![Page 1: APS Electric Vehicle Charging Pilots · APS Electric Vehicle Charging Station Pilots 3 Unmanaged Passenger EV Charging Load Shape Take Charge AZ 4 Level 2 EV Charger Pilot 2019 Fleet,](https://reader034.vdocuments.site/reader034/viewer/2022051806/5ffdb8a320b2c00b1526322d/html5/thumbnails/1.jpg)
APS Electric Vehicle Charging Pilots
C.J. BergEnergy Innovation Analyst
Customer Technology – Product Development
![Page 2: APS Electric Vehicle Charging Pilots · APS Electric Vehicle Charging Station Pilots 3 Unmanaged Passenger EV Charging Load Shape Take Charge AZ 4 Level 2 EV Charger Pilot 2019 Fleet,](https://reader034.vdocuments.site/reader034/viewer/2022051806/5ffdb8a320b2c00b1526322d/html5/thumbnails/2.jpg)
2
Take Charge AZ
• Encourage EV adoption through education
• Avoid charging during peak hours
• Build, own and operate EV infrastructure
• Analyze usage data and EV driver behavior
• Educate customers regarding the benefits of electric passenger and fleet vehicles
• Develop an understanding of the impacts of chargers to the grid
• Safely operating electrical equipment is a core competency of APS
• Reduce range anxiety
• Prepare for market inflection
• Strategic investments
• Partner with industry experts
APS Electric Vehicle Charging Station Pilots
![Page 3: APS Electric Vehicle Charging Pilots · APS Electric Vehicle Charging Station Pilots 3 Unmanaged Passenger EV Charging Load Shape Take Charge AZ 4 Level 2 EV Charger Pilot 2019 Fleet,](https://reader034.vdocuments.site/reader034/viewer/2022051806/5ffdb8a320b2c00b1526322d/html5/thumbnails/3.jpg)
3
Unmanaged Passenger EV Charging Load Shape
Take Charge AZ
![Page 4: APS Electric Vehicle Charging Pilots · APS Electric Vehicle Charging Station Pilots 3 Unmanaged Passenger EV Charging Load Shape Take Charge AZ 4 Level 2 EV Charger Pilot 2019 Fleet,](https://reader034.vdocuments.site/reader034/viewer/2022051806/5ffdb8a320b2c00b1526322d/html5/thumbnails/4.jpg)
4
Level 2 EV Charger Pilot 2019Fleet, Workplace, Multi Unit Dwelling
Plan and customer agreement developed
Customer applications begin
Vendor chosen
Execute contract with vendor
Designs completedConstruction
January - March April May June – December
Take Charge AZ
2019 investment - $2.7m
• Workplace, Fleet and Multiunit Dwelling sites
• Commercial and municipality customers
• Partnering with Clipper Creek (working on contract / not publicly announced)
• Installing approximately 150 – 200 plugs
![Page 5: APS Electric Vehicle Charging Pilots · APS Electric Vehicle Charging Station Pilots 3 Unmanaged Passenger EV Charging Load Shape Take Charge AZ 4 Level 2 EV Charger Pilot 2019 Fleet,](https://reader034.vdocuments.site/reader034/viewer/2022051806/5ffdb8a320b2c00b1526322d/html5/thumbnails/5.jpg)
Level 3 EV Charger Pilot 2019
Release RFPPartner
Cobrand sitesObtain data
June Construction
begins on APS identified sites
Tariff filed
Construction Own chargers
Take Charge AZ
April May June July – December
2019 investment - $3.6m
• Strategic investments in DC fast chargers
• Installing approximately 40 plugs in strategic locations to reduce range anxiety
• Customers: Commercial, municipalities, EV owners, EV charging companies
• Looking into L4 opportunities with partners
• Conducting RFQ to identify strategic partner May 2019
![Page 6: APS Electric Vehicle Charging Pilots · APS Electric Vehicle Charging Station Pilots 3 Unmanaged Passenger EV Charging Load Shape Take Charge AZ 4 Level 2 EV Charger Pilot 2019 Fleet,](https://reader034.vdocuments.site/reader034/viewer/2022051806/5ffdb8a320b2c00b1526322d/html5/thumbnails/6.jpg)
Navigant Studies
Purchase request
completedPhase 1 report Modeling tool
developed Phase 2 Report
• Phase 1 - Passenger EV growth and load impacts
• Phase 2 - Trucking and Interstate charging and load impacts
• EV penetration maps updated quarterly
Take Charge AZ
April May June July – December
2019 investment - $.7m
![Page 7: APS Electric Vehicle Charging Pilots · APS Electric Vehicle Charging Station Pilots 3 Unmanaged Passenger EV Charging Load Shape Take Charge AZ 4 Level 2 EV Charger Pilot 2019 Fleet,](https://reader034.vdocuments.site/reader034/viewer/2022051806/5ffdb8a320b2c00b1526322d/html5/thumbnails/7.jpg)
Contact Information
• C.J. Berg– [email protected]– (602) 250-3857
• Helpful Links:– take charge az– FAQs– [email protected]
• Customer Technology Support Team– (855) 202-8341