About Biotech• Incorporated in Nigeria in 2010

• Providing Engineer Wastewater &

Water Treatment Solutions

• Teamed Up With World Leader in

Decentralized WWTPs

• Over 200,000 Installations globally

• Over 25 Experts Dedicated to IR&D

• Over 105 Years Wealth of Experience

• ISO Certified

• Quality Effluent With 20:30:20

Our ValuesContributing to the prosperity of the customers we work with by developing long-term partnerships thatcontinually enhance and improve the communities we work in. We do this with vision and innovation, developingnew approaches and concepts that continually ensure our solutions improve the working practices of ourcustomers and enrich the lives of those living in our neighbourhoods. Focused on teamwork to make sure wecollaboratively reach solutions that reflect our commitment to corporate social responsibility, we perform withagility and precise execution to ensure we continually add value whilst always protecting the environment we livein.

Vision

Our vision is to be the best in the industry and the partner of choice for all packaged wastewater and waterapplications.

Mission

To ensure a cleaner environment for communities and families around the Country, to protect shared waterresources and to offer value-added solutions designed to perform and last.

OUR TECHNICAL TEAM

• Engr. Abdulrasheed Adebola Onanuga – Chairman: B. Sc(Hons.) Civil Engineering. MNSE, COREN

• Evangelos Petropolous – Technical Director: Ph.D., Msc, B.Eng

• Jim Palmer – Project Manager – Design & Tendering: Dip. Mt. Sc., B.Sc. Fd Bus. M Sc. Fd Sc. Tch.

• Tom Fitzgerald – Engineering Design Manager: Cert Mech Eng. Dip Manufacturing Eng, 3D Design, 2D Design & Drawing –City & Guilds Mgt Training, Mgt Health & Safety

• Ashish Mehna – Process Engineer: P. Eng Municipal, Commercial, Communal, Institutional, Industrial (M2C2I)

• Sebastian Hunter – Project Co-ordinator-Design & Tendering: B. Eng. Chemical Engineering

• Abayomi Shittu – Project Administrator: (B.Sc) Biochemistry

CONSULTATION DESIGN,

BUILD

AND SALE

INSTALLATION MAINTENANCE

Project

Evaluation to

determine a

proffered

solution.

Recommendati

on of

appropriate

Treatment

Plant.

This stage

includes

design of

prototype

model and

concept

design for the

facility

Installation and

Commissioning

of Treatment

Plant

Training, Routine

Maintenance and

Servicing of

Treatment Plant

Project Approach

Our Products – BTA (6-25PE)

Our Products – BTS (30-600PE as a single stream)

Our Products – BTM (200-5000PE as a single stream)

OUR ENGAGEMENTS

Some of Our Clients

This project by the Biotech Team was for the supply, mechanical and

electrical installation and commissioning of Biotech BTS N20

wastewater treatment plant at the Lagos State Wastewater

Management Office, Ikeja, Lagos.

Project Name: LSWMO Wastewater Treatment Plant

Client: Lagos State Wastewater Management Office

Sector: 100PE Commercial

Category: Wastewater Treatment

Completion Date: November, 2011

Degree of treatment: 20:30:20 mg/l BOD: SS: Ammonia

Treatment Process: Biotech BTS N20

LAGOS STATE WASTE MANAGEMENT , OFFICE, IKEJA

L A G O S S TAT E G O V E R N M E N T O F F I C I A L’ S E X P L O R ATO RY V I S I T TO O U R I R E L A N D O F F I C E

L A G O S S T A T E G O V E R N M E N T O F F I C I A L ’ S E X P L O R A T O R Y V I S I T T O O U R A M E R I C A N O F F I C E

SAFECOURT APARTMENTS, LEKKI, LAGOS

This project by the Biotech Team is for the supply, installation andcommissioning of Extended Aeration Wastewater Treatment Plant for

1,000PE at Safe Court Apartments, Lekki, Lagos.

Project Name: Wastewater Treatment for 200 Flats (1,000PE)

Client: Safe Trust Mortgage Bank

Completion Date: November 2011

OASIS CENTRE, IKEJA LAGOS, LAGOS

The Project is a commercial development comprising of a

shopping mall & hotel. Total Population is 1,166PE

Population distribution in accordance to building use:

Hotel Guest: 406: Shopping Mall (Visitors): 660: Staffs: 100

Client: Denver Building Services Ltd.

