before the haryana electricity regulatory commission - panchkula case no. herc/pro-6 ... · ·...
TRANSCRIPT
Page 1 of 54
BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION - PANCHKULA
Case No. HERC/PRO-6 of 2016
Date of Hearing : 10.08.2016
Date of Order : 12.09.2016
IN THE MATTER OF
Petition/application for approval of draft PPA signed with four Solar Power Developers
selected through Tender under NIT No. 51.
Petitioner Haryana Power Purchase Centre, Panchkula
Present On behalf of the Petitioner (Public hearing)
1. Shri. Nitin Yadav, MD, UHBVNL
2. Shri Shubham Arya, Advocate
3. Shri O.K. Sharma, CE, HPPC
4. Smt. Poorva Saigal, Advocate
5. Shri Neeraj Sharma, SE, HPPC
6. Shri. Gaurav Gupta, Xen., HPPC.
7. Smt. Seema Sidana, AE, HPPC.
QUORUM Shri Jagjeet Singh, Chairman
Shri M. S. Puri, Member
Back ground of the case
1. On 16.06.2014, the Petitioner, vide memo no C43/HPPC/SE/ C&R- 1/PPA-136
sent the communication to the Commission intimating as under:-
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar power to meet
RPO – approval thereof
It is intimated that HPPC is in the process of floating Two no. NITs for purchase
of 50 MW solar & 100 MW non-solar power. The date of opening of tenders has
been fixed as 31.7.2014 for solar & 14.8.2014 for non- solar power.
Page 2 of 54
Although NIT is based on the Standard RFP for procurement of power under
“Case 1 -RE” Bidding procedure through Tariff based Competitive Bidding
Process (As per Guidelines for tariff Based Competitive Bidding Process for
Grid Connected Power Projects Based on Renewable Energy Sources” issued
by the Govt. of India), however a few changes have been done mainly affiliates
have not been allowed, Delivery point is Haryana periphery and tariff to be
quoted and evaluated will be at Delivery point, negotiation will be done etc.
It is requested that HERC may furnish its valuable comments, if any, on the NIT
latest by 25.6.2014 so that HPPC may proceed further with tender process.”
2. By communication-dated 25.06.2014, the Commission held as under:-
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar power to
meet RPO.
This is with reference to your office memo no. Ch-43/HPPC/SE/C&R-I/PPA-136
dated 16.06.2014 vide which copy NITs for purchase of 50 MW solar & 100
MW non-solar power have been forwarded for comments.
Before the case is further processed, it is requested to clarify/intimate the
following:-
A copy of the Standard Bidding Documents for procurement of power under
“Case 1-RE” Bidding procedure through Tariff based Competitive Bidding
Process for Grid Connected Power Projects Based on Renewable Energy
Sources issued by the Government of India be provided.
The deviations made in the NIT with respect to the Standard Bidding Document
for procurement of power under “Case 1-RE” issued by the Government of
India be tabulated.
The copy of the statute, under which the deviations sought by HPPC from the
Standard Bidding Documents issued by the Government of India requires the
approval of the Commission, may also be provided.
The above clarification/information be provided within a week from the date of
issue of this letter.”
Page 3 of 54
3. Thereafter, by communication-dated 01.07.2014, the Petitioner furnished the
deviations from the Standard Bidding Document as per the direction of the
Commission with a covering letter as under:-
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar power to meet
RPO- approval thereof
This is with reference to your Memo. No. 1124/HERC/PPA/NIT-RE/Tariff dated
25.6.2014 on the subject.
In this regard, Standard Request for Proposal for Procurement of Power Under
case1 – RE” Bidding Procedure through tariff Based Competitive Bidding
Process (As per Guidelines for tariff Based Competitive Bidding Process for
Grid Connected Power Projects based on Renewable Energy Sources”) is
enclosed (Annexure A).
Deviations made in the NIT w.r.t the SBD for procurement of power under
“Case1- re” in tabulated form is enclosed. (Annexure B)
It is submitted that approval of Honorable Commission on the Two Nos. subject
cited NITs is required in view of the Clause 3.1.2 of MNRE “Guidelines for Tariff
based Competitive Bidding Process for Grid Connected Power Projects Based
on Renewable Energy Sources- December 2012” (Annexure C) which states
that
“Approval of the Appropriate Commission shall be sought in the event of the
deviations from the bidding conditions contained in these guidelines and SBD,
following the process described in para 6.9 of these guidelines.”
It is humbly requested that approval may please be granted on the NITs for
purchase of 50 MW solar and 100 MW non-solar power.”
4. In response to the above, the Commission by letter dated 28.07.2014 wrote as
under:-
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar power to meet
RPO.
Page 4 of 54
This is with reference to your office memo no. Ch-46/HPPC/SE/C&R-//PPA-
dated 25.06.2014.
The Commission has observed that there are many other deviations particularly
to Bid Bond, CPG, Payment Security etc. The Standard Bid Document may
have PPA also.
You are requested to submit all deviations made in the NIT with respect to the
Standard Bidding Document (SBD) for procurement of power under “Case 1-
RE” issued by the Government of India in tabulated form and also the PPA
attached with the SBD within a week from the date of issue of this letter.”
5. On 05.08.2014, the Petitioner submitted as under:-
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar power to meet
RPO
This is with reference to your memo No. 1535/HERC/PPA/NIT-RE/Tariff dated
28.7.2014 on the subject.
In this regard, it is submitted that major deviation in NIT from SBD in respect of
Bid Bond & Contract Performance Guarantee is that of the amount per MW to
be paid. All the minor deviations will be rectified to have the NIT exactly the
same as that of SBD. All these deviations have been color coded in the
comparison done in the tabular form. (Annexure A)
Also, Standard Bid Document does not contain any PPA.
It is humbly submitted that the date of opening of tenders is 22.8.2014 for solar
power and 29.8.2014 for non-solar power.
Submitted for the kind consideration of the Commission please.”
Along with the above letter, the list of deviation was also given.
6. On 08.08.2014, the Commission issued a letter-dated 08.08.2014, with the
approval of Hon’ble Member only, which read as under:-
“Subject: NIT for Purchase of 50 MW solar & 100 MW non-solar power to meet
RPO – approval thereof.
Page 5 of 54
kindly refer to your memo no Ch-43/HPPC/SE/C&R -I/PPA – 136 dated
16.06.2014 and Ch-46/HPPC/SE/C&R-I/PPA-67 dated 1.07.2014 vide which
approval of the Commission was sought to be deviations in the bid documents
vis-à-vis the Case – 1 RE Bidding Procedure of the Government of India. The
Commission has considered your application/petition and observes that the NIT
No. 51 & 52 for inviting competitive bids purchase of 50 MW for Solar Power
and 100 MW of Non- Solar (renewable energy) were issued on 16.04.2014 and
the approval of the Commission to the deviations were sought on 1.07.2014 i.e.
ex post facto.
The Commission observes that the Discoms have not fulfilled their RPO
including by way of purchase of REC. Consequently, the accumulated shortfall
allowed to be carried forward from FY 2011-12 up to FY 2013-14 (up to
December 2013) is about 720.83 Mus and the total RPO target set for FY
2014-15 is 1463.41 Mus. On several occasions the Commission has observed
that HPPC/HAREDA may invite bids/ reverse bids for purchase of renewable
energy in order to meet with the RPO targets and the fact that the bidding
process is already under way, HPPC may proceed with the same. Once the
bids are opened HPPC shall analyze the same and submit the details to the
Commission for its order and approval of the PPA with the successful bidders.
7. Subsequently, vide memo No. Ch-2/HPPC/SE/C&R-1/PPA-196, dated
16.07.2015 the HPPC informed the Commission that “after negotiation with the
eligible bidders, Rs. 6.44/kWh has been discovered as the lowest price for which LOI
has been issued to the following five bidders for a capacity of 25 MW solar power:-
Sr. No.
Name of the Bidder Quantity offered in MW
Levelized Tariff (Rs./kWh)
1. Balarch renewable energy Pvt. 20Ltd 1 6.44
2 Neel Metal Product Limited 20 6.44
3 Sudhakar Infratech Ltd 2 6.44
4 Ultimate Sun Systems Pvt. Ltd. 1 6.44
5 M/s Subhash Infraengineers Pvt. Ltd. 1 6.44
Total 25
HPPC has signed PPA with the above bidders except M/s Sudhakar Infratech
Ltd. Accordingly, HPPC seeks approval of PPA from the Hon’ble Commission.”
Page 6 of 54
8. The Commission vide Memo No. 1653/HERC/Tariff/PPA/Bid/2015 dated
10.09.2015 conveyed certain observations on the PPA. HPPC, vide its office letter
Memo No. Ch-30/HPPC/SE/C&R-I/T-26 dated 29.09.2015 submitted its reply on the
observations of the Commission.
9. Subsequent to the above and after examining the Draft PPA, the Commission
considered it appropriate to hear the matter especially in view of the fact that the
deviations to the SBD had not been approved by the Commission at any stage in the
case. Also, the petitioner had signed PPA in contravention of the Commission’s
directions issued vide memo No. Memo. No. 1725 dated 08.08.2014 without prior
approval of the Commission. The case was accordingly heard on 11.02.2016.
10. The Commission, in its interim order dated 11.02.2016, observed as under:-
a. HPPC may explain as to why the proper procedure as mandated by the
SBD was not adopted in this regard.
b. Disclose the composition of Bid evaluation committee and also that the
same was constituted in accordance with the SBD.
c. Whether the Bid evaluation committee consisted of an external expert in
the Committee as mandated by the SBD.
d. Whether the Bid Evaluation Committee certified that the rates quoted by
the bidders were aligned to the market conditions. As per the news item published in
“The Times of India” dated 20.01.2016, the Solar price tariff hits new low in Rajasthan
i.e. Rs. 4.34 to Rs. 4.63 paisa per unit quoted by Fortum India in one of the six
pockets bid out by state run generation utility NTPC in Rajasthan. Also, the latest bids
called by HPPC for 150MW solar power have thrown up the rate of Rs.5.00/Kwh.
e. In the present scenario how HPPC can negotiate with the developer at
such a high price of Rs. 6.44 per unit without any justification.
f. Why the HPPC has not followed its own process as mandated in Para
3.1.4 (IV).
g. Why negotiations were carried out with the bidders in spite of clear
instructions in the SBD forbidding the same.
11. HPPC, under affidavit dated 09.03.2016, made the following submissions:-
Page 7 of 54
i) The Commission, in its Order dated 29.05.2014, in Case relating to the
Aggregate Revenue Requirement for the Distribution & Retail Supply
Business under Multi Year Tariff Framework for the control period i.e.
Financial Year (FY) 2014-15 to FY 2015-16, held as under:-
Renewable Purchase Obligation (RPO)
Section 86 (1) (e) of the Electricity Act, 2003 mandates the Commission to promote
cogeneration and generation of electricity from renewable sources of energy by
providing suitable measures for connectivity with the grid and sale of electricity to
any person, and also specify, a percentage of the total consumption of electricity in
the area of distribution licensee, for mandatory purchase of electricity from such
sources. In accordance with the Regulation 64 of HERC (Terms and Conditions for
determination of Tariff for Renewable Energy Sources, Renewable Purchase
Obligation and Renewable energy Certificate) Regulations, 2010 the RPO for FYs
2011-12, 2012- 13 and 2013-14 as approved by the Commission are as under:-
Financial year
Energy Consumption (MU)
%age of overall RPO
Renewable energy (other than solar) required to be purchased as per overall RPO (MU)
%age of solar RPO (as a %age of overall RPO)
Energy required to be purchased as per solar RPO (MU)
Total renewable energy required to be purchased (MU)
2011-12 36075 1.50% 541 0.31% 1.69 543
2012-13 40000 2.00% 800 0.05%* 20 820
2013-14 41086 3.00% 1191.49 0.10%* 41.09 1232.58
As per data provided by the State Nodal Agency for FY 2011-12, FY 2012-13 and FY
2013-14 (up to Dec. 2013), the shortfall in meeting the RPO for the aforesaid years
has been worked out as under:-
Table 3.37: Shortfall in meeting RPO (MUs)
Type of RE source
FY 2011-12 FY 2012-13 FY 2013-14 (upto Dec 2013)
Solar 0 7.14 25.69
Non-Solar 143.00 319.89 695.14
Total 143.00 327.03 720.83
The Commission observes that the Discoms have failed to achieve the RPO target set
by the Commission. The Discoms have also not purchased any Renewable Energy
Certificates (REC) to fulfil their RPO.
ii) HPPC submitted that necessary approval of the Commission was duly
obtained, vide Commission’s letter dated 08.08.2014.
iii) HPPC further submitted that negotiation with the bidders, in the present
case did not vitiate the bidding process in any manner and it rather, added
value to the Haryana Utilities and the consumer at large. At the outset, it
Page 8 of 54
may be stated that the Petitioner or any other agency involved did not
undertake negotiation with the bidders in a manner to ignore a bidder who
had given a better price. The lowest bidder, namely, L1 had quoted a tariff
of Rs. 6.44/kwh. In the bidding documents, the Petitioner had already
disclosed the criteria for evaluation of the bid. These particularly included
the following:-
“3.1.4 STEP IV – Successful Bidder(s) Selection
Bids qualifying in Step III shall only be evaluated in this stage
I. The Bidder with the lowest levalized Tariff for 25 years in its
Financial Bid shall be considered as L-I.
II. The price discovered for per unit rate of solar power shall
generally determined based on the rates quoted by the L-1 bidder
and the negotiation, if any, held with the lowest bidder. However,
the negotiations could be held with remaining eligible bidders. In
case, the L-1 bidder refuses to further reduce his offered price
and the remaining bidders come forward to offer a price better
than the price offered by L-1 bidder, then the bidder offering the
lowest rate would become the L-1 bidder. However, in such a
situation, the original L-1 bidder shall be given one more
opportunity to match the discovered price.
III. On determination of the price discovery pursuant to the above
price, a counter offer would be made to all such eligible bidders,
for acceptance of the discovered price.
IV. Form the outcome of the above process, the bidders from
anywhere in India, agreeing to accept the counter-offer of the
discovered price, will be considered and selection will be done on
the following criteria.
i) Solar power Projects in the State of Haryana will be given
first priority.
ii) Thereafter, the bidder offering the maximum capacity will be
given priority.
V. At any step during the selection of Successful Bidder(s) in
accordance with Clauses I to IV above, the HPPC reserves the
right to increase / decrease the Requisitioned Capacity by up to
ten percent (10%) of the quantum indicated in Clause 2.1.
Page 9 of 54
VI. The Letter(s) of Intent shall be issued to all such Successful
Bidder(s) selected as per the provisions of this Clause 3.1.4.
VII. Each successful Bidder shall unconditionally accept the LoI, and
record on one (1) copy of the LoI, “Accepted Unconditionally”,
under the signature of the authorized signatory within seven (7)
days of issue of LoI.
VIII. If the Successful bidder, to whom the LoI has been issued, does
not fulfil any of the conditions specified in the Clauses 2.9 & 2.12,
HPPC reserves the right to annul the award of the letter of Intent
of such successful bidder.
IX. HPPC, in its own discretion, has the right to reject all Bids if the
Single Quoted Tariff is not aligned to the prevailing market
prices.”
iv) In the negotiation, the above criteria were only adopted. There were no new
or additional criteria introduced.
v) HPPC submitted that there has been no violation of the bidding documents
in regard to the non-constitution of evaluation Committee as per the
Guidelines issued by the Ministry of Non-Conventional Energy Sources.
HPPC further submitted that solar projects do not have to be compared with
other sources of energy to decide on the quoted price being aligned to
market prices. The committee would be relevant if power could be procured
from different sources. In terms of the RPO obligation, the power was to be
procured only from solar energy sources. Further, based on the market
prices prevalent, the Commission had decided on Rs 7.45/unit as the ceiling
price. In the circumstances, the issue of an evaluation Committee deciding
on the prices being aligned to the market forces, will have no application.
Further, the above requirement is in the Guidelines and does not form part
of the Bidding documents, as approved by the Commission.
vi) HPPC further submitted that after the opening of the Bid on 25.10.2015, the
following steps were taken
a. The technical and commercial bids (excluding the price bid-financial)
received from 10 participating bidders were first opened on
Page 10 of 54
22.10.2014 and was then evaluated by a Committee consisting of
Chief Engineer HPPC, Financial Advisor and Superintending
Engineer, HPPC. 8 out of 10 participating bidders were found to be
responsive.
b. The price bid of the 8 bidders was then opened on 22.12.2014. The
price bids were in the range of Rs. 6.50 to 7.45/kWh.
c. The Steering Committee for Power Planning constituted for
evaluating the purchase of power consisting of Additional Chief
Secretary, Power and Managing Directors of Electricity Utilities
(GENCO, TRANSCO AND TWO DISCOMS), CE/HPPC considered
the price bids and decided on the course of action to be taken in
accordance to the tender terms and conditions.
vii) In view of the position brought out above, HPPC has prayed as under:-
a. Approve the Power purchase Agreements entered into between the
Haryana Utilities and the four selected bidders; and
b. Pass such further order or order(s) as may be deemed necessary
and fit in the circumstances of the case.
12. The case was heard again by the Commission on 19.02.2016 and 10.03.2016.
The Petitioner was asked to clarify certain issues and also to submit certain
documents related to the tendering process. Additionally, in order to gain first hand
knowledge of the physical progress of the Solar Power Projects of the selected
bidders, the Chairman deputed a Committee of HERC Officers to visit the sites of the
Solar Power Developers.
Public Proceedings
13. During public hearing in the ARR held on 01.03.2016 and 30.05.2016, people
at large desired to be heard while approving the Power Purchase Agreement(s) of
the Discoms. Further, the Member of State Advisory Committee in the meeting held
on 29.05.2015, had also raised similar concerns. Additionally, the Government of
Haryana has also made it mandatory that public at large should be heard while
Page 11 of 54
formulating the public policies. As the tariff, so adopted/ determined by the
Commission, while approving the Power Purchase Agreement(s) is to be paid by the
consumer of Haryana State, the Commission, in order to ensure transparency,
decided to hold a public hearing in this regard.
The Commission issued Public Notice in The Tribune (English) and Dainik
Jagran (Hindi) dated 7.7.2016 inviting objections and intimating the date of hearing the
Petition(s). Public hearings, as per the aforesaid notice, were scheduled to be held on
21.07.2016 at 11:00 A.M. Since the hearing of the Petition(s) was rescheduled to
10.8.2016, Public Notice for the hearing was again published in the same newspapers
on 27.7.2016 intimating the stakeholders and general public regarding the change in
the date of public hearings. The Public Notice was also hosted on the website of the
Commission under the heading “Schedule of Hearings”.
The HPPC made detailed presentation of the petition(s) for approval of PPAs,
in the hearings wherein they highlighted the need for approval of PPAs in light of RPO
obligations imposed upon them.
14. In response to the Public Notice issued by the Commission in the present case,
the stakeholders/general public as listed below filed objections/comments:-
a. Kaushalya Devi, Sarpanch, Village Khokha, Hisar.
b. Rajvir, Sarpanch, Village Niyana, Hisar-I.
c. Suresh, Sarpanch, Gram Panchyat, Chirod, Hisar-I.
d. Manhoar, Sarpanch, Gram Panchyat, Dhansu, Hisar.
e. Dharamvir, Sarpanch, Gram Panchyat, Mirka, Hisar-I.
f. Suresh Devi, Sarpanch, Gram Panchyat, Kharkhari, Hisar-I.
g. Jaswant Singh, Sarpanch, Gram Panchyat, ramayana hansi, Hisar-I.
h. Sunil Kumar, Sarpanch, Gram Panchyat, Kharar, Hisar-I.
i. Om Prakash, Sarpanch, Gram Panchyat
j. Kuldeep Kaur, Sarpanch, Gram Panchyat, Theri, Fatehabad.
k. Saroj Devi, Sarpanch, Gram Panchyat, Alipur, Hisar-I.
l. Rajvir Singh, Sarpanch, Gram Panchyat, Village Mirzapur, Hisar-I.
m. Shakti Singh, Sarpanch, Gram Panchyat, Village Bhagana, Hisar-I.
n. Suresh Kumar, Sarpanch, Gram Panchyat, Village Balawas, Hisar-I.
o. Sanjay Kumar, Sarpanch, Gram Panchyat, Village Dubeta, Hisar-I.
p. Sarpanch, Gram Panchyat, Village Behbalpur, Jind.
q. Resident Welfare Association, Sector-9 & 11, Hisar
r. Welfare Association (Regd.), Sector-13 (P), Urban Estate, Hisar (Haryana).
s. Resident Welfare Association (Regd.), Sector-16-17 & Part-II, Hisar.
Page 12 of 54
t. Sector-15 A Welfare Association, Hisar, H.No. 575, Sector-15/A, Hisar.
u. Sector-14 Resident Welfare Association, Hisar.
v. Kuldeep Kaur, Sarpanch, Gram Panchyat, Theri, Fatehabad.
w. Manmohan Kaur, Gram Panchyat, Fatehabad.
x. Mr.Subhash and other advocates, District Court Complex, Panchkula.
y. Rattan Singh Pannu, # 3693, Sector-9 & 11, Hissar.
z. Satya Welfare Association, 10-92, Urban Estate-2, Hisar.
aa. Senior Citizens' Council (Regd.), Panchkula.
bb. President-cum-Chairman, Action Committee, CWA as endorsed by General
Secretary, House Owners Welfare Association, Sector-21, Panchkula,
President, R.W.D.A., Sector-15, Panchkula etc.
cc. Faridabad Industries Association
dd. Sh. Deepak Girdhar, Advocate.
