apvia q4 2016 market reportnews_htest.snec.org.cn/upload/files/apvia q4 2017... · apvia q4 2017...
TRANSCRIPT
-
APVIA Q4 2017 Market Report
With the support of the PV Market Alliance
-
Introduction
• Launched in 2017, this 4th edition of APVIA’s quarterly PV market report focus on “fiveselected Asia countries”, anticipated to witness solid growth in terms of additionallyadded solar PV power generation capacity throughout 2017, 2018 and beyond
• This report focuses on “China, Japan, Malaysia, Thailand, Vietnam” and theimportance of renewable energy in its energy mix in general as well highlights andtrends regarding solar PV in particular
• This report has been prepared with information provided by the PV Market Allianceand especially Asia Europe Clean Energy (Solar) Advisory Co. Ltd. (AECEA)
• All information collected are valid at the time of publication. The data published donot engage the responsibility of APVIA or AECEA and should be considered with all duecaution and are for informational purposes only 2
-
China – A Host of Up/Downstream Policies in Place since early 2000
Upstream Sector
• Early 2000 – Identification of so-called “7 Strategic Emerging Industries (SEI)” • SEI’s contribution to China’s GDP: 5% (2010) to 8% (2015) and 15% (2020) • Guiding Principle: From “Made in China” to “Designed in China” to “Global Leadership”• 12th FYP (2011-2015) : Central/Local Govt. & Private Sector Investment: USD 1.4 trillion foreseen • Since 2006 – every 5th Year-Plan just gets “greener”
3
Downstream Sector
• Since 2006 – Renewable Energy Law • Since 2008 – Power Surcharge is being levied on Commercial & Industrial Power User • Since 2008 – FIT Policy• Since 2010 – Domestic Market Expansion Program launched (Demo-Projects, Golden Sun Program,
RE-Hybrid Projects, Top-Runner Program, etc.
-
China – 12th Five-Year-Plan (2011-2015) –Plan vs. Reality
4
5
10
14
20
35
23,5
10,95 10,6
15,13
2,9
6,5
17,45
28,05
43,18
75
313
43
-3
0
5
10
15
20
25
30
35
40
45
50
2011 2012 2013 2014 2015
-50
0
50
100
150
200
250
300
35012th Five-Year-Plan (2011-2015) Solar PV Target (GW)
Annual Installations (GW)
Cumulative Installations (GW)
Annual Change (%)
• Unprecedented in Chinese history, a national five year plan target were increased four times over its five year plan period
• Due to the introduction of a FIT scheme the market exceeded its expectations and annual guiding target set by the govt.
Source: AECEA
Diagramm1
2011201120112011
2012201220122012
2013201320132013
2014201420142014
2015201520152015
12th Five-Year-Plan (2011-2015) Solar PV Target (GW)
Annual Installations (GW)
Cumulative Installations (GW)
Annual Change (%)
5
2
2.9
10
3.5
6.5
75
14
10.95
17.45
313
20
10.6
28.05
-3
35
15.13
43.18
43
Tabelle1
12th Five-Year-Plan (2011-2015) Solar PV Target (GW)Annual Installations (GW)Cumulative Installations (GW)Annual Change (%)
2011522.9
2012103.56.575
20131410.9517.45313
20142010.628.053
20153515.1343.1843
Tabelle1
12th Five-Year-Plan (2011-2015) Solar PV Target (GW)
Annual Installations (GW)
Cumulative Installations (GW)
Tabelle2
12th Five-Year-Plan (2011-2015) Solar PV Target (GW)Annual Installations (GW)Cumulative Installations (GW)Annual Change (%)
2011522.9
2012103.56.575
20131410.9517.45313
20142010.628.05-3
20153515.1343.1843
Tabelle2
12th Five-Year-Plan (2011-2015) Solar PV Target (GW)
Annual Installations (GW)
Cumulative Installations (GW)
Annual Change (%)
Tabelle3
-
China – Uneven Quarterly Demand
5
June 30 -Deadline
2017 FIT ReductionAnnounced June 30 - Deadline 2017 FIT Effective
• Due to the nature of the Chinese legislative framework, the full year demand is characterized by an uneven quarterly demand
• Quarterly installation volumes can vary significantly
• Projects have to be grid-connected before June 30, in order to be eligible for past years FITs
Source: AECEA
-
China – Distributed Generation is Taking Off
6
6,2
19,3
