BER in SA with Oracle Primavera Delivered successfully
to show how Primavera was used in South Australia to deliver the Building Education Revolution (BER)
for school building projects.Tim Readman – Tim Readman Planning Services
![Page 2: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/2.jpg)
BER in SA • The Nation Building – Economic Stimulus Plan released on
3 February 2009 • The Building the Education Revolution (BER) program • Department for Transport Energy and Infrastructure (DTEI)
Building Management is managing the procurement process on behalf of the State Coordinator-General and the Department of Education and Children’s Services (DECS)
• Master Builders Association
![Page 3: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/3.jpg)
Implementation of BER SA• Delivery DTEI direct to the builders• No Managing contractors• Minimal administration costs• Builder responsible from design to delivery• Cost Auditors (QS)• Program - tight timeframe• Transparency
![Page 4: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/4.jpg)
BER in SA DTEI
Judi Carr - Executive Director, Building Management, Derek Cruickshank - Principal Project manager
![Page 5: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/5.jpg)
Budget for schools• School budget $250,000 to $3m each• Construction Design, demolition, construction Fit
out - 88.5% • Building contingency 7%• FF & E - School Equipment 2.75%• Insurance 0.25%• Planning & report DECS/DETI 1.5%
![Page 6: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/6.jpg)
Standardisation
![Page 7: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/7.jpg)
Standard & non Standard
![Page 8: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/8.jpg)
Flow Chart of procurement
![Page 9: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/9.jpg)
Contractor School Allocation• Contractors pre qualified• Contractors applied for cluster schools • Builders allocated schools• Contractor/DTEI delivery deadlines• No big profits
![Page 10: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/10.jpg)
Smallest to largest
![Page 11: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/11.jpg)
Programme delivery• Responsible for the schedule for every school • Every school a project• Standard project schedule for each design• Schedule adapted for each school• Construction periods generous to suit large to
small contractors
![Page 12: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/12.jpg)
Standard Schedule per Design
![Page 13: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/13.jpg)
Key Milestones• Submit bid • Contract Award • Submit design, fixed price and fixed date for practical
completion • Submit final design scope, fixed price & completion date • Refurbishment price agreed • Start work• Date for Practical Completion
![Page 14: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/14.jpg)
Planners Key Deliverables• Review school project scope• Select the schedule for each project school• Put the key milestones into each contract
document• Print, and load schedule to the folderSimple ? Yes - Flexible - No!600 projects! Must be a better way.
![Page 15: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/15.jpg)
A better way• Primavera P6 Multiproject solution
![Page 16: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/16.jpg)
Simple Schedules - MSP look-a-likes
![Page 17: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/17.jpg)
Each standard & non stand school project
![Page 18: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/18.jpg)
Detailed construction schedule to determine reasonable ‘construction period’
![Page 19: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/19.jpg)
Detailed milestones , what would be monitored? Inspection dates?
![Page 20: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/20.jpg)
Programme development for school projects
• Build a template for every eventuality• Difficult to insert requirements later• Activity Codes• Cash flow – cost curves• Labour allocation• Ruled out methodology manager• Robust structure • Baselines
![Page 21: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/21.jpg)
Activity codes,, cost allocation for construction/refurbishment
![Page 22: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/22.jpg)
Cash flows? Labour Resources?
Per School
Per round, and overall
![Page 23: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/23.jpg)
Project Codes import via SDK
![Page 24: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/24.jpg)
Project Coding Options
![Page 25: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/25.jpg)
Sorting into standard & non standard projects
![Page 26: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/26.jpg)
Develop a separate schedule per school for inclusion in tender documents
• Understand school requirements• Select template school, copy paste template to
school round• Amend project coding• Amend funding amounts• Assess special requirements• PDF to contract documents• Be flexible for change
![Page 27: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/27.jpg)
Schedule Scopes
Refurbish all classroom spaces Project is 1 of 2 for school. Existing library to current standards. Refurbishment of learning area facilities supported as optimum outcome for school. Refurbishment is supported by DECS as the best option for this school with funding available, DEEWR Guidelines and space available Classrooms refurbishment focuses on bringing this facility up to 21st Century learning standards. DECS will provide schools & architects a standard refurbishment scope of work.
![Page 28: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/28.jpg)
Demonstration• To P6 school selection• Project level• Activity Screen
![Page 29: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/29.jpg)
Implementation• Individual schedule to contract documents• Coded Milestones from schedule into contract documents• Programme questions from contractors to meet deadlines• Adjusting or not adjusting contract periods• Federal government deadlines for each round• Upfront expenditure to mobilise
![Page 30: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/30.jpg)
Monitoring • Progress measurement by cash flow• School Principals verify progress by contractors• Payment made on progress of works• Reduced scope for TRPS, but ability to adapt• Database export o the DTEI data base using
reports CSV
![Page 31: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/31.jpg)
Open ReportsConfigure to export data
![Page 32: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/32.jpg)
Export to excel the data. Filter and run
• Group & sort• Filter for milestones
![Page 33: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/33.jpg)
Data Export CSV into BPIMS by IT
![Page 34: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/34.jpg)
BPIMs used for delivery integrated Primavera via excel to database
Open website communications to all
![Page 35: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/35.jpg)
Successful projects http://dtei.sa.gov.au/coordinator_general/completed_project_summaries_2#c
![Page 36: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/36.jpg)
Success• Key Milestones into contract documents• Project Schedules to each contractor• Adaptable to change• Satisfaction
![Page 37: Ber in sa with oracle primavera delivered successfully](https://reader036.vdocuments.site/reader036/viewer/2022062319/55524dcbb4c9059a4f8b4e33/html5/thumbnails/37.jpg)
BER in SA with Oracle Primavera Delivered successfully
• Questions
Completed Project Summaries - Department for Transport, Energy and Infrastructure (DTEI)