august 28, 2015 2014 attachment o true-up customer meeting

21
August 28, 2015 2014 ATTACHMENT O TRUE-UP CUSTOMER MEETING

Upload: ambrose-mcgee

Post on 29-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

August 28, 2015

2014 ATTACHMENT O TRUE-UP CUSTOMER MEETING

AGENDA

• Meeting Purpose

• Otter Tail Power Company Profile

• Attachment O Calculation

• 2014 Transmission Projects

• Question/Answer

2

MEETING PURPOSE

• To provide an informational forum regarding Otter Tail’s 2014 Attachment O for True-up.

• The 2014 Actual Year Attachment O is calculated using the FERC Form 1 Attachment O template under the MISO Tariff utilizing actual data as reported in the 2014 FERC Form 1 for Otter Tail Power.

• Any True-up for 2014 will be included in the 2016 FLTY Attachment O Calculation for rates effective January 1, 2016 for the joint pricing zone comprised of Otter Tail, Great River Energy, Missouri River Energy Services, Benson Municipal Utilities, Detroit Lakes Public Utilities, and Alexandria Light & Power.

3

OTTER TAIL POWER COMPANY PROFILE

NORTH DAKOTA

SOUTH DAKOTA

Garrison

Rugby

LANGDON WIND ENERGY CENTER

COYOTESTATION

Jamestown

LEGEND

Headquarters

Customer service center

HOOT LAKE PLANT

Fergus FallsWahpeton

Oakes

Morris

LAKE PRESTONCOMBUSTION TURBINE

BIG STONE PLANT

LUVERNE WIND FARM

ASHTABULA WIND ENERGY CENTER

ASHTABULA III

Milbank

SOLWAY COMBUSTION

TURBINE

Crookston

Devils Lake

Bemidji

JAMESTOWNCOMBUSTION

TURBINE

• 70,000 Square miles

• 130,200 Customers

• 422 Communities

• Avg. population about 400

• 785 Employees

• 495 Minnesota

• 200 North Dakota

• 90 South Dakota

• About 800 MW owned generation

• About 245 MW wind generation

• About 5,400 miles of transmission lines

SERVICE AREA

5

OUR MISSION

To produce and deliver electricity as reliably, economically, and environmentallyresponsibly as possible to the balanced benefitof customers, shareholders, and employees and to improve the quality of life in the areas in which we do business.

6

ATTACHMENT O CALCULATION

2014 ACTUAL YEAR ATTACHMENT O

• Actual Year Rate Requirements

• Rate Base

• Operating Expenses

• Revenue Requirement and Rate

• Network Rate Summary

8

RATE REQUIREMENTS

• By June 1 of each year, Otter Tail will post on OASIS all information regarding any Attachment O True-up Adjustments for the prior year.

• By September 1 of each year, Otter Tail will hold a customer meeting to explain its Actual Year True-up Calculation.– Ex., 2014 Forward Looking Attachment O will be trued-up by June 1, 2015 with a corresponding

Customer Meeting being held by September 1, 2015.

• By September 1 of each year, Otter Tail will post on OASIS its projected Net Revenue Requirement, including the True-Up Adjustment and load for the following year, and associated work papers.

• Otter Tail will hold a customer meeting by October 31 of each year to explain its formula rate input projections and cost detail.

• The MISO Transmission Owners will hold a Regional Cost Sharing stakeholder meeting by November 1 of each year.

9

RATE BASE

10Note: The above numbers are Transmission only

Rate Base Item 2014 Actual

2014 Projected $ Change % Change Explanation

Gross Plant in Service $315,321,865 $318,287,029 $(2,965,164) (0.9%)

The decrease in Plant in Service from Projected to Actual was due to timing of in-service dates and lower capitalized project costs than expected. Variance is less than 1% overall so very close to forecast.

Accumulated Depreciation

$106,772,283 $107,878,058 $(1,105,775) (1.0%) Net result of Annual Depreciation Expense combined with projected retirements.

Net Plant in Service $208,549,582 $210,408,971 $(1,859,389) (0.9%) = Gross Plant - A/D

Adjustments to Rate Base

$(52,627,921) $(50,181,698) ($2,446,223) 4.9%

ADIT - Book vs Tax Depreciation Timing Differences originating due to accelerated tax depreciation methods being used for large Transmission projects going into service.

CWIP for CON Projects $58,045,533 $65,920,432 $(7,874,899) (11.9%)The decrease in CWIP for CON Projects from Projected to Actual was mainly due to Fargo Phase III CAPX project going into service earlier than anticipated.

