analysis of the production system at abb combustion

67
Analysis of the Production System at ABB Combustion Engineering Newington Operations by Rhonda L. Patton B.S., Mechanical Engineering (1999) Massachusetts Institute of Technology Submitted to the Department of Mechanical Engineering in Partial Fulfillment of the Requirements for the Degree of Master of Science in Mechanical Engineering at the Massachusetts Institute of Technology June 2000 0 2000 Rhonda L. Patton All rights reserved The author hereby grants to MIT permission to reproduce and to distribute publicly paper and electronic copies of this thesis document in whole or in part. Signature of A uthor............................................... Department of Mechanical Engineering May 5> 2000 C ertified by ........................................................ David S. Cochran Assistant Professor of Mechanical Engineering A ccepted by ......................................................... Am A. )omn Chairman, Committee on Graduate Students MASSACHUSETTS INSTITUTE OF TECHNOLOGY SEP 2 0 2000 LIBRARIES

Upload: others

Post on 25-Apr-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Analysis of the Production System at ABB Combustion

Analysis of the Production System atABB Combustion Engineering Newington Operations

by

Rhonda L. Patton

B.S., Mechanical Engineering (1999)

Massachusetts Institute of Technology

Submitted to the Department of Mechanical Engineeringin Partial Fulfillment of the Requirements for the Degree of

Master of Science in Mechanical Engineering

at the

Massachusetts Institute of Technology

June 2000

0 2000 Rhonda L. PattonAll rights reserved

The author hereby grants to MIT permission to reproduce and todistribute publicly paper and electronic copies of this thesis document in whole or in part.

Signature of A uthor...............................................Department of Mechanical Engineering

May 5> 2000

C ertified by ........................................................David S. Cochran

Assistant Professor of Mechanical Engineering

A ccepted by .........................................................Am A. )omn

Chairman, Committee on Graduate StudentsMASSACHUSETTS INSTITUTE

OF TECHNOLOGY

SEP 2 0 2000

LIBRARIES

Page 2: Analysis of the Production System at ABB Combustion
Page 3: Analysis of the Production System at ABB Combustion

Analysis of the Production System atABB Combustion Engineering Newington Operations

by

Rhonda L. Patton

Submitted to the Department of Mechanical Engineeringon May 5, 2000 in partial fulfillment of the

requirements for the Degree of Master of Science inMechanical Engineering

ABSTRACT

ABB Combustion Engineering Nuclear Power Newington Operations is a manufacturerof industrial and nuclear equipment located in Newington, New Hampshire. This thesisexamines the current production system at ABB and applies the Manufacturing System DesignDecomposition, developed by Professor David Cochran, Professor Paulo Lima, and the studentsof the Production System Design Laboratory at MIT, to begin planning the transition to a leanmanufacturing system for the production of spent fuel dry storage canisters. Lean manufacturingis based on the philosophies of the Toyota Production System, developed by Taiichi Ohno. Just-in-time and autonomation are the two main pillars of TPS. The ultimate goal of TPS is toeliminate all waste in the system, which is accomplished by setting up cells, which reduce traveldistance, producing exactly the amount needed when needed, which minimizes inventory andprevents overproduction, and eliminates all non-value adding activities.

The main obstacles that ABB must deal with in transitioning to a lean manufacturingsystem are resistance to change, the challenge of combining a cellular manufacturing systemwith a project shop manufacturing system, and working with the quality regulations set forth inthe ASME Boiler and Pressure Vessel Code. ABB Newington has been producing industrial andnuclear equipment for over 40 years now. Many of the employees at ABB have been workingthere for a significant length of time. For these reasons, changing the philosophy of productionis going to be difficult. Some of the components of the spent fuel canisters are extremely largeand can't be moved easily. As a result, the production system at ABB will have to combinetypical cellular manufacturing methods with project shop methods, where some of thecomponents remain stationary and other parts come to them. Lastly, ABB must deal with thefact that the ASME Code prohibits inspection of parts by anyone that performed or directlysupervised the work being inspected. Thus, self inspection as part of the cell work loop isimpossible. ABB must be creative in dealing with this challenge and try to find ways tocompromise between the stipulated inspection requirements and the ideals of TPS.

Thesis Supervisor: David S. Cochran

Title: Assistant Professor of Mechanical Engineering

3

Page 4: Analysis of the Production System at ABB Combustion

4

Page 5: Analysis of the Production System at ABB Combustion

TABLE OF CONTENTS

TABLE OF CONTENTS .............................................................................. 5L IST O FIG U R E S ...................................................................................... 6LIST O F T A B LE S ...................................................................................... 6ACKNOWLEDGEMENTS ............................................................................ 71.0 Introduction and General Background Information................................................9

1.1 ABB Combustion Engineering Nuclear Power Newington Operation.............. 91.2 Spent Fuel Dry Storage Canister Production.......................................... 101.3 O u tlin e ........................................................................................ 1 1

2.0 "Lean" Manufacturing.............................................................................. 122.1 Toyota Production System............................................................... 122.2 Manufacturing System Design Decomposition.......................................... 14

2.2.1 A xiom atic D esign............................................................................... 142.2.2 Manufacturing System Design Decomposition.............................................15

2 .3 In spection ................................................................................... 162.3.1 Statistical Process Control and Acceptable Quality Levels.................................172.3.2 Judgem ent Inspection...............................................................................222.3.3 Inform ative Inspection....................................................................... . 22

3.0 Existing Conditions and Project Goals........................................................... 243.1 C urrent Plant L ayout........................................................................243.2 Flow of Parts and Information.............................................................263.3 Scrap, Non-conformances, and Corrective Action...................................283 .4 Inspection ................................................................................... 293.5 W orker A ctivities......................................................................... 303 .6 S chedulin g .................................................................................... 323.7 Project G oals.............................................................................. 33

4.0 MSD Decomposition Applied to ABB Newington.............................................. 344.1 Top Three Levels of PSD Decomposition............................................... 344 .2 Q u ality ........................................................................................ 374.3 Identifying and Resolving Problems.................................................... 404.4 Predictable Output.......................................................................424.5 D elay R eduction........................................................................... 45

4 .5 .1 T ak t T im e ............................................................................................ 4 74.5.2 F loor L ayout................................................................................... . .. 494.5.3 Sam ple M achining C ell........................................................................ 514 .5 .4 In spection ....................................................................................... . . 55

4 .6 D irect L ab or................................................................................. 574 .7 Indirect L abor................................................................................59

5.0 Concluding Comments............................................................................. 605.1 S um m ary .................................................................................... 605 .2 O b stacles.................................................................................... 605.3 T he N ext Steps.............................................................................. 6 15.4 F inal C om m ent.............................................................................. 63

R E FE R E N C E S .......................................................................................... 65A P P E N D IX A ............................................................................................. 66

5

Page 6: Analysis of the Production System at ABB Combustion

Figure 2-1:Figure 2-2:Figure 2-3:Figure 2-4:Figure 2-5:Figure 3-1:Figure 3-2:Figure 3-3:Figure 3-4:Figure 3-5:

Figure 3-6:

Type I and Type II errors of the Decision Making process............................Sample travel distances of selected parts.................................................Part demand in sample machining cell...................................................Cycles times of each part at each machine in the sample cell.........................Improvements resulting from formation of sample machining cell..................

2028525354

6

LIST OF FIGURES

O verall layout of the M SD D .............................................................. 16Normal distribution curve with p = 0, a& = 1......................................... 18Graphical representation of (x-error.................................................... 19Graphical representation of B-error.................................................... 20Confidence intervals of a standard normal distribution............................... 21Current layout of the Light Manufacturing Building................................. 25Current layout of the Heavy Manufacturing Building............................... 25Histogram of inspection times........................................................... 30Pareto chart of worker activities during a random 2-hour time slot...............31Percentage of total worker hours spent on each operation/activity during

a random 2-hour tim e slot............................................................. 31Pie chart of value adding, non-value adding but necessary, and waste

during a random 2-hour time slot...................................................... 32Levels I, II, and III of the MSDD.........................................................35"Quality" branch of the MSDD......................................................... 38"Identifying and Resolving Problems" branch of the MSDD....................... 41"Predictable Output" branch of the MSDD........................................... 43"Delay Reduction" branch of the MSDD............................................. 46Typical cellular manufacturing layout of the ship building industry................ 49Possible linked-cell layout for production of canisters at ABB..................... 50Machine-part matrix used to establish part families.................................. 52Possible layout for the sample machining cell........................................ 54

"Direct Labor" branch of the MSDD................................................ 57"Indirect Labor" branch of the MSDD................................................. 59

FigureFigureFigureFigureFigureFigureFigureFigureFigureFigureFigure

4-1:4-2:4-3:4-4:4-5:4-6:4-7:4-8:4-9:4-10:4-11:

LIST OF TABLES

TableTableTableTableTable

2-1:3-1:4-1:4-2:4-3:

Page 7: Analysis of the Production System at ABB Combustion

ACKNOWLEDGEMENTS

I would like to thank Professor David Cochran for providing guidance and inspiration forthis thesis. I would also like to thank everyone at ABB Combustion Engineering in Newington,New Hampshire for their constant support and assistance. I certainly couldn't have done thisthesis without their help.

'7

Page 8: Analysis of the Production System at ABB Combustion

8

Page 9: Analysis of the Production System at ABB Combustion

1.0 INTRODUCTION AND GENERAL BACKGROUND INFORMATION

This thesis presents a methodology that can be used as a guideline in the transformation

of a traditional job shop plant to a lean manufacturing plant in the nuclear industry and is based

on studies done during an internship at ABB Combustion Engineering Nuclear Power (ABB-

CENP), Newington Operations (Newington) in Newington, New Hampshire. The internship

project was primarily a "feasibility study" to examine the major roadblocks that ABB would

have to confront in developing a lean manufacturing system and devise a plan to deal with these

major issues. While the details of the system pertain particularly to ABB-CENP Newington

Operations, the general philosophies and methodologies can be applied to many other

manufacturing plants, particularly those in the nuclear industry or other highly regulated

industries.

