anthony j. vitale · anthony j. vitale site vice president pnp 2014-003 february 13, 2014 u. s....

224
__________________________________________________________________ Entergy Nuclear Operations, Inc. Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530 Tel 269 764 2000 Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 SUBJECT: Response to December 16, 2013 Request for Additional Information for License Amendment Request to Revise Emergency Response Organization Staff Augmentation Response Times Palisades Nuclear Plant Docket 50-255 License No. DPR-20 REFERENCES: 1. Entergy Nuclear Operations, Inc. (ENO) letter to NRC, PNP 2013-044, License Amendment Request to Revise Emergency Response Organization Staff Augmentation Response Times, dated June 25, 2013 (ADAMS Accession No. ML13176A405). 2. NRC email to ENO, MF2321 PNP Request for Additional Information (RAI) for License Amendment Request to Revise ERO Staff Augmentation Response Times, dated July 23, 2013. 3. ENO letter to NRC, PNP 2013-060, Response to Request for Additional Information for License Amendment Request to Revise Emergency Response Organization Staff Augmentation Response Times, dated August 7, 2013 (ADAMS Accession No. ML13220A008). 4. NRC email to ENO, Request for Additional Information - Palisades - Proposed Revision to Palisades Site Emergency Plan (SEP) to increase the staff Augmentation response time for certain Emergency Response Organization (ERO) positions from 30 to 60 minutes - MF2321, dated December 16, 2013.

Upload: others

Post on 31-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

__________________________________________________________________

Entergy Nuclear Operations, Inc. Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530 Tel 269 764 2000

Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 SUBJECT: Response to December 16, 2013 Request for Additional Information

for License Amendment Request to Revise Emergency Response Organization Staff Augmentation Response Times

Palisades Nuclear Plant Docket 50-255 License No. DPR-20 REFERENCES: 1. Entergy Nuclear Operations, Inc. (ENO) letter to NRC,

PNP 2013-044, License Amendment Request to Revise Emergency Response Organization Staff Augmentation Response Times, dated June 25, 2013 (ADAMS Accession No. ML13176A405).

2. NRC email to ENO, MF2321 PNP Request for Additional

Information (RAI) for License Amendment Request to Revise ERO Staff Augmentation Response Times, dated July 23, 2013.

3. ENO letter to NRC, PNP 2013-060, Response to Request for

Additional Information for License Amendment Request to Revise Emergency Response Organization Staff Augmentation Response Times, dated August 7, 2013 (ADAMS Accession No. ML13220A008).

4. NRC email to ENO, Request for Additional Information -

Palisades - Proposed Revision to Palisades Site Emergency Plan (SEP) to increase the staff Augmentation response time for certain Emergency Response Organization (ERO) positions from 30 to 60 minutes - MF2321, dated December 16, 2013.

Page 2: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PNP 2014-003Page 2

Dear Sir or Madam:

In Reference 1, Entergy Nuclear Operations, Inc. (ENO) submitted a licenseamendment request to revise the Site Emergency Plan (SEP) at the Palisades NuclearPlant (PNP). The proposed amendment would revise the PNP SEP to increase thestaff augmentation response times for certain emergency response organizationpositions. In Reference 2, ENO received a request for additional information (RAI)concerning the license amendment request (LAR), and ENO responded to the RAI inReference 3. ENO received a second RAI in Reference 4.

The ENO response to the RAI in Reference 4 is provided in Attachment 1.

Attachment 2 contains offsite dose assessment training documentation, as discussed inAttachment 1. Attachment 3 contains the On-shift Staffing Analysis Report, Revision 1,as discussed in Attachment 1. Attachment 4 contains a marked up version of the On-shift Staffing Analysis Report, Revision 1. Attachment 5 contains the proposed revisionto PNP SEP Figure 5-2, which is unchanged from the license amendment requestexcept for an updated reference to the revised On-shift Staffing Analysis Report.Attachment 6 contains changes to SEP Section 5.4, which align the section with theSEP Figure 5-2 changes proposed in the license amendment request. Attachment 7contains a marked up version of the changes to SEP Section 5.4.

A copy of this response has been provided to the designated representative of theState of Michigan.

This letter contains no new or revised commitments.

I declare under penalty of perjury that the foregoing is true and correct. Executed onFebruary 13, 2014.

Attachments: 1. Response to December 16, 2013 Request for AdditionalInformation for License Amendment Request to Revise EmergencyResponse Organization Staff Augmentation Response Times

2. Offsite Dose Assessment Training Documentation3. On-shift Staffing Analysis Report, Revision 14. On-shift Staffing Analysis Report, Revision 1 (marked up version)

Sincerely,

ajv/jse

PNP 2014-003 Page 2

Dear Sir or Madam:

In Reference 1, Entergy Nuclear Operations, Inc. (ENO) submitted a license amendment request to revise the Site Emergency Plan (SEP) at the Palisades Nuclear Plant (PNP). The proposed amendment would revise the PNP SEP to increase the staff augmentation response times for certain emergency response organization positions. In Reference 2, ENO received a request for additional information (RAI) concerning the license amendment request (LAR), and ENO responded to the RAI in Reference 3. ENO received a second RAI in Reference 4.

The ENO response to the RAI in Reference 4 is provided in Attachment 1.

Attachment 2 contains offsite dose assessment training documentation, as discussed in Attachment 1. Attachment 3 contains the On-shift Staffing Analysis Report, Revision 1, as discussed in Attachment 1. Attachment 4 contains a marked up version of the On­shift Staffing Analysis Report, Revision 1. Attachment 5 contains the proposed revision to PNP SEP Figure 5-2, which is unchanged from the license amendment request except for an updated reference to the revised On-shift Staffing Analysis Report. Attachment 6 contains changes to SEP Section 5.4, which align the section with the SEP Figure 5-2 changes proposed in the license amendment request. Attachment 7 contains a marked up version of the changes to SEP Section 5.4.

A copy of this response has been provided to the designated representative of the State of Michigan.

This letter contains no new or revised commitments.

I declare under penalty of perjury that the foregoing is true and correct. Executed on February 13, 2014.

Sincerely,

ajv/jse

Attachments: 1. Response to December 16, 2013 Request for Additional Information for License Amendment Request to Revise Emergency Response Organization Staff Augmentation Response Times

2. Offsite Dose Assessment Training Documentation 3. On-shift Staffing Analysis Report, Revision 1 4. On-shift Staffing Analysis Report, Revision 1 (marked up version)

Page 3: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PNP 2014-003 Page 3

5. Proposed Revision to Palisades Nuclear Plant Site Emergency Plan Figure 5-2

6. Proposed Revision to Palisades Nuclear Plant Site Emergency Plan Section 5.4

7. Proposed Revision to Palisades Nuclear Plant Site Emergency Plan Section 5.4 (marked up version)

cc: Administrator, Region III, USNRC Project Manager, Palisades, USNRC Resident Inspector, Palisades, USNRC State of Michigan

Page 4: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

1 of 20

ATTACHMENT 1

RESPONSE TO DECEMBER 16, 2013 REQUEST FOR ADDITIONAL INFORMATION FOR LICENSE AMENDMENT REQUEST TO REVISE EMERGENCY RESPONSE

ORGANIZATION STAFF AUGMENTATION RESPONSE TIMES

A follow-up request for additional information (RAI) was received from the Nuclear Regulatory Commission (NRC), by electronic mail on December 16, 2013. The Entergy Nuclear Operations, Inc. (ENO) Palisades Nuclear Plant (PNP) response to the RAI is provided below. The RAI questions reference the following documents:

Reference 1: ENO letter dated June 25, 2013 (ADAMS Accession No. ML1317A405) Reference 2: ENO letter dated August 7, 2013 (ADAMS Accession No. ML13220A008) Reference 3: NEI 10-05, Revision 0 (ADAMS Accession No. ML111751698) Reference 4: NSIR/DPR ISG-01 (ADAMS Accession No. ML113010523)

NRC Request (December 16, 2013)

1. Section 4.2.4.2 of Reference 1 states that the on-shift Chemistry Technician is

not required to perform any chemistry/radiochemistry sampling within the first 90-minutes of an analyzed event. Please explain how the reactor coolant sampling related emergency action levels (EALs) are determined for events that result in a loss of all three fission product barriers with no advance warning as required by section 2.10 of Reference 3. In addition, section 4.2.4.2 also states that the on-shift Chemistry Technician can perform offsite dose assessment calculations, including backup methodologies. Please provide evidence to support the qualifications of the on-shift Chemistry Technician to perform the normal and backup methods of offsite dose assessment calculations.

ENO Response

1. An event that results in a loss of all three fission product barriers would represent a condition that is already at a higher emergency classification than any emergency classification that could be achieved from EAL thresholds associated with sampling. For this condition, other fission product barrier EALs would be applied in order to facilitate timely assessment and classification of an emergency. Containment isolation would occur for accidents of this type. In order to collect and analyze a primary coolant sample following such an event, containment must be un-isolated manually. The On-shift Staffing Analysis (OSA) Report

Page 5: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

2 of 20

appropriately assessed that these actions would not take place in the first 90 minutes following such an accident sequence.

The qualification card used for offsite dose assessment training of the Chemistry Technician is provided in Attachment 2. The qualification card requires completion of an offsite dose assessment course as a prerequisite and also requires demonstration of dose assessment tasks. Section 4.2.4.2 of Reference 1 states that “…backup methodologies for inputs are provided should these indications fail or otherwise not be available.” This statement refers to the inputs provided for dose assessment, specifically meteorological data, rather than additional dose assessment methodologies that the Chemistry Technician is trained to implement.

NRC Request (December 16, 2013)

2. Section 4.2.4.4 of Reference 1 states that in-plant radiological monitoring instrumentation is sufficient for monitoring radiological conditions in the plant thus reducing the need for radiation protection (RP) personnel to enter the plant to obtain radiological data. Please explain how on-shift staff are made knowledgeable of area radiation levels in unknown and potentially escalating radioactive environments for events that result in an immediate loss of all three fission product barriers, which may potentially cause in-plant radiological instrumentation to be off-scale.

ENO Response

2. Thirty-four continuous monitoring points within the plant are selected to provide indication and warning where radioactivity may be present using area radiation monitors. All of these monitors have an upper range of at least 107 mrem/hr, providing sufficient range for severe accident conditions to provide indication of escalating radioactive environments. The Shift Manager prioritizes response actions based on all such inputs as well as knowledge of areas that may or may not need to be accessed. Areas will not be accessed to determine conditions if there is not an operational need.

In addition, PNP provides a specific radiation work permit with emergency dose

and dose rate limits for entry into areas under accident conditions. The established dose and dose rate limits for this radiation work permit are set for levels significantly higher than those expected for work performed under normal operating conditions. These values represent turn back limits where, if encountered, work is stopped, the area is exited, and additional instructions and follow-up with the Shift Manager and Radiation Protection is required, protecting worker safety. This radiation work permit is continuously available on the

Page 6: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

3 of 20

automated radiological access control system and does not require action by the on-shift RP Technician to set up or initiate for use.

Dedicated electronic alarming dosimeters set to the emergency radiation work

permit limits are provided in the immediate Control Room area and at the radiological access control point. The alarming instrumentation provides a continuous indication of the dose and dose rate for personnel entering areas where there is a need to perform an operational response action. Under the conditions presented in this RAI question and given an operational need to enter an area, personnel may enter the area under the emergency radiation work permit and its established limits without RP escort. Should personnel receive an alarm on dose or dose rate, they are required to exit the area immediately for additional instructions and follow-up. The on-shift RP Technician is assigned to support on-shift Operator actions as prioritized by the Shift Manager.

NRC Request (December 16, 2013)

3. Section 4.2.5.1 of Reference 1 justifies the increase in response time for the Shift Engineer/Shift Technical Advisor (STA) by the addition of an on-shift Communicator. Please explain how the addition of an on-shift Communicator justifies the increase in response time for the core/thermal hydraulic technical support function, which is not related to the need for communications.

ENO Response

3. ENO understands this RAI to refer to the requested increase in response time for the Technical Support Center core/thermal hydraulics augmented responder from 30 to 60 minutes. The addition of an on-shift Communicator is not in itself intended to justify the increase in response time for the core/thermal hydraulic technical support function. The addition of the communicator to the on-shift staff complement was referenced because it ensures the STA remains available to monitor core/thermal hydraulics and provide technical support for the additional 30 minutes of technical support response time requested. The STA monitors core/thermal hydraulics and provides technical support throughout the event until relieved by the augmented Emergency Response Organization (ERO). Previous to the changes resulting from the On-shift Staffing Analysis Report, the STA may have performed communications duties for some events. Further justification for the requested additional 30 minutes of technical support response time is related to enhanced STA training as discussed in item number 11 of section 4.2.10 of Reference 1. This item reads as follows: “The Shift Technical Advisor (STA) was originally trained as an advisor to the Control Room operating shift per NUREG-0737 ‘Clarification of TMI Action Plan Requirements.’ In 1990, additional guidelines were developed by the Institute of Nuclear Plant Operations (INPO) for the training of STAs. This is

Page 7: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

4 of 20

detailed in the guidance document INPO 90-003, ‘Guidelines for the Training and Qualification of Shift Technical Advisors.’ The STA performs independent assessments of plant operating concerns, technical support, appropriate corrective actions, analysis of events and their effects, effectiveness of response(s) to emergent conditions, classifications of emergencies, protection of the public, and any other actions related to critical safety functions and plant safety during abnormal and emergency situations. They also contribute to operations during normal plant conditions. By routine monitoring of equipment and plant operations, the STA can focus on preventative actions in order to mitigate the consequences of an accident.” In addition, since the PNP SEP was originally issued in the early 1980s, several changes have occurred that have lessened the burden on the STA during postulated events. In the 1990s, the PNP plant process computer (PPC) was installed. This computer provides plant personnel, including the STA, the capability to monitor and trend plant parameters in real time, including primary coolant system parameters, reactor core thermal performance parameters, emergency core cooling system parameters, meteorological data, containment isolation status, and radiation monitor readings. The Emergency Operating Procedures and Severe Accident Management Guidelines were implemented to improve the quality of operational information and guidance during emergency events. These improvements in the monitoring of plant parameters via the PPC, and in emergency procedures, have lessened the burden on the STA during postulated events.

NRC Request (December 16, 2013)

4. Section 4.2.5.2 of Reference 1 states that during the initial stages of an event, the major response activities are concentrated on determining the cause of the event and placing the plant in a safe condition through plant manipulations and system alignments. While the staff agrees with this statement, the repair and/or corrective action(s) needed during the most significant events are related to issues with the emergency core cooling system (ECCS) not operating correctly. Please elaborate as to how the Nuclear Plant Operators can perform action(s) typically assigned to qualified maintenance personnel for all reasonable failure modes of ECCS equipment, including logic manipulation. Please provide documentation that supports this analysis and supports the task(s) that the Nuclear Plant Operators may need to do, and the qualifications needed to perform them.

ENO Response

4. As noted in Section 2.5 of NEI 10-05, “Analysis of Repair and Corrective Action Responses,” a repair or corrective action is defined as an action that can be performed promptly to restore a non-functional component to functional status

Page 8: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

5 of 20

(e.g., resetting a breaker), or to place a component in a desired configuration (e.g., open a valve), and which does not require work planning or implementation of lockout or tagout controls to complete. The Nuclear Plant Operators are trained to perform repair and corrective action type tasks as defined in NEI 10-05.

The PNP ECCS includes four safety injection tanks, and two redundant, 100% capacity trains, each containing low and high pressure safety injection pumps. Backup power for each train is provided by a dedicated emergency diesel generator. All system components, including the emergency diesel generators, meet quality standards, and are designed to withstand phenomena such as seismic events, tornados, floods, and fires, without a loss of function. The site technical specifications contain operability and surveillance test requirements that assure that the ECCS is available to perform its required safety functions. The ECCS is designed such that it can perform its safety functions assuming a single failure and a loss of offsite power, as required by 10 CFR 50, Appendix A, “General Design Criteria for Nuclear Power Plants.” That is, the ECCS is designed to be capable of performing its required safety functions with no required repairs or corrective actions.

Repair and corrective actions as defined in NEI 10-05 are intended to enhance plant response in various accident scenarios and are limited in scope. Although highly unlikely, these actions may be desired to ensure that the ECCS performs its required functions. If any malfunction occurred that would require prompt manual action, the manual action would most likely involve a repair or corrective action as defined in NEI 10-05, which the Nuclear Plant Operators are fully capable of performing. These repair and corrective actions are to be promptly performed by Nuclear Plant Operators and are not dependent on the arrival of maintenance personnel on site. These actions involve activities such as resetting breakers and repositioning valves, prior to 90 minutes after event initiation. More complex and involved actions requiring maintenance personnel are not expected to be performed in a prompt manner (i.e., not within 90 minutes of event initiation), since work planning and implementation of tagout controls would typically preclude such prompt completion.

NRC Request (December 16, 2013)

5. Section 4.2.6.1 of Reference 1 provides an analysis of the PNP automated radiation work permit system but does not discuss how this automated system would work during accident conditions, particularly those with extensive radioactive environments and changing plant conditions. Is the system automation capable of adjusting dose margins when entry is required during the most egregious accident scenarios, i.e., an immediate loss of all three fission product barriers? If RP involvement is necessary, please provide an evaluation of the impact on the on-shift RP Technician.

Page 9: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

6 of 20

ENO Response

5. As stated in the response to RAI #2, an emergency radiation work permit is

pre-established allowing immediate access to areas with elevated radiological conditions when access is required to support operational needs. RP action is not required to adjust dose margins, set up, or initiate this radiation work permit for emergency use.

NRC Request (December 16, 2013)

6. Section 4.2.6.2 of Reference 1 provides justification for changing the RP Technician response time that includes the use of installed area radiation monitoring (ARMs) alarming at preset dose and dose rates. Please explain how these ARMs will suffice for events that are based upon an immediate loss of all three fission product barriers and thus may introduce dose or dose rates significantly greater than the alarm setpoints and/or the scale of the ARMs.

ENO Response 6. See response to RAI #2. NRC Request (December 16, 2013) 7. Section II of Reference 2 states that the accident scenario of a main control room

fire and shutdown at the remote shutdown panel is the most limiting. The staff believes that the accident scenario related to 10 CFR 50.54(hh)(1), involving potential or actual aircraft attacks could potentially be the accident scenario which would require the most use of available on-shift staff, particular those who would be assigned fire brigade duties or tasked with manipulating plant equipment in preparation for the potential attack. Please provide more justification that supports this decision.

ENO Response

7. ENO has revised the On-shift Staffing Analysis Report provided in Reference 2 to provide clarification and to update the analysis. A different treatment of the potential or actual aircraft attack-initiated accident scenario is provided in the revised analysis. In addition, the On-shift Staffing Analysis Report no longer specifies a most limiting accident scenario, providing better alignment with NEI 10-05. The revised report is provided in Attachments 3 and 4.

Page 10: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

7 of 20

NRC Request (December 16, 2013) 8. Section II.C of Reference 2 justifies adding the responsibility of some site specific

event notifications to the Shift Manager by stating that they are of a limited duration and does not require a time motion study (TMS) or analysis to justify it. While individual ERO functions of limited duration may be added without needing a TMS to justify it, the number of ERO functions assigned to the Shift Manager may be extra burdens that could affect the timeliness of emergency response actions. Please justify how these extra functions would not affect the timeliness of the Shift Manager’s responsibilities.

ENO Response 8. ENO has revised the On-shift Staffing Analysis Report provided in Reference 2

to provide clarification and to update the analysis. The revised analysis is provided in Attachments 3 and 4. The site specific notifications referenced above represent notifications to senior plant management (e.g., Duty Plant Manager, Operations Manager, and NRC Resident Inspector). These notifications are of short duration and were deemed acceptable in accordance with the guidance of NEI 10-05, Sections 3.1.13 and 3.2.2.6(a)(14). Additionally, the Shift Manager is routinely evaluated in the ability to maintain effective oversight and control of the plant and situational awareness of the event while performing various emergency response tasks, including the notifications noted above. These evaluations are normally in the form of simulator sessions during Operations training or emergency preparedness drills, and routinely test the ability of the Shift Manager to manage these various tasks while continuing to maintain oversight and control of the plant and situational awareness of the event. Finally, the notifications to ENO management are discretionary in the sense that a Shift Manager is empowered as the senior management representative with all final decision making authority. These notifications are not required in order for the Shift Manager to make decisions.

NRC Request (December 16, 2013)

9. Section II.C of Reference 2 states that an analysis, or TMS, is not needed to support the addition of communicator duties to a Nuclear Plant Operator, RP Technician, or Chemistry Technician, for a 10 CFR 50.54(hh) event. Please provide further technical discussions for this statement as the staff cannot determine what duties are assigned to these positions for this accident scenario.

ENO Response 9. No specific time-critical tasks/duties are assigned to the RP Technician or

Chemistry Technician for a 10 CFR 50.54(hh) event. The RP Technician and Chemistry Technician are not assigned to the Fire Brigade at PNP. Additionally,

Page 11: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

8 of 20

the RP Technician and multiple Nuclear Plant Operators have no time-critical tasks/duties, other than relocating to non-target areas of the plant, and are available (if needed) to maintain an open phone line with the NRC.

NRC Request (December 16, 2013)

10. Section IV.C.2, and Appendix A (Event # 14), of Reference 2 states that no emergency declaration would be expected for a dropped spent fuel cask. Please explain when EAL E-HU1 would be declared and provide further explanations as appropriate.

ENO Response

10. PNP Emergency Action Level (EAL) EU1.1 would be expected to be declared anytime the EAL entry conditions are met (i.e., damage to a loaded cask confinement boundary). A NRC-approved single failure proof crane is used to transport spent fuel casks, so a dropped spent fuel cask while transferring a loaded cask from the spent fuel pool to track alley is not expected.

