    Software Project Management PlanSixSigma, 20

    th

    August, 2012 SPMP -1.0

    P j t M

    Project Team:

    Emily Maguire, 0608170

    Laura Unsworth, 0611093Crista Cullen, 0535368

    Anne Panter, 0610024

    Hannah Macleod, 0590077

    Mark Knowles, 0608715

    Jamie Dwyer, 0608896

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    2/67

    Table of Contents

    Table of Contents...2List of Figures ....................................................................................................................... 4

    List of Tables ........................................................................................................................ 4

    Definitions ............................................................................................................................ 5

    1) Introduction and Objectives of the Project Plan ................................................................. 6

    1.1 Overview of the Organization ...................................................................................... 6

    1.2 Current Situation and Problem/ Opportunity Statement................................................ 61.3 Project Objectives........................................................................................................ 7

    2) Project .............................................................................................................................. 7

    2.1 Project Information ...................................................................................................... 7

    2.2 Project objectives ........................................................................................................ 7

    2.3 Project approach .......................................................................................................... 8

    2.4 Roles and Responsibilities ........................................................................................... 82.5 Project Constraints ...................................................................................................... 9

    2.6 Assumptions .............................................................................................................. 10

    2.7 Preliminary Schedule and Budget Estimates .............................................................. 10

    2.8 Plan Modification Rules ............................................................................................ 11

    2.9 Approval Signatures .................................................................................................. 11

    3) Project Scope Management plan ..................................................................................... 12

    3.1 Product description .................................................................................................... 12

    3.2 Project Deliverables................................................................................................... 12

    3.3 Scope Statement ........................................................................................................ 13

    3.4 Work Breakdown Structure Development .................................................................. 14

    3.5 Scope Change Management Process .......................................................................... 25

    3.5 Plan Modification Rules ............................................................................................ 27

    4) Schedule management plan ............................................................................................. 28

    4.1 Project Schedule ........................................................................................................ 28

    4.2 Assumptions .............................................................................................................. 29

    5) Cost Management Plan ................................................................................................... 29

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    3/67

    6.4 Quality Assurance ..................................................................................................... 34

    6.5 Quality Control .......................................................................................................... 37

    7) Risk Management ........................................................................................................... 39

    7.1 Risk Management Strategies ...................................................................................... 39

    7.2 Risk Management Tools ............................................................................................ 41

    7.3 Data Sources ............................................................................................................. 41

    7.4 Risk Categories ......................................................................................................... 42

    7.5 Risk Probability and Impact....................................................................................... 42

    8) HR management plan ...................................................................................................... 438.1 Project Organization .................................................................................................. 43

    8.1.1.1 Hierarchy of the project team ........................................................................... 44

    8.2 Resource Requirements ............................................................................................. 47

    8.3 Resource Assignment ................................................................................................ 47

    9) Communication plan ....................................................................................................... 50

    9.1 Stakeholder Analysis ................................................................................................. 509.2 Project Reports .......................................................................................................... 50

    9.3 Project Meetings ........................................................................................................ 51

    9.4 Project Information Accessibility ............................................................................... 51

    9.5 Communications Summary ........................................................................................ 52

    Reference List ..................................................................................................................... 54

    Appendices ......................................................................................................................... 55Appendix A: Generic Cost Estimate Classification Matrix .............................................. 55

    Appendix B: Project Budget ............................................................................................ 56

    Appendix C: Risk Categorization Table ..................................................................... 58-59

    Appendix D: Detailed Gantt Chart .............................................................................. 58-59

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    4/67

    List of Figures

    Figure 1: Hierarchy of the project team ............................................................................... 44Figure 2: Resource Allocation ............................................................................................. 47

    List of Tables

    Table 1 Project Approach ..................................................................................................08Table 2 Roles & Responsibilities .................................................................................. 08-09

    Table 3 Preliminary Project Schedule ............................................................................... 10Table 4 Preliminary Project Expenditures ......................................................................... 11Table 5 Project Deliverables ........................................................................................ 12-13Table 6 Level 2 WBS .................................................................................................. 16-25Table 7 Roles and Responsibilities Scope Change Management Process ....................... 26Table 8 Project Schedule .................................................................................................. 28Table 9 Summarized Budget ............................................................................................29Table 10 Quality Standards .............................................................................................. 31

    Table 11 Quality Metrics ..................................................................................................32Table 12 Quality Management Approach .................................................................... 33-34Table 13 Quality Assurance......................................................................................... 34-36Table 14 Quality Control ............................................................................................. 37-38Table 15 Risk Management Strategies ......................................................................... 39-41Table 16 Risk Management Tools .................................................................................... 41Table 17 Data Sources ................................................................................................. 41-42Table 18 Risk Probability ................................................................................................. 42Table 19 Project Team ..................................................................................................... 43Table 20 Key Stakeholders .......................................................................................... 45-46Table 21 Resource Assignment ...................................................................................47-50Table 22 Project Reports........50Table 23 Project Meetings ................................................................................................ 51Table 24 Communication Summary ............................................................................ 52-53

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    5/67

    Definitions

    Term Definition

    AD Architectural Design

    ADD Architectural Design Document

    ATP Acceptance Test Plan

    DD Detailed Design

    SDS Software Design DocumentITP Integration Test Plan

    SCMP Software Configuration Management Plan

    SM Senior Management

    SPMP Software Project Management Plan

    SQAP Software Quality Assurance Plan

    SR Software Requirements

    SRD Software Requirements DocumentSTD Software Transfer Document

    STP Software Test Plan

    SUM Software User Manual

    SVVP Software Verification and Validation Plan

    UR User Requirements

    URD User Requirements Document

    UTP Unit Test PlanVV Verification & Validation

    WBS Work Breakdown Structure

    WBS Level 2 WBS, where tasks are sub divided at most into 2 sub tasks

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    6/67

    1) Introduction and Objectives of the Project Plan

    1.1 Overview of the Organization

    South East Gippsland University is a prestigious university in Australia. The South EastGippsland Student Management System Project is to provide a state of the art system tosupport the universities endeavours, teaching and research.

    This project is attempting to revolutionize the service delivery to key stakeholders and fosterexcellence in teaching, research, and public service that will establish the University as a

    leader among the nation's major research universities. This project will consolidate ITInfrastructure. Importantly it will:

    Enable new voice and data applications to support the University's mission.

    Provide a robust, flexible, ways of communication between students and theuniversity to meet the communications needs of our instructional faculty, researchers,and students.

    Upgrade aging technology infrastructure and support the organization.

    1.2 Current Situation and Problem/ Opportunity Statement

    South East Gippsland University needs to replace its aging student management systems. Itruns on old technology, difficult and expensive to maintain, and does not provide theflexibility and services needed in a modern academic organization.

    Implementing an appropriate replacement presents an opportunity to integrate newtechnology such as SMS communication with students (ie. for the delivery of results), anduse of social media (such as Facebook, YouTube and Twitter). This new integration increasesthe overall ability of students to communicate with the university and to facilitate thecommunication and feedback with students.

    The ASMS Project will modernize the student management services and infrastructure at

    South East Gippsland University. In order to achieve that target University will implement astate-of-the-art web based system to provide a higher level of service at lower cost forUniversity customers. The system will integrate the use of SMS and other social mediatechnology with the student management system.

    The University's strategy is to replace all of its obsolete student management systems (student

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    7/67

    1.3 Project Objectives

    Here are some target benefits that will be accomplished by the Gippsland University afterimplementing the new integrated system.

    A modern, state-of-the-art student management system. Integration with othertechnologies and applications.

    Improved services for all staff and students (e.g., more streamlined processes formanagement of student enrolments, and results publications).

    Quicker and more responsive action on new and change service requests andtroubleshooting.

    Simplified billing.

    No increase in rates or charges for students.

    A more dependable, robust and secure network.

    2) Project

    2.1 Project Information

    Project Start Date 1st of June 2012

    Project End Date 2n of May 2015Project Manager Beth Storry

    Project Sponsor Information Technology Services (ITS),South East Gippsland University

    2.2 Project objectives

    Accomplish project within defined budget. Accomplish project phases within relevant time parameters.

    Deliver a Software Program which meets the organizational goals.

    Deliver Proper Project Documentations. Feasibility Analysis. System Requirement Specification.

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    8/67

    Table 1 Project Approach

    Deliver Software documentation. End user manual. Installation documentation.

    2.3 Project approach

    2.4 Roles and Responsibilities

    Name Role Phone Email Address

    Project Approach Phases Description

    Project Initiation All the project initiation approaches suchas allocating resources, establishing

    environmentProject Planning Developing the project plans and

    preparing the final Software ManagementProject Plan

    Project Execution Under project execution process theresseveral sub processes. Those should haverun as a parallel processes throughoutproject execution phase.

