background information document for activities …
TRANSCRIPT
1
2. PURPOSE OF THIS DOCUMENT This document has been prepared to inform you:
• about the proposed activities;
• about the EIA process to be followed;
• of possible environmental impacts;
• how you can have input into the EIA process
3. YOUR ROLE Public involvement is an essential part of the EIA process.
You have been identified as an interested and affected party (IAP) who may want to know about the proposed activities and have input into the EIA process.
All comments will be recorded and addressed in the EIA process.
5. HOW TO RESPOND
Responses to this document can be submitted
or through communication with the contact person
listed below.
Name: Immanuel N. Katali
Cell No: +264818035825
Email: [email protected]
.
WHO TO CONTACT
BACKGROUND INFORMATION DOCUMENT FOR ACTIVITIES ASSOCIATED WITH THE IIPUMBU YA TSHILONGO CONSERVANCY’S PROPOSED CONSTRUCTION OF A DAM, LOCATED IN UUKANGA VILLAGE, OSHANA REGION.
1. INTRODUCTION
The Iipumbu Ya Tshilongo Conservancy (hereinafter
referred to as IYTC), intends on obtaining an
Environmental Clearance Certificate (ECC) for the
construction of a dam with an increased water
carrying capacity, that will be used as a source of
drinking water for various animals, such as,
Wildebeest, Lions, Elephants, Oryx, Springbok,
Jackals, Rhinos, Elland, Zebras and livestock, in the
area.
The project is proposed to be located in Uukanga
Village in the Uuvudhiya Constiituency. The proposed
site is located approximately 1 km from the Etosha
National Park boundary fence.
4. ENVIRONMENTAL APPROVAL
Prior to the commencement of the proposed
construction activities, an application for
environmental clearance will be submitted in terms
of the Environmental Management Act, 7 of 2007
and Regulations 19 and 21 of the EIA Regulations
(January 2012) to the MEFT - Department of
Environmental Affairs (DEA). MEFT - DEA will
review the application and relevant reports for a final
decision. An EIA process will be conducted in terms
of the above-mentioned Act and Regulations.
I.N.K Enviro Consultants cc (I.N.K), is an
independent firm of environmental consultants and
has been appointed to manage the EIA process for
the above-mentioned activities.
2
`
7. STEPS IN THE EIA PROCESS
PHASE I – Internal Screening (April)
• EIA project initiation.
• Notify MEFT: DEA..
• Site visit and identify environmental issues.
• Identify key stakeholders.
PHASE II – Combined Scoping & Assessment
Phase and Environmental Management Plan
(EMP) (April – June)
• Submit Application form to MEFT
• Notify other regulatory authorities and IAPs of the proposed project (via newspaper advertisements, this document, emails, site notices).
• Conduct public meeting (see details provided) and key stakeholder (focus group) meetings.
• Assess impacts of proposed projects and compile Scoping (including assessment) report and EMP.
• Comment period: Reports will be made available for review and comment by regulatory authorities and registered IAPs.
• Compile final reports (including Issues and Response Report).
• Submit the final reports to MEFT for their review and decision-making.
6.8 Trucks for Construction
The construction phase will make use of 2 dip trucks,
1 excavator, 1 loading truck and 1 4x4 vehicle.
6.2 Waste Management
Relatively small quantities of waste will be generated
during the construction process of the dam. Waste
shall be transported to receptors at the Conservancy
offices on a weekly basis during construction.
6.3 Sanitation
Portable toilets with associated septic tanks will be
used. The septic tanks will be emptied on a regular
basis ensuring no spillages in the proposed sites of
infrastructure construction.
6. DESCRIPTION OF THE PROJECT
6.1 Introduction
The sections below provide a description of the
proposed project.
6.2 Proposed Dam Size
The Dam is proposed to be 50 m x 70 m in size.
6.3 Laydown Area
The laydown area is required for the storage and
partial assembly of the project
material/equipment/trucks to be used during the
construction. The proposed site for the dam will
require disturbance i.e., land clearing of the dominant
Mopane shrubs.
6.4 Closest Sensitive Receptors
The closest infrastructure to the proposed site is a
deserted cattle post, located approximately 5 km from
the site. No other infrastructure is found within a 5 km
radius to the site.
6.5 Access Road
A new access road to the proposed site will be
constructed. This road will be linking the dam to the
nearest road, which will be approximately 300 m long.
