6-3097

    sq.m./ha

    2641.03-

    4140.63 sq.m./

    ha

    Height

    Tallest building:

    225 m, 50

    oors

    Use Mix

    New

    house:1000-2000

    Non-residential:

    7500-15000 sq.m.

    Up to 15000

    sq.m. for

    commercial

    use

    Ofce building

    and commercial

    use

    Mix of retail and

    residential use

    Form/TypologyMix of tall and low

    buildingsTall buildings

    Mix of tall and

    low buildings

    2-4 storey

    buildings

    Environmental impact

    Respect to

    the historic

    environment;

    Accommodate

    latest developments

    in environmentally

    sustainable

    technology

    ground oors and upper oor level

    5. Visual connection across the site while main-taining clear security boundaries

    imaginative proposals for separating elements

    between public and private ie. through the

    use of changes in levels, water elements

    where there is no ambiguity of ownership of

    accessible spaces

    Secondly, we establish Parameters for Negotia-

    tion. The underlying intention with this concep-

    tual approach is to identify the key parameters of

    each of the above topics (Form, Typology, Grain,Height, Use Mix, Density, and Environmental Im-

    pact), based on the surrounding inuences (com-

    mercial drivers, existing built context, and the lo-

    cal authority / citys aspirations and obligations),

    which then in an applied way, can be tested on thesite within the existing conditions.

    This approach will allow for multiple proposal op-

    tions, whereby trade-offs between the topics will

    create different benets and compromises, and

    ultimately can be ne-tuned to reach an optimal

    balance.

    Below is a Matrix of the Parameters for Negotia-

    tion, capturing the key parameters as we under-

    stand them at this point in time. Each cell repre-

    sents a single perspective on a single topic, which

    in many cases will contradict other cells.

  • 8/3/2019 Bishops Gate Report

    28/76

    26

    North-South Section 1 (eastern edge)

    Related to the built environment and connectivity within the

    site, the graphic shows the recommendation that buildings in

    the eastern edge have similar heights to those of Brick Lane,

    as an aim to maintain the urban fabric of the area. The lower

    heights are also important for preserving views and allowing

    sunlight into the site. The graph further illustrates the connec-

    tions between the north and south that make the open space

    more accessible for resident and visitor use.

    Indicative Illustration for Inspiration

    The following 7 illustrations are intended to indi-

    cate how the above parameters can be applied

    and tested across the site.

    It is not envisioned that each cell can be achieved

    in its entirety, but through negotiation and a ho-listic assessment an optimum development pro-

    posal can be achieved. This matrix is intended

    to be viewed as a live document, which can be

    updated and built upon throughout the duration

    of the development of the site. This will allow de-

    velopment proposals to continually respond to the

    current state of affairs and prevailing priorities.

    This approach is the antithesis of a prescriptive

    development brief, and is intended to stimulate

    truly creative and appropriate approaches to de-velopment, which are viewed and reviewed in a

    holistic manner.

  • 8/3/2019 Bishops Gate Report

    29/76

    27

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    North-South Section 2 (middle of development site)

    Moving westward along the site, heights of buildings will in-

    crease to around 30 oors, reecting the urban grain trans-

    formation from low rise building in Brick Land to the high rise

    buildings in the city. These higher buildings may block sun-

    light from penetrating the north side of the site, therefore it is

    recommended that buildings are separated to let the sunlight

    go through. Furthermore the spaces between the towers can

    be used for open space, adding to the connectivity of the

    proposed park and archways.

    North-South Section 3 (western edge)

    In the western edge of the site, building heights reach their

    peak with the tallest buildings reaching 60 oors. This is strat-

    egy to maintain the urban grain represented in the western

    part of the City. As a goal to maintain the archways, we rec-

    ommend to build a structure, no more than 12 oors, above

    the arches. By maintaining the unlisted arches it can con-

    nect the station square in the north and the public square in

    the south as well as maintain the urban characteristics in the

    east.

  • 8/3/2019 Bishops Gate Report

    30/76

    28

    East-West Section 2 (at Overground Rail Station)

    The unique condition of the elevated box creates distinct

    conditions below the box and above, allowing for changes in

    use. At the principle location for vertical connection between

    the ground level and the platform level, there is opportunity to

    allow people permeate and occupy the upper level, creating a

    pedestrian street with retail and restaurant potential.

    East-West Section 3 (southern edge)The section through the southern edge of the site illustrates

    the existing viaduct, and the internal and external spaces it

    creates. The south-west corner of the site will be the ideal lo-

    cation for the tallest building on the site, for commercial use.

    The illustration shows the commercial uses raised above the

    viaduct level, freeing the ground and rst oor levels for more

    public uses, and allowing for connections to the highline park.

    East-West Section 1 (northern edge)In the northern edge of the site, building heights respond to

    the heights and residential use on Bethnal Green Road and

    Sclater Street. The heights are not uniform in height from

    east to west, but build in height from the more protected area

    adjoining Brick Lane, through a transitional zone to the tall

    buildings on the western edge along Shoreditch High Street.