9,212,2
36
0
5
10
15
20
25
30
35
40
45
50
2013 2014 2015 2016 2017e
Utility-Scale (GW)
Distributed (GW)
Total (GW)
DG Share of Total (%)
• Due to institutional, technical and economical reasons, past years installations volumes regarding commercial & industrial rooftop systems were significantly smaller compared to ground-mounted PV power plants
• In 2017, estimates suggests that possibly 18-19 GW of distributed PV could be installed
Source: AECEA
-
China – Residential Markt Prospects
7
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
2015 2016 2017 2018 2019 2020
MW
Number of Households(1000)
• To date, China’s residential solar PV market is in an infant stage
• Due to institutional, technical and financial reasons the total installed capacity of residential solar PV systems amounts to just a few hundred MWs
• Recently, numerous banks started to offer corresponding financial packages
Source: AECEA
-
China - Pilot Direct Power Sales for Distributed Generation Operational by Feb 2018
• Nov 2017: Chinese govt. proposed to establish a pilot direct power sales scheme specifically designed for distributed generation, notably wind and solar of less than 50 MW power generation capacity
• Solar farms will be eligible for DG subsidy • Solar projects are required to offer a no less than 10% subsidy discount for projects up to 20 MW • Solar projects are required to offer a no less than 20% subsidy discount for projects btw. 20-50 MW• A grid connection fee is to be paid to the grid companies • Detailed local pilot schemes Dec 2017, trading Feb 2018, July 2018 potential wider, national application • Aim: encourage local renewable power consumption and accelerate grid parity for wind and solar• Pilot scheme criteria: 1) high power demand regions with good grid infrastructure that can dispatch
renewable energy locally and to large cities, industrial parks, new cities and other economic
development zones. 2) regions with red alerts for wind and solar (or regions with over 5%
curtailment ratio) will not be applicable for such pilot schemes8Source: AECEA
-
China – Market Prospects till 2020
9Source: AECEA
-
Japan – Key-Points of Revised FIT Law
10
Distributor Transmission & Distribution Operator
Exemption rate based on energy efficiency efforts
Disclosure of connection capacity and price of GC work
More transparent rules for grid connection
Disclosure of supply and demand information
Guideline for grid connection
Framework to comply related laws and regulations
Addressing safety of PV systems O&M
New approval scheme for business plan
Addressing delayed/ unrealistic projects
Middle term price target
FIT level for multiple years
Tender program
Setting rules for FIT level
New approval scheme
Off-takers of RE power
Transparency for grid connection (GC)
Exemption of surcharge
• Effective since April 2017
Source: RTS Corporation
-
Japan – Revised FIT Law cause Cancellations
11
• As of March 2017:
• Possibly up to 30 GW of the 50 GW pipeline will be cancelled due to the revised FIT Law effective since April 2017
Source: RTS Corporation
-
Japan – Changes of Approval Scheme
12
Approval of Facility
Previous FIT Program
Approval of Project Business Plan
New FIT Program
1) The project contributes to promoting the use of electricity from renewable energy2) The project is expected to be smoothly and surely conducted3) The project is expected to realize stable and efficient power generation
Requirements for approval under the new FIT programTo be approved by the Minister of METI,the “Project Business Plan” must satisfy the following:
Guidance, Advice(Article 13)
Order for Improvement(Article 14)
Revocation of Approval(Article 15)
In case of violating the issues to be “observed”, the following measures may be taken:
Violation of issues to be “observed” in the govt & ministerial ordinancesas well as guidelines may result in revocation of approval.