6.6 Construction Timeline
The Construction period of the proposed dam is
anticipated to take approximately 1 month.
6.7 Closest Sensitive Receptors
The closest infrastructure to the proposed site is a
deserted cattle post, located approximately 5 km from
the site. No other infrastructure is found within a 5 km
radius to the site.
3
9. EIA PROCESS
The EIA process provides information on the
proposed project and the environment in which it
may be situated; it identifies, in consultation with
IAPs, the potential negative and positive
environmental aspects and associated impacts of
the proposed project; and reports on management
measures required to mitigate such impacts to
acceptable levels. The likely process steps and
timeframes are provided below.
A draft Scoping Report (including an assessment of
impacts) and an Environmental Management Plan
(EMP) for the proposed project will be made
available for a 7-day public comment period.
Registered IAPs will be notified via e-mail of the
review period and the availability of the draft Scoping
(Combined Assessment) Report.
The final Report, along with all IAP comments, will
be submitted to the (Environmental Commissioner)
for their review and a final decision.
8. POTENTIAL IMPACTS
Potential environmental issues associated with
the construction of the dam include:
• Noise from the construction activities
could disturb animals in the immediate
surroundings of the activities.
• Refuelling of machinery/equipment/trucks
on site poses an environmental risk due to
potential hydrocarbon spills. Hydrocarbon
spillages could potentially contaminate the
soil and groundwater.
• Physical destruction and general
disturbance of local vegetation as a result
of the construction activities.
• A chance find procedure will be followed in
the case any archaeological remains are
found on site during construction.
4
Full Name
Organisation
Postal Address
Date
Telephone Number
Please Identify Your Interest in the Project:
…………………………………………………………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………………………………………….
Please write your Comments and Questions here:
……………………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………………………..........
………………………………………Signature:
Reg No. CC/2015/01895
P O Box 31908, Pionierspark, Windhoek, Namibia24 Barbet Road, Hochland Park, Windhoek
Cell: +264 81 803 5825Email: [email protected]
28 June 2021
INVITATION
RESIDENTS/FARMERS CLOSE TO THE PROPOSED CONSTRUCTION OF A DAM IN UUKANGA VILLAGE
Dear Residents/Farmers
The Iipumbu Ya Tshilongo Conservancy (hereinafter referred to as IYTC), intends on obtaining an
Environmental Clearance Certificate (ECC) for the construction of a dam with an increased water
carrying capacity, that will be used as a source of drinking water for various animals, such as Kudu,
Elephant, Springbok, Duiker, Oryx, Red Hartebeest, Ostrich, Eland, Spotted Hyena, Black Hyena, jackal,
Guinea Fowl, Lion, Kori Bustard, Secretary Bird, Zebra, Giraffe, Kudu and livestock such as cattle, goats
and sheep in the area.
Prior to the commencement of the proposed activities, an application for environmental clearance will
be submitted in terms of the Environmental Management Act, 7 of 2007 and Regulations 19 and 21 of
the EIA Regulations (January 2012) to the MET - Department of Environmental Affairs (DEA). I.N.K Enviro
Consultants cc (I.N.K), is an independent firm of environmental consultants and has been appointed by
the IYTC to manage the EIA process for the above-mentioned activities. It is against this background,that
you have been identified as a key stakeholder to the above-mentioned project. You are hereby invited
to attend a key stakeholders’ meeting as per the following:
Date: 3 July 2021
Venue: IYTC Main Offices,
Time: 11h00 – 13h00 / 15h00 – 17h00
Should you be unavailable to attend the meeting, a Background Information Document is available on
request from I.N.K – [email protected]
Reg No. CC/2015/01895
P O Box 31908, Pionierspark, Windhoek, Namibia24 Barbet Road, Hochland Park, Windhoek
Cell: +264 81 803 5825Email: [email protected]
Please let us know should you require any further information.