In particular, the issue of quality control and quality assurance is largely addressed in this

thesis. The requirements for quality inspection imposed upon ABB (and the nuclear industry, in

general) by the U.S. government are in direct conflict with the main principles of cellular

manufacturing. The work done in this thesis examines that conflict and addresses possible

compromise.

1.1 ABB Combustion Engineering Nuclear Power Newington Operations

ABB-CENP Newington Operations is a manufacturer of industrial and nuclear

equipment. For more than 40 years, Newington has been manufacturing high precision stainless

steel and high alloy components for the nuclear energy industry. Newington manufactures the

reactor vessel internals (RVIs), which provide a support structure for the core and provide a flow

path within the reactor vessel; the control element drive mechanisms (CEDMs), which are

9

Page 10: Analysis of the Production System at ABB Combustion

electromechanical devices that insert and withdraw the control element assembly; and the reactor

coolant pumps (RCPs), four pumps that circulate water through the reactor coolant system, each

with a rated flow from 85,000 to 120,000 gallons per minutes at 8,000 to 12,000 horsepower.

Newington Operations is part of Nuclear Systems, a division of ABB Combustion

Engineering Nuclear Power, Inc.. Newington Operations employs 144 employees, 95 of which

are hourly employees.

The facilities in Newington consist of two large manufacturing warehouses, one known

as the "light manufacturing" building and the other known as the "heavy manufacturing"

building. The light manufacturing building runs two shifts, while the heavy manufacturing

building runs three shifts. There is also a building that houses quality assurance, including all

retained quality assurance records, and another building that houses design engineering, human

resources, production control, and purchasing.

1.2 Spent Fuel Dry Storage Canister Production

In December of 1998, ABB-CENP Nuclear Systems won a contract to build spent fuel

dry storage canisters. This contract is the first of many contracts that ABB expects to win over

the next few years.

Newington Operations is simply the fabricator of these canisters. External firms did the

design. There are three basic designs to the canisters that ABB may build over the next few

years, that are all similar in basic structure but vary in the amount of machining, welding, and

assembling involved.

During this internship period, production of the first canister contract was underway.

However, a major design problem was discovered partway through the internship period and

10

Page 11: Analysis of the Production System at ABB Combustion

production of the canisters was halted. ABB then began assisting in an R&D effort to correct the

problem. The projected restart is 2002, which is when rework on the partially constructed

canisters will be done, as well as complete production of additional canisters for the contract.

Fabrication of a second type of canister has already started at ABB, though no finished

products are scheduled to ship until July 2000.

Thus, this thesis focuses on the general state of the production system in Newington with

examples taken from canister production.

1.3 Outline

Chapter 2 gives a brief description of the Toyota Production System (TPS) and the

Manufacturing System Design Decomposition (MSDD), which are used to analyze the

production system at ABB and suggest improvements to the system. This chapter also details the

inspection philosophies of mass production and TPS.

The current state of the production system at ABB-CE Newington Operations is

described in Chapter 3. The goals of this project are also laid out.

Chapter 4 is the heart of this thesis. The MSDD is used as a tool to analyze the

production system at ABB and determine feasible ways to improve the system. Certain sections

of the MSDD are emphasized over others due to their pertinence to ABB's production system.

Finally, in Chapter 5, comments are made regarding inspection at ABB and the

regulations infringed upon the industry. Chapter 5 also includes a summary of the analysis

presented in this thesis and recommends the next steps for ABB to take.

11

Page 12: Analysis of the Production System at ABB Combustion

2.0 "LEAN" MANUFACTURING

This chapter provides a brief history and overview of the Toyota Production System, as

well as describes the Production System Design Decomposition Framework that was used to

analyze the current production system at ABB. Finally, a detailed look at the inspection

procedures and philosophies of mass versus "lean" production is presented.

2.1 Toyota Production System

Lean manufacturing, the Toyota Production System (TPS), and Just-in-Time

manufacturing are all synonyms for the production system developed by Taiichi Ohno.

Following World War II, when Japan was in a state of rebuilding and resources were scarce, the

President of the Toyota Motor Company, Kiichiro Toyoda, said, "Catch up with America in

three years. Otherwise, the automobile industry of Japan will not survive" [Ohno, 1988]. Ohno,

who worked for Toyota, looked at the mass production systems in existence in America at the

time to try to find ways to keep his company in business. Ohno had once been told that the work

force ratio between Japan and America was 1-to-9 [Ohno, 1988]. How could this be? Ohno

knew that there was no way that American workers could actually exerted ten times more

physical effort than Japanese workers. This was when he realized that there was simply too

much waste in the Japanese system that was getting in the way of productivity.

In Japan, demand for automobiles was not as high as in America and Toyota did not have

as many resources as the American companies. As a result, Ohno created a system based on two

pillars: just-in-time and autonomation (automation with a human touch). Just-in-time refers to

the method of making only what is needed, when it is needed. This meant that Toyota could

keep a minimal amount of inventory and work-in-process (WIP), which would reduce their costs.

12

Page 13: Analysis of the Production System at ABB Combustion

Autonomation is the use of machines "with a human touch" [Ohno, 1988]. That is, machines

that can detect defects autonomously. When a defect is detected, the machine stops and cannot

continue until the source of the problem is corrected.

The ultimate goal of TPS is to reduce the amount of time between when the customer's

order is taken and when the company receives the cash for the product. This time reduction is

accomplished by eliminating waste. The seven wastes as defined by TPS include [Ohno, 1988]:

" waste of overproduction" waste of time on hand (waiting on machines)" waste in transportation" waste of processing itself" waste of stock on hand (inventory)* waste of movement" waste of making defective products

Elimination of these wastes can improve system efficiency and reduce costs.

The main working unit of TPS is the cell. In mass production systems, all machines of

the same type are in one department, which requires parts to criss-cross through the shop from

one operation to another. Ohno realized that if he set up a sequence of machines in the proper

order of operations, the parts could quickly travel, one part at a time (referred to as single-piece

flow), through the U-shaped or L-shaped cell, drastically reducing the distance that the parts had

to travel. This layout also allowed workers to operate multiple machines at once. The worker

could set-up a part in a particular machine, hit a switch to make the machine begin, and while

that machine was running, move onto the next machine in the cell continuing in a similar

manner. By creating these "work loops," production efficiency drastically improved over the

"one operator, one process" methods of mass production.

To keep inventory levels low and assure smooth flow of parts through the cells, balanced

production and leveled production were implemented. In balanced production, all operations or

13

Page 14: Analysis of the Production System at ABB Combustion

cells produce at the same cycle time, which is less than or equal to the takt time [Cochran, 1999,

2.82/2.812 class notes]. Takt time is the pace at which parts should be produced to meet

customer demand, and is defined as the available time per shift divided by the average demand

per shift. Leveled production means that all operations make the quantity and mix of products

demanded by the final customer within a given time interval [Cochran, 1999, 2.82/2.812 class

notes]. Thus, instead of producing long runs of the same type of parts, a variety of parts are

produced in smaller runs. To achieve this objective, however, changeover times had to be

drastically reduced, which was accomplished through single-minute exchange of dies (SMED)

[Shingo, 1989]. Takt time and leveling of production should be recalculated and adjusted on a

regular basis. This could be weekly, monthly, or annually, depending on the rate of change of

customer demand.

The method used to enforce just-in-time is called kanban, which is the Japanese word for

"card." A kanban is typically a small card in a protective envelope that contains information

about pickup, transfer, and production [Ohno, 1988]. The use of kanban prevents

overproduction or production of the wrong parts.

The bottom line of Ohno's system is constant improvement. In taking a look around the

plant, small increments of progress can always be made to help get the product to the customer

faster and reduce waste. The Japanese word used to describe this philosophy is "kaizen."

2.2 Manufacturing System Design Decomposition

2.2.1 Axiomatic Design

Axiomatic Design provides a means to translate customer needs into specific design

implementations through mapping the Functional Requirements (FRs) and Design Parameters

14

Page 15: Analysis of the Production System at ABB Combustion

(DPs) [Suh, 1990]. The FRs, in the functional domain, are determined directly from the needs of

the customer and detail specific requirements that the design must accomplish. The DPs are in

the physical domain, and specify the physical implementations set forth by the FRs. Put simply,

the FRs state what to accomplish and the DPs state how to accomplish it.

A top-level functional requirement is established, with its corresponding design

parameter. More functional requirements are derived from the top level DP, which each have

their appropriate DPs. This breakdown continues until the bottom level DPs are feasible,

implementable solutions to the desired goals. The mapping of FRs and DPs must follow two

design axioms [Suh, 1990]:

Axiomi: The Independence AxiomMaintain the independence of functional requirements (FRs).

Axiom 2: The Information AxiomMinimize the information content.

2.2.2 Manufacturing System Design Decomposition

Professor David Cochran, Professor Paulo Lima, and the students of the Production

System Design Laboratory at MIT have developed a Design Decomposition, using the method of

axiomatic design, for a production system. The Manufacturing System Design Decomposition

(MSDD) can be used to closely examine "lean" production systems. A better understanding of

what needs to be achieved in order to attain a "lean" production system and how to achieve it can

be achieved by "zig-zagging" along the path mapped out by the FRs and DPs of the

Decomposition.

15

Page 16: Analysis of the Production System at ABB Combustion

The overall layout of the MSDD is shown in Figure 2-1. The MSD Decomposition can

be divided into six sections: (1) Quality, (2) Identifying and Resolving Problems, (3) Predictable

Output, (4) Delay Reduction, (5) Direct Labor, and (6) Indirect Labor. The sections are detailed

in Chapter 4.

IndirectLabor

Direct. . . . . .. ....... L abor

Quality Identifying and Predictable DelayResolving Output Reduction

Problems

Figure 2-1: Overall layout of the MSD Decompositionwith the six branches labeled.

2.3 Inspection

Because this thesis emphasizes the problems with inspection found at ABB and in the

nuclear industry, in general, we must first examine the differences between inspection methods

at mass production plants and job shops versus the inspection methods in the Toyota Production

System.