    The building footprints and gaps between maintain a similar

    grain and plot size to the blocks to the north.

    East-West Section 1

  • 8/3/2019 Bishops Gate Report

    31/76

    29

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    East-West Section 3

    East-West Section 2

  • 8/3/2019 Bishops Gate Report

    32/76

    30

    [U]rban Spaces lie fallow from time to time dur-

    ing the transition from one use to another, a pro-cess of ostensible disuse in fact possess strategic

    signicance

    (Schwarz and Rugare, 2009)

    As Schwarz and Rugare emphasise, whereas a

    vacant space is often seen as a failure of urban

    planners and developers, its potential temporary

    use during its fallow period should never be un-

    derestimated. Bishopsgate Goods Yard site, now

    vacant since its brief revival between 1998-2001,

    offers an ideal resource for housing temporaryuses until the current economic downturn sub-

    sides.

    The urban structure of the Bishopsgate Goods

    Yard site lends itself to two forms of temporary

    use:

    Those that remain on site for a given period

    and are removed when permanent development

    works begin; and

    Those that could potentially integrate into thelong-term proposals for the site.

    The latter being community oriented facilities, such

    as a library or sports facility, that require greater

    public investment. These uses would occupy the

    listed structures of the site while the former, uses

    requiring little structural investment such as work-

    shops and ofces, would occupy spaces that may

    be removed or redeveloped in the future, although

    we recommend preserving all historical structures

    of the site listed or unlisted - given that the sites

    heritage creates a unique sense of place.

    The phasing aspects required for the permanent

    development works need to be mindful of con-

    sidering temporary uses. While one zone of the

    site is partitioned and undergoing works for per-

    manent use, the other areas need to operate in-

    dependently. Relying on Brick Lane as a spine

    in the rst period of the arches development until

    an identity of the arches is established and at the

    same time reopening Wheeler Street to provide

    3.1.4_Temporary Use

    accessibility to Shoreditch High Street station.

    Both forms of temporary use should ensure

    round-the-clock activity in the area, acting as a

    natural form of surveillance and consequent crime

    deterrent.

    Moreover, uses should complement the neigh-

    bouring activities (i.e. Brick Lane and Spitalelds),

    while also forming networks with cultural and

    community facilities in the wider area (see next

    page). This will both distinguish the sites individu-

    al character from neighbouring uses and enhance

    the connectivity of the site forming a node of cul-

    tural and community facilities in an area that lacks

    a satisfactory number of these.

    The study of the existing facilities in the three coun-

    cils where the site is located demonstrates that

    there is not a lack of community facilities such as

    schools or libraries. In fact, there is a reasonably

    strong presence of community centres servicing

    the area. There is, however, a lack of cultural ven-

    ues - such as museums, art galleries, cinemas,

    mixed activities

    progressive renewal

  • 8/3/2019 Bishops Gate Report

    33/76

    31

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    theatres, and sport facilities. When observing the

    physical location of these community services,

    there is a striking disengagement of the Bishops-

    gate Goods Yard site and its immediate area with

    the community network. Currently, the BGY site is

    essentially an obstacle to these networks natu-

    ral ows. In this context, we recommend seizing

    the Bishopsgate Goods Yard development as an

    opportunity to rethink these networks and possi-

    bly even utilise the site as a central node of these

    activities - on the one hand complementing the

    existent community dynamics and, on the other,

    providing where community services currently

    lack. The temporary strategy adopted might prove

    a perfect opportunity to test the viability of some

    of these community enhancement options to be

    incorporated into the permanent proposal.

    museums/exhibitions spaces other recreational activitiescommunity centres

    educational facilities libraries

  • 8/3/2019 Bishops Gate Report

    34/76

    32

    Finally, the temporary uses should enhance the

    permeability of the site accentuating the west east connection from Shoreditch High Street to

    Brick Lane as well as north south creating a

    more direct link between Bethnal Green Road and

    the Bishopsgate transport node.

    Precedents

    From an international perspective there are a

    myriad of examples that relate to the Bishopsgate

    Goods Yard potential as a site of temporary use.

    The case of the LX Factory in Lisbon (Portugal)

    proves that the use of a dormant urban site might

    serve as a catalyst for regeneration of an area

    much bigger than the site itself.

    Privately owned and awaiting planning permission

    from the Lisbon city council, the 2.3 hectare site

    of this former textiles and graphics factory are be-ing used for a multitude of activities. The success

    of LX Factory is visible in its occupancy rates, the

    media attention and its round-the-clock activity

    with initiatives that appeal to very different sectors

    of society.

    As a consequence of the current economic down-

    turn, development sites that have stalled and lie

    vacant are now a familiar feature of the urban land-

    scape. There are interesting precedents, however,

    where a vacant site has been used temporar-ily while developers wait for grass shoot signs of

    recovery in the economy. For example, a stalled

    development site on Oxford Street, London, ear-

    marked for a mixed use development to be com-

    pleted in 2012, has recently been used to exhibit

    24 life size dinosaurs and attracted up to three

    thousand visitors a day during school holidays.

