APPLIED TECHNOLOGY CENTER
WELDING LAB
ROCK HILL SCHOOLS BID #18-1928 12/19/2018
ADDENDUM #1 009113 – 1 OF 1 PAGES
ADDENDUM #1
Applied Technology Center – Welding Lab
2399 West Main Street
Rock Hill, SC 29732
A. NOTICE TO BIDDER
1. This Addendum is issued pursuant to the Conditions of the Contract and is hereby made part of the
Contract Documents. The addendum serves to clarify, revise, and supersede information in the Project
Manual, the Drawings and previously issued Addenda. The Bidder shall acknowledge receipt of this
Addendum in the appropriate space on the Bid Form. Failure to do so may subject the Bidder to
disqualification. A list of attachments, if any, is part of this document.
2. The date and location for the non-mandatory Pre-Bid meeting has changed to January 9, 2019, 10 AM at
the Applied Technology Center, Building C. See details on the revised Notice to Bidders included in the
attachments.
3. The last day for questions has changed to January 11, 2019, 4 PM. See details on the revised Notice to
Bidders included in the attachments.
4. The date for receipt of bids for this project has changed to January 17, 2019, 2 PM. See details on the
revised Notice to Bidders included in the attachments.
B. MODIFICATIONS TO PROJECT MANUAL
1. Replace SECTION 004113 – BID FORM with the revised SECTION 004113 – BID FORM included in
the attachments.
C. MODIFICATIONS TO DRAWINGS
1. SHEET E101 PARTIAL FLOOR PLAN – WELDING LAB DEMOLITION, LIGHTING AND POWER
LIGHTING FIXTURE SCHEDULE: In addition to the Manufacturers and Series listed the following
fixture is also an approved fixture:
TYPE MFG PART
B1 H.E. WILLIAMS 17-4-L55/835-VBY/GC2/L/10-DIM-UNV
C1 H.E. WILLIAMS 75S-4-L30/835-DRV-UNV
2. Replace SHEET E201 ELECTRICAL RISERS AND PANEL SCHEDULES with the attached sheet
dated 12/13/18.
D. ATTACHMENTS
1. NOTICE TO BIDDERS
2. SECTION 004113 – BID FORM
3. SHEET E201 – ELECTRICAL RISERS AND PANEL SCHEDULES dated 12/13/18
END OF ADDENDUM #1
APPLIED TECHNOLOGY CENTER
WELDING LAB 12/19/2018
NOTICE TO BIDDERS 001113 - 1
DOCUMENT 001113 - NOTICE TO BIDDERS
Project Name: Applied Technology Center – Welding Lab
Bid Number 18-1928
Project Location: Applied Technology Center, 2399 West Main Street, Rock Hill, SC 29732
Owner: Rock Hill School District 3 of York County
DESCRIPTION OF PROJECT: Provide all electrical power, lighting, fire suppression and miscellaneous
demolition work required to hook up new welding equipment provided by Rock Hill Schools. Equipment to be
set in place my Owner. Contractor shall make all the electrical connections.
BID SUBMITTAL AND BID SECURITY:
The Owner will consider bids pursuant South Carolina ST SEC 11-35 prepared in compliance with the
Instructions to Bidders, and delivered as follows:
Bid Date: January 17, 2019
Bid Time: 2:00 PM
Bid Location: Rock Hill School District Facilities Building, 2171 W Main St., Rock Hill, SC 29732
Bids will be thereafter publicly opened and read aloud. Bid security shall be submitted with each bid in the
amount of 5 percent of the bid amount. No bids may be withdrawn for a period of 60 days following opening of
bids. The Owner reserves the right to reject any and all bids and to waive minor informalities and irregularities.
PRE-BID CONFERENCE:
A non-mandatory pre-bid conference for all bidders will be held at the Applied Technology Center, Building C
on January 9, 2019 at 10:00 a.m., local time. Prospective prime bidders are requested to attend. Subcontractors
and suppliers are invited to attend. A walkthrough of the existing building will take place following the
conference.
BIDDING DOCUMENTS: (Electronic Docs) Complete plans, specifications, and contract documents can be
obtained electronically via Vendor Registry. Formal solicitations and quotes are posted through Vendor
Registry. Vendors are encouraged to register with Vendor Registry. Registration for Rock Hill Schools is
FREE.
Link to Vendor Registry: https://vrapp.vendorregistry.com/Vendor/Register/Index/rock-hill-school-district-three-sc-vendor-registration
DEADLINE FOR QUESTIONS: The deadline for questions is January, 11, 2019 4:00 p.m. Questions should be
submitted to Kathy Fletcher at [email protected].
SUBSTANTIAL COMPLETION & FINAL COMPLETION:
Work shall be final and complete within 30 days of substantial completion.