In addition, spent fuel casks are designed such that the structural integrity of the

cask would not be compromised under postulated cask drop scenarios while the loaded cask is transported from the plant out to the concrete cask storage pad.

Personnel, in addition to the minimum on-shift complement, would be assigned

to the spent fuel movement and cask loading operations, including Radiation Protection personnel, and would be immediately available to respond to the event.

NRC Request (December 16, 2013)

11. Reference 2, Appendix B, Event #1, “Design Basis Threat (DBT)”:

a. Please explain why a water-based threat was not analyzed, do not use sensitive or safeguard information to respond.

b. In accordance with the direction given in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event: i. Declare the emergency classification level (ECL) ii. Approve content of State/Local notifications

1. Who completes this ‘content’? This is not listed in the ON-SHIFT STAFFING ANALYSIS and was not analyzed.

Page 12: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

9 of 20

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty Plant

Manager, INPO, ANI, etc.)

c. Please explain the basis for why the STA was not analyzed to justify the responsibility of performing notification to the NRC of the DBT event.

d. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

e. Reference 4, section IV.C (page 14) states that licensees should ensure that sufficient staff is available to simultaneously implement both the emergency plan and the security plan in a DBT environment to include, as a minimum, the potential for restricted movement of site personnel. The staff can find no evidence of this being reviewed, please review and provide further information to support the justification.

ENO Response

11. ENO has revised the On-shift Staffing Analysis Report provided in Reference 2 to provide clarification and to update the analysis. The revised report is provided in Attachments 3 and 4.

a. NEI 10-05, Appendix A, provides guidance to analyze the response to a

land and/or waterborne hostile action and the assumptions to use associated with this DBT event. Using the assumptions provided in NEI 10-05, no additional actions were identified for the on-shift ERO when responding to a waterborne attack as compared to a ground attack.

b. The Shift Manager is routinely evaluated in the ability to maintain effective oversight and control of the plant and situational awareness of the event while performing the various emergency response tasks noted above. These evaluations are normally in the form of simulator sessions during Operations training or emergency preparedness drills, and routinely test the ability of the Shift Manager to manage these various tasks while continuing to maintain oversight and control of the plant and situational awareness of the event. Additionally, as noted in Section 3.2.3 of NEI 10-05, all of the tasks noted above (except ERO notification and “other site specific notifications”) are

Page 13: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

10 of 20

acceptable tasks to be performed by the Shift Manager without requiring the performance of a TMS. The acceptability of the Shift Manager to perform ERO notification was documented in a TMS included in Section VIII of the On-shift Staffing Analysis Report. The acceptability of the Shift Manager to perform the brief communications identified as “other site-specific event notifications” is discussed in Section II. C. 2 of the On-shift Staffing Analysis Report, Section 3.1.13 of NEI 10-05, and the response to RAI #8. These “other site-specific event notifications” are normally limited to brief notifications to the Duty Plant Manager, Operations Manager, and Resident NRC Inspector. These short duration tasks were evaluated as being able to be performed by the Shift Manager without impacting the ability to perform other emergency functions/tasks. Completion of State/Local notification form – As described in Table 5 – Line 8 of Attachment 3 for each analyzed event, the Shift Manager completes the State/local notification form. A computer is used to generate this form. Long-term observation of performance during drill and simulator session indicates this form can be completed in 1-2 minutes using the computer-driven menus and drop-down lists. Completion of NRC event notification form – The completed State/Local message form as well as observation of actual plant conditions and decisions already made and communicated by the Shift Manager to the crew are used by the communicator to provide information to the NRC. The NRC event notification form (NRC Form 361) is not completed prior to calling the NRC for declared emergency events in the Control Room in the interest of providing timely notification. ERDS activation - Subsequent to the completion of the original On-shift Staffing Analysis Report, PNP has established a 24/7 ERDS connection with the NRC, obviating the need for any member of the on-shift staff to establish the connection and start the transmission of data. INPO/American Nuclear Insurers (ANI) - INPO/American Nuclear Insurers (ANI) - Other notifications, such as notifications to INPO and ANI, are not made by the on-shift staff, but instead are deferred to other supporting staff.

c. The STA position was analyzed to perform the abbreviated NRC notification for the DBT security threat event as noted in Appendix B, Accident Analysis #1, Table 5, Line #7, in the On-shift Staffing Analysis Report.

d. Thirty-minute responders are listed in the applicable table of the On-shift Staffing Analysis Report in accordance with the formatting requirements of NEI 10-05, Section 3.2.2.2.c, to depict existing SEP information. Section V.A.2 of the report indicates that the analysis was performed using a 90-minute augmentation response time. Upon approval of the changes

Page 14: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

11 of 20

requested in Reference 1, members of the augmented ERO would arrive within 60 minutes to relieve the on-shift Communicator and RP #1.

e. The On-shift Staffing Analysis Report verified the staff needed to simultaneously implement both the SEP and Security Plan in a DBT environment. The specific actions required to implement the SEP are detailed in Attachment 3. The analysis verified the on-shift Security staff was not needed to implement any immediate primary SEP response actions, leaving them available to implement required Security Plan actions for a DBT event. Security personnel are not assigned to the fire brigade at PNP.

NRC Request (December 16, 2013)

12. Reference 2, Appendix B, Event #2, “Control Rod Ejection Accident”:

a. In accordance with the guidance provided in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event: i. Declare the ECL ii. Approve content of State/Local notifications

1. Who completes this ‘content’? This is not listed in the ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty Plant

Manager, INPO, ANI, etc.)

b. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

ENO Response 12.a. See RAI #11 response b.

12.b. See RAI #11 response d.

Page 15: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

12 of 20

NRC Request (December 16, 2013)

13. Reference 2, Appendix B, Event #3, “Small Line Break Outside Containment”:

a. In accordance with the guidance provided in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event:

i. Declare the ECL ii. Approve content of State/Local notifications

1. Who completes this ‘content’? This is not listed in the ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty Plant

Manager, INPO, ANI, etc.)

b. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

ENO Response

13.a. See RAI #11 response b. 13.b. See RAI #11 response d.

NRC Request (December 16, 2013)

14. Reference 2, Appendix B, Event #4, “Main Steam Line Break Inside

Containment”:

a. In accordance with the guidance provided in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event:

i. Declare the ECL

Page 16: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

13 of 20

ii. Approve content of State/Local notifications 1. Who completes this ‘content’? This is not listed in the

ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty Plant

Manager, INPO, ANI, etc.)

b. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

ENO Response

14.a. See RAI #11 response b.

14.b. See RAI #11 response d. NRC Request (December 16, 2013)

15. Reference 2, Appendix B, Event #5, “Loss of Coolant Accident”:

a. In accordance with the guidance provided in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event:

i. Declare the ECL ii. Approve content of State/Local notifications

1. Who completes this ‘content’? This is not listed in the ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS

Page 17: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

14 of 20

viii. Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

b. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

ENO Response

15.a. See RAI #11 response b. 15.b. See RAI #11 response d.

NRC Request (December 16, 2013) 16. Reference 2, Appendix B, Event #6, “Fuel Handling Accident”;

a. In accordance with the guidance provided in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event:

i. Declare the ECL ii. Approve content of State/Local notifications

1. Who completes this ‘content’? This is not listed in the ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty Plant

Manager, INPO, ANI, etc.)

b. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

ENO Response

16.a. See RAI #11 response b. 16.b. See RAI #11 response d.

Page 18: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

15 of 20

NRC Request (December 16, 2013) 17. Reference 2, Appendix B, Event #7, “Waste Tank Rupture”:

a. In accordance with the guidance provided in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event:

i. Declare the ECL ii. Approve content of State/Local notifications

1. Who completes this ‘content’? This is not listed in the ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty Plant

Manager, INPO, ANI, etc.)

b. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

ENO Response

17.a. See RAI #11 response b. 17.b. See RAI #11 response d.

NRC Request (December 16, 2013) 18. Reference 2, Appendix B, Event #8, “Aircraft Probable Threat”:

a. In accordance with the guidance provided in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event:

i. Declare the ECL ii. Approve content of State/Local notifications

Page 19: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

16 of 20

1. Who completes this ‘content’? This is not listed in the ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty Plant

Manager, INPO, ANI, etc.)

b. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

c. The guidance in Reference 3, specifically Section 2.13, requires a site-specific list of response tasks for this event, and a collateral duty analysis (with possible TMS) to verify personnel are not assigned ERO functions that would preclude timely performance of their other assigned functions. As stated in the assumptions for this event in Reference 2, consideration of the dispersal of the site fire brigade away from target areas must be given, note that Table 3 appears to be inconsistent with this assumption. Please follow the guidance provided in Section 2.13 of Reference 3 and revise accordingly.

ENO Response

18.a. See RAI #11 response b. 18.b. See RAI #11 response d. 18.c. ENO has revised the On-shift Staffing Analysis Report provided in

Reference 2 to provide clarification and to update the analysis. The revised report is provided in Attachments 3 and 4.

NRC Request (December 16, 2013)

19. Reference 2, Appendix B, Event #9, “Control Room Fire Requiring Evacuation and Remote Shutdown”:

a. In accordance with the guidance provided in Reference 4, IV.C,

please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event:

Page 20: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

17 of 20

i. Declare the ECL ii. Approve content of State/Local notifications

1. Who completes this ‘content’? This is not listed in the ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty

Plant Manager, INPO, ANI, etc.)

b. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

c. In accordance with Section 2.9 of Reference 3, please provide the validation results for the assessment and determination that this event scenario is the most limiting fire related scenario.

ENO Response

19.a. See RAI #11 response b. 19.b. See RAI #11 response d. 19.c. ENO has revised the On-shift Staffing Analysis Report provided in

Reference 2 to provide clarification and to update the analysis. Specifically, in Section IV.C.3 of the report, a discussion was added concerning the basis for the most limiting fire scenarios. The revised report is provided in Attachments 3 and 4.

NRC Request (December 16, 2013) 20. Reference 2, Appendix B, Event #10, “Station Blackout”:

a. In accordance with the guidance provided in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event:

i. Declare the ECL

Page 21: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

18 of 20

ii. Approve content of State/Local notifications 1. Who completes this ‘content’? This is not listed in the

ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty

Plant Manager, INPO, ANI, etc.)

b. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

ENO Response

20.a. See RAI #11 response b. 20.b. See RAI #11 response d.

NRC Request (December 16, 2013) 21. Reference 2, Appendix B, Event #11, “LOCA/General Emergency with

Release and PAR”:

a. Please explain why the accident assumption is made that this event would be prefaced by the declaration of a Site Area Emergency (SAE), and thus all actions for the SAE are completed. Reference 3, Section 2.10, and Reference 4, Section IV.C, do not make this assumption. This event is based upon an immediate loss of all three fission product barriers with an offsite release, regardless of cause, and expects the on-shift organization to be able to effectively implement the emergency plan until relieved by the ERO staff, as paraphrased from Reference 3, 2.10, and Reference 4, Section IV.C. Please explain.

b. In accordance with the guidance provided in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event:

i. Declare the ECL

Page 22: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

19 of 20

ii. Approve content of State/Local notifications 1. Who completes this ‘content’? This is not listed in the

ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty

Plant Manager, INPO, ANI, etc.)

c. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

ENO Response

21.a. ENO has revised the On-shift Staffing Analysis Report provided in Reference 2 to provide clarification and to update the analysis. The revised report is provided in Attachments 3 and 4. The updated report analyzes an event that goes directly to a General Emergency.

21.b. See RAI #11 response b.

NRC Request (December 16, 2013) 22. Reference 2, Appendix B, Event #15, “Steam Tube Rupture with Concurrent

Loss of Off-Site Power”:

a. In accordance with the guidance provided in Reference 4, IV.C, please explain how the Shift Manager can perform the following and still maintain effective oversight and control of the plant, and maintain situational awareness of the event:

i. Declare the ECL ii. Approve content of State/Local notifications

1. Who completes this ‘content’? This is not listed in the ON-SHIFT STAFFING ANALYSIS and was not analyzed.

iii. Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

iv. ERO notification v. Complete State/Local notification form

Page 23: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

20 of 20

1. Inconsistent with ii above, please explain. vi. Complete NRC event notification form vii. Activate ERDS viii. Perform other site-specific event notifications (e.g., Duty

Plant Manager, INPO, ANI, etc.)

b. Please explain who will be relieving the Communicator and RP #1 within 30-minutes as depicted on Table #1 for this event.

ENO Response

22.a. See RAI #11 response b. 22.b. See RAI #11 response d.

Page 24: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ATTACHMENT 2

OFFSITE DOSE ASSESSMENT

TRAINING DOCUMENTATION

5 Pages Follow

Page 25: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ENTERGY NUCLEAR Page 1 E-DOC TITLE: E-DOC NO. REVISION NO.

TRAINING MATERIAL APPROVAL TQF-201-DD01 17

NOTE This form is used to approve training materials that do not have a review/approval block.

*TRAINING MATERIAL NUMBER:

PL-RPR- 582-206O Rev 1 *TRAINING MATERIAL TITLE:

Perform “Quick Method” Dose Assessment per EI-6.0 “Offsite Dose Calculation and Recommendation for Protective Actions”

Lesson Plan Qualification Card / Lab Guide Simulator Guide Familiarization Guide

CBT Course Electronic Document/Form Graded Approach to Training Other

New Material Minor Revision Major Revision Cancellation Lesson Plan/Material Superseded REASON FOR REVISION (include reason for site specific exception date as necessary):

Chemistry went from PL-N00150 rev 8 “Quick Dose Assessment” to PLLP-CM-QUICK DOSE. “Quick Dose Assessment” as the prerequisite because EP needed to continue to use PL-N00150 for OPS. Thus chemistry made minor editoral changes to PL-N00150 rev 8 and renamed the class PLLP-CM-QUICK DOSE.

REVIEW / APPROVAL: Electronic Approval (TEAR )

Prepared By: Jarrod J Miller 01-21-13 **Preparer Date

*Reviewed By: Michael G Mlynarek 01-07-13 **Technical Reviewer (e.g., SME, line management) Date

*Instructional Adequacy Determined By: Walter E Nelson 01-07-13

**Instructional Technologist or Qualified Instructor Date

Approved By: Walter E Nelson 01-21-13 **Discipline Training Superintendent or Fleet Training Manager Date

*Technical review, instructional adequacy, and fleet review N/A for electronic document or form. Instructional adequacy review is not required for graded approach to training topics. **Indicates that the training material has been reviewed for inclusion of items referenced on TQF-201-DD06, Training Material Checklist as appropriate.

FLEET PROGRAM REVIEW POINT OF CONTACT: Not Applicable Name or N/A Exception Date Name or N/A Exception Date ANO NP BRP PLP CNS PNPS GGNS RBS HQN VY IPEC W3 JAF

Indexing Information Signed Copy on File Class Code:

END OF DOCUMENT

Page 26: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ENTERGY NUCLEAR Page 2 of 5 E-DOC TITLE: E-DOC NO. REVISION NO.

OJT/TPE TQF-201-OJT 5

OJT and TPE Qualification Guide Trainee Name: Login ID:

Training Program: Chemistry Training ID #: PL-582 206 01 11

Task Title: Perform “Quick Method” Dose Assessment per EI-6.0 “Offsite Dose Calculation and Recommendation for Protective Actions”

List the OE to be used for OJT:

• OE25818, “Dose Assessment Computer Program, Raddose V, failed during an Emergency Response Drill”

Prerequisites: a. PLLP-CM-QUICKDOSE “Quick Dose Assessment”

Prerequisites verified complete: / Qualified Trainer Date

OJT completed: /

N/A if OJT challenged Qualified Trainer (print & sign name) or N/A & Trainee Initial Date

Task Performance Evaluation (TPE)

OJT has been completed / challenged per EN-TQ-204 for the listed task and I am ready to take the TPE.

/ Trainee Signature (print and sign name) Date

TPE unsuccessful (Document TPE failures per EN-TQ-204)

SAT - Task evaluation was successfully completed in accordance with EN-TQ-204.

/ Qualified Evaluator (print and sign name) Date

Qualification Trainee is competent (qualified) to perform this task independently.

/

(N/A for Duty Area or Job Qualification) Training Program Owner or designee or N/A (print and sign name)

Date

Verification Record has been verified to be complete.

/

Training Supervision (print and sign name) Date Training Records Updated

Entered / Print and Sign Name Date

Send completed OJT/TPE Documentation and Comment Sheets to Training Records Check here indicates the LMS was updated.

Page 27: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ENTERGY NUCLEAR Page 3 of 5 E-DOC TITLE: E-DOC NO. REVISION NO.

OJT/TPE TQF-201-OJT 5

I. Task:

Perform “Quick Method” Dose Assessment per EI-6.0 “Offsite Dose Calculation and Recommendation for Protective Actions”

II. Terminal Objective:

Given emergency conditions, perform Quick Dose Assessment Method in accordance with EI-6.0, “Offsite Dose Calculation and Recommendations for Protective Actions” and provide results to Control Room SRO.

III. References: 1. EI-6.0 “Offsite Dose Calculation and Recommendation for Protective Actions” 2. EP Job Aid GEN-012, “Palisades Event Technical Data Sheet Completion”

IV. General Tools and Equipment: 1. PPC (not required) 2. Dose Assessment computer

V. Initial Conditions Perform “Quick Method” Dose Assessment per EI-6.0 “Offsite Dose Calculation and Recommendation for Protective Actions” per Shift Manager Direction.

VI. Personnel Safety Considerations No special PPE is required for this task

VII. Commitments None

VII. Instructor Notes/Set-up

Simulator, TSC, and the Control Room all have a Dose Assessment computer

Page 28: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ENTERGY NUCLEAR Page 4 of 5 E-DOC TITLE: E-DOC NO. REVISION NO.

OJT/TPE TQF-201-OJT 5

PERFORMANCE OBJECTIVES (Section I)

Task Title: Perform “Quick Method” Dose Assessment per EI-6.0 “Offsite

Dose Calculation and Recommendation for Protective Actions”

Task #: PL-582 206 01 11

Trainee Name Date

Check if management observation required or stamp here

Initial Continuing

Overall Grade: PASS FAIL (Circle One)

Shaded objective numbers indicate a “must perform” step. An “*” next to the objective number indicates an alternate path. All alternate paths must be trained during OJT; at least one alternate path per performance objective must be evaluated during TPE.

OBJECTIVES Code OJT Complete

TPE Complete

1.

Management expectations/core work practices applied appropriately for the task. (See attachment 9.2 of EN-TQ-204 for pass/fail criteria)

P

2. Retrieve Meteorological data from the PPC and Dose Assessment computer P

3. Retrieve Meteorological data from the Control Room S

4. Perform “Quick Method” Dose Assessment per EI-6.0 “Offsite Dose Calculation and Recommendation for Protective Actions”

P

5. Determine if PAGs are exceeded. P

Page 29: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ENTERGY NUCLEAR Page 5 of 5 E-DOC TITLE: E-DOC NO. REVISION NO.

OJT/TPE TQF-201-OJT 5

COMMENTS (Section II)

COMMENTS:

Any clarifying asked and the trainee response must be documented.

Note any opportunities for improvement provided to the trainee.

Note reason for TPE failure, if applicable.

Page 30: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ATTACHMENT 3

ON-SHIFT STAFFING ANALYSIS REPORT, REVISION 1

92 Pages Follow

Page 31: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ONSHIFT STAFFING ANALYIS REPORT

PALISADES NUCLEAR STATION

ONSHIFT STAFFING ANALYSIS

Rev I

February 10, 2014

Prepared by: .. / Z 7-M. F. Guynn / Date

Peer

Review by— ..

My(J .e ate

I...,

.:

Approved by:Dan Malone / Date

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES NUCLEAR STATION

ON-SHIFT STAFFING ANALYSIS

Rev 1

February 10, 2014

P d b Pn 4 ~ / Z - 7- /u repare y: //L -<r .J'91~ I M. F. Guynn I Date

Approved by: ~~~~~~~P!4t.::..L.~-Dan Malone I Date

Page 32: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

TABLE OF CONTENTS

I. INTRODUCTION ............................................................................................................................ 4

II. ANALYSIS SUMMARY .................................................................................................................. 4

A. Emergency Plan Minimum Staffing .................................................................................. 5

B. Other Commitments to Shift Staffing ................................................................................ 6

C. Staffing Exceptions and Time Motion Studies (TMS) ..................................................... 6

D. Emergency Plan Tasks Not Analyzed .............................................................................. 7

III. ANALYSIS PROCESS ................................................................................................................... 8

IV. ACCIDENT SCENARIOS .............................................................................................................. 9

A. Accident Selection ............................................................................................................. 9

B. Accident Scenarios included in the Analysis ................................................................... 9

C. Accident Scenarios not included in the Analysis ........................................................... 10

V. GENERAL ASSUMPTIONS AND LIMITATIONS ...................................................................... 11

A. Notes and Assumptions applicable to all accidents in Palisades Staffing Analysis: .. 11

B. NEI 10-05 Rev 0 Assumptions ........................................................................................ 12

VI. APPENDIX A - ANALYZED EVENTS AND ACCIDENTS ........................................................ 14

VII. APPENDIX B – ON-SHIFT STAFFING ANALYSIS .................................................................. 16

A. Accident Analysis #1 – Design Basis Threat (DBT) ...................................................... 16

B. Design Basis Accident Analysis #2 – Control Rod Ejection ......................................... 23

C. Design Basis Accident Analysis #3 – Small Line Break Outside Containment as described in FSAR 14.23 ................................................................................................ 29

D. Design Basis Accident Analysis #4 – Main Steam Line Break Inside Containment. . 35

E. Design Basis Accident Analysis #5 – Loss of Coolant Accident. ................................. 41

F. Design Basis Accident Analysis #6 – Fuel Handling Accident ..................................... 47

G. Design Basis Accident Analysis #7 – Waste Tank Rupture ......................................... 53

H. Accident Analysis #8 – Aircraft Probable Threat ........................................................... 59

I. Accident Analysis #9 – Control Room Fire Requiring Evacuation and Remote Shutdown .......................................................................................................................... 65

J. Accident Analysis #10 – Station Blackout ...................................................................... 71

K. Accident Analysis #11 – LOCA/General Emergency with Release and PAR............. 76

Page 33: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

L. Accident Analysis #15 – Steam Generator Tube Rupture with Concurrent Loss of Off-site Power ................................................................................................................... 83

VIII. APPENDIX C – TIME MOTION STUDIES SUPPORTING THE STAFFING ANALYSIS ...... 89

IX. OVERLAP OF TASKS ACTIVITIES OR OTHER CONFLICTS IDENTIFIED ......................... 92

A. Overlap Requiring Compensatory Measures ................................................................ 92

X. CORRECTIVE ACTIONS ............................................................................................................ 92

A. Corrective Actions and Compensatory Measures ......................................................... 92

XI. REFERENCES ............................................................................................................................. 93

XII. STAFFING ANALYIS TEAM........................................................................................................ 93

Page 34: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

I. INTRODUCTION

This document is a revision to the Palisades Nuclear Station On-shift Staffing Analysis (OSA) report dated

December 18, 2012.. This revision provides additional clarification to actions performed by on-shift staff,

incorporates technological advancements implemented to reduce on-shift staff burden, and provides additional

discussion of the basis for some evaluated events.