Project Scope: Wastewater Treatment Plant for a Retail & Hotel

Development

Sector: Retail & Hospitality

Category: Wastewater

Treatment Process: BTS N20

Completion Date: Ongoing

Heirs Park Residences, Lekki (320PE Mini Estate)

This project by the Biotech was for the supply, mechanical andelectrical installation, commissioning and maintenance of anabove ground BTM wastewater treatment plant, Forward FeedPumps and Inlet Spiral Screen at Heirs Park Residences developedby Redriff Real Estate Dev. Population 250PE.

Client: Redriff Real Estate Development Company

Completion Date: October 2015

Degree of treatment: 20:30:20mg/l BOD:SS:Ammonia

Technology: Biotech BTM

This project by Biotech Team was for the supply, Mechanical,electrical installation and commissioning of a BTS N20 wastewatertreatment plant for 32 Terrace Houses at Harbour Point, Ijoraincluding installation of Sewer lines for the entire estate.

Project Scope: Pipe works, Manholes and Wastewater TreatmentPlant at Habour Point (32 Terrace Houses)

Client: Practical Habitat

Sector: Domestic

Category: Wastewater Treatment

Completion Date: April 2014

Treatment Process: Biotech BTS N20

Harbour Point Ijora

OVH ENERGY MARKETING LTD

This project by Biotech was for the supply, mechanical, electricalinstallation and commissioning of Biotech BTS N20 wastewatertreatment plant at OVH Energy, Apapa

Sector: Commercial

Category: Wastewater Treatment

Client: OVH Energy Marketing Ltd

Overview: Pipe works and Wastewater Treatment PlantDegree of treatment: 20:30:20 mg/l BOD:SS:AMMONIATechnology: Biotech BTS N20

General Hospital, Surulere

This project executed by Biotech was for the supply, mechanical and

electrical installation and commissioning of Biotech above ground BTM

wastewater treatment plant at Randle General Hospital, Surulere.

Project Scope: Wastewater Treatment Plant for a Hospital

Client: Lagos State Ministry of Health

Sector: Health Care

Category: Wastewater Treatment

Completion Date: December, 2013

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: Biotech BTM

General Hospital, Surulere – Additional Project Pictures

WEMA BANK AWOLOWO ROAD, IKOYI, LAGOSThis project by the Biotech Team was for the design, supply, mechanical

and electrical installation, commissioning and maintenance of a Biotech

BTS N20 wastewater treatment plant at WEMA Bank Branch Awolowo

Road, Ikoyi Lagos

Client: Brick House Construction

Project Scope: Wastewater Treatment Plant for a Bank Branch

Sector: Commercial

Category: Wastewater Treatment

Completion Date: April 2016

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Treatment Process: Biotech BTS N20

Sector: 350PE Commercial Development

Category: Wastewater Treatment

Completion Date: August 2019

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: Biotech BTS N20

Eko Pearl Office Development

Honeywell Flourgate Sagamu, Ogun state

Client: Honeywell Flour Mills

Sector: Commercial

Category: Wastewater Treatment Plant

Completion Date: July 2018

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Treatment Process: Biotech BTS N20

INTERNATIONAL ARBITRATION CENTER, LEKKI

This project by the Biotech was for the supply, installation and commissioning of

an BTS N20 wastewater treatment plant with a capacity of 32,000ltr/day

Client: Banci Nigeria Limited

Project Name: Sewage Treatment Plant for Court House

Sector: Commercial

Category: STP & Forward Feed Pumping Statio

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Treatment Process: Biotech BTS N20

Completion Date: March 2015

VEDIC LIFECARE CLINIC LEKKI

This project by the Biotech Team was for the supply installation,

commissioning and follow on maintenance of a BTS

N20wastewater treatment plant at Vedic Lifecare, Lekki.

Client: Vedic Lifecare Nigeria Limited

Project Scope: Wastewater Treatment Plant for a Diagnostic

Center

Sector: Health

Category: Wastewater Treatment

Completion Date: July 2013

Degree of treatment: 20:30:20mg/l BOD:SS:AMMONIA

Treatment Process: Biotech BTS N20

Lamb Court, Banana Island (mini estate)

This project by the Biotech team was for the design supply, mechanicaland electrical installation and commissioning of an above ground BTMwastewater treatment plant, Forward Feed Pumps and Inlet SpiralScreen at Lamb Court, Banana Island.

Client: Boldstep Nigeria Limited

Project Scope: Wastewater Treatment Plant for 250PE Mini Estate

Completion Date: January 2012

Technology: Biotech BTM

GUEST HOUSE, OSBORNE, IKOYI, LAGOS

This project by the is for the supply, mechanical and

electrical installation, commissioning and maintenance

of a BTS N20 wastewater treatment plant and Pumping

Solutions at Osborne Foreshore, Ikoyi

Client: Chief Phillip Asiodu

Project Scope: Guest House

Completion Date: December 2018Technology: BTS N20

CAR SHOW ROOM LEKKI, LAGOS

This project by the Biotech Team was for the design, supply,installation and commissioning of a BTS N20 wastewatertreatment plant at Kunech Car Show Room, Lekki.

