avoided cost presentation at sb32 workshop on september ... · september 26th, 2011* * additional...

35
R.11-05-005 RMD/lil ATTACHMENT C F I L E D 10-13-11 04:26 PM

Upload: lamlien

Post on 18-Mar-2019

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

R.11-05-005 RMD/lil

ATTACHMENT C

F I L E D10-13-1104:26 PM

Page 2: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Workshop Discussion: Using Avoided Costs to Set SB32 Feed-in Tariffs

SB32 Workshop

September 26th, 2011*

* Additional Slide 28 Included Since Workshop

Page 3: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Agenda

Legislative direction on SB32 feed-in tariff

Framework for using avoided costs

‘Results’ from most recent avoided costs in CSI

Complexities of delivering the value to ratepayers

Proposal for discussion

2

Page 4: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Legislative Direction for Setting Feed-in Tariff Pricing for Renewables

(SB 2 1X): California Renewable Energy Resources Act amends provisions of the Public Utilities Code § 399.20(d) relating to price for generation

• Price no longer tied to the cost containment provision of the Renewables Portfolio Standard (RPS)

• Previously, pricing for electric generation under § 399.20 was tied to the Market Price Referent (MPR) – this connection to the MPR no longer applies

FIT based on avoided cost mechanism

• Supported by ratepayer indifference provision in SB 32 and § 399.20(e) of Public Utility Code

3

Page 5: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Framework for Using Avoided Costs

Feed-in tariff price to be based on avoided renewable purchases plus additional ratepayer value

Energy Division proposed approach is to set a base price from the Renewable Auction Mechanism (RAM)

• Provides a price for peaking as available, baseload, non-peaking as-available resources

• Projects of size 20MW or under, location is unconstrained

Additional avoided costs for feed-in tariff projects is set based on latest avoided costs

• Additional value based on ‘local’ resources

• Area-specific avoided costs

• Avoided cost components; transmission, distribution, losses

Feed-in Tariff Price = RAM + Avoided Costs

4

Page 6: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Definition of ‘Local’ Resource

Definition for purposes of calculating additional value to ratepayers

• Renewable generators connected to the distribution system and serving load on the distribution system to which they are connected

• Evaluated using a ‘no backflow’ proxy meaning the output is never greater than the minimum load on distribution system

Since the feed-in tariff avoided cost is based on being a ‘local’ resource, CPUC proposes to require SB32 projects to be ‘local’

• This won’t affect most projects that are 3MW or less

• Limits large generators connected to small distribution systems

5

Page 7: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

History of Avoided Costs in California

CPUC has used area- and time-specific avoided costs for valuing distributed resources since 2004

• Provides long-term hourly forecast of the cost of delivering a kWh by hour to a specific location for 30 years

• Locations have varied by climate zone

Current uses of area-specific avoided costs cover all distributed resources

• Energy efficiency cost-effectiveness

• Self-Generation Incentive Program cost-effectiveness

• California Solar Initiative cost-effectiveness

• Demand Response cost-effectiveness

6

Page 8: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Components of Avoided Costs

Energy

Generation Capacity

Ancillary Services

CO2, NOx, PM10 reductions

Transmission Capacity

Distribution Capacity

Losses

These are provided by RAM projects as well, so are not additional value.

‘Local’ resources provided these values in addition to RAM projects.

7

Page 9: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Most Recent Update to Avoided Costs

E3 is near completion of a study of ‘local’ PV

• Expected release in 4th Quarter 2011

Avoided costs reflect most recent information

Updates include

• Most recent distribution capital expansion plans from utilities (however, vintage is still up to 3 years old)

• Updated transmission marginal cost

Higher granularity on area differentiation

• Distribution planning area rather than climate zone

8

Page 10: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Data Sources for Distribution Cost

Capital budget plans and load growth provided by each IOU in response to CPUC data request

• Capital budget plans isolated to load growth driven investments

• Load growth by area provided in data request

Defining “Distribution Areas”

• SCE defined by SYS ID areas; broader than other IOUs

• PG&E defined by DPAs

• SDG&E by distribution substation

Adjustments for Capital Budget Horizon

• PG&E and SDG&E 4-year capital plans are adjusted to reflect longer horizons, assuming investments recur after 15 years in calculating avoided distribution value

