before the maharashtra electricity regulatory commission 58 42/order-17 of 2015-08112016.pdf ·...
TRANSCRIPT
MERC Order in Case No. 17 of 2015 Page 1 of 19
Before the
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005
Tel. No. 022 22163964/65/69 – Fax 022 22163976
E-mail: [email protected]
Website: www.mercindia.org.in/www.merc.gov.in
CASE No.17 of 2015
In the matter of
Petition of Maharashtra Electricity Distribution Co. Ltd. for determination of Cross-
Subsidy Surcharge for the period from 1.9.2013 to 28.2. 2014
Coram
Shri. Azeez M. Khan, Member
Shri. Deepak Lad, Member
Maharashtra State Electricity Distribution Co. Ltd. Petitioner
Appearance
For the Petitioner :Shri. Ashish Singh (Advocate)
Shri. Abhijit Deshpande (Representative)
Shri. D. H. Kulkarni (Representative)
ORDER
Dated: 8 November, 2016
The Maharashtra State Electricity Distribution Co. Ltd. (MSEDCL) has filed a Petition
on 9 January, 2015 for determination of the Cross-Subsidy Surcharge (CSS) for the period
from 1 September, 2013 to 28 February, 2014. The Petition has been filed consequent to the
Judgment of the Appellate Tribunal for Electricity (ATE) dated 11 September, 2014 in Appeal
Nos. 23 of 2014 and 65 of 2014 setting aside the Order of the Commission in Case No. 107 of
2013 and remanding the matter to the Commission for the re-determination of the CSS for that
period.
The Miscellaneous Applications of Sterlite Technologies Ltd. (4 of 2015), UP Twiga
Fibreglass Ltd. (6 of 2015) and Sudarshan Chemical Industries Ltd., Roha and Mahad (7 and 8
of 2015, respectively) to intervene in the present proceedings prior to the public consultation
process were disposed of vide the Commission’s Daily Order dated 31 May, 2016.
MERC Order in Case No. 17 of 2015 Page 2 of 19
Background
2. The Commission had determined the tariff for supply of electricity by MSEDCL in its
Tariff Order dated 16 August 2012 in Case No. 19 of 2012, effective from 1 August, 2012.
Vide Order dated 21 February, 2013 in Case No. 138 of 2012 the Commission had
determined the CSS for MSEDCL in accordance with that Tariff Order. Thereafter, the
following Orders were passed by the Commission:
a. Case No. 77 of 2012 (8 February, 2013): The Order was issued on a Petition filed by
the Maharashtra State Power Generation Co. Ltd. (MSPGCL) seeking review of its
Tariff Order dated 21 June, 2012 in Case No. 6 of 2012. Accepting the review of
certain costs, the Commission had allowed certain additional amounts for recovery by
MSPGCL.
b. Case No. 56 of 2013 (13 May, 2013): The Commission approved the Transmission
Tariff for the Intra-State Transmission System (InSTS), including the tariffs payable
by MSEDCL in FY 2013-14 to FY 2015-16. This Order resulted in an increase in the
monthly Transmission Tariff payable by MSEDCL from April, 2013.
3. In view of the substantial financial implications of these Orders on MSEDCL, the
Commission, vide its Order dated 5 September, 2013 in Case No. 95 of 2013, allowed
MSEDCL to recover from its consumers two Additional Energy Charges (AEC) -- AEC-1
and AEC-2 -- over six months.
4. The Average Billing Rate (ABR) of MSEDCL increased on account of allowing the AEC
to be recovered from consumers. In Case No. 107 of 2013, MSEDCL consequently sought
re-determination of the CSS to take into account the increased ABR. In its Order dated 29
October, 2013, the Commission determined the CSS by considering the AEC-1 and AEC-2
that had been allowed for recovery. This CSS was applicable for the period from 1
September, 2013 to 28 February, 2014.
5. Vidarbha Industries Association (VIA) and Sterlite Industries filed Appeal Nos. 23 and 65
of 2014, respectively, against this Order. In its Judgment dated 11 September, 2014, the
ATE directed as follows:
“It is noticed that the Order passed on 05.09.2013 has already been set aside in Appeal
No. 295 of 2013, and the matter has been remanded for re-determination.
Consequently, the impugned Order dated 29.10.2013 challenged in this Appeal has also
to be set aside and remanded for re-determination. Accordingly, Ordered.
MERC Order in Case No. 17 of 2015 Page 3 of 19
In view of the above Order, it is open to the Appellants to approach the Distribution
Company for refund of the amount, which has been collected earlier.
With these observations, both the Appeals are disposed of.”
The present Petition has been filed by MSEDCL consequent to the ATE Judgment.