This revision continues to satisfy the requirements of 10 CFR 50 Appendix E Section IV.A.9, which states that

nuclear power licensees shall perform “a detailed analysis demonstrating that on-shift personnel assigned

emergency plan implementation functions are not assigned responsibilities that would prevent the timely

performance of their assigned functions as specified in the emergency plan.” A structured approach was utilized

to perform this analysis using the guidance found in NEI 10-05, Rev. 0, Assessment of On-Shift Emergency

Response Organization Staffing and Capabilities. This analysis examined the capability of the minimum staff

listed in Figure 5-2 of the Palisades Emergency Plan (E-Plan) to perform the actions for the key functional areas

of events described in NSIR/DPR-ISG-01, Interim Staff Guidance – Emergency Planning for Nuclear Power

Plants, until augmenting Emergency Response Organization (ERO) staff arrives in accordance with the E-Plan.

II. ANALYSIS SUMMARY

The OSA team determined that an on-shift staff of fourteen (14) is able to cope with the spectrum of analyzed events, as described in Section IV of this report, until augmenting Emergency Response Organization (ERO) staff arrives. The on-shift staff consists of individuals necessary to support each of the emergency plan functional areas or tasks:

Emergency Direction and Control Plant Operations and Safe Shutdown (SSD) Fire Fighting (FB) Accident Assessment Radiation Protection and Chemistry Notification/Communication Technical Support Access Control and Accountability

NEI 10-05 states it is acceptable for certain function to be assigned to personnel already assigned other functions/tasks. These include Repair and Corrective Action, Rescue Operations and First Aid.

The minimum on-shift staffing identified by this analysis is reflected in Table 1, “On-Shift Positions”, for each analyzed event. This is intended to identify the analyzed tasks performed by each on-shift ERO staff member based on the findings of the OSA.

Page 35: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

A. Emergency Plan Minimum Staffing

Per 10 CFR 50.54 (q)(1)(iii), Emergency planning function means a capability or resource necessary to prepare for and respond to a radiological emergency, as set forth in the elements of section IV of Appendix E and, for nuclear power reactor licensees, the planning standards of § 50.47(b).

The following table indicates the result of the NEI 10-05 staffing analysis of on-shift personnel to perform the required emergency planning functions and the licensing basis requirement for each on-shift position.

Position

Licensing Basis

Requirement E-Plan Functional Area On-Shift Staffing Analysis Results

Shift Manager (SM) 50.54m

E-Plan Figure 5-2

Emergency Direction and Control

1

Control Room Supervisor (CRS) 50.54m

E-Plan Figure 5-2

SSD 1

Shift Technical Advisor (STA) E-Plan Figure 5-2 Technical Support 1

Control Room Operator (RO #1) 50.54m

E-Plan Figure 5-2

SSD 1

Control Room Operator (RO #2) 50.54m

E-Plan Figure 5-2

SSD 1

Nuclear Plant Operator (NPO #1) E-Plan Figure 5-2 SSD 1

Nuclear Plant Operator (NPO #2) E-Plan Figure 5-2

FB 1

Nuclear Plant Operator (NPO #3) E-Plan Figure 5-2 FB 1

Nuclear Plant Operator (NPO #4) E-Plan Figure 5-2 FB 1

Nuclear Plant Operator (NPO #5) E-Plan Figure 5-2 FB 1

Nuclear Plant Operator (NPO #6) E-Plan Figure 5-2 FB 1

Communicator E-Plan Figure 5-2 Communications Notifications 1

Chemistry Technician E-Plan Figure 5-2

Accident Assessment/Chemistry 1

Radiation Protection (RP) #1 E-Plan Figure 5-2 Radiation Protection 1

Security Security Contingency Plan/E-Plan Figure

5-2

Access Control and Accountability

Per Security Contingency

Plan

TOTAL 14

Page 36: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

B. Other Commitments to Shift Staffing

No additional station commitments were identified conflicting with this staffing analysis.

C. Staffing Exceptions and Time Motion Studies (TMS)

1. The primary responsibility for the on-shift Chemistry Technician is chemistry/radiochemistry sampling; however no chemistry job tasks were noted as being required within the first 90 minutes of any of the analyzed events. As noted in the Site Emergency Plan, the on-shift Chemistry Technician may also be required to support the on-shift Radiation Protection Technician implement tasks to support the Major Functional Area of Protective Actions (In-plant). While the capability to perform these tasks are specified in the Emergency Plan, this analysis did not identify the need to utilize the on-shift Chemistry Technician to perform any of these Radiation Protection related tasks. It is recognized, however, that the Shift Manager will prioritize and utilize the on-shift staff as needed. It is therefore acceptable to assign the Chemistry Technician the E-Plan function of dose assessment. No further analysis or TMS is required.

2. The Shift Manager is assigned the responsibility to make site specific event notifications to the Duty Plant Manager, Operations Manager, and Resident Inspector. These notifications by phone are considered communications that are approximately one minute in length and are deemed acceptable in accordance with NEI 10-05 Section 3.2.2 (6)(a)(14) due to the short duration of the notifications. Additionally, these notifications are collectively evaluated in conjunction with other Shift Manager duties and responsibilities during Operations simulator training evaluations and Emergency Plan drills and are not deemed as impacting the Shift Managers ability to maintain oversight of the event or perform other required emergency plan tasks. In accordance with the guidance of NEI 10-05, Line 14 of NEI Table 5 contained in Section VII of this report does not reflect the performance of these short duration notifications. No further analysis or TMS is required.

3. Station staff are required to maintain continuous communications with the notification source during an aircraft threat in accordance with 10CFR50.54(hh) and Reg. Guide 1.214. There are no specific qualifications required to perform this task and the function is not required to be assigned in advance. The analysis of this event identified that the on-shift chemistry technician has no other assigned tasks in response to this event and would be available if needed to perform this task during the event. No further analysis or TMS is required.

Page 37: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

4. The Shift Manager is assigned the task of notifying the off-shift ERO of the emergency. A Time Motion Study (TMS) was conducted to ensure the Shift Manager could perform the concurrent tasks of maintaining emergency direction and control while notifying the ERO of the event using Everbridge. The TMS demonstrated the Shift Manager was able to maintain Emergency Direction and Control during the approximate two minutes it took to notify the ERO using Everbridge. Additionally, the task of ERO notification is routinely evaluated in conjunction with other Shift Manager duties and responsibilities during Operations simulator training evaluations and Emergency Plan drills.

5. The Palisades Emergency Response Data System (ERDS) link to the NRC is operated continuously and does not require activation following a declared emergency. The task of ERDS activation is therefore not included as an on-shift task requiring evaluation as part of this staffing analysis.

6. NRC event notifications required due to the declaration of an Emergency Classification in accordance with 10 CFR 50.72 is made verbally using the Emergency Notification System. A written event notification form is not generated by on-shift staff for this notification. Formal written notifications to the NRC as may be required by 10 CFR 50.72 resulting from any of the analyzed events may be generated by the augmented staff. The task of completing the NRC event notification form is therefore not included as an on-shift task requiring evaluation as part of this staffing analysis.

D. Emergency Plan Tasks Not Analyzed

1. Repair and Corrective Action - Per the guidance of NUREG-0654, Table B-1, repair and corrective action tasks may be performed by shift personnel assigned other functions. Repair and corrective action is defined as:

An action that can be performed promptly to restore a non-functional component to functional status (e.g., resetting a breaker), or to place a component in a desired configuration (e.g., open a valve), and which does not require work planning or implementation of lockout/tagout controls to complete.

In accordance with NEI 10-05 section 2.5, the analysis included a review of repair and corrective action tasks. For the purpose of this analysis, the tasks were considered to fall into two broad categories:

Unplanned/unexpected actions that address equipment failures. These actions are contingent in nature and cannot be specified in advance.

Planned/expected actions performed in support of operating procedure implementation, including severe accident management guidelines.

At Palisades, Nuclear Plant Operators are trained to perform the actions associated with this functional area. Actions (e.g., reset breakers, valve manipulation) directed by the Control Room Supervisor to mitigate the event per procedures were performed by the Nuclear Plant Operators in this analysis. Repair and Corrective Action is an acceptable collateral duty per the guidance of NEI 10-05 and was not analyzed

Page 38: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

2. Rescue Operations and First Aid: In accordance with NEI 10-05 section 2.6, the analysis also included a review of rescue operations and first aid response although neither task was required during the evaluated scenarios. Per the guidance of NUREG-0654, Table B-1, rescue operations and first aid may be performed by shift personnel assigned other functions. The on-shift Radiation Protection staff member is trained and available to perform first aid and the station Fire Brigade staff are trained and available to perform search and rescue if needed. Rescue operations and first aid response are acceptable collateral duties per the guidance of NEI 10-05.

III. ANALYSIS PROCESS

The initial staffing analysis (Revision 0) was conducted by a joint team of corporate Emergency Preparedness (EP) personnel and station personnel from the Operations, Training, Radiation Protection, Chemistry and Emergency Preparedness (EP) departments. Additionally, members of the Security staff provided input to the analysis.

The team members performing reviews to Revision 1 of the staffing analysis are identified in Section XII of this report. Revision 1 of this report was based on input, reviews and concurrence from station personnel from the same departments as those participating in the original analysis.

Each scenario was reviewed by the cross disciplinary team to determine what plant actions and emergency plan implementation actions were required based on plant procedures prior to staff augmentation. These actions were then compared to the minimum staffing for Emergency Plan implementation as described in the Emergency Plan Figure 5-2, ensuring that no actions were assigned to staff members that conflicted with either their dedicated emergency plan role or their dedicated operational role as appropriate. In cases where multiple tasks were assigned to an individual in their role, the team evaluated timing of the tasks to ensure that they could be performed by the individual in series within any specified time requirements.

The results of the analysis for each of the scenarios are included in Section VIII, APPENDIX B – ON-SHIFT STAFFING ANALYSIS. Note that NSIR DPR-ISG-01 states that only DBA accidents “which would result in an emergency declaration” should be evaluated in the staffing assessment. Each of Palisades DBA’s were evaluated and classified according to its FSAR Chapter 14 description. If the accident description alone did not result in a classification, the projected accident Exclusion Area Boundary (EAB) dose was utilized to determine if an EAL threshold would be exceeded within the first 60 minutes using the Abnormal Radiation Level EAL thresholds. In cases where several projected doses were provided or release data was not detailed significantly to determine an EAL, the assessment used the radiological consequences associated with the realistic case in accordance with NEI 10-05.

Page 39: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

IV. ACCIDENT SCENARIOS

A. Accident Selection

1. The OSA scenarios were chosen using the guidance of NEI 10-05 and NSIR/DPR-ISG-01, “Interim Staff Guidance – Emergency Planning for Nuclear Power Plants.” The evaluation considered the station Design Basis Accidents (DBA) described in the USAR along with additional scenarios specified by the guidance documents. The scenarios considered were:

Design Basis Threat (DBT) ground assault Control Rod Ejection Accident Main Steam Line Break Accident Loss of Coolant Accident, (LOCA) Fuel Handling Accident Aircraft Probable Threat Fire requiring evacuation of the Control Room and plant shutdown from remote location,

(Appendix R Fire) Station Blackout, (SBO) LOCA/General Emergency with release and PAR LOCA with entry into Severe Accident Management Small Line Break Outside Containment Waste Gas Accident Steam Generator Tube Rupture (SGTR) Dropped Cask Appendix R Fire

B. Accident Scenarios included in the Analysis 1. Design Basis Threat (DBT) as described in NEI 10-05

The event evaluated for this analysis assumes a land based threat that is neutralized immediately when inside the protected area fence, no significant damage to equipment or systems that require corrective actions before the ERO is staffed, no radiological release, and no fire that requires firefighting response before the ERO is staffed.

2. Control Rod Ejection Accident as described in FSAR 14.16

This event assumes the reactivity insertion from the control rod ejection results in an overpower trip. The thermal-hydraulic analysis for this event is performed for only a few seconds. The remaining consequences of this event are covered by the small break LOCA analysis as noted in Chapter 14.17.2 of the FSAR.

3. Main Steam Line Break (MSLB) Inside Containment as described in FSAR 14.14

This event assumes a double-ended guillotine break of a Main Steam Line inside containment with a loss of offsite power. Release information was not available in the FSAR, however, to determine if a radiation based EAL condition would be met in the first 60 minutes of the event. Emergency declaration was based on the loss of offsite power.

Page 40: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 10

4. Loss of Coolant Accident as described in FSAR 14.17.

This event is defined by a large rupture of the PCS cold leg piping between the PCP and the reactor vessel for the PCS loop containing the pressurizer. This event also includes a loss of offsite power and failure of 1 diesel generator.

5. Fuel Handling Accident (FHA) as described in 14.19.

The FHA is assumed to occur in containment two days after shutdown. An Alert emergency declaration was assumed to be declared due to the event.

6. Aircraft Probable Threat (50.54hh)

Notification is received from the NRC that a probable aircraft threat exists (>5 minutes, <30 minutes).

7. Fire requiring evacuation of the Control Room and plant shutdown from remote location, (Appendix R Fire) as described in NEI 10-05.

A fire occurs in the main control room requiring the evacuation and the procedure implemented to shutdown from the remote shutdown panels.

8. Station Blackout as described in NEI 10-05.

A loss of all offsite AC power occurs and the failure of the emergency diesel generators to start. The SM determines power cannot be restored and declares a SAE on EAL SS1.1.

9. LOCA/General Emergency (GE) with release and PAR as described in NEI 10-05.

This event is based on the same initial conditions of the LOCA but assumes system failures meet the GE conditions of a loss of 2 fission product boundaries with the potential loss of the third.

10. Small Line Break Outside Containment as described in FSAR 14.23.

This analysis assumes a charging line break resulting in a 160 gpm primary coolant leak outside containment.

11. Waste Gas Accident as described in FSAR 14.21.

This event assumes the rupture of a waste gas decay tank. EAL AA1.1 conditions are assumed to be met based on expected stack high range monitor readings.

12. Steam Generator Tube Rupture as described in FSAR 14.15 This event analyzes the response of a failure of a steam generator U-tube combined

with a loss of offsite power.

C. Accident Scenarios not included in the Analysis

1. LOCA with entry into Severe Accident Management Guidelines (SAMG) as described in NEI 10-05. NEI 10-05 Section 2.11 states that the analysis of the ability to implement SAMG focuses

on the reasonably expected initial mitigation action that would be performed by on-shift personnel other than licensed and non-licensed operators. Palisades SAMGs are guided by the TSC. All on-shift actions prior to off-site augmentation are performed by Licensed and Non-licensed operators. No additional analysis is required.

Page 41: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 11

2. Dropped Cask as described in FSAR 14.11. Analyzed dropped cask events were identified as events that would only occur with the

availability of additional station staff above and beyond those represented by station minimum staff and are outside the bounds of this analysis. Additionally, it was determined that no emergency declaration would be expected for this event.

3. Appendix R Fire The team concluded the Control Room and Cable Spreading Room fires to be the most

limiting fire events for resources and therefore a staffing analysis for the additional Appendix R fire scenario is not required. A review of operating procedures indicated that a fire in either of these rooms involves essentially the same operator actions, so the analysis considers only the Control Room fire in identifying required operator actions. The emergency plan and fire brigade responsibilities are the same for all fire events although the Control Room fire and the Cable Spreading Room fire also require the additional actions to support a remote plant shutdown. Station Fire Protection, Appendix R, and Operations staff were used to validate these fire events as being the most man-power intensive.

V. GENERAL ASSUMPTIONS AND LIMITATIONS

A. Notes and Assumptions applicable to all accidents in Palisades Staffing Analysis:

1. The RP and Chemistry tasks reviewed were those directed by the Shift Manager to support actions in Off Normal Procedures (ONP), Emergency Operating Procedures (EOP), and Emergency Implementing Procedures (EI). Any additional tasks directed by the Technical Support Center (TSC), Operations Support Center (OSC), or Emergency Operations Facility (EOF) procedures were not reviewed.

2. Palisades has 30 minute and 60 minute emergency responders when augmented while the ERO is offsite. This analysis was conducted assuming a 90 minute response of the augmented ERO to allow the use of this analysis for a possible future extension in ERO augmentation times. No specific emergency response tasks requiring the augmented ERO were identified prior to the 90 minutes following the emergency declaration.

3. The OSA team determined there are no time critical RP and Chemistry tasks and that task performance is directed and prioritized by the Shift Manager. The time RP or Chemistry is directed to perform a task and the amount of time taken to complete tasks are estimated. No Chemistry samples are required by Tech Specs within the 90 minute period after a declaration. Since the Shift Manager directs when the tasks are performed, there are no overlapping RP or chemistry tasks.

4. All crews have one individual filling the SM and one individual filling the STA roles therefore the analysis did not consider using a dual-role individual.

Page 42: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 12

B. NEI 10-05 Rev 0 Assumptions

1. Response time used for this analysis was the maximum acceptable number of minutes elapsed between emergency declaration and the augmented ERO position holder at a location necessary to relieve an on-shift position of the emergency response task. As noted above, this analysis assumed a 90 minute augmentation time.

2. On-shift personnel complement was limited to the minimum required number and composition as described in the site emergency plan. If the plan commitments allow for different minimum staffing levels (e.g., a variance between a normal dayshift and a backshift), the staffing with the smallest total number of personnel was used for the analysis.

3. Although the temporary absence of a position may be allowed by Tech Specs, the analysis was performed assuming that all required on-shift positions are filled.

4. Event occurred during off-normal work hours where ERO was offsite and all required minimum on-shift positions were filled.

5. On-shift personnel reported to their assigned response locations within timeframes sufficient to allow for performance of assigned actions.

6. On-shift staff had necessary Radiation Worker qualification to obtain normal dosimetry and enter the radiological control area (RCA) (but not locked high or very high radiation areas) without the aid of a RP technician.

7. Personnel assigned plant operations and SSD met the requirements and guidance (analyzed through other programs such as operator training) and were not evaluated as part of this assessment unless a role/function/task from another major response area was assigned as a collateral duty.

8. In-plant (manual) safety related operator actions to manipulate components and equipment from locations outside the control room to achieve and maintain safe shutdown were done by a member of the on-shift staff as defined in the unit’s Tech Specs.

9. Fire brigade (FB) staff performance is analyzed through other station programs (e.g., fire drills) and was not evaluated as part of this assessment unless a role/function/task from another major response area was assigned as a collateral duty.

10. Individuals holding the position of RP technician or Chemistry technician are qualified to perform the range of tasks expected of their position.

11. Security was not evaluated unless a role or function from another major response area was assigned as a collateral duty.

12. Communications, briefings, and peer checks are acceptable collateral duties.

13. All on-shift staff positions were evaluated, even if they had no known collateral duties, to ensure they can perform the tasks assigned to them. [Ref NSIR/DPR-ISG-01]

14. The Staffing Analysis specified the resources available to perform “Repair and Corrective Actions” and “Rescue Operations and First Aid” but these may be assigned as collateral duty to a designated on-shift responder.

Page 43: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 13

15. For assessment purposes, NRC notifications were treated as a continuous action per 10CFR50.72(c)(3) and 73.71(b)(1). This means once the initial NRC communications are established, the NRC will request an open line be maintained with the NRC Operations Center.

16. DBA (postulated accident, Condition IV event, or limiting fault) is considered as “Unanticipated occurrences that are postulated for accident analysis purposes but not expected to occur during the life of the plant. A postulated accident could result in sufficient damage to preclude resumption of plant operation. As a result, a greater number and variety of actions would need to be implemented by plant personnel.”

17. Unless otherwise specified in NSIR/DPR-ISG-01, Interim Staff Guidance – Emergency Planning for Nuclear Power Plants, or by the USAR initial conditions of a DBA analysis, it was assumed that the unit was in Mode 1, Power.