    Moreover, ostensibly permanent uses rely on tem-

    porary structures to integrate with, and preserve,

    an existing urban structure similar to the arches

    of Bishopsgate Goods Yard. Borough Market in

    London, for example, successfully combines a

    number of permanent use (restaurants and bars)

    alongside the more temporal uses of the market

    stalls that cluster underneath the Victorian railway

    arches.

    enhancing permeability phase 1

    enhancing permeability phase 2

  • 8/3/2019 Bishops Gate Report

    35/76

    33

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    On the right

    Examples of temporary use as exhibition venue and book-

    shop

    On the left

    Examples of more permanent use as shops and caf, mixed

    also with unconstrained uses as a daily fruit market

  • 8/3/2019 Bishops Gate Report

    36/76

  • 8/3/2019 Bishops Gate Report

    37/76

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    4.2Access

  • 8/3/2019 Bishops Gate Report

    38/76

    36

    4.2.0_Introduction: from general principles towards an access improvement

    Between the general principles mentioned in

    chapter 3.3.3., the ones related to the improve-ment of the accessibility towards and inside the

    site are:

    1. to improve the permeability to the site at

    different levels (ground and upper)

    in the east-west and north-south directions;

    2. to create a clear hierarchy of movement which

    puts pedestrians at the top: pedestrian paths and

    cycling routes should be clearly divided in the

    site; as well, pedestrian paths, cycling and vehicleroutes, should be clearly divided outside the site;

    3. to create recognizable and exible paths inside

    the site;

    4. to improve cycle and public transport networks

    and their interaction with the pedestrian one (bus

    stops, bike racks etc.)

    5. to improve nodes and signage through tradi-

    tional tools and through use of art.

    Guided by those principles, the development

    should address the issues identied in section

    4.2.2., working in the theoretical framework stated

    in section 4.2.1: the strategy (4.2.3) to implement

    the accessibility should be developed under the

    same framework.

    Above:

    movement of people on the study area;

    ows channeled toward the Yard.

  • 8/3/2019 Bishops Gate Report

    39/76

    37

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    Permeability

    Permeability is a perceived quality and rep-

    resents the degree to which an urban area al-

    lows movement and provides a choice of routes

    through an area (Bentley et Al, 1985). Beyond

    the availability of choice, its important that there

    is also an awareness of route choices so that the

    permeability is utilised.

    With respect to crime prevention, permeability can

    be viewed both negatively and positively. In some

    cases, a high degree of permeability is consid-ered undesirable as it provides a choice of escape

    routes for criminals (Cowan, 2005). On the other

    hand, non-permeable street networks, can create

    crime hotspots, such as dead-end streets. The

    desired degree of permeability has to be balanced

    by an assessment of the crime hotspots in the

    area so that permeability doesnt contribute to an

    increase in the crime in the area.

    4.2.1_Access: theoretical components

    On the right:

    example of the concept of permeability in nature;

    present impermeability of the Yard;

    different degrees of permeability on the study area related to

    the urban grain.

  • 8/3/2019 Bishops Gate Report

    40/76

    38

    Connectivity

    Connectivity refers to the directness of links and

    density of connections in a transport network

    (Cowan, 2005). Generally, a well-connected ur-

    ban area reduces travel distances and facilitates

    movement both within an area as well as from

    within to external areas.

    With respect to crime issues, one way to help in-

    crease the sense of community strength which

    can help to combat crime is to aim for the creation

    of one connected neighborhood rather than a col-lection of disconnected areas. This can lead to a

    sense of community responsibility and care of the

    area as a whole (Ofce of the Deputy Prime Minis-

    ter and Home Ofce, 2004).

    On the right:

    example of the concept of connectivity in nature;

    intersection of several paths near Spitaleld Market;

    different components related to Connectivity on the study

    area.

  • 8/3/2019 Bishops Gate Report

    41/76

    39

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    Legibility

    Legibility of an urban area signies the degree to

    which people are able to read their surround-

    ing environment and understand how to navigate

    themselves in a place using signs, built form, land-

    marks and marked routes. Legibility is the lan-

    guage of the city that helps people to feel either

    welcomed and well-oriented or uncomfortable

    and lost in the space. A gradual, phased strat-

    egy to the development of the site area, as is pro-

    posed in this development brief, can contribute

    to legibility as it enables residents and visitors togradually become familiar with the changes and

    accept them over time.

    Legibility is particularly important for bringing

    about a feeling of safety in an area prone to crime.

    Clear waynding and signage enable visitors and

    vulnerable populations to easily and comfortably

    either wander through an area or get to a particu-

    lar destination.

    On the right:

    example of legible environment (Piazza dei Miracoli in Pisa);

    landmark as space (outside Spitaleld Market);

    landmark as building (the Gherkin);

    landmark as event (Brick Lane Market).