MSEDCL Petition
6. MSEDCL’s substantive prayers are as follows:
“1. To admit the Petition for determination of cross subsidy surcharge accordance with
the Section 42 (2) and 86 (1) of Electricity Act 2003 and Regulation 13 of MERC
(Distribution Open Access) Regulations, 2005;
2. To approve the cross subsidy surcharge as worked out by MSEDCL.”
7. The Petition states as follows:
a. Vide its Order dated 3 September, 2013 in Case No. 28 of 2013 and Order dated 4
September, 2013 in Case No. 44 of 2013, the Commission approved certain dues payable
to MSPGCL. Vide its Order dated 5 September, 2013 in Case No. 95 of 2013, the
Commission determined suo-motu the Supplementary Charges recoverable by MSEDCL
from its consumers to meet the payments to be made to MSPGCL and the Maharashtra
State Electricity Transmission Co. Ltd. (MSETCL).
b. In all these Orders, the Commission ruled that the increase in the Energy Charge
component of the amount billed by MSPGCL to MSEDCL would be recoverable by
MSEDCL from its consumers through the Fuel Adjustment Charge (FAC) mechanism.
The Commission also allowed MSEDCL to recover from its consumers the increase in
the Fixed Charge component of the amount billed by MSPGCL and MSETCL in
proportion to the approved ABR of the respective consumer categories.
c. Accordingly, MSEDCL levied additional AEC and FAC in the monthly energy bills
from September, 2013. Consequently the ABR of its consumers increased. In turn, this
increase in ABR necessitated revision of the CSS payable to MSEDCL by Open Access
(OA) consumers.
d. Hence, MSEDCL filed a Petition in Case No. 107 of 2013 seeking re-determination of
CSS. The Petition inadvertently stated that MSEDCL had sought the re-determination of
CSS only due to the increase in the ABR arising from the Order in Case No. 95 of 2013.
The Commission, vide its Order dated 29 October, 2013 had determined the CSS
accordingly.
MERC Order in Case No. 17 of 2015 Page 4 of 19
g. MSEDCL also filed a separate Petition in Case No. 185 of 2013 seeking re-
determination of CSS considering the increased ABR arising from the Orders in Case
Nos. 28 of 2013 (dues payable to MSPGCL) and 44 of 2013 (dues payable to
MSPGCL). This Petition was dismissed vide Order dated 27 March, 2014 on the ground
that it was not filed under the Commission’s review jurisdiction, but the Commission
granted liberty to MSEDCL to take appropriate action under law. Therefore, MSEDCL
had filed a Petition in Case No. 108 of 2014 seeking review of the Order dated 29
October, 2013 in Case No. 107 of 2013.
h. In the meantime, the Commission’s Order in Case No. 107 of 2013 was challenged in
Appeal Nos. 23 of 2014 and 65 of 2014 before the ATE. Vide its Judgment dated 11,
September, 2014, the ATE set aside the Commission’s Order on the ground that the basis
on which the CSS was determined, i.e. the Order dated 5 September, 2013 (determining
the Supplementary Charges recoverable by MSEDCL) had already been set aside and
remanded vide its Judgment dated 22 August, 2014. This matter was also accordingly
remanded to the Commission.
i. In view of the ATE Judgment, the Commission is in the process of conducting suo-
motu proceedings in Case No. 95 of 2013 enabling MSEDCL to recover the charges
from its consumers on account of payments made to MSPGCL and MSETCL. Such re-
determination will further necessitate the re-determination of CSS payable by the OA
consumers.
j In accordance with the Order dated 29 October, 2013, MSEDCL has recovered CSS
from OA consumers during the relevant period. Hence, if the CSS is not re-determined
again, a refund will become due to those OA consumers who had paid it as per the
previous Order, which has been set aside.
k. While re-determining the CSS, the additional FAC (along with AEC) needs to be
considered, since it is not the regular FAC but a special FAC which is being levied as a
consequence of the recent Orders (in Case Nos. 28, 44 and 95 of 2013), and which was
constant for six months along with AEC.
l. The powers to determine CSS and other applicable charges payable by OA consumers
are vested with the Commission under Section 86 (1) of the Electricity Act (EA), 2003.
m. The National Tariff Policy, 2005 stipulates the CSS Formula as S = T– [C (1 + L/
100) + D]. Based on this formula, MSEDCL has calculated CSS by using inputs from
the following Orders of the Commission:
Order dated 16 August, 2012 in Case No. 19 of 2012
Order dated 21 February, 2013 in Case No. 138 of 2012
MERC Order in Case No. 17 of 2015 Page 5 of 19
Order dated 13 May, 2013 in Case No. 56 of 2013
Order dated 3 September, 2013 in Case No. 28 of 2013
Order dated 4 September, 2013 in Case No. 44 of 2013
Order dated 5 September, 2013 in Case No. 95 of 2013
n. Computation of Cross Subsidy Surcharge:
i. Computation of „C‟:
Computation of ‘C’ is based on the approved power purchase quantum and price for
FY 2012-13 as per the Tariff Order dated 16 August, 2012. The Merit Order stack of
approved power purchase for FY 2012-13 is as follows:
Station Power Purchase (MU) Average Cost (Rs/Unit)
Ratnagiri Gas (RGPPL) 5256 5.81
Short Term through
traders/exchanges
10675 4.5
Gandhar 1020 4.33
Captive Power Plant (CPP) 900 4.25
VSTP IV 381 4.17
Kawas 1080 4.1
Medium Term 3141 4.1
KSTPS-II 720 4.09
Indep. Power Producers (IPP)
– JSW
1934 3.54
MSPGCL 47663 3.14
TAPP 3&4 3293 3.01
KSTPS III 687 2.73
VSTP III 2400 2.56
Adani Power 1143 2.55
KAPP 760 2.37
Mundra UMPP 1738 2.26
VSTP I 3516 2.23
VSTP II 2940 2.2
Dodson I 42 2.18
SPP 990 2.05
Pench 72 2.05
Sipat TPS 4983 2.04
Dodson II 89 1.73
KSTPS 5400 1.41
TAPP 1&2 1280 1.06
Total PP excluding Non-
Conventional Energy (NCE)
102103
NCE excluding CPP 7744 4.52
Total PP including NCE 109847 3.39
MERC Order in Case No. 17 of 2015 Page 6 of 19
‘C’ can be taken as the weighted average power purchase cost of the top 5% at the
margin. Accordingly, Rs. 5.81 per unit, which is the power purchase cost of RGPPL
contributing 5.14% at the top of the stack, is to be treated as ‘C’ in the CSS
computation formula.