LIQUIDATED DAMAGES:
Work is subject to Liquidated Damages indicated in the Contract Documents and/or Bid Form.
BIDDER’S QUALIFICATIONS
APPLIED TECHNOLOGY CENTER
WELDING LAB 12/19/2018
NOTICE TO BIDDERS 001113 - 2
Bidders must be properly licensed under the state laws governing their respective trades appropriate to the size
of the Project. A Performance Bond, separate Labor and Material Payment Bond, and Insurance in a form
acceptable to the Owner will be required of the successful Bidder. Bidders and their subcontractors shall meet
qualification requirements indicated in the Contract Documents.
Submission of a bid shall serve as evidence that the Bidder has confirmed that the Bidder is properly qualified to
perform the work and is capable of obtaining the required bonds and insurance. Bidders shall, if requested,
submit evidence in affidavit form of applicable experience, licensure, approvals, and certifications, adequate
financial resources, work in hand capacity, adequate organization, and acceptable past performance. Submittal
will be in the form of AIA Document A305 Contractor’s Qualification Statement. Bidder’s qualification
information shall be considered privileged and confidential. Each bid is also subject to the Responsibility
requirements of §1810 of the Owner’s Procurement Code.
END OF DOCUMENT 001113
APPLIED TECHNOLOGY CENTER
WELDING LAB
RHS BID #18-1928 12/19/2018
BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT) 004113 - 1
DOCUMENT 004113 - BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT)
1.1 BID INFORMATION (OWNER PROJECT NO. 18-1928)
A. Bidder: ____________________________________________________.
B. Project Name: Applied Technology Center – Welding Shop
Bid Number 18-1928
Project Location: Applied Technology Center, 2399 West Main Street, Rock Hill, SC 29732
C. Owner: Rock Hill Schools (York County District 3)
1.2 CERTIFICATIONS AND BASE BID
A. Base Bid, Single-Prime (All Trades) Contract: The undersigned Bidder, having carefully
examined the Procurement and Contracting Requirements, Conditions of the Contract,
Drawings, Specifications, and all subsequent Addenda, as prepared by the Owner's consultants,
having visited the site, and being familiar with all conditions and requirements of the Work,
hereby agrees to furnish all material, labor, equipment and services, including all scheduled
allowances, necessary to complete the construction of the above-named project, according to the
requirements of the Procurement and Contracting Documents, for the stipulated sum of:
1. ________________________________________________ Dollars ($______________).
1.3 BID GUARANTEE
A. The undersigned Bidder agrees to execute a contract for this Work in the above amount and to
furnish surety as specified within 10 days after a written Notice of Award, if offered within 30
days after receipt of bids, and on failure to do so agrees to forfeit to Owner the attached cash,
cashier's check, certified check, U.S. money order, or bid bond, as liquidated damages for such
failure, in the following amount constituting five percent (5%) of the Base Bid amount above:
1. ________________________________________________ Dollars ($______________).
B. In the event Owner does not offer Notice of Award within the time limits stated above, Owner
will return to the undersigned the cash, cashier's check, certified check, U.S. money order, or
bid bond.
APPLIED TECHNOLOGY CENTER
WELDING LAB
RHS BID #18-1928 12/19/2018
BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT) 004113 - 2
1.4 SUBCONTRACTORS AND SUPPLIERS – Contractor to provide the name of subcontractor(s)
listed below.
A. IT IS THE BIDDER’S RESPONSIBILITY TO DETERMINE THAT EVERY SUBCONTRACTOR
LISTED HEREUNDER HOLDS ANY NECESSARY LICENSE(S) AT THE TIME OF BID OPENING.
THE DISTRICT VERIFIES THIS INFORMATION AS PART OF ITS RESPONSIBILITY AND
RESPONSIVENESS DETERMINATIONS PRIOR TO THE ISSUANCE OF ANY NOTICE OF
INTENT TO AWARD.
B. The following companies shall execute subcontracts for the portions of the Work indicated:
1. Electrical: _________________________________________________.
1.5 TIME OF COMPLETION – Contractor to provide proposed duration of work.
A. The undersigned Bidder proposes and agrees hereby to commence the Work of the Contract
Documents on a date specified in a written Notice to Proceed to be issued by the client within
20 days of the receipt of bids, and shall substantially complete the Work within 90 calendar
days from issuance of the Notice to Proceed and shall achieve final completion within 30
calendar days from the date of substantial completion.
1.6 LIQUDATED DAMAGES
Owner and Contractor recognize that time is of the essence to this Agreement and that the
Owner will suffer financial loss if the Work is not completed within the Contract Time. Both
Parties also recognize the delays, difficulties and expense involved in proving, in a legal
proceeding, the actual loss suffered by the Owner if the Work is not completed on time.