15. The following interveners supported the efforts made by HPPC to procure Solar
Power and suggested that the Commission should approve the PPA’s.
a) Sh. B.S. Yadav, Principal Advisor, Policy, Regulatory Affairs & Capacity
Building), National Solar Energy Federation of India, New Delhi.
b) National Solar Energy Federation of India (NSEFI) a) Faridabad Industries
Association.
c) Sh. B. Kumar.
d) Dr. Manish.
e) Sh..Prateek Singh, IIM, Rohtak.
f) Sh. Kushagra Agarwal.
g) Sh. Sandeep Mittal.
h) Sh. B.D. Sharma, Scientist, 3009, Sector 46, Gurgaon.
i) Sh. Karan Singh Pasina, Panipat.
j) Smt. Naina Jain, Student-Socially Active.
k) Sh. Rahul Gulia.
l) Smt Nirmala, Sarpanch, Village Barwa, Bhiwani.
m) Manu Richhoriya, Banker
16. While replying to the objections, HPPC has stated that the
comments/objections are generic and similar in nature. Therefore, HPPC is filing a
common reply A brief summary of the objections and HPPC replies thereto is as
under:
16.1 Objections raised by interveners at para 14 (a to w) and reply of the petitioner
are as under:-
16.1.1 Objection raised - In the hearing held on 2.7.2016 in HERC, it has been gathered that No power will be purchased in Haryana as already about 70 PPAs have been signed, so fixed charges of about 2000 crore are being paid
Page 13 of 54
whereas installed capacity available with Haryana is 11000 MW against the demand of 7500 MW.
Reply: The submission is generic in nature and in particular, does not relate to solar power purchase. The issue which is being raised has to be decided by the Hon’ble Commission in appropriate proceedings.
16.1.2 Objection raised – Govt. has started erecting solar panels on rooftop of 500 Sq. yard houses and rates of solar power are decreasing so solar power will become more cheaper. Under these circumstances, it is not legal to sign PPA for long term @ Rs 5.00/kwh and Rs.6.44/kwh
Reply: As far as solar rooftop is concerned, DISCOMS have taken prompt steps to move forward towards mission of installation of solar rooftop for which training program for field staff have been arranged and a team under the supervision SE/M&P has been formed for installation of Net meters. HPPC will not be able to meet its RPO requirement through Net metering of Solar Rooftop projects. The procurement of solar power through rooftop projects cannot be compared with procurement of ground mounted solar projects. The two are distinct, both in capacity as well as the ability to meet the RPO obligation.
Further, it is submitted that the tariff of Rs. 6.44/kWh was discovered in the Year 2014-15 through the competitive bidding process initiated by HPPC for procurement of 50 MW. The tariff, at that time, was the most competitive. For the particular Year, the levelised tariff by the Hon’ble Commission was Rs. 7.45/kWh and there being specific directions from the Hon’ble Commission vide order dated 20.11.2013 that HPPC should procure solar power at any price less than the levelised tariff.
The PPAs have been signed with the 4 developers and are ready for commissioning. The tariff that would be applicable to these PPAs would be made effective from the date Hon’ble Commission approves the PPA.
The Generic Levelized tariff (Rs./kwh) for the solar PV for the FY 2014-15 by Central Electricity Regulatory Commission (hereinafter referred to as the ‘Central Commission’) and State Electricity Regulatory Commissions (hereinafter referred to as ‘State Commission’) is tabulated below:
Haryana CERC Rajasthan M.P Punjab TamilNadu U.P Uttarakhand
7.45 7.72 7.5 8.05 7.72 7.01 8.91 6.99
As far as Rs. 5.00/kwh is concerned, the tariff is most competitive and the tariff(Rs./kwh) discovered by different State Discoms for solar power through competitive bidding floated during FY 2015-16 till 31st March 2016 is as follows:-
The documentary proof for the same have already been submitted to HERC.
Further, it is pertinent to point out that the Hon’ble Commission has in another case also approved the PPA executed by the Petitioner with another developer, M/s
Haryana Telangana Punjab Uttrakhand Jharkhand Madhya Pradesh
5.00 5.17 5.09 5.57 5.08 5.05
Page 14 of 54
Siwana Solar Power Ltd., for 5MW vide letter dated 21.02.2014. The aforesaid solar power developer is being paid tariff at the rate of Rs.6.44/Kwh as per clause 2.1.41 of the said PPA as the present tariff of Rs.6.44/Kwh discovered through the instant competitive bidding process carried out by HPPC was the lowest tariff vide HERC order dated 20.1.2016.
Hence, tariff of Rs. 6.44/kwh during FY 2014-15 and Rs. 5.00/kwh during FY 2015-16 is the most competitive discovered through competitive bidding as per HERC directives and the same is lower than the levelised tariff (Rs. 7.45/kWh) determined by HERC and Rs 7.72 kWh of CERC.
16.1.3 Objection raised- With cheaper Solar panels and Net metering, more capacity will be spare, therefore, it is requested that no PPA for solar or otherwise may be signed. To meet RPO, If REC are costly, signing MOU for a long time is even more costlier.
Reply: As far as solar rooftop is concerned, DISCOMS have taken prompt steps to move forward towards missionary of installation of solar rooftop for which training program for field staff have been arranged and a team under the supervision SE/M&P has been formed for installation of Net meters. HPPC will not be able to meet its RPO requirement through NET metering of Solar Rooftop projects. The procurement of solar power through rooftop projects cannot be compared with procurement of ground mounted solar projects. The two are distinct, both in capacity as well as the ability to meet the RPO obligation.
As far as purchase of REC certificate is concerned, HPPC submits as under:
a) HERC vide its Order dated 20.11.2013 has recommended to purchase Renewable power instead of REC. The abstract of the same is reproduced below:
The Commission is of the view that it is always preferable to purchase renewable
energy because of fact that such generation projects as per the statutes has to be encouraged, rather than to purchase REC wherein the amount paid for purchase of the same goes to the generator without even getting the benefit of power availability. Further because of its distributed nature, RE generation is considered advantageous in terms of reduced cost of transmission network and reduced transmission losses. This advantage becomes considerably enhanced when such RE is generated and consumed locally. Therefore the Discoms in Haryana should prefer to purchase RE generated in Haryana. This is also the spirit behind regulation 64(3) support of which has been sought by the Petitioner.
b) Firstly, it is submitted that the tender for 50 MW solar power was floated by
HPPC in October 2014 and the cost of REC for solar power at that time was Rs 9.30 per kWh.
c) Secondly, the very comparison with REC as an alternate to renewable power
purchase is not correct. REC can only be a fall back if for some reasons Renewable Purchase Obligation is not met. REC is not a long term solution for fulfilling the RPO obligations. Moreover, REC may not be available in future.
Page 15 of 54
d) Without prejudice to the above purchase of renewable Solar power in the present situation in Haryana is beneficial as compared to REC if the following aspects are considered:
Table-‘A’
The table showing comparison of REC vis-à-vis power procured through
tender clearly proves that the power procured through tender is most competitive.
16.1.4 Objection raised- It is decided that no more PPA should be done till the time the existing PPAs are forgone/power is purchased under Net metering/HPGCL Solar plant starts generation and if still power is required, PPA may be signed after two years.
Reply: HPPC will not be able to meet its RPO requirement through Net metering of Solar Rooftop projects.
Currently, HPGCL proposed solar power capacity is not able to meet Solar RPO targets as on date and HPPC as well as HPGCL have been taking immediate steps to meet solar RPO as soon as possible.
However, HPGCL has offered 10 MW solar power at PTPS, Panipat @ Rs. 4.88/kwh instead of Rs 4.18/kwh excluding the cost of transmission line and land cost. The proposal is under consideration.
New Haryana Solar Policy 2016 & new tariff policy formulated by GOI envisages even more purchase of solar power, thereby more burden on HPPC.
During the bidding process, negotiation was carried out in accordance with Policy notified by Govt. of Haryana. The bidding was done in fair and transparent manner and the objector is raising unnecessary, irrelevant and out of context objections.
Further, it is submitted that HERC vide their order dated 20.11.2013 titled “modification of Renewable Purchase Obligations” states that the DISCOMS/HPPC is able to procure renewable energy power (Solar and Non-Solar) at a Tariff lower than determined by the Commission by way of reverse bidding or otherwise, they may do so.
Purchase of REC Purchase of Solar Power
Total No. of units supplied 100 Total No. of units supplied 100
No. of Units at APPC Price 100 No. of Units at APPC Price
98
APPC Price for FY 2014-15 in Rs./kwh
3.53 APPC Price for FY 2014-15 in Rs./kwh
3.53
Let’s say 2 units of solar unit has to be purchased as REC to fulfil RPO
2 Let’s say 2 units out of 100 units served through solar
2
Cost of REC 3.50 Cost of solar unit/kWh 6.44
APPC rate after adding REC Cost in Rs./kwh
(100x3.53 +2x3.50)/100 =3.60
New APPC rate in Rs./kwh
(98x3.53 + 2x6.44)/100
=3.59
Page 16 of 54
The argument to cancel old PPAs, does not contain any merit. Moreover, it does not relate to HPPC & the issue which is being raised has to be decided by Hon’ble commission.
16.1.5 Other Objections raised : HPPC vide letter dated 05.08.2014, had submitted that major deviation in NIT from SBD were in respect of Bid Bond and Contract performance guarantee and all others are minor deviations which will be rectified to have the NIT exactly the same as SBD. Accordingly, on the basis of above letter of HPPC, the Commission informed HPPC on 08.08.2014 that since bidding process is already under way, HPPC may proceed with the same. However, later HPPC had not removed those deviations
a) Objection: Permission not sought for negotiation Reply of HPPC
The content of HERC letter dated 8.8.2014 are as under:
On 16.06.2014, the Petitioner sent the communication to the Commission intimating as under:
1. “Subject: NIT for purchase of 50 MW solar & 100 MW non-solar power to meet RPO – approval thereof
It is intimated that HPPC is in the process of floating Two no. NITs for purchase of 50 MW solar & 100 MW non-solar power. The date of opening of tenders has been fixed as 31.7.2014 for solar & 14.8.2014 for non- solar power.
Although NIT is based on the Standard RFP for procurement of power under “Case 1 -RE” Bidding procedure through Tariff based Competitive Bidding Process (As per Guidelines for tariff Based Competitive Bidding Process for Grid Connected Power Projects Based on Renewable Energy Sources” issued by the Govt. of India), however a few changes have been done mainly affiliates have not been allowed, Delivery point is Haryana periphery and tariff to be quoted and evaluated will be at Delivery point, negotiation will be done etc.
It is requested that HERC may furnish its valuable comments, if any, on the NIT latest by 25.6.2014 so that HPPC may proceed further with tender process.”
In the communication-dated 16.06.2014, the Petitioner has also placed on record that negotiations etc. will be done. This was in the context that negotiations will be required to be done for reducing the price as far as possible from the ceiling cost, in the larger interest of the consumers. 2. By communication-dated 25.06.2014, the Commission was pleased to hold as under:
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar power to meet RPO.
This is with reference to your office memo no. Ch-43/HPPC/SE/C&R-I/PPA-136 dated 16.06.2014 vide which copy NITs for purchase of 50 MW solar & 100 MW non-solar power have been forwarded for comments.
Page 17 of 54
Before the case is further processed, it is requested to clarify/intimate the following:
A copy of the Standard Bidding Documents for procurement of power under “Case 1-RE” Bidding procedure through Tariff based Competitive Bidding Process for Grid Connected Power Projects Based on Renewable Energy Sources issued by the Government of India be provided.
The deviations made in the NIT with respect to the Standard Bidding Document for procurement of power under “Case 1-RE” issued by the Government of India be tabulated.
The copy of the statute, under which the deviations sought by HPPC from the Standard Bidding Documents issued by the Government of India requires the approval of the Commission, may also be provided.
The above clarification/information be provided within a week from the date of issue of this letter.”
3. Thereafter, by communication-dated 01.07.2014, the Petitioner furnished the deviations from the Standard Bidding Document as per the direction of the Commission with a covering letter as under:
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar power to meet RPO- approval thereof
This is with reference to your Memo. No. 1124/HERC/PPA/NIT-RE/Tariff dated 25.6.2014 on the subject.
In this regard, Standard Request for Proposal for Procurement of Power Under case1 – RE” Bidding Procedure through tariff Based Competitive Bidding Process (As per Guidelines for tariff Based Competitive Bidding Process for Grid Connected Power Projects based on Renewable Energy Sources”) is enclosed. (Annexure A)
Deviations made in the NIT w.r.t the SBD for procurement of power under “Case 1- re” in tabulated form is enclosed. (Annexure B)
It is submitted that approval of Honorable Commission on the Two Nos. subject cited NITs is required in view of the Clause 3.1.2 of MNRE “Guidelines for Tariff based Competitive Bidding Process for Grid Connected Power Projects Based on Renewable Energy Sources- December 2012” (Annexure C) which states that
“Approval of the Appropriate Commission shall be sought in the event of the deviations from the bidding conditions contained in these guidelines and SBD, following the process described in para 6.9 of these guidelines.”
It is humbly requested that approval may please be granted on the NITs for purchase of 50 MW solar and 100 MW non-solar power.”
4. In response to the above, the Hon’ble Commission by communication-dated 28.07.2014 wrote as under:
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar power to meet RPO.
Page 18 of 54
This is with reference to your office memo no. Ch-46/HPPC/SE/C&R-//PPA- dated 25.06.2014.
The Commission has observed that there are many other deviations particularly to Bid Bond, CPG, Payment Security etc. The Standard Bid Document may heave PPA also.
You are requested to submit all deviations made in the NIT with respect to the Standard Bidding Document (SBD) for procurement of power under “Case 1- RE” issued by the Government of India in tabulated form and also the PPA attached with the SBD within a week from the date of issue of this letter.”
5. On 05.08.2014, the Petitioner submitted as under:
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar power to meet RPO
This is with reference to your memo No. 1535/HERC/PPA/NIT-RE/Tariff dated 28.7.2014 on the subject.
In this regard, it is submitted that major deviation in NIT from SBD in respect of Bid Bond & Contract Performance Guarantee is that of the amount per MW to be paid. All the minor deviations will be rectified to have the NIT exactly the same as that of SBD. All these deviations have been color coded in the comparison done in the tabular form. (Annexure A)
Also, Standard Bid Document does not contain any PPA.
It is humbly submitted that the date of opening of tenders is 22.8.2014 for solar power and 29.8.2014 for non-solar power.
Submitted for the kind consideration of the Commission please.”
Along with the above letter, the list of deviation was also given. 6. On 08.08.2014, the Hon’ble Commission was pleased to allow the Petitioner to proceed with the Competitive Bidding Process. The letter-dated 08.08.2014, reads as under:
“Subject: NIT for Purchase of 50 MW solar & 100 MW non-solar power to meet RPO – approval thereof.
kindly refer to your memo no Ch-43/HPPC/SE/C&R -I/PPA – 136 dated 16.06.2014 and Ch-46/HPPC/SE/C&R-I/PPA-67 dated 1.07.2014 vide which approval of the Commission was sought to be deviations in the bid documents vis-à-vis the Case – 1 RE Bidding Procedure of the Government of India. The Commission has considered your application/petition and observes that the NIT No. 51 & 52 for inviting competitive bids purchase of 50 MW for Solar Power and 100 MW of Non- Solar (renewable energy) were issued on 16.04.2014 and the approval of the Commission to the deviations were sought on 1.07.2014 i.e. ex post facto.
The Commission observes that the Discoms have not fulfilled their RPO including by way of purchase of REC. Consequently, the accumulated shortfall allowed to be carried forward from FY 2011-12 up to FY 2013-14 (up to December 2013) is about 720.83 Mus and the total RPO target set for FY 2014-15 is 1463.41 Mus. On several
Page 19 of 54
occasions the Commission has observed that HPPC/HAREDA may invite bids/ reverse bids for purchase of renewable energy in order to meet with the RPO targets and the fact that the bidding process is already under way, HPPC may proceed with the same. Once the bids are opened HPPC shall analyze the same and submit the details to the Commission for its order and approval of the PPA with the successful bidders.
7. After getting concurrence on 8.8.2014 by HERC and ceiling tariff of Rs 7.45/kwh determined by HERC vide order dated 13.8.2014, Technical bids were opened on 22.10.2014 & financial bids on 22.12.2014. Ten nos. bidders had submitted the tenders. Out of them, only Eight Nos. Bidders were found eligible for financial evaluation. Hence, only 23 MW could be tied up against the required capacity of 50 MW.
8. Further, it is submitted that HERC vide their order dated 20.11.2013 titled “modification of Renewable Purchase Obligations” states that the DISCOMS/HPPC is able to procure renewable energy power (Solar and Non-Solar) at a Tariff lower than determined by the Commission by way of reverse bidding or otherwise, they may do so.
However, it is stated that MNRE issued draft guidelines and SBD for purchase of renewable power through competitive bidding in Dec 2012 which were not notified as such. Further, it is pertinent to point out that the Hon’ble Commission has in another case also approved the PPA executed by the Petitioner with another developer, M/s Siwana Solar Power Ltd., for 5MW vide letter dated 21.02.2014. The aforesaid solar power developer is being paid tariff at the rate of Rs.6.44/Kwh as per clause 2.1.41 of the said PPA as the present tariff of Rs.6.44/Kwh discovered through the instant competitive bidding process carried out by HPPC was the lowest tariff vide HERC order dated 20.1.2016.
16.1.6 Objection: NSEFI has raised objection that as per Clause 6.8 of MNRE that order will be placed on the lowest discovered tariff, rest all the offers will be cancelled.
Reply: The tariff as decided by the HERC was the ceiling limit and bidders were to quote any tariff less than that. MNRE adopts bucket filling approach whereas HPPC asked the bidders to match the L-I tariff. Hence, only 23 MW could be tied up against the required capacity of 50 MW. As far as negotiation clause is concerned, HPPC has already conveyed to HERC vide letter 16.6.2014. Thereafter, HERC conveyed its consent vide letter dated 8.8.2014. It is submitted that there is no violation of any guidelines formulated by GoI. As per policy of Govt of Haryana, negotiation was done only after the quoted lowest price was discovered, so that maximum power could be procured at the lowest price discovered in the interest of State consumer. However, it is pertinent to mention here that MNRE issued draft guidelines and SBD for purchase of renewable power through competitive bidding in Dec 2012 which were not notified as such.
Page 20 of 54
Further, it is submitted that HERC vide their order dated 20.11.2013 titled “modification of Renewable Purchase Obligations” states that the DISCOMS/HPPC is able to procure renewable energy power (Solar and Non-Solar) at a Tariff lower than determined by the Commission by way of reverse bidding or otherwise, they may do so. 16.1.7 Objection raised: As per MNRE guidelines at Clause 6.3, there will be External Expert in Evaluation Committee.
Reply: The Petitioner submits that there has been no violation of the bidding documents in regard to the External Expert in evaluation Committee as per the Guidelines issued by the Ministry of Non-Conventional Energy Sources. The bidding submission date was after the Hon’ble commission has decided the ceiling tariff for Solar power projects at Rs 7.45/kwh in the Order dated 13.8.2014. Similarly, in the Order dated 15.5.2014, the Central Commission has also determined the tariff for Solar power projects at Rs 7.72/kwh. The above decision of the Hon’ble Commission dated 13.8.2014 was required before the bid submissions. The bid submissions date was in fact deferred from time to time till 22.10.2014. The Petitioner submits that the fixation of the above tariff at Rs 7.45/kwh by the Hon’ble Commission and Rs 7.72/kwh by the Central Commission provided the price aligned to the market conditions. The Hon’ble Commission and the Central Commission had determined the above tariff after considering all the relevant facts and taking into account the price which could be the appropriate one, i.e. the ceiling price. Infact, inviting competitive bids in the light of the above tariff determined necessarily means that bidders were to bid keeping the tariff already decided i.e. in a competitive environment to quote lower to the extent they decide.
However, it is pertinent to mention here that MNRE issued draft guidelines and SBD for purchase of renewable power through competitive bidding in Dec 2012 which were not notified as such.
16.1.8 Objection: Networth has been taken as Rs. 2.00 crores instead of Rs.3.50 crores
Reply: The Networth of the Solar Power Developer was reduced to invite the maximum nos. of bidders to have the most competitive rates .Also , in the RFP document issued by Punjab Energy Development Agency( PEDA) for 300 MW solar photo voltaic power projects under phase -1 in March 2012, the net worth had been taken as 2 crores/ MW.
16.1.9 Objection: M/s Neel metal (M/s JBM) has not intimated the location of project. The change of location of land was not permitted in NIT.
Reply: The following clause of NIT states that:
2.8.3. Consents, Clearances and Permits
2.8.3.1. Site Identification and Land Acquisition:
At this stage, the project developer would also provide evidence that the requisite technical criteria have been fulfilled and required land for project development @ 2 Hectares/MW (or as per requirement of the project) is under
Page 21 of 54
clear possession of the project developer. In this regard the Project developer shall be required to furnish the following documentary evidences:- i. Ownership or lease hold rights (for at least 30 years) in the name of the Project Developer and possession of 100% of the area of land required for the allotted project. ii. Requisite documents from the concerned and competent revenue/registration authority for the acquisition/ownership/vesting of the land in the name of Project Developer and in case private land converted for industrial use. iii. In case of land to be acquired under the Land Acquisition Act 1894 or its equivalent, the Bidder shall submit copy of notification issued for such land under Section 6 of the Land Acquisition Act 1894 or its equivalent. iv. In all other cases, the Bidder shall furnish documentary evidence in the form of certificate by concerned and competent revenue / registration authority for allotment of the land. In case of non-availability of land with the bidder at the time of bidding, an undertaking has to be submitted that the documentary evidence will be produced by the bidder of the availability of land at the time financial closure of the project. The undertaking can be provided in the Format 4.4 (C). v. If the identified generation source is an existing power station, the Bidder shall submit the documentary evidence regarding commissioning of the power station. In case of supply being proposed from an existing power station, the Bidder should submit evidence in the form of a declaration sent to RLDC/SLDC, as the case may be, in support of commercial operation of the power station. vi. If the Bidder is a trading licensee, it shall have executed exclusive power purchase agreement(s) for the quantity of power offered in its Bid and shall provide a copy of the same as part of its Bid. In such a case, the Bidder shall ensure that the entity with whom it has executed the exclusive Power Purchase Agreement (PPA) for supply of power under the bidding process has completed the project preparatory activities as mentioned in this clause.