Land Held for Future Use $9,037 $9,038 $(1) 0.0%

Working Capital $5,840,784 $5,710,799 $129,985 2.3%Increase in CWC due to slight increases in inventory, prepayments and direct Transmission and A&G-related O&Ms.

Rate Base $219,817,014 $231,867,542 $(12,050,527) (5.2%) = Net Plant + Adj + CWIP + Land + Working Capital

OPERATING EXPENSES

11Note: The above numbers are Transmission only

Expense Item

2014 Actual

2014 Projected $ Change % Change Explanation

O&M $14,259,856 $14,317,565 $(57,709) (0.4%) Tracking close to forecast.

Depreciation Expense

$5,867,878 $6,566,168 $(698,290) (10.6%)

Decrease in depreciation expense coincides with the reduction in Plant in Service reported on the previous slide as well as lower transmission depreciation rates filed late in 2013 for use in actual year 2014.

Taxes Other than Income

$2,647,490 $2,711,397 $(63,907) (2.4%) Tracking close to forecast.

Income Taxes $8,617,574 $8,343,341 $274,233 3.3%

Higher ETR in the 2014 actual vs the FLTY filing increased the tax calculation slightly. This is somewhat offset by a Decrease in Rate Base = Decrease in Return = Decrease in Income Tax Expense.

Operating Expense

$31,392,798 $31,938,471 $(545,673) (1.7%) = O&M + A&G + Depreciation + Taxes

REVENUE REQUIREMENT AND RATE

12

 2014 Actual

2014 Projected

$ Change % Change Explanation

Long Term Debt 50.84% 50.54%   0.30% Tracking close to forecast.

Common Stock 49.16% 49.46%   (0.30%) Tracking close to forecast.

Total 100.00% 100.00%     = Debt + Equity

Weighted Cost of Debt 5.50% 5.49%   0.01% Tracking close to forecast.

Cost of Common Stock 12.38% 12.38%   0.00% Unchanged

Rate of Return 8.88% 8.90%   (0.02%) = (LTD*Cost)+(Preferred Stock*Cost)+(Common Stock*Cost)

Rate Base $219,817,014 $231,867,542 $(12,050,528) (5.20%) From "Rate Base" Calculation

Allowed Return $19,519,538 $20,629,078 $(1,109,540) (5.38%) = Rate of Return * Rate Base

Operating Expenses $31,392,798 $31,938,471 $(545,673) (1.71%) From "Operating Expense" Calculation

Attachment GG Adjustments

$16,168,882 $16,562,703 $(393,821) (2.38%)The reduction in revenue requirements is mainly due to less spend on Fargo CAPX than originally projected and a lower rate of return as calculated above.

Attachment MM Adjustments $4,373,580 $4,573,259 ($199,679) (4.37%)

The reduction in revenue requirements is mainly due to less capital spend on all projects, pushing the in-service date for Brookings CAPX from December 2013 in the FLTY to an actual in-service date of April 2014 as well as a lower Rate of Return as calculated above.

Gross Revenue Requirement $30,369,874 $31,431,586 $(1,061,713) (3.38%) = Return + Expenses - Adjustments

Revenue Credits $6,129,709 $6,449,668 $(319,959) (4.96%) The reduction is mainly due to less MISO Schedule 26 and 26A credits than forecasted.

2014 True-up (Including Interest)

$(4,638,732) $(4,638,732) - 0.00% N/A

Net Revenue Requirement $19,601,433 $20,343,186 (741,753) (3.65%) = Gross Revenue Requirement - Revenue Credits + True-up

2014 ATTACHMENT O TRUE-UPCALCULATION

13

Attachment O True-up Calculation 

2014 Actual

2014 Projected $ Change % Change Explanation

ATRR True-up $(741,753)  From “Net Revenue Requirement” line on previous slide.

Divisor $730,327 $659,524 $(70,803) (10.74%) From Line Above

Projected Cost ($/kW/Yr) $30.85 From 2014 FLTY Attachment O Template

Divisor True-up $(2,183,927) = Divisor x Projected Cost ($/kW/Yr)

Total Principal True-up $(2,925,680) = ATRR + Divisor True-up Amounts

Interest on True-up $(192,171) = Avg. Monthly FERC Interest Rate on Refunds x Principal True-up