    Requirement Identification System Design

    Implementation

    Verification & Validation

    Project Monitoring & Control

    Documentation Development

    Training

    Installation In the installation phase all the hardwareand software systems installed.

    Operation and Support Support for further operations of thesystem and required support for thesystem and staff.

    Maintenance Maintain the system

    Project Closure Finalize and end the project

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    9/67

    Table 2 Roles & Responsibilities

    Anne Panter Configuration Manager 0724526264 [email protected]

    Hannah Macleod Quality Analyst 0712730729 [email protected]

    Mark Knowles Database Engineer 0723424233 [email protected]

    Jamie Dwyer Software Designer 0772323097 [email protected]

    Liam de Young Validation Engineer 0782382327 [email protected]

    Simon Orchard Verification Engineer 0712468075 [email protected]

    Glenn Turner Consultant 0771245769 [email protected]

    Chris Ciriello Installation Specialist 0729434740 [email protected]

    Technical Writer 0783232394 [email protected]

    Russell Ford Training Specialist 0773292928 [email protected]

    Eddie Ockenden Help Desk Level 1 0718373427 [email protected]

    Peter Samuels Human ResourceManager

    0715879564 [email protected]

    2.5 Project Constraints

    Scope:

    The solution is covering wide area we have to consider number of variables

    when making the decisions

    Time Schedule:

    Project requires to be implemented within 24 months or less time frame andthe existing services have to be maintained continuously

    Quality:

    Delivered software should be a highly robust system. Because system will beused for very critical and sensitive processing such as student marks releasing,etc.

    Budget Constraints:

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    10/67

    2.6 Assumptions

    Project Funding:Funding sources for the project will stably remain during the project execution time.

    Hardware Facilities:All the hardware needed for the project will be provided and newly purchased. Therefor the according to the Australian law up to minimum 5 years manufacturers have toprovide insurance and maintain expenses have to bare.

    Situational Changes:The Project Plan may change as new information and issues are revealed.

    Project Budget:Upon the agreement we have agreed to calculate the profit based on the initial budgetup to 10%. Any change beyond that limit will be considered as the new base for theprofit calculation.

    2.7 Preliminary Schedule and Budget Estimates

    Schedule Estimated Duration (days)

    Project Initiation 150

    Project Monitoring &Control

    650

    Configuration Management 70

    Software QualityManagement

    150

    System Allocation 20

    Requirement 60

    Design 180

    Verification & Validation 350

    Documentation Development 80

    Training 270

    Implementation 210

    Installation 150

    Operation & Support 21

    Maintenance 7

    Table 3 Preliminary Project Schedule

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    11/67

    Table 4 Preliminary Project Expenditures

    2.8 Plan Modification Rules

    Theres several modification rules applied in this project.

    General Modifications

    All the general modifications which modification is independent from another area of theplan can be requested to modify via the project manager. Project manager is responsiblefor reviewing the requested modification and accept or decline the modification. And ifmodification accepted project manager responsible for inform the relevant stake holdersaffected by that modification.

    Critical Modifications

    Critical modifications such as critical paths, labor rates, schedules and other budgets thatare more likely to affect other areas by its modification in the project plan. This kind ofmodification also should be requested through project manager. After reviewing themodification, if manager feels that its a critical modification, Project manager shouldcall a meeting consists of relevant stakeholders and review further about the

    modification. The modification decision will made according to the meeting conclusion.If any modification done in the project plan, project manager is responsible for informthe stake holders of the project.

    2.9 Approval Signatures

    Project Manager:

    Project Expenditures

    EstimatedCost (USD)

    Employee Cost 3,000,000.00

    Rent Fee 80,000.00

    Insurance Cost 7,000.00

    Software Cost 1,000,000.00

    Hardware Cost 100,000.00

    Administrative Cost 30,000.00

    Legal Consultation 120,000.00

    Total Cost 3,337,000.00

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    12/67

    3) Project Scope Management plan

    3.1 Product description

    South East Gippsland Universitys SMS (Student Management System) runs on old

    technology, difficult and expensive to maintain, and does not provide the flexibility and

    services needed in a modern academic organization. Implementing an appropriate

    replacement presents an opportunity to integrate new technology such as SMS

    communication with students (i.e. for the delivery of results), and use of social media (such

    as Facebook, YouTube and Twitter). It increases the overall ability of students to

    communicate with the university and to facilitate the communication and feedback with

    students.

    The existing student management suite: Cannot utilize cost-effective new technology such as SMS and other social media.

    Cannot be effectively maintained due to a scarcity of trained systems developers due

    to the age of the system and the compartmentalised nature of previous enhancements

    of the systems.

    The new implementation will provide: A modern, state-of-the-art student management system. Integration with other

    technologies and applications.

    Improved services for all staff and students. (e.g., more streamlined processes for

    management of student enrolments, and results publications)

    Quicker and more responsive action on new and change service requests and

    troubleshooting.

    Simplified billing.

    No increase in rates or charges for students.

    A more dependable, robust and secure network.

    3.2 Project Deliverables

    Phase Deliverables To whom Format

    UR URD

    ATP

    SM / Customer

    SM / Customer

    Paper and electronic form

    Paper and electronic form

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    13/67

    Table 5 Project Deliverables

    SR SRD

    STP

    SM / Customer

    SM / Customer

    Paper and electronic form

    Paper and electronic form

    AD ADD

    ITP

    SM / Customer

    SM / Customer

    Paper and electronic form

    Paper and electronic form

    DD DDD

    UTP

    SUM

    STD

    Source code

    SM / Customer

    SM / Customer

    Paper and electronic form

    Paper and electronic form

    Paper and electronic form

    Paper and electronic form

    Electronic form

    3.3 Scope Statement

    Project Title: Automated Student Management System (ASMS)

    Date: 20th June 2012

    Prepared by: Beth Storry, Project Manager, [email protected]

    Project Justification: South East Gippsland University, requested this project be done toassist the university in meeting its strategic goals. This new system will increase visibility of

    the university members as it will integrate new technology such as SMS (i.e. for the delivery

    of results) and social media (such as Facebook, YouTube and Twitter). It will also help

    improve profitability by reducing internal costs by providing standard tools and techniques.

    Product-related deliverables within the scope (Includes)

    a) Survey current consultants, university members and business case sponsor to help

    determine desired content and features for the new student management system.

    b) Evaluation of the requirements for the new system Desired content and features for the

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    14/67

    d) Training sessions will be launched by the team for the university staff and other members.

    All the training materials will be provided by the team except IT infrastructure.

    e) A test plan will be documented how the site will be tested, who will do the testing, andhow bugs will be reported.

    f) Full documentation of the system will be provided at the documentation phase. This will

    be useful for the university in their future extensions.

    g) Hardware and software installation will be done by the development team.

    h)

    Project beneficial measurement plan will be prepared in order to measure the financialvalue of the system.

    i) IT help/service desk (both pre and post) will be provided by the development company.

    j) Maintenance will be provided for the system for 21 days of time free of charge. Further

    maintenance will be done under an added cost.

    Excludes

    a) Space for the system establishment should be provided by the university. Rent fee will be

    paid by the development company according to the Australian rate.

    b) Air-conditioning for the system establishment will be provided by the university.

    c) New servers, wireless broadband hardware and software will be accommodated by theuniversity.

    Project Success Criteria: Our goal is to complete this project within 2 years between

    $3,500,000/= and $4,000,000/=. The project sponsor, South East Gippsland University, has

    emphasized the importance of the project paying for itself within one year after the site is

    completed. If the project takes a little longer to complete or costs a little more than planned, it

    will still be viewed as a success if it has a good payback and helps promote our companys

    image as a world class consulting organization.

    3.4 Work Breakdown Structure Development

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    15/67

    Project Manager, Software Architect, Programmer, Requirements Analyst, Configuration

    Manager, Quality Analyst, Database Engineer, Software Designer, Verification & Validation

    Engineer, Consultants, Technical writers, Installation Specialists, Human Resource Manager

    and Programmers engaged in developing the WBS.

    Note: Level 2 WBS structure is positioned here and the detailed WBS structure will be on the

    Gant chart at the appendices.