18. DBT assumed a hostile force breached the protected area fence but was neutralized with no adverse consequences to plant safety. Damage inflicted on plant systems, structures and components was not sufficient to prevent safe shutdown or cause a radiological release. There was no fire significant enough to warrant firefighting efforts prior to arrival of offsite resources and/or the augmented ERO.

19. The Staffing Analysis used DBA analysis assumptions, inputs, timing of events, plant protective response, and specified manual operator actions and their timing, as documented in the FSAR.

20. In cases where a DBA analysis included a radiological release, and the starting point of the release was not clearly defined, the staffing analysis assumed that the release began 15-minutes after the initiating event.

21. Severe Accident Management Guideline (SAMG) - this analysis assumed the accident progressed to conditions requiring a severe accident response; it did not include determining specific failures and the accident sequence.

22. SAMG - The actions analyzed included those that implement the initial site-specific actions assuming the core is not ex-vessel (i.e., no reactor vessel failure), and there is no actual or imminent challenge to containment integrity.

Page 44: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 14

VI. APPENDIX A - ANALYZED EVENTS AND ACCIDENTS Event

# Event Type

Summary Description of Event

Plant Mode1

Reference Document(s) Event ECL Analysis

Required? 1 DBT Land and/or

waterborne HOSTILE ACTION directed against the Protected Area by a HOSTILE FORCE. Assume adversary characteristics defined by the Design Basis Threat (DBT).

1 NEI 10-05 Site Area Emergency

Yes

2 DBA Control Rod Ejection 1 FSAR 14.16 Site Area Emergency

Yes

3 DBA Small Line Break Outside Containment

1 FSAR 14.23 Site Area Emergency

Yes

4 DBA Main Steam Line Break Inside Containment with LOOP (bounding for steam piping failures)

1 FSAR 14.14 Unusual Event (due to LOOP)

Yes

5 DBA LOCA 1 FSAR 14.17 Site Area Emergency

Yes

6 DBA Fuel Handling Accident 5 FSAR 14.19 Alert Yes 7 DBA Waste Tank Rupture 1 FSAR 14.21 Alert Yes 8 Assumed

for analysis purpose

Aircraft Probable Threat

1 10CFR50.54hh(1)

RG 1.214

Alert Yes

9 Assumed for

Analysis Purpose

Control Room Evacuation and Remote Shutdown (fire in main control room)

1 10CFR50 Appendix R

Procedure ONP-25.2

Alert Yes

10 Assumed for

analysis purpose

Station Blackout 1 10CFR50.63

Site Area Emergency

Yes

11 Assumed for

Analysis Purpose

LOCA – General Emergency with radiological release and PAR

1 ISG IV.C General Emergency

Yes

12 Assumed for

Analysis Purpose

LOCA with entry into severe accident procedures.

1 ISG IV.C General Emergency

No2

Page 45: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 15

Event #

Event Type

Summary Description of Event

Plant Mode1

Reference Document(s) Event ECL Analysis

Required? 13 Assumed

for Analysis Purpose

Appendix R Fire 1 ISG IV.C Alert No3

14 DBA Dropped Cask 1 FSAR 14.11 None No4 15 DBA Steam Generator Tube

Rupture with concurrent LOOP

1 FSAR 14.15 Alert Yes

1 Plant mode per FSAR or assumed for analysis purpose 2 SAMG is written to be implemented by the TSC. NEI 10-05 Section 2.11 states that the analysis of the ability to implement SAMG focuses on the reasonably expected initial mitigation action that would be performed by on-shift personnel other than licensed and non-licensed operators. Palisades does not include maintenance qualified to perform maintenance job tasks in minimum staffing and any response actions would be performed by operators. 3 Appendix R Fire is bound by the Control Room Fire and Remote Shutdown. 4 No emergency declaration is expected for this event.

Page 46: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 16

VII. APPENDIX B – ON-SHIFT STAFFING ANALYSIS

A. Accident Analysis #1 – Design Basis Threat (DBT)

1. Accident Summary

Land and/or waterborne HOSTILE ACTION directed against the Protected Area by a HOSTILE FORCE. Assume adversary characteristics defined by the Design Basis Threat.

This analysis concluded that sufficient staff was available to simultaneously implement both the emergency plan and the security plan. The conclusion that sufficient staff was available to implement the security plan was based on security staff personnel not being assigned collateral duties that would prevent the timely performance of their assigned functions.[m1] As noted in the analysis assumptions detailed in Section V.B.11 of this report and NEI 10-05 Section 3.1 items 12, the security organization is assumed to be able to satisfactorily perform all tasks related to Site and Protected Area Access Controls, under all event or accident conditions.

2. Accident Specific Assumptions Made

The Palisades DBT for this analysis assumes a land based threat although a waterborne threat was also considered to determine if it was a more man-power limiting event. This analysis identified that a change to the mode of the attack did not impact the staffing analysis or identify the assignment of any additional collateral duties for on-shift personnel that would prevent the timely performance of their assigned functions as specified in the emergency plan.

This event assumes the threat is neutralized immediately when inside the protected area fence, no significant damage to equipment or systems that require corrective actions before the ERO is staffed, no radiological release, and no fire that requires firefighting response before the ERO is staffed.

Assume at power in Mode 1

Security notifies the Shift Manager of condition of hostile action occurring within the protected area (Security code RED)

Assume all non-security staff is located inside the protected area at their normal work station when the event occurs.

Assume all systems function and the core remains covered. No fuel damage and no release.

3. Procedures for Accident Response

AOP-44 Rev. 0, Response to Attack on Palisades

EOP-1.0 Rev. 15, Standard Post Trip Actions

EI-1 Rev. 56, Emergency Classification and Actions

EI-3 Rev. 31, Communications and Notifications

EI-2.2 Rev. 15, Emergency Staff Augmentation

EI-12.1 Rev. 18, Personnel Accountability and Assembly

ADMIN-4, Rev. 52, Operations Organization, Responsibilities and Conduct

Page 47: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 17

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis # 1 DBT Security Threat

Line #

On-shift Position Basis Document

Augmentation Elapsed Time

(min)*

Role in Table # /

Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60

T2/L3 T5/L7

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 N/A No No

14 RP#1 Emergency Plan Figure 5-2 30 N/A No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A N/A No No

Page 48: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 18

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 1 DBT Security Threat Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable Line # Generic Title/Role On-Shift Position Task Analysis

Controlling Method

1 Shift Manager Shift Manager Licensed Operator Training

Program

2 Unit Supervisor CRS Licensed Operator Training

Program

3 Shift Technical Advisor STA Licensed Operator Training

Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator #1 Non-Licensed Operator

Training Program Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 49: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 19

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 1 DBT Security Threat

Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 50: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 20

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis # 1 DBT Security Threat

L I N E

Position Performing Function / Task

Performance Time Period After Emergency Declaration (minutes)

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85

85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: N/A

5 Offsite Rad Assessment: N/A

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

No chemistry or RP job function tasks for the conditions described in the DBT assumptions. RP and Chemistry take cover as directed.

Page 51: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 21

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis # 1 DBT Security Threat

Line# Function / Task On-Shift Position

Task Analysis Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager Emergency Planning Training

Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event STA Licensed Operator Training Program

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A

12 Offsite radiological assessment N/A N/A

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.) N/A N/A

15 Personnel Accountability Security Security Training Program / EP Drills

Page 52: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 22

B. Design Basis Accident Analysis #2 – Control Rod Ejection

1. Accident Summary This event assumes the reactivity insertion from the control rod ejection results in an

overpower trip. The thermal-hydraulic analysis for this event is performed for only a few seconds. The remaining consequences of this event are covered by the small break LOCA analysis as noted in Chapter 14.17.2 of the FSAR.

2. Accident Specific Assumptions Made

Reactivity insertion – overpower trip. The thermal-hydraulic analysis for this event is performed for only a few seconds. The

remaining consequences of this event are covered by the small break LOCA analysis in Chapter 14.17.2

The analysis assumes 14.7% of the fuel fails due to DNB considerations. 100% of the activity released from the damaged fuel is instantaneously released to the

containment atmosphere, from which leakage to the environment occurs. Radioactivity is transported to the secondary system through a 0.3 gpm primary to

secondary leak in each steam generator. EAB worst 2 hour dose containment release is within acceptable limits.

3. Procedures for Accident Response EOP-4.0 Rev. 22, Loss of Coolant Accident Recovery EOP-1.0 Rev. 15, Standard Post Trip Actions EI-1 Rev. 56, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 53: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 23

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis # 2 Control Rod Ejection Accident

Line #

On-shift Position Basis Document

Augmentation Elapsed Time

(min)*

Role in Table # /

Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30

T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A N/A No No

Page 54: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 24

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 2 Control Rod Ejection Accident Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable Line # Generic Title/Role On-Shift Position Task Analysis

Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 55: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 25

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 2 Control Rod Ejection Accident Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 56: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 26

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis # 2 Control Rod Ejection Accident

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP goes to CR for job support X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5)

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) - N/A

8 Chemistry Function task #2 (describe) – N/A

RP will perform the above task as directed by the Shift Manager. Task are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Page 57: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 27

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis # 2 Control Rod Ejection Accident

Line

# Function / Task On-Shift Position Task Analysis

Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A` Licensed Operator Training Program

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A

12 Offsite radiological assessment Chem Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/A N/A

15 Personnel Accountability Security Security Training Program / EP Drills

Page 58: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 28

C. Design Basis Accident Analysis #3 – Small Line Break Outside Containment as described in FSAR 14.23

1. Accident Summary

This analysis assumes a charging line break resulting in a 160 gpm primary coolant leak outside containment.

2. Accident Specific Assumptions Made

PCS activity of 1µCi/gm DEI released to the Auxiliary Building atmosphere. No reactor depressurization or trip was assumed to occur. An iodine spike was not

assumed. Leak isolation time assumed to be 1 hour.

3. Procedures for Accident Response

AOP-23 Rev. 0, Primary Coolant Leak EOP-4 Rev. 22, LOCA Recovery EOP-1.0 Rev. 15, Standard Post Trip Actions EI-1 Rev. 56, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 59: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 29

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis # 3 Small Line Break Outside Containment

Line #

On-shift Position Basis Document

Augmentation Elapsed Time

(min)*

Role in Table # /

Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 60: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 30

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 3 Small Line Break Outside Containment Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable Line # Generic Title/Role On-Shift Position Task Analysis

Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 61: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 31

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 3 Small Line Break Outside Containment Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 62: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 32

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis # 3 Small Line Break Outside Containment

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP goes to CR for job support X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5)

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) - N/A

8 Chemistry Function task #2 (describe) – N/A

RP will perform the above task as directed by the Shift Manager. Task are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Page 63: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 33

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis # 3 Small Line Break Outside Containment

Line

# Function / Task On-Shift Position Task Analysis

Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A Licensed Operator Training Program

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A

11 Activate ERDS N/A N/A

12 Offsite radiological assessment Chem Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/A N/A

15 Personnel Accountability Security Security Training Program / EP Drills

Page 64: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 34

D. Design Basis Accident Analysis #4 – Main Steam Line Break Inside Containment.

1. Accident Summary This event assumes a double-ended guillotine break of a Main Steam Line inside

containment with a loss of offsite power. Release information was not available in the FSAR to determine if a radiation based EAL condition would be met in the first 60 minutes of the event. Emergency declaration was based on the loss of offsite power.

2. Accident Specific Assumptions Made

MSL break assumes 0.3 gpm primary to secondary leak for the affected SG that flashes to steam and is released through the break area.

FSAR analysis assumes radionuclide releases from the primary coolant associated with 0.5% fuel failures.

The EAB worst 2 hour dose was noted in the FSAR as being within acceptable criteria but specific release information was not available to determine if a radiation based EAL condition was met in the first 60 minutes of the event. The event declaration was therefore made based on the loss of off-site power.

3. Procedures for Accident Response EOP-1.0 Rev. 15, Standard Post Trip Actions EI-1 Rev. 56, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications AOP-2 Rev. 0, Excessive Load ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct EOP-6.0 Rev.19, Excess Steam Demand Event

Page 65: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 35

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis # 4 Main Steam Line Break

Line # On-shift Position

E-Plan Reference Augmentation Elapsed Time

(min)

Role in Table # / Line # Unanalyzed

Task? TMS

Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 66: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 36

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 4 Main Steam Line Break Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis

Controlling Method 7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

Page 67: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 37

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 4 Main Steam Line Break Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 68: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 38

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis # 4 Main Steam Line Break

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP is available to support job coverage or surveys as required

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Table 5)

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

Although no specific radiological tasks were identified, the RP is available to provide support as directed by the Shift Manager. Tasks are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Page 69: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 39

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis # 4 Main Steam Line Break

Line # Function / Task On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/A N/A

15 Personnel Accountability Security Officer Security Training Program / EP Drills

Page 70: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 40

E. Design Basis Accident Analysis #5 – Loss of Coolant Accident.

1. Accident Summary

This event is defined by a large rupture of the PCS cold leg piping between the PCP and the reactor vessel for the PCS loop containing the pressurizer. This event also includes a loss of offsite power and failure of 1 diesel generator.

2. Accident Specific Assumptions Made

Large rupture of the PCS cold leg piping between the PCP and the reactor vessel for the PCS loop containing the pressurizer.

Rapid depressurization of the PCS, reactor trip signal but credit is taken for shut down by coolant voiding in the core. Experience DNB.

SIAS signal initiated Loss of offsite power and failure of 1 D/G Assumes loss of one ECCS train, one HPSI, one LPSI, all containment spray pumps and

all containment fan coolers are operational.

3. Procedures for Accident Response EOP-4.0 Rev. 22, Loss of Coolant Accident Recovery EOP-1.0 Rev. 15, Standard Post Trip Actions EI-1 Rev. 56, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct AOP-23, Rev. 0, Primary Coolant Leak

Page 71: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 41

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis # 5 Loss of Coolant Accident

Line #

On-shift Position E-Plan Reference

Augmentation Elapsed Time

(min)

Role in Table # / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L2 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 72: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 42

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 5 Loss of Coolant Accident Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

Page 73: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 43

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 5 Loss of Coolant Accident Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 74: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 44

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis # 5 Loss of Coolant Accident

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP reports to the CR to provide RP support (including in plant and out of plant surveys) as directed by the SM.

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: _(Included in Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

RP will perform the above task as directed by the Shift Manager. Tasks are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

.

Page 75: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 45

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION

Analysis # 5 Loss of Coolant Accident

Line #

Function / Task On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL)

Shift Manager Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

N/A Emergency Planning Training Program

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A Emergency Planning Training Program

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

Shift Manager Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.) N/A

N/A

15 Personnel Accountability Security Officer Security Training Program

Page 76: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 46

F. Design Basis Accident Analysis #6 – Fuel Handling Accident

1. Accident Summary The fuel handling accident is assumed to occur as a consequence of a failure of the fuel

assembly lifting mechanism, resulting in the dropping of a raised fuel assembly onto stored fuel bundles. The FHA is assumed to occur in containment two days after shutdown. An Alert emergency declaration was assumed to be declared due to the event.

2. Accident Specific Assumptions Made

An Alert is declared on the fuel handling event. Radiological release rates are not available to classify on the release.

Additional station personnel, including Operations and Health Physics Technicians, would normally be on-site during fuel movement activities. Additional station personnel were not required, however, to support initial response actions.

3. Procedures for Accident Response AOP-34 Rev. 0, Fuel Handling Accident EI-1 Rev. 56, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 77: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 47

4. TablesPALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis #6 – Fuel Handling Accident

Line # On-shift Position E-Plan Reference

Augmentation Elapsed Time

(min)

Role in Table # / Line # Unanalyzed

Task? TMS

Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 78: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 48

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 6 – Fuel Handling Accident Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 79: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 49

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 6 – Fuel Handling Accident Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 80: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 50

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #6 – Fuel Handling Accident

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: RP#2

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP reports to the CR to provide RP support (including in plant and out of plant surveys) as directed by the SM.

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

RP will perform the above task as directed by the Shift Manager. Tasks are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Page 81: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 51

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION

Analysis #6 – Fuel Handling Accident Line

# Function / Task On-Shift Position Task Analysis Controlling

Method

1 Declare the emergency classification level (ECL)

Shift Manager Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.) N/A

N/A

15 Personnel Accountability Security Officer Security Training Program

Page 82: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 52

G. Design Basis Accident Analysis #7 – Waste Tank Rupture

1. Accident Summary

This event assumes the rupture of a waste gas decay tank. EAL AA1.1 conditions are assumed to be met based on expected stack high range monitor readings.

2. Accident Specific Assumptions Made A rupture in the Waste Gas System or a rupture of the volume control tank would result

in offsite doses well below the 10 CFR 100 limits, and would not present any undue risk to the health and safety of the public.

The release for this accident is similar to the small break LOCA outside containment. Details are not provided to determine an EAL, therefore an assumption is made that EAL AA1.1 conditions are met based on the stack high range monitor.

3. Procedures for Accident Response

HP-2.8 Rev. 25, Response to Unusual Radiological Occurrences[m2] EI-1 Rev. 56, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 83: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 53

4. TablesPALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis #7 – Waste Tank Rupture

Line # On-shift Position E-Plan Reference

Augmentation Elapsed Time

(min)

Role in Table # / Line # Unanalyzed

Task? TMS

Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 84: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 54

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 7 – Waste Tank Rupture Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 85: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 55

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 7 – Waste Tank Rupture Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 86: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 56

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #7 –Waste Tank Rupture

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: RP#2

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP reports to the CR to provide RP support (including in plant and out of plant surveys) as directed by the SM.

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

RP will perform the above task as directed by the Shift Manager. Tasks are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Page 87: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 57

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION

Analysis #7 – Waste Tank Rupture Line

# Function / Task On-Shift Position Task Analysis Controlling

Method

1 Declare the emergency classification level (ECL)

Shift Manager Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.) N/A

N/A

15 Personnel Accountability Security Officer Security Training Program

Page 88: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 58

H. Accident Analysis #8 – Aircraft Probable Threat

1. Accident Summary

The analysis includes all emergency response actions taken prior to an aircraft impact in accordance with RG 1.214 for an aircraft threat that is greater than 5 minutes, but less than 30 minutes from the site, and considers the dispersal of the site fire brigade away from target areas for firefighting.

The analysis does not include a scenario or response actions taken during or after a crash.

2. Accident Specific Assumptions Made

The Shift Manager receives the call from the NRC of probable aircraft threat.

All non-security on-shift personnel are inside the protected area fence at their normal workstation.

Fire brigade personnel are included in Table 3, “Firefighting” to signify they are performing actions (relocation outside of the target area) specific to their assignment to the fire brigade and are not available to perform other tasks. While the inclusion of the fire brigade in Table 3 varies from the guidance of NEI 10-05, Section 3.2.2 (4)(a), the addition more clearly identifies on-shift staff actions.

3. Procedures for Accident Response

AOP-44 Rev. 0, Response to Security Threats EOP-1.0 Rev. 15, Standard Post Trip Actions EI-1 Rev. 56, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 89: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 59

4. Tables

PALISADES TABLE 1 – ON-SHIFT POSITIONS Analysis #8 – Aircraft Probable Threat

Line # On-shift Position Basis Document

Augmentation Elapsed Time

(min)

Role in Table 5 / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A T3/L1 No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A T3/L2 No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A T3/L3 No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

T3/L4

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A T3/L5 No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T4/L7 No No

14 RP#1 Emergency Plan Figure 5-2 30 T4/L6 No No

15 Security

Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 90: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 60

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN

One Unit – One Control Room Analysis #8 – Aircraft Probable Threat Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 91: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 61

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING Analysis #8 – Aircraft Probable Threat Line

# Performed by Task Analysis Controlling Method

1 Nuclear Plant Operator #2 Fire Brigade Training

2 Nuclear Plant Operator #3 Fire Brigade Training

3 Nuclear Plant Operator #4 Fire Brigade Training

4 Nuclear Plant Operator #5 Fire Brigade Training

5 Nuclear Plant Operator #6 Fire Brigade Training

This accident does not include the need for firefighting, first aid or search & rescue. The fire brigade is required, however, to relocate to the Training Center and is therefore not available to perform other tasks.

Page 92: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 62

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #8 – Aircraft Probable Threat

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: N/A

5 Offsite Rad Assessment: (Included in Table 5 – N/A

6 Other site specific RP : Relocate to survey vehicle outside PA

X X X X X X X X X X

7 Chemistry Function task #1: Support NRC open-line communications if needed

X X X X X X X X X X

8 Chemistry Function task #2 (describe) – N/A

*Times are estimated No specific RP or Chemistry tasks are performed for this event. At the on-set of this event, RP relocates to the survey vehicle outside the protected area and the Chemistry Technician is available to support NRC communications from the Control Room.

Page 93: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 63

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis #8 – Aircraft Probable Threat

Line #

Function / Task* On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A 12 Offsite radiological assessment N/A N/A

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/A N/A

15 Personnel Accountability Security Security Training Program

Page 94: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 64

I. Accident Analysis #9 – Control Room Fire Requiring Evacuation and Remote Shutdown

1. Accident Summary

This event involves a large transient fire requiring evacuation of the Control Room. The event has the potential to include shorts and/or spurious signals producing potential LOCA pathways and/or incorrect system lineup for shutdown.

2. Accident Specific Assumptions Made

The Nuclear Control Operator will initiate a manual reactor trip prior to evacuating the control room.

The Shift Manager will make the plant announcement prior to evacuating the control room.