  • 8/3/2019 Bishops Gate Report

    42/76

    40

    4.2.2_Issues to be addressed

    Waynding and clarity of movement

    Our analysis indicated that the waynding and sig-

    nage in the area surrounding the site is reasonably

    good due to visual landmarks created by domi-

    nant built forms, particularly in the Western end of

    the site. The main exception to ease of waynding

    is in the Brick Lane/Fournier Street area, where

    there is an opportunity to increase the amount of

    strategically placed non-commercial signage.

  • 8/3/2019 Bishops Gate Report

    43/76

  • 8/3/2019 Bishops Gate Report

    44/76

    42

    Ambiguous and conicting uses

    Areas such as Shoreditch High Street, Sclater

    Street, Brick Lane and Norton Falgate reveals how

    there are unclear and often conicting signals with

    respect to the use of spaces. For example, while

    Shoreditch High Street is proposed as an ofcial

    cycle route yet it has no dedicated or designated

    cycle lane.

    Contribution of area permeability

    The street network around the site demonstrates

    an high level of permeability, with the obvious

    exception of the immediate site itself, which

    currently serves as a blockade to easy north-south

    and east-west passage. Re-development of the

    Bishopsgate Goods Yard should consider howthe site can t seamlessly into the permeability

    network of the area and avoid abrupt passage

    transitions.

  • 8/3/2019 Bishops Gate Report

    45/76

    43

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    Generally, we are in agreement with the design

    principles set out in the Planning Guidelines in termsof creating equitable and safe access for visitors

    and residents to the area. The proposed streets,

    paths and spaces identied for development

    achieve a well-connected and permeable network

    contributing to an integration into wider London.

    That said, we believe that the guidelines are

    narrow in their focus on the primarily technical

    and physical meaning of access. In this sense, the

    guidelines are disregarding the human element of

    the site and how it connects to the surroundingcommunity. The guidelines acknowledge the

    strong local character of the area, however they

    do not specically address how this character

    can be incorporated into the issue of access. The

    way we perceive access is not only a matter of

    mechanical movement from point A to point B

    but it is the cultural, environmental and emotional

    experience that accompanies this movement.

    Therefore, dening a legible space as something

    able to produce vividly identied images of thebuilt environment (Lynch, 1960), the space itself

    should become a landmark, along with the events

    it could host: markets, celebrations or whatever.

    To achieve this, our recommendation is to maintain

    the character of extreme exibility visible in some

    derelict areas around the Yard or in the spaces

    that usually host the market (which have a great

    potentiality in terms of informal and temporary

    uses).

    Moreover, our recommendation is to see the site

    as a potential catalyst of ows, a sponge able to

    attract and absorb the density of people walking

    in the surroundings.The ows should not be seen

    simply as disappearing traces on a dull open

    space, but as something able to shape the space

    itself. Therefore, the system of accesses, paths

    and open areas should derive directly from the

    interpretation of those ows.

    Above:

    a legible environment depicted in a De Chirico painting;

    a suggestion of the possibility to host events on the Yard;

    disappearing traces in a nomadic space: the Yard itself

    should be seen as nomadic, but at the same time able to

    interpret and incorporate those traces.

    4.2.3.0_Confronting the planning guidelines: general approach

  • 8/3/2019 Bishops Gate Report

    46/76

    44

    4.2.3.1_Strategy: changing the context through the theoretical components

    Short

    term

    Me

    diumt

    erm

    Longterm

    Present

    In the short, medium and long term, several in-

    terventions will lead to a general improvement ofthe Permeability, Connectivity and Legibility of the

    study area.

    In terms of Permeability, the site should be in-

    creasingly treated as a sponge, cutting its imper-

    meable fabric with several paths. Both the North-

    South and the East-West connections should be

    improved. The nal image suggests really perme-

    able grain.

    In terms of Connectivity, an incremental opening ofpaths inside the site (the red ones in the schemes)

    and some improvements of public transport and

    cycle network (see section 4.2.3.4) should be im-

    plemented in order to enhance a higher freedom

    to move within and towards the site.

    In the schemes, the black routes are the ones ac-

    tually involved in the improvement of Connectivity

    around the site: moving from the short of the long

    term this involvement will interest a higher amount

    of routes.

    In terms of Legibility, the images show in black

    Landmark Buildings and in grey Landmark Spac-

    es. Several interventions (the construction of the

    built evironment itself, the use of art see section

    4.2.3.3 and the improvement of waynding sig-

    nage) should lead to a general increase of recog-

    nisable elements.

    PERMEABILITY

  • 8/3/2019 Bishops Gate Report

    47/76

    45

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    Short

    term

    Short

    term

    Me

    diumt

    erm

    Me

    diumt

    erm

    Longterm

    Longterm

    Present

    Present

    CONNECTIVITY LEGIBILITY

  • 8/3/2019 Bishops Gate Report

    48/76

    46

    4.2.3.2_Strategy: an incremental development at different scales. Design guidelines.