Note: (i) Change in the location of land from one place to other location is
permitted till the Financial closure (ii) The land should be free from all encumbrances. (iii) The land should neither have been proposed for other purposes &
nor should have been mortgaged.
From the above, it is clear that it was not mandatory for the bidder to possess the land at the time of bid submission and he could even change the location till the Financial closure.
16.1.10 Objection: The following information was to be furnished at the preliminary stage:
a) Site identification and land possession b) The steering committee had conducted the meeting for power purchase. It
had taken the bench mark tariff of HERC as the ceiling limit.
Page 22 of 54
c) Why levelized tariff of FY 2013-14 has not been taken as ceiling limit while levelized tariff of 2014-15 as ceiling limit has been considered.
Reply: a) Clause 2.8.3 of NIT as reproduced above may be perused. b) All the record namely Minutes of Meeting (MoM) of Steering Committee for Power Planning (SCPP) constituted by Govt of Haryana held on 23.02.2015 wherein lowest tariff i.e. Rs. 6.44/kwh was discovered, which was lower than the HERC levelized tariff of Rs.7.45/kwh, has been submitted to HERC for the kind consideration of the Hon’ble Commission. c) The tariff of Rs.5.70/kwh as determined by the HERC in FY 2013-14 contains two errors. The first one is that it has not taken into account Income tax before arriving at ROE and the second one is that O & M expenses have been taken as Rs 1.1 lac per MW instead of Rs. 11 Lac per MW. Further, it is pointed out that NIT was floated after the levelized tariff (Rs. 7.45/kwh) was determined by HERC for the FY 2014-15 & 2015-16 and tariff was discovered through competitive bidding as Rs 6.44/kwh which is lower than HERC tariff.
16.2 Objections filed by Sh. Subhash, District Court Complex,
Panchkula.
That I have gone through the MNRE guidelines, Petition and interim orders of
the Hon’ble Commission and have following observations and objection:
16.2.1 The HPPC in point no 5 of their petition no PRO 6 submitted that
“Petitioner initiated competitive bidding process as per the Guidelines for Tariff
Based Competitive Bidding Process for Grid-connected Power Projects based
on Renewable Energy Sources issued by the Government of India.” It has been
further stated that “the Standard Request for Proposal for procurement of
power from Renewable Energy Sources notified by the Government of India
under Section 63 of the Electricity Act, 2003 was adopted for the above
purpose.”
Objection: The above statement of HPPC that bidding has been done in
accordance with guidelines and standard request for proposal notified by govt.
of India, later proved to be wrong and accepted by HPPC also as mentioned in
point no. (b) below.
16.2.2 The HPPC in point no. 8 of the petition has mentioned that “Although
NIT is based on the Standard RFP for procurement of power under “Case 1 -
RE” Bidding procedure through Tariff based Competitive Bidding Process (As
per Guidelines for tariff Based Competitive Bidding Process for Grid Connected
Power Projects Based on Renewable Energy Sources” issued by the Govt. of
India), however a few changes have been done mainly affiliates have not been
allowed, Delivery point is Haryana periphery and tariff to be quoted and
evaluated will be at Delivery point, negotiation will be done etc.”
Page 23 of 54
Objection: The HPPC first said that everything is in accordance with guidelines
and then said that few changes have been done from standards.
16.2.3 The HPPC in point no. 9 has stated that “negotiations will be required to
be done for reducing the price as far as possible from the ceiling cost, in the
larger interest of the consumers.”
Objection: In the petition nowhere it is mentioned that what was the ceiling
cost mentioned in the NIT, from which further reduction was supposed to be
done by negotiating. Because bidders would bid based on ceiling cost
mentioned in the NIT only.
I have to search for the NIT dated April 2014 on the website and found that
Levelised tariff in the NIT was the levelised tariff of HERC i.e. Rs. 5.7/kwh, as
per commission’s order dated 20.11.2013 (clause 2.5.5 of NIT). Whereas, tariff
approved is Rs. 6.44/kwh. Although, Commission later vide order dated
13.08.2014 determined the levelised tariff at Rs. 7.45/kwh for the projects
commissioned during the FY 2014-15 & 2015-16, the same cannot form basis
for merit order prepared on 23.02.2015, in contravention of the rate mentioned
in NIT. Further, MNRE Guidelines, 2012 at clause 5.4 (iii) specified that bids
should contain tariff comprising of escalable components and non-escalable
components. The bids shall be evaluated for the levellised tariffs based on the
components of the tariff quoted by the Bidder.
Further, the ceiling tariff against which bids are to be evaluated should not
contain a general statement but should have been fixed taking into
consideration of all the factors prevalent in state of Haryana and neighboring
states.
Further, MNRE guidelines states that bids should be evaluated against a
benchmark rates to be decided taking into consideration of the prevalent
market conditions. No such rate was fixed. Bidders under the impression of
benchmark rate as Rs. 5.70 never applied for the bid and clandestinely the
higher rate of Rs. 6.44 was settled.
16.2.4 The commission has itself raised various objections on the bidding
process, evaluation committee, negotiation process, contravention of SBD etc.
by interim order dated 11.02.2016:
i) HPPC may explain as to why the proper procedure as mandated by the SBD was not adopted in this regard.
ii) Disclose the composition of Bid evaluation committee and also that the same was constituted in accordance with the SBD.
iii) Whether the Bid evaluation committee consisted of an external expert in the Committee as mandated by the SBD.
iv) Whether the Bid Evaluation Committee certified that the rates quoted by the bidders were aligned to the market conditions. As per the news item
Page 24 of 54
published in “TheTimes of India” dated 20.01.2016, the Solar price tariff hits new low in Rajasthan i.e. Rs. 4.34 to Rs. 4.63 paisa per unit quoted by Fortum India in one of the six pockets bid out by state run generation utility NTPC in Rajasthan. Also, the latest bids called by HPPC for 150MW solar power have thrown up the rate of Rs.5.00/Kwh.
v) In the present scenario how HPPC can negotiate with the developer at such a high price of Rs. 6.44 per unit without any justification.
vi) Why the HPPC has not followed its own process as mandated in Para 3.1.4 (IV)
vii) Why negotiations were carried out with the bidders in spite of clear instructions in the SBD forbidding the same.
Objection: The above observations of Hon’ble Commission are serious and
warrants out right rejection of proposed PPAs.
16.2.5 It appears that MNRE guidelines regarding bid evaluation committee,
fixation of ceiling tariff aligned to market conditions, negotiation etc. were not
followed.
The negotiation process has been objected by National Solar Energy
Federation of India, also, stating that the same violates the CVC guidelines on
tendering.
Further, Clause 6.8 of MNRE guidelines states that “The Bidder, who has
quoted lowest levellised tariff as per evaluation procedure, shall be considered
for the award. The Evaluation Committee shall have the right to reject all price
bids if the rates quoted are not aligned to the prevailing market prices. “
Further, Clause 6.3 of MNRE guidelines specified that “The Procurer shall
constitute committee for evaluation of the bids (Evaluation Committee) with at
least one member external to the Procurer’s organization and affiliates. The
external member shall have expertise in financial matters / bid evaluation. The
Procurer shall reveal past associations with the external member - directly or
through its affiliates - that could create potential conflict of interest. “
16.2.6 Has HPPC ascertained the fact that the bidders have adequate
land/arrangement to procure requisite land. Location of project was important
clause in NIT (Clause 2.8.3.1) and even change in the location of land from one
place to other location was not permitted.
Clause 3.2(I) of MNRE Guidelines on Tariff based competitive bidding for RE
dated Dec 2012 states that “to ensure serious participation in the bidding
process and timely completion of commencement of supply of power, the
Bidder, in case the supply is proposed from a power station to be set-up,
should be required to submit along with its bid, documents in support of having
completed specific actions for project preparatory activities in respect of matters
mentioned in (i) to (v) below.
Page 25 of 54
16.2.7 i) Site identification and land acquisition: ……………………..”
Objection: The compliance of above clauses which provides for location of
land be ascertained of all the shortlisted bidders.
16.2.8 That it is normally seen that whenever govt. initiate some scheme, some
unscrupulous elements take advantage by showing that they want to promote
govt. schemes. Like in this case, just to show that RPO obligations are to be
met, PPAs are being undertaken without considering the impact on the people
of Haryana of the same. Other alternatives to fulfill RPO obligations like Roof
Top Solar, Solar on the waste land proposed by Hon’ble CM, Renewable
Energy Certificates (REC) are not being explored. However, either no mind has
been applied by the concerned officers or very cleverly some private players
are being given the benefit.
16.2.9 That taking into consideration of falling Solar Electricity Rate, it is
prudent if purchase of solar electricity is delayed from 1-2 years, till the time
prices stabilizes. An analysis was done for the cost to be incurred, in case
purchase of solar electricity is delayed by two years and one year and for these
period REC are purchased. It has been noticed that for PPA @ Rs. 5/- is
delayed by two years, then net saving is Rs. 1.1 crore and in case the same is
delayed by one year, then net saving is Rs. 0.60 lacs. Similary, it has been
noticed that for PPA @ Rs. 6.44/- is delayed by two years, then net saving is
Rs. 3.34 crore and in case the same is delayed by one year, then net saving is
Rs. 2.84 crore.
16.2.10 Pollution: Most of the photovoltaic penals are made up of silicon
and other toxic metals like mercury, lead and cadmium. Pollution in the
environment can also degrade the quality and efficiency of photovoltaic cells,
New innovative technologies can overcome the worst of these effects.
16.2.11 Inefficiency: Since not all the light from the sun is absorbed by the
solar penals therefore most solar penals have a 40% efficiency rate which
means 60% of the sunlight gets wasted and is not harnessed. New emerging
technologies however have increased the rate of efficiency of solar penals from
40 to 80% and on the downside have increased the cost of solar penals as well.
16.2.12 Reliability: Unlike other renewable energy sources which can also
be operated during night, solar penals prove to be useless which means you
have to depend on the local utility grid to draw power in the night or you can
buy solar batteries to store excess power which you can later utilize in the night
Apart from that, storms or hurricanes also reduce your ability to draw power
during those days.
16.2.13 Installation Area: For home users, a Solar energy installation may
not require huge space as it can be installed on rooftops that can produce
Page 26 of 54
sufficient energy but for big companies, a large area is required for the system
to be efficient in providing electricity on a constant basis.
HPPC’s Reply:
HPPC has filed a common reply to the objections raised by Sh. Subhash, Panchkula and Sh. Rattan Singh Pannu, Hisar. as under:
16.2.1 and 16.2.2 Same as reply to Objection at Sr. No. 16.1.5
Reply to point 16.2.3: The ceiling limit in the NIT was the levelized tariff determined by HERC for the projects to be commissioned in FY 2014-15 as is evident from the following clause (Definition) of NIT: “Quoted Tariff” shall mean the Quoted Energy Charges, as applicable, quoted by the Bidder as per the prescribed Format 4.7 and shall be construed to be at the Delivery Point as mentioned in its Bid;
The levellized tariff (i.e. Rs7.45/kwh) for Renewable Energy Projects to be commissioned in FY 2014-15 as determined by HERC will be the ceiling limit and the bidder quoting the tariff above that will be allowed only the levellized generic tariff decided by HERC. It can be seen from the above, Rs.5.70/kwh was the levelized tariff for the projects to be commissioned in FY 2013-14 but NIT was floated in the month of October of FY 2014-15.Hence, in NIT No. 51, the ceiling limit is Rs 7.45/kwh i.e. the levelized tariff determined by the Commission for FY 2014-15. Further, MNRE Guidelines, 2012 is about all kind of Renewable Energy sources hence, tariff is comprising of escalable and non-escalable components. But in case of solar power, there is no variable cost in lieu of fuel. Hence, fixed tariff was kept in the NIT. Reply to point 16.2.4 HPPC has filed the written submission dated 9.3.2016 in reply to all the queries of the HERC. The same may please be referred. However, As far as negotiation clause is concerned, HPPC has already conveyed to HERC vide letter 16.6.2014. Thereafter, HERC conveyed its consent vide letter dated 8.8.2014. It is submitted that there is no violation of any guidelines formulated by GoI. As per policy of Govt of Haryana, negotiation was done only after the quoted lowest price was discovered, so that maximum power could be procured at the lowest price discovered in the interest of State consumer.
Reply to point 16.2.5 as per reply to objection at 16.1.9 Reply to point 16.2.6 The allegation is not correct and is denied. The procurement of solar power through rooftop project cannot be compared with procurement of ground mounted solar projects. The two are distinct, both in capacity as well as the ability to meet the RPO obligation. As far as REC is concerned, from the Table-
Page 27 of 54
‘A’, it is very much proved that the solar power procure through competitive bidding by HPPC is very much competitive/economical as compare to buying REC. Reply to point 16.2.7 As far as REC is concerned, from the Table- ‘A’, it is very much proved that the solar power procure through competitive bidding by HPPC is very much competitive/economical as compare to buying REC.
Reply to point 16.2.8 The facts are not correct. The multi crystalline modules are the most environment friendly technology available to the mankind. Degradation in the modules are caused by separate events. It’s a separate chapter altogether and nothing to do with present proceedings. Moreover, tariff offered in this case is irrespective of degradations. That means tariff is fixed for 25 years and risk of degradation lies with the SPD and hence consumers of Haryana are de risked in that way.
Reply to point 16.2.9 The point raised is totally not correct and out of context.
Reply to point 16.2.10 The point is out of context. However, the consumer is de-risked of any such eventuality and SLDC & DISCOMS take care that consumer gets power all the time at the best possible rates.
Reply to point 16.2.11 Again, the argument made here is totally out of context. It seems that the points made out here to mislead the Honorable commission. The roof top area per KW is either higher or equal as compared to ground mounted solar PV power Plant. Anyhow, land arrangement is the responsibility of the developer in this case and HPPC has nothing to do at all. In view of matter explained on pre-page, from the facts/reply to questionnaire, it is understood that as far as procedure for selection of bidder is concerned, HPPC has done transparent & competitive bidding as per Govt. Instructions/guidelines and discovered the lowest tariff for respective period w.r.t. levelized tariff determined by HERC for FY- 2014-15 & 2015-16. It is also submitted that HERC vide their order dated 20.11.2013 titled “modification of Renewable Purchase Obligations” states that the DISCOMS/HPPC is able to procure renewable energy power (Solar and Non-Solar) at a Tariff lower than determined by the Commission by way of reverse bidding or otherwise, they may do so. Further, it is added that other state DISCOM/Govt. of India is using bucket filling approach wherein various tariff is to be given to solar power developers till the capacity of bucket. However, HPPC has carried out negotiation as per State policy to reduce the tariff in the interest of consumers. Further, it is pertinent to point out that the Hon’ble Commission has in another case also approved the PPA executed by the Petitioner with another developer, M/s Siwana Solar Power Ltd., for 5MW vide letter dated 21.02.2014. The aforesaid solar power developer is being paid tariff at the rate of Rs.6.44/Kwh as per clause 2.1.41 of the said PPA as the present tariff of Rs.6.44/Kwh
Page 28 of 54
discovered through the instant competitive bidding process carried out by HPPC was the lowest tariff vide HERC order dated 20.1.2016. It is also stated that tariff of Rs 4.34 to Rs 4.63/unit was the bidding rate for solar park for the state of Rajasthan wherein lot of facilities like land on lease, Transmission line, water ,sewerage system and boundary wall are to be provided by State and solar radiation in Rajasthan is much higher than Haryana to get more generation. Moreover, land cost is also high in state of Haryana. It is also submitted as far as buying REC is concerned; it is very much proved that buying REC instead of procuring solar power through competitive bidding is not economical as shown in Table-‘A’. 16.3 Objections filed by Senior Citizens' Council (Regd.), Panchkula. The
objection already raised by the Hon’ble Commission by interim order dated
11.02.2016 is of serious nature. Replies of the DISCOMs on the same should
be sought and made public. The observation of the Commission are as under:
i) HPPC may explain as to why the proper procedure as mandated by the
SBD was not adopted in this regard.
ii) Disclose the composition of Bid evaluation committee and also that the
same was constituted in accordance with the SBD.
16.3.1 Whether the Bid evaluation committee consisted of an external expert in
the Committee as mandated by the SBD.
16.3.2 Whether the Bid Evaluation Committee certified that the rates quoted by
the bidders were aligned to the market conditions. As per the news item
published in “The Times of India” dated 20.01.2016, the Solar price tariff hits
new low in Rajasthan i.e. Rs. 4.34 to Rs. 4.63 paisa per unit quoted by Forum
India in one of the six pockets bid out by state run generation utility NTPC in
Rajasthan. Also, the latest bids called by HPPC for 150MW solar power have
thrown up the rate of Rs. 5.00/Kwh.
16.3.3 In the present scenario how HPPC can negotiate with the developer at
such a high price of Rs. 6.44 per unit without any justification.
16.3.4 Why the HPPC has not followed its own process as mandated in Para
3.1.4 (iv)
16.3.5 Why negotiations were carried out with the bidders in spite of clear
instructions in the SBD forbidding the same.
16.3.6 How the negotiations have been done in the NIT. Were the negotiations
permitted as per CVC guidelines and MNRE guidelines. If not permitted, how
can HPPC undertake negotiations.
Page 29 of 54
16.3.7 Has HPPC determined any benchmark tariff taking into consideration of
the prevalent market conditions and recorded the same and circulated to the
public so that bidders can know the maximum price they can fetch for their sale
of electricity.
16.3.8 HPPC to show that they communicated to the bidders the firm price i.e.
benchmark tariff, against which the bids are to be evaluated and on the basis of
which bidders have done the bidding. In case that benchmark tariff increased,
then has HPPC issued notice to the public intimating such increase, so that
competition can be increased and more parties can bid.
16.3.9 The HPPC in point no 5 of their petition no PRO 6 submitted that
“Petitioner initiated competitive bidding process as per the Guidelines for Tariff
Based Competitive Bidding Process for Grid-connected Power Projects based
on Renewable Energy Sources issued by the Government of India.” It has been
further stated that “the Standard Request for Proposal for procurement of
power from Renewable Energy Sources notified by the Government of India
under Section 63 of the Electricity Act, 2003 was adopted for the above
purpose.”
In this context, HPPC to show the compliance, because the interim order of the
Hon’ble Commission states otherwise.
16.3.10 It has been gathered that some of the bidders were selected
without even ascertaining that they possess the land. Even the location in
Haryana, where land is available was not provided by the bidders and only after
their selection, the bidders went on in search of land. HPPC to provide
comments on the same.
16.3.11 It has been gathered that private parties are being benefitted by
signing PPA at very high rate of 6.44/- and 5/-, when there is no need of
electricity and electricity is already surplus, on the pretext of fulfilling RPO
obligations. RPO obligations should be meant only for further power to be
purchased, in case of need for the same and not for purchasing power without
need just to fulfill RPO obligations.
RPO obligations should be met from promotion of Rooftop Solar scheme by
giving incentives of Rs. 1.25/ unit instead of 0.25/unit at present.
Further, other alternatives on installing Solar plant on waste land of Govt. be
considered.
Page 30 of 54
HPPC should prepare projected availability of power from these sources, if
implemented. Without preparing projections for these, a situation may come
where on the one side Haryana will be purchasing costly power from Private
suppliers and on the other PRO obligations will be fulfilled by Rooftop and
Govt. Solar Power plants on waste land.
16.3.12 Purchase of solar electricity should be delayed in view of the
falling market price of solar electricity, till the time it stabilizes, since at present
there is no shortage of power in Haryana.
16.3.13 HPPC should formulate a scheme of fulfilling RPO obligations by
specifying what percentage be met from various means of Renewable power
i.e. rooftop, municipal waste land, educational institution roof top etc.
It would be high appreciated by our members, in case such high cost PPA with
apparent malafide intentions and with grave irregularities are not approved.
16.3.14 HPPC’s Reply
1. The reply to HERC observations raised vide interim order dated 11.2.2016 has already been submitted by HPPC vide letter dated 09.03.2016. Further, action as deemed fit may be taken by the Hon’ble Commission. 2. Negotiations were carried out as per policy of Govt. of Haryana and after taking approval of Hon’ble commission vide their letter dated 08.08.2014 in order to reduce the tariff in the interest of consumer. HPPC submits that the negotiation with the bidders, in the present case did not vitiate the bidding process in any manner and it rather, added value to the Haryana Utilities and the consumer at large. 3. The bench mark tariff was the generic levelized tariff determined by HERC for the FY 2014-15, which was in public domain i.e. @Rs 7.45/kwh. However, HPPC discovered the lowest tariff through competitive biddings @ Rs 6.44/kwh and Rs 5/kwh which is much lower as compared to the levelized tariff determined by the HERC.
Further, it is pertinent to point out that the Hon’ble Commission has in another case also approved the PPA executed by the Petitioner with another developer, M/s Siwana Solar Power Ltd., for 5MW vide letter dated 21.02.2014. The aforesaid solar power developer is being paid tariff at the rate of Rs.6.44/Kwh as per clause 2.1.41 of the said PPA as the present tariff of Rs.6.44/Kwh discovered through the instant competitive bidding process carried out by HPPC was the lowest tariff vide HERC order dated 20.1.2016.