Yours Sincerely,
Immanuel N. Katali
Reg No. CC/2015/01895
P O Box 31908, Pionierspark, Windhoek, Namibia24 Barbet Road, Hochland Park, Windhoek
Cell: +264 81 803 5825Email: [email protected]
Issues and Response Report for the Public and Key Stakeholders Meeting conducted as per the following:
Date: 3 July
Time: 11h00
Venue: IYTC Main Office
ATTENDEES:
Name Organisation Contact
Immanuel Katali EAP - I.N.K Enviro Consultants cc +264818035825
Silas Iitengula Project Administrator - IYTC +264810445001
Simon Haufiku Farmer with Cattle Post +264816389799
Pax Fillipus Farmer with Cattle Post +264813598483
Sabianus Iiyambo Farmer with Cattle Post +264814917171
Johannes Philipus Farmer with Cattle Post +264812076886
Reg No. CC/2015/01895
P O Box 31908, Pionierspark, Windhoek, Namibia24 Barbet Road, Hochland Park, Windhoek
Cell: +264 81 803 5825Email: [email protected]
Comments/Issues and Relevant Reponses
Comment Comment By: Response
When will the construction start? Sabianus Iiyambo The construction will commence as soon as the environmental
clearance has been issued.
We have been suffering due to lack of water in the area.
Our cattle have to travel kilometres just for water points.
This project will provide us, the farmers with a lot of relief.
Thank you for coming to talk to us and we hope the
construction starts soon.
Simon Haufiku Thank you and noted.
Will this be the only dam or are there others to be
constructed in the future?
Johannes Philipus At this point, we are only focusing on one dam. However, there are
plans by the Ministry of Environment, Forestry and Tourism to establish
more points for future construction of dams in the area
We, thank you for coming to talk to us. Please do let us
know should you require any assistance from us and once
again, we really hope the construction commences as soon
as possible, before the rainy season.
Sabianus Iiyambo Noted.
SITE NOTICE
ENVIRONMENTAL IMPACT ASSESSMENT AND PUBLICPARTICIPATION PROCESS
The Iipumbu Ya Tshilongo Conservancy hereby gives notice to all the potentialInterested and Affected Parties (IAPs), that an application for an EnvironmentalClearance in accordance with the Environmental Management Act, 7 of 2007 andRegulations 19 and 21 of the Environmental Impact Assessment Regulations(January 2012) will be made as per the following:
Project and Applicant:The Iipumbu Ya Tshilongo Conservancy (IYTC)
Nature of the Proposed Activity:The Iipumbu Ya Tshilongo Conservancy (IYTC) intends on obtaining an
Environmental Clearance Certificate (ECC) for the construction of a dam with anincreased water carrying capacity, that will be used as a source of drinking water
for various wild animals in the area.
Location of the Proposed Activity:The project is proposed to be located in Uukanga Village in the Uuvudhiya
Constiituency. The proposed site is located approximately 7 km from the EtoshaNational Park boundary fence.
Independent Environmental Assessment Practitioner:I.N.K Enviro Consultants cc has been appointed by IYTC to undertake the EIA
process for the project. Please contact Mr. Immanuel Katali: P.O Box: 31908, Pionierspark, Windhoek.
Tel: +264 81 803 5825. E-mail: [email protected]
Registration to Receive Notifications and Information:Register as an Interested and Affected Party (IAP) with Immanuel Katali bysubmitting your comments, full name and contact details by post or email. A
Background Information Document (BID) is available for a review and commentperiod from 28 June to 21 July 2021. Electronic copies of the BID are available on
request from I.N.K as per above details.
Monday 28 June 20212 Market Watch
Sofia ChriStenSen
Africa is facing a vicious corona-virus resurgence,
with unprecedented hos-pital admissions and fa-talities pushing health fa-cilities to the brink as the continent falls far behind in the global vaccination drive.
With just under 5.3 million reported cases and around 139 000 deaths among its nearly 1.3 billion people, Africa is still the world’s least-affected continent after Oceania, according to an AFP tally.
So far African nations have been spared disas-ters comparable to Brazil or India.
But the pandemic is re-surging at an alarming rate in at least 12 coun-tries, with continental cases expected to hit a record peak in around three weeks.
“The third wave is picking up speed, spread-ing faster, hitting harder,” World Health Organisa-tion Africa director Mat-shidiso Moeti warned Thursday. “The latest surge threatens to be Af-rica’s worst yet”.
Africa Centres for Disease Control and Pre-vention (Africa CDC) di-rector John Nkengasong on Thursday described the third wave as “ex-tremely brutal” and “very devastating”.
And Liberia’s president George Weah has warned the wave is “far more alarming than a year ago” as hospitals overflow in his country.
Compounding Africa’s third wave are immunisa-
tion hitches, the spread of more transmissible virus variants and winter tem-peratures in the Southern Hemisphere.
The Delta variant, first
detected in India, has so far been reported in 14 African countries, making up the bulk of new cases in the Demo-cratic Republic of Congo and Uganda, according to the WHO.