    In the short term, along with the general im-

    provement of several nodes around the site, theopening of two new routes in the site itself should

    improve the connectivity in the North-South direc-

    tion.

    The forecasted opening of the rehabilitated arches

    will make possible to host some activities on the

    site: the route beside these spaces will be a public

    passage that could host part of the Brick Lane

    Market on Sunday.

    On the upper level, the construction of a park

    could partially ll the lack of green spaces inside

    the study area.

    LARGE SCALE

    In the medium term, the pedestrian network will

    be extended toward Allen Gardens that should be

    connected to the park on the upper level (the park

    itself should be expanded on the space upon the

    overground).

    Looking at the site the development of the North-

    Eastern area should follow a ne grain pattern to

    allow the opening of several paths to better con-nect the site to the Bethnal Green Road area.

    A pedestrian space between the arches and the

    overground footprint should encompass the fea-

    tures we have suggested at section 4.2.3.0.

    In the long term the improvements in the pedes-

    trian and cycle networks will reach its apex, highly

    enriching the connectivity on the area.

    The development of the Eastern area will give the

    opportunity to complete the East-West connec-

    tion.

    Furthermore the North-South connection should

    be denitively strengthened with some interven-

    tions, aimed to enhance a higher legibility of that

    public space.

  • 8/3/2019 Bishops Gate Report

    49/76

    47

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    SMALL SCALE: GROUND LEVEL SMALL SCALE: UPPER LEVEL

  • 8/3/2019 Bishops Gate Report

    50/76

    48

    Local creativity and artistic talent can be har-

    nessed for the purpose of making streets morelegible in particular in the areas north and north-

    east of the site. For example, an artistic take on

    signage, zebra crossings and street art could help

    to distinguish the area from other parts of London

    and create a memorable and unique feeling for the

    neighbourhood. Beyond the functional purpose

    of helping people navigate their way through the

    streets, this will also create a greater sense of com-

    munity ownership and connection to the changes

    occurring if people can see that local stakeholders

    have participated in its improvements.

    The following initiatives could be implemented to

    utilise local artistic talent to improve legibility:

    Hold a mural competition for area schools in the

    Boroughs of Tower Hamlets and Hackney to add

    their community vision to a new blank wall that

    results from site development.

    Work with local building owners and street/graf-

    ti artists to identify locations that lack legibility toadd unique works of grafti on the sides of exist-

    ing buildings to create more orienting features in

    the neighbourhood.

    4.2.3.3_Strategy: use of art as a tool to improve legibility

  • 8/3/2019 Bishops Gate Report

    51/76

    49

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    Cycle network strategy

    Over the long-term, the placement of bus stops

    should be rationalised to serve the new Shoreditch

    High Street station and to create an increase the

    number of pedestrians and public transport users

    with access to the station. In the short and me-

    dium term, the gaps in the bus network (noted in

    yellow in the diagram) should be noted so that al-

    ternative less capital-intensive transport solutions,

    such as cycling and walking, can be considered

    and integrated into the development strategy.

    Public transportation strategy

    Around the Bishopsgate Goods Yard site, gaps ordeciencies in the cycle network are located on

    the main roads and intersections. To establish a

    cohesive and safe system of bicycle routes, the

    designated roads for cycling should be enhanced

    with special cycle lanes, advanced stop lines,

    cycle signage and cycle parking along the pri-

    mary routes used. Additionally, bike racks should

    be added with local area information for cyclists

    abundantly available. Furthermore, the London

    Cycle Hire Scheme represents a great opportunity

    to integrate the site into a London-wide scheme

    while tapping into the areas existing interest in cy-

    cling. Key areas of deciency around the site are

    indicated in yellow.

    4.2.3.4_Strategy: improving cycling and bus network

    Above:

    recommended improvements to cycle network;

    recommended improvements to bus network.

  • 8/3/2019 Bishops Gate Report

    52/76

  • 8/3/2019 Bishops Gate Report

    53/76

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    4.3Public Realm

  • 8/3/2019 Bishops Gate Report

    54/76

    52

    Dening Public Realm

    Public realm is the space that links communities

    beyond buildings. Streets, sidewalks, parks and

    squares constitute the elements through which,

    by diverse means of design, people interact and

    circulate. As stated by Carmona (2003), public

    realm is a common ground for social interaction,

    intermingling, and communication; and a stage

    for social learning, personal development, and

    information exchange. Furthermore, public realm

    and open space in particular- is intrinsically

    linked to social conditions, transcending itsphysical nature into a fundamental component

    of livelihoods quality: Comprehensive planning

    policies for open space are fundamental to social

    inclusion, community cohesion, health and well-

    being (Open Spaces Strategies: best practice

    guidance, 2009).