16

Page 17: Analysis of the Production System at ABB Combustion

2.3.1 Statistical Process Control (SPC) and Acceptable Quality Levels (AQL)

In the 1920s, at Bell Telephone Laboratories, statistical process control (SPC) began

[DeVor et al., 1992]. SPC uses statistics and probability concepts to draw conclusions about a

population after examining a small amount of data. These conclusions, however, cannot be

stated with absolute certainty. The introduction of uncertainty into the picture causes some

problems. Typically, sample inspection involves two particular monitoring tools, acceptance

sampling and/or control charts.

Sampling is done when it is either too costly, too difficult, or impossible to inspect all the

parts. For example, the cost associated with the time needed to inspect every part may be too

much, inspection of the parts may be destructive, or not all of the parts may yet to have been

produced.

In acceptance sampling, a maximum amount of defective parts is allowed to be produced

for the lot to be considered satisfactory. This "acceptable quality level" (AQL) means that some

defects are accepted in each lot sampled. In today's competitive world of high-quality, no

defects are acceptable.

Control charts are used to track the mean and variability of a process. Key characteristics

of the parts produced are, again, sampled, and their mean value is plotted on an X-average chart,

while their range or variability is plotted on an R chart or cy chart, respectively. These charts are

known as Shewhart Control Charts, named after their founder, W.A. Shewhart, who worked at

Bell Labs in the 1920's. Upper and lower control limits are set on each chart and the

characteristics of each sample are plotted. The plot is examined for trends or "out-of-control"

data points, which are then evaluated for their probable cause. The theory behind control charts

is that there are two types of causes of variation. "Chance" causes are natural causes that are

17

Page 18: Analysis of the Production System at ABB Combustion

inherent in the process. They are extremely difficult to isolate, and, frankly, are usually too

small to really care about. Chance causes result from inherent variability in, for example,

material properties and measurement error. Control charts are mainly used to detect the presence

of "assignable" causes. Assignable causes are events that alter the accuracy and/or precision of

the process. Examples of assignable causes are environmental changes (temperature fluctuations

in the factory), tool wear, noise resulting from excessive machine vibrations, and intentional

adjustments to the machine's settings. When assignable causes are detected, they must be

evaluated and fixed to bring the process under control.

Shewhart developed this method of charting the mean and variability of key

characteristics of processes based on the fact that natural sample statistics will be "normally

distributed" about its mean value. Figure 2-2 shows a normal distribution with the mean value at

zero. The width of the curve is determined by the variability, c2. This figure also shows how the

normal distribution curve, when still centered at a mean value of zero, "narrows" when

022 < 7 . The upper and lower control limits, in this case, set at +/-2o, are shown on the chart.

LCL 22 UCL

2

-4y -3c -27 -ic7 0 icy 2cy 3(y 4a

x

Figure 2-2: Normal distribution curve with p=O, 02=1.

18

Page 19: Analysis of the Production System at ABB Combustion

The region under the curve and outside the control limits is called the x-error, also

known as a Type I error. A Type I error is defined as "viewing a process as bad, when it is

actually not making defects." cx is known as the "significance of the test." See Figure 2-3.

LCL UCL

W 2 aY2

-4a -3a -2a -la 0 la 2a 3a 4cy

x

Figure 2-3: The area under the normal curve andoutside of the control limits is the x-error.

The opposite kind of error that can be made is to "view a process as good, when it is actually

making defects." This is known as a Type II error or P-error. The value (1-$) is known as the

"power of the test." The value of P is determined from the area under the curve that is inside the

original control limits when a shift in the mean value of the process has occurred. Figure 2-4

depicts the value of P for a process whose mean value has shifted over +3a.

In a manufacturing setting, either ct-error or 1-error can be minimized, but not both.

Minimizing one type of error compromises the other. Table 2-1 illustrates the decision-making

(DM) process that results from control charts and Type I and Type II errors [Black, 1991].

19

Page 20: Analysis of the Production System at ABB Combustion

L 0

-4a -3cy -2a -la 0x

la 2a 3a 4a

Figure 2-4: The value of P is equal to the area under the curveof the shifted curve that is within the original control limits.

The sample suggested to the DM that:

The process has notchanged.

The process has changed.

The truth was that the DM takes no actions as DM takes action, but nothingprocess had not changed. nothing is wrong. can be found to be wrong with

the process; Type I error, DMembarrassed.

DM takes no action, butprocess making more defects;

Type II error.

DM takes action, findsproblem with process. DM

looks good!

Table 2-1: Two types of errors can be made during the "Decision Making"process, Type I and Type II errors.

This type of inspection is known as "judgement inspection." Improving judgement

inspection increases the chances of detecting defects (minimizing a-error), but does not actually

reduce the number of defects produced.

20

The truth was that theprocess had changed.

L EnewLC

Page 21: Analysis of the Production System at ABB Combustion

To illustrate Type I and Type II errors numerically, consider a standard normal

distribution curve with control limits set at +/-3G from the mean value, which is a typical

acceptance range. 99.7% of the measured values will fall inside this acceptance range. (See

Figure 2-5.) Thus, the u-error, the probability that a part will be marked defective when it is

actually a good part, is 0.3%. In other words, there is a 3/1000 chance that the inspector will

think that the process is bad, when it has not changed at all.

LCL UCL

-4cy Ry 2y I CT 0 G ( Cr 4cy

95.4% P

99.7%

Figure 2-5: Confidence intervals of a standard normal distribution.

Now suppose that the mean value shifts over one standard deviation. Instead of the mean

value of the process being at zero, the mean value of the process is now at +1. For this shifted

standard normal distribution, the area under the shifted curve but still inside the control limits is

$ = 97.7%. There is a 97.7% chance that the part will be detected as good, when in reality, the

process has shifted. Due to the fact that sample inspection is being used, instead of 100%

inspection, this failure to detect the mean shift allows defective parts to be passed on to the

customer (internal or external).

21

Page 22: Analysis of the Production System at ABB Combustion

2.3.2 Judgement Inspection

At many companies, inspection is simply defect detection. Improving judgement

inspection increases the chances of finding defective parts, but does not actually decrease the

number of defective parts.

2.3.3 Informative Inspection

TPS used "informative inspection" methods to detect defects immediately after they are

made, or, better yet, to detect defects at their source, before the defects are actually made.

Preventative inspection reduces the amount of waste (defects) produced, which reduces overall

costs. While production is often stopped (money lost) while the problem that caused the defect

is being corrected, the cost associated with this production loss is less than the cost that would

have incurred due to the production of defective parts (cost of scrap or rework). There are three

basic types of informative inspection: self inspection and successive inspection, enhance self

inspection, and source inspection. All three methods are used in TPS.

In self inspection, each worker inspects his/her own work. A few problems can arise with

this type of inspection, though. If the worker misunderstood the work orders, he/she may

unintentionally pass along parts that should have been rejected. Another drawback is that the

worker may compromise judgement and knowingly accept parts that are actually defective. To

keep inspection within the cell but avoid these problems, the worker can pass along his/her parts

to the next worker who inspects them. Successive inspection provides the immediate feedback

that self inspection provides, but provides more objectivity.

Another solution to address the conflict of interest that can arise in self inspection is to

provide a "mistake-proofing" device, or poka-yoke, to assist in the inspection. Again,

22

Page 23: Analysis of the Production System at ABB Combustion

production benefits from the immediate feedback provided by enhanced self-inspection, without

the drawbacks of standard self inspection.

The best inspection method is source inspection. By monitoring and controlling the

conditions at the source of the operation, defects can be prevented rather than detected. Source

inspection can trace the problems "vertically" through the process flow or "horizontally" within

an operation.

The most important aspect of the inspection philosophies of TPS is that every part is

inspected. 100% inspection assures that defects are not passed to subsequent processes and

certainly not to the final customer. All it takes is for one customer to buy one defective product

and that company has lost that person's business forever.

23

Page 24: Analysis of the Production System at ABB Combustion

3.0 EXISTING CONDITIONS AND PROJECT GOALS

3.1 Current Plant Layout

Production of parts in Newington is split up into two categories: light and heavy

manufacturing, which also (generally) corresponds to small and large components. These

components are appropriately machined and sub-assembled in the respective light and heavy

manufacturing buildings.

The light manufacturing building is set up mainly in a departmental layout. It also houses

a warehouse for the storage of raw stock, as well as partially machined parts and fully-machined

parts that are awaiting assembly. A 2-ton boom crane in the light manufacturing building

facilitates material handling. See Figure 3-1 for a schematic of the light manufacturing building.

The heavy manufacturing building contains assembly areas, as well as machines needed

to produce the large components that Newington makes. These machines are permanent fixtures

in the building. The heavy manufacturing building is divided into two halves, one of which is

served by a 30 ton crane with a height of 29 feet, while the other half is served by a 100 ton

crane with a height of 70 feet. See Figure 3-2 for a schematic of the heavy manufacturing

building. There are also three fork trucks that are used to move material around - small,

medium, and large.

In June, at the beginning of the internship, production of the canisters was already

underway and plans for a new building (300 feet x 85 feet in area) dedicated to canister

production were being developed. In the meantime, fabrication of the canisters occurred on the

existing machines in the shops and wherever floor space could be found.

24

Page 25: Analysis of the Production System at ABB Combustion

RCPASSEMBLY

WAREHOUSE

receiving

CeltAssembly

storageof finishedcomponentsawaitingassembly

storageof finishedcomponentsawaitingassembly

Classroom

cut-off s Machine poison strip,..assembly 0C M"eNE ROOM Lunch

storage wellsaj E _torage

! tat es TOOL & CUnER- bands aw

GRNINNG AREA -ai

CrosseeAssembly

storage he ""*i deburrng___- 11~ grinders--

Figure 3-1: Schematic of Light Manufacturing Building.(Note: Drawing not to scale.)

