JANUARY 14 TH 2019 ARLINGTON HIGH SCHOOL BUILDING PROJECT Schematic Design: Project Update and Cost Discussion www.ahsbuilding.org

Upload: others

Post on 20-Jul-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

J A N U A R Y 1 4 T H 2 0 1 9

ARLINGTON HIGH SCHOOL BUILDING PROJECT

Schematic Design:Project Update and Cost Discussion

www.ahsbuilding.org

Page 2: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Project Overview• Schematic Design Update• Sustainability Update• Q&A

• Cost Discussion• Q&A

Agenda

Page 3: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

The AHS Facility Today

More than just a High School

Does not meet educational needs

Deteriorating facility (NEASC Warning)

Page 4: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Menotomy Preschool• Integrated preschool, ~100 students

• LABBB Collaborative• Partnership with Lexington, Belmont,

Bedford and Burlington• Arlington Community Education• Town/School offices

• IT, Facilities, Comptroller, Payroll• Education-related operations

• School District offices• Compact site of only 22 acres

Other Uses and Challenges

Page 5: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

Statement of Interest (SOI)

MSBA Invites Arlington to Eligibility Period

AHS Building Committee formed

Schematic Design

Process

2015

2016

2017

2018

Page 6: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• 1,755 design enrollment• Dictates # of homerooms

• Goal is to ensure large enough common spaces to accommodate growth

• Library, Gym, Auditorium, Cafeteria, etc.• 4,300 => ~6,000 Arlington students

in last 15 years

Enrollment

Page 7: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• School building is welcoming, accessible, easy to navigate• Large, central learning commons (aka library) allows research,

collaborative group work• Hands-on experience in STEM/STEAM

(Science, Technology, Engineering, Arts, Math)• Project-based and personalized learning• Up-to-date technology throughout school• Many different, new kinds of spaces: gathering, display, breakout,

performance

Educational Vision – Basis for Design

Page 8: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• All new building best suits educational vision and enrollment growth

• Build on a portion of the front lawn to shorten project and minimize student disruption

• STEAM and Auditorium front wings finished by January 2022

Design Decisions

Page 9: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Site, façade, interior design are being finalized now

Schematic Design

??

?

Page 10: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

AHS Partiparti = the general scheme of an architectural design

A R L I N G T O N H I G H S C H O O L

humanities

STEAM

athletics

performingarts

Page 11: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

Central spine concepts

A R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 1 / 1 4 / 2 0 1 9

Page 12: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

Mass Avenue Exterior Design Concepts

A R L I N G T O N H I G H S C H O O L

Page 13: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

A R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 0 1 / 1 4 / 1 9A

Page 14: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

AA R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 0 1 / 1 4 / 1 9

Page 15: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

AA R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 0 1 / 1 4 / 1 9

Page 16: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

B A R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 0 1 / 1 4 / 1 9

Page 17: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

BA R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 0 1 / 1 4 / 1 9

Page 18: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

BA R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 0 1 / 1 4 / 1 9

Page 19: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

CA R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 0 1 / 1 4 / 1 9

Page 20: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

CA R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 0 1 / 1 4 / 1 9

Page 21: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

CA R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 0 1 / 1 4 / 1 9

Page 22: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

Schematic Site Plan Development

A R L I N G T O N H I G H S C H O O L

Page 23: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

A R L I N G T O N H I G H S C H O O LD R A F T C O N C E P T 0 1 / 1 4 / 1 9

S ite Plan2 2 7 p a r k i n g s p a c e s

b a s e b a l l

M a s s A v e

M M B i k e w a y

s o f t b a l l

e x i s t i n g

s t a d i u m

a m p h i t h e a t e r

d e l i v e r i e s

n e w

s c h o o l

p r e s c h o o l

p l a y & d r o p o f f

c o u r t y a r dM a s s A v e

e n t r y

f i e l d s e n t r y

Page 24: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Achieve net-zero energy operation• Design for an all-electric building• Create a healthy indoor environment

• Ample daylight• No- and low-VOC materials and finishes

• Sustainability is integral to the overall design of the building

Sustainability Update – Goals

Page 25: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Pilot program with Eversource and National Grid• Provides us with FREE technical support and additional

financial incentives• Adopt aggressive, but realistic, energy use targets early in the

design process• Site energy use intensity (EUI) at least 25% lower than code compliant

building• Targeting ~40% reduction

• Achieve desired energy performance at no or low incremental cost

Accelerate Performance Program Overview

Page 26: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Passive design (very efficient building envelope)

• Reduce lighting and plug loads

• Geothermal heat pumps for efficient heating and cooling

• Rooftop solar (~2x what is currently at AHS)

• Good energy management & user engagement

• Also:

• Minimize energy use “after-hours”

• Design for ease of maintenance / low maintenance costs

Some Key Energy Features

Page 27: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

Sustainability Update

Page 28: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Direct access to Minuteman Bikeway• Provide some covered bicycle parking

