Page 1: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

1

BERLIAN EASTFIELD DEVELOPMENT PLAN

Prepared by G2:

Amira binti Abdul Rasib

Chiew Kwang Chian

Dexter Brian Anak Nyambang

Mohamad Azir Syazwan bin Sufri

Mohammed Ahmed Omer

Mohd Farid Bin Mohd Toha

Muhammad Syafiq Syahidzat Sabri

Thian Hui Chie

Supervisor: Dr Khaled Abdalla Elraies

Page 2: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

2

RESERVOIR ENGINEERING

Page 3: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

3

OUTLINE

Introduction Reservoir Data Depletion Strategy Proposed Number of Wells Production Profile Reservoir Management Plan (RMP) EOR Considerations

Page 4: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

4

INTRODUCTION – PREVIOUS VOLUMETRIC ESTIMATION

SandSTOIIP (MMstb)

Low Case Base Case High Case

M 2/3 23.4 50.5 89.8

M 7/8 52.4 62.1 73.4

M 9/14 33.9 41.9 58.0

M 15 3.8 5.0 6.4

TOTAL 113.5 159.5 227.6

SandGIIP ( Bscf)

Low Case Base Case High Case

L 16.6 22.9 30.9

M 2/3 2.8 3.2 3.7

TOTAL 19.4 26.1 34.6

Page 5: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

5

PVT DATA & INFORMATION PVT data of bottomhole sample from BE-1, M2A sand

Pi >>

Pb >>

• Datum = 1300 m ss• Initial Pressure (Pi) @ datum = 1854 psig• Reservoir Temperature @ datum = 215 °F• Bubble Point Pressure (Pb) = 1332 psig

Page 6: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

6

GOR & RS

Rsi = 1400 scf/stb

Pb = 1332 psig

Source: Reservoir Engineering Handbook by T.Ahmed (2001)

Page 7: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

7

PVT DATA & INFORMATION Hydrocarbon Analysis on surface fluids:

Page 8: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

8

DEPLETION STRATEGY

2 depletion strategies are proposed: Natural depletion drive Water injection depletion drive

Natural Depletion Drive: Recovery factor ≈ 20% of STOIIP Initial production rate = 2000 – 3000 stb/d (from

production test results) Production rates decline (exponentially) @ 38% per year Each well is expected to produce ≈ 3 MMstb Well lifetime ≈ 10 years Abandonment rate = 150 stb/d of gross liquid Water cut < 6% throughout production life

Page 9: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

9

DEPLETION STRATEGY

Water Injection Depletion Drive: Natural aquifer does not contribute much Water is injected to support reservoir pressure (not to

flood or displace oil) Recovery factor ≈ 35% of STOIIP Initial production rate = 3000 – 4000 stb/d (from

production test results) Production rates remain constant (plateau) until 40% of

EUR had been produced, then decline @ 40% per year Each well is expected to produce ≈ 5 MMstb Well lifetime ≈ 10 years GOR = Rs throughout production life since Pres > Pb

Maximum injection rate = 4000 stb/d Voidage replacement ratio, VRR = 1.44

Page 10: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

10

PROPOSED NUMBER OF WELLS & LOCATIONS – NATURAL DEPLETION

UnitSTOIIP

(MMstb)EUR (20%)

No. of Wells*

Dual Completion

M2/3 50.52 10.10 31

M7/8 62.09 12.42 4

M9/14 41.86 8.37 21

M15 4.98 1.00 0

Total 159.46 31.89 9 2

TOTAL WELLS 11

* Each well will produce ≈ 3 MMstb of oil throughout production life

Page 11: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

11

PROPOSED NUMBER OF WELLS & LOCATIONS – NATURAL DEPLETION

11 producers

Page 12: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

12

PROPOSED NUMBER OF WELLS & LOCATIONS – WATER INJECTION DEPLETION

UnitSTOIIP

(MMstb)EUR (35%)

No. of Wells*

Dual Completio

n

No. of Injectors**

M2/3 50.52 17.68 31

14

M7/8 62.09 21.73 4

M9/14 41.86 14.65 31

M15 4.98 1.74 0

Total 159.46 55.81 10 2

TOTAL WELLS 12 14

* Each well will produce ≈ 5 MMstb of oil throughout production life

** VRR =1.44 rb/stb; Highest production rate = 39 Mstb/day; Max injection rate = 4000 stb/d

Page 13: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

13

PROPOSED NUMBER OF WELLS & LOCATIONS – WATER INJECTION DEPLETION

Injectors12 producers, 14 injectors

Page 14: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

14

PRODUCTION PROFILE (MONTHLY) – NATURAL DEPLETION

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 97 1011050.00

5.00

10.00

15.00

20.00

25.00

30.00

35.00

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

Rate (Mstb/d) Cumulative Production

Month

Prod

uctio

n Ra

te (M

stb/

day)