SYS 80CORE

SHROUD

The work inthis area

changes daily

LOW BAY (3

GAGEROOM RCP ASSY

POWERSUB-STATION

CNC SYS 80 FAB &CARLTON 6 G&L FINAL ASSY

RADIAL HBM, DRILL RCP FINAL ASSY

0 TON) HIGH BAY (100 TON)

______ -CNCINT DORRIESFROREIP ASSY VEM

VBM CNC STANDVBM ~7" GRAY HBM TN

MAINT. TROOM OFFICESTESTLOOP

CRAVENVBM

BLAST/PAINTFACILITY

Figure 3-2: Schematic of the Heavy Manufacturing Building.(Note: Drawing not to scale.)

25

m == - -

Page 26: Analysis of the Production System at ABB Combustion

3.2 Flow of Parts and Information

Production begins when a project engineer creates a Manufacturing Process Sheet (MPS).

The main body of an MPS contains manufacturing and inspection instructions set up in

sequences of operations. The MPS also includes a list of parts/raw materials needed (called the

"items checklist"), referenced drawings, weld procedures (which are added later), and inspection

procedures. The last page of the MPS is an accounting document called a "J50", which is

basically the engineer's best estimate of how long each sequence in the MPS should take, and is

used to record the actual hours that each sequence takes.

The MPS then moves to the weld engineer, who adds the specific welding instructions, if

any are necessary. Next, the MPS goes to Quality Assurance (QA), who writes up any

Dimensional Inspection Reports (DIR) if they are needed. Manufacturing services receives the

MPS next and checks to make sure that all items listed in the items checklist are currently in the

warehouse. If they are, then the MPS is ready to be released to the shop floor.

At the same time that the MPS is travelling around getting all its necessary components,

the project engineer orders the parts/raw stock needed. When the material arrives in Newington,

it must go through the receiving department. Large items that will be machined in the heavy

manufacturing building are delivered directly to that building. The parts are received at one of

two doors, depending on the weight of the material. (Anything greater than 30 tons must be

received at the back entrance, where there is a 100 ton overhead crane. The overhead crane at

the front of the building is a 30 ton crane.) All other items are delivered to the light

manufacturing building, which contains the warehouse. (Note: The warehouse only contains

material that has been approved for use. Nothing can be kept in the warehouse until it has passed

through receiving inspection.) The receiving department checks to make sure that what has been

26

Page 27: Analysis of the Production System at ABB Combustion

delivered is truly what was ordered, and also checks to make sure that the material has all

necessary certification documents with it. If everything checks out okay, the material is placed

in the warehouse until needed. If receiving doesn't approve the shipment, a Non-Conformance

Report (NCR) is written stating what the problem is, which then must be verified by QA. The

material can either then be returned to the supplier, scrapped, or "repaired" if possible.

At this point, manufacturing services releases the MPS to the shop floor. The items

checklist is given to a material handler, who kits the parts and delivers them to the proper work

station, which could be in either the light manufacturing building or the heavy manufacturing

building. If the machining is happening in the heavy manufacturing building, the items checklist

page is usually given to a material handler a day or so in advance of when the parts are actually

needed. In the light manufacturing building, if the MPS is currently on the shop floor, it is

common for the machinist to walk over to the warehouse, himself, and fill out a "material

withdrawal request" to get the material that he needs, rather than go through the shop foreman

again. The machinist then begins working.

After the first part is machined, it must be inspected by Quality Control (QC). To do this,

the machinist must go to his immediate supervisor (the shop foreman) and tell the foreman that

he needs an inspector for a first piece inspection. The foreman then fills out an Inspection

Service Request (ISR), which he usually then brings directly to a QC inspector. Inspection

generally happens on a first come, first serve basis, so if an inspector is currently free, he

performs the first piece inspection. Otherwise, the machinist must wait for a few minutes until

an inspector is available. If QC approves the part, the machinist can then continue machining the

remaining parts for that particular sequence of the MPS. Sometimes first piece inspection will

happen after a few sequences of the MPS have been performed, which then allows the machinist

27

Page 28: Analysis of the Production System at ABB Combustion

to perform all of those operations on the remaining pieces. Other times, first piece inspection

happens after each individual sequence of the MPS. The project engineer that wrote the MPS

determines which of the above procedures to follow.

When the machinist has finished machining all the parts, a QC inspector is needed, again,

for final inspection, which can be either 100% inspection or sample inspection, depending on the

type and number of the parts. At this point, typically, the machinist will move on to another job,

and the ISR will be dropped off in the QC "in-box" and tended to the next day or at the first

convenience. If necessary, certain inspection requests can be prioritized over others if the job is

in high demand.

The above procedures hold true for assembly, also.

Parts travel all over the shop in Newington. They also travel a good deal between the

light manufacturing and heavy manufacturing buildings. Below is a table of a few selected

canister parts and the distances that those parts traveled in the current production system at ABB.

Part Name, Number Distance traveled (ft.)

5x2 tube steel arms, P05-001 580

Structural Ed, P04-001 2,196.5

Shield Lid, top plate, P03-001 1,293.6

Shield Lid, bottom plate, P03-003 1,293.6

Shield Lid, P03-001 welded to P03-003 3,009.6

Table 3-1: Sample travel distances of selected parts.

3.3 Scrap, Non-conformances and Corrective Action

To date, there is no numerical record of the level of scrap in Newington. As for non-

conformances, ABB keeps a large database detailing the disposition of all non-conformance

28

Page 29: Analysis of the Production System at ABB Combustion

reports (NCR). They track failures, defects, operator, and machine work center involved with

each non-conformance, as well as all NCRs caused by suppliers.

When an in-process defect is made, the machinist brings it to the attention of the

foreman, who then fills out an NCR detailing the defect. In the NCR, the foreman will also

describe any corrective action measures that could be taken to prevent such a defect from

occurring in the future. The NCR then goes back to the project engineer, who writes another

MPS to either repair the damaged parts or produce completely new ones. Hopefully, also, the

project engineer uses the "corrective action" suggestion in the NCR and edits the old MPS so as

to improve the instructions and prevent the same mistake from happening in the future. At the

same time, the machinists usually take notes on the operations that they do and keep track, for

themselves, of things that go wrong, why, and how to prevent them in the future. Unfortunately,

the machinists do not always refer back to these notes and thus, repeat the same mistake.

3.4 Inspection

As describe in the previous section, inspection happens many times during each MPS.

The first sequence of most MPSs is "QI verify items checklist," which simply requires an

inspector to verify that the material has been approved for use. QI is needed for first piece

inspection, for verification of fit-ups and weld tacks, for dimensional inspection, as well as for

inspection of welds.

Inspection of parts can take anywhere from a few minutes to a few hours, depending on

the type of inspection that is performed, the size of the part being inspected, and the complexity

of the part being inspected. The following histogram shows the distribution of inspection times

per part for 26 MPSs that were part of the first canister contract. The mean inspection time is

29

Page 30: Analysis of the Production System at ABB Combustion

just over half an hour (33 minutes), though the range is from 6 seconds (for a quality inspector to

verify the part number of 2816 parts in 3 hours) to 97.5 hours (for the first piece inspection of the

5x2 tube steel arm for the main cross assembly).

Histogram

1 61

13

1 0 0 1

0.001 0.751 1

0 1

.501 2.251 3.001 3.750 4.500 5.250 More

Inspection Time (hours)

Figure 3-3: Histogram of inspection times per part for 26 MPSs of the initial canister contract.

3.5 Worker Activities

ABB Newington is a union shop. Each worker has a specified role and never cross-trains

between roles. There are machinists, assemblers, welders, material handlers, and quality

inspectors. Machining and assembly in Newington is highly manual. There is very, very little

automation in the plant.

To document typical daily activities, a random 2-hour time slot was chosen and 9

workers were observed during this time slot. The following charts show a breakdown of the time

spent on each activity per worker and the percentage of total time (9 workers x 125 minutes of

30

a)IL

70

60

50

40

30

20

10

0 -- --- - - - -- ----------

Page 31: Analysis of the Production System at ABB Combustion

observation =1125 minutes) spent on each value adding and non-value adding but necessary

operations.

Pareto Chart of Activities

250

S200 -

S150 - -

*~100-0.

4) 500 ) E/ )C)U

C ) 0 E 0a

a- 0 C . 0 0

CUC - CL a)0C .C )

4) .9 a) 0)> .0=

Ra-)c 0@ a)~- V> LU CU LL tMr- - ) 0)

-O 0 0 .-c 0

C 00

Activity

Figure 3-4: Pareto chart of worker activities during a random 2-hour time slot.

Total Time Spent on Each Operation/Activity

E 40%-P 35%* 30%-,* 25%-'1 20%-

15%S10%

W. -Y E (

0 C

0) 0)0 :92

0) 7~ -

C. (D .0-

V~( 0)0.

Operation/Activity

Figure 3-5: Percentage of total worker hours spent on each operation/activity

during the same random 2-hour time slot.

31

Page 32: Analysis of the Production System at ABB Combustion

Sorting the above activities into value-adding, waste, and non-value adding but

necessary, results in the following breakdown:

Non-valueadding butnecessary

27%

Waste36%

Value adding37%

Figure 3-6: Pie chart of value adding, non-value adding but necessary, and pure waste

observed during the random 2-hour observation period.

3.6 Scheduling

Initial scheduling put together for the bidding process is based on experience for up-front

engineering span, long lead material spans, and rough estimates on duration (normally, the latter

is a high level look), plus shipping added onto the end. Production scheduling is based on actual

engineering/QA tasks scheduled in hours for 40 hours per week per person. Shop work is based

on estimated duration for major operations at the sub-MPS level, but not quite at the operation

level.

A typical contract at ABB for the System 80 Power Plant components (described briefly

in Section 1.1) takes three years to complete. There is a good amount of play in a 3-year

schedule, so ABB doesn't necessarily have to adhere to the nitty-gritty details of their proposed

32

Page 33: Analysis of the Production System at ABB Combustion

schedule. There is a lot of opportunity to "catch up" to the schedule and ship the final product(s)

on time. For the canisters, however, ABB must adhere to a much stricter schedule. For

example, production of one particular canister contract began in the beginning of March and the

first finished canister is expected to ship in July, with another finished product following every

two weeks thereafter.

