baseline change request bcr title: ebd new 6 ton bridge crane installation bcr #: n/a presenter’s...
TRANSCRIPT
Baseline Change RequestBCR Title: EBD New 6 Ton Bridge Crane InstallationBCR #: N/A
Presenter’s Name: Robert Law
CCB Presentation Date:
2
BCR Summary
This BCR entails the requirement for a new 7 ton motorized chain hoist &
bridge crane system to be installed in EBD Area to efficiently, safely and
timely facilitate the removal and/or installation EBD system activities as
follows:• Removal of (2) existing LCLS dumps shielding with combined weight of
approximately 92 tons (57 tons for South dump; 35 tons for North dump)• Installation of LCLS-II new dumps shielding with combined weight of
approximately 408 tons (204 tons each for both North and South dumps)
including 90 plates weighing 2 tons/plate, • Relocation / Installation of EBD hard & soft beam lines components /
devices including (3) permanent magnets, and (2) dump slugs with
shielding coffins weighing between 5 and 6 tons each.• Installation of over 200 new shielding components for both hard & soft
beam lines components / devices.
CCB Presentation – MM-DD-YYYY
3
BCR Form
CCB Presentation – MM-DD-YYYY
4CCB Presentation – MM-DD-YYYY
• Background
In Electron Beam Dump (EBD) housing there are (2) monorail
cranes on the North and the South sides. Each rail starts with a
short piece and finishes with short piece assumable 20.5’ each .
The middle section is a long rail assumable 41’ long.
The two crane rails are parallel ( field verified). Distance between
rails is 98.5”. The distance from South and North walls to the South
and North rails center is 39.25”.
Both cranes have lifting capacity of 5 tons (10,000 lbs) each. Based
on current SLAC crane records, only the South monorail crane has
anchored fixture for crane certification with quadrennial certification
date of November 1, 2011.
Refer to Figures 1 & 2 for existing monorail cranes arrangement.
Background, Problem, Solution
5CCB Presentation – MM-DD-YYYY
• Background (Continued)
Background, Problem, Solution (Continued)
BEAM
Monorail crane rails - 41’ EBD Housing End
Figure 1: Existing monorail crane rail view from the South side
6CCB Presentation – MM-DD-YYYY
• Background (Continued)
Background, Problem, Solution (Continued)
Figure 2: Existing monorail cranes view downstream
Monorail crane rails - 98.5” apart
EBD Housing 177”W X 150”H
7CCB Presentation – MM-DD-YYYY
• Problem- Relocation of (3) permanent magnets in EBD will be a challenge since
the current crane rails do not fully align with both North and South
beam lines as shown in Figure 3.- New beam lines after the BYD magnets are not parallel to each other
and to the existing crane rails. Existing cranes will cover very limited
service areas as shown in Figure 4.- Existing shielding was put in the pit with forklift when there was no
East wall in the housing and there were no obstructions on the North
side.- New dump will have two similar beam lines on the North and South
sides with very limited space between them and forklift access will be
either unsafe or not feasible.
Background, Problem, Solution (Continued)
8CCB Presentation – MM-DD-YYYY
• Problem (Continued)- New shielding will be much larger than the existing ones in magnitude
of more than 4 (total combined new dumps shielding quantity will be
about 408 vs total existing dumps shielding quantity of 92. The
average single shielding plate weighs about 2 tons. Besides new
shielding, there will be over 200 new shielding components to be
installed for both hard & soft beam lines components / devices.
- A single heaviest device to be lifted, the dump slug with shielding coffin
required by RP, weighs between 5 to 6 tons.
Background, Problem, Solution (Continued)
9CCB Presentation – MM-DD-YYYY
• Problem (Continued)
Background, Problem, Solution (Continued)
10CCB Presentation – MM-DD-YYYY
• Problem (Continued)
Background, Problem, Solution (Continued)
Figure 4: Top view of existing cranes coverage areas
11CCB Presentation – MM-DD-YYYY
• Solution- Install a new 7 ton motorized chain hoist / trolley and bridge crane
system in EBD Area using existing monorail crane rails to meet
EBD System’s crane capacity and space dimensions requirements
as outlined in Figures 5 & 6.- The new crane system will provide the required coverage area as
shown in Figure 7.- Installing shielding and beam lines components / devices with the
new bridge crane will be safer, reduce potential worker injury,
equipment damage, and maintain the project’s fast paced
installation schedule.- The entire EBD Area will be modified and the installation of the new
crane system will not impact EBD system installation schedule.
