Page 1: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Bayou Verdine Superfund Site Casey Luckett Snyder

Page 2: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

  

Presentation Overview

• Site History

• Site Cleanup

• Reuse Planning

• Reuse Outcomes

• Lessons Learned

2

Page 3: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

       

Site History

• Lake Charles, Louisiana • Southwest Louisiana • Westlake Community • Near Lake Charles and Calcasieu River • 130 miles west of Baton Rouge

• Petroleum refinery and petrochemical complex

• Polycyclic aromatic hydrocarbons (PAHs) and heavy metals

3

Page 4: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Site Cleanup

• 2003 – EPA Calcasieu Estuary Investigation

• 2010 – Consent Decree

• December 2011 – Removal Action Work Plan

• September 2012 – Cleanup begins

4

Page 5: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Site Cleanup

5

Page 6: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

   

Site Cleanup

• Dredging • Hydraulic dredging • Mechanical excavation

• Calcasieu Estuary Task Force

6

Page 7: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Site Cleanup

• September 2012 – Cleanup begins

• February 2014 – Dredging completed

• October 2014 – Sediments solidified in the settling basin

• December 2014 – Top liner installed on containment cell

7

Page 8: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

  

Reuse Planning

• Green remediation

• Considered ecological reuse during cleanup

• Ecological Revitalization Plan

8

Page 9: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

  

Reuse Planning

• West pond deepened

• East pond containment cell covered

• Cleanup completed April 2015

9

Page 10: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Reuse Outcomes

10

Page 11: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Reuse Outcomes

January 2015 February 2015 11

Page 12: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Reuse Outcomes

March 2015 September 2015 12

Page 13: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Reuse Outcomes

13

Page 14: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Reuse Outcomes

14

Page 15: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Reuse Outcomes

15

Page 16: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Reuse Outcomes

• October 2015, EPA Region 6 Greenovations Award

• 2016, EPA National Notable Achievement Award - Casey Luckett Snyder

16

Page 17: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Lessons Learned

• Approach projects with out-of-thebox thinking

• Incorporate reuse considerations in cleanup design

• Communicate, collaborate and build relationships

17

Page 18: Bayou Verdine Superfund Site - CLU-IN · • Dredging • Hydraulic dredging • Mechanical excavation ... • December 2014 – Top liner installed on containment cell 7 . Reuse

Contact Information

Casey Luckett Snyder