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    16/67

    ID SubID

    Task Name Sub Task 1 Sub Task 2 ResourceName

    Duration

    1 1 Project

    Initiation2 1.1 Selecting right

    process model5 days

    3 1.1.1 Analyze currentsituation &problem

    ProjectManager

    2 days

    4 1.1.2 Identifyingobjective for the

    project

    ProjectManager

    1 day

    5 1.1.3 Identifying projectcharacteristics

    ProjectManager

    1 day

    6 1.1.4 Selecting the idealprocess model

    ProjectManager

    1 day

    7 1.2 Allocatingproject resources

    60 days

    8 1.2.1 Identify staffing

    requirements

    Project

    Manager, HRManager

    5 days

    9 1.2.2 identify the assets ProjectManager

    10 days

    10 1.3 Establish projectenvironment

    60 days

    11 1.3.1 Identify & acquireequipments and

    tools for theproject

    ProjectManager

    30 days

    12 1.3.2 Installation,operation &maintenancemanual for theproject

    ProjectManager

    7 days

    13 1.3.3 Based on the

    requirement createa communicationplan

    Project

    Manager, HRManager

    8 days

    14 1.3.4 Establish adocumentationrepository

    ProjectManager

    1 day

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    17/67

    Programmer

    18 1.4.2 Create SPMP subplans

    ProjectManager,RequirementsAnalyst,Programmer,Softwarearchitect, HRManager

    60 days

    26 1.4.3 Assemble baselineSPMP document

    ProjectManager

    4 days

    27 1.4.4 Baseline SPMPcompleted

    0 days

    28 1.4.5 Create schedulebaseline

    ProjectManager

    2 days

    29 1.4.6 Finalize projectcharter

    120 days

    30 2 ProjectMonitoring &

    Control

    650days?

    31 2.1 Start the project 1 day

    32 2.2 Analyze risks ProjectManager

    10 days

    33 2.3 Createcontingency plan

    ProjectManager

    10 days

    34 2.4 Manage theproject

    450 days

    35 2.4.1 Project teammeetings

    ProjectManager, HRManager

    100 days

    36 2.4.2 Retain records ProjectManager

    30 days

    37 2.4.3 Maintain projectcharter

    ProjectManager

    400 days

    38 2.4.4 SPMP document

    updates

    Project

    Manager

    450 days

    39 2.3 All projectdeliverables havebeen delivered

    0 days

    40 2.4 project closeout 0 days

    41 3 Configuration 70 days

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    18/67

    Identification

    44 3.3 Configurationplan finalization

    ConfigurationManager

    10 days

    45 3.4 SCMPcompleted

    0 days

    46 3.5 ConfigurationControl

    ConfigurationManager

    20 days

    47 3.6 ConfigurationAuditing/Reporting

    ConfigurationManager

    20 days

    48 4 Software

    QualityManagement

    150

    days?

    49 4.1 Plan softwarequalitymanagement

    QualityAnalyst

    2 days

    50 4.2 Create SoftwareQualityAssurance Plan

    (SQAP)

    QualityAnalyst

    25 days

    51 4.3 SQAP completed QualityAnalyst

    0 days

    52 4.4 Define indicators QualityAnalyst

    20 days

    53 4.5 Manage softwarequality

    QualityAnalyst

    100 days

    54 4.6 Identify quality

    improvementneeds

    Quality

    Analyst

    10 days

    55 5 SystemAllocation

    20 days

    56 5.1 Analyzingsystem functions

    SoftwareArchitect

    5 days

    57 5.2 Develop SystemArchitecture

    SoftwareArchitect

    10 days

    58 5.2.1 IdentifyHardware/Software functions

    5 days

    59 5.3 Decomposesystemrequirements

    SoftwareArchitect

    5 days

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    19/67

    develop softwarerequirements

    Analyst

    64 6.2 Define interface

    requirements

    10 days

    65 6.2.1 Define ASMSsoftware interfacerequirements

    RequirementsAnalyst

    5 days

    66 6.2.2 Define ASMShardware interfacerequirements

    RequirementsAnalyst

    5 days

    67 6.2.3 Define ASMS user

    interfacerequirements

    Requirements

    Analyst

    5 days

    68 6.3 Prioritize andintegraterequirements

    20 days

    69 Prioritize andintegrate softwarerequirements

    RequirementsAnalyst

    5 days

    70 Prioritize andintegrate hardwarerequirements

    RequirementsAnalyst

    5 days

    71 Prioritize andintegrate allrequirements

    RequirementsAnalyst

    10 days

    72 6.4 Create SoftwareRequirement

    Specification(SRS)

    RequirementsAnalyst

    7 days

    73 6.5 SRS Completed 0 days

    74 7 Design 180days?

    75 7.1 Perform thearchitecturaldesign of the

    system

    40 days

    76 7.1.1 Design thearchitecture of theintegrated system

    SoftwareArchitect

    20 days

    77 7.1.2 Design thesoftware internal

    SoftwareArchitect

    20 days

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    20/67

    central databasesystem

    81 7.2.3 Provide weekly

    updates

    Database

    Engineer

    4 days

    82 7.3 Design interfaces 50 days

    83 7.3.1 Design userinterfaces

    15 days

    88 7.3.2 Design softwareinterfaces

    SoftwareDesigner

    10 days

    89 7.3.3 Design hardware-software interfaces

    SoftwareDesigner

    10 days

    90 7.4 SelectAlgorithms

    SoftwareDesigner

    10 days

    91 7.5 Detail Design 80 days

    92 7.5.1 Detail designsoftware interfaces

    SoftwareDesigner

    20 days

    93 7.5.2 Detail design userinterfaces

    SoftwareDesigner

    20 days

    94 7.5.3 Detail design

    admin interfaces

    Software

    Designer

    20 days

    95 7.5.4 Create Softwaredesignspecification(SDS)

    SoftwareDesigner

    20 days

    96 7.5.5 SDS completed 0 days

    97 8 Verification &Validation

    350days?

    98 8.1 Plan verification

    and validation

    250 days

    99 8.1.1 Plan requirementsverification andvalidation

    Verification,ValidationEngineer andConsultant

    15 days

    100 8.1.2 Plan architectureverification andvalidation

    Verification,ValidationEngineer and

    Consultant

    15 days

    101 8.1.3 Plan interfacedesign verificationand validation

    Verification,ValidationEngineer andConsultant

    15 days

    102 8 1 4 Plan database Verification 15 days

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    21/67

    104 8.1.6 SVVP completed 0 days

    105 8.2 Executeverification and

    validation tasks

    120 days

    106 8.2.1 Verifyrequirements

    VerificationEngineer

    10 days

    107 8.2.2 Validaterequirements

    VerificationEngineer

    10 days

    108 8.2.3 Verify architecture VerificationEngineer

    10 days

    109 8.2.4 Validate

    architecture

    Verification

    Engineer

    10 days

    110 8.2.5 Verify interfacedesign

    VerificationEngineer

    10 days

    111 8.2.6 Validate interfacedesign

    VerificationEngineer

    10 days

    112 8.2.7 Verify databasedesign

    VerificationEngineer

    10 days

    113 8.2.8 Validate database

    design

    Verification

    Engineer

    10 days

    114 8.3 Requirements &Design V&Vcompleted

    0 days

    115 8.4 Plan testing 120 days

    116 8.4.1 Plan interfaceblack box testing

    VerificationEngineer

    8 days

    117 8.4.2 Plan end User test Verification

    Engineer

    4 days

    118 8.4.3 Plan admin panelinterface blackbox test

    VerificationEngineer

    15 days

    119 8.4.4 Create SoftwareTest Plan (STP)

    VerificationEngineer

    10 days

    120 8.4.5 STP completed 0 days

    121 8.5 Develop test

    requirements

    40 days

    122 8.5.1 Design interfaceblack box testing

    VerificationEngineer

    10 days

    123 8.5.2 Design end Usertest

    VerificationEngineer

    10 days

    124 8 5 3 Design admin Verification 10 days

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    22/67

    128 8.6.3 Execute adminpanel interfaceblack box test

    VerificationEngineer

    5 days

    129 8.7 V&V completed 0 days130 9 Documentation

    development80 days

    131 9.1 Plandocumentation

    80 days

    132 9.1.1 Define installationdocumentationcontents

    TechnicalWriter

    10 days

    133 9.1.2 Define ASMSsoftwaredocumentationcontents

    TechnicalWriter

    10 days

    134 9.1.3 Createdocumentationplan

    TechnicalWriter

    10 days

    135 9.2 Implement

    documentation

    40 days

    136 9.2.1 Write installationdocumentation

    TechnicalWriter,InstallationSpecialist

    10 days

    137 9.2.2 Write ASMSdocumentation

    TechnicalWriter,Consultant

    10 days

    138 9.3 Produce anddistributedocumentation

    30 days

    139 9.3.1 Print installationdocumentation

    Help DeskLevel 1

    2 days

    140 9.3.2 Print ASMSsoftwaredocumentation

    Help DeskLevel 2

    2 days

    141 9.3.3 Distributeinstallationdocumentation toinstallers

    ProjectManager

    5 days

    142 9.4 Documentationcompleted

    0 days

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    23/67

    147 10.1.3 Plan softwaremaintenancetraining content

    TrainingSpecialist

    10 days

    148 10.2 Develop trainingmaterials

    240 days

    149 10.2.1 Create installationtraining content

    TrainingSpecialist

    10 days

    150 10.2.2 Create systemtraining materials

    TrainingSpecialist

    10 days

    10.2.3 Create softwaremaintenance

    training materials

    TrainingSpecialist

    10 days

    10.3 Validate trainingprogram

    240 days

    10.3.1 Validateinstallationtraining content

    TrainingSpecialist

    2 days

    10.3.2 Validate systemtraining materials

    TrainingSpecialist

    2 days

    151 10.3.3 Validate softwaremaintenancetraining

    TrainingSpecialist

    2 days

    152 10.4 Implement thetraining program

    240 days

    153 10.4.1 Hold trainingsession for endusers

    TrainingSpecialist

    10 days

    154 10.4.2 Hold trainingsession forsoftwaremaintenance team

    TrainingSpecialist

    20 days

    155 10.4 Trainingcompleted

    0 days

    156 11 Implementation 210days?