Cum

ulati

ve P

rodu

ction

(MM

stb)

Rate decreases due to S/D of wells which flows below abandonment rate

Page 15: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

15

PRODUCTION PROFILE (YEARLY) – NATURAL DEPLETION

1 2 3 4 5 6 7 8 90.00

5.00

10.00

15.00

20.00

25.00

30.00

35.00

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

Rate (Mstb/d) Cumulative Production

Year

Prod

uctio

n Ra

te (M

stb/

day)

Cum

ulati

ve P

rodu

ction

(MM

stb)

Page 16: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

16

PRODUCTION PROFILE (MONTHLY) – WATER INJECTION DEPLETION

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 97 1011050.00

10.00

20.00

30.00

40.00

50.00

60.00

0.0

10.0

20.0

30.0

40.0

50.0

60.0

Rate (Mstb/d) Cumulative Production

Month

Prod

uctio

n Ra

te (M

stb/

day)

Cum

ulati

ve P

rodu

ction

(MM

stb)

Plateau ends after 40% EUR is produced

Page 17: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

17

PRODUCTION PROFILE (YEARLY) – WATER INJECTION DEPLETION

1 2 3 4 5 6 7 8 90.00

10.00

20.00

30.00

40.00

50.00

60.00

0.00

10.00

20.00

30.00

40.00

50.00

60.00

Rate (Mstb/d) Cumulative Production

Year

Prod

uctio

n Ra

te (M

stb/

day)

Cum

ulati

ve P

rodu

ction

(MM

stb)

Page 18: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

18

COMPARISON OF PRODUCTION RATE DECLINATION

1 2 3 4 5 6 7 8 90.00

5.00

10.00

15.00

20.00

25.00

30.00

35.00

40.00

45.00

Natural Depletion Water Injection

Year

Prod

uctio

n Ra

te (M

stb/

day)

Page 19: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

19

COMPARISON OF CUMULATIVE PRODUCTION

0 1 2 3 4 5 6 7 8 9 100

10

20

30

40

50

60

Natural Depletion Water Injection

Year

Cum

ulati

ve P

rodu

ction

(MM

stb)

Page 20: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

20

RESERVOIR MANAGEMENT PLAN Objectives:

Maximize recoverable oil Maintain reservoir pressure above bubble point (1800 psia) Abide by PETRONAS Procedures and Guidelines for Upstream

Activities (PPGUA)

Operation Strategies: Water Injection to keep P > Pb

VRR = 1.44 and maximum injection rate per well = 4 Mstb/d Gas lift in third year to maintain well rate

Surveillance & Monitoring: Monitor water cut & GOR Utilize S/I for well tests (e.g. interference test, pulse test)

Page 21: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

21

ENHANCED OIL RECOVERY (EOR) CONSIDERATIONS

EORTherm

alGas

Chemical

Others

EOR Considerations

Thermal Very costly, suitable for field with oil of high viscosity and low API gravity

Chemical Costly and dependent on many factors: current oil price, water hardness, salinity, temperature etc.

Gas Most suitable compared to other EOR methods. Can consider gas re-injection.

Other Microbial & electromagnetic – new technique, less confidence

Page 22: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

22

DRILLING

Page 23: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

23

OUTLINE

Rig selection Casing design Bit selection Drilling Fluid design Cementing design

Page 24: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

24

RIG SELECTION

• Cost• Rig stability• Water depth offshore

Sea level for Berlian East field = 249.28ft (76m)

Drilling Rigs Water Depth (ft) Average Day Rate (USD)

Jacket Rig 40 – 400 ft $ 40,000

Tender Assisted Rig Anchor length $ 130,000

Jack Up Rig < 350 ft $ 140,000

Semi Submersible Rig 150 – 6000 ft $ 414,000

Drill Ship/ Submersible Rig 1000 – 13000 ft $ 450,000

Page 25: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

25

Jack-up Rig• Suitable for shallow depth water • Stable work platform• Lower mobilization cost• Safer and lower risk