ii. Computation of System loss „L‟:
Approved Wheeling Losses at the respective voltage levels and the Transmission
Losses are used to arrive at the grossed-up total system losses as shown in the Table
below:
Particulars EHV Level 33 kV 22/11 kV LT Level
Transmission Loss (%) 4.19% 4.19% 4.19% 4.19%
Wheeling Loss LT (%) 0% 6.0% 9.0% 12.5%
Total System Losses (%) 4.19% 9.94% 12.81% 16.17%
iii. Computation of Wheeling Charge „D‟:
Approved Wheeling Charges at the respective voltage levels are used to arrive at the
grossed-up total system losses as shown in table below:
Particulars EHV Level 33 kV 22/11 kV LT Level
Wheeling Charge (Rs/Unit) 0 0.11 0.60 1.03
iv. Computation of Average Billing Rate „T‟:
Average Billing Rate (ABR) for each consumer category has been taken as the
effective ABR approved in the Tariff Order dated 16 August, 2012 for 2012-13 and
the AEC (AEC-1, AEC-2, AEC-3 and AEC-4) as approved in Order dated 3
September, 2013 (Case No. 28 of 2013), 4 September, 2013 (Case No. 44 of 2013)
and 5 September, 2013 (95 of 2013).
v. Determination of CSS „S‟:
MSEDCL has computed the category-wise CSS with regard to the computation of
‘C’, ‘L’, ‘D’ and ‘T’ as above.
Preliminary Hearings
8. At the hearing on 17 November, 2015, MSEDCL reiterated the submissions in its Petition,
and sought the following reliefs:
MERC Order in Case No. 17 of 2015 Page 7 of 19
a. Subsequent to the Order dated 26 June, 2015 in Case No. 95 of 2013 confirming AEC-1
and AEC-2, the Commission may declare that the CSS determined to reflect AEC-1 and
AEC-2 in Order dated 29 October, 2013 in Case No. 107 of 2013 was correct.
b. Re-determine the CSS calculated in Case No. 107 of 2013 considering the additional
impact of AEC-3, AEC-4 and additional FAC.
MSEDCL also stated that a consumer has approached it for refund of CSS as per the ATE
Judgment dated 11 September, 2013 which remanded the Commission’s Order in Case No.
107 of 2013. However, MSEDCL is yet to refund the CSS as the present matter is sub
judice before the Commission.
9. At the hearing, the Commission observed that the period under consideration is part of FY
2013-14. The true-up of expenses and revenue for FY 2013-14 has been completed in the
Multi Year Tariff (MYT) Order dated 26 June, 2015 (Case No. 121 of 2014). Hence, the
Commission directed MSEDCL to file its submission on the following:
a. Whether over/under-recovery of CSS for FY 2013-14 has not been factored in the true-
up, and its financial implications, if any, on MSEDCL.
b. Procedure to be followed for redetermination of CSS, if any.
10. Accordingly, vide letter dated 11 December, 2015 MSEDCL submitted as follows:
a. In the MYT Order, the Commission observed that it is determining the tariff for FY
2015-16 as petitioned by MSEDCL, duly considering the impact of all the past revenue
gaps/surplus and additional claims up to FY 2015-16. Therefore, it cannot be denied
that the under-recovery of CSS for FY 2013-14 has been factored in the true-up. There
are no financial implications of the same on MSEDCL.
b. However, the under-recovery of CSS for FY 2013-14 gets passed on to the common
consumers who continue to stay with MSEDCL. In the process, OA consumers have
unduly benefited due to levy of less CSS. This has resulted in an inadvertent hike in
tariff to that extent, the burden of which is wrongly borne by common consumers of
MSEDCL.
c. The Commission may re-determine the CSS as per the procedure contemplated under
the EA, 2003.
d. The Commission may undertake a public consultation process by inviting comments
and suggestions from all stake-holders as may be necessary.