Doctors in South Africa, which accounts for more than 35% of all cases re-corded on the continent, are struggling with an un-precedented influx of pa-
tients.Unlike past waves,
this time “the hospital system is not coping,” said doctors’ association chief Angelique Coetzee.
South Africa’s average new daily infections have increased 15-fold since early April, with hospital admissions rising around 60%.
Namibia and Zambia are also seeing steep in-
fection curves.Zambia’s health minis-
try has reported an “un-precedented” number of Covid-19 deaths piling pressure on mortuaries while Africa CDC said the country was “over-whelmed”.
With similar trends in Uganda, health minis-ter Jane Ruth Acheng blamed highly infec-tious variants for the new
spread, “different from the second wave” with a large number of young people hospitalised.
Uganda is one of the countries facing report-ed oxygen shortages, al-though Acheng denied civil society groups’ claim that the shortfall amounts to 24.5 million litres per day.
raCe aGainSt tiMeGovernments are again tightening restrictions, including a new nation-wide lockdown in Uganda and a tougher curfew in 13 Kenyan counties.
At the same time the pace of vaccinations is struggling to get off the ground.
According to the WHO, about one percent of the continent’s population is fully vaccinated - the lowest ratio globally - and 90% of African nations will miss a target to inoc-ulate a tenth of their pop-ulations by September.
“We are running a race behind time, the pan-demic is ahead of us. We are not winning in Africa this battle against the virus,” said Africa CDC’s Nkengasong.
“It’s frightening what is going on on the conti-nent,” he added.
‘Brutal’ third wave hits Africa as vaccination slowsCompounding Af-rica’s third wave are immunisation hitches, the spread of more transmis-sible virus variants and winter temper-atures in the South-ern Hemisphere.
The Delta variant, first detected in India, has so far been reported in 14 African countries. Photo NamPa/aP
At least 12 countries affected
DIAGNOSTIC RADIOLOGISTS
Applications are invited for the following vacancy
at NAMRAD, GOBABIS, Namibia
Diagnostic Radiographer position at Gobabis branch
Requirements:
• Diploma / Degree in Diagnostic Radiography • Proof of registration at HPCNA • Fluent in English • Must be computer-literate • Must be able to work independantly• Orientation and interview will be scheduled in Windhoek• Namibian citizen or permanent residence permit• Radiographer will reside in Gobabis permanently • Include the following with your application: ID/Passport, CV, HPCNA
registration and diploma / Degree in Diagnostic Radiology
Email: [email protected] shortlisted applicants will be contacted.
NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT AND
PUBLIC PARTICIPATION PROCESS
The Iipumbu Ya Tshilongo Conservancy hereby gives notice to all the potential Interested and
Affected Parties (IAPs), that an application for an Environmental Clearance in accordance with
the Environmental Management Act, 7 of 2007 and Regulations 19 and 21 of the Environmental
Impact Assessment Regulations (January 2012) will be made as per the following:
Project and Applicant: The Iipumbu Ya Tshilongo Conservancy’s (IYTC) Proposed Dam Nature and location of the Proposed Activity: The Iipumbu Ya Tshilongo Conservancy
(IYTC) intends on obtaining an ECC for the construction of a dam, that will be used as a source
of drinking water for various wild animals in the area. The project is proposed to be located in
Uukanga Village, located approximately 12 km from the Etosha National Park boundary fence.
Independent Environmental Assessment Practitioner: I.N.K Enviro Consultants cc has been appointed by IYTC to undertake the EIA process. Please contact Immanuel Katali: P.O Box: 31908, Windhoek. Tel: +264818035825. E-mail: [email protected] Notifications and Information: Register as an I&AP with Immanuel Katali. A Background
Information Document is available for a review and comment period - 28 June to 21 July 2021.
DIGITAL REPORT The Iipumbu Ya Tsilonngo Conservancy
REPORT COVERAGE DATES: 09/07/2021 Facebook Page(s): Republikein
11 231 TOTAL REACHED 41 TOTAL ENGAGEMENTS
1 TOTAL DAY(S)
STATS PER MONTH
AMOUNT OF DAYS ADVERT WAS ON
FacebookFacebook Page
TOTAL PEOPLE
REACHEDENGAGEMENTS
09/07/2021 Namibian Sun 11 231 41
SOURCE: Facebook
Report