4. Same as reply to point No. 16.2.3 of Sh Subhash as above. 5. Same as reply to Objection at 16.1.5 as above 6. Same as reply to 16.1.9 Objection as above
7. HPPC had initiated purchasing solar power under following
circumstances:
Page 31 of 54
Section 86 (1)(e) of the Electricity Act, 2003 inter-alia, provides for the function of the State Commission as under:
“promote cogeneration and generation of electricity from renewable sources
of energy by providing suitable measures for connectivity with the grid and
sale of electricity to any person, and also specify, for purchase of electricity
from such sources, a percentage of the total consumption of electricity in the
area of a distribution licensee”
In the Tariff Orders passed by the Hon’ble Commission from time to time, the Haryana Utilities have been mandated to purchase power to meet the Renewable Purchase Obligation. In this regard, the Hon’ble Commission has notified HERC (Terms and Conditions for determination of tariff for Renewable Energy Sources, Renewable Purchase Obligation and Renewable Energy Certificate) Regulation, 2010. The Table below shows the RPO Targets as set by HERC,Targets achieved and shortfall therein in the previous five years:
Renewable Purchase Obligation from the FY 2011-12 to FY 2015-16
Financial year
Energy Consumption (MU)
%age of solar RPO (as a %age of overall RPO)
Energy required to be purchased as per solar RPO (MU)
Energy actually purchased
Shortfall therein ( MU)
2011-12 36075 0.31% 1.69 2.3 -0.69
2012-13 40000 0.05% 20 12.86 7.14
2013-14 41086 0.10% 41.09 10 31
2014-15 45028 0.25% 112.57 10 102.57
2015-16 46731 0.75% 350 127 223
From the above it can be seen that Haryana DISCOMs were finding it hard to meet the RPO targets set by the Hon’ble Commission. Therefore, HPPC filed various petitions from time to time with a prayer for amendment of RE Regulations, 2010 and relaxation or carry forward of Renewable Purchase Obligation (RPO) :
I) Petition dated 8.06.2012 for seeking review / or modification of Renewable Purchase Obligation (RPO). II) Petition dated 19.10.2012 and Supplementary filing dated 25.01.2013 for seeking review and / or modification of the Haryana Electricity Regulatory Commission (Terms and Conditions of Determination of Tariff from Renewable Energy Sources, Renewable Purchase Obligation and Renewable Energy Certificate) Regulations, 2010. III) Petition dated 20.08.2013 for seeking relaxation or carry forward of Renewable
Purchase Obligation (RPO) for FY 2011-12 and FY 2012-13.
Disposing of the above petitions, HERC issued an order dated 20.11.2013. The
abstract of the same is reproduced hereunder:
Page 32 of 54
It is clarified that the tariff determined by the Commission is the ceiling
tariff. In case the Discoms / HPPC is able to procure renewable energy
(solar and non – solar) at a rate lower than that determined by the
Commission by way of reverse bidding or otherwise, they may do so.
However, the Discoms / HPPC, may not evade their responsibilities of
achieving the RPO specified in the RE Regulations, 2010 for the
respective years on the plea that they are in the process of inviting bids
or merely making a statement that renewable energy is available at a tariff
lower than that determined by the Commission.
Further, HERC vide its order dated 7.5.2015 for true- up for the FY 2013-14,
annual (mid-year) performance review for the FY 2014-15, revised aggregate
revenue requirement of UHBVNL & DHBVNL & distribution & retail supply tariff
for the FY 2015-16 stated as under:
The Commission directs the Discoms to purchase renewable energy as
per RPO targets set for the FY 2015-16 and the shortfall carried forward,
on actual basis, for previous years. In case they can purchase the same at
a tariff lower than determined by this Commission they may do so,
otherwise they must purchase all such power offered to them by the
renewable energy power producers at the tariff determined by this
Commission.
It is pertinent to point out that HPPC did not purchase any power during all
these years in order to avoid the burden on the consumers of the State. Also,
HPPC was reluctant to purchase power citing the reasons that there are not
much resources of renewable energy in Haryana viz Wind energy cannot be
generated, not much hydro potential is available as irrigation system is based
on canals having low head, mostly agriculture land is available.
8. HPPC reply is same as Sr. No. 7 above. 9. It does not relate to HPPC & the issue regarding percentage to be met from various means of Renewable power for fulfilling RPO obligations has to be decided by Hon’ble commission. Suggestion given is to be taken care of by HERC and is not in the purview of HPPC.
16.4 Objections filed by Faridabad Industries Association.
16.4.1 That the Objector wants to clarify here itself that proposed petition has
not mentioned any benefits public/ consumer at large will have if in case their
petition is passed by Hon’ble Commission after doing Balance of Conveniences
from both sides i.e. Generator/ Consumer which consumer had every night to
know as sec 86 of EA act, NTP Policy and under article 14 of Constitution of India like.
a. Copy of Proposed PPA or Prospective terms and conditions of said PPA
should be available to consumer, because all taxes levied by competent
authority; Electricity Duty and any other levies in respect of the energy
Page 33 of 54
generated by the developer shall be reimbursed by the procurers. With all these
element and added transmission losses and the obligation to make
arrangements for evacuation of power, the total tariff to be paid by DISCOMS
would increase from time to time and shall be burden n the consumers.
b. Petitioner in their petition has not provided any load forecast, including
demand growth, addition of installed capacity, transmission and distribution
capacity etc. to justify the need from procurement of power from SOLAR just
because for sake of compliance and regulation and any policy of Government
DISCOM superficially putting a petition for the approval by Commission will be
against the Principal of Natural Justice and Law of Equity and constitution of
India because in case, Commission passed the petition without data in case
due to bad management of DISCOM or due any unforeseen reasons will
increase in O&M Charges which shall be made part and parcel through mode
of increase in tariff of Tariff proposal of Discoms in future u/s 62 of Electricity
Act will passed on to the Consumers.
16.4.2 In their petition they have not mentioned anywhere when would
Transmission Corridor be available for evacuation of power? Has the Petitioner
booked Transmission Corridor from CTU and STU concerned?
So therefore Petitioner need to also mention in the petition about all these facts
so that a better analysis can be made at large by the Commission.
16.4.3 Judicious mix of both long and short term procurement should be
deployed based on forecast demand and price forecasts.
16.4.4 Before going through Petition of the Petitioner, the Commission should
seek information relating to capital cost of the project, sources of supply etc.
and make it available to the public because we are again reiterating that the
ultimate financial implication shall be recovered from procurer/ consumer
without going into negates who are responsible for the said scenario whether
DISCOM/GENRATOR/DEVELOPER.
16.4.5 Before allowing the said petition of the Petitioner, Hon’ble Commission
need to see the financial principal such as Benchmarking of Capital cost, Dept,
Equity, Loan and Financial Charges, Deprecation, Return on Equity, Intrest on
Working on Capital.
16.4.6 Commission should also seek implement scheduling on experimental
basis as scheduling of Solar Power is at a nascent stage in India and error
margin would be higher +/- 30% during most of the times.
16.4.7 Copies of all PPA or terms and conditions on which prospective PPA is
supposed to be entered between parties whether related to SOLAR POWER,
Gas Power impacting tariff of Haryana or industrial consumer should be liable
to annexed with the Petition otherwise Commission judicial decision can be
based on wrong notion and on normative figures which tantamount to violation
of the basic essence for which Commission was established.
Page 34 of 54
16.4.8 16.4.8 HPPC’s Reply
1. Justification to purchase Solar power : same as reply at point 7 of para
16.3.14
a) The copy of the proposed PPA was part of NIT for which Hon’ble
commission has already given approval vide letter dated 08.08.2014 & the
same can be made public by HERC.
As far as tariff (Rs 6.44/kwh) is concerned, it is fixed for whole tenure of the
PPA i.e. 25 years and the same is lower than levelized tariff as determined
by HERC.
b) HPPC has carried out competitive bidding as per HERC order dated
20.11.2013 and 07.05.2015 wherein Hon’ble commission states that:
As per HERC order dated 20.11.2013:
It is clarified that the tariff determined by the Commission is the ceiling tariff.
In case the Discoms / HPPC is able to procure renewable energy (solar
and non – solar) at a rate lower than that determined by the Commission by
way of reverse bidding or otherwise, they may do so. However, the
Discoms / HPPC, may not evade their responsibilities of achieving the RPO
specified in the RE Regulations, 2010 for the respective years on the plea
that they are in the process of inviting bids or merely making a statement
that renewable energy is available at a tariff lower than that determined by
the Commission.
As per HERC order dated 07.05.2015:
The Commission directs the Discoms to purchase renewable energy as
per RPO targets set for the FY 2015-16 and the shortfall carried forward, on
actual basis, for previous years. In case they can purchase the same at a
tariff lower than determined by this Commission they may do so, otherwise
they must purchase all such power offered to them by the renewable
energy power producers at the tariff determined by this Commission.
2. As the projects were to be commissioned within the State. Hence,
transmission corridor was not required. Even if the projects had been located
outside the State, the availability of Transmission corridor was the
responsibility of developers.
3. It is reiterated that solar power is purchased to meet RPO targets fixed by
HERC and not under Demand supply scenario.
4. As far as capital cost of the project is concerned, the HERC is well
conversant with the same as it determines the generic tariff every year on
the basis of the same.
5. HERC takes into consideration all the terms like ROE, Interest on loan etc.
while determining the generic tariff every year after considering all the
financial parameters, HERC vide their dated 13.08.2014 determined the
levelized tariff @ Rs 7.45/kwh for the FY 2014-15 and 2015-16. Thereafter,
Page 35 of 54
HPPC carried out competitive bidding after getting approval from HERC and
discovered lowest tariff @ Rs 6.44/kwh which is lower than the tariff
determined by HERC.
6. The Commission may consider the contention.
7. PPA is already with the Commission for approval.
16.5 Objections filed by Sh. Deepak Girdhar, Advocate.
16.5.1 During last a few years, the technology of harnessing solar energy has
developed a lot. With it the manufacturing price has reasonably reduced. The
solar electricity has become a reasonable option for replacing other
conventional manufacturing sources.
Recently it is a news that our neighboring state of Rajasthan has been
successful to have a solar PPA at a price in between Rs. 3 to Rs. 4 per unit.
Also it is in news that in Maharashtra as well there has been a drastic decline in
PPA rates.
Haryana Electricity Regulatory Commission is under statutory responsibility to
ensure that PPA remain within realistic frame. Solar electricity manufacturing
being a unconventional process of manufacturing electricity, as such it would
be most desirable that the expert opinion with the demonstration in a public
view be arranged, and the experts advise be made public so that the public at
large is not defrauded.
We hope that the power utilities during the bidding process would have already
obtained experts written advice on the subject.
We very humbly bring to your goodself’s kind notice that there being large
number of experts in Haryana and Delhi who can be very conveniently put on
duty to give their export opinion in writing and let the reality of the
manufacturing price be decided for the advantage of public at large.
It is further submitted with concern that a country of few manufacturers and non
manufacturers pool and arrange for bidding price above Rs. 3 per unit while the
manufacturing cost is only between Rs. 3 and Rs. 4 per unit.
If allowed we can send the names of few experts. Otherwise we are sure that
your good self are resourceful enough to appoint experts committee and can
obtain expert advise in within a reasonable time of one to two weeks in a best
interest of public in large.
It is right that solar power can be expensive but compared to other power PPAs
in the country which are below Rs. 4 per unit, then why does the power utilities
Page 36 of 54
want to do PPA on a higher price. This is when there are already large number
of PPA signed by the utility in the past and the power companies. And the
utilities are paying huge amount to power companies at fix charge every year.
The Hon’ble power minister has given the slogan of one nation, one grid and
one price and Haryana must contribute to this effort. The Hon’ble Commission
should also give directions to Private companies and the utilities that the
average market rates should be at par with other states because cost of solar
energy is at a historic low.
If achieving the RPO is important, then the bidding must be kept at the market
rate. It is further important to note that power in the state of Haryana is surplus.
Instead of accepting the costly high price PPA and paying fix charge it is better
to buy renewable advance certificates.
HPPC’s Reply
16.5.2 Justification to purchase Solar Power: same as reply at para 16.4.8
I. Purchase of solar power is beneficial as compared to RECs as can be seen from the table below:-
However it is pertinent to note that HPPC had floated tender in the month of Oct 2014
and at that time the cost of REC was Rs 9.30/kwh.
16.6 Oral Objections in the hearing:
16.6.1 Ms. Ranjita Mehta, Member, District Legal Service Authority:
In old PPAs an amount of Rs. 2000 Crores is being given as fixed charges.
Rajasthan is doing PPAs @ Rs.4.34 whereas in Haryana at Rs.6.44. This should not
be done and public should not be burdened with heavy bills of electricity by
purchasing power at much higher rates.
Purchase of REC Purchase of Solar Power
Total No. of units supplied 100 Total No. of units supplied 100
No. of Units at APPC Price 100 No. of Units at APPC Price 98
APPC Price for FY 2014-15 in Rs./kwh
3.53 APPC Price for FY 2014-15 in Rs./kwh
3.53
Let’s say 2 units of solar unit has to be purchased as REC to fulfil RPO
2 Let’s say 2 units out of 100 units served through solar
2
Cost of REC in FY 2014-15 3.50 Cost of solar unit/kWh 6.44
APPC rate after adding REC Cost in Rs./kwh
(100x3.53 +2 x 3.50)/100
= 3.60
New APPC rate in Rs./kwh
(98x3.53 + 2x6.44)/100
=3.59
Page 37 of 54
16.6.2 Sh. Gaurav Chauhan, Gurgaon:
PPAs @ Rs.4.34 are being done in Rajasthan and State Govt. is providing line.
Line charges are being borne by the State. Generators are much in number there. If
all PPAs are scrapped, then whole system will collapse. Land cost in Rajasthan and
MP is very less as compared to Haryana, so PPAs at lower rates are possible there.
16.6.3 Sh.Praveen Atrey,
PPAs at the rate of Rs.6.44 are much higher as compared to other States.
State is giving fixed charges amounting to Rs.2000 crores every year which is a
wastage of public money. All old PPAs be cancelled. Power Minister, GOI is ready to
given power at the rate of Rs.2.06 why Discoms are not purchasing the same from
GOI at such a lower rates and are doing PPAs at much higher rates. He further stated
that on the one hand it is being stated that power is surplus in the state and asked
‘where the surplus power is being utilized’. Public should not be burdened by creating
PPAs at higher rates. Interest of consumers should also be watched.
16.6.4 Mr. Subham, Advocate
PPAs have been signed in compliance with the directions issued by the Hon’ble
Commission. Clear mandate has been given by the Commission to sign the PPAs to
purchase solar power in accordance with Commission’s directions and the same have
been signed at very competitive on lowest discovered tariff. Reply of the Advocate to
the question of Hon’ble Chairman as to how the RPOs gap will be met, was that it will
be done according to the order (for which request has been made) to be issued by the
Commission. This is mandated from MNRE also. It is being done under RPO. The
RPO is going to be 8% in the coming years. One order dated 20.11.2013 has been
passed by the Commission vide which DISCOMs have been empowered to purchase
solar power on lowest tariff discovered based in the reverse tender bidding (one
paragraph of the same was read). Therefore, the Commission cannot flout its own
order.
16.6.5 Mr. Arvind, Jind:
In other States, PPAs are being executed @ Rs.4.35/unit whereas in Haryana it
is being done @ Rs.6.44/unit. Interests of only well-to-do (rich people) are being
watched and the poors are being ignored. Announcement of the Prime Minister is for
making electricity available to the consumers at the lowest tariff. As such, all old
MOUs should be cancelled forthwith. Although our land, water sources etc stand
diverted for the Thermal Plants but the same are lying closed or under-utilised, and we
are getting no benefit out of this. Under the circumstance, the tariff will go up even
from the present Rs.8.44/unit. All actions should be taken keeping the interests of
consumers in view. No new PPA should be approved.
Page 38 of 54
16.7 Reply of Sh. Nitin Yadav, MD, UHBVNL.
MD, UHBVNL, while replying to the objections raised by various stakeholders
during the public hearing submitted that though the Solar energy is costly, the
Discoms have to make efforts to meet the RPO obligations for the current year and
also the backlog since 2012. He submitted that though it is mandatory for owners of
houses of 500 Sq.yards and above to install Roof top solar power plants, but the
targets are not being achieved even after all efforts. He further pleaded that the rates
were negotiated in accordance with the State Procurement Policy and it will not be
possible to cancel the PPAs. Also, rates of solar energy are different in different areas
due to differences in topography and solar radiations e.g. Andhra Pradesh etc. near
sea, wind energy is cheaper, in HP & J&K hydro project energy is cheaper, in
Rajasthan there are more solar power and Wind power plants. Due to the RPO
obligation the Discoms cannot wait for the rates to fall unless the Commission agrees
for deferment of the RPO obligation. In order to explore the market, the tenders were
first floated for 50 MW with the ceiling rate being the Generic tariff determined by the
Commission and the Utility was able to negotiate a lower rate. Ultimately he prayed
that if the Commission rejects the PPAs entirely, RPO will not be met. He further
submitted that negotiations do take place in bidding and this was done to ensure the
best rate. In this way whatever lowest rate arrived, the electricity was purchased at
that rate. Against the tender for 50 MW, offer for only 23 MW was received.
Subsequently, another tender was floated in which rate of 5.09/unit was achieved
which came down to Rs.5.00/unit after negotiations. So it was a very competitive rate
as compared to other states.
Objections//comments of stakeholders number 15.b to 15.m were received
after the date of Public Hearing i.e. 10.08.2016.
Order of the Commission
17 The Commission has examined the petition filed by HPPC seeking ex-post
facto approval of the PPAs, Comments/objections of the stakeholders/general public,
as well as the replies/additional information filed by HPPC on the observations
conveyed to them.
Page 39 of 54
The Commission observes that vide the instant petition; the petitioner HPPC has
sought the following reliefs:
1. Adoption of Tariff discovered through transparent bidding process u/s 63 of
the Electricity Act, 2003.
2. Approval of PPA with solar power developers selected by it under the NIT
No. 51 at the said tariff.
18 For adoption of tariff u/s 63, the Commission is required to examine whether
the Tariff of Rs. 6.44 / Unit has been discovered by the petitioner in accordance with
provisions of section 63 of the Electricity Act, 2003.
The guidelines for competitive procurement have been framed under Section 63 of the
Electricity Act, 2003 which states as under:-
“Notwithstanding anything contained in Section 62, the Appropriate Commission shall
adopt the tariff if such tariff has been determined through transparent process of
bidding in accordance with the guidelines (emphasis added) issued by the Central
Government”.
HPPC has sought the approval of the Commission in view of MNRE Guidelines for
Tariff based Competitive Bidding Process for Grid Connected Powers Projects Based
on Renewable Energy Sources, December, 2012.
As per clause 3.1.1 & 3.1.2 of MNRE Guidelines for Grid Connected Powers Projects
Based on Renewable Energy Sources, December, 2012, the approval of the
Appropriate Commission is required in the event of any deviation from the bidding
conditions as approved by the Gol.
Clause 3.1.1 & 3.1.2 of the MNRE Guidelines are reproduced as under:-
3.1.1 The Standard Bid Documents (SBD) shall be prepared and issued by the
Central Government in accordance with these guidelines. The documents for inviting
bids shall be prepared in accordance with these guidelines and SBD. In such cases,
intimation shall be sent by the Procurer to the appropriate Regulatory Commission
about initiation of the bidding process. The approval of the appropriate Regulatory
Page 40 of 54
Commission shall be obtained unless the bid documents are as per the SBD issued
by the Central Govt.
3.1.2 Approval of the Appropriate Commission shall be sought in the event of the
deviations from the bidding conditions contained in these guidelines and SBD,
following the process described in Para 6.9 of these guidelines.
Clause 6.9 of these guidelines reproduced as under:-
6.9 In case there is any deviation from these guidelines, the same shall only be
with the prior approval of the Appropriate Commission. The Appropriate Commission
shall decide on the modifications to the bid documents within a reasonable time not
exceeding 90 days.
19 While the allocation for Solar Power Project in the present case has admittedly
been done through competitive bidding, the issue arises whether the competitive
bidding was carried out in line with the guidelines issued by the Central Government.
This issue is examined in light of the correspondence exchanged between the
petitioner and the Commission in the matter as given below:-
The petitioner, vide memo no. C43/HPPC/SE/ C&R- 1/PPA-136 dated 16.06.2014
informed the Commission that HPPC is in process of floating two number NITs for
purchase of 50 MW solar and 100 MW non solar power. The date for opening the
tender has been fixed as 31.07.2014 for solar and 14.08.2014 for non solar power.
Petitioner further informed the commission that although the NIT is based on the
standard RFP for procurement of power under “case -1/RE” bidding procedure
through tariff based competitive bidding process (as per the guidelines for Tariff based
competitive bidding process for grid connected power projects based on renewable
energy sources issued by the Government of India), however a few changes have
been done mainly affiliates have not been allowed, delivery point is at Haryana
periphery and tariff to be quoted and evaluated will be at delivery point, negotiation will
be done etc.etc. HPPC had requested that HERC may furnish its valuable comments,
if any on the NIT latest by 25.06.2014 so that HPPC may proceed further with tender
process.
20 The Commission examined the case and directed the petitioner to submit a
copy of the SBD and deviations made in NIT with respect to the SBD vide Memo no
1124 dated 25.6.2014. The information was provided by the petitioner vide diary entry
Page 41 of 54
no. 761 dated 4.7.2014. Subsequently, the Commission directed the petitioner to list
all deviations made in the NIT with respect to the Standard Bidding Document (SBD)
for procurement of Power under case 1-RE issued by the Govt. of India in a tabulated
form and also to provide the PPA attached with the SBD vide Memo no 1535 dated
28.7.2014. Subsequent to these developments, the petitioner, vide memo no.
C50/HPPC/SE/ C&R- 1/PSA/ SECI dated 05.08.2014 informed the Commission that
“in this regard it is submitted that major deviation in NIT from SBD in respect of
Bid Bond and Contract performance Guarantee is that of the amount per MW to
be paid. All the minor deviations will be rectified to have the NIT exactly the
same as that of SBD. All these deviations have been colour coded in the comparison
done in the tabular form. Also the Standard Bid Document does not contain any PPA”
21 Consequently, the Commission, vide memo no. 1725/ HERC/ Tariff/ NIT/ RE/
2014 dated 08.08.2014 informed the petitioner that “Kindly refer to memo no. Ch-
43/HPPC/SE/C&R-I/PPA-936 dated 16.06.2014 and Ch-46/HPPC/SE/C&R-I/PPA-67
dated 1.07.2014 vide which approval of the Commission was sought to the deviations
in the bid documents vis-à-vis the Case 1 RE Bidding Procedure of the Government of
India. The Commission has considered your application/petition and observes that the
NIT No. 51 & 52 for inviting competitive bids for purchase of 50 MW Solar Power and
100 MW of Non – Solar (renewable energy) were issued on 16.04.2014 and the
approval of the Commission to the deviations were sought on 1.07.2014 i.e. ex post
facto.