    157 11.1 Create test data VerificationEngineer

    5 days

    158 11.2 Create sourcecode

    200 days

    159 11.2.1 Code ASMSsoftware-to-

    Programmer 40 days

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    24/67

    163 11.3.1 Generate ASMSsoftware-to-hardware interface

    object code

    Programmer 3 days

    164 11.3.2 Generate ASMSsoftware interfaceobject code

    Programmer 3 days

    165 11.3.3 Generate ASMSuser interfaceobject codegeneration

    Programmer 3 days

    166 11.4 Plan integration 100 days167 11.4.1 Plan integration of

    ASMSsoftware/hardwareinterface andsoftware

    Programmer 5 days

    168 11.4.2 Plan integration ofASMS software

    with userinterfaces

    Programmer 5 days

    169 11.5 Performintegration

    80 days

    170 11.5.1 Integrate ASMSsoftware/hardwareinterface withsoftware interface.

    Programmer,DatabaseEngineer

    10 days

    171 11.5.2 Integrate ASMSsoftware with userinterfaces

    Programmer 10 days

    172 11.6 Implementationcompleted

    0 days

    173 12 Installation 150 days

    174 12.1 Plan installationof the ASMS

    InstallationSpecialist

    10 days

    175 12.2 DistributeSoftware 20 days

    176 12.2.1 Distribute ASMSto the installationteam

    InstallationSpecialist

    1 day

    177 12.3 Install software 70 days

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    25/67

    Table 6 Level 2 WBS

    3.5 Scope Change Management Process

    3.5.1 Scope of Change Requests

    1. Modifications to software.

    2. Acquisition of third party software.

    3. Changes to contracted professional services (e.g. additional consultancy assistance).

    4. Scope (includes modules, data conversion and migration, interfaces, etc.).

    5. Milestone dates and major go-lives.

    6. Additional project spending (hardware, training and conferences).

    7. Functionality required by policy changes at the university and/or external mandates.

    3.5.2. Change Request Process

    Specialist

    181 12.6 InstallationCompleted

    0 days

    182 13 Operation &Support

    7 days

    183 13.1 Operate thesystem

    Help DeskLevel 1

    2 days

    184 13.2 Provide technicalassistance andconsulting

    Help DeskLevel 1

    2 days

    185 13.3 Maintain support

    request log

    Help Desk

    Level 1

    4 days

    186 14 Maintenance 21 Days

    187 14.1 Re-applySoftwareDevelopmentLife Cycle

    Consultant 21 days

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    26/67

    3. Project Manager prepares and submits Change Request Impact Analysis section and

    submits to the Change Management Team.

    4. Institution Implementation Team receives weekly updates of pending change requests andprovides input as needed / requested.

    5. Change Management Team approves/denies change request after the clarification, provides

    final recommendation on the Change Request Form and advises Project Manager.

    6. If appropriate, forward for review and disposition.

    7. Project Manager converses the decision to:

    a. The Team Lead making the request of the Change Review Team decision.

    b. Implementation Team.

    c. All appropriate interested parties.

    8. Amend Scope Management Plan and documentation as needed to incorporate sanctioned

    change.

    3.5.2. Roles and Responsibilities

    Team Leads Instigate change requests based on implementation

    needs using approved forms and communication

    processes. Requests from team members should be

    discussed with the appropriate Team Lead prior to

    submitting an official change request.

    Project Manager Facilitate the completion of change requests and

    information gathering. Work directly with vendors

    and with appropriate IT personnel, administrative

    and academic to collect information needed to

    complete the request.

    Implementation Team Receives updates of completed change requests

    awaiting approval. Provide input as

    needed/requested.

    Change Review Team Evaluates, allow or disallow change requests based

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    27/67

    3.5.3. Notes

    Requests resulting in changes to the vendor contract require approval from the Project

    Sponsor.

    No changes to the contract should be proceeded upon or conveyed as an approved change

    until Change Review Team have verified that they are in agreement with the original

    contract.

    Changes to software, budget, quality and schedule will be reviewed, managed and approved

    by the Project Manager.

    First priority will be given to change requests for acute functions and services. Other criteria

    for evaluating change requests will be approved by the Change Review Team.

    Project Scope Change Management Plan Documents:

    Change Request Form

    Change Request Log

    Scope Change Management Plan

    3.5 Plan Modification Rules

    1.

    Analyse the current project scope management plan to determine if this modification mayimpact project costs, resources, quality and the other directions of the project. If it is an

    insignificant change for the better, team may not need to escalate this further than those

    directly affected by the plan change. Project manager has the authority to change this

    plan.

    2. Meet with the project team members and vendors potentially impacted by the project plan

    change. Gather their feedback on how much time and resources this change may take.

    Ask their opinions on the feasibility of the change and if it may cause a barrier to project

    completions or time lines.

    3. Meet with project sponsors, stakeholders and management to discuss the change. Seek out

    their approval before moving forward if this is a significant change to either the outcome

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    28/67

    5. Distribute the project management plan to the project team and sponsors. Post internallyon a shared site or intranet and solicit feedback. Do not hide the change if everyone needsto know it and be forthcoming with how the change may or may not impact the project.

    4) Schedule management plan

    4.1 Project Schedule

    This section contains information about Automated Student Management System (ASMS)project schedule. A list of the milestones and their completion days are included in this

    section, while the detailed Gantt chart is included in the appendices.

    WBS ID Milestone Date Responsible Roles

    1.5.9 Baseline SPMP completed Fri 12-12-07 Project Manager

    1.6 Finalize project charter Fri 13-03-15 Project Manager

    2.5 All project deliverables have

    been delivered

    Tue 14-11-17 Project Manager

    3.4 SCMP completed Fri 13-07-26 Configuration Manager

    4.3 SQAP completed Mon 13-06-24 Quality Analyst

    5.4 System allocation completed Mon 13-06-24 Software Architect

    6.5 SRS Completed Fri 13-08-23 Requirements Analyst

    7.5.5 SDS completed Fri 14-02-28 Software Designer

    8.1.6 SVVP completed Thu 14-09-04 Verification Engineer,Validation Engineer, Consultant

    8.4.5 STP completed Fri 14-06-27 Verification Engineer

    8.7 V&V completed Mon 14-10-27 Verification Engineer

    9.4 Documentation completed Thu 14-05-01 Technical Writer, Installation

    Specialist, Consultant, HelpDesk Level 1, Project Manager

    10.5 Training completed Mon 14-11-17 Training Specialist

    11.6 Implementation completed Fri 14-10-10 Programmer

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    29/67

    4.2 Assumptions

    1. This schedule is for 2 years of time while Saturdays and Sundays have been left as non-

    working days. Corresponding project team members will be working for 8 hours eachworking day.

    2. The Project Schedule may change as new information and issues are revealed.

    5) Cost Management Plan

    5.1 Project Budget

    Budget Report - ASMS Project South East Gippsland University (2012-2015)ID Project Expenditures Rate(USD) Cost(USD)

    * Stated under assumptions

    1 Employee Cost1.1 Labor Cost $2,074,144.00

    1.2 Food & Beverage 12$/hour $210,528.00

    2 Rent Fee* $800/Week $76,800.00

    3 Insurance Cost

    3.1 Employee*$150 for $50000Labor cost $6,222.43

    3.2 Equipment* $0.00

    4 Software Cost4.1 Student Management System(TCO) $900,000.00

    4.2 Software Development Kit(SDK) $25,000.00

    4.3Microsoft Office 2010

    $495/Year $2,970.00

    4.4 Testing Tools $1000/machine $3,000.00

    5 Hardware Cost5.1 New Servers TCO $30,000.00

    5.2 Wireless Broadband Hardware $50,000.005.3 Wireless Broadband Hardware Maintenance $5000/annum $10,000.00

    6 Administrative Costs6.1 IT Service Desk $20,000.00

    6 2 Ad i i t ti b d t $5 000 00

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    30/67

    5.2 Budget Assumptions & Constraints

    Assumptions

    1. All the cost calculations will be calculated in the form of United States Dollars (USD).

    2. Since the workspace is given by the university, we assume that all electricity, water andsanitary facilities will be provided by the university.

    3.