Page 26: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

26

CASING DESIGN

Casing Casing OD (in) Depth (m-TVDSS)

Conductor 26 “ 80

Surface 13 3/8 “ 400

Intermediate 9 5/8 “ 850

Production 7 “ 1330

Page 27: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

27

CASING SETTING DEPTH

Page 28: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

28

BIT SELECTION

Casing Casing Size OD (in)

Type of Bit Bit Size (in)

Conductor 26 Rock Bit 30

Surface 13 3/8 Rock Bit 17 ½

Intermediate 9 5/8 PDC Bit 12 ½

Production 7 PDC Bit 8 ½

•PDC bit has most efficient cutting mechanism in sedimentary rock such as sandstone and shale•PDC also have high rate of penetration and long bit life span.

Page 29: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

29

DRILLING FLUID DESIGN

Depth, m-TVDSS Mud Design

0-200 Guar Gum Spud Mud

200-1330 High Performance Water Based Mud (HPWBM) + KCL/PHPA additive

• HPWBM performance comparable with Synthetic Based Mud.• Offer environment compliance.• Has been successfully tested on offshore (shallow and depth water). • Cost effective compared to Oil Based Mud.

Page 30: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

30

CEMENT DESIGN

Class “G” cement type Additives:

Retarder Fluid loss Dispersant

Page 31: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

31

Page 32: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

32

COMPLETION

Page 33: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

33

OUTLINE

Preliminary Studies and Well Test Well Locations Completion Matrix Well Completion Options Proposed Well Completion Proposed Perforation Design Proposed Sand Control Design Completion Design Diagram Completion Problem

Page 34: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

PRELIMINARY STUDIES AND WELL TEST Field should be developed by initially targeting;

M formation > L formation Sand production were traced in 6-well High permeability; 118-900md Geologically younger Tertiary sedimentary

formations; little cementation material between sand grains

Page 35: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

WELL LOCATIONS

12 producers, 14 injectors

Page 36: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

COMPLETION MATRIX

UnitSTOIIP (MMst

b)

OIL PRODUCER WELL

W1 W2 W3 W4 W5 W6 W7 W8 W9 W10

W11

W12

M2/3 50.52

M7/8 62.09M9/1

4 41.86

M15 4.98

Page 37: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

WELL COMPLETION OPTIONS

COMPLETION PARAMETERS OPTIONS

Tubing size Range from 2-3/8” to 4-1/2”

Type of completion Single or Dual String

Tubing material Carbon steel, Low Alloy Steel or Corrosion Resistance Alloy (CRA)

Perforation Tubing Conveyed Perforating/ Wireline Conveyed Perforating

Artificial Lift ESP or Gas Lift

Sand Control Sand Screen or Gravel Pack

Page 38: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

WELL COMPLETION SELECTION COMPLETION PARAMETERS SELECTION COMMENT

Well Orientation Vertical Low risk

Tubing size 2-7/8”, 6.5 PPF, J-55

Based on Nodal Analysis, Shallow Depth

Tubing materialCorrosion Resistance Alloy (CRA)

Due to high carbon dioxide, CO2

Perforation TCP 200psi overbalance (6 shots/foot, 60⁰ degree)

Sand Control Sand Screen Sand production traced

Artificial Lift Gas LiftDepending on production requirements at designated depth

Type of completion

Single and Dual String

For well more than 2 drainage points, used dual strings

Page 39: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

PERFORATION DESIGN

Parameters Selection Justification

Perforation Density (spf) 6

Low flow rate of single perforation, low fluid velocity, low sand

Phase 60 provide more efficient flow characteristics

Charge Type DPProvide mechanical stability

Penetration Depth 10-30ft

Perforation Diameter

8-10 times size of the particle Best effectiveness

Completion FluidNitrogen and Clear Solid Brine

Cheap, avoid contaminants precipitation and crystallizationDensity: 7.5 – 10ppg

Page 40: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

SAND CONTROL DESIGN CRITERIA

Gravel Packing

Parameters Criteria

Size US Mesh 12/20 – 40/70 (5 times mean diameter of formation sand)

Sphericity ≥0.6

Roundness ≥0.6

Class Natural or Manmade

Screen

Gravel Size (US Mesh) Gravel Size (in.) Screen Gauge (in.)