The Commission observes that the Discoms have not fulfilled their RPO including by
way of purchase of REC. Consequently, the accumulated shortfall allowed to be
carried forward from FY 2011-12 to FY 2013-14 (up to December 2013) is about
720.83 MUs amd the total RPO target set for FY 2014-15 is 1463.41 MUs. On several
occasions the Commission has observed that HPPC/HAREDA may invite bids/reverse
bids for purchase of renewable energy in order to meet with the RPO targets and the
fact that the bidding process is already under way, HPPC may proceed with the
same. Once the bids are opened HPPC shall analyze the same and submit the
details to the Commission for its order and approval of the PPA with the
successful bidders”.
Page 42 of 54
22 On examination of the above correspondence exchanged between the
Commission and the petitioner, it is observed that the petitioner submitted a set of
documents (proposed RFP) for perusal of the Commission and also sought approval
of the Commission to certain deviations to the NIT that was based on the standard
RFP for procurement of power under “case -1/RE” bidding procedure through tariff
based competitive bidding process (as per the guidelines for Tariff based competitive
bidding process for grid connected power projects based on renewable energy
sources issued by the Government of India).
23 On examination of the correspondence that has been reproduced at para 1 to
para 6 of the order, it is observed that the Commission has, at no place, approved the
deviations as has been claimed by the petitioner in its reply dated 28.04.2016. The
last communication of the Commission to the petitioner is vide memo no.
1725/HERC/Tariff/NIT/2014 dated 08.08.2014, wherein the Commission had allowed
HPPC to go ahead with the process as it was already underway. The Commission did
not grant approval to the deviations and also directed that once the bids are opened,
the HPPC shall analyze the same and submit the details to the Commission for its
orders and approval of the PPA with the successful bidders. The Commission
observes that this communication can in no way be interpreted as approval to
the deviations to the SBD submitted by the petitioner.
24 Even if for argument sake, the contention of the petitioner that the Memo no.
1725/HERC/Tariff/NIT/2014 dated 08.08.2014, conveyed HERC go ahead to the
process, it is imperative to note that before this communication was issued, the
petitioner, vide memo vide memo no. C50/HPPC/SE/ C&R- 1/PSA/ SECI dated
05.08.2014 informed the Commission that “in this regard it is submitted that major
deviation in NIT from SBD in respect of Bid Bond and Contract performance
Guarantee is that of the amount per MW to be paid. All the minor deviations will be
rectified to have the NIT exactly the same as that of SBD. All these deviations have
been color coded in the comparison done in the tabular form. Also the Standard Bid
Document does not contain any PPA”. A perusal of this communication conveys the
commitment by the petitioner to have the NIT exactly the same as that of SBD except
for the amount per MW to be paid for Bid Bond and Contract performance Guarantee.
Therefore, by no stretch of imagination can it be inferred that the Commission
Page 43 of 54
had granted its approval to any deviation except that related to the amount per
MW to be paid for Bid Bond and Contract performance Guarantee.
25 The Commission had, vide memo no. 1725/HERC/Tariff/NIT/2014 dated
08.08.2014, had expressly directed the petitioner that “once the bids are opened, the
HPPC shall analyze the same and submit the details to the Commission for its orders
and approval of the PPA with the successful bidders”. Whether the petitioner
complied with the orders of the Commission conveyed to it? The answer to it is
that it definitely did not.
26 The Commission had pointed out certain deviations in the bid documents and
asked the petitioner for its comments. The Petitioner assured the Commission that all
deviations except those related to Bid money and the Contract Performance
Guarantee money would be removed to make the bid documents same as SBD.
When the same commitment has, admittedly not been adhered to, it renders the so
called go ahead of the Commission conveyed vide memo no.
1725/HERC/Tariff/NIT/2014 dated 08.08.2014 null and void. Therefore it is held that
the deviations to the SBD do not have the prior approval of the Commission.
27 In “Babu Verghese & Ors vs Bar Council Of Kerala & Ors on 16 March,
1999”, the Hon’ble Supreme court has held that it is the basic principle of law long
settled that if the manner of doing a particular act is prescribed under any
Statute, the act must be done in that manner or not at all. The origin of this rule is
traceable to the decision in Taylor vs. Taylor (1875) 1 Ch.D 426 which was followed
by Lord Roche in Nazir Ahmad vs. King Emperor 63 Indian Appeals 372 AIR 1936 PC
253 who stated as under :
"Where a power is given to do a certain thing in a certain way, the thing must be done
in that way or not at all."
This rule has since been approved by this Court in Rao Shiv Bahadur Singh & Anr. vs.
State of Vindhya Pradesh 1954 SCR 1098 AIR 1954 SC 322 and again in Deep
Chand vs. State of Rajasthan 1962(1) SCR 662 AIR 1961 SC 1527. These cases
were considered by a Three-Judge Bench of this Court in State of Uttar Pradesh vs.
Page 44 of 54
Singhara Singh & Ors. AIR 1964 SC 358 (1964) 1 SCWR 57 and the rule laid down in
Nazir Ahmad's case (supra) was again upheld. This rule has since been applied to the
exercise of jurisdiction by courts and has also been recognised as a salutary principle
of administrative law. “
28 When it is mandated that deviations to the Standard Bid Documents and
Standard guidelines, if any, are to have prior approval of the Commission, it is not
open to the Commission to grant ex-post facto approval. The same interpretation of
this statute was taken by the Hon’ble Appellate tribunal for Electricity in Essar Power
Ltd. V Uttar Pradesh Electricity Regulatory Commission, 2012 ELR (APTEL) 182
wherein it was held as under:-
“The competitive bidding process adopted under the Act must, therefore, meet
the following statutory requirements: (a) Competitive bidding process under
Section 63 must be consistent with the Government of India guidelines. Any
deviation from the standard Request for Proposal (RFP) and model PPA notified
by the Government of India must be approved by the State Commission.
(b) This process must discover competitive tariff in accordance with market
conditions from the successful bid-consistent with the guiding principles under
section 61 of the Act.
(c) If the deviations are permitted by failing to safeguard the consumer interests as
well as to promote competition to ensure efficiency, it will destroy the basic
structure of the guidelines.” …………………
As indicated above, the bid process under Section 63 of the Act is entirely
different from normal procurement of goods through competitive bidding process
which is not governed by specific statutory scheme and guidelines. The bidding
process under Section 63 is wholly based upon the objective of section 61 of the
Act as well as the objectives of the Government of India guidelines. The
Government of India guidelines have been framed to comply with the principles
specified under Section 61 of the Act. The Government of India guidelines
contained the mandate to safeguard the consumer’s interest as well as to
encourage competition, efficiency and economical use of the resources. Let us
quote Section 63 of the Act for better understanding. “63. Determination of tariff by
bidding process.- Notwithstanding anything contained in section 62, the
Appropriate Commission shall adopt the tariff if such tariff has been determined
Page 45 of 54
through transparent process of bidding in accordance with the guidelines issued
by the Central Government.” 78. Thus the competitive bidding process as
contemplated under Section 63 of the Act must meet the following mandatory
statutory requirements:
(a) Competitive bidding process under Section 63 must be consistent with the
Government of India guidelines and Request for Proposal (RFP) including the
finalized PPA approved by the State Commission
(b) The process must discover competitive tariff in accordance with market
conditions from the successful bid – consistent with the guiding principles under
Section 61 of the Act as well as the Government of India guidelines which strike a
balance between the transparency, fairness, consumer interest and viability.
79. At the risk of repetition, it has to be stated that if these requirements have not
been followed and if the process has failed to safeguard the consumer interest as well
as to promote competition and efficiency by permitting the deviations, it would not only
destroy the basic structure of the guidelines but also would frustrate the objectives of
the Government guidelines.
Hon’ble Appellate Tribunal for Electricity in Appeal no. 70 of 2013 Dated 10th
February, 2015 In the matter of: Wardha Power Company Limited Versus.
Maharashtra Electricity Regulatory and others has held has below:-
“118. The State Commission is required to act consistent with the scheme and
objective of the Section 63 as well as other provisions of the Act, 2003. It is settled law
that when a statute vests power in the authority to be exercised in a particular manner,
then the said authority has to exercise it only in that manner provided in the Statue
and not otherwise. …………………. Under Section 63 there are only two options for
the State Commission:
(a) Either to reject the petition if it finds that the bidding was not as per the statutory
frame work;
Or
(b) To adopt the tariff if it is discovered through transparent process conducted as per
the bidding guidelines.
Page 46 of 54
29 It is also observed that, apart from the fact that the deviation(s) to the Standard Bid
Documents, the process by which the tariff of Rs. 6.44 per unit has been discovered, suffers
from certain other infirmities also.
As per clause 6.3 of the MNRE Guidelines it is mandated that the procurer shall constitute a
committee for evaluation of the bids (Evaluation Committee), Clause 7.3 provides for the said
Committee to provide a certificate on conformity of the bid process and evaluation as per the
guidelines. Admittedly, the Bid Evaluation Committee was not constituted by the procurer in
the present case as per the guidelines. The bid evaluation committee did not comprise of an
external expert, nor was any effort made to ensure that the rate discovered is in accordance
with the market conditions. The deficiencies in the bid process has also been in the
notice of the Commission and consequently, the Commission, at NP-26 of the file, on
20.1.2016, observed that the whole process followed by the HPPC appears to be in
violation of the Electricity Act, Rules and the guidelines issued by the Central
Government as well as the directions of the Commission and therefore, the
Commission decided that it would not be appropriate to approve the PPA.
30 The tariff discovered by the process by the petitioner is Rs. 6.44 per unit and
the petitioner has sought to justify that the said tariff was in line with the prevailing
market conditions. However, the petitioners have not submitted any document to the
Commission that can demonstrate the fact that an attempt was made by the petitioner
to examine whether the rate quoted by the bidders was in line with the prevailing
market conditions or not before the LOI was issued and the PPA’s were signed. The
petitioner was required to undertake this exercise as part of the Standard Bidding
Guidelines. As held by the Hon’ble Appellate Tribunal “The process must discover
competitive tariff in accordance with market conditions from the successful bid –
consistent with the guiding principles under Section 61 of the Act as well as the
Government of India guidelines which strike a balance between the transparency,
fairness, consumer interest and viability”.
Whether the rate was lower than the benchmark rate is not relevant to the comparison
of the rate with market conditions which is an activity mandated to be carried out
before grant of LOI. It is also observed that the documents submitted to the
Commission carried a benchmark rate of Rs. 5.70 and not Rs. 7.54 per unit.
31 The Commission observes that there are certain deviations that have a
substantive effect on the bidding process and the price discovery thereto. These are
as under :-
Page 47 of 54
a) Deviations relating to eligibility conditions.
b) Deviations relating to reductions in Bid guarantee amount and Contract
Performance Guarantee.
c) Introduction of Negotiation Process: Ministry of New & Renewable Energy
(MNRE), Government of India (GoI), had issued guidelines for tariff based
competitive bidding process for grid connected power projects and Clause 6.8
of MNRE guidelines states that “The Bidder, who has quoted lowest levellised
tariff as per evaluation procedure, shall be considered for the award. The
Evaluation Committee shall have the right to reject all price bids if the rates
quoted are not aligned to the prevailing market prices. “
d) Deviation relating to the constitution of Evaluation Committee: Clause 6.3 of
MNRE guidelines specified that “The Procurer shall constitute committee for
evaluation of the bids (Evaluation Committee) with at least one member
external to the Procurer’s organization and affiliates. The external member
shall have expertise in financial matters / bid evaluation. The Procurer shall
reveal past associations with the external member - directly or through its
affiliates - that could create potential conflict of interest. “
It is observed that widening the scope of participation of prospective bidders by
relaxing the eligibility conditions and by reducing the Bid guarantee and Contract
Performance Guarantee money may generally lead to better participation but it cannot
be said that the price so discovered would necessarily be on the lower side.
Commission has examined this deviation from the SBD and is of the considered view
that pegging qualifying net worth at a lower level may be counterproductive. In fact,
such dispensation may lead to a situation that a financially weak developer, on the
basis of aggressive bid submitted by them, is awarded the project but may fail to
execute the same or execute the same at a cost higher than assumptions made by
them while submitting his bid. Hence, given their lower net worth such developers
may not be able to absorb the cost slippages vis-à-vis that assumed by them. Further,
introducing a scope of negotiation would be counterproductive and introduce an
element of uncertainty in the whole process which may result in hardening of the offer
price.
32 The petitioner has also sought to introduce another dimension to the instant
petition by claiming that MNRE issued draft guidelines and SBD for purchase of
Page 48 of 54
renewable power through competitive bidding in Dec 2012 which were not notified as
such. The Commission observes that the petitioner, from the very first stage of the
case has considered the draft guidelines as a template and has sought the approval of
the Commission on the deviations from the said draft guidelines. Therefore, The
Commission holds, at this stage, it is not open to the petitioner to question the validity
of the guidelines.
33 In the surplus power supply scenario in the State, entering into long term PPA’s
just to comply with the RPO obligation on high cost, would have resulted in burdening
the consumers of the state with higher tariff and the same was protested by the
consumers. Therefore the Commission has also considered the views of the general
public who, ultimately, has to bear the financial burden on this account.
34 Accordingly, the Commission observes as under :-
i) The deviations from the Standard Bidding guidelines and Standard Bid
Documents do not have prior approval of the Commission.
ii) No explanation has been given by HPPC as to why the deviations other
than Bid Bond and Contract Performance Guarantee were not rectified
to have the NIT the same as SBD as communicated to the Commission.
iii) There is no assessment/certification by the Bid Evaluation Committee
that the rates quoted by the bidders being aligned to the market
conditions. To the contrary as per the news item published in “The
Times of India” dated 20.01.2016, the Solar tariff hits new low in
Rajasthan i.e. Rs. 4.34 to Rs. 4.63 paisa per unit. Though the price as
claimed by the petitioner is within the ceiling tariff of Rs. 7.45/ kWh fixed
by the Commission, it is almost 30% higher than the price recently
discovered by the petitioner itself as submitted by them in case No.
PRO-9 of 2016 at Rs.5.00/Kwh. Even the Petitioner has mentioned while
replying to the objection filed at para no. 15.1 of this Order that HPGCL
has offered 10 MW solar power at PTPS, Panipat @ Rs. 4.88/kwh
instead of Rs 4.18/kwh excluding the cost of transmission line and land
cost.
iv) The petitioner was already procuring solar power @ Rs. 5.50 per unit
under the JNNSM since June, 2015; the PSA with Solar Energy
Corporation of India (SECI) for this procurement was signed by the
petitioner in 22.8.2014, the date on which it floated the bids at the ceiling
Page 49 of 54
tariff of Rs. 7.54 per unit. Thus it is apparent that the negotiations have
not been conducted keeping in view the prevalent market rates. This has
led to a situation where the Discoms and the consumers have been
unfairly bound by the PPA’s at a higher rate.
v) The petitioner has been causing delays in submitting its filings to the
Commission. It is observed that after the Commission asked the
Petitioner to go ahead with opening the bids vide letter dated 8.8.2014;
the next filing by the petitioner was after one year i.e 16.7.2015.
Subsequently also, on numerous occasions, the responses have been
tardy, thus leading to delay in processing the case.
vi) The process mandated under the statute has not been adhered to by the
petitioner.
vii) In view of the above, there appears no justification for HPPC to enter
into PPA with the solar project developers at such a high tariff of
Rs. 6.44 per unit. In comparison with the recently discovered price, the
proposed PPA’s would lead to an additional financial burden on the
Electricity Consumers of Haryana. Taking into consideration of surplus
supply scenario in Haryana and falling Solar Electricity Rate, point raised
by some of the stakeholders regarding fulfilling RPO obligations from the
purchase of REC for next two years, till the time prices stabilizes. As per
the calculations provided by stakeholders, this could save an amount of
Rs. 3.34 crore for PPA @ 6.44/- and Rs. 1.1 crore for PPA @ 5/-.
viii) Inspite of existence of statute and regulations regarding procurement of
power, the petitioner signed PPA’s with developers on its own and
without approval of the Commission thereby putting the discoms in a
poor legal position and also tried to impress upon the Commission to
grant ex-post fact approval to the signed PPA’s.
ix) Various members of State Advisory Committee, individual consumers,
consumers association and industry association, during the recently
concluded public hearing on the ARR petition of the Distribution
licensees in the State of Haryana, and also during the public hearing
held in the case on 10.08.2016 objected to the fact that the Discoms are
on the one hand having surplus power and are disposing off the same at
a loss, while on the other hand, they are still signing long-term PPAs
Page 50 of 54
with the power producers. Hence, the stakeholders had suggested that
no new PPAs should be allowed to be signed at tariff not aligned to the
market and old stranded PPAs ought to be reviewed and cancelled so
that the burden of ‘fixed cost’ of such stranded PPA, on the Consumers
of Haryana, is reined in. The anguish expressed by the consumers
during the hearing is genuine and the same is supported by facts
appearing in the various ARR/Tariff Petitions filed in the Commission by
the Discoms. Hence, the objection of the stakeholders cannot be ignored
as doing so shall aggravate the financial distress of the Discoms and put
avoidable burden on the electricity consumers of Haryana.
x) Additionally, the process of negotiation does not appear to be
transparent. HPPC does not appear to have followed its own process as
mandated in Para 3.1.4 (IV) and violated all Act, Rules and Regulations
in this regard, rather negotiated in a clandestine and haphazard manner
with the developers.
xi) Thus the entire process followed by HPPC appears to be in violation of
the Electricity Act. Rules and the guidelines issued by the Central
Government as well as directions of the Commission.
35 The Commission, before arriving at any conclusion in the matter, thought it
appropriate to examine the situation on the ground and accordingly constituted a
committee of its officers to visit the sites of the four solar power developers with whom
the petitioner has signed the PPA. The said Committee submitted a report after
visiting the site on 06.05.2016 that JBM Solar Pvt. Ltd. has made significant progress
for implementation of 20 MW Solar Power Project allocated to them while M/s Balarch
has completed site fencing after acquiring land for the project on lease basis. It is
therefore clear that the said bidders have altered their financial position based on the
draft PPAs signed with the HPPC and would be in some degree of financial distress in
case the PPA’s are rejected by the Commission. Also, a large amount of funds would
have been raised through borrowings from the banks/and financial institutions and
disallowing the PPA would only add to the NPAs of the banks/financial institutions.
36 In view of the above discussions the Commission has examined the entire
issue threadbare as under:-
Page 51 of 54
The functions of State Commission is provided in section 86 of the Electricity
Act, 2003 which includes “regulate electricity purchase and procurement process of
the distribution licensees including the price at which electricity shall be procured from
the generating companies..”. Further, section 86(3) of the said Act provides as under:-
(3) In discharge of its functions, the State Commission shall ensure
transparency while exercising its powers and discharging its functions”.
In line with the above mandate, the Commission considered it appropriate to
hold public hearing in the matter. The Commission considered widespread
resentment expressed by the public regarding high cost PPAs being entered into by
HPPC thereby putting additional financial burden on them while others emphasized
the need for procuring environmentally benign power for the Discoms to meet their
RPO.
The Commission, after hearing the parties and perusing the statutes occupying
the field is of the considered view that the powers of the Commission while dealing
petition(s) under section 63 is in a very narrow confine i.e. the Commission can
either adopt the tariff if the same was discovered by a transparent process of
bidding conducted as per the Government of India Guidelines or reject the
petition if the bidding was not found to be as per the statutory
framework/Guidelines.
In the present case there is some confusion created regarding existence of
Standard Bidding Document (SBD). HPPC, in response to the queries of the
Commission did submit SBD and the deviations made by them. However, at a later
stage the said SBD turned out to be a draft which was never finalized and notified by
the MNRE. As far as this Commission is concerned the SBD submitted by HPPC has
been considered as the benchmark. Besides the SBD what does exist is the MNRE
Guidelines for procurement of RE power by competitive bidding.
It is well established that the objective of the competitive bidding is to protect
and balance the interest of all the parties concerned i.e. the distribution licensees, the
bidders and the consumer. In other words, the entire competitive bidding process is
not only to discover the tariff but also to discover the supplier who would be able to
supply the required quantum of power to the procurer in timely manner.
Page 52 of 54
In the present case, the NIT in question admittedly incorporated quite a few
clauses which impinged upon the very objectives of inviting competitive bidding for
procurement of Solar Power on a long term basis. Further, the statutory requirement
of recommendations of the ‘Evaluation Committee’ on the reasonableness of the tariff
so discovered was never fulfilled. The significance of the recommendations of the
evaluation committee ought not to be diluted. As given the limited number of private
players in the market, the tariff discovered through competitive bidding may not
always be aligned to the market. Thus, the Commission, in the present case, did not
have the benefit of the mandatory report of the evaluation committee.
The Commission is also constrained to take a somewhat liberal view given the
predicament of the petitioner and the bidders in view of the provisions in the National
and Haryana State Policy for Promotion of Solar Power.