3. Procedures for Accident Response AOP-40 Rev. 0, Fire Which Threatens Safety Related Equipment AOP-41 Rev. 0, Alternate Safe Shutdown Procedure EI-1 Rev. 56, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4.0 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 95: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 65

4. Tables

PALISADES TABLE 1 – ON-SHIFT POSITIONS Analysis #9 – CR Evacuation & Remote SD

Line # On-shift Position Basis Document

Augmentation Elapsed Time

(min)

Role in Table 5 / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A T3/L1 No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A T3/L2 No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A T3/L3 No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

T3/L4

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A T3/L5 No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 N/A No No

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security

Security Contingency Plan / Emergency Plan Figure 5-2

N/A N/A No No

Page 96: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 66

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN

One Unit – One Control Room Analysis #9 – CR Evacuation & Remote SD

Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 97: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 67

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING Analysis #9 – CR Evacuation & Remote SD Line

# Performed by Task Analysis Controlling Method

1 Nuclear Plant Operator #2 Fire Brigade Training

2 Nuclear Plant Operator #3 Fire Brigade Training

3 Nuclear Plant Operator #4 Fire Brigade Training

4 Nuclear Plant Operator #5 Fire Brigade Training

5 Nuclear Plant Operator #6 Fire Brigade Training

Page 98: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 68

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #9 – CR Evacuation & Remote SD

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP#1 Support FB X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) – N/A

8 Chemistry Function task #2 (describe) – N/A

*Times are estimated

Page 99: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 69

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis #9 – CR Evacuation & Remote SD

Line #

Function / Task* On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A 12 Offsite radiological assessment N/A N/A

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.) N/A N/A

15 Personnel Accountability N/A N/A

Page 100: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 70

J. Accident Analysis #10 – Station Blackout

1. Accident Summary

A loss of all offsite AC power occurs and the failure of the emergency diesel generators to start. The SM determines power cannot be restored and declares a SAE on EAL SS1.1.

2. Accident Specific Assumptions Made At time T-0 a loss of all AC power occurs No release occurs

3. Procedures for Accident Response

EOP-3 Rev. 15, Station Blackout Recovery AOP-26 Rev. o, Loss of Spent Fuel Pool cooling SOP-34 Rev. 29, Palisades Plant Computer (PPC) System EMG Emergency Management guideline

Page 101: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 71

4. Tables

PALISADES TABLE 1 – ON-SHIFT POSITIONS Analysis #10 – Station Blackout

Line # On-shift Position Basis

Document Augmentation Elapsed Time

(min)

Role in Table 5 / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 N/A No No

14 RP#1 Emergency Plan Figure 5-2 30 N/A No No

15 Security

Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 102: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 72

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

Analysis #10 – Station Blackout Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 103: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 73

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING Analysis #10 – Station Blackout Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 104: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 74

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #10 – Station Blackout

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP#1 CR for job coverage and CR habitability

X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) – N/A

8 Chemistry Function task #2 (describe) – N/A

*Times are estimated

Chemistry does not have an assigned chemistry task for SBO. Chemistry is available for dose assessment if a release occurs.

Page 105: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 75

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION

Analysis #10 – Station Blackout Line

# Function / Task* On-Shift Position Task Analysis

Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A 12 Offsite radiological assessment N/A N/A

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.) N/A N/A

15 Personnel Accountability Security Security Training Program

K. Accident Analysis #11 – LOCA/General Emergency with Release and PAR

1. Accident Summary (Assumed for Staffing Analysis Purpose)

The unit immediately enters a condition requiring the declaration of a General Emergency with indication of a radiological release that results in a dose that exceeds the Environmental Protection Agency’s Protective Action Guides beyond the site boundary, necessitating Protective Actions Recommendations..

2. Accident Specific Assumptions Made

No transients other than LOCA are considered.

3. Procedures for Accident Response EOP-4.0 Rev. 22, Loss of Coolant Accident Recovery EOP-1.0 Rev. 15, Standard Post Trip Actions EI-1 Rev. 56, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications

Page 106: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 76

EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct EI-6.13, Rev. 23, Protective Action Recommendations for Offsite Populations

Page 107: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 77

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis #11 – LOCA/GE with PAR

Line # On-shift Position Basis

Document Augmentation Elapsed Time

(min)

Role in Table 5 / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L2 T5/L3 T5/L4 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 N/A No No

15 Security

Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 108: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 78

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

Analysis #11 – LOCA/GE with PAR Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 109: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 79

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING Analysis #11 – LOCA/GE with PAR Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 110: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 80

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #11 – LOCA/GE with PAR

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: RP#1

2 On-site Survey: RP#2

3 Personnel Monitoring:

4 Job Coverage: RP reports to the CR to provide RP support (including in plant and out of plant surveys) as directed by the SM.

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: See Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

RP will perform the above task as directed by the Shift Manager. Tasks are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Chemistry does not have an assigned chemistry task for LOCA. Chemistry is available for dose assessment.

Page 111: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 81

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis #11 – LOCA/GE with PAR

Line #

Function / Task* On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL)

Shift Manager Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

Shift Manager Emergency Planning Training Program

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose Shift Manager Emergency Planning Training Program

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A Licensed Operator Training Program

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/A N/A

15 Personnel Accountability Security Security Training Program

Page 112: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 82

L. Accident Analysis #15 – Steam Generator Tube Rupture with Concurrent Loss of Off-site Power

1. Accident Summary

This event analyzes the response of a failure of a steam generator U-tube combined with a loss of offsite power.

2. Accident Specific Assumptions Made

Radiation monitor alarms on the MSLs, condenser air ejector discharge, SG blowdown line, fan room and plant stack before the reactor trip/turbine trip.

Following a reactor trip and turbine trip, the radioactive fluid is released through the steam generator safety or atmospheric dump valves as a result of the loss of normal AC power.

Doses are calculated for an event generated iodine spike, initial activity of 1 µCI/gm and a spiking factor of 335 (GIS) and a pre-accident iodine spike 40 µCI/gm (PIS).

Primary to secondary leakage rate of 432 gallons per day is assumed in the unaffected steam generator for the duration of the transient.

3. Procedures for Accident Response EOP-5.0 Rev. 17, Steam Generator Tube Rupture Recovery EOP-1.0 Rev. 15, Standard Post Trip Actions EI-1 Rev. 56, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct AOP-24 Rev. 0, SGT leak

Page 113: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 83

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS Analysis #15 – Steam Generator Tube Rupture

Line # On-shift Position Basis

Document Augmentation Elapsed Time

(min)

Role in Table 5 / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security

Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 114: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 84

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

Analysis #15 – Steam Generator Tube Rupture Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 115: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 85

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING Analysis #15 – Steam Generator Tube Rupture Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 116: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 86

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #15 – Steam Generator Tube Rupture

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring:

4 Job Coverage: RP performs surveys and job coverage as needed and directed by the SM.

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: See Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

*Times are estimated

Chemistry does not have an assigned chemistry task and is available for dose assessment.

Page 117: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 87

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis #15 – Steam Generator Tube Rupture

Line #

Function / Task* On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL)

Shift Manager Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

N/A Emergency Planning Training Program

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A Emergency Planning Training Program

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A Licensed Operator Training Program

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/A N/A 11 Activate ERDS N/A N/A

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/A N/A

15 Personnel Accountability Security Security Training Program

Page 118: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 88

VIII. APPENDIX C – TIME MOTION STUDIES SUPPORTING THE STAFFING ANALYSIS A. Dose Assessment

1. See Section II.C.1 for the exception taken for the Chemistry Technician to perform dose assessment. No time motion study or corrective actions is required.

B. ERO notification (Everbridge activation)

PALISADES

TIME MOTION STUDY OF OVERLAPPING TASKS

TASK 1: ACTIVATE THE ERO USING EVERBRIDGE

JOB: SHIFT MANAGER

TASK 2: EMERGENCY DIRECTION AND CONTROL

JOB: SHIFT MANAGER

Page 119: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT PURPOSE:

Perform a Time Motion Study to evaluate whether assigning the performance of ERO notification using Everbridge to the Shift Manager or STA can be justified as an acceptable overlap to the Shift Manager’s primary emergency plan function of direction and control.

LOCATION:

Simulator (to use the “TRAINING” event code to avoid inadvertent ERO activation for an EMERGENCY event.) Codes are site specific.

REQUIRED TOOLS/EQUIPMENT:

A. Individual performing the procedure actions must be logged on to the computer being used.

B. PC with Internet 7.0 and internet access.

C. Instructions/codes for activating Everbridge in the TRAINING mode. [Staged Instruction sheet for activating Everbridge may be used in lieu of EN-EP-310, Emergency Response Organization Notification System)]

NOTE

The Time Motion Study may be completed during simulator training/evaluation or during

EP drills

Page 120: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 90

Function / Responsibility (Task) Analysis Template

Event: ALL Site: Palisades Position: Shift Manager Line #: 1

Function Responsibility (Task) Action Step Duration

1.Notification 1.1 Initiate notification to

the ERO via the ERON

Program

Retrieve the Everbridge instruction that contains the [TRAINING] Access code and Pass code.

10 seconds

(On the PC) Open ERO Notification System by clicking:

Start Nuclear Corporate Apps (ESM) Nuclear Emergency Response (ESM) ERON

20 seconds

Enter Access code (XXXXX) and Pass code (XXXXX) and click the SUBMIT button

15 seconds

Select the appropriate classification by clicking on it.

(Select ALERT or scenario ECL)

15 seconds

Answer “Yes” or “No” to Security EAL question, “Was the event declared on a Security EAL?” [ Click on “NO”]

5 seconds

Select proper response action by clicking on it.

[Select “Activate All ERFs”}

10 seconds

Review the message that was generated in the User Message box at the bottom of the screen. Ensure the message contains the information to communicate to the ERO. Additional information can be added to the message by clicking in the User Message box and typing.

20 seconds

Once satisfied with the message content, click send notification button. [Click “Send Notification”]

10 seconds

Answer “YES” to send verification question, “Are you CERTAIN you want to send this message?” [Click “YES”]

5 seconds

If message was successfully sent, you will see a dialog box. [Click “Return”] 10 seconds

END OF INITIATE NOTIFICATION TO ERO TASK 2 minutes

(total time)

2.Emergency

Direction and

Control

2.1 Maintain emergency

direction and control of the

event response.

Oversight of the emergency response. Maintained Throughout

Initiate any emergency actions. Initiated as required

END OF EMERGENCY DIRECTION AND CONTROL TASK

Task Performer: Bruce Bauer Position: Shift Manager Date: 11/05/2012 Name Job Title Evaluator: Dan Malone Position: EP Manager Date: 11/05/2012 Name Job Title

Page 121: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 91

IX. OVERLAP OF TASKS ACTIVITIES OR OTHER CONFLICTS IDENTIFIED

A. Overlap Requiring Compensatory Measures

None

X. CORRECTIVE ACTIONS

A. Corrective Actions and Compensatory Measures

None

Page 122: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 92

XI. REFERENCES

NEI 10-05, Rev 0, Assessment of On-Shift Emergency Response Organization Staffing and Capabilities NSIR DPR-ISG-01, Interim Staff Guidance – Emergency Planning for Nuclear Power Plants NUREG-0654, Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and

Preparedness in Support of Nuclear Power Plants. Palisades Emergency Plan, Rev 25

XII. STAFFING ANALYIS TEAM

The staffing analysis team consisted of plant and Entergy Corporate staff representing the following departments / organizations: Fleet Emergency Preparedness Project Management Operations Training Security Chemistry Radiation Protection Regulatory Assurance Emergency Planning Engineering

o Fire Protection o Appendix R

Page 123: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ATTACHMENT 4

ON-SHIFT STAFFING ANALYSIS REPORT, REVISION 1

(marked up version)

(additions are underlined, deletions are stricken out)

(additions and deletions are not shown for Table of Contents)

93 Pages Follow

Page 124: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ONSHIFT STAFFING ANALYIS REPORT

PALISADES NUCLEAR STATION

ONSHIFT STAFFING ANALYSIS

Rev I

February 10, 2014

Prepared by: .. / Z 7-M. F. Guynn / Date

Peer

Review by— ..

My(J .e ate

I...,

.:

Approved by:Dan Malone / Date

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES NUCLEAR STATION

ON-SHIFT STAFFING ANALYSIS

Rev 1

February 10, 2014

P d b Pn 4 ~ / Z - 7- /u repare y: //L -<r .J'91~ I M. F. Guynn I Date

Approved by: ~~~~~~~P!4t.::..L.~-Dan Malone I Date

Page 125: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

TABLE OF CONTENTS

I. INTRODUCTION ............................................................................................................................ 4

II. ANALYSIS SUMMARY .................................................................................................................. 4

A. Emergency Plan Minimum Staffing .................................................................................. 6

B. Other Commitments to Shift Staffing ................................................................................ 7

C. Staffing Exceptions and Time Motion Studies (TMS) ..................................................... 7

D. Emergency Plan Tasks Not Analyzed .............................................................................. 8

III. ANALYSIS PROCESS ................................................................................................................... 9

IV. ACCIDENT SCENARIOS ............................................................................................................ 10

A. Accident Selection ........................................................................................................... 10

B. Accident Scenarios included in the Analysis ................................................................. 10

C. Accident Scenarios not included in the Analysis ........................................................... 11

V. GENERAL ASSUMPTIONS AND LIMITATIONS ...................................................................... 12

A. Notes and Assumptions applicable to all accidents in Palisades Staffing Analysis: .. 12

B. NEI 10-05 Rev 0 Assumptions ........................................................................................ 13

VI. APPENDIX A - ANALYZED EVENTS AND ACCIDENTS ........................................................ 15

VII. APPENDIX B – ON-SHIFT STAFFING ANALYSIS .................................................................. 17

A. Accident Analysis #1 – Design Basis Threat (DBT) ...................................................... 17

B. Design Basis Accident Analysis #2 – Control Rod Ejection ......................................... 23

C. Design Basis Accident Analysis #3 – Small Line Break Outside Containment as described in FSAR 14.23 ................................................................................................ 29

D. Design Basis Accident Analysis #4 – Main Steam Line Break Inside Containment. . 35

E. Design Basis Accident Analysis #5 – Loss of Coolant Accident. ................................. 41

F. Design Basis Accident Analysis #6 – Fuel Handling Accident ..................................... 47

G. Design Basis Accident Analysis #7 – Waste Tank Rupture ......................................... 53

H. Accident Analysis #8 – Aircraft Probable Threat ........................................................... 59

I. Accident Analysis #9 – Control Room Fire Requiring Evacuation and Remote Shutdown .......................................................................................................................... 65

J. Accident Analysis #10 – Station Blackout ...................................................................... 71

K. Accident Analysis #11 – LOCA/General Emergency with Release and PAR............. 77

Page 126: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

L. Accident Analysis #15 – Steam Generator Tube Rupture with Concurrent Loss of Off-site Power ................................................................................................................... 83

VIII. APPENDIX C – TIME MOTION STUDIES SUPPORTING THE STAFFING ANALYSIS ...... 89

IX. OVERLAP OF TASKS ACTIVITIES OR OTHER CONFLICTS IDENTIFIED ......................... 92

A. Overlap Requiring Compensatory Measures ................................................................ 92

X. CORRECTIVE ACTIONS ............................................................................................................ 92

A. Corrective Actions and Compensatory Measures ......................................................... 92

XI. REFERENCES ............................................................................................................................. 93

XII. STAFFING ANALYIS TEAM........................................................................................................ 93

Page 127: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

I. INTRODUCTION

This document is a revision to the Palisades Nuclear Station the final report for the On-shift Staffing Analysis

(OSA) report dated December 18, 2012.that commenced at Palisades Nuclear Station during the week of June

11, 2012. This revision provides additional clarification to actions performed by on-shift staff, incorporates

technological advancements implemented to reduce on-shift staff burden, and provides additional discussion of

the basis for some evaluated events.

This revision continues to OSA satisfyies the requirements of 10 CFR 50 Appendix E Section IV.A.9, which states

that nuclear power licensees shall perform “a detailed analysis demonstrating that on-shift personnel assigned

emergency plan implementation functions are not assigned responsibilities that would prevent the timely

performance of their assigned functions as specified in the emergency plan.” A structured approach was utilized

to perform this analysis using the guidance found in NEI 10-05, Rev. 0, Assessment of On-Shift Emergency

Response Organization Staffing and Capabilities. This analysis examined the capability of the minimum staff

listed in Figure 5-2 of the Palisades Emergency Plan (E-Plan) to perform the actions for the key functional areas

of events described in NSIR/DPR-ISG-01, Interim Staff Guidance – Emergency Planning for Nuclear Power

Plants, until augmenting Emergency Response Organization (ERO) staff arrives in accordance with the E-Plan.

II. ANALYSIS SUMMARY

The OSA team determined that an on-shift staff of fourteen (14) is able to cope with the spectrum of analyzed events, as described in Section IV of this report, until augmenting Emergency Response Organization (ERO) staff arrives.required to respond to the most limiting accident scenario reviewed, main control room fire and shutdown at the remote shutdown panel. The on-shift staff consists of individuals necessary to support each of the emergency plan functional areas or tasks:

Emergency Direction and Control Plant Operations and Safe Shutdown (SSD) Fire Fighting (FB) Accident Assessment Radiation Protection and Chemistry Notification/Communication Technical Support Access Control and Accountability

NEI 10-05 states it is acceptable for certain function to be assigned to personnel already assigned other functions/tasks. These include Repair and Corrective Action, Rescue Operations and First Aid.

The minimum on-shift staffing identified by this analysis is reflected in Table 1, “On-Shift Positions”, for each analyzed event. This is intended to identify the analyzed tasks performed by each on-shift ERO staff member

Page 128: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

based on the findings of the OSA. Any overlap of tasks or other conflicts identified during this OSA are captured in Section IX of this report and are based on the actual staffing at the time the analysis was considered complete.

Page 129: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

A. Emergency Plan Minimum Staffing

Per 10 CFR 50.54 (q)(1)(iii), Emergency planning function means a capability or resource necessary to prepare for and respond to a radiological emergency, as set forth in the elements of section IV of Appendix E and, for nuclear power reactor licensees, the planning standards of § 50.47(b).

The following table indicates the result of the NEI 10-05 staffing analysis of on-shift personnel to perform the required emergency planning functions and the licensing basis requirement for each on-shift position.

Position

Licensing Basis

Requirement E-Plan Functional Area On-Shift Staffing Analysis Results

Shift Manager (SM) 50.54m

E-Plan Figure 5-2

Emergency Direction and Control

1

Control Room Supervisor (CRS) 50.54m

E-Plan Figure 5-2

SSD 1

Shift Technical Advisor (STA) E-Plan Figure 5-2 Technical Support 1

Control Room Operator (RO #1) 50.54m

E-Plan Figure 5-2

SSD 1

Control Room Operator (RO #2) 50.54m

E-Plan Figure 5-2

SSD 1

Nuclear Plant Operator (NPO #1) E-Plan Figure 5-2 SSD 1

Nuclear Plant Operator (NPO #2) E-Plan Figure 5-2

FB 1

Nuclear Plant Operator (NPO #3) E-Plan Figure 5-2 FB 1

Nuclear Plant Operator (NPO #4) E-Plan Figure 5-2 FB 1

Nuclear Plant Operator (NPO #5) E-Plan Figure 5-2 FB 1

Nuclear Plant Operator (NPO #6) E-Plan Figure 5-2 FB 1

Communicator E-Plan Figure 5-2 Communications Notifications 1

Chemistry Technician E-Plan Figure 5-2

Accident Assessment/Chemistry 1

Radiation Protection (RP) #1 E-Plan Figure 5-2 Radiation Protection 1

Security Security Contingency Plan/E-Plan Figure

5-2

Access Control and Accountability

Per Security Contingency

Plan

TOTAL 14

Page 130: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

B. Other Commitments to Shift Staffing

No additional stations commitments were identified conflicting with this staffing analysis.

C. Staffing Exceptions and Time Motion Studies (TMS)

1. The primary responsibility for the on-shift Chemistry Technician is chemistry/radiochemistry sampling; however no chemistry job tasks were noted as being required within the first 90 minutes of any of the analyzed events. As noted in the Site Emergency Plan, the on-shift Chemistry Technician may also be required to support the on-shift Radiation Protection Technician implement specific tasks to support the Major Functional Area of Protective Actions (In-plant). These specific tasks consist of access control, RP Coverage, Ppersonnel monitoring, and dosimetry. While the capability to perform these tasks are specified in the Emergency Plan, this analysis did not identify the need to utilize the on-shift Chemistry Technician to perform any of these Radiation Protection related tasks. It is recognized, however, that the Shift Manager will prioritize and utilize the on-shift staff as needed. It is therefore acceptable to assign the Chemistry Technician the E-Plan function of dose assessment. No further analysis or TMS is required.

2. The Shift Manager is assigned the responsibility to make some site specific event notifications such as to the Duty Plant Manager, Operations Manager, and Resident Inspector. These notifications by phone are considered communications that are approximately one minute in length and are acceptable tasks for the Shift Manager.deemed acceptable in accordance with NEI 10-05 Section 3.2.2 (6)(a)(14) due to the short duration of the notifications. Additionally, these notifications are collectively evaluated in conjunction with other Shift Manager duties and responsibilities during Operations simulator training evaluations and Emergency Plan drills and are not deemed as impacting the Shift Managers ability to maintain oversight of the event or perform other required emergency plan tasks. In accordance with the guidance of NEI 10-05, Line 14 of NEI Table 5 contained in Section VII of this report does not reflect the performance of these short duration notifications. No further analysis or TMS is required.

3. Station staff are required to maintain continuous communications with the notification source during an aircraft threat in accordance with 10CFR50.54(hh) and Reg. Guide 1.214. There are no specific qualifications required to perform this task and the function is not required to be assigned in advance. The analysis of this event identified that the on-shift chemistry technician has no other assigned tasks in response to this event and would be available if needed to there are sufficient personnel on-shift to perform this task during the event. Specifically, a Nuclear Plant Operator, the radiation protection technician and/or chemistry technician can be made available to fill this function. No further analysis or TMS is required.