Source: RTS Corporation
-
Japan – Summary of Tender Scheme
• Tender for the right to apply for FIT approval
• Tender for the Feed-in tariffs (FIT) and the system capacity (the unit of tender price is Yen/kWh: submission is accepted with the unit
of 0.01 Yen at minimum, the unit of system capacity is MWAC: AC capacity)
• The ceiling bidding price is limited to the FIT for 10 kW - < 2 MW capacity range (the ceiling bidding price for FY 2017 is 21 Yen/kWh =
16.8 Eurocent/kWh)
• A uniform tender throughout Japan (not by region)
• Tender document was published end of June. Revised document issued in September and bidding application started in October.
• ≥ 2 MW extra high voltage projects are subject to the tender scheme
on or after January 21, 2017, normal application for approval of extra high voltage projects are not accepted (only tenders)
• Methodology to decide FITs: Pay as Bid
• After winning the bid, application for FIT approval shall be submitted within 1 month and approval shall be acquired within 3 months13Source: RTS Corporation
-
Japan - Eligibility Criteria for Tenders
• The grid connection capacity is secured (signing of grid connection contract is not essentially required, but application forapproval is not accepted if contract is not concluded immediately after winning the tender)
• The criteria for approval : same as the new FIT criteria
• Explanation of the project plan, etc. to the relevant municipality is necessary (briefing to local residents is required)
• Compliance with permission and authorization, etc. under other laws and regulations
• The first guarantee deposit (500 Yen/kW) + handling charge for participating in the tender and second guarantee deposit (5,000 Yen/kW) when winning the tender are required to be paid (they will be refunded in case the development of project runs smoothly)
14
First Tender Results Nov 2017
• Nov 22, 2017: Japan’s Ministry of Economy, Trade and Industry (METI) has awarded 140 MW of solar capacity to eight companies across nine locations, with the lowest bid coming in at JPY 17.2 ($0.15)/kWh
• The lowest successful bid was roughly 28% lower than the feed-in tariff (FIT) rate of JPY 24 (around US$0.214) that the government offered throughout the last fiscal year
• The highest successful bid in the country’s first reverse auction for solar came in at JPY 21/kWh
• METI plans to hold two bidding rounds per year from fiscal 2018 onwardsSource: RTS Corporation
-
Japan – FY 2030 Prospects
15
• Several factors will influence the forecasting of the to be installed solar PV capacity till 2030
-
Japan – Forecast of Installed PV Capacity
16
• Business as Usual (BAU) scenario is were policy, deregulation, technology development, etc. continue according current trajectory
• Accelerated Scenario is the case were ambitious policy is introduced and deregulation significantly advanced, dev of various BOS technologies make progress
• Paradigm Shift Scenario is the case were accelerated policy is introduced and obstacles such as grid integration is solved combined with technological advancement
Source: RTS Corporation, http://www.rts-pv.com/uploads/2016/10/Forecast-FY-2020_FY2030_2017.pdf
-
Japan – Paradigm Shit Scenario till 2030
17Source: RTS Corporation, http://www.rts-pv.com/uploads/2016/10/Forecast-FY-2020_FY2030_2017.pdf
-
Japan – 150 GW by Fiscal Year 2030
18
• Several factors will influence the forecasting of to be installed solar PV capacity till 2030
Source: RTS Corporation
-
Malaysia – A Decade of RE Promotion