MERC Order in Case No. 17 of 2015 Page 8 of 19
11. At the hearing held on 15 December, 2015, MSEDCL submitted that, although it is
financially neutral to under-recovery of CSS from OA consumers, such under-recovery has
been passed on to its other consumers. Hence, MSEDCL requested the Commission to re-
determine the CSS for the period of September, 2013 to February, 2014 through a process
of public hearing. MSEDCL stated that one consumer has approached it for refund of CSS
as per the ATE Judgment dated 11 September, 2013 remanding the Order in Case No. 107
of 2013. More consumers may approach it for refund in future. MSEDCL is yet to refund
such CSS as the present matter is sub-judice before the Commission. On the quantification
of under-recovered CSS, MSEDCL stated that such quantification is yet to be carried out.
The Commission suggested that MSEDCL may rethink its stand on the present Petition by
considering the quantum of alleged under-recovery, and also the fact that MSEDCL is
revenue-neutral.
12. Vide its submission dated 30 May. 2016, MSEDCL stated that, during the period of
September, 2013 to February, 2014, an additional CSS of Rs. 41.57 crore (subject to audit)
was levied on OA consumers as per the Order dated 29 October, 2013. Applications from
23 OA consumers are received demanding refund of additional CSS to the tune of Rs.
25.97 crore.
13. At the hearing held on 31 May, 2016, MSEDCL stated that the present Petition has been
filed as a consequence of the ATE Judgment dated 11 September, 2014 which set aside the
Commission’s Order dated 29 October 2013 and remanded the matter to the Commission
for re-determination of CSS. The CSS determined in the Order dated 29 October, 2013 was
based on the Commission’s Order in Case No. 95 of 2013, which has now been confirmed
by the Commission through an Order dated 26 June, 2015 after conducting a public
consultation process. Therefore, MSEDCL prayed for re-determination of CSS by
undertaking a public consultation process. Such public consultation may be undertaken
along with the Public Hearings on MSEDCL’s latest MYT Petition.
14. MSEDCL also stated that ATE, in its Judgment dated 11 September, 2014, allowed the
consumers to approach MSEDCL for refund of CSS recovered under Order dated 29
October, 2013. Accordingly, 23 applications have been received for refunds, which are
being processed. However, instead of refunding the amount at this stage and collecting it
again from the same consumers after the Commission’s final Order in the present Case,
such refund may be deferred till the issue of the final Order in the present matter.
15. At the hearing, the Commission observed that the ATE in its Judgment dated 11
September, 2014 has set aside the Order dated 29 October, 2013 and remanded the matter
for re-determination. Pursuant to this Judgment, MSEDCL has filed the present Petition for
determination of CSS for the period of September, 2013 to February, 2014. As
determination of CSS requires public consultation, the Commission has decided to conduct
a public consultation process and Public Hearing(s) on the present Petition. Regarding the
refund of the CSS recovered under the earlier Order, the ATE has set aside that Order and
MERC Order in Case No. 17 of 2015 Page 9 of 19
allowed consumers to approach MSEDCL for refund. The Order dated 29 October, 2013
has lost its legal sanctity, and hence any amount recovered pursuant to that Order also loses
its validity in law. Under such circumstances, there is no other alternative but to refund the
amount recovered. Hence, the Commission directed MSEDCL to refund the CSS
recovered, in the light of the ATE Judgment.
Public Consultation Process and Public Hearings
16. Vide letter dated 14 June, 2016, the Commission directed MSEDCL to publish a Public
Notice under Section 64 of the EA, 2003 on its Petition. Accordingly, MSEDCL published
Public Notices on 16 June, 2016 in three English (Indian Express, Hindustan Times and
Times of India) and two Marathi (Lokmat and Punya Nagari) daily newspapers inviting
suggestions and objections on its Petition for determination of CSS for the period of 1
September, 2013 to 28 February, 2014. The Petition was made available for inspection or
purchase at MSEDCL's offices. It was also available on MSEDCL's website
(www.mahadiscom.in) and on the websites of the Commission (www.mercindia.org.in) /
(www.merc.gov.in) in downloadable format.
17. The list of persons from whom the Commission received responses in writing and at the
Public Hearings is at Annexure - I. The Public Hearings were held at Amravati, Nagpur,
Aurangabad, Pune, Nashik, and Navi Mumbai from 11 July, 2016 to 28 July, 2016, as per
the schedule shown in the Table below, along with the Public Hearings in Case No. 48 of
2016 on MSEDCL’s MYT Petition for the 3rd Control Period FY 2016-17 to FY 2019-20.
Sr. No.
Place/Venue of Public Hearing Date of Hearing
1
Amravati -
Hall No.1, Divisional Commissioner’s
Office, Camp, Amravati Monday, 11 July, 2016
2
Nagpur -
Vanamati Hall, V.I.P. Road, Dharampeth,
Nagpur Wednesday, 13 July, 2016
3
Aurangabad -
Meeting Hall, Office of the Divisional
Commissioner, Aurangabad Monday, 18 July, 2016
4
Pune -
Council Hall, Office of the Divisional
Commissioner, Pune Wednesday, 20 July, 2016
5
Nashik -
Niyojan Bhavan, Collector’s Office
Campus, Old Agra Road, Nashik
Monday, 25 July, 2016
6
Navi Mumbai -
Agri Koli Sanskriti Bhavan, Palm Beach
Road, Sector 24, Nerul, Navi Mumbai
Thursday, 28 July, 2016
MERC Order in Case No. 17 of 2015 Page 10 of 19
18. The Commission has ensured that the due process contemplated under law was followed at
every stage to ensure transparency and public participation. Adequate opportunity was
given to all to submit their responses. The various suggestions and objections received after
issue of the Public Notice, in writing as well as during the Public Hearings, have been
summarized in this Order, and have been addressed in the Section on the Commission’s
Rulings.