Background, Problem, Solution (Continued)
12CCB Presentation – MM-DD-YYYY
• Solution (Continued)
Background, Problem, Solution (Continued)
Figure 5Crane upgrade requirements:- Single hoist rail;- Capacity – 6t Min;- Dim “A” – 10” Min;- Dim “B” – 160” Min;- Dim “C” – 118” Min
Existing rails
Ceiling
13CCB Presentation – MM-DD-YYYY
• Solution (Continued)
Background, Problem, Solution (Continued)
Figure 6Crane upgrade requirements(continued):- Dim “D” – 920” min;- Dim “E” – 30” Max;
14CCB Presentation – MM-DD-YYYY
• Solution (Continued)
Background, Problem, Solution (Continued)
New bridge crane coverage area
Figure 7: Top view of new bridge crane coverage area
15CCB Presentation – MM-DD-YYYY
• Alternative Solutions Considered- No new crane: Material handling equipment access for
shielding, beam lines components / devices installation works
in EBD Area will be seriously affected in terms of logistics,
cost and schedule. Inadequate available crane capacity to lift
heaviest object will be a problem. - Different shielding design to meet RP requirements will be a
challenge in terms of cost and schedule.- Option to install a new 7 ton manual hoist / trolley and
motorized bridge crane system vs the current proposed 7 ton
motorized hoist / trolley and bridge crane is currently being
considered as another option to lower first cost.
Background, Problem, Solution (Continued)
16CCB Presentation – MM-DD-YYYY
Technical Review
• EBD installation bi-weekly meetings have been held for
several months to plan Accelerator and Photon System
installations.
• The group has concluded that a modified crane is
required to:
• Install the heavier objects like shielding and dump slug.• Facilitate remotely removing a radioactive dump slug in the
event this will be required.
17CCB Presentation – MM-DD-YYYY
Summary of Cost/Schedule Changes
• For new proposed 7 ton motorized hoist/trolley and motorized bridge crane system:- Total Construction Cost: $223k- Total Estimated Cost: $235k- Installation to start after December 17, 2016 (LCLS short downtime)- No change to current construction schedule
• For new alternate 7 ton manual hoist/trolley and motorized bridge crane system:- Total Construction Cost: $184k- Total Estimated Cost: $196k- Installation to start after December 17, 2016 (LCLS short downtime)- No change to current construction schedule
• For no new crane option
- Total Construction Cost Increase: $600k (ROM)
- Total Estimated Cost Increase: $700k (ROM)
- Construction schedule delay (short downtime): ~ 25 days
- Construction schedule delay (long downtime): ~ 35 days
18CCB Presentation – MM-DD-YYYY
Impact of not approving
• Material handling equipment access for shielding, beam lines
components / devices installation work in EBD Area will be
seriously affected in terms of logistics, cost and schedule.
Inadequate available crane capacity to lift heaviest object will be
a problem.
• Design of a temporarily installed lifting device capable of
moving 2-6 ton objects in a restricted area will be challenging
and likely result in a less safe working environment.
• If the dump slug ever needs to be removed, radiation exposure
time is expected to be longer relative to having a crane design
optimized for this purpose.
• Increased risk relative to safety, hardware damage, and
schedule.
19
Stakeholder Review
• Stakeholder Input Received- PMCS group: Updating P6- System Managers and CAMs: Infrastructure Systems, Photon
Systems, and Accelerator Systems have been working together
on this.- ES&H: Reviewed details with Jim Healy. Jim provided feedback
indicating that installing shielding and devices by crane will be
safer, reduce potential worker injury, equipment damage, and
maintain the project’s fast paced schedule.
CCB Presentation MM-DD-YYYY
20
Documents Updated
• If approved, the following will be updated:• Applicable ICD and RDS• eCAM Book• BOE’s
CCB Presentation MM-DD-YYYY
21CCB Presentation – MM-DD-YYYY
What else should we know?
22CCB Presentation – MM-DD-YYYY
Questions?
23CCB Presentation – MM-DD-YYYY