BAE SYSTEMS TOTAL REFURBISHMENT FOR DIRECTORS
AND BOARD FACILITIES
B TOMLINSON
RECEPTION AND WALK WAY THROUGH AREAS
GENERAL PLAN LAYOUT GROUND FLOOR
MD TELE-PRESENCE AND MEETING ROOM
HOSPITALITY BREAK OUT
AREA
MD OFFICEMD’s PA OFFICE
SALE PRESENTATOION AREA CINEMA EXPERIANCE
MAIN BOARD ROOM
TOILET FACILITIES
KITCHEN AND BUFFET
PREPERATION AREA
DIRECTOR
SALE PRESENTATOION AREA
CINEMA EXPERI
DIRECTOR
PA
DIRECTOR DIRECTOR
DIRECTOR
PA
PAPAPA
PA
PA
DIRECTOR
MAIN ENTRANCE
WAITING AREA
MD’s AN D BOARDROOM WAIYING AREA
OFFICE FACILTIES HUB
RECEPTION
PROJ
ECTI
ON
ROOM
WAITING AREA
(TOP) DIRECTORS OFFICES (BOTTOM) MD’s TELE PRESENCE AND MEETING ROOM ALSO WAIT SEATING AREA
DIRETORS MAIN BOARD ROOM – PARTICULAR ATTENTION PAID TO ACCOUSTICS AND INLAY OF MIROPHONES AND PERSONNEL SPEAKER INTO MEETING TABLE FABRIC, SO THAT SPEAKING FROM ONE END OF THE TABLE WAS AS CLEAR TO THE OTHER END.BOARDROOM WAS ALSO CONTRUCTED WITH SURROUND GLASS. THIS WAS WHITEW SHADE ELECTRONIC GLASS THAT COULD BE TURNED ON/OFF WHEN REQUIRED TO SUIT PRIVERSEY.BOTTOM LEFT IS HOSPITALITY BREAK OUT AREA TO SERVE THE BOARD ROOM
A POCKET HISTORY OF THE PROJECT
TYPICAL STRIP OUT AFTER YEARS OF OCCUPATION AND LOCALIZED MODIFICATIONS.MAMOUTH AMMOUNT OF DATA CABLES ABOVE THE CEILINGS.PLUS THE USUAL AMMOUNT OF THR UNKNOWN. THE BUILDING WAS STRIPPED BACK TO THE BEAR STRUCTURE, TO ENABLE ENERGY IMPROVEMENTS TO THE BUILDIN FABRIC.
CLEANED OUT NEXT STAGE
AREAS CLEARED, FIT OUT COMMENCED. M&E SERVICES BEING INSTALLED.INSULATION CLADDING ADDED TO ALL EXTERNAL WALLS. ALL WINDOWS AND FRAMES CHANGED TO DEVELOP A HIGH ENERGY SAVING HIGH SPEC FINISH BUILDING
MOVING ON
FITTING OUT COMMENCED AREAS AND ROOMS START TO TAKE SHAPE.MAJORITY OF M&E SERVICES NOW INSTALLEDCEILING GRIDS BE INSTALLED
AREA NOW SHOWING DESIGN INTENT
AREA BEING FITTED OUT OFFICES NOW FORMED AND GLAZING INSTALLED.DECORATION FINISHES IN PROGRESS
JUST PRIOR TO OCCUPANCY