    In Australia an employer have to spend $150 per every $50000 as insurance cost.

    4. All the equipments will be purchased newly for the project and according to theAustralian low seller have to bare the insurance cost for the equipments for first 5 years.

    5. Upon the agreement we have agreed to calculate the profit based on the initial budget upto 10%. Any change beyond that limit will be considered as the new base for the profitcalculation.

    6. Funding sources for the project will stably remain during the project execution time.

    Constraints

    1. All the labor costs are calculated based on the rates available on the current marketsituation and it signifies 55.6% of total cost ($2,289,864/ $4,113,034). Since we donthave direct control over human resources and we are directly exposed to fluctuations of

    the market rates.

    2. Since the project team is allocated after a tendering procedure, SixSigma has to use theirprevious knowledge in budget estimation which is a crucial point of a plan.

    3. Since the profit was calculated based on the initial budget any expenditure beyond theinitial limit will be subjected to consideration of the Change Review Team.

    4. If the budget goes beyond the 10% buffer soon, expenditures have to be rationalizedbefore the client.

    5. Class 1 budget estimate has been used in this project with the consideration of theproject nature. It is a deterministic approach. Further details are added in the appendix A.

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    31/67

    6) Quality Management Plan

    6.1 Quality Standards

    Project Processes/Reports Quality Standards

    Project Initiation IEEE 1058-1998IEEE[1] 1074-1997Project Initiation Check List[2]

    Project Monitoring & Control IEEE 1058-1998

    IEEE 1074-1997IEEE 828-1998IEEE 730-2002IEEE 1012-1998 + IEEE 1012a-1998IEEE 830-1998IEEE 829-1998IEEE 1016-1998Project Monitoring & Control CheckList

    Configuration Management IEEE 828-1998Configuration Management Check List

    Software QualityManagement

    IEEE 730-2002Quality Management Check List

    System Allocation N/A[3]

    Requirement Analysis IEEE 830-1998Requirement Analysis Check List

    Design IEEE 1016-1998

    Verification & Validation IEEE 1012-1998 + IEEE 1012a-1998IEEE 829-1998V&V check list

    Documentation development IEEE 1063-2001

    Training Training Check List

    Implementation Implementation Check List

    Installation N/A

    Operation & Support N/A

    Maintenance N/A

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    32/67

    Table 11 Quality Metrics

    6.2 Quality Metrics

    Notes:[1] Kilo Lines Of Code

    Project Deliverables Quality metrics

    Software Product Functional Point AnalysisLines of CodeCustomer Satisfaction (Usability)Response TimeBugs per KLOC[1] (Correctness)FunctionalityComments per KLOC

    Software DesignSpecification (SDS)

    CorrectnessIntegrity

    Software ProjectManagement Plan(SPMP)

    CorrectnessIntegrityCustomer Satisfaction / Acceptance

    Software ConfigurationManagement Plan(SCMP)

    CorrectnessIntegrity

    Software QualityAssurance Plan(SQAP)

    CorrectnessIntegrity

    Software Verificationand Validation Plan(SVVP)

    CorrectnessIntegrity

    Software RequirementsSpecification(SRS)

    CorrectnessIntegrity

    Software Test Plan(STP)

    CorrectnessIntegrity

    Software RiskManagement Plan(SRMP)

    CorrectnessIntegrity

    Software User Manual CorrectnessIntegrity

    Customer Satisfaction / AcceptanceEnd User Training Customer Satisfaction

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    33/67

    6.3 Quality Management Approach

    The quality management approach of this Automated Student Management System (ASMS)project will establish and ensure the required quality of the project deliverables and itsprocesses. Considering in the higher level quality management perspective, this project willfollow the traditional quality management phases to establish required quality of the project.According to traditional quality management approach quality planning, assuring andcontrolling are the three main phases which taken place in quality management.

    At the initial phase of the quality management approach will focus into define or deriverequired quality standards, quality metrics and tools to gain the expected quality of theproject and its deliverables. The next phase is Quality Assurance (QA) which ensures thatproject processes are used effectively to produce quality project deliverables.

    The approaches for quality assurance phase will describe in detail under Quality Assurancetopic of this document. Final step of the quality management approach is Quality Controlling(QC) phase that monitors the project deliverables to verify that the deliverables haveacceptable quality and the customer is satisfied. In detail description about QC process willprovide under Quality Control topic of this document.

    Following tools will be used to support the quality management process throughout the QAand QC phases of the project.

    Phase Tool Tool Description

    Qual

    ityAssurance

    Quality Audits Quality audit is an essential quality assurance toolused in assessing process successfulness of the

    projects. Quality audit is a systematic approach toidentify the problems in project processes and reportinefficiencies for improvements. Quality analysts areresponsible for performing the quality audits atpredefined intervals to ensure the quality of theproject processes

    Process Analysis Process analysis is a set of logically related

    instructions which aimed for continuous improvementof project processes.

    Benchmarking Comparing project processes with another comparableproject

    Flow Charting Flow charts are various kinds of diagrams used to

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    34/67

    Table 12 Quality Management Approach

    processesStatistical Sampling Statistical process control is a quality control method

    which uses statistical methods to monitor and control a

    process. That ensures the process operates with its fullpotential.

    Control Charts Control charts are statistical process controlling methodused for quality control.

    Standards and matrices for quality can be identified by any stake holder of the project. Projectmanager responsible for review the standards, matrices to determine cost versus benefit and

    how processes or deliverables affected by that standard or metric. If a standard or metricimplemented, project manager should update all related project documentation for qualitymanagement.

    6.4 Quality Assurance

    Quality assurance ensures that project processes are used effectively to produce quality

    project deliverables In order to ensure quality; an iterative quality process will be usedthroughout the project life cycle. This iterative process includes measuring process metrics,analyzing process data, and continuously improving the processes.

    Quality manager and the quality team will perform assessments at planned intervalsthroughout the project to ensure all processes are being correctly implemented and executed.Process improvement is another aspect of quality assurance. Quality assurance reviews,findings, and assessments should always result in some form of process improvement and, as

    a result, product improvement. All process improvement efforts must be documented,implemented, and communicated to all stakeholders as changes are made.

    Following table describes the quality assurance plan for the project processes.

    Project Process QualityStandardsStakeholderExpectations

    QualityAssurance

    Activity

    Frequency/Interval

    ResponsiblePerson(s)

    ProjectInitiation

    SPMPSPMP CheckList

    Planning theupcoming sub

    tasks with

    After every subtask have beencompleted

    ProjectManager

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    35/67

    process analysis.Implement anyimprovements

    identifiedProjectMonitoring &Control

    SPMP, SRS,SDS, SQAP,SVVP, STP,SCMP, SRMP,ProjectMonitoring &Control Check

    List

    Normal qualityaudits and

    process analysis.If any exceptionalsituation occurs,additional QA

    activities such as

    Benchmarkingand fishbonediagrams will use

    to identify theproblems.

    Weekly ProjectManager

    ConfigurationManagement

    SCMPSCMP CheckList

    Analyze theprocess andimplementidentified

    improvements

    After eachiteration of thesoftware in theprojectexecution

    ProjectManager,ConfigurationManager

    SoftwareQualityManagement

    SQMPSQMP CheckList

    Audit the qualitysystem. Identifyquality problems

    and needs.Improve the

    quality system

    Weekly,throughout theproject.

    ProjectManager,Quality Analyst

    System

    Allocation

    N/A[*]

    Requirement SRSSRS Check List

    Audit and analyzethe requirement

    identifying,validation anddocumentation

    process.Eliminate the

    problemsidentified andimprove the

    process.

    Weekly, in therequirementphase.

    ProjectManager,RequirementAnalyst

    Design SDSSDS Check List

    Review theprogress of

    Weekly, in thedesign phase

    ProjectManager

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    36/67

    Table 13 Quality Assurance

    Verification &Validation

    SVVPSVVP CheckList

    Review the V&Vprocess progress.

    Identify the

    inconsistencieswith the V&V

    standards.Eliminate the

    issues.

    Weekly, in theV&V phase

    Verification,ValidationEngineer and

    Consultant

    DocumentationDevelopment

    IEEE 1063-2001

    Review thedocumentationcontents and

    progress. Identifytheinconsistencies

    and issues.Improve the

    documentationquality

    Weekly TechnicalWriter

    Training Training CheckList

    Peer review thetraining progress.

    Improve thetraining process.

    Weekly, Whentraininghappens.

    TrainingSpecialist

    Implementation ImplementationCheck List

    Review theimplemented

    source codes withdesign andidentify the

    inconsistencies.

    Audit the sourcecode relevant

    matrices to ensurethe quality.Execute a

    resolution plan.

    Weekly, in theimplementationphase.