Suggestions/ Objections
19. The suggestions/ objections received during the public consultation process are presented
below:
a. As per Section 62 (4) of the EA, 2003, the Tariff may not be amended more frequently
than once in a financial year. MSEDCL issued Commercial Circular No. 190 dated 14
March, 2013 for CSS, and is now again demanding arrears after a period of more than
2 years, which has no legal standing.
b. As per Section 56 (2), no sum due from any consumer shall be recoverable after the
period of two years from the date when such sum becomes first due, unless it has been
shown continuously as recoverable as arrears of charges for electricity supplied.
c. In the MYT Order dated 26 June, 2015 (Case No. 121 of 2014), the Commission had
determined the tariff for FY 2015-16 by considering the impacts of all past revenue
gaps/surplus and additional claims upto FY 2015-16, which also includes impacts
relating to the truing-up of the previous period. Therefore, the Commission had taken
the view that the question of re-determination of CSS for OA transactions for FY
2014-15 and also for FY 2013-14 does not arise.
d. In its MYT Order, the Commission has finalised CSS on the basis of the Tariff Policy.
has clearly mentioned regarding not recovering CSS retrospectively. The Commission
has also simplified the determination of CSS by considering 75% of Average Cost of
Supply (ACoS), and ruled out MSEDCL’s request to recover CSS retrospectively.
e. The demand raised by MSEDCL for past recovery of CSS for the period of September,
2013 to February, 2014 from those consumers who availed OA power during that
period is against the philosophy of promoting competition in the power market as
stipulated in the Tariff Policy and the EA, 2003. The OA was availed by consumers
based on the competitive landed energy cost from the respective Generators. In case
the past recovery is made applicable, the OA power procurement cost may become
higher than MSEDCL’s rates, which would defeat the objective of a competitive power
market.
MERC Order in Case No. 17 of 2015 Page 11 of 19
f. The Central Government has assured industry repeatedly that there will be no new
retrospective imposition of tax, with the in-principle understanding that this is against
the viability of the commercial assessments by parties based on the applicable law at
that point of time. MSEDCL is asking for retrospective implementation of a CSS
which is very high as compared to the earlier CSS. This additional burden on industries
will severely constrain the purpose of OA. Hence, the Commission should not allow
past recoveries of CSS from OA consumers.
g. As per the ATE Order dated 11 September, 2014, the amount collected by MSEDCL
on account of additional CSS has become illegal. Hence, it should have been refunded
in the next billing cycle of September, 2014. Since it has not been refunded so far,
MSEDCL is liable to pay interest at the Bank Rate as per Section 62 (6) of the EA,
2003 till the refund is made.
MSEDCL’s Responses
20. In its responses, MSEDCL has stated as follows in support of its claim for re-determination
of CSS:
a. As stipulated in the Tariff Policy, the EA, 2003 Act and the prevailing OA
Regulations, the CSS shall be utilized to compensate the Distribution Licensee for the
current level of cross subsidy of the respective tariff categories / tariff slabs and / or
voltage level to which a consumer or person belongs or is connected to.
b. Accordingly, the consumers who opted for OA during 1 September, 2013 to 28
February, 2014 are required to pay the CSS to compensate for the level of cross-
subsidy which prevailed during that period by virtue of the Commission’s Orders dated
3, 4 and 5th
September, 2013. This is necessary to avoid passing on the burden on other
non-OA embedded consumers of MSEDCL.
c. The Commission has duly considered the concerns and determined the CSS vide Order
dated 29 October, 2013, which was subsequently recovered from OA consumers by
MSEDCL. That Order was then set aside by the ATE on technical grounds, and was
remanded to the Commission for re-determination.
Commission’s Analysis and Rulings
21. The present proceedings were initiated on the basis of the following remand Judgment
dated 11 September, 2014 of the ATE in Appeal Nos. 23 and 65 of 2014 on the
Commission’s Order dated 29 October, 2013:
“We have heard the learned counsel for the parties.
MERC Order in Case No. 17 of 2015 Page 12 of 19
It is noticed that the Order passed on 05.09.2013 has already been set aside in Appeal
No. 295 of 2013, and the matter has been remanded for re-determination.
Consequently, the impugned Order dated 29.10.2013 challenged in this Appeal has
also to be set aside and remanded for re-determination. Accordingly, Ordered.
In view of the above Order, it is open to the Appellants to approach the Distribution
Company for refund of the amount, which has been collected earlier.
With these observations, both the Appeals are disposed of.”