Client: BQC CONSULTANTS

Sector: Commercial

Project Scope: Wastewater Treatment Plant for a Car ShowRoom

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Completion: September 2014

Technology: BTS N20

This project by the Biotech Team was for the design, supply,installation and commissioning of a BTS N20 wastewatertreatment plant at Ikoyi.

Client: Littlefield Investment

Project Scope: Wastewater Treatment Plant & Grease Trap

Completion Date: 2013

RESIDENTIAL APARTMENTS IKOYI, LAGOS

RESIDENTIAL APARTMENT, BANANA ISLAND

This project by the Biotech was for the design, supply, installation

and commissioning of an BTS N20 wastewater treatment plant

for: 8 nos Residential Apartment in Banana Island, Ikoyi Lagos.

Client: PRIVATE

Project Scope: Wastewater Treatment Plant for a Single Building

Completion Date: July 2014

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Treatment Process: BTS N20

OIL STATION COMPLEX, ADMIRALTY WAY LEKKI

This project by the Biotech Team was for the supply, mechanical and

electrical installation and commissioning of a BTS N20 wastewater

treatment plant at Lekki Phase 1, Lekki

Client: Ascon Oil NigeriaProject Scope: Wastewater Treatment Plant for a filling Station

Sector: Commercial

Category: Wastewater Treatm51ent

Completion Date: July 2015

Technology: BTS N20

WESTON SHEBA PARKS

This project by the Biotech is for the supply, mechanical and electrical

installation and commissioning of a BTS N20 Sewage treatment plant.

Client: Oshea Projects Limited

Project Scope: Wastewater Treatment Plant for a mini estate

Sector: Residential Development (Commercial and Residential)

Category: Wastewater Treatment

Completion Date: March 2015

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTS N20

ROSE OF SHARON, IKOYI

This project by the Biotech Team is for the supply, installation andcommissioning of a BTS N20 wastewater treatment plant for 50

residents

Client: Vicak Consult

Project Scope: Wastewater Treatment Plant for a residential

development

Completion Date: December 2015

Degree of Treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Sector: Residential

Category: Wastewater Treatment

Technology:BTS N20

THE BUILTFORMS – PARKVIEW, IKOYI

This project by the Biotech Team was for the design, supply,

installation and commissioning of a BTS N20 wastewater

treatment plant at Parkview Ikoyi.

Client: The Builtforms

Project Scope: Wastewater Treatment Plant for 15nos Residential

Apartments

Sector: Residential

Category: Wastewater Treatment

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTS N20

Completion Date: November 2015

This project by the Biotech Team is for the design, supply, installation

and commissioning of a BTS N20 wastewater treatment plant at

Cooper Road Ikoyi.

Client: Consultant Collaborative Partnership

Project Scope: Wastewater Treatment Plant for a Mixed Development

Sector: Mixed Development Commercial and Residential)

Category: Wastewater Treatment

Completion Date: December 2015

COOPER ROAD, IKOYI

RUXTON RESIDENTIAL DEVELOPMENT

This project by the Biotech Team was for the supply, installation

supervision and commissioning of BTS N20 wastewater treatment plant

at Ruxton Terraces.

Client: Oshea Projects

Project Scope: Wastewater Treatment Plant for 12nos Terrace Houses

Sector: Residential

Category: Wastewater Treatment

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTS N20

VINET RESIDENTIAL DEVELOPMENT, IKOYI

This project by the Biotech Team was for the supply, installation

supervision and commissioning of BTS N20 wastewater treatment

plant

Client: Private Client

Project Scope : Wastewater Treatment Plant for Residential Apartments

Sector: Residential

Category: Wastewater & Water Treatment

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTS N20

Completion Date: November 2016

RESIDENDITIAL DEVELOPMENT, BANANA ISLAND

This project by the Biotech Team was for the supply, installation

supervision and commissioning of a BTS N20 wastewater

treatment plant and packaged water treatment at Banana

Island.

Client: Private Client

Project Name: Wastewater & Water Treatment Plant for 5nos

Residential Apartments

Sector: Residential

Category: Wastewater & Water Treatment

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTS N20 & Filtration System

Completion Date: November 2015

RESIDENTIAL APARTMENTS, PARKVIEW, IKOYI

This project by the Biotech Team is for the supply, installation andcommissioning of BTS N20 wastewater treatment plant at 8 nos Residential

Apartment in Banana Island, Ikoyi Lagos.