3.7 Project Goals

The purpose of this project is to determine to what extent a cellular manufacturing system

is truly feasible at ABB-CENP Newington Operations. The intentions of creating a cellular

manufacturing system are to improve the flow of parts through the shop, reduce the amount of

inventory and work-in-process (WIP), reduce the amount of floor space taken up by production,

and reduce the throughput time and manufacturing lead time.

It is intended that, at the end of this project, ABB can use this thesis as a basis to begin

making changes in their manufacturing system. The ideas set forth in this thesis will provide a

starting point for ABB to work off of, as well as illustrate the improvements that can be made by

making simple changes.

Another goal of this thesis is to address the conflict that arises between the ideals of

cellular manufacturing and the necessary "evils" of the nuclear power industry. Specifically, the

issue of quality assurance is addressed, as well as the combination of cellular manufacturing and

project-shop manufacturing that must take place for the production of these spent fuel canisters.

Chapters 4 and 5 explore these issues deeper.

33

Page 34: Analysis of the Production System at ABB Combustion

4.0 MSD DECOMPOSITION APPPLIED TO ABB NEWINGTON

The main goal of this thesis is to analyze the current production system at ABB in order

to systematically improve the system as a whole. In Chapter 3, the current situation at ABB was

described. In this chapter, the MSD Decomposition will be detailed branch-by-branch and

applied to the production system at ABB to determine the necessary path that ABB needs to take

in order to transform their plant into a "lean" production system. Suggestions are made or

examples are given wherever possible to illustrate potential improvements to ABB's system.

As discussed in Chapter 2, the MSD Decomposition is based on axiomatic design and

provides a comprehensive approach to designing a lean production system. The ideas of TPS are

encapsulated in the structured MSDD. The MSDD is used in this thesis because it provides a

systematic framework for analyzing a production system.

4.1 Top Three Levels of the MSD Decomposition

Levels I, II, and III of the MSD Decomposition are detailed in Figure 4-1. "FR" states

the functional requirement, "PM" details the performance measurement, and "DP" lists the

corresponding design parameter.

The functional requirements of these three levels outline the ultimate goals of the system.

As a company, ABB wants to maximize the long-term return on investment, which means

maximizing sales revenue, minimizing manufacturing costs, and minimizing investment over the

production system lifecycle.

To maximize sales revenue, a company must make sure it's producing quality parts,

delivering products on time, and meeting the customers' expected lead time. Minimizing

34

Page 35: Analysis of the Production System at ABB Combustion

FR112Deliverproducts ontime

PM112Percentageon-timedeliveries

FR1IMaximize long-termreturn on Investment

PM1Return on investment oversystem lifecycle

DP1Manufacturing System Design

FR113Meetcustomerexpected leadtime

PM113Differencebetween meanthroughput

FR121Reduce wastein direct labor

PM121Percentage ofoperators'time spent onwasted

FR122Reduce wastein indirectlabor

PM122Amount ofrequired

FR123Minimizefacilities cost

PM123Facilities cost

time and motions and indirect laborcustomer's waitingexpected leadtimi

DP-111 DP112 DP113 DP121 DP122 DP123Production Throughput Mean Elimination of Reduction of Reduction ofprocesses time variation throughput non-value indirect labor consumedwith minimal reduction time reduction adding manual tasks floor spacevariation from tasksthe target

Quality Identifying Predictable Delay Direct Indirectand Output Reduction Labor Labor

ResolvingProblems

Figure 4-1: Levels I, II, and III of the MSD Decomposition.

35

Level I

FR11Maximize sales revenue

PM11Sales revenue

Leve II

Level Ill

FR12Minimize manufacturing costs

PM12Manufacturing costs

-I - - - -

DP11DP1 1Production to maximizecustomer satisfaction

I

FR13Minimize investment overproduction system lifecycle

PM13Investment over systemlifecycle

DP1 2Elimination of non-value addingsources of cost

FR111Manufactureproducts totarget designspecifications

PM111Processcapability

DP1 3Investment based on a longterm strategy

Page 36: Analysis of the Production System at ABB Combustion

manufacturing costs involves reducing waste in both direct and indirect labor, as well as

minimizing facilities cost.

These functional requirements lead to design parameters that describe a cellular

manufacturing system perfectly. The design parameters call for a system that produces with

minimal variation from the target, works to reduce mean throughput time and throughput time

variation, eliminates all non-value adding tasks, reduces indirect labor tasks, and reduces the

necessary floor space. A linked-cell production system exemplifying the philosophies of the

Toyota Production System is the best way to implement these design parameters.

Before beginning a discussion on each Level IV branch of the MSDD, FR-123

"Minimize facilities cost" needs to be addressed. DP-123 calls for the "reduction of consumed

floor space." ABB is currently constructing a new building to house the spent-fuel canister

production. At the same time, approximately 30-40% of the already-existing Light

Manufacturing Building is occupied by a warehouse. This warehouse contains a large amount of

inventory. Much of this inventory is parts that are needed for upcoming contracts that may be

received a few months to a few years in advance of when they are actually needed. There are

also many smaller components that are ordered in bulk and stored in the warehouse for use

whenever needed. If ABB would simply reduced the amount of inventory in the warehouse, they

could cut the size of the warehouse drastically and use that added floor space for production. By

employing the concept of "just-in-time," whereby parts are received when needed and in the

amount needed, ABB can eliminate the need to store parts in the warehouse. To meet this

objective, requires having confidence in suppliers to deliver quality products on time, which is an

issue that will be addressed in section 4.2, and may not even be feasible.

36

Page 37: Analysis of the Production System at ABB Combustion

4.2 Quality

Figure 4-2 details Level IV of the Quality branch of the MSDD. The very first functional

requirement is FR-Q 1: "Operate processes within control limits." As mentioned in Chapter 3,

ABB does not currently monitor in-process production or provide immediate (or even moderate)

feedback to the operator regarding the quality of the parts. After first-piece inspection, the parts

are produced in large batches (usually the entire quantity needed for that particular contract) and

are not inspected again until final/sample inspection. At which point, prevention of defects is

impossible. It is recommended that ABB begin use of a control system to determine the

characteristics of the parts being produced immediately after they are produced. A simple first

step would be dimensional inspection, by the operator, of each part as it is produced. Run charts

can then be used to alert the operator of the presence of assignable causes of variation. Should

problems arise, an investigation must be done to determine the cause of variation and then action

must be taken to eliminate the assignable causes of variation due to the machine, operator,

method, and material (FR-Q1 1 through FR-Q 14). (For further reading on this subject, refer to

Statistical Quality Design and Control: Contemporary Concepts and Methods, DeVor, Chang,

and Sutherland, Prentice Hall, 1992.) It should be noted, however, that, as discussed in Chapter

2, sample inspection allows defects to be passed on through the system. 100% inspection is

the only way to assure that no defects end up in the hands of the final customer.

Taking a slightly deeper look into the elimination of operator assignable causes, FR-

Q122 states: "Ensure that operator consistently performs tasks correctly." The corresponding

DP-Q122 is the use of "standard work methods." This is an area where ABB can make some

significant improvements. As it currently stands, the Manufacturing Process Sheets (MPSs)

37

Page 38: Analysis of the Production System at ABB Combustion

Level IV

I---------------------

DP-Q1Elimination of assignablecauses of variation

DP-Q2Process parameter adjustment

FR-Q11 FR-Q12 FR-Q13 FR-Q14 FR-Q31 FR-Q32Eliminate machine Eliminate operator Eliminate method Eliminate material Reduce noise in Reduce impact ofassignable causes assignable causes assignable causes assignable causes process inputs input noise on

process outputPM-Q11 PM-Q12 PM-Q13 PM-Q14Number of defects Number of defects Number of defects Number of defects PM-Q31 PM-Q32per n parts per n parts per n parts per n parts Variance of process Output variance /assignable to assignable to assignable to the assignable to the inputs input varianceequipment operators process quality of incoming

material

DP-Q11 DP-Q12 DP-Q13 DP-Q14 DP-Q31 DP-Q32Failure mode and Stable output from Process plan design Supplier quality Conversion of Robust processeffects analysis operators program common causes design

into assignablecauses

FR-Q121Ensure that operator hasknowledge of required tasks

PM-Q121Number of defects per n partscaused by an operator's lack ofunderstanding about methods

DP-Q121Training program'

FR-Q122Ensure that operatorconsistently performs taskscorrectly

PM-Q122Number of defects per n partscaused by non-standardmethods

DP-Q122Standard work methods

FR-Q123Ensure that operator humanerrors do not translate todefects

PM-Q1123Number of defects per n partscaused by human error

DP-Q123Mistake proof operations (Poka-Yoke)

Figure 4-2: Level IV of the "Quality" branch of the MSD Decomposition.

38

FR-Q1Operate processes withincontrol limits

PM-Q1Number of defects per n partswith an assignable cause

FR-Q2Center process mean on thetarget

PM-Q2Difference between processmean and target

FR-Q3Reduce variation in processoutput

PM-Q3Variance of process output

DP-Q3Reduction of process noise

I

Page 39: Analysis of the Production System at ABB Combustion

written by the project engineers are intended to be the guidelines for outlining the proper

operations that need to be done on a part. However, the instructions in the MPSs are not detailed

enough to serve as step by step instructions. Thus, many times the machinists have to consult the

foreman for exact procedures or decide on their own the best way to go about the process. As a

result, multiple methods are employed to produce the same part over time and mistakes are often

repeated on subsequent contracts. Though each machinist takes notes on each job for future

reference, there's no guarantee that the same machinist will perform the same operations for the

next contract. The new machinist may not know about the previous machinist's notes, which

may result in the same mistakes being made twice. Therefore, MPSs need to be more detailed

and contain specific operating procedures to assure that each worker is using standard work

methods.