Vide its Order dated 29 October, 2013 in Case No. 107 of 2013, the Commission had
determined the CSS for the period from 1 September, 2013 to 28 February, 2014 by
considering the increased tariff on account of its Order dated 5 September, 2013 in Case
No. 95 of 2013. However, that Order dated 5 September, 2013 was set aside and remanded
for re-determination by the ATE in Appeal No. 295 of 2013. As the basis on which the
Commission had determined CSS was remanded for re-determination, the ATE also set
aside the Order dated 29 October, 2013 and remanded the matter for re-determination as
quoted above.
22. The present proceedings for determination of CSS for the period of 1 September, 2013 to
28 February, 2014 being a consequence of the above Judgment of ATE dated 11
September, 2014, the question of maintainability of the present Petition or proceedings
does not arise.
23. Further, the recovery of CSS for that period had already been made before the ATE
remanded the matter for re-determination. Hence, the issue of recovery of dues which are
older than two years also does not arise.
24. The ATE remanded the matter for re-determination on the ground that the basis on which
the CSS was determined, i.e. the Order dated 5 September, 2013, had also been set aside
remanded. Subsequent to that remand, the Commission had undertaken the due public
consultation process and issued its final Order in the matter on 26 June, 2015 in Case No.
95 of 2013 with the following rulings:
“13.1 ATE has highlighted in its Judgment that the impugned Order was issued by the
Commission without following the mandatory procedures contemplated under Sections
64 and 86 (3) of the EA 2003 for giving opportunity to the public to raise objections
and suggestions, and ensuring transparency.
13.2 In line with the observations made by the ATE, the Commission has now
conducted the due regulatory and public consultation process through the present
proceedings, as set out earlier in this Order…
Summary of Rulings
MERC Order in Case No. 17 of 2015 Page 13 of 19
15. The cost components of AEC-1 & AEC-2 were approved by the Commission in
the respective Orders following due regulatory process. However, these cost
components were not allowed to be recovered by MSEDCL from its consumers in
those Orders. The Commission is of the view that allowing the recovery of these costs
to MSEDCL is justifiable and necessary.
16. The Commission has scrutinised the rates at which AEC-1 and AEC-2 were
applied by MSEDCL in terms of the principles adopted by the Commission. The total
category-wise AEC charged by MSEDCL is less than the amount of costs allowed to
be recovered, and the category-wise rates levied are also lower than if the principles
had been correctly applied. Hence, the question of allowing carrying cost for over
recovery does not arise.”
Thus, vide its final Order dated 26 June, 2015 in Case No. 95 of 2013, the Commission has
confirmed the recovery of costs through AEC-1 and AEC-2 as stipulated in the earlier
Order dated 5 September, 2013.
25. Subsequent to that final Order dated 26 June, 2015 in Case No. 95 of 2013, at the hearing in
the present matter held on 17 November, 2015, MSEDCL requested the following reliefs:
a. Subsequent to the Commission’s Order dated 26 June, 2015 in Case No. 95 of 2013
confirming AEC-1 and AEC-2, declare that the CSS determined to reflect AEC-1 and
AEC-2 in the earlier Order dated 29 October, 2013 in Case No. 107 of 2013 was correct;
and
b. Re-determine the CSS computed in Case No. 107 of 2013 considering the additional
impact of AEC-3, AEC-4 and additional FAC.
26. As regards the relief sought at 25(a) above, the Commission observes that the CSS
determined in its Order dated 29 October, 2013 was based on the AEC-1 and AEC-2
stipulated in the Order dated 5 September, 2013:
“19. Applicability of Category wise Cross Subsidy Surcharge:
19.1.The category-wise applicable CSS as arrived on consideration of the
additional amount recoverable by MSPGCL from MSEDCL vide Order dated 5
September, 2013 in Case No. 95 of 2013 (providing AEC-1 & AEC-2) and
corresponding components T, C, L & D from the above section is provided in
Annexure II.”
As mentioned at para. 24, vide its Order dated 26 June, 2015, the Commission has already
confirmed the AEC-1 and AEC-2 stipulated in the Order dated 5 September, 2013.
Therefore, the ground on which CSS computation in the Order dated 29 October, 2013 was
remanded for re-determination has ceased to exist.
MERC Order in Case No. 17 of 2015 Page 14 of 19
27. Hence, the Commission confirms that the CSS determined to reflect the increased
ABR on account of AEC-1 and AEC-2 in the Order dated 29 October, 2013 in Case
No. 107 of 2013 is correct and applicable for the period from 1 September, 2013 to 28
February, 2014. Accordingly, the computation of the category-wise CSS is shown in
Annexure II. Along the lines of the dispensation approved by the Commission in its
Order dated 29 October, 2013, only 25% of the applicable CSS will be payable by OA
consumers purchasing power from renewable sources of energy.
28. With reference to the relief sought at para 25(b) above, the Commission notes that, as in
the Order dated 29 October, 2013, in the present remand proceedings MSEDCL has applied
the CSS formula stipulated in the Tariff Policy, 2005. The values of each parameter of the
CSS formula are also the same as in the Order dated 29 October, 2013 except for the value
of the ABR (‘T’). In the Order dated 29 October, 2013, ‘T’ was calculated based on the
AEC approved in Order dated 5 September, 2013. However, for calculating ‘T’, MSEDCL
has now included the impact of other Orders, i.e. dated 3 September, 2013 (Case No. 28 of
2013) and Order dated 4 September, 2013 (Case No. 44 of 2013), along with the AEC-1
and AEC-2 approved in the Order dated 5 September, 2013 (Case No. 95 of 2013).