• Plan ahead for electric vehicle future• >75% diversion of construction & demolition debris from landfills

(goal of 95%)• Salvage & donate old furniture• 100% recovery of food waste from cafeteria• Low-flow water fixtures• No-irrigation landscaping

Additional Sustainability Features and Goals

Page 29: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Questions & Answers on educational vision, design, site plan, sustainability

Project Update – First Discussion Break

Stay Updated atwww.ahsbuilding.org

Page 30: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

Cost Cutting Measure Amount Effect

Selection of Design Option 3A – New Building (Option 1 - retain original buildings more expensive)

$25M Reduces overall project cost

LEED Certification Goal $3M - $4M Increased MSBA reimbursement

Construction Manager at Risk approach $1M - $2M Increased MSBA reimbursement

Proactive Building Maintenance Budget $3.5M - $4.5M Increased MSBA reimbursement

Relocation of Comptroller, Facilities and IT offices $6M - $7M Reduction in Arlington’s share of the project

Accelerate Performance partnership $200,000+ in energy rebates

Reduction in lifecycle costs of building

Cost Reductions Already Made

Page 31: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Former elementary school – closed 1983• Leased to Arlington Children’s Center (ACC) for 30+ years• HMFH studied feasibility of Parmenter as:

• Temporary location for Preschool• Permanent location for Preschool• Permanent location for District Administration

Parmenter School

Page 32: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Classrooms are smaller than MSBA guidelines unless use ACC space; acceptable for temporary location but not permanent

• Permanent relocation would require ACC moving elsewhere• Requires upgrades

• Elevator, new furnace, electrical upgrades• ACC’s lease runs until 2024• Even if used ACC’s portion of the building, it would not include

enough classrooms for growing Menotomy Preschool program• District Admin spaces at AHS provides ‘future-proof’ solution for

enrollment growth

Parmenter School - Considerations

Page 33: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Town Offices• Comptroller => Town Hall• IT, Facilities => New DPW facility

• Remaining non-AHS spaces• Payroll, School District Administration,

Menotomy Preschool, Community Ed.• Evaluation of other Town buildings

Status: Non-AHS Spaces

Page 34: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Project cannot and will not exceed $308M

• Building Committee will discuss refined estimates at Jan. 29 and Jan. 31 meetings

• If cuts need to be made, school administration and School Committee will provide priorities

Value Engineering

Page 35: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

Arlington HSWaltham HS

(Vocational Included)

Belmont HS (Upper Middle

Included)

Saugus HS-MS (Upper Middle

Included)

Somerville HS (Vocational Included)

Total Project Cost

Escalated to AHS

Schedule

$308M $381M $339M $189M $291M

Construction Cost

Per Sq. Ft. $573 Unknown $585 $533 $597

Project Cost Per

Pupil $175,657 $208,356 $153,310 $138,862 $183,196

High School Benchmark Analysis (PSR)

Note: Analysis is based on PSR estimates and all are escalated to AHS schedule. Visit www.ahsbuilding.org for full analysis and sources.

Page 36: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

ProjectCompletion

DateConstruction

CostConstruction

Cost Escalated to AHS Timeline

Total Escalated Cost with Soft

Cost Factor (1.3)

Newton North

HS

2010 $166M $286M $371M

Thompson

School

2013 $15M $23.2M $30.1M

Gibbs School 2018 $19M $22.9M $29.8M

Minuteman

Regional HS (~600 students)

2020 $121M $144M $186M

Cost Escalation

Refer to http://www.arlington.k12.ma.us/administration/ahsfacilities/pdfs/cost/msbaprojbenchmarks01-14-19.pdf for more detail.

Page 37: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

Dwelling Average Assessed Value (Jan. ‘19)

Annual Tax Impact (full load)

Condominium $464,795 $511

Single Family Home $752,184 $827

2 Family Home $860,758 $946

3 Family Home $915,450 $1,006

Estimated Taxpayer Impact

Page 38: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

February Submit scope & budget to MSBA

April MSBA approval 120 days for local funding

2019 -2020 Design Development

2020 - 2025 Construction Jan. 2022 New Auditorium, STEAM

Next Steps

Page 39: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• We have a chance to shape the future• Meets 21st century Educational Vision• Addresses enrollment growth

Conclusion

Stay Updated atwww.ahsbuilding.org

Page 40: ARLINGTON HIGH SCHOOL BUILDING PROJECT · LEED Certification Goal $3M -$4M Increased MSBA reimbursement Construction Manager at Risk approach $1M -$2M Increased MSBA reimbursement

1/14/19ARLINGTON HIGH SCHOOL BUILDING PROJECT

• Visit www.ahsbuilding.org for updates• Blog Posts are in-depth articles about topics of interest• Sign up for e-Bulletins• Follow us on Facebook

Stay Updated & Engaged