FR-Q14 is another area that ABB needs to look closely at. This functional requirement

calls for the elimination of material assignable causes. The corresponding design parameter is a

"supplier quality program." As detailed in the performance measure, ABB needs to minimize

"the number of defects per n parts assignable to the quality of incoming material." Between

March 1999 and February 2000, there were a total of 232 non-conformance reports filed on

incoming material. 22% of those Non-Conformance Reports (NCRs) were due to "document

deficiency," which means that the material was delivered to ABB without the necessary

paperwork stating exactly what the material is, the lot that the material came from, the fact that it

meets specified standards, etc.. 9.1% were filed because the certifications on the material were

illegible. These types of errors are not acceptable. During the 1999 calendar year, ABB had six

suppliers that caused 10 or more NCRs each. One of the key aspects to creating a well-

functioning production system is to have the same type of "lean" system occur upstream and

39

Page 40: Analysis of the Production System at ABB Combustion

downstream. In ABB's instance, the quality aspect of a lean production system is not happening

upstream, which is resulting in ABB's receipt of defects. As it stands right now, ABB must

inspect all incoming material to make sure it meets all requirements and regulations. Ideally,

however, ABB shouldn't have to inspect any incoming material at all. Perhaps the best approach

that ABB could take to resolve this problem is to tally the NCRs caused by each supplier and

note the types of defects that occur and how often each defect occurs from the same supplier.

Then, ABB can approach the most troublesome suppliers about improving their quality and have

specific aspects of the suppliers' system that need special attention. Creating this linked chain of

improvement will benefit the entire production stream.

4.3 Identifying and Resolving Problems

This branch of the MSD Decomposition addresses ways to minimize disruptions in

production. Figure 4-3 shows the components of this particular branch. Because most

operations at ABB are manual, detection of production disruptions is immediate. When a

disruption occurs, the machinist/welder/assembler brings it to the attention of his/her supervisor.

If possible, the problem is resolved at this point and production resumes. Sometimes, however,

either the worker and/or the shop foreman will bring the disruption to the attention of the project

engineer that issued the MPS under which the disruption occurred. Again, if the problem can be

resolved at this level, then production begins again. Otherwise, management becomes involved,

also.

FR-R13 states: "Solve problems immediately." This functional requirement is not

always fulfilled at ABB. A production disruption is most likely caused by the production of a

40

Page 41: Analysis of the Production System at ABB Combustion

FR-R1Respond rapidly to productiondisruptions

PM-R1Time between occurrence andresolution of disruptions

DP-R1Procedure for detection &response to productiondisruptions

- - -i171 - -

DP-R11Subsystem configuration toenable operator's detection ofdisruptions

FR-R111Identify disruptionswhen they occur

PM-R111Time betweenoccurrence andrecognition thatdisruption occurred

FR-R1 12Identify disruptionswhere they occur

PM-R112Time betweenidentification ofdisruption andidentification ofwhere the disruptionoccurred

71FR-R113Identify what thedisruption is

PM-R113Time betweenidentification ofwhere disruptionoccurred and

DP-R12Process for feedback ofoperation's state

FR-R1 21Identify correctsupport resources

PM-R121Time betweenidentification of whatthe disruption is andidentification of thecorrect support

DP-R13Standard method to identify andeliminate root cause

FR-R1i22Minimize delay incontacting correctsupport resources

PM-R122Time betweenidentification andcontact of correctsupport resource

FR-R1i23Minimize time forsupport resource tounderstanddisruption

PM-R123Time betweencontact of correctsupport resourceand support

identification of what resource resourcethe disruption is understanding what

the disruption is

DP-R111 DP-R112 DP-R113 DP-R121 DP-R122 DP-R123

Increased operator Simplified material Context sensitive Specified support Rapid support System that

sampling rate of flow paths feedback resources for each contact procedure conveys what the

equipment status failure mode disruption is

Figure 4-3: Level IV of the "Identifying and Resolving Problems"branch of the MSD Decomposition.

defective part, which means that an NCR needs to be filed. As mentioned in Chapter 3, the

physical piece of paper detailing the non-conformance travels to approximately 3-4 people,

41

Level IV

FR-R11Rapidly recognize productiondisruptions

PM-R11Time between occurrence ofdisruption and identification ofwhat the disruption is

FR-R12Communicate problems to theright people

PM-R12Time between identification ofwhat the disruption is andsupport resource understandingwhat the disruption is

FR-R13Solve problems immediately

PM-R13Time between support resourceunderstanding what thedisruption is and problemresolution

I

Vl

V1

I

Page 42: Analysis of the Production System at ABB Combustion

depending on whether the Quality Assurance department is involved or not. It isn't until the

project engineer gets the NCR and writes a "repair traveler" to either fix the defective parts or

produce new parts, that action can be taken to solve the problem. Quite often, a few days or even

weeks will pass before the new MPS is issued. This time delay needs to be eliminated so that

production disruption delays are as short as possible.

4.4 Predictable Output

Not only do disruptions need to be identified and corrected rapidly, but they need to be

minimized, as well. Both the length of time and the frequency of the disruptions must be

addressed. The "Predictable Output" branch of the MSDD is detailed in Figure 4-4.

The spent fuel storage canisters are a new product for ABB. Construction is at an

"experimental" level at this stage in production. One of the main causes for this is that the

design of the canisters was completely separate from the manufacturing. Another firm designed

the canisters and then "tossed the design over the wall" to ABB, who is fabricating the canisters.

For this reason, the beginning of production of each new type of canisters is going to be filled

with trial and error procedures until the best methods are found. Once the best methods are

determined, ABB can then focus on the "Predictable Output" branch of the Decomposition.

Functional requirements FR-P13 and FR-P14 and the subsequent lower level FRs will be

key areas for ABB to focus on once they establish exact production methods. To "ensure

predictable worker output" (FR-P13), ABB must have a "motivated work-force performing

standard work" (DP-P13). Once again, this issue of standard work arises. Knowing exactly

which operations were performed on a part makes it easy to pinpoint the source of error and

correct it. If different procedures are used to make the same part, multiple reasons may arise

42

Page 43: Analysis of the Production System at ABB Combustion

Level IV

time for information downtime of interruption time for time for materialdisruptions operators shortages

DP-P11 D DP-P13 DP-P1 4Capable and reliable Maintenance of Motivated work-force Standard materialinformation system equipment reliability performing standard work replenishment system

FR-P121 FR-P122 FR-P131 FR-P132 FR-P133 FR-P141 FR-P142Ensure that Service Reduce Ensure Do not Ensure that Ensure properequipment is equipment variability of availability of interrupt parts are timing of parteasily regularly task workers production for available to arrivalsserviceable completion worker the material

PM-P122 time PM-P132 allowances handlersPM-P121 Frequency of Number ofAmount of equipment PM-P131 occurrences of PM-P133 PM-P141 PM-P142time required servicing Variance in operator Number of Number of Partsto service task lateness, disruptions occurrences of demanded -equipment completion Amount of due to marketplace parts delivered

time operator operator shortages

DP-P121 DP-P122 DP-P131Machines Regular Standard workdesigned for preventative methods to

serviceability maintenance provideprogram repeatable

processing

lateness allowances,amount ofinterruptiontime forworkerallowances

DP-P132 DP-P133Perfect Mutual ReliefAttendance System withProgram cross-trained

workers

DP-P141 DP-P142Standard work Parts movedin process to downstreambetween sub- operationssystems according to

pitch

Figure 4-4: Level IV of the "Predictable Output" branch of the MSD Decomposition.

43

FR-P1Minimize production disruptions

PM-P1Number of occurrence ofdisruptions & Amount of timelost to disruptions

DP-P1Predictable productionresources (people, equipment,info)

FR-P11hEnsure availability ofrelevant productioninformation

PM-Ph1Number of occurrences ofinformation disruptions,Amount of interruption

FR-P12Ensure predictableequipment output

PM-P12Number of occurrences ofunplanned equipmentdowntime, Amount ofunplanned equipment

FR-P13Ensure predictable workeroutput

PM-P13Number of disruptionsdue to operators, Amount

FR-P14Ensure materialavailability

PM-P14Number of disruptionsdue to material shortages,amount of interruption

Page 44: Analysis of the Production System at ABB Combustion

when trying to determine what caused a defect. In order to be able to predict the output, the

same operations need to be performed in the same order each time the same part is made.

Standardizing the work will also help in predicting how much time it will take to

complete a task. Currently, production scheduling is done at the sub-MPS level, but not quite at

the operation level. If standardized work was employed, scheduling could be done at the

individual operation level, which would make scheduling more accurate and predictable. This

practice will improve scheduling for bidding purposes and increase the chance of delivering the

finished products on time to the customer.

"Ensure material availability" is FR-P14, with its corresponding DP-P14 of "Standard

material replenishment system." The next functional requirements are "Ensure that parts are

available to the material handlers" (FR-P141) and "Ensure proper timing of part arrivals" (FR-

P142). Both of these bottom level FRs would drastically improve ABB's material handling

system. The utilization of the computerized inventory system at ABB needs to be improved, as

well as the overall philosophy regarding the level of inventory, in general, and the manner in

which material is delivered to each work station.

Currently, when material is received from a supplier, it is immediately entered into the

computerized inventory system. The information entered into the system includes the part

number, part description, quantity, location in the warehouse where the material will be stored,

who ordered the material, and how much the material cost. Not everyone at ABB uses the same

notation to designate, within the program, when a quantity of parts has been allotted to a specific

job, which often causes confusion and occasionally either a shortage or an excess of parts. Even

though many employees at ABB have been working there for quite some time, if ABB wants to

44

Page 45: Analysis of the Production System at ABB Combustion

make this inventory system work properly, they need to have another training session and come

to a consensus on proper notation and designation methods within the system.

Regarding the level of inventory, in general, however, ABB shouldn't need a

"warehouse" to store parts. A typical contract for System 80 power plant components takes three

years to build. Many of the components arrive at ABB pre-machined, cast, sandblasted, etc..

Each project engineer must keep track of the parts that he will need a few years in advance and

make sure that he places the order to the supplier far enough ahead of schedule so that the parts

arrive in time for assembly. Quite often, however, parts will be ordered so far in advance that

the parts sit in the warehouse for months or even years. This practice is an ineffective use of

capital. As discussed in section 4.1, purchasing materials when needed and in the quantity

needed will reduce the amount of money invested by the company and also free up space in the

Light Manufacturing Building that can be used for production instead of storage.