29. The Order dated 3 September, 2013 in Case No. 28 of 2013 related to implementation of
the ATE Judgment in respect of MSPGCL. In that Order, the Commission had allowed
MSPGCL to recover the impact of the ATE Order from MSEDCL, and in turn allowed
MSEDCL to pass on such impact to its consumers through the FAC mechanism. Similarly,
in its Order dated 4 September, 2013 in Case No. 44 of 2013 regarding the capital cost and
tariff for FY 2012-13 of Khaperkheda Unit 5, the Commission allowed MSPGCL to pass
on its impact to MSEDCL, and MSEDCL to pass on that impact to its consumers through
the FAC. As these Orders specifically provided a mechanism for passing on the impact to
consumers, their impacts were not included in the Order dated 5 September, 2013 in Case
No. 95 of 2013. MSEDCL’s Petition in Case No. 107 of 2013 for determination of CSS for
1 September, 2013 to 28 February, 2014 was based only on the increased tariff on account
of the Order dated 5 September, 2013. The increase in tariff on account of other Orders, i.e.
dated 3 and 4 September, 2013, was not included in that Petition. Hence, in its Order dated
29 October, 2013, the Commission had determined the CSS considering only the higher
tariff on account of the Order dated 5 September, 2013.
30. In these proceedings, MSEDCL is seeking inclusion and consideration of the
increased tariff arising from the Orders dated 3 and 4 September, 2013 also for the
re-determination of CSS upon remand. However, the Commission is of the view that
now including the impact of other Orders also for calculating ‘T’, which was not part
of the original Order dated 29 October, 2013, is beyond the scope of the remand
ordered by the ATE. Moreover, MSEDCL is revenue-neutral in this regard since the
impact has already been passed on in the truing-up for FY 2013-14 which has been
separately concluded. Hence, the Commission has not accepted MSEDCL’s prayer for
re-determination of the CSS computed in the Order dated 29 October, 2013 for the
MERC Order in Case No. 17 of 2015 Page 15 of 19
above period inclusive of the impact of the Orders dated 3 and 4 September, 2013.
31. During these proceedings, the Commission, vide its Daily Order dated 31 May, 2016,
directed MSEDCL to refund the CSS recovered on the basis of the Order dated 29
October, 2013 as that Order had been set aside by the ATE. Now, after the due
process of public consultation, the Commission has confirmed the CSS determined to
reflect the increased ABR on account of AEC-1 and AEC-2 in the Order dated 29
October, 2013 in Case No. 107 of 2013 as correct, and applicable for the period from 1
September, 2013 to 28 February, 2014. Hence, MSEDCL may recover such refunded
amounts, if any, from the respective OA consumers.
The Petition of Maharashtra State Electricity Distribution Co. Ltd. in Case No. 17 of
2015 stands disposed of accordingly.
Sd/- Sd/-
(Deepak Lad) (Azeez M. Khan)
Member Member
MERC Order in Case No. 17 of 2015 Page 16 of 19
Annexure-I
List of Objectors
Sr. No. Name and Organisation
1 Sterlite Technologies Limited, Aurangabad
2 TechNova Imaging System (P) Ltd, Mumbai
3 Indo Rama Synthetic (India) Limited, Nagpur
4 Piaggio Vehicles Private Limited, Pune
5 Videocon Industries Ltd., Aurangabad
6 Sudarshan Chemical Industries Ltd, Roha, Distt. Raigad
7 The Institution of Engineers (India), Mumbai
8 Asahi India Glass Ltd, Taloja MIDC, Distt. Raigad
9 WNS Global Service Pvt. Ltd, Pune
MERC Order in Case No. 17 of 2015 Page 17 of 19
Annexure II
Computation of Cross Subsidy Surcharge applicable from 1 September, 2013 to 28 February, 2014, as approved by Commission