Page 131: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

4. The Shift Manager is assigned the task of notifying the off-shift ERO of the emergency. A Time Motion Study (TMS) was conducted to ensure the Shift Manager could perform the concurrent tasks of maintaining emergency direction and control while notifying the ERO of the event using Everbridge. The TMS demonstrated the Shift Manager was able to maintain Emergency Direction and Control during the approximate two minutes it took to notify the ERO using Everbridge. Additionally, the task of ERO notification is routinely evaluated in conjunction with other Shift Manager duties and responsibilities during Operations simulator training evaluations and Emergency Plan drills.

5. The Palisades Emergency Response Data System (ERDS) link to the NRC is operated continuously and does not require activation following a declared emergency. The task of ERDS activation is therefore not included as an on-shift task requiring evaluation as part of this staffing analysis.

6. NRC event notifications required due to the declaration of an Emergency Classification in accordance with 10 CFR 50.72 is made verbally using the Emergency Notification System. A written event notification form is not generated by on-shift staff for this notification. Formal written notifications to the NRC as may be required by 10 CFR 50.72 resulting from any of the analyzed events may be generated by the augmented staff. The task of completing the NRC event notification form is therefore not included as an on-shift task requiring evaluation as part of this staffing analysis.

D. Emergency Plan Tasks Not Analyzed

1. Repair and Corrective Action - Per the guidance of NUREG-0654, Table B-1, repair and corrective action tasks may be performed by shift personnel assigned other functions. Repair and corrective action is defined as:

An action that can be performed promptly to restore a non-functional component to functional status (e.g., resetting a breaker), or to place a component in a desired configuration (e.g., open a valve), and which does not require work planning or implementation of lockout/tagout controls to complete.

In accordance with NEI 10-05 section 2.5, the analysis included a review of repair and corrective action tasks. For the purpose of this analysis, the tasks were considered to fall into two broad categories:

Unplanned/unexpected actions that address equipment failures. These actions are contingent in nature and cannot be specified in advance.

Planned/expected actions performed in support of operating procedure implementation, including severe accident management guidelines.

At Palisades, Nuclear Plant Operators are trained to perform the actions associated with this functional area. Actions (e.g., reset breakers, valve manipulation) directed by the Control Room Supervisor to mitigate the event per procedures were performed by the Nuclear Plant Operators in this analysis. Repair and Corrective Action is an acceptable collateral duty per the guidance of NEI 10-05 and was not analyzed

Page 132: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page

2. Rescue Operations and First Aid: In accordance with NEI 10-05 section 2.6, the analysis also included a review of rescue operations and first aid response although neither task was required during the evaluated scenarios. Per the guidance of NUREG-0654, Table B-1, rescue operations and first aid may be performed by shift personnel assigned other functions. The on-shift Radiation Protection staff member is trained and available to perform first aid and the station Fire Brigade staff are trained and available to perform search and rescue if needed. Rescue operations and first aid response are acceptable collateral duties per the guidance of NEI 10-05.

III. ANALYSIS PROCESS

The initial staffing analysis (Revision 0) was conducted by a joint team of corporate Emergency Preparedness (EP) personnel and station personnel from the Operations, Training, Radiation Protection, Chemistry and Emergency Preparedness (EP) departments. Additionally, members of the Security staff provided input to the analysis.

The team members performing reviews to Revision 1 of the staffing analysis are identified in Section XII of this report. Revision 1 of this report was based on input, reviews and concurrence from station personnel from the same departments as those participating in the original analysis.

This analysis was conducted by a joint team of corporate Emergency Preparedness (EP) personnel and station personnel from the Operations, Training, Radiation Protection, Chemistry and Emergency Preparedness (EP) departments. Additionally, personnel from Engineering and Security provided input to the analysis. The team members are identified in Section XII of this report.

The emergency response to each event was determined by conducting a tabletop of the event using the emergency plan and procedures and the applicable department procedures such as Operations emergency and abnormal operating procedures.

Each scenario was reviewed by the cross disciplinary team to determine what plant actions and emergency plan implementation actions were required based on plant procedures prior to staff augmentation. These actions were then compared to the minimum staffing for Emergency Plan implementation as described in the Emergency Plan Figure 5-2, ensuring that no actions were assigned to staff members that conflicted with either their dedicated emergency plan role or their dedicated operational role as appropriate. In cases where multiple tasks were assigned to an individual in their role, the team evaluated timing of the tasks to ensure that they could be performed by the individual in series within any specified time requirements.

The results of the analysis for each of the scenarios are included in Section VIII, APPENDIX B – ON-SHIFT STAFFING ANALYSIS. Note that NSIR DPR-ISG-01 states that only DBA accidents “which would result in an emergency declaration” should be evaluated in the staffing assessment. Each of Palisades DBA’s were evaluated and classified according to its FSAR Chapter 14 description. If the accident description alone did not result in a classification, the projected accident Exclusion Area Boundary (EAB) dose was utilized to determine if an EAL threshold would be exceeded within the first 60 minutes using the Abnormal Radiation Level EAL thresholds. In cases where several projected doses were provided or release data was not detailed significantly to determine an EAL, the assessment used the radiological consequences associated with the realistic case in accordance with NEI 10-05.

Page 133: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 10

IV. ACCIDENT SCENARIOS

A. Accident Selection

1. The OSA scenarios were chosen using the guidance of NEI 10-05 and NSIR/DPR-ISG-01, “Interim Staff Guidance – Emergency Planning for Nuclear Power Plants.” The evaluation considered the station Design Basis Accidents (DBA) described in the USAR along with additional scenarios specified by the guidance documents. The scenarios considered were:

Design Basis Threat (DBT) ground assault Control Rod Ejection Accident Main Steam Line Break Accident Loss of Coolant Accident, (LOCA) Fuel Handling Accident Aircraft Probable Threat Fire requiring evacuation of the Control Room and plant shutdown from remote location,

(Appendix R Fire) Station Blackout, (SBO) LOCA/General Emergency with release and PAR LOCA with entry into Severe Accident Management Small Line Break Outside Containment Waste Gas Accident Steam Generator Tube Rupture (SGTR) Dropped Cask Appendix R Fire

B. Accident Scenarios included in the Analysis 1. Design Basis Threat (DBT) as described in NEI 10-05

The event evaluated for this analysis assumes a land based threat that is neutralized immediately when inside the protected area fence, no significant damage to equipment or systems that require corrective actions before the ERO is staffed, no radiological release, and no fire that requires firefighting response before the ERO is staffed.

2. Control Rod Ejection Accident as described in FSAR 14.16

This event assumes the reactivity insertion from the control rod ejection results in an overpower trip. The thermal-hydraulic analysis for this event is performed for only a few seconds. The remaining consequences of this event are covered by the small break LOCA analysis as noted in Chapter 14.17.2 of the FSAR.

3. Main Steam Line Break (MSLB) Inside Containment as described in FSAR 14.14

This event assumes a double-ended guillotine break of a Main Steam Line inside containment with a loss of offsite power. Release information was not available in the FSAR, however, to determine if a radiation based EAL condition would be met in the first 60 minutes of the event. Emergency declaration was based on the loss of offsite power.

Page 134: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 11

4. Loss of Coolant Accident as described in FSAR 14.17.

This event is defined by a large rupture of the PCS cold leg piping between the PCP and the reactor vessel for the PCS loop containing the pressurizer. This event also includes a loss of offsite power and failure of 1 diesel generator.

5. Fuel Handling Accident (FHA) as described in 14.19.

The FHA is assumed to occur in containment two days after shutdown. An Alert emergency declaration was assumed to be declared due to the event.

6. Aircraft Probable Threat (50.54hh)

Notification is received from the NRC that a probable aircraft threat exists (>5 minutes, <30 minutes).

7. Fire requiring evacuation of the Control Room and plant shutdown from remote location, (Appendix R Fire) as described in NEI 10-05.

A fire occurs in the main control room requiring the evacuation and the procedure implemented to shutdown from the remote shutdown panels.

8. Station Blackout as described in NEI 10-05.

A loss of all offsite AC power occurs and the failure of the emergency diesel generators to start. The SM determines power cannot be restored and declares a SAE on EAL SS1.1.

9. LOCA/General Emergency (GE) with release and PAR as described in NEI 10-05.

This event is based on the same initial conditions of the LOCA but assumes system failures meet the GE conditions of a loss of 2 fission product boundaries with the potential loss of the third.

10. Small Line Break Outside Containment as described in FSAR 14.23.

This analysis assumes a charging line break resulting in a 160 gpm primary coolant leak outside containment.

11. Waste Gas Accident as described in FSAR 14.21.

This event assumes the rupture of a waste gas decay tank. EAL AA1.1 conditions are assumed to be met based on expected stack high range monitor readings.

12. Steam Generator Tube Rupture as described in FSAR 14.15 This event analyzes the response of a failure of a steam generator U-tube combined

with a loss of offsite power.

C. Accident Scenarios not included in the Analysis

1. LOCA with entry into Severe Accident Management Guidelines (SAMG) as described in NEI 10-05. NEI 10-05 Section 2.11 states that the analysis of the ability to implement SAMG focuses

on the reasonably expected initial mitigation action that would be performed by on-shift

Page 135: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 12

personnel other than licensed and non-licensed operators. Palisades SAMGs are guided by the TSC. All on-shift actions prior to off-site augmentation are performed by Licensed and Non-licensed operators. No additional analysis is required.

2. Dropped Cask as described in FSAR 14.11. Analyzed dropped cask events were identified as events that would only occur with the

availability of additional station staff above and beyond those represented by station minimum staff and are outside the bounds of this analysis. Additionally, it was determined that no emergency declaration would be expected for this event.

3. Appendix R Fire The team concluded the Control Room and Cable Spreading Room fires to be the most

limiting fire events for resources and therefore a staffing analysis for the additional Appendix R fire scenario is not required. A review of operating procedures indicated that a fire in either of these rooms involves essentially the same operator actions, so the analysis considers only the Control Room fire in identifying required operator actions. The emergency plan and fire brigade responsibilities are the same for all fire events although the Control Room fire and the Cable Spreading Room fire also require the additional actions to support a remote plant shutdown. Station Fire Protection, Appendix R, and Operations staff were used to validate these fire events as being the most man-power intensive.

The team concluded the Control Room fire to be the most limiting for resources and therefore a staffing analysis for an additional fire scenario is not required. The emergency plan and fire brigade responsibilities are the same for both events.

V. GENERAL ASSUMPTIONS AND LIMITATIONS

A. Notes and Assumptions applicable to all accidents in Palisades Staffing Analysis:

1. The RP and Chemistry tasks reviewed were those directed by the Shift Manager to support actions in Off Normal Procedures (ONP), Emergency Operating Procedures (EOP), and Emergency Implementing Procedures (EI). Any additional tasks directed by the Technical Support Center (TSC), Operations Support Center (OSC), or Emergency Operations Facility (EOF) procedures were not reviewed.

2. Palisades has 30 minute and 60 minute emergency responders when augmented while the ERO is offsite. This analysis was conducted assuming a 90 minute response of the augmented ERO to allow the use of this analysis for a possible future extension in ERO augmentation times. No specific emergency response tasks requiring the augmented ERO were identified prior to the 90 minutes following the emergency declaration.

3. The OSA team determined there are no time critical RP and Chemistry tasks and that task performance is directed and prioritized by the Shift Manager. The time RP or Chemistry is directed to perform a task and the amount of time taken to complete tasks are estimated. No Chemistry samples are required by Tech Specs within the 90 minute period after a declaration. Since the Shift Manager directs when the tasks are performed, there are no overlapping RP or chemistry tasks.

Page 136: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 13

4. All crews have one individual filling the SM and one individual filling the STA roles therefore the analysis did not consider using a dual-role individual.

B. NEI 10-05 Rev 0 Assumptions

1. Response time used for this analysis was the maximum acceptable number of minutes elapsed between emergency declaration and the augmented ERO position holder at a location necessary to relieve an on-shift position of the emergency response task. As noted above, this analysis assumed a 90 minute augmentation time.

2. On-shift personnel complement was limited to the minimum required number and composition as described in the site emergency plan. If the plan commitments allow for different minimum staffing levels (e.g., a variance between a normal dayshift and a backshift), the staffing with the smallest total number of personnel was used for the analysis.

3. Although the temporary absence of a position may be allowed by Tech Specs, the analysis was performed assuming that all required on-shift positions are filled.

4. Event occurred during off-normal work hours where ERO was offsite and all required minimum on-shift positions were filled.

5. On-shift personnel reported to their assigned response locations within timeframes sufficient to allow for performance of assigned actions.

6. On-shift staff had necessary Radiation Worker qualification to obtain normal dosimetry and enter the radiological control area (RCA) (but not locked high or very high radiation areas) without the aid of a RP technician.

7. Personnel assigned plant operations and SSD met the requirements and guidance (analyzed through other programs such as operator training) and were not evaluated as part of this assessment unless a role/function/task from another major response area was assigned as a collateral duty.

8. In-plant (manual) safety related operator actions to manipulate components and equipment from locations outside the control room to achieve and maintain safe shutdown were done by a member of the on-shift staff as defined in the unit’s Tech Specs.

9. Fire brigade (FB) staff performance is analyzed through other station programs (e.g., fire drills) and was not evaluated as part of this assessment unless a role/function/task from another major response area was assigned as a collateral duty.

10. Individuals holding the position of RP technician or Chemistry technician are qualified to perform the range of tasks expected of their position.

11. Security was not evaluated unless a role or function from another major response area was assigned as a collateral duty.

12. Communications, briefings, and peer checks are acceptable collateral duties.

Page 137: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 14

13. All on-shift staff positions were evaluated, even if they had no known collateral duties, to ensure they can perform the tasks assigned to them. [Ref NSIR/DPR-ISG-01]

14. The Staffing Analysis specified the resources available to perform “Repair and Corrective Actions” and “Rescue Operations and First Aid” but these may be assigned as collateral duty to a designated on-shift responder.

15. For assessment purposes, NRC notifications were treated as a continuous action per 10CFR50.72(c)(3) and 73.71(b)(1). This means once the initial NRC communications are established, the NRC will request an open line be maintained with the NRC Operations Center.

16. DBA (postulated accident, Condition IV event, or limiting fault) is considered as “Unanticipated occurrences that are postulated for accident analysis purposes but not expected to occur during the life of the plant. A postulated accident could result in sufficient damage to preclude resumption of plant operation. As a result, a greater number and variety of actions would need to be implemented by plant personnel.”

17. Unless otherwise specified in NSIR/DPR-ISG-01, Interim Staff Guidance – Emergency Planning for Nuclear Power Plants, or by the USAR initial conditions of a DBA analysis, it was assumed that the unit was in Mode 1, Power.

18. DBT assumed a hostile force breached the protected area fence but was neutralized with no adverse consequences to plant safety. Damage inflicted on plant systems, structures and components was not sufficient to prevent safe shutdown or cause a radiological release. There was no fire significant enough to warrant firefighting efforts prior to arrival of offsite resources and/or the augmented ERO.

19. The Staffing Analysis used DBA analysis assumptions, inputs, timing of events, plant protective response, and specified manual operator actions and their timing, as documented in the FSAR.

20. In cases where a DBA analysis included a radiological release, and the starting point of the release was not clearly defined, the staffing analysis assumed that the release began 15-minutes after the initiating event.

21. Severe Accident Management Guideline (SAMG) - this analysis assumed the accident progressed to conditions requiring a severe accident response; it did not include determining specific failures and the accident sequence.

22. SAMG - The actions analyzed included those that implement the initial site-specific actions assuming the core is not ex-vessel (i.e., no reactor vessel failure), and there is no actual or imminent challenge to containment integrity.

Page 138: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 15

VI. APPENDIX A - ANALYZED EVENTS AND ACCIDENTS Event

# Event Type

Summary Description of Event

Plant Mode1

Reference Document(s) Event ECL Analysis

Required? 1 DBT Land and/or

waterborne HOSTILE ACTION directed against the Protected Area by a HOSTILE FORCE. Assume adversary characteristics defined by the Design Basis Threat (DBT).

1 NEI 10-05 Site Area Emergency

Yes

2 DBA Control Rod Ejection 1 FSAR 14.16 Site Area Emergency

Yes

3 DBA Small Line Break Outside Containment

1 FSAR 14.23 Site Area Emergency

Yes

4 DBA Main Steam Line Break Inside Containment with LOOP (bounding for steam piping failures)

1 FSAR 14.14 Unusual Event (due to LOOP)

Yes

5 DBA LOCA 1 FSAR 14.17 Site Area Emergency

Yes

6 DBA Fuel Handling Accident 5 FSAR 14.19 Alert Yes 7 DBA Waste Tank Rupture 1 FSAR 14.21 Alert Yes 8 Assumed

for analysis purpose

Aircraft Probable Threat

1 10CFR50.54hh(1)

RG 1.214

Alert Yes

9 Assumed for

Analysis Purpose

Control Room Evacuation and Remote Shutdown (fire in main control room)

1 10CFR50 Appendix R

Procedure ONP-25.2

Alert Yes

10 Assumed for

analysis purpose

Station Blackout 1 10CFR50.63

Site Area Emergency

Yes

11 Assumed for

Analysis Purpose

LOCA – General Emergency with radiological release and PAR

1 ISG IV.C General Emergency

Yes

12 Assumed for

Analysis Purpose

LOCA with entry into severe accident procedures.

1 ISG IV.C General Emergency

No2

Page 139: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 16

Event #

Event Type

Summary Description of Event

Plant Mode1

Reference Document(s) Event ECL Analysis

Required? 13 Assumed

for Analysis Purpose

Appendix R Fire 1 ISG IV.C Alert No3

14 DBA Dropped Cask 1 FSAR 14.11 None No4 15 DBA Steam Generator Tube

Rupture with concurrent LOOP

1 FSAR 14.15 Alert Yes

1 Plant mode per FSAR or assumed for analysis purpose 2 SAMG is written to be implemented by the TSC. NEI 10-05 Section 2.11 states that the analysis of the ability to implement SAMG focuses on the reasonably expected initial mitigation action that would be performed by on-shift personnel other than licensed and non-licensed operators. Palisades does not include maintenance qualified to perform maintenance job tasks in minimum staffing and any response actions would be performed by operators. 3 Appendix R Fire is bound by the Control Room Fire and Remote Shutdown. 4 No emergency declaration is expected for this event.

Page 140: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 17

VII. APPENDIX B – ON-SHIFT STAFFING ANALYSIS

A. Accident Analysis #1 – Design Basis Threat (DBT)

1. Accident Summary

Land and/or waterborne HOSTILE ACTION directed against the Protected Area by a HOSTILE FORCE. Assume adversary characteristics defined by the Design Basis Threat.

This analysis concluded that sufficient staff was available to simultaneously implement both the emergency plan and the security plan. The conclusion that sufficient staff was available to implement the security plan was based on security staff personnel not being assigned collateral duties that would prevent the timely performance of their assigned functions. As noted in the analysis assumptions detailed in Section V.B.11 of this report and NEI 10-05 Section 3.1 items 12, the security organization is assumed to be able to satisfactorily perform all tasks related to Site and Protected Area Access Controls, under all event or accident conditions.

2. Accident Specific Assumptions Made

The Palisades DBT for this analysis assumes a land based threat.threat although a waterborne threat was also considered to determine if it was a more man-power limiting event. This analysis identified that a change to the mode of the attack did not impact the staffing analysis or identify the assignment of any additional collateral duties for on-shift personnel that would prevent the timely performance of their assigned functions as specified in the emergency plan.

This event assumes the threat is neutralized immediately when inside the protected area fence, no significant damage to equipment or systems that require corrective actions before the ERO is staffed, no radiological release, and no fire that requires firefighting response before the ERO is staffed.

Assume at power in Mode 1

Security notifies the Shift Manager of condition of hostile action occurring within the protected area (Security code RED)

Assume all non-security staff is located inside the protected area at their normal work station when the event occurs.

Assume all systems function and the core remains covered. No fuel damage and no release.

3. Procedures for Accident Response

ONP-28.2 Rev.2AOP-44 Rev. 0, Response to Attack on Palisades

EOP-1.0 Rev. 1315, Standard Post Trip Actions

EI-1 Rev. 5456, Emergency Classification and Actions

EI-3 Rev. 31, Communications and Notifications

EI-2.2 Rev. 15, Emergency Staff Augmentation

EI-12.1 Rev. 18, Personnel Accountability and Assembly

ADMIN-4, Rev. 52, Operations Organization, Responsibilities and Conduct

Page 141: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 18

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis # 1 DBT Security Threat

Line #

On-shift Position Basis Document

Augmentation Elapsed Time

(min)*

Role in Table # /

Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8 T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60

T2/L3 T5/L7

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 N/A No No

14 RP#1 Emergency Plan Figure 5-2 30 N/A No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A N/A No No

Page 142: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 19

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 1 DBT Security Threat Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable Line # Generic Title/Role On-Shift Position Task Analysis

Controlling Method

1 Shift Manager Shift Manager Licensed Operator Training

Program

2 Unit Supervisor CRS Licensed Operator Training

Program

3 Shift Technical Advisor STA Licensed Operator Training

Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator #1 Non-Licensed Operator

Training Program Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 143: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 20

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 1 DBT Security Threat

Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 144: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 21

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis # 1 DBT Security Threat

L I N E

Position Performing Function / Task

Performance Time Period After Emergency Declaration (minutes)

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85

85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: N/A

5 Offsite Rad Assessment: N/A

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

No chemistry or RP job function tasks for the conditions described in the DBT assumptions. RP and Chemistry take cover as directed.