• 9th Malaysia Plan (2006 – 2010)• Target RE: 300 MW – Peninsular Malaysia plus 50 MW – Sabah (East Malaysia)• 61.2MW (17% from 9th MP target through Small Renewable Energy Programme (SREP)• Cabinet approved National RE Policy & Action Plan (October 2010)
• 10th Malaysia Plan (2011-2015)• Enactment of RE Act 2011 & SEDA Act 2011 (27 & 28 April 2011)• Establishment of SEDA, implemented Feed-in Tariff (FIT)• 2015: Energy mix 43% coal, 40% gas, 14% large hydro, 2% RE, 1% oil
• 11th Malaysia Plan (2016-2020)• Target energy mix of 53% coal, 29% gas, 15% large hydro, 3% RE.• Target RE (FIT) capacity of 2,080 MW• Introduce Net Energy Metering (NEM)
19Source: SEDA
-
Malaysia – PV Market Development Stages
20Source: MPIA; * SEDA Malaysia = Sustainable Energy Development Authority Malaysia
Installed Capacities
SURIA1000 program : 1.25MWp
FIT program : 345.35MWp (installed as of 19 October 2017 (2012 – 2017)
Net-Energy-Metering (NEM) : 5.44MWp (installed as of 19 October 2017 (Target 500MW by 2020)
Large-Scale-Solar (LSS) : 1250MW (Target by 2020)
Service Provider : 121 (companies registered with SEDA Malaysia* as of 3 October 2017)
2006 – 2010SURIA1000
2011 – 2016Feed-in Tariff
(FIT)
2016 - Present- Large Scale Solar (LSS)- Net Energy Metering (NEM) - Self-consumption (SELCO)
-
Malaysia – PV Market Development
21Source: MPIA
-
Malaysia – PV Market – Status Quo
22
• As of August 2017:
• 344 MW operational
• 892 MW approved by Govt.
Source: SEDA
-
Malaysia – Large-Scale Solar Auction Scheme
23
• Available Quota: 360MWac (x 4) in Peninsular Malaysia
• 100MWac (x 2) in Sabah (commercially operational by 2019-2020);
• Exchange rate: US$1 = RM4.21
Source: SEDA
-
Malaysia – Current FIT Structure
24
• FIT Rate for Solar PV (2017):
• US$1 = RM 4.21
Source: SEDA
-
Malaysia – Current Market Challenges
25Source: MPIA
Net Energy Metering (NEM) Self-Consumption Large Scale Solar PV (LSSPV)
1: LOW DISPLACED COST = LOW EXPORT RATE LV Connection: RM 0.31/kWh (Peninsula), RM 0.30/kWh (Sabah)MV Connection: RM 0.23/kWh (Peninsula), RM 0.22/kWh (Sabah)
2: 1 MW INSTALLATION CAP
3: GST COMPLICATIONHousehold/individuals issuing GST invoiceNO Tax refund for household/individualAdditional administration cost for ALL parties involved
4: NEM METER COSTLY FOR SMALL INSTALLATION (Example: Less than 3kWp)Especially for residential – RM 950/unit + 6% GST
1: REGULATIONSRequirement for SCADA monitoring system for installation above 1MW
Requirement for Power Supply Study (PSS) for installation above 425kW
1: LIBERALISATIONNon-compliance by foreign EPCs to nationally-accepted standards
Local companies not being given chance to grow
-
Thailand – 10 yrs of solar PV Policies
26Source: GIZ
-
Thailand – Sound Market Development
27
Key DriversPolicy/Schemes + Attractive tariffsDecreasing CAPEX
Key BarriersQuota limitationsSpontaneous announcement of schemes
2017 Projection = 500 MWGround Mount: 200 MWRooftop: 300 MW
Source: GIZ
-
Thailand – Upcoming New Market Trends
28
Ground-Mount
Agro-SolarPhase 2
SPP Hybrid
Self-Consumption
• FiT: 4.12 THB/kWh [€0.11/kWh]• Project Size: 5 MW per project• Quota: 219 MW• PPA term: 25 years with DSO• Condition: Private Public Partnership (PPP)
• Electricity must be 100% consumed on-site• No feed in of electricity to the grid
Rooftop
• FiT: Ceiling price 3.66 THB/kWh [€0.10/kWh]• Project Size: 10-90 MW (Small Power
Producer)• Quota: 300 MW• PPA term: 20 years with TSO• Possible to hybridize different RE and energy
storage under one PPA(To be announced late 2017-2018)
Net-Metering
• Export of electricity is allowed & compensated for