    Programmer

    Installation N/A[*]

    Operation &Support N/A

    [*]

    Maintenance N/A[*]

    Note:[*] D t ti t d th t i t lit ill t b f d f th

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    37/67

    6.5 Quality Control

    Quality control ensures that project deliverables complies with quality standards and

    customer satisfied with the deliverable.

    ProjectDeliverable

    Quality Standards/Customer

    Satisfaction

    QualityControlActivity

    Frequency/Interval

    ResponsiblePerson(s)

    SoftwareProject

    ManagementPlan (SPMP)

    Document mustcomplies with

    following StandardsIEEE 1058-1998IEEE 1074-1997

    Review byProject

    Sponsor

    After plan hasdelivered

    ProjectManager

    SoftwareConfigurationManagementPlan (SCMP)

    Document mustcomplies with

    following StandardsIEEE 828-1998

    Review byProject

    Manager

    After plan hasdelivered

    ConfigurationManager

    SoftwareQualityAssurance Plan(SQAP)

    Document mustcomplies with

    following StandardsIEEE 730-2002

    Review byProject

    Manager

    After plan hasdelivered

    QualityAnalyst

    SoftwareVerificationand ValidationPlan (SVVP)

    Document mustcomplies with

    following StandardsIEEE 1012-1998 +IEEE 1012a-1998

    Review byProject

    Manager

    After plan hasdelivered

    VerificationEngineer ,Consultant ,ValidationEngineer

    Software

    RequirementsSpecification(SRS)

    Document must

    complies withfollowing Standards

    IEEE 830-1998

    Review by

    RequirementsAnalyst and

    ProjectManager

    After

    document hasdelivered

    Requirements

    Analyst

    Software TestPlan (STP)

    Document mustcomplies with

    following StandardsIEEE 829-1998

    Review byProject

    Manager

    After plan hasdelivered

    VerificationEngineer

    SoftwareDesignSpecification(SDS)

    Document mustcomplies with

    following StandardsIEEE 1016-1998

    Review byProject

    Manager

    After plan hasdelivered

    System Designer

    Software RiskManagement

    Document mustcomplies with

    Review byProject

    After plan hasdelivered

    Project Manager

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    38/67

    Table 14 Quality Control

    Average customersatisfaction rating

    should be above 7.0

    Review andrated the

    satisfaction by

    the usersusing 0 to 10satisfaction

    scale.SoftwareSource Code

    Bugs per KLOC < 5 Codewalkthroughs

    and AlphaTesting

    After sourcecode for eachiteration havedelivered

    Programmer

    Response Time 100

    Codewalkthroughs

    User Training

    Average usersatisfaction rating

    should be above 8.0

    Review andrated the

    satisfaction bythe users

    using 0 to 10satisfaction

    scale.

    After usertraining

    finished

    TrainingSpecialist

    Review

    Reviewing a deliverable documentation or work products, particularly for consistency with

    the higher-level plans on which the document is based (i.e. design consistency with

    requirements, source code consistent with design). Inconsistencies will be noted and an

    action plan for resolution produced. Inspection of a document for compliance with the

    standard or template on which mentioned in the table should be carried out within the project

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    39/67

    7) Risk Management

    7.1 Risk Management Strategies

    Risk management is aimed to identification measurement of risks and prioritizing them. Inrisk management we are more focused on risks that are more probable and effect more for theproject

    ProcessName

    Process Description

    1.0 Establishingthe context

    1.1 Factors thatmay effect

    Physical An electrical failure

    Long working hours and bad siting positionsFinancial

    Over expenditureLegal

    Client may sue against company

    Employee may sue against company

    Environmental Bad environmental conditions.

    1.2 Stakeholderswho need to beinvolved

    University maintain staff

    Employees of the project

    Project manager

    University administrative staff

    Lectures of the university

    Local government

    1.3 risk criteriaidentified

    Likelihood of death or serious injury

    Likelihood of decreasing profitability

    Likelihood of litigation

    Likelihood of inclement weather

    2.0 Identify theRisks 2.1 To identify therisk

    Looked at the records of previous accidents of theuniversity

    Inspect the area provide and get advice fromengineers

    Interview the stakeholders

    Check financial stability of the university

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    40/67

    Legal that caused due to breech of agreement withthe client

    2.3 Major risksidentified

    Employee problems due to bad seating positions Fluctuations in labor rates

    If there is heavy rains its hard to continue theproject

    If the implementation process was crashed withstudent management system client may sue for thefinancial damages

    3.0 Analyze the

    Risk

    3.1 Evaluate the

    effect againstprobability

    Likelihood Low Likelihood High

    ConsequencesLow

    If theimplementationprocess wascrashed withstudentmanagementsystem client maysue for the financial

    damages

    Employee problemsdue to bad seatingpositions

    ConsequencesHigh

    If there is heavyrains its hard tocontinue theproject

    Fluctuations inlabor rates

    4.0 Evaluate

    the Risk

    4.1 whether a risk isacceptable

    High probable high Consequences risks need to be gettingmore concern. Employee problems due to bad seatingpositions is a risk need our concern. Flood problem is aconcern that needs our attention.

    5.0 Manage theRisks

    5.1 Avoid the risk,Control the risk,Transfer therisk orRetain the risk

    1. Fluctuations in labor rates - Avoid the riskMaking arrangement with client to calculateprofit on the proposed budget +/- 10% ofinitial figure and beyond that limit willconcern as the new base for profit

    calculation2. Employee problems due to bad seating

    positions - Control the riskConducting training sessions on properpositions and insuring

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    41/67

    Table 16 Risk Management Tools

    Table 15 Risk Management Strategies

    7.2 Risk Management Tools

    Risk management tools are mainly used to measure the magnitude of a risk and probability

    and they help to calculate and rank the risks

    Tool Name Tool Description

    1.0 Risk Register Acts as a central repository for all risks recognized by the project or businessand, for each risk, consist of information such as risk likelihood, impact,counter-measures, risk holder

    2.0 SAPHIRE Probabilistic risk and reliability assessment software tool. SAPHIRE standsfor Systems Analysis Programs for Hands-on Integrated Reliability

    Evaluations.

    7.3 Data Sources

    riskLet the university staff to decide what timewe are going to conduct integration to the

    main system

    6.0 Review 6.1 monitor andevaluate

    Need to constantly monitor and evaluate the strategies thatare using to manage risks, as risks do not remain the same.There may find that over time new risks are created,existing risks are increased or decreased, some risks nolonger exist and risk management strategies are no longereffective.

    Category Data Source Name Data Source Description

    1.0 Weather1.1 Local environment agency

    area officesThere does not appear to be a singledatabase of historical flood events(maps) or arecord of their outcomes

    l il i ll l l il

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    42/67

    Table 17 Data Sources

    7.4 Risk Categories

    These are the areas that may likely to contain risks (Refer risk strategies factors that mayaffect).

    Physical

    Financial

    Legal

    Environmental

    7.5 Risk Probability and Impact

    2.0 Health

    2.1 Health and safety - Australia Provide detail guide to employee healthand free consultation services

    3.0 Financial3.1 Banks Provide detail of financial history of

    university and its credibility

    3.2 Other contractors to theuniversity

    Not a very official way of gatheringinformation but valuable source ofinformation

    4.0 Legal

    4.1 Company legal officer Provide initial bases for the legal risk

    identification4.2 Consultants Provide in deep assessment of legal

    environment

    Item Probability(P)

    Impact (I) Total RiskScore

    1.0 Employee problems due to bad seating positions 0.8 3 2.4

    2.0 Fluctuations in labor rates 0.6 8 4.8

    3.0 If there is heavy rains its hard to continue theproject

    0.3 9 2.7

    4.0 If the implementation process was crashed with 0.2 5 1

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    43/67

    Table 19 Project Team

    8) HR management plan

    8.1 Project Organization

    8.1.1 Project Team

    This list would include the information of project manager and all the team members whowill be involved with the planning and execution of the project.