Page 145: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 22

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis # 1 DBT Security Threat

Line# Function / Task On-Shift Position

Task Analysis Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager Emergency Planning Training

Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event STA Licensed Operator Training Program

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form Shift ManagerN/A

Licensed Operator Training ProgramN/A

11 Activate ERDS Shift ManagerN/A

Emergency Planning Training ProgramN/A

12 Offsite radiological assessment N/A N/A

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

Shift ManagerN/A

Licensed Operator Training ProgramN/A

15 Personnel Accountability Security Security Training Program / EP Drills

Page 146: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 23

B. Design Basis Accident Analysis #2 – Control Rod Ejection

1. Accident Summary This event assumes the reactivity insertion from the control rod ejection results in an

overpower trip. The thermal-hydraulic analysis for this event is performed for only a few seconds. The remaining consequences of this event are covered by the small break LOCA analysis as noted in Chapter 14.17.2 of the FSAR.

2. Accident Specific Assumptions Made

Reactivity insertion – overpower trip. The thermal-hydraulic analysis for this event is performed for only a few seconds. The

remaining consequences of this event are covered by the small break LOCA analysis in Chapter 14.17.2

The analysis assumes 14.7% of the fuel fails due to DNB considerations. 100% of the activity released from the damaged fuel is instantaneously released to the

containment atmosphere, from which leakage to the environment occurs. Radioactivity is transported to the secondary system through a 0.3 gpm primary to

secondary leak in each steam generator. EAB worst 2 hour dose containment release is within acceptable limits.

3. Procedures for Accident Response EOP-4.0 Rev. 2220, Loss of Coolant Accident Recovery EOP-1.0 Rev. 1315, Standard Post Trip Actions EI-1 Rev. 5456, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 147: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 24

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis # 2 Control Rod Ejection Accident

Line #

On-shift Position Basis Document

Augmentation Elapsed Time

(min)*

Role in Table # /

Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8 T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30

T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A N/A No No

Page 148: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 25

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 2 Control Rod Ejection Accident Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable Line # Generic Title/Role On-Shift Position Task Analysis

Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 149: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 26

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 2 Control Rod Ejection Accident Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 150: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 27

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis # 2 Control Rod Ejection Accident

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP goes to CR for job support X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5)

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) - N/A

8 Chemistry Function task #2 (describe) – N/A

RP will perform the above task as directed by the Shift Manager. Task are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Page 151: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 28

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis # 2 Control Rod Ejection Accident

Line

# Function / Task On-Shift Position Task Analysis

Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A` Licensed Operator Training Program

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form Shift ManagerN/A Licensed Operator Training ProgramN/A

11 Activate ERDS Shift ManagerN/A Emergency Planning Training ProgramN/A

12 Offsite radiological assessment Chem Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

Shift ManagerN/A Licensed Operator Training ProgramN/A

15 Personnel Accountability Security Security Training Program / EP Drills

Page 152: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 29

C. Design Basis Accident Analysis #3 – Small Line Break Outside Containment as described in FSAR 14.23

1. Accident Summary

This analysis assumes a charging line break resulting in a 160 gpm primary coolant leak outside containment.

2. Accident Specific Assumptions Made

PCS activity of 1µCi/gm DEI released to the Auxiliary Building atmosphere. No reactor depressurization or trip was assumed to occur. An iodine spike was not

assumed. Leak isolation time assumed to be 1 hour.

3. Procedures for Accident Response

ONPAOP-23.1 Rev. 025, Primary Coolant Leak EOP-4 Rev. 2022, LOCA Recovery EOP-1.0 Rev. 1315, Standard Post Trip Actions EI-1 Rev. 5456, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 153: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 30

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis # 3 Small Line Break Outside Containment

Line #

On-shift Position Basis Document

Augmentation Elapsed Time

(min)*

Role in Table # /

Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8 T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 154: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 31

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 3 Small Line Break Outside Containment Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable Line # Generic Title/Role On-Shift Position Task Analysis

Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 155: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 32

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 3 Small Line Break Outside Containment Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 156: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 33

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis # 3 Small Line Break Outside Containment

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP goes to CR for job support X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5)

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) - N/A

8 Chemistry Function task #2 (describe) – N/A

RP will perform the above task as directed by the Shift Manager. Task are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Page 157: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 34

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis # 3 Small Line Break Outside Containment

Line

# Function / Task On-Shift Position Task Analysis

Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A Licensed Operator Training Program

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form Shift ManagerN/A N/ALicensed Operator Training Program

11 Activate ERDS N/AShift Manager N/AEmergency Planning Training Program

12 Offsite radiological assessment Chem Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/AShift Manager N/ALicensed Operator Training Program

15 Personnel Accountability Security Security Training Program / EP Drills

Page 158: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 35

D. Design Basis Accident Analysis #4 – Main Steam Line Break Inside Containment.

1. Accident Summary This event assumes a double-ended guillotine break of a Main Steam Line inside

containment with a loss of offsite power. Release information was not available in the FSAR to determine if a radiation based EAL condition would be met in the first 60 minutes of the event. Emergency declaration was based on the loss of offsite power.

2. Accident Specific Assumptions Made

MSL break assumes 0.3 gpm primary to secondary leak for the affected SG that flashes to steam and is released through the break area.

FSAR analysis assumes radionuclide releases from the primary coolant associated with 0.5% fuel failures.

The EAB worst 2 hour dose was noted in the FSAR as being within acceptable criteria but specific release information was not available to determine if a radiation based EAL condition was met in the first 60 minutes of the event. The event declaration was therefore made based on the loss of off-site power.

3. Procedures for Accident Response EOP-1.0 Rev. 1315, Standard Post Trip Actions EI-1 Rev. 5456, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications ONP-9AOP-2 Rev. 07, Excessive Load ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct EOP-6.0 Rev.1719, Excess Steam Demand Event

Page 159: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 36

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis # 4 Main Steam Line Break

Line # On-shift Position

E-Plan Reference Augmentation Elapsed Time

(min)

Role in Table # / Line # Unanalyzed

Task? TMS

Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 160: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 37

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 4 Main Steam Line Break Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis

Controlling Method 7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

Page 161: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 38

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 4 Main Steam Line Break Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 162: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 39

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis # 4 Main Steam Line Break

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP is available to support job coverage or surveys as required

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Table 5)

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

Although no specific radiological tasks were identified, the RP is available to provide support as directed by the Shift Manager. Tasks are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Page 163: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 40

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis # 4 Main Steam Line Break

Line # Function / Task On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/AShift Manager N/ALicensed Operator Training Program

11 Activate ERDS N/AShift Manager N/AEmergency Planning Training Program

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/AShift Manager N/ALicensed Operator Training Program

15 Personnel Accountability Security Officer Security Training Program / EP Drills

Page 164: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 41

E. Design Basis Accident Analysis #5 – Loss of Coolant Accident.

1. Accident Summary

This event is defined by a large rupture of the PCS cold leg piping between the PCP and the reactor vessel for the PCS loop containing the pressurizer. This event also includes a loss of offsite power and failure of 1 diesel generator.

2. Accident Specific Assumptions Made

Large rupture of the PCS cold leg piping between the PCP and the reactor vessel for the PCS loop containing the pressurizer.

Rapid depressurization of the PCS, reactor trip signal but credit is taken for shut down by coolant voiding in the core. Experience DNB.

SIAS signal initiated Loss of offsite power and failure of 1 D/G Assumes loss of one ECCS train, one HPSI, one LPSI, all containment spray pumps and

all containment fan coolers are operational.

3. Procedures for Accident Response EOP-4.0 Rev. 20 22, Loss of Coolant Accident Recovery EOP-1.0 Rev. 1315, Standard Post Trip Actions EI-1 Rev. 5456, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct ONPAOP-23.1, Rev. 25 0, Primary Coolant Leak

Page 165: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 42

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis # 5 Loss of Coolant Accident

Line #

On-shift Position E-Plan Reference

Augmentation Elapsed Time

(min)

Role in Table # / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L2 T5/L3 T5/L5 T5/L6 T5/L8 T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 166: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 43

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN

One Unit – One Control Room ANALYSIS # 5 Loss of Coolant Accident

Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

Page 167: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 44

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 5 Loss of Coolant Accident Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 168: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 45

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis # 5 Loss of Coolant Accident

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP reports to the CR to provide RP support (including in plant and out of plant surveys) as directed by the SM.

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: _(Included in Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

RP will perform the above task as directed by the Shift Manager. Tasks are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

.

Page 169: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 46

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION

Analysis # 5 Loss of Coolant Accident

Line #

Function / Task On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL)

Shift Manager Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

N/A Emergency Planning Training Program

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A Emergency Planning Training Program

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.)

Shift Manager Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/AShift Manager N/ALicensed Operator Training Program

11 Activate ERDS N/AShift Manager N/AEmergency Planning Training Program

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.) N/AShift Manager

N/ALicensed Operator Training Program

15 Personnel Accountability Security Officer Security Training Program

Page 170: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 47

F. Design Basis Accident Analysis #6 – Fuel Handling Accident

1. Accident Summary The fuel handling accident is assumed to occur as a consequence of a failure of the fuel

assembly lifting mechanism, resulting in the dropping of a raised fuel assembly onto stored fuel bundles. The FHA is assumed to occur in containment two days after shutdown. An Alert emergency declaration was assumed to be declared due to the event.

2. Accident Specific Assumptions Made

An Alert is declared on the fuel handling event. Radiological release rates are not available to classify on the release.

Additional station personnel, including Operations and Health Physics Technicians, would normally be on-site during fuel movement activities. Additional station personnel were not required, however, to support initial response actions.

3. Procedures for Accident Response ONPAOP-11.234 Rev. 07, Fuel Handling Accident EI-1 Rev. 5456, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 171: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 48

4. TablesPALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis #6 – Fuel Handling Accident

Line # On-shift Position E-Plan Reference

Augmentation Elapsed Time

(min)

Role in Table # / Line # Unanalyzed

Task? TMS

Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 172: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 49

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 6 – Fuel Handling Accident Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 173: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 50

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 6 – Fuel Handling Accident Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 174: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 51

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #6 – Fuel Handling Accident

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: RP#2

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP reports to the CR to provide RP support (including in plant and out of plant surveys) as directed by the SM.

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

RP will perform the above task as directed by the Shift Manager. Tasks are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Page 175: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 52

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION

Analysis #6 – Fuel Handling Accident Line

# Function / Task On-Shift Position Task Analysis Controlling

Method

1 Declare the emergency classification level (ECL)

Shift Manager Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/AShift Manager N/ALicensed Operator Training Program

11 Activate ERDS N/AShift Manager N/AEmergency Planning Training Program

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/AShift Manager N/ALicensed Operator Training Program

15 Personnel Accountability Security Officer Security Training Program

Page 176: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 53

G. Design Basis Accident Analysis #7 – Waste Tank Rupture

1. Accident Summary

This event assumes the rupture of a waste gas decay tank. EAL AA1.1 conditions are assumed to be met based on expected stack high range monitor readings.

2. Accident Specific Assumptions Made A rupture in the Waste Gas System or a rupture of the volume control tank would result

in offsite doses well below the 10 CFR 100 limits, and would not present any undue risk to the health and safety of the public.

The release for this accident is similar to the small break LOCA outside containment. Details are not provided to determine an EAL, therefore an assumption is made that EAL AA1.1 conditions are met based on the stack high range monitor.

3. Procedures for Accident Response

HP-2.8 Rev. 25, Response to Unusual Radiological Occurrences EI-1 Rev. 5456, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 177: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 54

4. TablesPALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis #7 – Waste Tank Rupture

Line # On-shift Position E-Plan Reference

Augmentation Elapsed Time

(min)

Role in Table # / Line # Unanalyzed

Task? TMS

Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8

T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 178: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 55

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

ANALYSIS # 7 – Waste Tank Rupture Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 179: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 56

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING ANALYSIS # 7 – Waste Tank Rupture Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 180: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 57

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #7 –Waste Tank Rupture

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: RP#2

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP reports to the CR to provide RP support (including in plant and out of plant surveys) as directed by the SM.

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

RP will perform the above task as directed by the Shift Manager. Tasks are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Page 181: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 58

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION

Analysis #7 – Waste Tank Rupture Line

# Function / Task On-Shift Position Task Analysis Controlling

Method

1 Declare the emergency classification level (ECL)

Shift Manager Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/AShift Manager N/ALicensed Operator Training Program

11 Activate ERDS N/AShift Manager N/AEmergency Planning Training Program

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/AShift Manager N/ALicensed Operator Training Program

15 Personnel Accountability Security Officer Security Training Program

Page 182: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 59

H. Accident Analysis #8 – Aircraft Probable Threat

1. Accident Summary

The analysis includes all emergency response actions taken prior to an aircraft impact in accordance with RG 1.214 for an aircraft threat that is greater than 5 minutes, but less than 30 minutes from the site, and considers the dispersal of the site fire brigade away from target areas for firefighting.

The analysis does not include a scenario or response actions taken during or after a crash.

2. Accident Specific Assumptions Made

The Shift Manager receives the call from the NRC of probable aircraft threat.

All non-security on-shift personnel are inside the protected area fence at their normal workstation.

Fire brigade personnel are included in Table 3, “Firefighting” to signify they are performing actions (relocation outside of the target area) specific to their assignment to the fire brigade and are not available to perform other tasks. While the inclusion of the fire brigade in Table 3 varies from the guidance of NEI 10-05, Section 3.2.2 (4)(a), the addition more clearly identifies on-shift staff actions.

3. Procedures for Accident Response

ONPAOP-28.144 Rev. 10, Response to Security Threats EOP-1.0 Rev. 1315, Standard Post Trip Actions EI-1 Rev. 5456, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct

Page 183: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 60

4. Tables

PALISADES TABLE 1 – ON-SHIFT POSITIONS Analysis #8 – Aircraft Probable Threat

Line # On-shift Position Basis Document

Augmentation Elapsed Time

(min)

Role in Table 5 / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8 T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/AT3/L1 No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/AT3/L2 No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/AT3/L3 No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A T3/L4

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/AT3/L5 No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T4/L7 No No

14 RP#1 Emergency Plan Figure 5-2 30 T4/L6 No No

15 Security

Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 184: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 61

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN

One Unit – One Control Room Analysis #8 – Aircraft Probable Threat Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 185: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 62

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING Analysis #8 – Aircraft Probable Threat Line

# Performed by Task Analysis Controlling Method

1 Nuclear Plant Operator #2N/A Fire Brigade Training N/A

2 Nuclear Plant Operator #3N/A Fire Brigade Training N/A

3 Nuclear Plant Operator #4N/A Fire Brigade Training N/A

4 Nuclear Plant Operator #5N/A Fire Brigade Training N/A

5 Nuclear Plant Operator #6N/A Fire Brigade Training N/A

This accident does not include the need for firefighting, first aid or search & rescue. The fire brigade is required, however, to relocates to the Training Center and is therefore not available to perform other tasks.

Page 186: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 63

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #8 – Aircraft Probable Threat

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: N/A

5 Offsite Rad Assessment: (Included in Table 5 – N/A

6 Other site specific RP (describe): Relocate to survey vehicle outside PA

X X X X X X X X X X

7 Chemistry Function task #1 (describe): Support NRC open-line communications if needed

X X X X X X X X X X

8 Chemistry Function task #2 (describe) – N/A

*Times are estimated No specific RP or Chemistry tasks are performed for this event. At the on-set of this event, RP relocates to the survey vehicle outside the protected area and the Chemistry Technician relocates to the Training Centeris available to support NRC communications from the Control Room.

Page 187: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 64

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis #8 – Aircraft Probable Threat

Line #

Function / Task* On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form Shift ManagerN/A N/ALicensed Operator Training Program

11 Activate ERDS N/AShift Manager N/AEmergency Planning Training Program

12 Offsite radiological assessment N/A N/A

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/AShift Manager N/ALicensed Operator Training Program

15 Personnel Accountability Security Security Training Program

Page 188: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 65

I. Accident Analysis #9 – Control Room Fire Requiring Evacuation and Remote Shutdown

1. Accident Summary

This event involves a large transient fire requiring evacuation of the Control Room. The event has the potential to include shorts and/or spurious signals producing potential LOCA pathways and/or incorrect system lineup for shutdown.

2. Accident Specific Assumptions Made

The Nuclear Control Operator will initiate a manual reactor trip prior to evacuating the control room.

The Shift Manager will make the plant announcement prior to evacuating the control room.

3. Procedures for Accident Response ONPAOP-25.140 Rev. 021, Fire Which Threatens Safety Related Equipment ONPAOP-25.241 Rev. 028, Alternate Safe Shutdown Procedure EI-1 Rev. 5456, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4.0 Rev. 5247, Operations Organization, Responsibilities and Conduct

Page 189: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 66

4. Tables

PALISADES TABLE 1 – ON-SHIFT POSITIONS Analysis #9 – CR Evacuation & Remote SD

Line # On-shift Position Basis Document

Augmentation Elapsed Time

(min)

Role in Table 5 / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8 T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A T3/L1 No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A T3/L2 No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A T3/L3 No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

T3/L4

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A T3/L5 No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 N/A No No

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security

Security Contingency Plan / Emergency Plan Figure 5-2

N/A N/A No No

Page 190: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 67

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN

One Unit – One Control Room Analysis #9 – CR Evacuation & Remote SD

Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 191: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 68

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING Analysis #9 – CR Evacuation & Remote SD Line

# Performed by Task Analysis Controlling Method

1 Nuclear Plant Operator #2 Fire Brigade Training

2 Nuclear Plant Operator #3 Fire Brigade Training

3 Nuclear Plant Operator #4 Fire Brigade Training

4 Nuclear Plant Operator #5 Fire Brigade Training

5 Nuclear Plant Operator #6 Fire Brigade Training

Page 192: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 69

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #9 – CR Evacuation & Remote SD

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP#1 Support FB X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) – N/A

8 Chemistry Function task #2 (describe) – N/A

*Times are estimated

Page 193: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 70

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis #9 – CR Evacuation & Remote SD

Line #

Function / Task* On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/AShift Manager N/ALicensed Operator Training Program

11 Activate ERDS N/AShift Manager N/AEmergency Planning Training Program

12 Offsite radiological assessment N/A N/A

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.) N/AShift Manager N/ALicensed Operator

Training Program 15 Personnel Accountability N/A N/A

Page 194: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 71

J. Accident Analysis #10 – Station Blackout

1. Accident Summary

A loss of all offsite AC power occurs and the failure of the emergency diesel generators to start. The SM determines power cannot be restored and declares a SAE on EAL SS1.1.

2. Accident Specific Assumptions Made At time T-0 a loss of all AC power occurs No release occurs

3. Procedures for Accident Response

EOP-3 Rev. 1415, Station Blackout Recovery ONPAOP-23.426 Rev. o3, Loss of Spent Fuel Pool cooling SOP-34 Rev. 29, Palisades Plant Computer (PPC) System EMG Emergency Management guideline

Page 195: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 72

4. Tables

PALISADES TABLE 1 – ON-SHIFT POSITIONS Analysis #10 – Station Blackout

Line # On-shift Position Basis

Document Augmentation Elapsed Time

(min)

Role in Table 5 / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8 T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 N/A No No

14 RP#1 Emergency Plan Figure 5-2 30 N/A No No

15 Security

Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 196: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 73

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

Analysis #10 – Station Blackout Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 197: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 74

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING Analysis #10 – Station Blackout Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 198: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 75

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #10 – Station Blackout

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring: N/A

4 Job Coverage: RP#1 CR for job coverage and CR habitability

X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: (Included in Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) – N/A

8 Chemistry Function task #2 (describe) – N/A

*Times are estimated

Chemistry does not have an assigned chemistry task for SBO. Chemistry is available for dose assessment if a release occurs.

Page 199: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 76

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION

Analysis #10 – Station Blackout Line

# Function / Task* On-Shift Position Task Analysis

Controlling Method

1 Declare the emergency classification level (ECL) Shift Manager

Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations N/A N/A

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A N/A

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A N/A

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form N/AShift Manager N/ALicensed Operator Training Program

11 Activate ERDS N/AShift Manager N/AEmergency Planning Training Program

12 Offsite radiological assessment N/A N/A

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.) N/AShift Manager N/ALicensed Operator

Training Program 15 Personnel Accountability Security Security Training Program

Page 200: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 77

K. Accident Analysis #11 – LOCA/General Emergency with Release and PAR

1. Accident Summary (Assumed for Staffing Analysis Purpose)

The unit immediately enters a condition requiring the declaration of a General Emergency with indication of a radiological release that results in a dose that exceeds the Environmental Protection Agency’s Protective Action Guides beyond the site boundary, necessitating Protective Actions Recommendations.is in a Site Area Emergency when the Shift Manager is given a dose assessment update that projects >1 Rem TEDE dose at the site boundary.

2. Accident Specific Assumptions Made

All actions for SAE are complete.

No transients other than LOCA are considered.

The ERO would be activated at an Alert or SAE. For Staffing Analysis purpose, the T=0 clock is used for the emergency plan actions to evaluate the capability to implement the GE classification, PAR and notification functions before the ERO arrives.

3. Procedures for Accident Response EOP-4.0 Rev. 20 22, Loss of Coolant Accident Recovery EOP-1.0 Rev. 1315, Standard Post Trip Actions EI-1 Rev. 5456, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct EI-6.13, Rev. 21 23, Protective Action Recommendations for Offsite Populations

Page 201: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 78

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS

Analysis #11 – LOCA/GE with PAR

Line # On-shift Position Basis

Document Augmentation Elapsed Time

(min)

Role in Table 5 / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L2 T5/L3 T5/L4 T5/L5 T5/L6 T5/L8 T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 N/A No No

15 Security

Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 202: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 79

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

Analysis #11 – LOCA/GE with PAR Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 203: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 80

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING Analysis #11 – LOCA/GE with PAR Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 204: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 81

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #11 – LOCA/GE with PAR

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: RP#1

2 On-site Survey: RP#2

3 Personnel Monitoring:

4 Job Coverage: RP reports to the CR to provide RP support (including in plant and out of plant surveys) as directed by the SM.