Total Principal and Interest True-up

$(3,117,851) To be Applied to 2016 FLTY Attachment O Calculation

RATE SUMMARY

14

Z $0.33 or 12.8% Decrease

2014

Pro

ject

ed A

TRR

Div

isor

Cha

nge

Rat

e B

ase

Ope

ratin

g E

xpen

seD

epre

ciat

ion

& P

rope

rty T

axes

Cha

nge

in C

apita

l Stru

ctur

e/R

OR

Atta

chm

ent G

G A

djus

tmen

tA

ttach

men

t MM

Adj

ustm

ent

Rev

enue

Cre

dits

Mis

cella

neou

s

2014

Act

ual A

TRR

($1.00)

($0.50)

$0.00

$0.50

$1.00

$1.50

$2.00

$2.50

$3.00

$2.57

($0.25) ($0.20)

$0.02

($0.09)($0.01)

$0.05 $0.03 $0.04 $0.08

$2.24

TOTAL TRANSMISSION REVENUE REQUIREMENT BREAKDOWN

15

Total Rev. Req. =

$40,143,895

Net Attch. O ATRR =

$19,601,433

Attch. GG Rev. Req. = $16,168,882

Attch. MM Rev. Req. = $4,373,580

2014 TRANSMISSION PROJECTS

ATTACHMENT O CAPITAL PROJECTS: TRANSMISSION LINE PROJECTS > $200K

17

Project Forecasted 2014 Capital

Addition

Actual 2014 Capital

Addition$ Change % Variance Reason for Variance

Circuit Breaker Replacements $300,000 $277,949 ($22,051) -7.4% Tracking close to budget.

Rejected Pole Replacements $500,000 $635,533 $135,533 27.1% Material purchases for 2015 projects accelerated into 2014.

Parshall Area 115 kV Source $1,151,478 $197,929 ($953,549) -82.8% Project delayed due to stalled negotiations with a third party.

Summit 115/41.6 kV Transformer Replacement $252,012 $348,791 $96,779 38.4% Progress payments to third party

resulted in more spend in 2014.

Proactive Worst Performing Lines $319,688 $383,701 $64,013 20.0% Material purchases for 2015 projects accelerated into 2014.

Proactive Relay Upgrade $200,000 $89,136 ($110,864) -55.4% Resource constraints did not allow for all of this work to get completed.

ATTACHMENT O CAPITAL PROJECTS: TRANSMISSION LINE PROJECTS > $200K

18

Project Forecasted 2014 Capital

Addition

Actual 2014 Capital

Addition$ Change % Variance Reason for Variance

Oakes Area Transmission Improvements $3,153,332 $3,562,015 $408,683 13.0% Poor soil conditions led to a change

in the design of the structures.

Devils Lake – Spirit Lake 41.6 kV Line $532,031 $614,686 $82,655 15.5% Permit conditions required a change in the project design.

Winger – Thief River Falls 230 kV Line $60,000 $0 ($60,000) -100.0% Refreshed load projections allowed for a delay in the project.

Clearbrook – Solway 115 kV Line $1,045,000 $233,108 ($811,892) -77.7%Project was placed on hold due to addressing an expanded need for the project.

Transmission Line Capacity Upgrades (NERC Alert) $6,800,826 $3,634,674 ($3,166,152) -46.6% Engineering efforts delayed the

initiation of construction work.

ATTACHMENTS GG AND MM CAPITAL PROJECTS: TRANSMISSION LINE PROJECTS > $200K

19

Project Forecasted 2014 Capital Addition

Actual 2014 Capital Addition $ Change % Variance Reason for Variance

Attachment GG

Buffalo – Casselton 115 kV Line $7,199,999 $1,996,629 ($5,203,370) -72.3% Underlying improvements delayed to analyze design opportunity.

Fargo – St. Cloud 345 kV Line $22,939,882 $20,855,423 ($2,084,459) -9.1% Tracking close to budget.

Bemidji – Grand Rapids 230 kV Line $0 $221,612 $221,612 100.0% Financial close of the project resulted in a true-up of final costs.

Attachment MM

Brookings – Hampton Line $6,505,790 $6,304,795 ($200,995) -3.1% Tracking close to budget.

Big Stone South – Brookings Line $2,420,065 $2,967,388 $547,323 22.6% Easement payments for land rights occurred prior to forecasted.

Big Stone South – Ellendale Line $3,696,143 $2,971,198 ($724,945) -19.6% Obtaining project permits took longer than forecasted.

QUESTIONS?

If you have any additional questions after the meeting, please submit via e-mail to:

Kyle Sem, CPA

Manager – Business Planning

[email protected]

All questions and answers will be distributed by e-mail to all attendees. Additionally, the questions and answers will be posted on Otter Tail’s

OASIS website (http://www.oasis.oati.com/OTP/index.html) within two weeks from the date of inquiry.

20