Accordingly, in lieu of requiring such proof, the Owner and Contractor agree that as liquidated
damages for delay (but not as a penalty) the Contractor, and the Contractor’s surety if any, shall
pay to the Owner for each day in excess of the Contract Time the amount of $250.00 per
calendar day as liquidated damages. Said liquidated damages shall not be construed as
constituting a claim or award for consequential damages.
1.7 ACKNOWLEDGEMENT OF ADDENDA
A. The undersigned Bidder acknowledges receipt of and use of the following Addenda in the
preparation of this Bid:
1. Addendum #1, dated 12/19/18 _________ Initial here to acknowledge receipt
2. ____________________________ _________ Initial here to acknowledge receipt
3. ____________________________ _________ Initial here to acknowledge receipt
APPLIED TECHNOLOGY CENTER
WELDING LAB
RHS BID #18-1928 12/19/2018
BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT) 004113 - 3
1.8 PERFORMANCE AND PAYMENT BONDS
A. Unless otherwise provided in the bid documents, PERFORMANCE and LABOR AND
MATERIAL PAYMENT BONDS, each in the amount equal to one hundred percent (100%) of
the contract price for the Base Bid shall be required of the successful bidder if the contract is
awarded.
1.9 DRUG-FREE WORKPLACE
A. The undersigned certifies to the District that it will provide a Drug-Free Workplace, as required
by Title 44, Chapter 107 of the South Carolina Code of Laws, as amended.
1.10 CONTRACTOR'S LICENSE
A. The undersigned further states that it is a duly licensed contractor, for the type of work
proposed, and that all fees, permits, etc., pursuant to submitting this proposal have been paid in
full.
1.11 SUBMISSION OF BID
A. Respectfully submitted this _______ day of ______________, 2018.
B. Submitted By: __________________________________________________________ (Name of bidding firm or corporation).
C. Authorized Signature: ______________________________________ (Handwritten signature).
D. Signed By: ___________________________ Title: ________________________________ (Print or type Name) (Owner/Partner/President/Vice President)
E. Witness By: ___________________________________________ (Handwritten signature).
F. Attest: _______________________________________________ (Handwritten signature).
G. By: ________________________________ Title: ________________________________ (Print or type Name) (Corporate Secretary or Assistant Secretary)
H. Street Address: ___________________________________________________________.
I. City, State, Zip: __________________________________________________________.
J. Phone: _________________________________________________________________.
K. License No.: ____________ Federal ID No.: _______________(Affix Corporate Seal Here).
END OF DOCUMENT 004113
FIRE ALARM RISER DIAGRAM 3
FF F
SD
~
~
~
NOTES:A. THIS IS AN EXTENSION OF AN EXISTING FIRE ALARM SYSTEM. ALL NEW DEVICES SHALL
BE LISTED BY THE ROCK HILL SCHOOL SYSTEMS FACP MANUFACTURER AS 100% COMPATIBLE
AND SYNCHRONIZED WITH THE EXISTING FIRE ALARM SYSTEM.
B. CONTRACTOR TO ENSURE THAT TECHNICIANS MAKING ANY CONNECTIONS OR PERFORMING ANY
PROGRAMMING FOR THE FIRE ALARM SYSTEM ARE TRAINED AND INDIVIDUALLY CERTIFIED BY THE
MANUFACTURER. TRAINING AND CERTIFICATION MUST HAVE OCCURRED WITHIN THE MOST RECENT
24 MONTHS.
C. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO KEEP THE BUILDING FIRE ALARM SYSTEM
FUNCTIONAL DURING THE PERFORMANCE OF THIS PROJECT. ANY FIRE ALARM SHUT DOWN SHALL
BE CONDUCTED ONLY ON INDIVIDUAL ZONES AND NOT THE ENTIRE SYSTEM. IF A BUILDING-WIDE
FIRE ALARM SHUTDOWN IS REQUIRED, THE CONTRACTOR SHALL NOTIFY THE OWNER AND SUBMIT
A "FIRE-WATCH PLAN" TO THE CAMPUS FIRE MARSHALL AT LEAST ONE WEEK IN ADVANCE. THE
CONTRACTOR MUST RECEIVE APPROVAL FROM THE OWNER PRIOR TO SHUTTING DOWN THE FIRE
ALARM SYSTEM.
D. AT THE CONCLUSION OF THIS PROJECT, THE FIRE ALARM SYSTEM WILL BE TESTED AND
RE-CERTIFIED IN ACCORDANCE WITH THE LATEST EDITION OF NFPA 72 SECTION 10.4.1.2,
INCLUDING THE REQUIREMENT FOR TEST OF RANDOMLY SELECTED EXISTING DEVICES LOCATED
OUTSIDE THE AREA OF CONSTRUCTION.