Standardizing the work throughout the system will also help to assure that the material

handlers always have the proper quantity of parts that they need to deliver to the next work

station at the proper time. When parts are produced on a regular schedule, the material handlers

will always know how many parts will be produced in a certain amount of time and can use that

fact to stick to a regular material delivery schedule. This notion of producing parts at regular

intervals of time will be discussed in more detail in section 4.5 when the idea of "takt time"

arises.

4.5 Delay Reduction

As can be seen in Figure 4-5, the top design parameters of Level IV of the "Delay

Reduction" branch of the MSDD call for single-piece flow, production to run at takt time,

45

Page 46: Analysis of the Production System at ABB Combustion

Level IVFR-T1 FR-T2 FR-T3 FR-T4Reduce lot delay Reduce process Reduce run size Reduce

delay delay transportation delay(caused by ra > r,)

PM-T1 PM-T2 PM-T3 PM-T4Inventory due to lot Inventory due to Inventory due to run Inventory due tosize delay process delay size delay transportation delay

DP- T1 DP-T2 DP-T3 DP-T4Reduction of transfer Production designed Production of the Material flowbatch size for the takt time desired mix and oriented layout(single-piece flow) quantity during each design

demand interval

FR-T21 FR-T22 FR-T23 FR-T31 FR-T32 FR-T51Define Ensure that Ensure that Provide Produce in Ensure thattakt time(s) production part arrival knowledge of sufficiently support

cycle time rate is equal to demanded small run resourcesequals takt service rate product mix sizes don't interferetime (ra=rs) (part types with

and quantities) productionPM-T21 resourcesHas takt time PM-T22 PM-T23 PM-T31 PM-T32been defined? Difference Difference Has this Actual run size PM-T51(Yes / No) between between information - target run Production

production arrival and been size time lost duecycle time and service rates provided? to supporttakt time (Yes/No) resources

interferenceswithproductionresources

DP-T21 DP-T22 DP-T23Definition or Subsystem Arrival of partsgrouping of enabled to at downstreamcustomers to meet the operationsachieve takt desired takt according totimes within time (design pitchan ideal range and operation)

DP-T31 DP-T32Information Design quickflow from changeoverdownstream for materialcustomer handling and

equipment

DP-T51Subsystemsandequipmentconfigured toseparatesupport andproductionaccess req'ts

FR-T5Reduce systematicoperational delays

PM-T5Production time lostdue to interferencesamong resources

DP-T5Subsystem designto avoid productioninterruptions

FR-T52 FR-T53Ensure that Ensure thatproduction supportresources resources(people/autom (people/automation) don't ation) don'tinterfere with interfere withone another one another

PM-T52 PM-T53Production Productiontime lost due time lost dueto production to supportresources resourcesinterferences interferenceswith one with oneanother another

DP-T52 DP-T53Ensure Ensurecoordination coordinationand andseparation of separation ofproduction support workwork patterns patterns

FR-T221Ensure that automatic cycletime minimum takt time

PM-T221

FR-T222Ensure thatmanual cycle time 5 takt time

FR-T223Ensure level cycle time mix

Has this been achieved? (Yes / PM-T223No) PM-T222 Is average cycle t

Has this been achieved? (Yes / takt time in desireNol interval?

DP- T221 DP- T222 DP-T223Design of appropriate automatic Design of appropriate operator Stagger productiowork content at each station work content/loops different cycle tim

ime less thand time

n of parts withes

Figure 4-5: Level IV of the "Delay Reduction" branch of the MSD Decomposition.

46

Page 47: Analysis of the Production System at ABB Combustion

balanced and level production, as well as minimum transport of material. All of these

parameters are prime descriptors of a cellular manufacturing system.

The first step in reducing delay is to create single-piece flow. When large batch sizes are

used, parts end up sitting after being machined or assembled, waiting for the rest of the batch to

go through the same operation. The parts don't move on to the next operation until that

particular operation has been performed on every piece in the batch. This routine is one of the

seven wastes as defined by the Toyota Production System. In a cellular manufacturing system,

each part is passed on one at a time as each operation is completed. This allows for final

products to be produced much sooner than in batch production and also reduces the quantity of

work-in-process (WIP).

The next functional requirement, FR-T2, is to "reduce process delay." This is

accomplished by running production at "takt time," which is the available time per shift divided

by the average demand per shift. At the time of this thesis project, ABB was working on its first

canister contract. While this contract ended up being put on hold due to design problems, the

cellular design suggested in this thesis is based on this initial contract. This thesis aims to set an

example of how to design the cellular system, not necessarily detail the exact system that ABB

should develop. Therefore, all numbers and details used to design the cellular system described

in the remainder of this thesis are fictitious.

4.5.1 Takt Time

FR-T21 says that takt time(s) need to be defined. At ABB, based on a working schedule

of 6 hours and 45 minutes of work per shift (which results from subtracting breaks from the full

47

Page 48: Analysis of the Production System at ABB Combustion

8-hour day), 2 shifts per day, and 22 working days per month, and assuming customer demand of

50 canisters per year, the takt time is:

405 minutes/shift = 4276.8 minutes/canister = 71.28 hours/canister(50 canisters/12 months)/(44 shifts/month)

This calculation means that every 71.28 hours of operation, a finished product should be

produced. The finished canister is made up of subassemblies, which are, in turn, made up of

individual components. Each of these subassemblies will be made in separate cells, which will

run at their own takt times, depending on the quantity of subassemblies needed per canister. For

example, there is only one shell per canister. The shell arrives at ABB in four segments, which

are welded together and then go through a series of machining operations. One shell should be

produced every 71.28 hours to feed the final assembly cell. There are 32 main cross assemblies,

however, which means that the main cross assembly cell should produce one complete product

every 133 minutes.

Continuing with the example of the main cross assemblies, we further break them down

into individual components, which will come from machining cells. Each machining cell will

produce at its own takt time, depending on the number of parts going through the cell and the

level of demand.

48

Page 49: Analysis of the Production System at ABB Combustion

4.5.2 Floor Layout

One of the main ideas of a linked-cell system is to minimize the throughput time, to

maximize workers' effectivity, to highlight problems, and to provide an environment for

continuous improvement. As a result, cells are typically U-shaped and machining cells are

physically located so that they feed easily into the subassembly cells, which, likewise, are set up

to feed easily into the final assembly cell. The ship building industry uses a set-up similar to that

shown in Figure 4-6 [Storch et al.]. Note, however, that the overall shape of this layout is a

square. ABB's new building, however, in going to be 300 feet x 85 feet. Such a rectangle

makes it difficult to surround final assembly with the subassembly cells, and impossible to place

machining cells in a ring beyond that. Adequate pathways must be left between the cells to

allow for passage of fork trucks and large parts moved by overhead cranes. Adjusting to this

long, skinny rectangular shape, a possible layout for the canister production is shown in Figure

4-7. This possible layout pertains to a general form of a spent fuel canister with components

MachiningCell ubcssemb y Subassembly

components aolcome from componentsmachining purchased

cells from outsidevendor

Machinir g Fina Shipping/LACells ALAemhly Receiving

Subassembly Subassemblyall

components componentscome from purchased

Machining machinig from outsideCell cLls vendor

Figure 4-6: A square layout, with the final assembly cell surrounded by a ring ofsubassembly cells, which are fed by machining cells, is typical of the ship building industry.

49

Page 50: Analysis of the Production System at ABB Combustion

consisting of a shell, a top lid with a ventilation system, a bottom lid, and some type of inner

network that holds the fuel rods and keeps them separated within the canister. Material flow is

shown by solid lines, while information flow is shown by dashed lines.

KJjJHiH1H FinaL( \Machining Celts -0.A s rb

U

NetworkL Sub as sembly V ti t n0 10 ni Ventilati ni To Lid- 1

-- system TpSubassembyMa hini Cel U osrk1y(H

material

Top Lid and Bottom Shell machining occurs in informationLid machining occurs Heavy Manufacturing

in Heavy BuildingManufacturing

Building

Figure 4-7: Possible linked-cell layout for the production of canisters at ABB.

Within this system, kanban would be used for final assembly to notify each subassembly cell

when to produce another part, which, in turn, would signal the appropriate machining cells.

Material handling loops would need to be established to provide the proper amount of material to

the proper cells at a specified interval of time.

For the machining cells, new machining centers will need to be purchased and/or

machines currently in other buildings may need to be moved to the canister building. The

current system of machining some parts in the Light Manufacturing Building and transporting

them to the Heavy Manufacturing Building for final assembly is inefficient. The overall cost of

purchasing new machines (such as a small lathe or milling machine) will be less than the cost

associated with transporting parts back and forth between all three buildings over time. There is

50

Page 51: Analysis of the Production System at ABB Combustion

a catch to this layout, however. The two lids and the shell require machining on the large (2-3

story high) machining centers that are located in the heavy manufacturing building, located

adjacent to the canister building. These machines are extremely expensive and are, literally, part

of the building. Purchasing multiples of these machines is simply not practical. The canister

building will be build adjacent to the Heavy Manufacturing Building. Therefore, it is

recommended that the current machines in the Heavy Manufacturing Building remain the

machining centers used for these large canister components. However, it is important to try to

minimize the distance that the parts need to travel. That is why, as can be seen in Figure 4-7, the

subassembly areas for these large components of the canisters should be located as close as

possible to one of the pathways between the buildings. It is also important to note that these

pathways and doorways should be large enough to handle the passage of such components and

that overhead cranes, if needed, should be installed appropriately.

4.5.3 Sample Machining Cell

Functional requirements FR-T221, FR-T222, and FR-T223 all deal with the subsystems

of the entire system, whereas the previous section dealt with the system as a whole. FR-T221

states, "Ensure that automatic cycle time minimum takt time." Most of the operations at ABB

are manual, so this FR can't quite be dealt with yet. As ABB acquires more and more automated

machinery (which is recommended if new machines are purchased for the machining cells), then

this FR and corresponding DP can be addressed.