• SCE provided 9 year capital budget plans and no adjustment is being made to those

9

Page 11: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Distribution Avoided Costs

0

50

100

150

200

250

300

350

400

450

Dis

trib

uti

on

Avo

ide

d C

ost

($

/kW

-yr)

PGE

SCE

SDGE

Distribution Avoided Costs by Planning Area ($/kW-year):

10

Page 12: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Transmission and Losses

Network transmission similarly based on growth driven projects. Broader regional value

Losses based on avoided cost estimates by utility

TOU Description PG&E SCE SDG&E

1 Summer Peak 1.109 1.084 1.081

2 Summer Shoulder 1.073 1.080 1.077

3 Summer Off-Peak 1.057 1.073 1.068

4 Winter Peak - - 1.083

5 Winter Shoulder 1.090 1.077 1.076

6 Winter Off-Peak 1.061 1.070 1.068

Transmission Capacity Value

$/kW-year

PG&E 19.29$

SCE 22.93$

SDG&E 20.66$

11

Page 13: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Calculating the Local Value by Distribution Area for each IOU

Peaking As-available

• Use simulated photovoltaic output for each substation

• Compute average avoided cost for T, D, and Losses

Baseload

• Use flat 8760 profile output

• Compute average avoided cost for T, D, and Losses

Non-peaking As-available

• Use flat 8760 profile output

• Multiply T by 20% NQC, remove D, and losses

12

Page 14: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Example: Avoided Cost Breakdown for an example SCE location

0

0.01

0.02

0.03

0.04

0.05

0.06

0.07

0.08

0.09

Peaking as Available Baseload Non-peaking as Available

$/k

Wh Losses

Transmission

Distribution

13

Page 15: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

COMPLEXITIES OF DELIVERING VALUE TO RATEPAYERS

Page 16: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Challenges of Capturing Value

Distribution

• Majority of avoided cost is distribution capacity savings resulting from deferral of distribution system investments.

• Most challenging to capture because of area-dependent nature and integration with distribution planning process

Transmission

• Transmission avoided cost is lower, and location is less important

Losses

• Least challenging to capture

15

Page 17: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Distribution Planning Process

Load forecast of growth in an area

• Local area load forecast shows need for capacity expansion, or upgrades to meet reliability criteria

Develop distribution upgrade

• Preferred alternative is developed to solve the problem, minimum lifecycle revenue requirement

Establish capital budgeting plan

• Expected projects are compiled into a capital budgeting plan. Period of the plan depends on the utility, typically 5 to 10 years

16

Page 18: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Illustrative Project

17

Peak Load

Years

Capacity Limit

Load Growth Forecast

Project Cost

New Capacity Limit

$10M

Years

Page 19: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Illustrative Project

18

Peak Load

Years

Capacity Limit

Load Growth Forecast

Project Cost

New Capacity Limit

Capacity Limit

$10M 2 year deferral

5MW Load Reduction

Capacity Limit

Page 20: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

What Was Saved?

Original PV of revenue requirement (PVRR)

• $10 million

Deferred PV of revenue requirement (PVRR)

• $9 million

Savings of approximately

• $1 million

• $200/kW

• $10/kW-year for 20 years

19

(1+ 2%)^2

(1+ 7.5%)^2 = $10 million *

Assumptions: Inflation = 2%, WACC = 7.5%

= $1 million / 5,000kW

= $200/kW amortized over 20 years

Page 21: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

How does marginal compare with actual savings?

20

Dec

reas

e in

R

even

ue R

equi

rem

ent

MW Reduction

Marginal Value = $10/kW-year

• Actual value is “lumpy”

• Decreasing value with further deferrals

Page 22: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

What is Needed to Capture Value?