Project Scope: Wastewater Treatment for 8nos Apartments

Client: Arc Bayo Odunlami

Completion Date: November 2015

This project by the Biotech Team was for the supply, installationsupervision and commissioning of 12 (nos) BTA Wastewater

treatment plant for an estate of 52 units of houses in 12 Blocksand maximum occupancy of 312 residents.

Client: Practical Habitat

Project Scope Wastewater Treatment Plant for An Estate

Sector: Residential

Category: Wastewater

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTA

Completion Date: 2014

PRAISEVILLE PHASE 1,OGUDU, LAGOSPRAISEVILLE PHASE 1,OGUDU, LAGOS

This project by the Biotech Team is for the supply, mechanical and

electrical installation and commissioning of BTA wastewater

treatment plant at Cameron Road, Ikoyi.

Client: Private

Project Scope: Wastewater Treatment Plant for a Single House

Sector: Domestic

Category: Wastewater Treatment

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTAProjected Completion Date: November 2016

Private Residence, Ikoyi

Private Residence, Ikoyi

This project by the Biotech Team was for the supply, mechanicaland electrical installation and commissioning of a BTA wastewater

treatment plant at a private Residence, Ikoyi , Lagos.

Client: Mr Shobanjo

Project Scope: Wastewater Treatment Plant for a Single Duplex

Sector: Domestic

Category: Wastewater Treatment

Completion Date: November, 2011

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTA

Private Residence, Ogun State

This project by the Biotech Team was for the design, supply, mechanical

and electrical installation, commissioning and of a BTA wastewater

treatment plant at a private residence, Ogun State.

Client: Mr Shobanjo

Project Scope: Wastewater Treatment Plant for a Single House

Sector: Domestic

Category: Wastewater Treatment

Completion Date: September, 2013

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTA

PRIVATE DEVELOPMENT, NICON TOWN

This project by the Biotech Team is for the design, supply,

mechanical and electrical installation, commissioning and

maintenance of an ASP wastewater treatment plant, at Nicon

Town, Lekki Expressway, Lagos

Client: Private

Project Scope: Wastewater Treatment Plant for a Residential

Development

Sector: Residential

Category: Wastewater Treatment

Technology: BTA

Projected Completion Date: October 2016

This project by the Biotech Team is for the supply,

mechanical and electrical installation and commissioning of

BTA wastewater treatment plant at a Private residence Ikoyi,

Lagos.

Client: Consultant Collaborative Partnership

Project Scope: Wastewater Treatment Plant for a Single

House

Sector: Domestic

Category: Wastewater Treatment

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA Technology: BTA

Projected Completion Date: November 2016

SKA VILLA, IKOYI, LAGOS

ORITSEMONE’S PLACE, LEKKI

This project by the Biotech Team is for the supply, mechanical and

electrical installation and commissioning of BTA wastewater

treatment plant at Oritsemone’s Place VGC Lekki.

Client: Oritsemone’s Place

Project Scope: Wastewater Treatment Plant for a Single House

Sector: Domestic

Category: Wastewater Treatment

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTAProjected Completion Date: November 2016

PRIVATE DEVELOPMENT, NICON TOWN

This project by the Biotech is for the design. supply, mechanical and

electrical installation and commissioning of an BTA wastewater

treatment plant, at Nicon Town, Lekki Expressway, Lagos

Client: Smata Squared Development

Project Scope: Wastewater Treatment Plant for a Residential

Development

Sector: Residential

Category: Wastewater Treatment

Degree of treatment: 20:30:20 mg/l BOD:SS:AMMONIA

Technology: BTA

Completion Date: October 2016

FEDERAL PALACE HOTEL

This project by the Biotech Team was for the supply,

installation supervision and commissioning of a

water treatment plant at Federal Palace Hotel,

Victoria Island.

Project Scope: Water Treatment System for a Hotel

Sector: Hospitality

Category: Water Treatment

Treatment Process: Deep Bed Filtration Process Using

Quantum DMI Media, Activated Carbon with

Automated Backwash Head UnitsCapacity/Flow

Rate: 80-120m³/day

BIOTECH SOLUTION COMPANY LIMITED

Plot 16, Otunba Jobi Fele Way,

Tax Professional House, (2nd Floor)

Alausa Ikeja, Lagos

Nigeria.

Tel: +234 1 2914545

+234 81 68285849

Email: [email protected]

Website: www.biotechng.com

CONTACT

THANK YOU.