As per the Ministry of New & Renewable Energy (MNRE), Government of India
(GoI), Haryana has Solar Potential of 4.56 GWp. As against the said potential as on
March, 2016 only 12 MW has been commissioned in Haryana and another 200 MW
has been allotted under the State Solar Policy. Further, at 3% Solar RPO by the year
2022 about 1300 MW Solar Power is required and if the RPO is scaled up to 8% in
line with the National Tariff Policy, 2016 the Solar Power requirement shall be about
3200 MW including the target of 1600 MW Rooftop capacity. It is therefore evident
that the Solar Power Capacity addition has to be stepped up in the State.
Further, the vision / mission of the Haryana Solar Policy, 2016 is as under:-
A Vision for Power – the Mission therein In an environment where the demand for energy and power is growing rapidly the state seeks to build on renewable energy and be a part of the drive that is taking a firm shape in the entire country. The state is blessed with high solar radiation levels with more than 300days of clear sunlight and seeks to harness the untapped and inexhaustible solar energy potential in the state. The state therefore seeks to: Promote generation of green and clean power Create conditions that would be conducive to the participation of the private as well as public sector in the setting up of solar energy projects in the country. To encourage and promote a feasible Investment environment for the same.
Page 53 of 54
Spread environmental consciousness among all citizens of the state. Aim for a decentralized and diversified management of the energy sector. To work consistently towards an increase of the share of the renewable solar power. To attain its target of Soar Renewable Purchase Obligation (Solar RPO) which is just 0.25% at present and would be scaled up to at least 8% by 2021-22. To ultimately create a technology driven state with the right ‘energy mix’
Given the position discussed above and the fact that this Commission, on
many occasions, has emphasized the need for procurement of RE Power by the
Discoms as well as taken serious note of shortfall in both Solar as well as Non-Solar
RPO. Hence, to balance the equity on both sides the Commission Orders as under:-
i) In order to restore HPPC and the successful bidders to their initial status,
HPPC shall restore the bank guarantee, if not already done, as well as CPG amount
without any other cost i.e. interest etc.
ii) However, in the case of the successful bidders who have already commissioned
their plants or are nearing completion (more than 80% complete) under the PPA
executed by HPPC, and are willing, may explore the possibilities for arriving at an
equitable and reasonable solution to arrive at a tariff aligned to the prevailing market
conditions subject to the ceiling of the project cost determined by CERC for the FY
2016-17 in accordance with the 6.4 (3) of the National Tariff Policy, 2016 and HERC
RE Regulations in vogue as the projects are likely to be commissioned during FY
2016-17 only. In such an event HPPC, shall submit the outcome arrived at for
the consideration and Order of the Commission, before 30th September, 2016.
iii) In case of successful bidder(s), other than those covered in point no. ii above,
the PPAs are not approved. HPPC, if required, may invite fresh bids after
following the due process prescribed for the purpose and these bidders may be
given preference in the next round of fresh bids to be called by the Power
Utilities in the State. The developer shall be allowed to supply the quantity of
power for which the PPA has already been signed and at the rate allowed to the
successful bidder in that round of procurement of Solar power.
Page 54 of 54
This order is signed, dated and issued by the Haryana Electricity Regulatory
Commission on 12.09.2016.
Date: 12.09.2016 (M. S. Puri) (Jagjeet Singh)
Place: Panchkula Member Chairman
The Order dated 12.09.2016 in case no. HERC/PRO-6 of 2016 has been signed
by Shri Jagjeet Singh, Hon’ble Chairman, HERC (hereinafter referred to as “the Order”
I express my difference of opinion as per my Dissenting Note attached and approve
the draft PPAs submitted by the Petitioner with four Solar Power Project
Developers selected through competitive bidding.
Date: 4th October, 2016 (M. S. Puri) Place: Panchkula Member
ORDER
In terms of Section 92(3) of the Electricity Act, 2003, I exercise the second / casting
vote vested in me, accordingly the Order of the Chairman shall be the Order of the
Commission.
However, in view of the change in the date of issue of the Order, the date mentioned
at para 36 ii) at page 53 shall read as 20th October, 2016 in place of 30th September,
2016
This order is signed, dated and issued by the Haryana Electricity Regulatory
Commission on 04.10.2016
Date : 04.10.2016 (M. S. Puri) (Jagjeet Singh)
Place: Panchkula Member Chairman
1 | P a g e
Dissenting Order in Case No: HERC/PRO-6 of 2016 in the matter of
Petition/application filed by the Haryana Power Purchase Centre (HPPC) for
approval of draft Power Purchase Agreements (PPAs) with four Solar Power
Developers selected through tender NIT No. 51.
The Order dated 12.09.2016 in case no. HERC/PRO-6 of 2016 has been signed
by Shri Jagjeet Singh, Hon’ble Chairman, HERC (hereinafter referred to as “the Order”,
I express my difference of opinion as under:-
1. Para 1 to 12 of the Order
The aforesaid paragraphs provide the background of the case and the
submissions made by the Petitioner, However the complete submission made by the
petitioner in its affidavit dated 09.03.2016 is reproduced below:-
1. The Petitioner, Haryana Power Purchase Centre (hereinafter
referred to as ‘HPPC’) represents the two State Distribution Licensees,
namely, Uttar Haryana Bijli Vitran Nigam Limited and Dakshin Haryana
Bijli Vitran Nigam Limited (hereinafter collectively referred to as
‘Haryana Utilities’) in the purchase of power from Generating
Companies including renewable and non-conventional sources. The
electricity so contracted and/or procured is primarily for maintenance of
electricity supply to the consumers at large in the State of Haryana.
2. HPPC has been undertaking the above power procurement as per
the decision taken on the basis of power requirements and projections to
meet the demands of the consumers in the State of Haryana. The
Haryana Utilities have been placing before the Hon’ble Commission, the
quantum of power contracted/procured in the tariff proceedings.
3. Section 86 (1)(e) of the Electricity Act, 2003 inter-alia, provides for
the function of the State Commission as under:
2 | P a g e
“promote cogeneration and generation of electricity from
renewable sources of energy by providing suitable measures for
connectivity with the grid and sale of electricity to any person,
and also specify, for purchase of electricity from such sources, a
percentage of the total consumption of electricity in the area of a
distribution licensee”
4. In the Tariff Orders passed by the Hon’ble Commission from time
to time, the Haryana Utilities have been mandated to purchase power to
meet the Renewable Purchase Obligation. In this regard, the Hon’ble
Commission has notified HERC (Terms and Conditions for determination
of tariff for Renewable Energy Sources, Renewable Purchase Obligation
and Renewable Energy Certificate) Regulation, 2010. The Petitioner
would crave leave to refer to the said Regulation at the time of the
hearing.
5. In accordance with the above and in order to fulfill the Renewable
Purchase Obligation in regard to purchase of power from Solar sources,
the Petitioner initiated competitive bidding process as per the Guidelines
for Tariff Based Competitive Bidding Process for Grid-connected Power
Projects based on Renewable Energy Sources issued by the Government
of India. The Standard Request for Proposal for procurement of power
from Renewable Energy Sources notified by the Government of India
under Section 63 of the Electricity Act, 2003 was adopted for the above
purpose.
6. The Notice inviting tender with the above Standard Documents on
22th April, 2014.
3 | P a g e
7. The Petitioner states that at the relevant time, the Hon’ble
Commission had already held hearing on the Petition filed by the Haryana
Utilities in regard to Aggregate Revenue Requirements for the
Distribution and Retail Supply Business under Multi Year Tariff Framework
for the Control Period i.e. Financial Year (FY) 2014-15 to FY 2016-17 and
for the approval of Distribution and Retail Supply tariff for the period FY
2014-15. On 29.05.2014, the Hon’ble Commission decided the Petition
mentioned hereinabove and determined the aggregate revenue
requirement and tariff as mentioned hereinabove. On the aspects of the
procurement of power from the Renewable Energy sources, the Hon’ble
Commission in the said order held as under:
“Renewable Purchase Obligation (RPO)
Section 86 (1) (e) of the Electricity Act, 2003 mandates the
Commission to promote cogeneration and generation of electricity
from renewable sources of energy by providing suitable measures
for connectivity with the grid and sale of electricity to any person,
and also specify, a percentage of the total consumption of
electricity in the area of distribution licensee, for mandatory
purchase of electricity from such sources. In accordance with the
Regulation 64 of HERC (Terms and Conditions for determination of
Tariff for Renewable Energy Sources, Renewable Purchase
Obligation and Renewable energy Certificate) Regulations, 2010
the RPO for FYs 2011-12, 2012-13 and 2013-14 as approved by the
Commission are as under:
Renewable Purchase Obligation for 2011-12, 2012-13 and 2013-
14
4 | P a g e
* Solar power purchase obligation is 0.05% & 0.1% of total energy consumption for the financial years 2012-13 & 2013&14 respectively. As per data provided by the State Nodal Agency for FY 2011-12, FY 2012-13 and FY 2013-14 (up to Dec. 2013), the shortfall in meeting the RPO for the aforesaid years has been worked out as under:
Shortfall in meeting RPO (MUs)
The Commission observes that the Discoms have failed to achieve the RPO target set by the Commission. The Discoms have also not purchased any Renewable Energy Certificates (REC) to fulfil their RPO. The Commission vide its order dated 20.11.2013 in case no. HERC/RA-04 of 2012, HERC/RA-08 of 2012, HERC/RA-11 of 2013 &
5 | P a g e
HERC/PRO-30 of 2013 allowed the Discoms to carry forward the shortfall, on actual basis, the RPO compliance for FY 2011-12, FY 2012-13 and FY 2013-14 to the next financial year i.e. FY 2014-15 in addition to the RPO for FY 2014-15. The Discoms are directed to submit an action plan as per the Regulation in vogue to meet their RPO shortfall for the previous years and the current year. Theaction plan shall be submitted by the Discoms within a month from the date of this order.
In accordance with the provisions of the draft amended regulations the RPO for the FY 2014-15 is 3.25% of the total energy consumption. The approved RPO for FY 2014-15 is as under:
Renewable Purchase Obligation for FY 2014-15
The volume of energy to be purchased from renewable energy sources as per above table is the total RPO of the distribution licensee for the financial year 2014-15. Therefore, the volume of renewable energy purchase as approved by the Commission as above shall be adjusted against the total RPO of the distribution licensees. Further, RPO of 1163.41 MUs shall be part of total power purchase volume approved by the Commission for FY 2014-15 and set off against the costliest power in the merit order.
The Commission directs the Discoms to purchase renewable energy as per RPO targets set for FY 2014-15 and the shortfall carried forward, on actual basis, for previous years. In case they can purchase the same at a tariff lower than determined by this Commission they may do so, otherwise they must purchase all such power offered to them by the renewable energy power producers at the tariff determined by this Commission. The shortfall in meeting the RPO for the FYs 2011-
6 | P a g e
12, 2012-13 and 2013-14 as per details given above shall also be met in the FY 2014-15 in addition to the RPO of FY 2014-15. The Commission has taken a serious note of non-compliance of RPO targets including non purchase of REC to meet RPO. In case no action is taken by the Discoms, the officer concerned shall be held liable for non-compliance and proceeded against u/s Section 142 of the Act.”
Re: Approval of the Hon’ble Commission
8. On 16.06.2014, the Petitioner sent the communication to the
Hon’ble Commission intimating as under:
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar
power to meet RPO – approval thereof
It is intimated that HPPC is in the process of floating Two no. NITs
for purchase of 50 MW solar & 100 MW non-solar power. The date
of opening of tenders has been fixed as 31.7.2014 for solar &
14.8.2014 for non- solar power.
Although NIT is based on the Standard RFP for procurement of
power under “Case 1 -RE” Bidding procedure through Tariff based
Competitive Bidding Process (As per Guidelines for tariff Based
Competitive Bidding Process for Grid Connected Power Projects
Based on Renewable Energy Sources” issued by the Govt. of India),
however a few changes have been done mainly affiliates have not
been allowed, Delivery point is Haryana periphery and tariff to be
quoted and evaluated will be at Delivery point, negotiation will
be done etc.
It is requested that HERC may furnish its valuable comments, if
any, on the NIT latest by 25.6.2014 so that HPPC may proceed
further with tender process.”
7 | P a g e
9. In the communication-dated 16.06.2014, the Petitioner has also
placed on record that negotiations etc. will be done. This was in the
context that negotiations will be required to be done for reducing the
price as far as possible from the ceiling cost, in the larger interest of the
consumers.
10. By communication-dated 25.06.2014, the Hon’ble Commission was
pleased to hold as under:
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar
power to meet RPO.
This is with reference to your office memo no. Ch-
43/HPPC/SE/C&R-I/PPA-136 dated 16.06.2014 vide which copy
NITs for purchase of 50 MW solar & 100 MW non-solar power have
been forwarded for comments.
Before the case is further processed, it is requested to
clarify/intimate the following:
1. A copy of the Standard Bidding Documents for procurement of power under “Case 1-RE” Bidding procedure through Tariff based Competitive Bidding Process for Grid Connected Power Projects Based on Renewable Energy Sources issued by the Government of India be provided.
2. The deviations made in the NIT with respect to the Standard Bidding Document for procurement of power under “Case 1-RE” issued by the Government of India be tabulated.
3. The copy of the statute, under which the deviations sought by HPPC from the Standard Bidding Documents issued by the Government of India requires the approval of the Commission, may also be provided. The above clarification/information be provided within a week
from the date of issue of this letter.”
8 | P a g e
11. Thereafter, by communication-dated 01.07.2014, the Petitioner
furnished the deviations from the Standard Document as per the
direction of the Hon’ble Commission with a covering letter as under:
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar
power to meet RPO- approval thereof
This is with reference to your Memo. No. 1124/HERC/PPA/NIT-
RE/Tariff dated 25.6.2014 on the subject.
In this regard.
1. Standard Request for Proposal for Procurement of Power Under case1 – RE” Bidding Procedure through tariff Based Competitive Bidding Process (As per Guidelines for tariff Based Competitive Bidding Process for Grid Connected Power Projects based on Renewable Energy Sources”) is enclosed. (Annexure A)
2. Deviations made in the NIT w.r.t the SBD for procurement of power under “Case1- re” in tabulated form is enclosed. (Annexure B)
3. It is submitted that approval of Honorable Commission on the Two Nos. subject cited NITs is required in view of the Clause 3.1.2 of MNRE “Guidelines for Tariff based
Competitive Bidding Process for Grid Connected Power Projects
Based on Renewable Energy Sources- December 2012”
(Annexure C) which states that
“Approval of the Appropriate Commission shall be sought in the
event of the deviations from the bidding conditions contained
in these guidelines and SBD, following the process described in
para 6.9 of these guidelines.”
It is humbly requested that approval may please be granted on
the NITs for purchase of 50 MW solar and 100 MW non-solar
power.”
12. In response to the above, the Hon’ble Commission by
communication-dated 28.07.2014 wrote as under:
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar
power to meet RPO.
9 | P a g e
This is with reference to your office memo no. Ch-
46/HPPC/SE/C&R-//PPA- dated 25.06.2014.
The Commission has observed that there are many other
deviations particularly to Bid Bond, CPG, Payment Security etc.
The Standard Bid Document may heave PPA also.
You are requested to submit all deviations made in the NIT with
respect to the Standard Bidding Document (SBD) for
procurement of power under “Case 1- RE” issued by the
Government of India in tabulated form and also the PPA
attached with the SBD within a week from the date of issue of
this letter.”
13. On 05.08.2014, the Petitioner submitted as under:
“Subject: NIT for purchase of 50 MW solar & 100 MW non-solar
power to meet RPO
This is with reference to your memo No. 1535/HERC/PPA/NIT-
RE/Tariff dated 28.7.2014 on the subject.
In this regard, it is submitted that major deviation in NIT from
SBD in respect of Bid Bond & Contract Performance Guarantee is
that of the amount per MW to be paid. All the minor deviations
will be rectified to have the NIT exactly the same as that of SBD.
All these deviations have been color coded in the comparison done
in the tabular form. (Annexure A)
Also, Standard Bid Document does not contain any PPA.
It is humbly submitted that the date of opening of tenders is
22.8.2014 for solar power and 29.8.2014 for non-solar power.
Submitted for the kind consideration of the Commission please.”
Alongwith the above letter, the list of deviation was also given.
10 | P a g e
14. On 08.08.2014, the Hon’ble Commission was pleased to allow the
Petitioner to proceed with the Competitive Bidding Process. The letter-
dated 08.08.2014, reads as under:
“Subject: NIT for Purchase of 50 MW solar & 100 MW non-solar
power to meet RPO – approval thereof.
kindly refer to your memo no Ch-43/HPPC/SE/C&R -I/PPA – 136
dated 16.06.2014 and Ch-46/HPPC/SE/C&R-I/PPA-67 dated
1.07.2014 vide which approval of the Commission was sought to be
deviations in the bid documents vis-à-vis the Case – 1 RE Bidding
Procedure of the Government of India. The Commission has
considered your application/petition and observes that the NIT No.
51 & 52 for inviting competitive bids purchase of 50 MW for Solar
Power and 100 MW of Non- Solar (renewable energy) were issued on
16.04.2014 and the approval of the Commission to the deviations
were sought on 1.07.2014 i.e. ex post facto.
The Commission observes that the Discoms have not fulfilled their
RPO including by way of purchase of REC. Consequently, the
accumulated shortfall allowed to be carried forward from FY 2011-
12 up to FY 2013-14 (up to December 2013) is about 720.83 Mus and
the total RPO target set for FY 2014-15 is 1463.41 Mus. On several
occasions the Commission has observed that HPPC/HAREDA may
invite bids/ reverse bids for purchase of renewable energy in order
to meet with the RPO targets and the fact that the bidding process
is already under way, HPPC may proceed with the same. Once the
bids are opened HPPC shall analyze the same and submit the details
to the Commission for its order and approval of the PPA with the
successful bidders.
This issues with the approval of the Commission.”
15. In the circumstances mentioned above, the Competitive bid
process was with the approval of the Hon’ble Commission, namely that
the bid submission date was 22.10.2014 namely, after the letter dated
11 | P a g e
08.08.2014 from the Hon’ble Commission permitting the Petitioner to
proceed with the process.
16. It is respectfully submitted that the relevant date with reference
to which the Hon’ble Commission approval is necessary is the bid
submission date. The issue of Request for Proposal to the interested
parties is a preliminary step in the Competitive Bidding Process. The
Request for Proposal containing the Standard Bid Documents with
deviation was not proceeded with for submission of the bid by the
interested participants till 08.08.2014. The deviations as per the
communication sent by the Petitioner to the Hon’ble Commission till
08.08.2014 were duly incorporated in the bid documents and the
submission of the bid by the participating bidders was on the bid
documents with such deviation.
17. In view of the above, it is respectfully submitted that the
Petitioner had taken the approval of the Hon’ble Commission to proceed
with the Competitive Bidding Process for inviting the bids on 22.10.2014,
such approval having been granted vide communication-dated
08.08.2014. As mentioned above, the bids were submitted on 22.10.2014
and was opened on 22.10.2014.
18. In view of the above, there is no violation on the part of the
Petitioner in regard to taking approval of the Hon’ble Commission on the
bid documents.
12 | P a g e
19. Without prejudice to the above, it is also pertinent to mention that
the Hon’ble Commission had already notified the quantum of renewable
purchase obligation for procurement of solar power. The Petitioner was
adopting the Standard Bid documents notified by the Government of
India. The Petitioner had to obtain the views of the participating bidders
in a Pre-bid Conference before finalizing the bid documents. Such pre-
bid conference was held on 05.05.2014. The Petitioner was required to
take an informed decision on the deviations or changes to be made as per
the suggestion of the participating bidders only after such pre-bid
conference. The Petitioner had approached the Hon’ble Commission
immediately thereafter on 16.06.2014.
20. In view of the above, it is respectfully submitted that there was
neither a requirement nor it was practicable for the Petitioner to
approach the Hon’ble Commission in April, 2014 i.e. at the time of issue
of Notice of inviting tender.
Re: NEGOTIATIONS:
21. The Petitioner submits that the negotiation with the bidders, in
the present case did not vitiate the bidding process in any manner and it
rather, added value to the Haryana Utilities and the consumer at large.
At the outset, it may be stated that the Petitioner or any other agency
involved did not undertake negotiation with the bidders in a manner to
ignore a bidder who had given a better price. The lowest bidder, namely,
L1 had quoted a tariff of Rs. 6.44/kwh. In the bidding documents, the
13 | P a g e
Petitioner had already disclosed the criteria for evaluation of the bid.
These particularly included the following:
“3.1.4 STEP IV – Successful Bidder(s) Selection
Bids qualifying in Step III shall only be evaluated in this stage
I. The Bidder with the lowest levalized Tariff for 25 years in
its Financial Bid shall be considered as L-I.
II. The price discovered for per unit rate of solar power shall
generally determined based on the rates quoted by the L-1
bidder and the negotiation, if any, held with the lowest
bidder. However, the negotiations could be held with
remaining eligible bidders. In case, the L-1 bidder refuses to
further reduce his offered price and the remaining bidders
come forward to offer a price better than the price offered
by L-1 bidder, then the bidder offering the lowest rate
would become the L-1 bidder. However, in such a situation,
the original L-1 bidder shall be given one more opportunity
to match the discovered price.
III. On determination of the price discovery pursuant to the
above price, a counter offer would be made to all such
eligible bidders, for acceptance of the discovered price.
IV. Form the outcome of the above process, the bidders from
anywhere in India, agreeing to accept the counter-offer of
the discovered price, will be considered and selection will
be done on the following criteria.
i) Solar power Projects in the State of Haryana will be
given first priority.
ii) Thereafter, the bidder offering the maximum capacity
will be given priority.
V. At any step during the selection of Successful Bidder(s) in
accordance with Clauses I to IV above, the HPPC reserves the
right to increase / decrease the Requisitioned Capacity by
14 | P a g e
up to ten percent (10%) of the quantum indicated in Clause
2.1.
