ROUGH COST ESTIMATE FOR CONSTRUCTION OF DORMITORY FOR BOYS & GIRLS AT FIRST FLOOR IN BAL NIKETAN SECTOR 15-C CHANDIGARH. QTYS.NO.DESCRIPTION OF ITEMS UNITRATEDSRAMOUNT

1.Construction of dormitory for boys & girls consisting brick walls, RCC beams & roof pressed steel chowkhats, wooden doors and windows shutter, kota stone flooring, wall tiles in toilets up to 6-9 High complete as per C. A. drg. No 26 Job no 2094.

1000.44 sqmi)Double storey/SqmRs. (11700+520)2.2.2/5+2.62Rs. 1,22,25377.00

Add 5% contingency charges Rs. 6,11,269.00

Total Rs. 1,28,36646.00

2.Provision for Public Health Services @ 15% i.e on Rs. 1,22,25,377.00 (DSR 3.1)Rs. 18,33,807.00

3.Provision for Electrical Installation @ 12.5% i.e on Rs. 1,22,25,377.00Rs. 15,28,172.00

TotqlRs. 16198625.00

Say Rs. 1,61,98,600/-Certified that the rates taken in the estimate are reasonable andEconomical and also the design of the scheme as covered in the Scope of the work is technically in order and also economical andHence estimate recommended for approval.Executive EngineerC.P. Division No. 3, Chd