• Rates are under consideration, expected to be
-
Thailand – Self-Consumption Rooftop Market
Self-Financed• Large corporations are going solar• Tesco Lotus installed 10 MW in 2016 and 20 MW more in 2017
Third-Party Financing/Ownership• Private-Private PPAs/Leasing models are emerging• Giving 10-15% discounts off retail electricity prices [€0.10/kWh]• Largest Deal today: 15 MW at Thammas University
29
Current Market
Self-Financed:100-200 MW
Third Party:50-100 MW
70%
30%
Source: GIZ
-
Thailand – Long-term Prospect till 2040
30
• Thailand’s power system will transform dramatically over the next 25 years
• Of the 67GW of new power capacity in 2040, 39% will be solar PV, which will surge tenfold to 27.8GW by 2040 to account for 30% of total installed capacity
• Cost of solar PV will become cost competitive with gas and coal generation within 10-15 years
-
Viet Nam – A Booming Economy needs Power
• Economy guided by 5-Year Plans
• 1986 launch of political and economic reforms “Doi Moi”
• Average GDP Growth Rate 2005-2015: ≈ 6.1%
• 2005-2015 Average Electricity Demand Growth Rate: 12%
• 2010-2017 Average Power Loss: 8.1%
• 2016-2020: Socio-Economic Development Strategy (SEDS) Targets
• Average Annual GDP Growth 6.5 – 7%
• Industry (40%) and Services (45%) account for 85% of GDP
• Urbanization Rate: 40%• 2016-2020 Average Electricity Demand Growth Rate: 10.5%
• 2021-2030 Average Electricity Demand Growth Rate: 8%31Source: AECEA
-
Viet Nam – National Power Development Plan
National Power Development Plan VII rev (2016-2030) – USD 148 bln Investment
32
• Strong Focus on RE and Power Market Liberalization | Former RE Targets: 2020 (4.5%) | 2030 (6%)
• Total Power Generation Capacities: 2016 (39 GW) | 2020 (60 GW) | 2025 (96 GW) | 2030 (135 GW)
• RE Targets excluding large/medium-scale + pumped hydro storage
• 2016-2020 investment foreseen amounts to USD 40 bln (75% power generation + 25% grid network upgrade)
Source: AECEA
-
Viet Nam – High Levels of Solar Irradiation
Blessed with High Levels of Solar Irradiation
• (GHI) Irradiation range btw. 3 to 5.6 kWh/m2/day
• (GHI) Annual daily average 3.4 – 3.8 – 4.8 kWh/m2/day
• (DNI) Irradiation range btw. 2.1 to 5.1 kWh/m2/day
• (DNI) Annual daily average btw. 2.5 – 4.2 – 4.7 kWh/m2/day
• Northern Viet Nam: 1,460-1,825 kWh/m2/a
• Southern Viet Nam: up to 2,000 kWh/m2/a
• Total sunlight hours 1600 to 2700 hrs/a
• Theoretical Potential for solar PV btw. 0.9 to 1.2 GWh/a
• Due to mountainous terrain, 1/3 unsuitable for solar PV
• Total technical solar potential est. 13 GW or 18 TWh/a 33Source: AECEA
-
Viet Nam – Energy Sector Landscape
• Vietnamese Govt and Prime Minister: policies, regulations, strategies and plans designed for the development of the renewable energy sector
• Ministry of Industry and Trade (MoIT): manages all energy sectors, such as coal, oil, gas, electricity, nuclear energy and renewable energies. Responsible for policy design and national plans subject to Prime Minister’s approval
• Ministry of Planning and Investment (MPI): lead role in coordinating and allocating funds for energy projects submitted by line ministries and agencies, for consideration and approval by the Prime Minister
• Ministry of Finance (MoF): taxation / energy tariff policies applied to the energy sector
Viet Nam’s energy sector is subject to a complex institutional structure
34
Electricity Regulatory Authority of
Viet Nam
Provincial Dept. of
Industry and Trade (DoIT)
General Directorate of Energy
Electricity of Vietnam
Group (EVN)
Institute of Energy
New and Renewable
Dept.