Consumer Category ABR C WL TL L D
CSS
Computed
CSS
Approved
(Rs./Unit) (%) (%) (%) (Rs./Unit) (Rs./Unit) (Rs./Unit)
HT Consumers (66kV and
Above)
Industry
Express Feeder 8.80 5.81 0.00% 4.19% 4.19% 0.00 2.75 2.75
Non Express Feeder 8.31 5.81 0.00% 4.19% 4.19% 0.00 2.26 2.26
Seasonal Industry 10.18 5.81 0.00% 4.19% 4.19% 0.00 4.13 4.13
Commercial
Express Feeder 13.27 5.81 0.00% 4.19% 4.19% 0.00 7.22 7.22
Non Express Feeder 12.56 5.81 0.00% 4.19% 4.19% 0.00 6.51 6.51
Railways 8.95 5.81 0.00% 4.19% 4.19% 0.00 2.90 2.90
Public Water Works
Express Feeder 6.36 5.81 0.00% 4.19% 4.19% 0.00 0.30 0.30
Non Express Feeder 6.56 5.81 0.00% 4.19% 4.19% 0.00 0.51 0.51
Bulk Supply
Residential Complex 6.23 5.81 0.00% 4.19% 4.19% 0.00 0.18 0.18
Commercial Complex 6.25 5.81 0.00% 4.19% 4.19% 0.00 0.20 0.20
HT-IX Public Services
Express feeders 10.70 5.81 0.00% 4.19% 4.19% 0.00 4.65 4.65
Non-Express feeders 10.07 5.81 0.00% 4.19% 4.19% 0.00 4.01 4.01
HT Consumers (33kV)
Industry
Express Feeder 8.80 5.81 6.00% 4.19% 9.94% 0.11 2.30 2.30
Non Express Feeder 8.31 5.81 6.00% 4.19% 9.94% 0.11 1.82 1.82
Seasonal Industry 10.18 5.81 6.00% 4.19% 9.94% 0.11 3.69 3.69
MERC Order in Case No. 17 of 2015 Page 18 of 19
Consumer Category ABR C WL TL L D
CSS
Computed
CSS
Approved
(Rs./Unit) (%) (%) (%) (Rs./Unit) (Rs./Unit) (Rs./Unit)
Commercial
Express Feeder 13.27 5.81 6.00% 4.19% 9.94% 0.11 6.77 6.77
Non Express Feeder 12.56 5.81 6.00% 4.19% 9.94% 0.11 6.06 6.06
Railways 8.95 5.81 6.00% 4.19% 9.94% 0.11 2.45 2.45
Public Water Works
Express Feeder 6.36 5.81 6.00% 4.19% 9.94% 0.11 -0.14 -
Non Express Feeder 6.56 5.81 6.00% 4.19% 9.94% 0.11 0.07 0.07
HT-IX Public services
Express feeders 10.70 5.81 6.00% 4.19% 9.94% 0.11 4.21 4.21
Non-Express feeders 10.07 5.81 6.00% 4.19% 9.94% 0.11 3.57 3.57
HT Consumers (22/11 kV))
Industry
Express Feeder 8.80 5.81 9.00% 4.19% 12.81% 0.60 1.65 1.65
Non Express Feeder 8.31 5.81 9.00% 4.19% 12.81% 0.60 1.16 1.16
Seasonal Industry 10.18 5.81 9.00% 4.19% 12.81% 0.60 3.03 3.03
Commercial
Express Feeder 13.27 5.81 9.00% 4.19% 12.81% 0.60 6.12 6.12
Non Express Feeder 12.56 5.81 9.00% 4.19% 12.81% 0.60 5.41 5.41
Railways 8.95 5.81 9.00% 4.19% 12.81% 0.60 1.80 1.80
HT-IX Public Services
Express feeders 10.70 5.81 9.00% 4.19% 12.81% 0.60 3.55 3.55
Non-Express feeders 10.07 5.81 9.00% 4.19% 12.81% 0.60 2.91 2.91
LT Consumers
Non-Residential
Up to 20 kW
0-200 Units 8.10 5.81 12.50% 4.19% 16.17% 1.03 0.32 0.32
MERC Order in Case No. 17 of 2015 Page 19 of 19
Consumer Category ABR C WL TL L D
CSS
Computed
CSS
Approved
(Rs./Unit) (%) (%) (%) (Rs./Unit) (Rs./Unit) (Rs./Unit)
Above 200 units 12.48 5.81 12.50% 4.19% 16.17% 1.03 4.70 4.69
'> 20 kW & < 50kW' 11.58 5.81 12.50% 4.19% 16.17% 1.03 3.80 3.79
Above 50kW 14.45 5.81 12.50% 4.19% 16.17% 1.03 6.67 6.67
Industry
Below 20kW load 6.10 5.81 12.50% 4.19% 16.17% 1.03 -1.69 -
Above 20kW load 9.74 5.81 12.50% 4.19% 16.17% 1.03 1.97 1.96
Residential
0-100 Units 4.45 5.81 12.50% 4.19% 16.17% 1.03 -3.33 -
101-300 Units 7.51 5.81 12.50% 4.19% 16.17% 1.03 -0.27 -
301-500 Units 9.37 5.81 12.50% 4.19% 16.17% 1.03 1.59 1.58
500 -1000Units 10.17 5.81 12.50% 4.19% 16.17% 1.03 2.40 2.39
above 1000 units 10.26 5.81 12.50% 4.19% 16.17% 1.03 2.49 2.48
Advertisements 26.76 5.81 12.50% 4.19% 16.17% 1.03 18.98 18.97
Temporary - Others
Other Purpose 17.83 5.81 12.50% 4.19% 16.17% 1.03 10.06 10.06
LT Public Services
Up to 20 kW
0-200 Units 6.37 5.81 12.50% 4.19% 16.17% 1.03 -1.41 -
>200 units 9.55 5.81 12.50% 4.19% 16.17% 1.03 1.78 1.77
>20-50 KW 10.82 5.81 12.50% 4.19% 16.17% 1.03 3.05 3.05
>50 KW 11.41 5.81 12.50% 4.19% 16.17% 1.03 3.63 3.62