VI. The Letter(s) of Intent shall be issued to all such Successful
Bidder(s) selected as per the provisions of this Clause 3.1.4.
VII. Each successful Bidder shall unconditionally accept the LoI,
and record on one (1) copy of the LoI, “Accepted
Unconditionally”, under the signature of the authorized
signatory within seven (7) days of issue of LoI.
VIII. If the Successful bidder, to whom the LoI has been issued,
does not fulfil any of the conditions specified in the Clauses
2.9 & 2.12, HPPC reserves the right to annul the award of
the letter of Intent of such successful bidder.
IX. HPPC, in its own discretion, has the right to reject all Bids if
the Single Quoted Tariff is not aligned to the prevailing
market prices.”
In the negotiation, the above criteria was only adopted. There were no
new or additional criteria introduced.
22. The Petitioner respectfully submits that the scheme adopted after
opening of the bid cannot even be termed as negotiation in the sense it is
understood as vitiating the bidding process. Keeping the criteria
prescribed in the bidding document as quoted hereinabove; the Petitioner
had proceeded to call upon all the bidders to match the L1 bid. This was
to reduce the impact of tariff to the consumer at large and at the same
time to fulfill the RPO obligation notified by the Hon’ble Commission. All
the bidders were fully aware of the technical and financial criteria
including the condition that preference would be given to projects within
the State of Haryana and for long-term contracts. The five selected
15 | P a g e
bidders with an aggregate capacity of 25 MWs were only those who
matched the bidding criteria and also the L1 quoted price of Rs. 6.44 per
unit.
23. Although five bidders were selected by HPPC for 25MW capacity
initially, PPAs were signed for only 23 MW capacity with four bidders as
one bidder did not fulfill the terms and conditions of bid document
issued by the Petitioner.
24. The Petitioner respectfully submits that the scheme to reduce the
quoted price of others to the lowest quoted price of Rs. 6.44/unit
achieves the object of the Electricity Act, namely, both the promotion of
renewable sources of energy and also reduction in the cost to the
consumers at large and therefore, consistent with the provisions of the
Electricity Act, 2003.
25. It is also reiterated that in the communication dated 16.6.2014,
the Petitioner had placed on record about the negotiation; consistent
with the policy of the Government of Haryana as contained in the
Government order dated 16.6.2014. A copy of the said order dated
16.6.2014 is attached hereto as Annexure A.
Re: EVALUATION COMMITTEE
26. The Petitioner submits that there has been no violation of the
bidding documents in regard to the non-constitution of evaluation
Committee as per the Guidelines issued by the Ministry of Non-
16 | P a g e
Conventional Energy Sources. The bidding submission date was after the
Hon’ble commission has decided the ceiling tariff for Solar power
projects at Rs 7.45/kwh in the Order dated 13.8.2014. A copy of the
Order dated 13.8.2014 is attached hereto.(Annexure-B) Similarly, in the
Order dated 15.5.2014, the Central Commission has also determined the
tariff for Solar power projects at Rs 7.72/kwh.(Annexure-C) The above
decision of the Hon’ble Commission dated 13.8.2014 was required before
the bid submissions. The bid submissions date was in fact deferred from
time to time till 22.10.2014.
27. The Petitioner submits that the fixation of the above tariff at Rs
7.45/kwh by the Hon’ble Commission and Rs 7.72/kwh by the Central
Commission provided the price aligned to the market conditions. The
Hon’ble Commission and the Central Commission had determined the
above tariff after considering all the relevant facts and taking into
account the price which could be the appropriate one, i.e. the ceiling
price. In fact, inviting competitive bids in the light of the above tariff
determined necessarily means that bidders were to bid keeping the tariff
already decided i.e. in a competitive environment to quote lower to the
extent they decide.
28. It is also relevant that the solar projects do not have to be
compared with other sources of energy to decide on the quoted price
being aligned to market prices. The commission would be relevant if
power could be procured from different sources. In terms of the RPO
obligation, the power was to be procured only from solar energy sources.
Further, based on the market prices prevalent, the Hon’ble Commission
had decided on Rs 7.45… /unit as the ceiling price.
17 | P a g e
29. In the circumstances, the issue of an evaluation Committee
deciding on the prices being aligned to the market forces, will have no
application. Further, the above requirement is in the Guidelines and does
not form part of the Bidding documents, as approved by the Hon’ble
Commission.
30. After the opening of the Bid on 25.10.2015, the following steps
were taken
a) The technical and commercial bids (excluding the price bid-
financial) received from 10 participating bidders were first opened
on 22.10.2014 and was then evaluated by a Committee consisting
of Chief Engineer HPPC, Financial Advisor and Superintending
Engineer, HPPC. 8 out of 10 participating bidders were found to be
responsive.
b) The price bid of the 8 bidders was then opened on 22.12.2014. The
price bids were in the range of Rs. 6.50 to 7.45/kwh.
c) The Steering Committee for Power Planning constituted for
evaluating the purchase of power consisting of Additional Chief
Secretary, Power and Managing Directors of Electricity Utilities
(GENCO, TRANSCO AND TWO DISCOMS), CE/HPPC considered the
price bids and decided on the course of action to be taken in
accordance to the tender terms and conditions.
18 | P a g e
31. Further, the Hon’ble Commission has in another case also approved
the PPA executed by the Petitioner with another developer, M/s. Siwana
Solar Power Ltd., for 5MW vide letter dated 21.02.2014.(Annexure-D)
The aforesaid solar power developer is being paid tariff at the rate of
Rs.6.44/Kwh as per clause 2.1.41 of the said PPA. In terms of the above
clause, duly approved by the Hon’ble Commission, the developer was to
be paid the lowest tariff out of (a) the Generic Tariff Orders passed by
the Hon’ble Commission and (b) the lowest tariff quoted and accepted in
the first long terms tender for purchase of solar power by HPPC or
HAREDA till 31.12.2015.
32. The present tariff of Rs.6.44/Kwh discovered through the instant
competitive bidding process carried out by HPPC was the lowest tariff.
The Hon’ble Commission vide order dated 20.01.2016 in Case No.
HERC/PRO-24 of 2015 has also upheld the payment of tariff at
Rs.6.44/Kwh being paid to the aforesaid solar power developer M/s.
Siwana Solar Power Ltd. ( Annexure-E)
33. In the above process and in order to minimize the impact to
consumer at large, as mentioned hereinabove, the L1 bidder was called
upon to reduce the price and the L1 bidder accordingly reduced the price
to Rs. 6.44/kwh. Thereupon, all the other bidders were called upon to
match the lowest price of the L1 bidder.
34. The bidders who did not agree to match the L1 reduced price were
not selected. The Petitioner is filing also herewith a statement of prices
at which the solar power had been procured in other States during the
19 | P a g e
relevant time (i.e. before the finalization of selected bidders by the
Petitioner. The statement is marked as Annexure F.
35. A perusal of same would show the price at which the Petitioner
had finalised 23 MW was most reasonable as compared to the others.
36. As mentioned hereinabove, the selection was done strictly with
Clause 3.1.4 of the tender documents.
37. In view of the above, it is respectfully submitted that the Hon’ble
Commission may be pleased to-
a) Approve the Power purchase Agreements entered into between the
Haryana Utilities and the four selected bidders; and
b) Pass such further order or order(s) as may be deemed necessary
and fit in the circumstances of the case.
2. Para 13 to 16 of the Order
The public hearing on the ARR held on 1.03.2016 and 30th May, 2016 including
the discussions in the State Advisory Committee meeting referred to in the order, has
not been presented in an objective manner.
During the public hearings referred to above, Interveners had raised concern on
the high fixed cost being paid by the Disoms due to stranded PPAs. The same issue
was also raised in the last meeting of the State Advisory Committee. The issue of
Standard PPAs pertains to conventional power and has nothing to do with Obligation to
purchase Renewable Power. Therefore, to put the entire matter in a proper
perspective, it is to be noted that procurement of RE power is a Statutory Obligation and
that no RE Power PPAs are stranded and as against the conventional power PPAs
20 | P a g e
there is no obligation on the Discoms to pay fixed cost. What is being paid by
HPPC/Discoms is the tariff for actual RE power generated and injected by the RE
Generators in the Haryana Grid. Additionally, what has been attributed to the
Government of Haryana making it mandatory to hold public hearing while formulating
public policies is also entirely out of context. The Haryana Government, in exercise of
the powers conferred on it under section 108 of the Electricity Act, 2003, has not issued
any such directive to this Commission. Further, para no. 14 and 15 pertaining to
objections/comments received from stakeholders/general public is also not
appropriately reflected due to the following reasons:-
The said public proceeding, including inviting objections/suggestions from the
Stakeholders, was clubbed with the public proceedings in case no. HERC/PRO-9 of
2016 in the matter of Petition/application filed by the Haryana Power Purchase Centre
(HPPC) for approval of draft Power Purchase Agreements (PPAs) with 13 Solar Power
Developers selected through Tender. Hence, the objections / comments received from
the Interveners were common to both the cases. Accordingly, I observe as under:-
The objectors listed in the present Order, as evident from the hearing
attendance maintained by the office; most of them were not present in the hearing held
on 10.08.2016. Those who were present, except two or three, had submitted that the
PPAs under consideration ought to be approved for promotion solar power plants in
Haryana. Moreover, a large number of comments, other than those mentioned in the
Order at para 15 were filed requesting the Commission to approve the PPAs under
consideration. A few other Interveners who had urged the Commission to approve the
PPAs are as under:-
Sarpanch Grampanchayat (Mangal Salu)
Jai Prakash (Dongli)
Sanjay Singh (Village Jakhni)
Sarpanch (Dohar Kalan)
Nihal Singh (Kamania, Dt. Mahendragarh)
Suresh Chand, Sarpanch, Jailaf, Narnaul)
21 | P a g e
Dalip Singh (Ex Sarpanch, Khatoli Jat)
Manjit, Karota, (Sarpanch, Khatoli Jat)
Rajkumar, (Sarpanch,, Mukendpuhl)
Sushma & 12 others (Bhiwani, Rewari, Narnaul, Ambala, Gurgaon,Mahendragarh)
Sumeet Gupta & eight others (Gurgaon, Rewari, Mewat, Mahendragarh, Panipat)
All the aforesaid persons had no objections and requested the Commission to
approve the PPAs at Rs. 6.44/kWh. These persons had mostly relied on the fact that
setting up more and more solar power plant will help the rural economy and also help in
the betterment of the environment.
It is observed that most of the objections received were subsequent to the
hearing held on 10.08.2016 in the matter and hence, as such, were not deliberated in
the said hearing. Further, the very arguments of these objections built on the premises
that Haryana has signed 70 PPAs and are paying about Rs. 2000 Crore towards fixed
charges without drawing any power are also untenable as the same is in no way
relevant to procurement of RE Power which is a statutory obligation. Further objection
raised are that government has started erecting solar panels on roof top and rates of
solar power is decreasing so solar power will become more cheaper hence it is not legal
to sign PPA for long term at Rs5/kWh and Rs.6.44/kWh. One of the other objections of
that with cheaper solar panels and net-metering, more capacity will be spare, therefore
it is requested that no PPA for solar or otherwise may be signed. As per the RPO
trajectory set by the Commission there have been persistent shortfall in meeting the
RPO (both Solar and Non-Solar) by the Discoms, hence, there is a need for
procurement of such power which is also evident from the reply filed by HPPC that they
will not be able to meet its RPO requirement through net – metering of Solar Rooftop
power projects objection were also received regarding permission not sought for
negotiation, about deviations relating to EMD, CPG in NIT from that of SBD, about
selection of bidders, about absence of external expert in the Evaluation committee as
per MNRE guidelines, about Net-worth taken as Rs.2.0crore instead of Rs3.5 Core in
the SBD, prior approved by the Commission, ceiling limit to be Rs.5.7/kWh and not
22 | P a g e
R7.45/kWh, buying REC instead of solar power through competitive bidding, justification
to purchase solar power etc. Petitioner has filed replies to each of these objections and
I find the replies of the petitioner are in order.
Most of the objections filed by the interveners, as also observed by the Petitioner
in its reply, were of generic nature. Hence, no specific case was made out by the
Interveners based on the process followed by the Petitioner or competiveness of tariff
so discovered that may merit any serious consideration by the Commission while
deciding the present case. The specific issues relating to negotiation, net-worth, prior
approval of the Commission ceiling limit of the tariff, buying REC, and justification to
purchase solar power has been dealt in the subsequent paras of this order.
3. Analysis & My Order
3.1. In paragraph 17 (1) of the Order, it is observed that the Petitioner , HPPC, has
sought the following relief:-
1. Adoption of Tariff discovered through transparent bidding process u/s
63 of the Electricity Act, 2003.
2. Approval of PPAs with solar power developers selected by it under the
NIT No. 51 at the said tariff.
I have perused the Petition / Application filed by HPPC in the present case, the
following is observed:-
i) The first letter dated 16.06.2014 (Ch-43/HPPC/SE/C&R-I/PPA-136) received from the
Petitioner carried a simple request i.e. “It is requested that HERC may furnish its
valuable comments, if any, on the NIT latest by 25.06.2014 so that HPPC may
proceed further with the tender process”. Hence, at that stage, no approval of the
Commission for adoption of tariff or approval of PPAs under the Electricity Act, 2003,
was sought.
23 | P a g e
ii) Subsequently, vide Memo No. Ch-46/HPPC/SE/C&R-I/PPA-67 dated 1.07.2014 the
Petitioner prayed that, “It is humbly requested that approval may please be granted
to the NITs for purchase of 50 MW solar and 100 MW non-solar power”.
Admittedly, even at this stage no approval of the Commission for adoption of
tariff or approval of PPAs under the Electricity Act, 2003, was sought by the Petitioner.
iii) Thereafter, the Petitioner vide Memo No. Ch-2/HPPC/SE/C&R-I/PPA-196 dated
16.07.2015 intimated as under:-
“HPPC had floated tender to purchase 50 MW solar power. The Technical bid
was opened on 22.10.2014 & financial bid on 22.12.2014. Ten nos. bidders
submitted the tenders. Out of them, only eight Nos. Bidders were found eligible
for financial evaluation. The negotiations were done with the eligible bidders. As
a result, Rs.6.44/kWh was discovered as the lowest price for which LOI has been
issued to the following Five Nos. bidders for a capacity of 25 MW solar
power…………………………
HPPC has signed PPA with the above bidders except M/s Sudhakar Infratech
Ltd. Accordingly, HPPC seeks approval of PPA from the Hon’ble
Commission” emphasis added.
It is evident from the above that the Petitioner, at this stage, sought approval of
the PPAs and also submitted the requisite fee as required under HERC (Fee)
Regulations, 2005 (1st Amendment, 2013) for approval of four PPAs for procurement of
23 MW power. Hence, even at this stage no prayer was made or “relief sought” u/s
section 63 of the Electricity Act, 2003 as observed in the order.
For the sake of brevity Section 63 of the Act reproduced as under:-
“63. Determination of tariff by bidding process. - Notwithstanding anything
contained in section 62, the Appropriate Commission shall adopt the tariff if such
24 | P a g e
tariff has been determined through transparent process of bidding in accordance
with the guideline issued by the Central Government”.
Admittedly, as also recorded at para 32 of the Order the draft guidelines shall be
considered as template, there is no guidelines notified by the Central Government /
MNRE. Hence, the validity of the tendering process cannot be questioned on the basis
of deviations from a non-existing guidelines and SBD and Commission’s approval
thereto. In this context the judgment dated 16th March, 1999 in Babu Verghese & Ors.
Vs. Bar Council of Kerala & Ors has been relied upon in the order i.e. the basic principle
of law long settled that if the manner of doing a particular act is prescribed under any
Statute, the act must be done in that manner or not at all (emphasis supplied) cited
by the Hon’ble Chairman at para 27 of the Order strongly supports my considered view
that absence of ‘Guidelines’ as provided in Section 63 of the Act shall negate any
proceedings under the said section of the Act. Therefore, even if this Commission is
required to proceed u/s 63 of the Act the same, in the absence of ‘Guidelines’ shall be
ultra-virus. This is probably the reason that a few other States either invited reverse bids
considering the tariff determined by the SERC u/s 62 of the Act or opted for Feed in
Tariff (FIT). Similarly, the Petitioner also followed reverse bidding process as per the
directions of the Commission in its Order dated 20.11.2013.
Additionally, as also evident from the reply dated 9th March, 2016 filed by the Ld.
Advocate Shri M.G. Ramachandran, for Petitioner, that the Petitioner has initiated the
tendering process for procurement of solar power in order to fulfill its Solar RPO as
mandated by the HERC RE Regulations as well as various Orders of the Commission
regarding bridging the shortfall in RPO compliance.
In view of the above discussions considering the present petition under Section
63 of the Act, which was not prayed for, and then rejecting the same because the
conditions stipulated therein has not been fulfilled, falls short of merit. Further, as
observed earlier also, in the absence of Guidelines / Standard Bidding Documents
notified by the MNRE/Central Government there are no benchmarks available to point
25 | P a g e
out deviations. Hence, the reliance placed on the Hon’ble APTEL’s judgment at para 28
of the Order is not valid as the circumstances in the present case is entirely different
from those dealt by the Hon’ble APTEL in the said case.
The Hon’ble APTEL, in the judgment in Appeal Nos 106 and 107 of 2009,
recognized the fact that the State Commission have been given discretionary powers
either to choose Section 62, 62(1)a to approve the PPA or to direct the distribution
licensees to resort to the competitive bidding process. However, in the present case, the
distribution licensees resorted to competitive bidding by floating the present NIT after
informing the Commission vide its letter dated 1.07.2014 regarding the same. In fact,
the Commission vide its letter dated 8.08.2014 advised them to go ahead with the
tendering process as the same was already in progress. In this letter also the
Commission dwelt at length on the issue of the need to procure RE Power. The relevant
part of the said letter is reproduced below:-
“The Commission observes that the Discoms have not fulfilled their RPO
including by way of purchase of REC. Consequently, the accumulated shortfall
allowed to be carried forward from FY 2011-12 up to FY 2013-14 (up to
December, 2013) is about 720.83 MUs and the total RPO target set for FY
2014-15 is 1463.41 MUs. On several occasions the Commission has observed
that HPPC/HAREDA may invite bids/reverse bids (emphasis supplied) for
purchase of renewable energy to meet with the RPO targets and the fact that
the bidding process is already under way, HPPC may proceed with the same.
Once the bids are opened HPPC shall analyze the same and submit the details
for its order and approval of the PPA with the successful bidders ”.
Thus, after creating enabling provision for inviting bids/reverse bids for
procurement of RE Power, a statutory/quasi-judicial body i.e. this Commission is
estopped from reneging on the same on the plea that the bidding process is not in line
with the provisions of Section 63 of the Act.
26 | P a g e
Notwithstanding the above, in case the bidding process was so vitiated, then the
appropriate course of action was to direct the Discoms to abort the bidding process
forthwith and initiate a fresh bidding process at the time when the Petitioner, way
back on 16.06.2014, sought comments from this Commission on the NIT.
3.2. At para 31 (page 46) of the Order, it has been observed that there are certain
deviations that have a substantive effect on the bidding process and the price discovery
thereto. Regarding the deviations relating to eligibility conditions, I observe that the
amount of net worth for eligibility was reduced to Rs. 2 crore to encourage wider
participation to have most competitive rates. The petitioner has also referred to the RFP
document issued by Punjab Energy Development Agency (PEDA) for 300Mw solar
photo voltaic power project under Phase-I in March, 2012 wherein the net- worth had
been taken as Rs. 2 crore / Mw. It is further observed that the amount of bid guarantee
and the contract performance guarantee were reduced by the Petitioner to have
competitive bids. Considering the submissions of the Petitioner and the absence of any
statutory Guidelines, I find these deviations in order.
3.3 The Order (para 31, page 47) also points out that the bid evaluation committee
was not constituted by the procurer as per the ‘Guidelines’. Regarding this, as per the
details submitted by the Petitioner, technical and commercial bids (excluding financial
bids) were evaluated by a Committee comprising of Chief Engineer (HPPC), Financial
Advisor and Superintending Engineer (HPPC). Additionally, the Steering Committee for
Power Planning (SCPP) constituted for evaluating the purchase of power, consisting of
Additional Chief Secretary (Power), and the Managing Directors of the Haryana Power
Utilities i.e. UHBVN, DHBVN (Discoms), HPGCL (Generation Company), HVPNL
(Transmission Company) and the Chief Engineer (HPPC) considered the prices bids
and decided on the course of action to be taken in accordance to the tender terms and
conditions. As such, in my considered view the procedure adopted by the Petitioner for
technical and financial evaluation was adequate.
3.4 It is further observed at para 31 (page no. 47) of the order that introducing scope
of negotiation would be counter - productive and introduce an element of un-certainty in
27 | P a g e
the whole process which may lead to hardening of the offered price I have examined
this issue and observe as under:-
The Hon’ble APTEL in its judgment 6th May,2010 (Appeal No. 44 of 2010)
M.P.Power Trading Co., Ltd. v/s MP Electricity Regulatory Commission & Ors., has held
as under:-
"38. If we go through the entire bidding documents, we can easily conclude that
the negotiation is inherent and in-built in the bidding process. With regard to
the principle relating to negotiation for reduction in prices (emphasis
added), the Supreme Court has held in Food Corporation of India v. Messrs
Kamdhenu Cattle Feed' (1993) 1 SCC 71, as under:-
10. From the above, it is clear that even though the highest tender can claim no
right to have his tender accepted, there being a power while inviting tenders to
reject all the tenders, yet the power to reject all the tenders cannot be exercised
arbitrarily and must depend for its validity on the existence of cogent reasons for
such action. The object of inviting tenders for disposal of a commodity is to
procure the highest price while giving equal opportunity to all the intending
bidders to compete. Procuring the highest price for the commodity is
undoubtedly in public interest since the amount so collected goes to the public
fund.