12/20 0.0660-0.0330 0.020

16/30 0.0470-0.0230 0.016

20/40 0.0330-0.0165 0.012

40/60 0.0165-0.0098 0.008

Page 41: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

COMPLETION SCHEMATIC DIAGRAM(SINGLE STRING)

Wellhead1. Assemble 1

1. 2-7/8” Flow Coupling2. 2-7/8” TR-SCSSSV3. 2-7/8” Flow Coupling

2. 2-7/8” GLM (Dummy Valve)3. 2-7/8” CIV Mandrel4. 2-7/8” PDG Mandrel5. 2-7/8” Sliding Sleeve6. 2-7/8” XN Nipple7. Single Swell Packer8. EOT

1

2

34

567

8

Page 42: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

COMPLETION SCHEMATIC DIAGRAM(DUAL STRING)

Wellhead1. Assemble 1

1. 2-7/8” Flow Coupling2. 2-7/8” TR-SCSSSV3. 2-7/8” Flow Coupling

2. XN-Nipple3. 2-7/8” GLM (Dummy Valve)4. Assemble 2

1. Flow Coupling2. XD-SSD3. Flow Coupling

5. Dual Swell Packer6. Assemble 37. Single Swell Packer8. XN Nipple9. EOT

12

3

45

6

78

9

Page 43: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

COMPLETION SCHEMATIC DIAGRAM(INJECTION WELL)

Wellhead1. Assemble 1

1. 2-7/8” Flow Coupling2. 2-7/8” TR-SCSSSV3. 2-7/8” Flow Coupling

2. X-Nipple3. XD-SSD4. Single HYD Packer5. X-Nipple6. EOT

1

2

34

5

6

Page 44: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

COMPLETION PROBLEMSPRODUCTION

PROBLEM EFFECT MITIGATION PLAN

Wax deposition • Flow assurance issue• Surface/downhole

equipment blockage

• Thermodynamic or chemical injection approach

• Maintenance pigging operation

Scale formation • Wellbore and flowline blockage

• Reduction in production rate

• Fluid filtration • Scale inhibitor• Acid treatment

Emulsion formation

• Cause formation damage• Well productivity decrease

• Use surfactant; reduce surface and IFT of fluids

High CO2 content

• Facilities corrosion (valve, pipeline)

• Use corrosion inhibitor, CRA

Sand Production • Erosion at surface and downhole equipment

• Collapse of the formation

• Sand screening, minimum entry hole diameter, high shot density

Page 45: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

45

FACILITIES

Page 46: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

46

OUTLINE

Design Philosophy Proposed Philosophy Proposed Development Plan Screening Process Development Plan Selection

Page 47: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

47

INTRODUCTION

Provide information on the surface facilities

based on the subsurface production in order to

develop Berlian East Field

Design basis

Environment

Sea Floor Site

Production

Processes

Flexibility

Page 48: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

48

26 wells [12 producers and 14 water injectors]

tie-in with 2 mother platforms (2 SWP for each mother platform)

Full well stream the crude oil to Berlian complex via pipelines

DESIGN PHILOSOPHY

Page 49: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

49

Unmanned facilities

Minimum maintenance

Meet simultaneous production and drilling

operations and workover requirements.

Remote well testing on monthly basis.

Maximise remote monitoring and control

capability from supply terminal at pekan.

Over 9 years of operating life and 30 years of

design life.

PROPOSED PHILOSOPHY

Page 50: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

50

PROPOSED DEVELOPMENT PLAN

Option A – Satellite Wellhead Platform:

A1) Satellite wellhead platform, tie-in to

mother platform and full well stream

pipeline to Berlian complex.

A2) Connecting the Satellite Wellhead

platform to a FPSO.

A3) Connecting the Satellite Wellhead

platform to a MOPU.

Page 51: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

51

Option B – Subsea Wellhead Platform:

B1) Subsea wellhead platform, tie-in to

mother platform with full well stream

pipeline to Berlian Complex.

B2) Connecting the Subsea wellhead

platform to a FPSO

B3) Connecting the Subsea wellhead

platform to a MOPU

Page 52: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

52

Option C – Central Processing Platform:

C1) Central processing platform and tie-in

with Berlian export oil pipeline to

Pekan Crude Oil Terminal

C2) Central processing platform and

pipeline to Pekan Crude Oil Terminal.