    Importance of Social Well-being

    When approaching design principles, social

    trends and information should be identied to

    create a comprehensive understanding of the

    areas context. Both the Hackney and TowerHamlets councils suffer considerable levels of

    socio-economic disadvantages, unemployment,

    homelessness, neighbourhood violence and

    crime. Statistics show how these elements have

    contributed to high levels of health concerns

    amongst all community groups, with high number

    of mental illnesses, depression and suicide. The

    emphasis on sustainable development for new

    projects can aid the abatement of mental illness

    through the provision of green and open spaces,

    highlighting the importance in the relationship ofsocial, economic and environmental spheres.

    By means of design parameters, the upgrading of

    the public realm and the natural environment can

    provide a rapid reduction in stress. This serves

    a purpose for both the residents of the area and

    the transitory users from the ofce workers that

    circulate the area during the week. Some benets

    of a rich public realm include the improvement

    of personal relations with the environment, an

    appreciation of local urban character and the

    reinforcement of outside community interaction.

    4.3.1_Denitions

  • 8/3/2019 Bishops Gate Report

    55/76

    53

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    SWOT Analysis Dening the site

    The Bishopsgate Goods Yard (BGY) site is under

    heavy scrutiny for its ongoing development plan.

    Its transformation for the near future is sure to have

    a lasting effect on the surrounding communities,

    as well as a makeshift of the public realm environ-

    ment. In this sense, the design guidelines that now

    exist should account for the contextual effects this

    project has; its impact will denitely reach a largerdimension than the sites perimeter. In terms of the

    public realm, focalized development still needs an

    integrated approach, and the BGY is no excep-

    tion. Under these spatial denitions, a series of

    considerations can be understood in the following

    SWOT analysis.

    Strengths Weaknesses

    Transformation of building use allow for a constant evolu-

    tion of neighbourhood identity

    Diversity and vibrancy form strong economic activity

    Adaptable spaces

    Serves as a bridge from residential areas to The City of

    London

    Commercial spaces target a range of socio-economic

    groups

    Good lighting on major streets

    Markets attract people from surrounding areas

    Marquee project for the East London Green Grid (ELGG)

    Derelict buildings and construction disrupts city fabric

    Irregular public use can create weekday voids in activity

    There is less then half of the recommended amount of

    green space in Hackney and Tower Hamlets

    Poor East/West connections

    Poorly demarcated Public/Private space

    Street clutter prevents seamless pedestrian ow and

    confusing street intersections

    Lack of street furniture, especially benches and bicycle

    stands

    Guidelines for pedestrian and vehicle trafc are not strictly

    followed which can lead to accidents

    Opportunities Threats

    Incorporation of a variety of community and structural

    identities

    Areas of heightened new construction can prioritise neigh-

    bourhoods needs

    Create a space that is not an amalgamation and blending

    of identities, but instead representative of individual

    neighborhood characteristics

    New multi-use buildings unlock potential of course grain

    buildings. The same ideology can be used for mixed-use

    open spaces.

    Use local community organizations to attract interest in the

    temporary site from the community

    Bridge Goods Yard with Eastern Yards

    Make connection between Goods Yard, Allan Gardens, and

    markets

    Site will remain unused as it is reliant on economic climate

    Wishes of developers with money and power will mandate

    what is built on and around the site and will build high mass

    commercial buildings that do not add to population density

    Gentrication

    Risk of crime on streets of irregular activity

    Developers will disregard community identity and create a

    generic space

    Public Space on the Goods Yard site will de facto belong

    to those living on the site and will isolate the surrounding

    community

    Poorly designed open space can correlate to increased

    crime rates

    Redevelopment of the area can cause an increase in

    density thus making the affects of the additional housing

    provision in the area negligible

    4.3.2_SWOT Analysis

  • 8/3/2019 Bishops Gate Report

    56/76

    54

    SWOT mapping

    These maps spatially locate the strengths,

    weaknesses, opportunities and threats to the

    Bishopsgate goods yard. The strengths of the

    site are centered around the major paths and

    nodes around the site. In contrast, weaknesses

    are concentrated on smaller, less penetrable

    spaces. Temporary and long term development

    has the opportunity to connect public spaces to

    one another and represent individual community

    identities on the site. The threats of the creation

    of generic and exclusive space is focused on how

    the surrounding area will eventually affect the site.

    Design principles

    The driving principle for the BGY intervention

    should be the creation of an integrated, plural

    public realm that reects community livelihoods.

    4.3.3_Design Principles

    STRENGTHS WEAKNESSES

    OPPORTUNITIES THREATS

    1. Strengthen already existing columns

    of activity into an integrated public

    realm fabric.

    2. Develop a strategy to create a public

    realm language that ows uently

    between the three councils around the

    site.

    3. Establish an evenhanded public-

    private partnership with councilleadership to ensure equal access to

    public realm benefts.

    4. Foster the development of landmark

    spaces from public to private, from

    open to enclosed.

    5. Balance the private requirements of

    land use with the existing local needs

    regarding health issues and space

    pressures.