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: See Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

RP will perform the above task as directed by the Shift Manager. Tasks are not time critical. The time* to perform the tasks and the time to complete the tasks are estimated.

Chemistry does not have an assigned chemistry task for LOCA. Chemistry is available for dose assessment.

Page 205: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 82

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis #11 – LOCA/GE with PAR

Line #

Function / Task* On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL)

Shift Manager Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

Shift Manager Emergency Planning Training Program

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose Shift Manager Emergency Planning Training Program

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift ManagerN/A Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A Licensed Operator Training Program

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form Shift ManagerN/A Licensed Operator Training ProgramN/A

11 Activate ERDS N/A N/AEmergency Planning Training Program

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/AShift Manager N/ALicensed Operator Training Program

15 Personnel Accountability Security Security Training Program

Page 206: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 83

L. Accident Analysis #15 – Steam Generator Tube Rupture with Concurrent Loss of Off-site Power

1. Accident Summary

This event analyzes the response of a failure of a steam generator U-tube combined with a loss of offsite power.

2. Accident Specific Assumptions Made

Radiation monitor alarms on the MSLs, condenser air ejector discharge, SG blowdown line, fan room and plant stack before the reactor trip/turbine trip.

Following a reactor trip and turbine trip, the radioactive fluid is released through the steam generator safety or atmospheric dump valves as a result of the loss of normal AC power.

Doses are calculated for an event generated iodine spike, initial activity of 1 µCI/gm and a spiking factor of 335 (GIS) and a pre-accident iodine spike 40 µCI/gm (PIS).

Primary to secondary leakage rate of 432 gallons per day is assumed in the unaffected steam generator for the duration of the transient.

3. Procedures for Accident Response EOP-5.0 Rev. 1517, Steam Generator Tube Rupture Recovery EOP-1.0 Rev. 1315, Standard Post Trip Actions EI-1 Rev. 5456, Emergency Classification and Actions EI-3 Rev. 31, Communications and Notifications EI-2.2 Rev. 15, Emergency Staff Augmentation EI-12.1 Rev. 18, Personnel Accountability and Assembly ADMIN-4 Rev. 52, Operations Organization, Responsibilities and Conduct ONPAOP-23.224 Rev. 014, SGT leak

Page 207: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 84

4. Tables PALISADES TABLE 1 – ON-SHIFT POSITIONS Analysis #15 – Steam Generator Tube Rupture

Line # On-shift Position Basis

Document Augmentation Elapsed Time

(min)

Role in Table 5 / Line #

Unanalyzed Task?

TMS Required?

1 Shift Manager Emergency Plan Figure 5-2 60

T2/L1 T5/L1 T5/L3 T5/L5 T5/L6 T5/L8 T5/L10 T5/L11 T5/L14

No Yes

2 Control Room Supervisor

Emergency Plan Figure 5-2 N/A T2/L2 No No

3 Shift Technical Advisor

Emergency Plan Figure 5-2 60 T2/L3

No No

4 Nuclear Control Operator #1

Emergency Plan Figure 5-2 N/A T2/L4 No No

5 Nuclear Control Operator #2

Emergency Plan Figure 5-2 N/A T2/L5 No No

6 Nuclear Plant Operator #1

Emergency Plan Figure 5-2 N/A T2/L6 No No

7 Nuclear Plant Operator #2

Emergency Plan Figure 5-2 N/A N/A No No

8 Nuclear Plant Operator #3

Emergency Plan Figure 5-2

N/A N/A No No

9 Nuclear Plant Operator #4

Emergency Plan Figure 5-2

N/A N/A No No

10 Nuclear Plant Operator #5

Emergency Plan Figure 5-2

N/A

N/A

No No

11 Nuclear Plant Operator #6

Emergency Plan Figure 5-2

N/A N/A No No

12 Communicator Emergency Plan Figure 5-2

30 T5/L9 T5/L13 No No

13 Chem Tech Emergency Plan Figure 5-2 60 T5/L12 No Yes

14 RP#1 Emergency Plan Figure 5-2 30 T4/L4 No No

15 Security

Security Contingency Plan / Emergency Plan Figure 5-2

N/A T5/L15 No No

Page 208: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 85

PALISADES TABLE 2 – PLANT OPERATIONS & SAFE SHUTDOWN One Unit – One Control Room

Analysis #15 – Steam Generator Tube Rupture Minimum Operations Crew Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

1 Shift Manager Shift Manager Licensed Operator

Training Program

2 Unit Supervisor CRS Licensed Operator

Training Program

3 Shift Technical Advisor STA Licensed Operator

Training Program

4 Reactor Operator #1 Nuclear Control Operator

#1 Licensed Operator Training Program

5 Reactor Operator #2 Nuclear Control Operator

#2 Licensed Operator Training Program

6 Auxiliary Operator #1 Nuclear Plant Operator

#1 Non-Licensed Operator Training Program

Other (non-Operations) Personnel Necessary to Implement ONPs and EOPs or SAMGs if Applicable

Line # Generic Title/Role On-Shift Position Task Analysis Controlling Method

7 Mechanic N/A N/A

8 Electrician N/A N/A

9 I&C Technician N/A N/A

10 Other N/A N/A

11 Other N/A N/A

Page 209: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 86

Fire Brigade

PALISADES TABLE 3 – FIREFIGHTING Analysis #15 – Steam Generator Tube Rupture Line

# Performed by Task Analysis Controlling Method

1 N/A N/A

2 N/A N/A

3 N/A N/A

4 N/A N/A

5 N/A N/A

This accident does not include the need for firefighting, first aid or search & rescue.

Page 210: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 87

PALISADES TABLE 4 – RADIATION PROTECTION AND CHEMISTRY Analysis #15 – Steam Generator Tube Rupture

L I N E

Position Performing Function / Task Performance Time Period After Emergency Declaration (minutes)*

0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70

70-75

75-80

80-85 85-90

1 In-Plant Survey: N/A

2 On-site Survey: N/A

3 Personnel Monitoring:

4 Job Coverage: RP performs surveys and job coverage as needed and directed by the SM.

X X X X X X X X X X X X X X X X X

5 Offsite Rad Assessment: See Table 5

6 Other site specific RP (describe): N/A

7 Chemistry Function task #1 (describe) N/A

8 Chemistry Function task #2 (describe) N/A

*Times are estimated

Chemistry does not have an assigned chemistry task and is available for dose assessment.

Page 211: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 88

PALISADES TABLE 5 – EMERGENCY PLAN IMPLEMENTATION Analysis #15 – Steam Generator Tube Rupture

Line #

Function / Task* On-Shift Position Task Analysis Controlling Method

1 Declare the emergency classification level (ECL)

Shift Manager Emergency Planning Training Program / EP Drills

2 Approve Offsite Protective Action Recommendations

N/A Emergency Planning Training Program

3 Approve content of State/local notifications Shift Manager Emergency Planning Training Program

4 Approve extension to allowable dose N/A Emergency Planning Training Program

5 Notification and direction to on-shift staff (e.g., to assemble, evacuate, etc.) Shift Manager

Licensed Operator Training Program / Emergency Planning Training Program

6 ERO notification Shift Manager Emergency Planning Training Program

7 Abbreviated NRC notification for DBT event N/A Licensed Operator Training Program

8 Complete State/local notification form Shift Manager Emergency Planning Training Program

9 Perform State/local notifications Communicator Emergency Planning Training Program

10 Complete NRC event notification form Shift ManagerN/A N/ALicensed Operator Training Program

11 Activate ERDS N/AShift Manager N/AEmergency Planning Training Program

12 Offsite radiological assessment Chemistry Technician Emergency Planning Training Program

13 Perform NRC notifications Communicator Emergency Planning Training Program

14 Perform other site-specific event notifications (e.g., Duty Plant Manager, INPO, ANI, etc.)

N/AShift Manager N/ALicensed Operator Training Program

15 Personnel Accountability Security Security Training Program

Page 212: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 89

VIII. APPENDIX C – TIME MOTION STUDIES SUPPORTING THE STAFFING ANALYSIS A. Dose Assessment

1. See Section II.C.1 for the exception taken for the Chemistry Technician to perform dose assessment. No time motion study or corrective actions is required.

B. ERO notification (Everbridge activation)

PALISADES

TIME MOTION STUDY OF OVERLAPPING TASKS

TASK 1: ACTIVATE THE ERO USING EVERBRIDGE

JOB: SHIFT MANAGER

TASK 2: EMERGENCY DIRECTION AND CONTROL

JOB: SHIFT MANAGER

Page 213: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 90

PURPOSE:

Perform a Time Motion Study to evaluate whether assigning the performance of ERO notification using Everbridge to the Shift Manager or STA can be justified as an acceptable overlap to the Shift Manager’s primary emergency plan function of direction and control.

LOCATION:

Simulator (to use the “TRAINING” event code to avoid inadvertent ERO activation for an EMERGENCY event.) Codes are site specific.

REQUIRED TOOLS/EQUIPMENT:

A. Individual performing the procedure actions must be logged on to the computer being used.

B. PC with Internet 7.0 and internet access.

C. Instructions/codes for activating Everbridge in the TRAINING mode. [Staged Instruction sheet for activating Everbridge may be used in lieu of EN-EP-310, Emergency Response Organization Notification System)]

NOTE

The Time Motion Study may be completed during simulator training/evaluation or during

EP drills

Page 214: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 91

Function / Responsibility (Task) Analysis Template

Event: ALL Site: Palisades Position: Shift Manager Line #: 1

Function Responsibility (Task) Action Step Duration

1.Notification 1.1 Initiate notification to

the ERO via the ERON

Program

Retrieve the Everbridge instruction that contains the [TRAINING] Access code and Pass code.

10 seconds

(On the PC) Open ERO Notification System by clicking:

Start Nuclear Corporate Apps (ESM) Nuclear Emergency Response (ESM) ERON

20 seconds

Enter Access code (XXXXX) and Pass code (XXXXX) and click the SUBMIT button

15 seconds

Select the appropriate classification by clicking on it.

(Select ALERT or scenario ECL)

15 seconds

Answer “Yes” or “No” to Security EAL question, “Was the event declared on a Security EAL?” [ Click on “NO”]

5 seconds

Select proper response action by clicking on it.

[Select “Activate All ERFs”}

10 seconds

Review the message that was generated in the User Message box at the bottom of the screen. Ensure the message contains the information to communicate to the ERO. Additional information can be added to the message by clicking in the User Message box and typing.

20 seconds

Once satisfied with the message content, click send notification button. [Click “Send Notification”]

10 seconds

Answer “YES” to send verification question, “Are you CERTAIN you want to send this message?” [Click “YES”]

5 seconds

If message was successfully sent, you will see a dialog box. [Click “Return”] 10 seconds

END OF INITIATE NOTIFICATION TO ERO TASK 2 minutes

(total time)

2.Emergency

Direction and

Control

2.1 Maintain emergency

direction and control of the

event response.

Oversight of the emergency response. Maintained Throughout

Initiate any emergency actions. Initiated as required

END OF EMERGENCY DIRECTION AND CONTROL TASK

Task Performer: Bruce Bauer Position: Shift Manager Date: 11/05/2012 Name Job Title Evaluator: Dan Malone Position: EP Manager Date: 11/05/2012 Name Job Title

Page 215: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 92

IX. OVERLAP OF TASKS ACTIVITIES OR OTHER CONFLICTS IDENTIFIED

A. Overlap Requiring Compensatory Measures

1. The SM and STA perform off-site notifications for some analyzed events resulting in tasks that are concurrent and conflict with the SM and STAs primary Emergency Plan tasks.

2. The SM is assigned the task of performing radiological assessment. The assignment of radiological assessment to the SM results in concurrent and conflicting tasks with SM Emergency Direction and Control.None

X. CORRECTIVE ACTIONS

A. Corrective Actions and Compensatory Measures

1. Assign an additional on-shift ERO staff member to relieve the SM and/or STA from the concurrent tasks of off-site communication tasks. The additional on-shift ERO staff member will be responsible to perform state/local and NRC off-site notifications.

2. Assign the task of radiological assessment to the on-shift Chemist to relieve the SM and/or STA of concurrent tasks.None

Page 216: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES ON-SHIFT STAFFING ANALYIS REPORT

PALISADES Page 93

XI. REFERENCES

NEI 10-05, Rev 0, Assessment of On-Shift Emergency Response Organization Staffing and Capabilities NSIR DPR-ISG-01, Interim Staff Guidance – Emergency Planning for Nuclear Power Plants NUREG-0654, Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and

Preparedness in Support of Nuclear Power Plants. Palisades Emergency Plan, Rev 2225

XII. STAFFING ANALYIS TEAM

The staffing analysis team consisted of plant and Entergy Corporate staff representing the following departments / organizations: Fleet Emergency Preparedness Project Management Operations Training Security Chemistry Radiation Protection Regulatory Assurance Emergency Planning Engineering

o Fire Protection o Appendix R

Fred Guynn, Entergy ECH Project Manager, EP Myra Jones, Contractor CMCG Todd Mulford, Assistant Operations Manager Kevin Schneider,Training Don Karnes, Senior Operations Training Instructor Steve Andrews, Chemistry Specialist Steve Mims, Radiation Control Supervisor Dan Malone, Emergency Preparedness Manager

Page 217: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ATTACHMENT 5

PROPOSED REVISION TO PALISADES NUCLEAR PLANT SITE EMERGENCY PLAN FIGURE 5-2

3 Pages Follow

Page 218: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Proposed Revision to Palisades Nuclear Plant Site Emergency Plan Figure 5-2

1 of 3

FIGURE 5-2

PLANT STAFFING AND AUGMENTATION REQUIREMENTS

MAJOR FUNCTIONAL AREA MAJOR TASKS POSITION TITLE OR EXPERTISE

ON SHIFT

STAFF AUGMENTATION CAPABILITY AND RESPONSE TIME

60 Min

Plant Operations and Assessment of Operational Aspects

Shift Engineer/Shift Technical Advisor (SRO) Shift Manager (SRO) Control Room Supervisor (SRO) Control Room Operators Nuclear Plant Operators

1 1 1 2 6

--

-- -- -- -- --

Emergency Director Shift Manager 1* --

Notification/ Communication

Notify licensee, state, local, and federal personnel and maintain communication

1 3

Radiological Accident Assessment and Support of Operational Accident Assessment

Emergency Operations Facility (EOF) Director Offsite Dose Assessment

Senior Manager Senior Radiation Protection (RP) Expertise

--

1*

1

1

Offsite Surveys Onsite (Out-of-Plant) In-Plant Surveys

Rad Protection Technicians

-- -- 1

4 2 2

* May be provided by shift personnel assigned other functions.

Page 219: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Proposed Revision to Palisades Nuclear Plant Site Emergency Plan Figure 5-2

2 of 3

FIGURE 5-2 PLANT STAFFING AND AUGMENTATION REQUIREMENTS

MAJOR FUNCTIONAL AREA MAJOR TASKS POSITION TITLE OR EXPERTISE

ON SHIFT

STAFF AUGMENTATION CAPABILITY AND RESPONSE TIME

60 Min

Chemistry/Radiochemistry Chem Technicians 1 1

Plant System Engineering, Repair, and Corrective Actions

Technical Support Core/Thermal Hydraulics Electrical Mechanical

1* -- --

1 1 1

Repair and Corrective Actions

Mechanical Maintenance Radwaste Operator Electrical Maintenance Instrument and Control (I&C) Technician

1* -- 1*

--

1 1 2

1 Protective Actions (In-Plant)

Radiation Protection: a. Access Control b. RP Coverage c. Personnel monitoring d. Dosimetry

RP Technicians 2* 4

Fire Fighting -- -- Fire Brigade per Technical Specifications

Local Support

* May be provided by shift personnel assigned other functions.

Page 220: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Proposed Revision to Palisades Nuclear Plant Site Emergency Plan Figure 5-2

3 of 3

FIGURE 5-2 PLANT STAFFING AND AUGMENTATION REQUIREMENTS

MAJOR FUNCTIONAL AREA MAJOR TASKS POSITION TITLE OR EXPERTISE

ON SHIFT

STAFF AUGMENTATION CAPABILITY AND RESPONSE TIME

60 Min Rescue Operations and First-Aid

-- -- 2* Local Support

Site Access Control and Personnel

Security, fire fighting communications, personnel accountability

Security Personnel All per Security

Plan

TOTAL 14 26 NOTES: 1. Staff augmentation personnel are required to respond as quickly as possible, within the required response time. 2. The Shift Manager may call out designated ERO members or the full ERO complement at any time in an

emergency event regardless of classification. 3. Even when they are not on duty, staff augmentation personnel are to respond to an emergency call out when they

are fit for duty and otherwise available for timely response. 4. The on-shift staffing requirements listed in this figure are a result of the Palisades Nuclear Plant On-shift Staffing

Analysis Report, Revision 1, dated February 10, 2014, conducted in accordance with NEI 10-05 and required by 10CFR50 Appendix E, Section IV.A.9.

* May be provided by shift personnel assigned other functions.

Page 221: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ATTACHMENT 6

PROPOSED REVISION TO PALISADES NUCLEAR PLANT

SITE EMERGENCY PLAN SECTION 5.4

1 Page Follows

Page 222: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES NUCLEAR PLANT SEP SITE EMERGENCY PLAN Revision xx Page 38 of 101 TITLE: SITE EMERGENCY PLAN

5.3.5 Joint Information Center (JIC) The plant Communications personnel shall be responsible for maintenance of the

Palisades Nuclear Plant Public Information Policies and Procedures. These provide for disseminating information to the public via the media and establishing a system for rumor control during an emergency. Public Affairs personnel shall coordinate the activation and management of the Joint Information Center (JIC) in cooperation with the Corporate Public Affairs Department. He shall prepare and issue press releases in cooperation with state and local agencies. Reference Palisades Nuclear Plant Emergency Public Information Policies and Procedures for details.

5.4 EMERGENCY STAFFING Normal Plant staffing provides sufficient personnel for continuous protracted

emergency operation. The extent to which the emergency organization is activated is dependent upon the classification of the emergency. A method for emergency staff augmentation is available to the Shift Manager. Figure 5-2 provides requirements for minimum additional staffing and arrival times. Details of emergency staff augmentation are available in Emergency Implementing Procedure EI-2.2, "Emergency Staff Augmentation."

5.4.1 Shift Manager/EOF Emergency Director The Shift Manager/EOF Emergency Director is responsible for the overall

assessment of emergency conditions, especially where emergency conditions present a real or potential hazard to off-site persons or property. The Shift Manager/EOF Emergency Director will have the overall responsibility for operational decisions involving the safety of the Plant and its personnel, and for making recommendations based on technical information supplied by support personnel regarding the general public during an emergency situation. He will also implement the Palisades Site Emergency Plan through the use of specific Emergency Plan Implementing Procedures. The Shift Manager/EOF Emergency Director is responsible for ensuring the capability for continuous operation of emergency response centers, including personnel and material resources. In addition, the Shift Manager/EOF Emergency Director is responsible for providing off-site officials with pertinent information regarding the conditions at the Plant.

Page 223: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

ATTACHMENT 7

PROPOSED REVISION TO PALISADES NUCLEAR PLANT

SITE EMERGENCY PLAN SECTION 5.4

(marked up version)

1 Page Follows

Page 224: Anthony J. Vitale · Anthony J. Vitale Site Vice President PNP 2014-003 February 13, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

PALISADES NUCLEAR PLANT SEP SITE EMERGENCY PLAN Revision xx Page 38 of 101 TITLE: SITE EMERGENCY PLAN

5.3.5 Joint Information Center (JIC) The plant Communications personnel shall be responsible for maintenance of the

Palisades Nuclear Plant Public Information Policies and Procedures. These provide for disseminating information to the public via the media and establishing a system for rumor control during an emergency. Public Affairs personnel shall coordinate the activation and management of the Joint Information Center (JIC) in cooperation with the Corporate Public Affairs Department. He shall prepare and issue press releases in cooperation with state and local agencies. Reference Palisades Nuclear Plant Emergency Public Information Policies and Procedures for details.

5.4 EMERGENCY STAFFING Normal Plant staffing provides sufficient personnel for continuous protracted

emergency operation. The extent to which the emergency organization is activated is dependent upon the classification of the emergency. A method for emergency staff augmentation is available to the Shift Manager. Figure 5-2 provides a guideline requirements for minimum additional staffing and approximate arrival times. Details of emergency staff augmentation are available in Emergency Implementing Procedure EI-2.2, "Emergency Staff Augmentation."

5.4.1 Shift Manager/EOF Emergency Director The Shift Manager/EOF Emergency Director is responsible for the overall

assessment of emergency conditions, especially where emergency conditions present a real or potential hazard to off-site persons or property. The Shift Manager/EOF Emergency Director will have the overall responsibility for operational decisions involving the safety of the Plant and its personnel, and for making recommendations based on technical information supplied by support personnel regarding the general public during an emergency situation. He will also implement the Palisades Site Emergency Plan through the use of specific Emergency Plan Implementing Procedures. The Shift Manager/EOF Emergency Director is responsible for ensuring the capability for continuous operation of emergency response centers, including personnel and material resources. In addition, the Shift Manager/EOF Emergency Director is responsible for providing off-site officials with pertinent information regarding the conditions at the Plant.