Page 53: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

53

SCREENING PROCESS

FPSO eliminated;

High cost – rental

Major modification

Bad weather condition

Subsea Wellhead Platform eliminated;

Only for deepwater operation

High cost

Page 54: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

54

CPP eliminated;

High cost – start-up, operating &

abandonment

Require manpower

Complexity operation

MOPU

Bad weather – same as FPSO

Page 55: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

55

DEVELOPMENT PLAN SELECTION

We opted the Satellite wellhead platform, tie-

in to mother platform and full well stream

pipeline to Berlian complex (Option A1)

Reason;

Low CAPEX and OPEX

Unmanned operation

Existing facilities utilized

Page 56: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

56

Substructure 6 pile-steel Riser (seabed to platform) Boat landing bay Pipeline

Top structure Crane Helipad Well servicing equipment Main production facilities;

Wellhead Three-phase separator Gas injector Electrical / lighting Flare boom

Safety equipment

Page 57: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

57

Schematic diagram of Berlian East conceptual facility design

Page 58: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

58Schematic diagram for each well location in Berlian East field

Page 59: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

59

ECONOMICS

Page 60: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

60

FISCAL TERM FOR PSC 1997

Terms Details

Contract area EPCP Block

Contract duration Max 22 years

Production period 15 years

Royalty rate 10%

Cost oil ceiling rate Oil Gas

50%60%

Profit oil share (PETRONAS: Contractor) 60:40

PSC base price US$40/bbl escalated 3% p.a. from current year

Export duty (ED) rate 10% of profit oil exported

Research cess 0.5% oil/gas entitlement

Abandonment cess 5 USD Mill

Petroleum tax rate 38%

Oil supplemental payment 60% (PSC oil price – base price) cont. PO – export duty

Fixed structure 10% per year (10 years)

Page 61: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

61

Base case

Reference year

First oil Expected to be in 2016

Production period 10 years

Decommissioning year

Exactly after 10 years of production period (2013)

Cash flow model Assumed to be in the Money of the Day (MOD) term

Base oil price US$40/bbl escalated 3% p.a. from current year

Operating cost (OPEX) 4% of cum. CAPEX per annum (fixed OPEX) plus US$3.50/bbl (variable OPEX)

Hurdle rate for IRR 15%

Discount rate 15%

ECONOMIC ASSUMPTIONS

Page 62: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

62

Production facilities Option A1: Satellite wellhead platform, tie –in to mother platform and full stream pipeline to Berlian complex

Production case • 11 producer wells•14 injector wells• RF of 20% = 5 MMSTB

NPV @ 15%

IRR 25%

CAPEX USD 393 Million

OPEX USD 303 Million

Decommisioning USD 119 Million

Payback period 2 years

Economic life 10 years

DEVELOPMENT OPTION

Page 63: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

63

1 2 3 4 5 6 7 8 9 10 11 12 13

-200

-100

0

100

200

300

400

Net Cash Flow Diagram

Year

USD

Mill.

Page 64: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

64 Payback period = 2.3 years after first oil @ year 5

1 2 3 4 5 6 7 8 9 10 11 12 13

-400

-300

-200

-100

0

100

200

Cum Net Cash Flow Diagram

Year

USD

Mill.

Page 65: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

65

REVENUE SPILT

Summary of Economic Indicators

Contrac.Petronas Govern. Capex Opex Total Project

PV Cash Surplus @ 15% 89 329 611 277 139 1445 379

Internal Rate of Return (IRR) 25% 46.8%

Payout Time 2 Years

USD Mill.

Page 66: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

66

SENSITIVITY ANALYSIS

Page 67: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

67

HSE & WELL ABANDONMENT

Page 68: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

68

HEALTH, SAFETY AND ENVIRONMENT

Objective: The design of the Berlian East facilities shall be

in accordance with the relevant PETRONAS Technical Standards (PTS).

to ensure that the facilities are operated in a safe and responsible manner.

Identified, evaluate and control all potential hazards that could cause a major accident

Page 69: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

69

HSE MANAGEMENT SYSTEM (HSE-MS)

Page 70: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

70

APPROACHES:

Safety & Risk Management Occupational Health Management Quality Management Environmental Impact Assessment

Page 71: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

71

WELL ABANDONMENT

To isolate the reserves remaining in the reservoir

No fluid movement

Page 72: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

72

ABANDONMENT DESIGN

1. Isolate perforation intervals

2. Isolate tubing & casing annulus

3. Isolate non-cemented annulus

4. Cut and pull the casing5. Plug surface cement

Well abandonment planning is considered during well construction planning.