Accordingly, inadequacy of the price offered in the highest tender would be a
cogent ground for negotiating with the tenderers giving them equal opportunity
to revise their bids with a view to obtain the highest available price. The
inadequacy may be for several reasons known in the commercial field.
Inadequacy of the price quoted in the highest tender would be a question of fact
in each case. Retaining the option to accept the highest tender, in case the
negotiations do not yield a significantly higher offer would be fair to the
tenderers besides protecting the public interest. A procedure wherein resort is
had to negotiations with the tenderers for obtaining a significantly higher bid
28 | P a g e
during the period when the offers in the tenders remain open for acceptance and
rejection of the tenders only in the event of a significant higher bid being
obtained during negotiations would ordinarily satisfy this requirement. This
procedure involves giving due weight to the legitimate expectation of the highest
bidder to have his tender accepted unless outbid by a higher offer, in which case
acceptance of the highest offer within the time the offers remain open would be
a reasonable exercise of power for public good.
39. The above principle has been laid down by the Supreme Court in a case of
sale of food grains where higher price was beneficial for the public good. The
present case relates to the purchase of electricity by the procurer for
consumers for the lower price in the public interest. The ratio decided by
the above decision taking note of public interest squarely applies to the
present case as well (emphasis added)l."
52. The Hon’ble Supreme Court in the case of AIR India Vs Cochin International
Airport (2000) (SC) SCC 617 has held at para (7) that :-
“The award of a contract, whether it is by a private party or by a public body or
the State, is essentially a commercial transaction. In arriving at a commercial
decision considerations which are paramount are commercial considerations.
The State can choose its own method to arrive at a decision. It can fix its
own terms or invitation to tender and that is not open to judicial scrutiny. It
can enter into negotiations before finally deciding to accept one of the
offers made to it (emphasis added). Price need not always be the sole
criterion for awarding a contract. It is free to grant any relaxation for bona fide
reasons, if the tender conditions permit such a relaxation. It may not accept the
offer even though it happens to be the highest or the lowest but the state, its
corporations, instrumentalities and agencies are bound to adhere to the norms,
standards and procedures laid down by them and cannot depart from them
arbitrarily. Though that decision is not amenable to judicial review, the,
29 | P a g e
court can examine the decision-making process and interfere if it is found
vitiated by mala fides, unreasonableness and arbitrariness (emphasis
added). The State, its corporations, instrumentalities and agencies have the
public duty to be fair to all concerned. Even when some defect is found in the
decision-making process the court must exercise its discretionary power under
Article 226 with great caution and should exercise it only in furtherance of public
interest and not merely on the making out of legal point. The court should
always keep the larger public interest in mind in order to decide whether its
intervention is called for or not. Only when it comes to conclusion that
overwhelming public interest requires interference, the court should intervene.”
53. Hon’ble APTEL in the above case at para (38) of its judgment held that
the negotiations are only for reduction of tariff which is in the best interest
of the consumer (emphasis added). Further it was also held that negotiations
are inherent and inbuilt in the bidding process. Hon’ble Supreme Court in its
aforesaid judgment also held that larger public interest should always be
kept in mind (emphasis added). As observed earlier, negotiations held in
the present case were transparent and have resulted in the reduction of
tariff by L-3 bidder though not by the first two bidders. Any purchase of
additional quantum of power at the lower rate than the quoted rate or the rate
quoted by the bidder cannot be held to be contrary to law. On the contrary it is in
the interest of the public. Even clause 3.5.7 authorises the petitioner to increase
or decrease the quantum more than 10% with the approval of the Commission.
54. In the light of the facts noticed as above and the law laid down by Hon’ble
Supreme Court and APTEL, we are of view that the bidding process carried out
by the petitioner and negotiations held are not in violation of either Section 63 of
the Act or the bidding guidelines/bidding conditions.
Examining the present case in view of the above case laws, the moot point, as
held by the Hon’ble Supreme Court, that emerges is whether larger public interest
30 | P a g e
was kept in mind by HPPC while entering into negotiation with the bidders.
Regarding this it is observed that the four successful bidders, in their bids, had
quoted/offered a levelised tariff of Rs.6.50/kWh (Balarch Renewable Energy Pvt. Ltd.),
Rs. 6.90/kWh (Subhash Infraengineers Pvt. Ltd.), Rs. 6.99/kWh to Rs.7.45/kWh (Neel
Metal Product Ltd) and Rs. 7.36/kWh (Ultimate Sun Systems Pvt. Ltd.). It is observed
that the Steering Committee under the Chairmanship of the Additional Chief Secretary,
Haryana Government and the Managing Directors of all the Haryana Power Utilities i.e.
UHBVN, DHBVN (Discoms), HPGCL (Generation Company) and other senior officers
deliberated the issue and modalities of negotiation with eight eligible bidders against
NIT No. 51/CE/HPPC dated 16.04.2014. Accordingly, the negotiations were done, as
also provided in the NIT, and the four bidders mentioned above agreed to offer Solar
Power at Rs.6.44/kWh i.e. the lowest tariff discovered after the negotiations with the
eight successful bidders. As such in my view, the negotiation with bidders, in the
present case did not vitiate the bidding process in any manner and it rather, added
value to the Haryana Utilities and the consumers at large as also claimed by the
petitioner
3.5. It is observed that the lowest price discovered is lower than the ceiling tariff of
Rs.7.45/kWh determined by the Commission as well as the initial levelised tariff quoted
by the eight successful bidders. As far as competiveness of the tariff is concerned the
following rates determined by the SERCs were submitted by the Petitioner:-
Levellised Tariff for FY 2014-15 (Rs./kWh)
Haryana CERC Rajasthan M.P. Punjab Tamil Nadu U.P. Uttarakhand
7.45 7.72 7.50 8.05 7.72 7.01 8.91 6.99
In view of the above, it was submitted by the Petitioner, that the tariff @
6.44/kWh discovered by way of the tendering process was far more competitive than
the tariff determined by the SERCs including Haryana. It is added that this Commission
31 | P a g e
while issuing generic tariff Order for the RE Projects for the FY 2014-15 {(Case No.
HERC / PRO - 50 of 2014 (Suo Motu) had categorically observed as under:-
“9.0 The Commission directs the Discoms to purchase renewable energy as
per RPO targets set in the 3rd amendment to the HERC RE Regulations, 2010.
In case they can purchase the same at a tariff lower than determined by
this Commission they may do so, otherwise they must purchase all such
power offered to them by the renewable energy power producers at the
tariff determined by this Commission (emphasis supplied). Further the
Commission is of the view that it is always preferable to purchase renewable
energy because of fact that such generation projects as per the statutes has to
be encouraged, rather than to purchase REC wherein the amount paid for
purchase of the same goes to the generator without even getting the benefit of
power availability. Additionally, because of its distributed nature, RE generation
is considered advantageous in terms of reduced cost of transmission network
and reduced transmission losses. This advantage becomes considerably
enhanced when such RE is generated and consumed locally”.
In view of the above and given the fact that the Petitioner, incompliance of the
Commission’s Order, carried out the tendering process and discovered / negotiated a
tariff considerably lower than that determined by the Commission, it now not open for
the Commission to evaluate the competiveness of the tariff so discovered on the basis
of tariff discovered at a later point of time or in some other State(s).
3.6. I have carefully perused the observations of the order at para 34, quite a few of
the observations has already been dealt by me in the preceding paragraphs. In the
paragraph below, my observations are restricted to some of the additional / relevant
issues brought out in the Order in this paragraph.
Sub para ii) (page no. 48) dwells on deviations from the SBD, deviations other
than Bid Bond and CPG were not rectified. As already observed by me these would
32 | P a g e
have been relevant in case the Petitioner had prayed for adoption of tariff u/s 63 of the
Act. Additionally, reference to HPGCL’s offered price of Rs. 4.88/kWh and
subsequently discovered bid price of Rs. 5.0/- is completely out of context. The
purported tariff of Rs.4.88/- has not been determined/approved by the Commission, as
of now, it is just a proposal that too after considering a much higher CUF of 21% and
without including cost of transmission line and land. Further, it is well known that the
cost of setting up solar power plant is declining; hence, bids price at different points of
time is strictly not comparable. The per unit tariff of solar power being procured from
SECI i.e. Rs.5.50/Unit is also not comparable as the same take into account the Viability
Gap Funding (VGF) available for setting up such projects under Jawahalal Nehru Solar
Mission (JNNSM) of Government of India. Moreover, the PSA is yet to be approved by
this Commission. Additionally, the said tariff is ex- generator(s) bus and hence after
accounting for transmission charges/losses and VGF the landed cost/tariff for the said
power shall work out to higher than Rs. 6.0/Unit.
The observations (para vii) regarding savings of Rs. 3.34 Crore and Rs. 1.1 Crore
attributed to the stakeholders probably quantifying on the basis of fulfilling RPO during
the next two years through REC route is also not true reflection of the facts. The
response of the Petitioner that meeting RPO through purchase of RECs for the next two
years will be marginally higher than procuring solar power under the PPAs under
consideration has not been considered / evaluated. In my considered view also
procuring power @ Rs. 6.44/kWh, is a cheaper option compared to purchasing REC at
Rs. 3.50/kWh if we consider the average price of power procurement of about Rs.
4.0/kWh.
It is observed in the order at sub para x) that “HPPC does not appear to have
followed its own process as mandated in Para 3.1.4 (iv)”. The said clause provides that
solar power projects in the State of Haryana will be given first priority and thereafter, the
bidder offering the maximum capacity will be given the priority. It is observed that the
Solar Power projects of all the four successful bidders are located at different districts of
Haryana. Hence, as per the said clause priority was accordingly given to the projects to
be set up in Haryana. Further, these were the ones who agreed to offer solar power @
6.44/kWh i.e. at the lowest discovered price. Hence, HPPC has not violated any
33 | P a g e
provisions of the Electricity Act, Rules and Regulations and has adopted a transparent
bidding process as evident from the submissions made by the Petitioner.
4. In conclusion, I Observe and Order as under:-
4.1. As per the replies submitted by the petitioner in its response to the objections
filed by the Senior Citizens Council & Others, the petitioner has stated that in the tariff
orders passed by the Commission from time to Time, the Haryana Utilities have been
mandated to purchase power to meet the Renewable Purchase Obligation. It is further
stated that Haryana Discoms were finding hard to meet the RPO targets set by the
Commission. HPPC filed various petitions from time to time with prayer for amendment
of RE regulations, 2010 and relaxation or carry forward of RPO as under:-
I) Petition dated 8.06.2012 for seeking review / or modification of Renewable
Purchase Obligation (RPO).
II) Petition dated 19.10.2012 and Supplementary filling dated 25.01.2013 for
seeking review and / or modification of the Haryana Electricity Regulatory
Commission (Terms and Conditions of Determination of Tariff form
Renewable Energy Sources, Renewable Purchase Obligation and Renewable
Energy Certificate) Regulations, 2010.
III) Petition dated 20.08.2013 for seeking relaxation or carry forward of
Renewable Purchase Obligation (RPO) for FY 2011-12 and FY 2012-13.
Disposing of the above petitions, the Commission issued an Order dated
20.112013. The abstract of the same is reproduced hereunder:-
“It is clarified that the tariff determined by the Commission is the ceiling
tariff. In case the Discoms / HPPC is able to procure renewable energy
(solar and non – solar) at a rate lower than that determined by the
Commission by way of reverse bidding or otherwise, they may do so.
However, the Discoms / HPPC, may not evade their responsibilities of
achieving the RPO specified in the RE regulations, 2010 for the
respective years on the plea that they are in the process of inviting bids
34 | P a g e
or merely making a statement that renewable energy is available at a
tariff lower than that determined by the Commission”.
Further, the Petitioner in its affidavit 09.03.2016 has also submitted that the
Commission in it is order dated 29.05.2014 regarding approval of Distribution and Retail
supply tariff for the FY 2014-15 had directed to the discoms as under:-
The Commission directs the Discoms to purchase renewable energy as per RPO targets set for FY 2014-15 and the shortfall carried forward, on actual basis, for previous years. In case they can purchase the same at a tariff lower than determined by this Commission they may do so, otherwise they must purchase all such power offered to them by the renewable energy power producers at the tariff determined by this Commission. The shortfall in meeting the RPO for the FYs 2011-12, 2012-13 and 2013-14 as per details given above shall also be met in the FY 2014-15 in addition to the RPO of FY 2014-15. The Commission has taken a serious note of non-compliance of RPO targets including non purchase of REC to meet RPO. In case no action is taken by the Discoms, the officer concerned shall be held liable for non-compliance and proceeded against u/s Section 142 of the Act.”
HPPC, in its submissions, has submitted that they had initiated competitive
bidding process in compliance to the above mentioned directions of the Commission.
4.2. The NIT, in the present case, as already observed by me, was submitted by the
Petitioner to the Commission for comments and the PPAs were subject to approval of
the Commission and the Commission had allowed the Petitioner to ‘go ahead’ with the
tendering process. Further, the tendering process was carried out in compliance with
the Order/directives of this Commission. The tariff, discovered after negotiations was
also competitive and significantly below the tariff determined by this Commission as
well as a few other SERCs for the solar power plants to be commissioned in the FY
2014-15. Additionally, it has been observed in the Order at Para 30 (page no. 46) that
the documents submitted to the Commission carried a benchmark rate of Rs. 5.70 and
not Rs. 7.54 per unit. On this issue I observe that the levellised tariff of HERC @ Rs.
35 | P a g e
5.70/kWh was for the projects commissioned / to be commissioned in the FY 2013-14
as pointed out by the petitioner in his reply to the objections and the same also had a
few computational errors. Further, in the revised (final) NIT No. 51 issued by the
Petitioner it was clearly provided that the levelised tariff determined by the Commission
for the Solar PV Power projects as per HERC RE Regulations, 2010, for the FY 2014-
15 shall be the ceiling tariff. As the levelised tariff determined by the Commission for
the FY 2014-15 was @ Rs. 7.45/Unit the relevant benchmark for inviting the present
tender was rightly considered by the Petitioner @ Rs.7.45/kWh (mentioned as
Rs.7.54/Unit in the Order).
4.3. Admittedly, there are no SBD/Guidelines approved and notified by the
MNRE/Central Government. What does exist is the draft MNRE Guidelines and draft
SBD for procurement of long term RE Power. This probably the reason that the few
other states either invited reverse bids considering the tariff determined by the HERC as
ceiling tariff or opted for feed in tariff (FIT). Similarly the petitioner also followed reverse
bidding process as per the directions of the Commission in its order dated 20.11.2013.
Hence, it is evident that the ibid draft Guidelines / Documents were used by the
Petitioner as a broad framework only. Thus, inviting bids for small capacity Solar Power
Projects quite a few modifications was required as done by the Petitioner. It is observed
that this Commission, vide letter dated 8.08.2014, communicated to the Petitioner
(HPPC) as under:-
“Kindly refer to memo no. Ch-43/HPPC/SE/C&R-I/PPA-136 dated 16.06.2014
and Ch-46/HPPC/SE/C&R-I/PPA-67 dated 1.07.2014 vide which approval of
the Commission was sought to the deviations in the bid documents vis-à-vis
the Case 1 RE Bidding Procedure of the Government of India. The
Commission has considered your application/petition and observes that the
NIT No. 51 & 52 for inviting competitive bids for purchase of 50 MW Solar
Power and 100 MW of Non – Solar (renewable energy) were issued on
16.04.2014 and the approval of the Commission to the deviations were
sought on 1.07.2014 i.e. ex post facto.
36 | P a g e
The Commission observes that the Discoms have not fulfilled their RPO
including by way of purchase of REC. Consequently, the accumulated
shortfall allowed to be carried forward from FY 2011-12 to FY 201314 (up to
December 2013) is about 720.83 MUs amd the total RPO target set for FY
2014-15 is 1463.41 MUs. On several occasions the Commission has
observed that HPPC/HAREDA may invite bids/reverse bids for purchase of
renewable energy in order to meet with the RPO targets and the fact that the
bidding process is already under way, HPPC may proceed with the same.
Once the bids are opened HPPC shall analyze the same and submit the
details to the Commission for its order and approval of the PPA with the
successful bidders”.
A plain reading of the Commission’s letter dated 8.08.2014 establishes the fact
that the deviations in the said NIT documents were in the knowledge of the
Commission. Further, the Commission was also concerned about sustained shortfall in
the RPO of the Discoms. Hence, this Commission allowed the Petitioner to proceed with
the tendering process. The intentions, clearly, was not to sit in judgment regarding the
‘deviations’ after opening of the bids.
4.4. While the allocation for Solar Power Project in the present case has already been
done through competitive bidding as per Orders Directions issued by the Commission
from time to time, the issue may arise, whether the competitive bidding was carried out
on the basis of professed norms of completive bidding to reduce the overall cost of
power procurement. This issue has been examined at length and following is
observed:-
1) The Petitioners issued Notice of inviting Tender (NIT) on 17.04.2014 for
procurement of 15Mw solar power to tariff based committee bidding in the,
Newspapers Hindustan Times, Mail Today and Business Standard. The NIT has
been prepared based on the draft SBD of the MNRE with certain modifications to
have wider participation and completive rates. The NIT document consisted of
37 | P a g e
all the relevant information such as general instructions to the bidders, project
details, criteria of generation, grid connectivity, qualification requirement,
consents, clearances and permits, bid bond, CPG, Bank Guarantees, Financial
Closure, Commissioning Schedule, Penalty for delay in Commissioning, Penalty
for short fall in generation, rate for excess generation over threshhold capacity
utilization factor (CUF), evaluation criteria etc. The draft power purchase
agreement also made part of the bid document.
2) Petitioner held pre-bid conference on 05.05.2014 to obtain suggestion of the
participating bidders. Around 15 firms participated in the pre bid meeting. The
petitioner received queries from 8 firms regarding terms and conditions of the
NIT. These queries were generally relating to generic tariff, delivery point, CUF,
penalty for less generation etc.
3) After incorporating the comments raised by the bidders during pre bid
conference, the petitioner forwarded the copy of the NIT to the Commission on
16.06.2014 for comments.
4) The Commission vide letter dated 08.08.2014 allowed the petitioner to go ahead
with the bidding process.
5) The revised NIT was issued on 14.08.2014. In the revised (final) NIT No. 51
issued by the petitioner it was clearly provided that the levelised tariff determined
by the Commission for the Solar PV power projects as per HERC RE
Regulations,2010, for the FY 2014-15 shall be the ceiling tariff.
6) The last date of submission of the bids was extended upto 22.10.2014. The bids
were opened on 22.10.2015.
7) The technical and commercial bids (excluding the price bid-financial) received
form 10 participating bidders were first opened on 22.10.2014 and was then
evaluated by a Committee consisting of Chief Engineer HPPC, Financial Advisor
and Superintending Engineer, HPPC. 8 out 10 participating bidders were found
to be responsive.
8) The price bid of the 8 bidders was then opened on 22.12.2014. The price bids
were in the range of Rs. 6.50 to 7.45/kWh.
38 | P a g e
9) The Steering Committee for Power Planning constituted for evaluating the
purchase of power consisting of Additional Chef Secretary, Power and Managing
Directors of Electricity Utilities (GENCO, TRANSCO AND DISCOMS), Chief
Engineer /HPPC considered the price bids and decided on the course of action to
be taken in accordance to the tender terms and conditions.
10) Negotiation was held by the above mentioned Steering Committee with the
bidders as per the criteria given in the NIT. After negotiation lowest tariff was
arrived at Rs. 6.44/kWh lower than the L1 quoted price.
11) The five selected bidders with an aggregate capacity of 25Mw were only those
who matched the bidding criteria and also the lowest quoted price of 6.44/kWh
12) Although five bidders were selected by HPPC for 25 MW capacity initially, PPAs
were signed for only 23 MW capacity with 4 bidders as one bidder did not fulfill
the terms and conditions of the bid document issued by the petitioner.
Form the details given above it is clear that the petitioner followed an elaborate
completive bidding process in a transparent manner which is also evident from the fact
that a large number of bidders submitted the bids. The petitioner accordingly discovered
a completive tariff which is significantly below the tariff determined by this Commission
for the FY 2014-15 as well as FY 2015-16. Thus, in my considered view the bidding
process adopted by HPPC meets with the underlying objective of regulation of electricity
purchase and procurement process of distribution licensees on the basis of professed
norm of competitive bidding to reduce the overall cost of procurement of solar power in
the interest of the electricity consumers.
4.5. As the SBD was not in existence, hence, the question of other deviations (which
has not been mentioned in the order) from the SBD does not arise. Further, the order
also refers to the newspaper report dated 20.01.2016 that the Solar tariff hits new low in
Rajasthan i.e. Rs. 4.34 to Rs.4.63/kWh and Rs.5.0/kWh in Haryana in a subsequent
bidding process. I have considered the figures relied upon in the Order and I am of the
view that the Solar tariff obtained in Rajasthan could be very different because of much
better CUF and cheaper land available in Rajasthan more so if the Solar Power Projects
39 | P a g e
are located in the Solar Park promoted by the Rajasthan Government. Additionally, the
projects envisaged / bids called at different points of time as in the case of subsequent
bids for 165 MW Solar Power invited in Haryana or the tariff reported sometimes in
January, 2016 in Rajasthan as against the present bids received by HPPC sometimes
in October, 2014 are strictly not comparable as with the passage of time the project cost
has witnessed a sustained decline. Hence, any decision based on such comparison is
futile. As a corollary if we wait for some more time the tariff discovered / offered may
turn out to be lower or higher depending on the market conditions.
In view of the above discussions, I approve the draft PPAs submitted
by the Petitioner with four Solar Power Developers selected through competitive
bidding.
Date: 04th October, 2016 (M. S. Puri)
Place: Panchkula Member