Distribution engineer feels confident in reliability when they actually delay the investment decision

• Sufficient peak load is reduced to defer the investment

• Utility planning process accommodates embedded load

21

Page 23: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Additional Considerations

Utility capital plans are continually updating, as are the load forecasts

• Vintage of the data in our analysis is up to 3 years old

Utility capital plans have shorter durations than the life of the renewable DG

22

Page 24: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

PROPOSED APPROACH

Page 25: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Proposed Approach

Most recent avoided cost data sets the level of the additional value

• ‘Hot’ spots have one value

• Other areas have another

Utilities choose areas where FIT DG would be most beneficial to the distribution system

• Areas are locked in for 3 to 5 years

• Areas must encompass at least 5-10% of load depending on utility needs

• Additional areas can be designated at any time

24

Page 26: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Avoided Cost – Peaking as Available

0.00

0.02

0.04

0.06

0.08

0.10

0.12

0.14

0.16

0.18

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Avo

ide

d C

ost

$/k

Wh

% of Peak Load MW

SCE

PG&E

SDG&E

25

Page 27: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Average Avoided Cost – Peaking as Available

Note: Non-averaged avoided costs shown as semi-transparent line for comparison

0.00

0.02

0.04

0.06

0.08

0.10

0.12

0.14

0.16

0.18

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Ave

rage

Avo

ide

d C

ost

$/k

Wh

% of Peak Load MW

SCE

PG&E

SDG&E

Percent of

Territory

Hot Spot

Value $/kWh

Non-Hotspot

Value $/kWh

SCE 10% 0.0775$ 0.0200$

PG&E 5% 0.0350$ 0.0175$

SDG&E 5% 0.0225$ 0.0100$

26

Page 28: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Location of Hot Spots from Avoided Cost Data*

Share of Load Represented SCE 10% of load PG&E 5% of load SDG&E 5% of load

* Proposal is that each utility identify the ‘hot spots’ in their service territory

PG&E

SCE

SDG&E

27

Page 29: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

PV Site Potential in Hot Spots

Screen of raw site potential for PV in the hot spots

• Residential roofs based on land use designated residential

• Commercial roofs based on satellite imagery (Black & Veatch)

• Ground sites based on RETI analysis (Black and Veatch)

• Other resources could potentially locate in hot spots, but the technical potential data was not available to perform the analysis

MW Residential Roof Commercial Roof Ground Total

SCE 1962 423 721 3106

SDGE 231 0 200 431

PGE 1286 37 2454 3777

Total 3479 460 3375 7314

Hot Spot Nameplate Potential Based on Available Sites (MW)*

* Raw site potential, not adjusted for interconnection limits

Additional Slide NOT Presented at Workshop 28

Page 30: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Avoided Cost - Baseload

0.00

0.01

0.02

0.03

0.04

0.05

0.06

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Avo

ide

d C

ost

$/k

Wh

% of Peak Load MW

SCE

PGE&E

SDG&E

29

Page 31: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

0.00

0.01

0.02

0.03

0.04

0.05

0.06

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Ave

rage

Avo

ide

d C

ost

$/k

Wh

% of Peak Load MW

SCE

PGE&E

SDG&E

Average Avoided Cost - Baseload

Note: Non-averaged avoided costs shown as semi-transparent line for comparison

Percent of

Territory

Hot Spot

Value $/kWh

Non-Hotspot

Value $/kWh

SCE 10% 0.0375$ 0.0125$

PG&E 5% 0.0150$ 0.0100$

SDG&E 5% 0.0125$ 0.0075$

30

Page 32: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Avoided Cost – Non Peaking as Available

0.000

0.001

0.002

0.003

0.004

0.005

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Avo

ide

d C

ost

$/k

Wh

% of Peak Load MW

SCE

SDG&E

PG&E

31

Page 33: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

0.000

0.001

0.002

0.003

0.004

0.005

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Ave

rage

Avo

ide

d C

ost

$/k

Wh

% of Peak Load MW

SCE

SDG&E

PG&E

Average Avoided Cost – Non Peaking as Available

Note: Non-averaged avoided costs shown as semi-transparent line for comparison

Percent of

Territory

Hot Spot

Value $/kWh

Non-Hotspot

Value $/kWh

SCE 10% 0.0050$ 0.0050$

PG&E 5% 0.0050$ 0.0050$

SDG&E 5% 0.0050$ 0.0050$

32

Page 34: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

Thank You!

Contact Information Snuller Price, Partner Energy and Environmental Economics, Inc. (415)391-5100 [email protected]

Page 35: Avoided Cost Presentation at SB32 Workshop on September ... · September 26th, 2011* * Additional Slide 28 Included Since Workshop . Agenda ... Most Recent Update to Avoided Costs

R.11-05-005 RMD/lil

(END OF ATTACHMENT C)