E. ALL FIRE ALARM SYSTEM MODIFICATIONS SHALL BE PERFORMED IN ACCORDANCE WITH SC SCO
FIRE ALARM POLICIES AND GUIDELINES, 2011 EDITION.
F. FIRE ALARM NOTIFICATION AND ALARM SIGNALING SHALL BE IN CONFORMANCE WITH ROCK HILL
SCHOOLS APPLIED TECHNOLOGY CENTER INFORMAL GENERAL CONDITIONS.
FIRE ALARM
CONTROL
PANEL
TO UL
CENTRAL
MONITORING
STATION
TO EXISTING
20A CIRCUIT
EXISTING
EXISTING
NOTIFICATION
APPLIANCES
EXISTING
INITIATING
DEVICES
NEW INITIATING
DEVICES. SEE PLAN
FOR NUMBER OF
DEVICES.
SD F
L
HD
EXISTING
PANEL
"LB1"
150A M.B.
120/208V
EXISTING
PANEL
"HB1"
150A M.B.
277/480V
EXISTING
"SDPB"
800A M.L.O.
277/480V
EXISTING
SERVICE
SWITCHBD
"MDP"
2000A M.L.O.
277/480V
MANUF.
ITE
EXISTING
45KVA
#4G
WELDING LAB.
B201.1
STORAGE RM.
B212
MAIN ELECT. RM.
B212.1
4#4/0,1#4G,2-1/2"C.
(RUN ABOVE EXISTING
CEILING)
ALL DASHED ITEMS ARE EXISTING TO REMAIN, UNLESS OTHERWISE NOTED.1
NOTES:
NEW
PANEL
"LB2"
100A M.B.
120/208V
NEW
PANEL
"HB2"
225A MB.
277/480V
POWER RISER DIIAGRAM 2
TRANSFORMER
PAD MOUNTED
SERVICE POINT, THE POINT OF CONNECTION
BETWEEN THE FACILITIES OF THE SERVING
UTILITY AND THE PREMISES WIRING.
TO UTILITY
480Y/277V
~
ELECTRICAL PANEL SCHEDULE 1
65K AIC
12,5K AFC
EXISTING BUILDING LOAD - MAX DEMAND FOR LAS T 12 MONTH 272.54 KW (MAY 14, 2018)
(PER NEC 220.87) - 25% OF MAX DEMAND 68.13 KW
TOTAL EXISTING BUILDING DEMAND LOAD 340.68 KW
NEW ADDED LOAD 135.10 KW
TOTAL BUILDING LOAD (EXISTING + NEW) 475.77 KW
DESIGN LOAD > TOTAL BUILDING LOAD
531 KW > 476.77 KW
NEW
30KVA
#8G
3#8, #10G; 3/4 "C. 4#3, #8 G.; 1 1/2" C.
1
ARCHITECT
KSQ Design
200 W Tremont Avenue, Suite 200
Charlotte, NC 28203
704.364.3400 office
704.364.7080 fax
www.ksq.design
NEW YORK OKLAHOMA NORTH CAROLINA
TEXAS COLORADO SOUTH CAROLINA
ROCK HILL SCHOOL DISTRICT 3
ROCK HILL BOND WORK
660 N. ANDERSON RD
ROCK HILL, SC 29730
803.981.1000 office
803.981.1094 fax
www.rock-hill.k12.sc.us
Owner
MEP Engineer
Structural Engineer
NONE
Civil Engineer
NONE
KSQ DESIGN
200 W Tremont Avenue, Suite 200
CHARLOTTE, NC 28203
704.364.3400 office
704.364.7080 fax
www.ksq.design
COPYRIGHT © 2016 KSQ ARCHITECTS, PC
SCALE
DATE
SHEET NAME
SHEET NUMBER
ISSUED
REVISIONS
KEY PLAN
18 17 16 15 1314 9101112
17 1618 15 14 13 12 11 10 9
678 345 12
A
B
D
C
E
F
G
8 7 6 4 35
H
J
L
K
M
2 1
N
P
A
B
D
C
E
F
G
H
J
L
K
M
N
P
PROJECT NO.
C
B
A
PROJECT
NORTH
WELDING LAB
As indicated
11/30/2018
CONSTRUCTION
DRAWINGS
APPLIEDTECHNOLOGY
CENTER WELDINGLAB
Rock Hill Schools District 3
2399 W Main Street, Rock
Hill, SC 29732
1824901.00
No. Description Date
E201
ELECTRICAL RISERS AND
PANEL SCHEDULES
ADDENDUM #1
12/13/08
1
12/13/18