    The supporting design principles are:

  • 8/3/2019 Bishops Gate Report

    57/76

    55

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    Challenging the Planning Guidelines

    Under the current planning guidelines, the

    Bishopsgate Goods Yard is set to have an

    important intervention in terms of public realm

    design and conception. Reinforcing the elements

    of accessibility and urban structure that now

    shape the site, the new proposal introduces two

    main areas of public realm:

    I. A junction of two squares, namely Public Square

    and Station Square along the re-opened Wheeler

    Street on the north-south corridor.

    II. A second-level park that lies over the arches

    structure on the southeastern side of the site.

    These interventions are sustained by a series of

    additional street openings that would increase

    the squares accessibility and its relation with the

    arches compound. Furthermore, the guidelines

    state the importance of extending the sites open

    space links with areas beyond its limits, as well as

    the necessity of addressing crime prevention andmaintaining local character.

    The public realm, as stated before, is constituted

    by multilayered factors that crosscut typical design

    principles. It should not only answer to design

    requirements but to social needs.

    Recommendations

    Some of the main aspects that the planning

    guidelines should take into consideration are the

    following:

    1. Integrate the public realm proposals and

    interventions with a wider approach towards a

    local improvement of the urban fabric, well beyond

    the site and not limited to the new developments

    immediate space.

    2. Study the character of the area in order to avoid

    generic public spaces that comply with design

    standards but that speak to a very specic set of

    aesthetic values.

    3. Consider the impact that a higher densication

    of the area may bring to the public realm. As statedbefore, public realm should answer to current

    social needs including health benets, social

    deprivations and, in general, livelihoods. In this

    respect, the planning guidelines should consider

    the following aspects:

    a. The sites vicinity is already in need of quality

    urban spaces that can be partially addressed

    with the interventions on the site. However, the

    new massive densication will again create new

    pressures due to an increased population anddemand.

    b.The proximity of new development to the sites

    public realm interventions should carefully avoid

    creating a contested or exclusive space, where

    the park and the squares operate as backyards of

    the proposed high-rises.

    c. The abrupt change of scale in the proposed

    buildings will impact the presence of shadows

    and canyon-like streets (due to short distancebetween the building frontages). This affects

    the general quality of the space, introduces

    elements of discomfort (e.g. wind currents) and

    calls for added, and costlier, measures of design

    intervention (e.g. furniture, lighting) to maintain a

    continued sense of security.

    4. Strengthen links to the eastern side open space

    network, to balance the polarisation of renewal

    only on the western side of the site. This ensures

    an integral approach to public realm, a wider

    inclusion of communities and forties the network

    of green spaces that exist to the east. Public

    realm can be more efcient the less fragmented it

    appears to be.

    4.3.4_Planning Guidelines

  • 8/3/2019 Bishops Gate Report

    58/76

  • 8/3/2019 Bishops Gate Report

    59/76

    57

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    4.3.5_Macro Level

    Improving Networks and Adaptive Spaces

    It is essential to understand the concepts of tem-

    porary and permanent use of open spaces, as well

    as, the distinction between the intensity of use of

    these spaces into weekdays and weekends. Such

    concepts are crucial; for improvements of dis-

    rupted networks, understanding where and when

    these disruptions occur, while taking into account

    the notion of space and time. Moreover, one must

    consider to whom the future development plan-

    ning is for and why, whether residents as appro-

    priate community spaces? Workers that utilize theeastern side area during lunch time of weekdays?

    Or external visitors prevalent during street market

    activities? The challenge is to create a exible en-

    vironment taking into account the multiplicity of

    public space uses. Since the richness of use of

    open space in the area is informed by its exibility

    and adaptability, the idea is to plan for an inclu-

    sive, multidimensional, and adaptative space that

    can accommodate the various dimensions of use.

    Stregnthening links

    Greater inclusivity should be achieved not only in

    terms of use of public space, but also by provid-

    ing better connectivity taking into consideration

    the networks disruptions in order to provide co-

    herence and continuity to the existing public realm

    system. Strengthen links between the east and

    west side of the wider area and creating public

    space that by its use mediates between the two

    sides, is essential. Improving west-east connectiv-

    ity concerns the site, in addition to the wider area.

    On the other hand, creating connectivity between

    the north and south on the Bishopsgate Goods

    Yard as stated in the planning guidance, which is

    critical for increased permeability of the area. Si-

    multaneously, the increased ow of people across

    the site resulting from the improved permeability

    will enhance the safety and natural surveillance in

    the area. A collection of strategies proposed to in-

    tervene in the public realm network accommodat-

    ing these needs are set out as guidelines in the

    following sections.

  • 8/3/2019 Bishops Gate Report

    60/76

    58

    4.3.6_Mesa Level

    Sector analysis

    The future BGY will be the link between two major

    ow corridors at the west and at the east, namely

    Shoreditch High Street and Brick Lane. In both

    cases, several conditions have constrained the

    public realm and its quality (see below).