    Name Role PhoneNumber

    Email Address

    Beth Storry Project Manager 0778442010 [email protected]

    Emily Maguire Software Architect 0711993060 [email protected]

    LauraUnsworth

    Programmer 0717625535 [email protected]

    Crista Cullen Requirements Analyst 0719251470 [email protected]

    Anne Panter Configuration Manager 0724526264 [email protected]

    HannahMacleod

    Quality Analyst 0712730729 [email protected]

    Mark Knowles Database Engineer 0723424233 [email protected]

    Jamie Dwyer Software Designer 0772323097 [email protected]

    Liam de Young Validation Engineer 0782382327 [email protected]

    Simon Orchard Verification Engineer 0712468075 [email protected]

    Glenn Turner Consultant 0771245769 [email protected]

    Chris Ciriello Installation Specialist 0729434740 [email protected]

    MatthewButturini

    Technical Writer 0783232394 [email protected]

    Russell Ford Training Specialist 0773292928 [email protected]

    Eddie

    Ockenden

    Help Desk Level 1 0718373427 [email protected]

    Peter Samuels Human ResourceManager

    0715879564 [email protected]

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    44/67

    8.1.1.1 Hierarchy of the project team

    Sponsor

    InformationTechnologyServices

    Consultant

    Project Manager

    Configuration Manager Software Architect

    Design & Development

    Software Designer

    Programmer

    Analysis

    Requirements Analyst

    Quality Analyst

    Database Handling Database Engineer

    Testing & Installation

    Validation Engineer

    Verification Engineer

    Installation Specialist

    Operation & Support

    Help Desk Level 1

    Technical Writer

    Training Specialist

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    45/67

    UCSC ICT 2009 IT Project Management Assignment 2012 | Page 45 of60

    8.1.2 Key Stakeholders

    Information

    Technology

    Services

    Gilbert Roks Beth Storry Emily Maguire,

    Crista Cullen,

    Anne Panter,

    Hannah Macleod,

    Mark Knowles,

    Jamie Dwyer,

    Liam de Young,

    Simon Orchard,Glenn Turner,

    Chris Ciriello,

    Matthew Butturini,

    Russell Ford,

    Eddie Ockenden

    Role on Project ProjectSponsor

    ChiefInformation

    Officer (CIO)

    Project Manager Project Team Students Lecturers AdministrativeStaff

    Organization South East

    Gippsland

    University

    SouthEast

    Gippsland

    University

    MIT Company MIT Company South East

    Gippsland

    University

    South East

    Gippsland

    University

    South East

    Gippsland

    University

    Contact

    Information

    southeastgip

    [email protected]

    om

    gilbertroks@gm

    ail.com

    bethstorry@gmail

    .com

    itpm-group-

    [email protected]

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    46/67

    UCSC ICT 2009 IT Project Management Assignment 2012 | Page 46 of60

    Table 20 Key Stakeholders

    Unique Facts Prefers use

    of email forproject

    documents

    Responsible for

    Develop,maintain, and

    facilitate

    implementation

    of a sound and

    integrated IT

    architecture as

    such they

    require more

    detailedcommunications

    Manages day to

    day resources,provides project

    guidance and

    monitors and

    reports on the

    projects metrics

    Need to have a clear

    understanding of thework to be completed

    and the framework in

    which the project is to

    be executed.

    Level of

    Interest

    High High High High Medium Medium Medium

    Level of

    Influence

    High High High High Low Low Low

    Suggestions for

    managing

    relationships

    Keep

    informed of

    all projectprogress

    Keep all

    information

    about theproject progress

    He is the primary

    communicator for

    the projectdistributing

    information

    according to this

    Communications

    Management Plan

    Require a detailed

    level of

    communicationswhich is achieved

    through day to day

    interactions with the

    Project Manager and

    other team members

    along with weekly

    team meetings

    Keep

    informed

    aboutcurrent

    changes and

    can get

    feedback to

    assist the

    progress

    Keep

    informed

    about currentchanges and

    can get

    feedback to

    assist the

    progress

    Keep informed

    about current

    changes and canget feedback to

    assist the

    progress

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    47/67

    8.2 Resource Requirements

    Following chart depicts you how the resources will be used within each month. This graph

    helps you to analyse the resource usage of the project. The team members of the project have

    to engage with different type of tasks & activities. They should be responsible for each task

    & activities that they have been assigned.

    8.3 Resource Assignment

    .

    Note: Here we have assigned resources according to the Level 2 WBS. Further informationcan be perceived in the Gantt chart at the appendices.

    8.3 Resource Assignment

    WBS

    Tasks anager

    Architect

    mer en

    tsAnalyst

    tionManager

    nalyst

    Engineer

    Designer

    nEngineer

    onEngineer

    t nSpecialist

    Writer

    Specialist

    kLevel1

    ger

    Figure 2

    0

    200400

    600

    800

    1000

    1200

    1400

    1600

    1800

    June

    August

    October

    December

    February

    April

    June

    August

    October

    December

    February

    April

    June

    August

    October

    December

    February

    2012 2013 2014 2015

    Resources Allocation - Hours Per MonthHR Manager

    Help Desk Level 1

    Training Specialist

    Technical Writer

    Installation Specialist

    Consultant

    Verification Engineer

    Validation Engineer

    Software Designer

    Database Engineer

    Quality Analyst

    Configuration Manager

    Requirements Analyst

    Programmer

    Software Architect

    Project Manager

    Hours

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    48/67

    1.3 Establish project environment X X

    1.4 Plan project management X X X X X

    2 Project Monitoring & Control X X

    2.1 Start the project X

    2.2 Analyze risks X

    2.3 Create contingency plan X

    2.4 Manage the project X X

    2.5All project deliverables have beendelivered

    X

    2.6 project closeout X3 Configuration Management X

    3.1 Plan configuration management plan X

    3.2 Configuration Items Identification X

    3.3 Configuration plan finalization X

    3.4 SCMP completed X

    3.5 Configuration ControlX

    3.6 Configuration Auditing/Reporting X

    4 Software Quality Management X

    4.1 Plan software quality management X

    4.2Create Software Quality AssurancePlan (SQAP)

    X

    4.3 SQAP completed X

    4.4 Define indicators X

    4.5 Manage software quality X

    4.6 Identify quality improvement needs X

    5 System Allocation X

    5.1 Analyzing system functions X

    5.2 Develop System Architecture X

    5.3 Decompose system requirements X5.4 System allocation completed X

    6 Defining Requirements X

    6 1Define and develop softwarerequirements

    X

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    49/67

    7.1Perform the architectural design ofthe system

    X

    7.2 Design the database X

    7.3 Design interfaces X

    7.4 Select Algorithms X

    7.5 Detail Design X

    8 Verification & Validation X X X

    8.1 Plan verification and validation X X X

    8.2

    Execute verification and validation

    tasks

    X

    8.3Requirements & Design V&Vcompleted

    X

    8.4 Plan testing X

    8.5 Develop test requirements X

    8.6 Execute the tests X

    8.7 V&V completed X

    9 Documentation development X X X X X

    9.1 Plan documentation X

    9.2 Implement documentation X X X

    9.3Produce and distributedocumentation

    X

    9.4 Documentation completed X

    10 Training X

    10.1 Plan training program X

    10.2 Develop training materials X

    10.3 Validate training program X

    10.4 Implement the training program X

    10.5 Training completed X

    11 Implementation X X

    11.1 Create test data X

    11.2 Create source code X

    11.3 Generate object code X

    11.4 Plan integration X

    12 4 H d i ll i X

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    50/67

    Table 21 Resource Assignment

    *Assumption: Resources for the project will stably remain during the project execution

    time.

    9) Communication plan

    9.1 Stakeholder Analysis

    *Refer 8.1.2

    9.2 Project Reports

    Data Needed FrequencyofCollection

    ResponsibleParty forDataCollection& Analysis

    Report Media& Format

    ResponsibleParty forDistributingReport

    Project Status

    Dashboard/report

    Tracking

    Gantt Chart

    Weekly Beth Storry Status Form Eddie Ockenden

    Trend Analysis Past projectdata,PreviousStatus reports

    Monthly CristaCullen

    Printeddocument withcalculations

    Crista Cullen

    Variance Analysis Proposed Bi weekly Mark Through e Mark Knowles

    12.4 Hardware installation X

    12.5Accept software in operationalenvironment

    X

    12.6 Installation Completed X X

    13Operation & Support X

    13.1Operate the system X

    13.2Provide technical assistance andconsulting X

    13.3Maintain support request log X

    14 Maintenance X

    14.1Re-apply Software DevelopmentLife Cycle

    X

    proposed

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    51/67

    Table 22 Project Reports

    proposedbugdet

    9.3 Project Meetings

    Purpose Frequency Attendees Reporting Requirements

    Status ReviewMeeting

    Update onprojectstatus,Informand identifyproblems andidentyfy

    posssibleaction items

    Weekly(Monthly withthe ITSreperesentativeand GilbertRoks)

    All of theprojectteam,GilbertRoks,ITSrepresentative(ifneeded)

    Meeting Minutes,varianceand trend analysis, Statusreport

    Problem SolvingMeeting

    Specially tosolve problemsarised

    Bi-Weekly(if aproblem arisesinstantly)

    ProjectManager, GlennTurner and theproject teammembersresponsible

    Requirement specification,Problem document

    Tecnical DesignReview Meeting

    To review thesystem design

    After everydesignoutput(mainlypreliminaryand final)

    Projectmanager,GilbertRoks,MITrepresentative,Emily Maguire,Crista Cullen,Jamie Dwyer

    Design specificationdocuments,Requirementspecification documents

    Project Wikisthrough CentralDesktp

    Communicatewith all theteam membersregarding anysituation

    Instantly(anytime) All the teammembers andGlenn Turner

    Electronic File sharing

    Customer ProjectReview meeting

    Show anddiscuss theprogress of theproject with thecustomer

    Monthly BethStorry,GlennTurner, ITSrepresentaiveand UniversityadministrationincludingGilbert Roks

    Status report, Requirementspecification document

    are given access to the server information through their individual logins. But the project

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    52/67

    are given access to the server information through their individual logins. But the projectmanager and the consultant have higher authority along with the project sponsor (Universityauthority) to view and access all the information. Other team members and stakeholders aregiven necessary access grants to carry out their work effectively.