Page 73: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

73

CONCLUSION

Page 74: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

74

CONCLUSION Reservoir Drilling

12 producer wells 14 injection wells

Completion• Internal gravel pack with wire wrapped screen

(WWS)• Tubing: 2-7/8”, 6.5 PPF, J-55 (CRA)

Facilities• 4 satellite wellhead, 2 mother platforms• Tie-in to Berlian CPP

Page 75: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

75

Economics• Payback period=??

o HSE & Well Abandonment• Personnel, equipment & facilities comply to HSE

policy

Page 76: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

76

THANK YOU

Page 77: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

77

BACK UP

Page 78: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

78

DATA AVAILABLE – FORMATION WATER Sample taken from BE-3, M2/3 sand

Appearance – Light blackish Total dissolved solids – 30.13 g/L Specific gravity @ 750 °F – 1.023 pH @ 22 °C – 8.14

Formation Water Analysis:

Page 79: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

79

DATA AVAILABLE – WELL TEST RESULTS

Page 80: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

80

DATA AVAILABLE – WELL TEST RESULTS

Page 81: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

81

SUMMARY OF RESERVOIR FLUID

Sampling datum = 1300 m ss Reservoir Pressure @ datum = 1854 psig Reservoir Temperature @ datum = 215 °F Bubble Point Pressure, Pb = 1332 psig

Oil FVF, Bo = 1.4372 rb/stb

Initial Solution Gas Ratio, Rsi = 1400 scf/stb

Page 82: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

82

PROPOSED WELL LOCATIONS – NATURAL DEPLETION

Page 83: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

83

PROPOSED WELL LOCATIONS – NATURAL DEPLETION

Page 84: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

84

PROPOSED WELL LOCATIONS – NATURAL DEPLETION

Page 85: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

85

PROPOSED WELL LOCATIONS – NATURAL DEPLETION

Page 86: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

86

PROPOSED WELL LOCATIONS – WATER INJECTION DEPLETION

Injectors

Page 87: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

87

PROPOSED WELL LOCATIONS – WATER INJECTION DEPLETION

Injectors

Page 88: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

88

PROPOSED WELL LOCATIONS – WATER INJECTION DEPLETION

Injectors

Page 89: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

89

PROPOSED WELL LOCATIONS – WATER INJECTION DEPLETION

Injectors

Page 90: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

90

SAFETY AND RISK MANAGEMENT

All personnel shall show leadership and commitment towards the HSE requirements.

HSE Hold Points shall be held to ensure that all the HSE activities requirements stipulated in the PETRONAS HSE-MS shall be carried out.

All identified concerned risk on the chemicals should be listed in the Material Safety Data Sheet (MSDS) and operational safety in the Hazards Effect Register (HER) .

Page 91: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

91

OCCUPATIONAL HEALTH MANAGEMENT

Guidelines and procedures shall be establish and implemented: Job Safety Analysis (JSA), Permit to Work (PTW), Material Safety Data Sheet (MSDS) for

consumables. Hazards Effect Registers (HER) where operation

involves heavy machineries. Offshore Safety Passport system for all

personnel - to ensure the fitness of the personnel working offshore

Page 92: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

92

QUALITY MANAGEMENT

Objective: Provide assurance and maintain control in

ensuring that all services and products resulting from its activities are in accordance with the specified requirements.

Demonstrate that any non-compliance has been appropriately endorsed, documented and resolved/close-out.

Ensure that records and hand-over documentation are properly planned, compiled and completed during work.

Page 93: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

93

ENVIRONMENTAL MANAGEMENT

Environment Impact Assessment (EIA) Approval seeking from Department of

Environment prior to project start. comprise three major steps; Preliminary

Assessment, Detailed Assessment and EIA Review.

be prepared in parallel with detail technical studies of the overall project feasibility in order to review options and to eliminate or refine alternatives regarding to environment effects.

Waste Management pollution and waste management during

installing, hook up and commissioning, drilling and production activities.

Page 94: BERLIAN EAST F IELD D EVELOPMENT P LAN Prepared by G2: Amira binti Abdul Rasib Chiew Kwang Chian Dexter Brian Anak Nyambang Mohamad Azir Syazwan bin Sufri

94

POTENTIAL DRILLING PROBLEM

Mechanical Pipe Sticking Loss of Circulation Hole Deviation Hydrogen Sulfide- Bearing Zones and Shallow

Gas