    The void generated between these two corridors

    can be partly attributed to the irregular language

    in the public realm, with contrasting sites such as

    the Bishops Square sector and its empty adja-

    cent streets. This fragmentation reinforces physi-

    cal and social barriers; at the same time though, it

    positions the BGY site as a common ground that

    could serve as a node in itself and as an interme-

    diary catalyst for the public realm of the area.

  • 8/3/2019 Bishops Gate Report

    61/76

    59

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    4.3.6_Strategies

    General strategies

    Under the stresses indicated above, the public

    realm network can begin its upgrading by including

    a series of design strategies that can have a

    signicant impact on the context of the BGY site.

    The main strategies considered for the upgrading

    of the public realm are the following:

    1. Pedestrian policies

    a. Introduce pedestrian priority: widen foot-

    ways, pedestrian priority streets

    b. Improve crossings, pedestrian rights ofway, design a sustained pavement and light-

    ing system.

    2. Walking routes and obstacles

    a. Widen sidewalks when possible, introduc-

    ing street furniture and vegetation lanes

    that dont interfere with pedestrian ows.

    b. Reduce street clutter (furniture, signage,

    bus stops) in busy areas yet maintain pres-ence of supporting furniture elements.

    3. Catalyst interventions & open landmark spaces

    a. Introduce design interventions for specic

    space improvement along general policies of

    spatial upgrade.

    b. Reinforce existing openings (wide streets,

    markets, lots) with character elements: sitting

    space, green areas and pavements.

    4. Lighting and safetya. Create a lighting language across the area,

    highlighting important paths and supporting

    a sense of environmental safety.

    b. Support transparent building frontages at

    night that integrate with the exterior.

    c. Introduce quality street furniture and plants

    with an adequate scale.

  • 8/3/2019 Bishops Gate Report

    62/76

    60

    Dening Character of the Site

    This brief suggests a few broad characteristics

    that offer a set of attributes that are desirable

    for the Public Realm taking cues from the urban

    analysis stage and in terms of its critique. These

    characteristics have been laid out in a matrix to

    better explain the interconnectivity and complexity.They are not mutually exclusive of each other and

    should be read in conjunction with the Urban

    Design Characteristics dened in the previous

    sections.

    4.3.7_Micro Level

    PERMEABILITY CONNECTIVITY

    PLURALITY, FLUX & FORMALITY LANDMARK SPACE

    The visual and physical apects that would promote

    legibility, facilitating access and a sense of security

    Connections within the site will promote activity

    and a thorough vitalising of the public realm

    Temporary multiuse spaces would promote inclu-

    sivity, integrate safety, and security related aspects.

    Creating an identity for the site and the space

    would increase its legibility and readability.

  • 8/3/2019 Bishops Gate Report

    63/76

    61

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    Design Guidelines

    4.3.7_Micro Level

    MAINTAINING A MIXED/PLURAL EDGE BETWEEN PUBLIC AND PRIVATE

    PLANNING GUIDELINES: EXTRUDED REALMS

    LEVELS 0 AND +1 CATERING TO PUBLIC FUNCTIONS IN THE PUBLIC REALM

    LEVELS +2 AND ABOVE WITH SEMI-PRIVATE AND PRIVATE LAYERS

    INTERFACE WITH STRUCTURE FROM PLANNING GUIDELINES

    The guideline for the rst level should juxtapose

    public and private space, both in terms of horizon-

    tal layering and its interface with the street. This

    relies on the pedestrian openings that will run ac-

    cross the site.

    The ground is proposed to be public including

    ground oors of buildings. The rst level is alsoproposed to be public which includes the roof-top

    park promoting horizontal and vertical connec-

    tions.

    A well balanced combination of public and semi-

    public vertical interfaces between the street and

    the buildings promote a mix of activities and

    create opportunities for multiuse and multipurpose

    spaces.

    These levels are proposed within the physical

    structure of Bishopsgate Goods Yard Planning

    Guidance. The Public realm is proposed to ow

    through the buildings in a horizontal and vertical

    continuum at both levels.

    The second level is proposed to be semi-public

    with the subsequent levels being private. Smooth

    transition to the second level should allow a grad-

    ual access to the roof-top garden while avoiding

    vertical exclusion.

  • 8/3/2019 Bishops Gate Report

    64/76

  • 8/3/2019 Bishops Gate Report

    65/76

    DPU_BUDD_2010_BU1_Bishops Gate Goodsyard_Development Brief

    5.0Phasing

  • 8/3/2019 Bishops Gate Report

    66/76

    64

    The complexity of the site and its inuence on the

    surrounding urban fabric, the range and scope ofpotential development interventions and uncertain

    economic climate combine to indicate the neces-

    sity of a phased development. Any phasing must

    be sensitive to these variables as well as time-

    bound external drivers such as the opening of the

    ELL extension and the London 2012 Olympics.

    The proposed phasing of the development is

    driven through initially realizing the use value of

    the site following the opening of Shoreditch High

    Street Station in 2010 and up to the London 2012Games with the initiation of a range of tempo