    And the communication will be done mainly through e-mails as it is easy and moreconvenient. And it is also the professional way of work and is easy to keep track of thedocuments passed. Use of Central Desktop is very helpful as the project team members andthe stakeholders can communicate instantly when they want with anyone in the network. Allthe documents will be shared through the system to all the necessary users and they have theability to reply or call a meeting regarding an issue through the system whenever they want.And all the documents will be archived in this system too, making it a backup storage of the

    project information.

    9.5 Communications Summary

    Stakeholder Type Communication

    Medium

    Frequency Responsible

    PartyBeth Storry

    Status Report E-mail and printedcopy handed

    Every Tuesdayand after everymilestone

    EddieOckenden

    EmilyMaguire

    Trend analysis Email Monthly Crita Cullen

    CristaCullen

    Status report,Requirementspecification,Varianceanalysis,Trendanalysis

    Email and printedcopy andcollaborativesoftware

    Weekly EddieOckenden

    AnnePanter Status report,Trendanalysis E-mail,collaborativesoftware Bi-weekly HannahMacleod

    HannahMacleod

    Status report E-mail Weekly EddieOckenden

    Si St t E il C l b ti Bi kl H h

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    53/67

    Table 24 Communication Summary

    SimonOrchard

    Statusreport.TechnicalDesign Review

    report

    E-mail,Colaborativesoftware

    Bi-weekly HannahMacleod

    GlennTurner

    Status review,Trendanalysis,Varianceanalysis

    E-mail,Collaborativesoftware

    Weekly (instantlyif needed )

    EddieOckenden

    MatthewButturini

    All the reports E-mail As those reportsare made

    EddieOckenden,

    HannahMacleod

    EddieOckenden

    All the reports E-mail and hecreates

    As these reportsare created

    HannahMacleod andhe createthem

    PeterSamuels

    Status report,Variance analysis,Trend Analysis

    E-mail andcollaborativesoftware

    Weekly andMonthly(analysis)

    EddieOckenden,HannahMacleod

    Reference List

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    54/67

    Unknown, 2012. PROJECT QUALITY MANAGEMENT PLAN TEMPLATE, [E book],Available: http://www.projectmanagementdocs.com/templates/Quality_Management_Plan_Template.pdf, [Accessed date: 10th Aug 2012]

    Unknown, 2012,IT Project Quality Management Plan,[Document],Available: http://www.itplanning.org.vt.edu/pm/ITPMQualityMgmtPlan.doc, [Accessed Date10th Aug 2012]

    Wikipedia, 2012, SRS- Wikipedia, the free encyclopedia, [online],Available:http://en.wikipedia.org/wiki/Software_Requirements_Specification,[Accessed date:4th June 2012]

    Pcubed, 2012, Write a scope statement - Project - Office.com, [online], Available:http://office.microsoft.com/en-us/project-help/write-a-scope-statement-HA001142472.aspx,[Accessed date: 5th June 2012]

    Preferred Customer, 2012, [Document], Available:http://wweb.uta.edu/insyopma/prater/OPMA%205364%20Scope%20statement.doc,[Accessed date: 10th June 2012]

    IT Department, Scope Statement, 2012, [Document], Available:http://www.augsburg.edu/ppages/~schwalbe/scope_statement.doc, [Accessed date: 12th June2012]

    Prof. B. Meyer, Prof. P. Kolb, 2012, [E book], Available:http://se.inf.ethz.ch/old/teaching/ws2005/0273/slides/Template%20Project%20Plan.pdf,[Accessed date: 16th June 2012]

    Unknown, 2008, [E book], Available:http://www.collegiateproject.com/articles/Preliminary%20Change%20Management%20Plan.pdf, [Accessed date: 16th June 2012]

    Francine Richards,2012,How to Change a Project Management Plan | eHow.com, [Online],Available: http://www.ehow.com/how_7798951_change-project-management-plan.html,[Accessed date: 5th June 2012]

    Unknown, 2012, Legal Consultant Salary in California - Legal Consultant Salary, [online],

    Appendices

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    55/67

    pp

    Appendix A: Generic Cost Estimate Classification Matrix

    Note:

    [a] If the range index value of 1 represents %10/.5%, then an index value of 10 represents

    %100/.50%.

    [b] If the cost index value of 1 represents 0.005% of project costs, then an index value

    of 100 represents 0.5%.

    PrimaryCharacteristics

    Secondary Characteristics

    EstimateClass

    LEVEL OFPROJECTDEFINITION[

    Expressedas % ofcompletedefinition]

    ENDUSAGE[Typical Purpose

    of Estimate]

    METHODOLOGY[Typicalestimating

    methodology]

    EXPECTEDACCURACYCHANGE[Ty

    pical +/- rangerelative tobest index of 1(a)* ]

    PREPARATIONEFFORT[Typic

    al degree ofeffort relative toleast cost indexof 1 (b)*]

    Class 5 0% to 2%Screening orFeasibility

    Stochastic orJudgment

    4 to 20 1

    Class 4 1% to 15%

    Concept

    Study orFeasibility

    PrimarilyStochastic 3 to 12 2 to 4

    Class 3 10% to 40%Budget,Authorization,or Control

    Mixed, butPrimarilyStochastic

    2 to 6 3 to 10

    Class 2 30% to 70%Control orBid/ Tender

    PrimarilyDeterministic

    1 to 3 5 to 10

    Class 1 50% to 100% Bid/Tender Deterministic 1 10 to 100

    Appendix B: Project Budget

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    56/67

    Budget Report - ASMS Project South East Gippsland University (2012-2015)ID Project Expenditures Rate(USD) Cost(USD)

    * Stated under assumptions

    Estimated Total Working Hours = 175441 Employee Cost

    1.1 Labor Cost $2,074,144.001.1.1 Project Manager $978,920.00

    1.1.2 Software Architect $83,200.001.1.3 Programmer $118.080.001.1.4 Requirement Analyst $50,160.00

    1.1.5 Configuration Manager $56,000.00

    1.1.6 Quality Analyst $100,480.00

    1.1.7 Database Engineer $18,720.00

    1.1.8 Software Designer $92,400.00

    1.1.9 Validation Engineer $72,000.00

    1.1.10 Verification Engineer $246,720.001.1.11 Consultant $101,760.00

    1.1.12 Installation Specialist $20,640.00

    1.1.13 Technical Writer $36,000.00

    1.1.14 Training Specialist $61,440.00

    1.1.15 Help Desk Level 1 $3,840.00

    1.1.16 Human Resource Manager $33,984.00

    1.2 Food & Beverage 12$/hour $210,528.00

    2 Rent Fee* $800/Week $76,800.00

    3 Insurance Cost

    3.1 Employee*$150 for $50000Labor cost $6,222.43

    3.2 Equipment* $0.00

    4 Software Cost4.1 Student Management System(TCO) $900,000.00

    4.2 Software Development Kit(SDK) $25,000.00

    4.3Microsoft Office 2010

    $495/Year $2,970.00

    4 4 Testing Tools $1000/machine $3 000 00

    6.1 IT Service Desk $20,000.00

    6 2 Ad i i t ti b d t $5 000 00

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    57/67

    Table 9 Summarized Budget

    Appendix C: Risk Categorization Table

    6.2 Administrative budget $5,000.00

    Total Implementation Cost $3,413,664.43

    7 Legal Consultation $60000/annum $120,000.00

    Total Budget for the Project $3,533,664.43

  • 7/30/2019 Automated Student Management System for South East Gippsland University - SPMP

    58/67

    UCSC ICT 2009 IT Project Management Assignment 2012 | Page 58 of60

    Risk Factors and

    Categories

    Low Risk Evidence (L) Medium Risk Evidence (M) High Risk Evidence (H) Risk

    Rating

    (H,M,L)

    Comments

    Project Fit Project fits within

    SixSigmas area of

    expertise and interest

    Project limits SixSigmas

    ability to take on other

    attractive projects

    Mid-project, the project

    conflicts with a change in

    SixSigmas direction.

    L Unlikely to be an issue, since

    the project involves most of

    SixSigmas resources and

    therefore sustains it

    Organization management factors

    Project team

    Stability

    Project staff are expected

    to stay with SixSigma forthe duration of the project

    One or more key project staff

    are expected to leaveSixSigma before their

    accountabilities are met

    More than three key

    project staff are expectedto leav