best practice - lessons learned · best practice - lessons learned general contract management ......

10
Best Practice - Lessons learned General Contract Management Roy Piek, Director PMC TEBODIN Moscow | April 19, 2017

Upload: haanh

Post on 21-Jun-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

Best Practice - Lessons learned General Contract Management

Roy Piek, Director PMC

TEBODIN

Moscow | April 19, 2017

Visualization of Influence vs Expenditures during project

Tebodin |Chemical Event | RP April 19, 2017 page 2

Detail

Engineering

Project Life Cycle

Le

ve

l o

f In

flu

en

ce

Pro

ject E

xp

en

ditu

res

Major Influence Decreasing Influence Low Influence

Project

Authorization

Scouting

Phase

Conceptual

Design Phase

BASIC

Engineering

TO /

SU

Mechanical

Completion

Overall

Cost

Influence

Curve

Project

Expenditures

Procurement

/Construction

Point where changes

influence result rapidly

BIM – it is a tool for engineering, when 3D model is developed with

indication of technical, financial and time attributes of each element.

Tebodin executes projects using this technology in

order to reach high quality and time & cost saving.

Building Information Modeling (BIM)

Tebodin |Chemical Event | RP April 19, 2017 page 3

BIM advantages*:

▪ 10% - saving of the contract value through clash

detections.

7% - reduction of project time

3% - cost estimation accuracy (MTO)

80% - reduction in time taken to generate a cost

estimate

*Based on Stanford University center for Integrated Facilities Engineering

Engineering - Procurement - Construction: EPC

Contractor with responsibility for design (all or parts)

Project Management - Contract/Consultancy: PMC

Management company controlling Contractor(s) & Construction

Engineering - Procurement - Construction

Management: EPCM

Design/Management company responsible for design (detail

level t.b.d.) and controlling Contractor(s) & Construction

Various contract strategies

Tebodin |Chemical Event | RP April 19, 2017 page 4

EPC/PCM or EPCM ? Advantages compared

Tebodin |Chemical Event | RP April 19, 2017 page 5

EPC + PMC:

One Stop Shopping "One point of

Contact"

Best/Only for well defined projects

before EPC Contractor selected

(Minimal Unknowns)

Hands off" client approach to

project

Minimal Legal / Financial Risk

Minimal Client Staffing

Requirements

EPCM:

More Control over (Engineering)

Process`

Better for less defined projects with

anticipated changes to scope of supply

Less Legal Litigation (Identify issues

early and remedy situation before larger

problems arise)

Owner's contracting Flexibility (different

contractors, materials purchasing etc)

• General Contractor was changed

to multi-subcontractors with PMC

team >20 FTE on site

• No general contractor at site,

these functions taken over by the

PMC team

• Logistics and Materials by PMC

team

• Brownfield requires huge

attention (design, utilities,

materials, interfaces, etc.)

Recent experience CherepovetsTebodin is the partner for integration of foreign installations in large plants

Tebodin |Chemical Event | RP April 19, 2017 page 6

General contractor vs multi subcontracting:

▪ Only the strong points of a contractor shall be used, scope which contractor

has weaknesses shall not be hired.

▪ For different scope of works, multiple contractors to involve with proven

experience

▪ To avoid any monopoly position of one company

▪ Only financially strong companies to involve

▪ It is an option to have No general contractor at site: it can be done

▪ Purchasing by three party agreements is an option

See also the investors guide for information on many more topics

Tebodin |Chemical Event | RP April 19, 2017 page 7

Choice of Project organization is crucial for success

Best practice / Lessons learned , general contract

management

Tebodin |Chemical Event | RP April 19, 2017 page 8

• Introducing of extra contractual clauses to the contractors contract: Examples

• avoid claims of extra works based on an incomplete BOQ: working drawings and clients requirements shall

prevail over BOQ

• avoid charge of huge indirect cost by contractors in case of delays on others behalf: there shall be an

indication/limitation of monthly indirect cost in the contract or main proposal;

• avoid charge of huge amounts of manpower for extra works: in the contract a man power schedule shall be

included, which can be used against (over estimated) extra works negotiations;

• Use performance guarantee retention clauses (up to 10% to hold from monthly payments)

Watch out: First delays up to 1 to two months occur already at start of the construction: Management/control of in

time contract signing by client, LOI, and in time advance payment (contractors promise to start based on LOI, but

later will claim delay on the contract signing. Do not use the LOI advantage in the critical path.

Best practice / Lessons learned , general contract

management

Tebodin |Chemical Event | RP April 19, 2017 page 9

If you want to be secured

by a reliable and cost

aware engineering and

PMC company, call us.

We make CHEMICALS work