Source: AECEA
-
Viet Nam – Long-Term Solar Targets till 2030
National Mid and Long-Term Solar Targets till 2030
35Source: AECEA
-
Viet Nam – Policy Toolbox
Policy Toolbox Designed to Support Renewable Energy Development
• 11/2015: The Renewable Energy Development Strategy till 2030 (with vision to 2050) approved• Establish a fund for sustainable energy development • Develop & establish a Feed-in-Tariff (FIT) scheme for on-grid renewable energy• Develop & establish a Power Purchase Agreement (PPA) based scheme• Implementation of a Net–Metering scheme• Implementation of a Renewable Portfolio Standard (RPS) system (planned):
• Share of electricity generated from renewable sources for power utilities with capacities larger than 1 GW (excluding BOT);
• by 2020 no less than 3% | by 2030 no less than 10% | by 2050 no less than 20% • Share of power purchased from renewable energy sources from power distribution network utilities; • by 2020 no less than 5% | 10% by 2030 | 20% by 2050
• Provisions to offer other incentives, e.g. tax, land, environment, etc. 36Source: AECEA
-
Viet Nam – Renewables are Special
Investment Law Tax Incentives – Renewables are Special Encouraged Industries
Fiscal and Additional Incentives for Renewable Energy Projects – Excerpts • Preferential corporate tax rates / Accelerated depreciation rates / 0% VAT for RE projects• Exemption from import tax on equipment and materials • Export credits for up to 70% of construction cost (credit for 12 years, benchmarked to govt bond interest rates) • CDM projects comply with Kyoto Protocol are entitled to additional support measure e.g. land rent exemptions • Housing Law/Real Estate Business Law “land-use rights” – Foreign Investors can lease land up to 50 years/up to 70 years in areas 37
CorporateIncome Tax (CIT) Rate
CIT Availability(Years)
CIT Exemption Holiday (Years)
50% Reduction of CIT (Consecutive years after tax exemption period)
Encouraged Sectors 20 10 2 3
Encouraged Areas 20 10 2 6
Encouraged sectors in Encouraged Areas 15 12 3 7
Special Encouraged Industries and Special Encouraged Areas 10 15 4 9
Source: AECEA
-
Viet Nam – Current PV Market Structure
38
• Current total installed solar PV capacity amounts to approx. 10-15 MW • Approx. 20% are grid-connected installations • A few pilot / demonstration medium/large size systems of more than 50 kWp• First commercial investment such as: Avery Dennison (ex-PUMA, 100kW); Intel Corp.
(220kW); X Power (40kWp); Big C Binh Duong (212kWp); DBW (165kWp) … • Prevailing Business Model: Self-Consumption
• Approx. 80% are off-grid installations • 60-70% small applications e.g. SHS + solar public lighting systems• 30-40% are bigger systems, such as local solar network stations
and off-grid hybrid systems in remote areas or on islands
Source: AECEA, Rainer Brohm
-
Viet Nam – Low Retail Electricity Tariffs
39
37
11 12 11 12
34
117,6
0
5
10
15
20
25
30
35
40
Brazil China India Indonesia Malaysia Philippines Thailand Viet Nam
Average power tariff (USD cents/kWh)
• Business sector pays up to USCents 18/kWh during peak hrs
• Investments in solar PV rooftop systems for self-consumption are already financially feasible
• Equity payback times of 6-10 years are possible in certain sectors
• Net metering will further enhance attractiveness of investmentsSource: AECEA
-
Viet Nam – FIT Scheme announced April 2017
• The FIT Scheme applies for both, ground-mounted and roof-top solar PV systems
• Technical Requirements: cell efficiency 16%; module efficiency over 15%
• FIT: VND 2.086/kWh = USCents 9.35/kWh exclusive VAT (as of April 10, 2017)
• FIT: Subject to VND-USD exchange rate fluctuations | PPA 20 year period
• Roof sys subject to bi-directional net metering, excess electricity can be sold at FIT rate
• Projects with a capacity larger than 50 MW requires Prime Minister approval
• April 2017 decision is valid from June 2017 through June 2019
• September 2017 the Vietnamese authorities, in cooperation with the World Bank, have revealed plans to launch a pilot auction program for solar projects. It plans to set a floor price of $0.0935/kWh for the trial auctions, with the aim of launching the pilot phase before the country’s current feed-in tariff (FIT) rates expire in June 2019
40Source: AECEA
-
Viet Nam – FIT Scheme Challenges
41
• VND-USD exchange rate – no indexation of the FIT to e.g. address inflation risks
• Vietnam Electricity (EVN) serves as the sole off-taker – creditworthiness not sufficient
• PPA: EVN is not required to purchase or off-take electricity e.g. during grid maintenance
• PPA: non-utility customer e.g. industrial parks / manufacturer can not directly buy
• PPA: existing standardized PPA template for wind/biomass – considered non-bankable
• No project distinction, e.g. different scale or btw. utility-scale / self-consumption resi
• Rooftop: rate at which surplus is being purchased by EVN is unclear
• Grid connection costs and associated risks e.g. line loss
• June 2019: could witness a potential retroactive adjustment of the FIT
Source: AECEA
-
Courtesy
42
• Market data have been collected and analysed by members of the PVMarket Alliance.
• Special thanks to RTS Corporation / Japan for providing content!• More information: [email protected]• www.pvmarketalliance.com
mailto:[email protected]://www.pvmarketalliance.com/
APVIA Q4 2017 Market ReportIntroductionChina – A Host of Up/Downstream Policies in � Place since early 2000 China – 12th Five-Year-Plan (2011-2015) – � Plan vs. RealityChina – Uneven Quarterly Demand China – Distributed Generation is Taking Off China – Residential Markt Prospects China - Pilot Direct Power Sales for Distributed � Generation Operational by Feb 2018 China – Market Prospects till 2020 Japan – Key-Points of Revised FIT LawJapan – Revised FIT Law cause CancellationsJapan – Changes of Approval SchemeJapan – Summary of Tender SchemeJapan - Eligibility Criteria for TendersJapan – FY 2030 Prospects Japan – Forecast of Installed PV Capacity Japan – Paradigm Shit Scenario till 2030Japan – 150 GW by Fiscal Year 2030 Malaysia – A Decade of RE Promotion Malaysia – PV Market Development Stages Malaysia – PV Market Development Malaysia – PV Market – Status QuoMalaysia – Large-Scale Solar Auction SchemeMalaysia – Current FIT Structure Malaysia – Current Market Challenges Thailand – 10 yrs of solar PV Policies Thailand – Sound Market Development Thailand – Upcoming New Market TrendsThailand – Self-Consumption Rooftop MarketThailand – Long-term Prospect till 2040 Viet Nam – A Booming Economy needs PowerViet Nam – National Power Development Plan Viet Nam – High Levels of Solar IrradiationViet Nam – Energy Sector Landscape Viet Nam – Long-Term Solar Targets till 2030Viet Nam – Policy Toolbox Viet Nam – Renewables are Special Viet Nam – Current PV Market Structure Viet Nam – Low Retail Electricity Tariffs Viet Nam – FIT Scheme announced April 2017Viet Nam – FIT Scheme ChallengesCourtesy