FR-T222 states "Ensure that manual cycle time takt time." This FR is extremely

important to a cellular system at ABB. DP-T222 calls for the "design of appropriate operator

work content/loops." To illustrate what this FR and DP mean, a sample machining cell will be

51

Page 52: Analysis of the Production System at ABB Combustion

discussed. To create this sample machining cell, various steps were taken. First, all parts of the

canister were compared to determine which machining centers were used to make the part and in

which order the machining centers were used. Each cluster of the machine-part matrix

represents a part family that can be produced in a cell. The sample machining cell described in

this thesis is shown by the shaded portion of the chart in Figure 4-8.

Part Number

Part# 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

TMM X X

AJV X X-Li X X X X X X

HBM X X X X I

COS1 XX X X X X X X XVM X X X

TMM2 X X XWS X -

BSW X _

VH3 X

Pch XCPM X XCOS2 X X X .X X X

TMM3 X x X X XSBE X X

TMM4 X XGHBM X X X X X

CRD X X XFRP X X X X X X

DOR X X X

Figure 4-8: Machine-part matrix used to establish part families.

To determine the takt time of the cell, the demand of the parts (quantity per canister x 50

canisters per year) must be determined.

Part Number Quantity/Canister

17 64

18 128

19 16

20 12

21 12

22 32

23 4

Total # of Parts 268

Table 4-1: Part demand in sample machining cell.

52

Page 53: Analysis of the Production System at ABB Combustion

Thus, the takt time of the cell is 15.96 minutes/part. This takt time means that the cycle

time of each operation within the cell must be less than or equal to 15.96 minutes/part. Table 4-2

lists the cycle times at each machine for each part in the sample cell.

Part # COS TMM WS BSW VH3 Pch CPM SBE

17 2.81 1.5 4.23 6.44 3.5 14.2

18 2 1.5 0.35 6.67

19 2 1.5 1.8 6.67

20 1.03 1.5 4.05

21 1.03 1.5

22 3.32 1.5 3.2

23 3.32 1.5 3.2

Table 4-2: Cycle times of each part at each machine in the sample cell.All times are in minutes.

Fortunately, the cycle times are all less than takt time already, so there is no need to

divide any operations into multiple tasks. To achieve leveled production, there should be a

proper mix of parts going through the cell. Before small run sizes of parts can be achieved,

however, set-up times must be drastically reduced [Shingo, 1989].

Figure 4-9 shows a possible layout for this sample machining cell. This cell produces the

main cross braces, as well, as the corner braces for the corner cell assemblies. Two of the

standardized work combination sheets for two of the parts that go through this cell are in

Appendix A. Similar charts were done for all parts in the cell. In this particular cell, not every

part goes to every work station. The numbering system in the figure refers to the order in which

the parts move to each machining center. Part number (P/N) 18 follows path a, P/N 19 follows

path b, P/N 17 follows path c, and P/N 20 follows path d. P/N 22 and P/N 23 exit the cell after

operation #3 and go to the sandblasting area. P/N 21 exits the cell and goes to the next

subassembly cell after operation #3. Possible work loops are shown.

53

Page 54: Analysis of the Production System at ABB Combustion

P/N 22,P/N 23 tosonoblost

All drenslons PN2 xtore a4,proxlnote. P/ 1e t

ColM 7

'_8q T

Punct4o sJ w

Insa.eu I a Sawhole J[~~J I~e7

Horionta NI

ext cl _ _ __ _ _ __ _ __ __Q_

6c-

Fiure 4-9 osbelyu o h ahnigcl htpoue at othe mancos rcs 9s ela hecre9el rcs

Tabe 43 sowstheimpoveent ofthesamle ellove th jo shp mtho.oprdcngtesmeprs.(l Istane anaieaeapoxmt.

Job Shop Machining Cell % ImprovementFloor space 3700 sq. ft. 1250 sq. ft. 66% reduction

Throughput time 4131 minutes 25 minutes 99% reduction(additional waiting

time possible)Number of workers minimum of 4 2 (+occasional 50% reduction

required inspector)

Travel distance of 580 ft. 105 ft. 82% reductionparts

Table 4-3: Improvements resulting from formation of sample machining cell.(All times and distances are approximate.)

Similar machining cells can be formed for other part families. Assembly cells must be

formed, also. Much of the assembly of the canisters is stationary. Because the canister

components are so large when they are sub-assembled, and especially final assembled, moving

54

Page 55: Analysis of the Production System at ABB Combustion

the assemblies from work station to work station would be inefficient and costly. This is where

ABB's system must combine a traditional "project shop" atmosphere with the improvements of a

cellular manufacturing system.

4.5.4 Inspection

In the above sample machining cell, note that the inspection stations are integrated into

the cell. The procedure of physically taking parts to a gauge room to inspect them is a waste of

time and material handling. There is no need to relocate parts simply to inspect their

dimensional features. In theory, there is also no need to call in special "inspectors" to do the job,

either. Unfortunately, this is where ABB runs into a need to compromise the TPS ideals.

ABB Newington must abide by the regulations set forth in "The American Society of

Mechanical Engineers Boiler and Pressure Vessel Code, Section III, Division 1, Nuclear Power

Plant Components" and/or "Section III, Division 3, Nuclear Power Plant Components

(Containment Systems and Transport Packagings for Spent Nuclear Fuel and High Level of

Radioactive Waste)." All components that fall into this category must be physically "Code

Stamped" with either N, N-TP, NA, NPT, or NPT-TP ASMIE Code Stamps. As stated in the

"Quality Assurance Program Requirements for Nuclear Facilities, ANSI/ASME NQA-1," Basic

Requirement 10: Inspection:

"Inspections required to verify conformance of an item oractivity to specified requirements shall be planned and executed.Characteristics to be inspected and inspection methods to beemployed shall be specified. Inspection results shall bedocumented. Inspection for acceptance shall be performed by

persons other than those who performed or directly supervised the

work being inspected." (emphasis added)

55

Page 56: Analysis of the Production System at ABB Combustion

This requirement is in direct conflict with the philosophies of the Toyota Production System,

where the ideal is to have 100% inspection performed by the workers, themselves.

Changing this practice involves more politics and economics than technology. To change

the code would require joining ASME, serving on the committee that forms the codes and

standards, and working from the inside to change them. ABB would have to form a cell,

knowing that using an external inspector is not the best way to go, and include the inspector in

the work loop of the cell to allow the inspector to see the difference between the job shop way of

inspection versus the lean way of inspection. To change the ASME Code would require the

cooperation of a qualified inspector who understands lean manufacturing. A preliminary code

would have to be drafted for inspection requirements in a lean manufacturing cell environment

(Black, 2000).

Another compromise between the TPS ideals and the ASME Code is possible. The

regulations require specially-qualified personnel to perform the final inspection and sign off that

the parts have been approved for use. The regulations also, however, allow for sample

inspection to be done, rather than requiring 100% inspection. This difference is where ABB can

take advantage of the regulations and create the compromise. 100% inspection can be performed

in the cells by the workers as stipulated by TPS, while a "qualified inspector" can roam between

a few cells to perform random sample inspection as required by the ASME regulations.

Inspection sometimes calls for non-destructive examination. These tests require more

time than simple dimensional inspection. Perhaps one or two of the inspectors on each shift

could be specifically designated to do all NDE tests, which would require these inspectors to

rotate between the cells that require such inspection. In any case, inspection should be

performed as part of the cell loop.

56

Page 57: Analysis of the Production System at ABB Combustion

4.6 Direct Labor

The next branch of the MSDD is the "Direct Labor" branch and is show in Figure 4-10.

IZILIZ-7--i771

FR-D3Eliminate operators' waiting onother operators

PM-D3Percentage of operators' timespent waiting on other operators

DP-D3Balanced work-loops

FR-D11 FR-D12Reduce time Enable worker tooperators spend on operate more thannon-value added one machine /tasks at each station station

PM-D11 PM-D12Percentage of Percentage ofoperators' time stations in a systemspent on non value- that each workeradding tasks while can operate

FR-D21Minimize wastedmotion of operatorsbetween stations

PM-D21Percentage ofoperators' timespent walkingbetween stations

FR-D22Minimize wastedmotion in operators'work preparation

PM-D22Percentage ofoperators' timespent on wastedmotions during workprparti~n

FR-D23Minimize wastedmotion in operators'work tasks

PM-D23Percentage ofoperators' timespent on wastedmotions during work

prepaationroltinawaiting at a station

DP-D11 DP-D12 DP-D21 DP-D22 DP-D23Machines & stations Workers trained to Machines / stations Standard tools / Ergonomic interfacedesigned to run operate multiple configured to reduce equipment located between the worker,autonomously stations walking distance at each station machine and fixture

(5S)

Figure 4-10: Level IV of the "Direct Labor" branch of the MSD Decomposition.

FR-D1 requires elimination of "operators' waiting on machines," which is accomplished

by "human-machine separation." Currently at ABB, most of the work is manual. Many of the

simple lathes, milling machines, etc. that are used are not automated. This ties the workers to the

machines for extended periods of time. If ABB could purchase automated machinery, operations

could be performed at the push of a button and allow the worker to move on to the next operation

57

Level IV FR-D1Eliminate operators' waiting onmachines

PM-D1Percentage of operators' timespent waiting on equipment

FR-D2Eliminate wasted motion ofoperators

PM-D2Percentage of operators' timespent on wasted motions

DP-D1Human -Machine separation

DP-D2Design of workstations / work-loops to facilitate operator tasks

Page 58: Analysis of the Production System at ABB Combustion

in the work loop. In order for this to be truly effective, though, the machines must also be

"autonomous," meaning that the machines can detect when a defect has occurred, and shut

themselves down until a worker can correct the source of the problem.

The next functional requirement is an area where ABB can easily take large strides

toward improving their system. FR-D2 states "Eliminate wasted motion of operators," which is

further broken down into three FRs. The first of which, FR-D21, states: "Minimize wasted

motion of operators between stations," which is accomplished by DP-D21: "Machines/stations

configured to reduce walking distance." The development of a linked-cellular system will do

exactly this. The walking distance to the next machine in the sequence will be 5 feet instead of

30 feet.

FR-D22 calls for minimizing "wasted motion in operators' work preparation." Having

all necessary tools/equipment at each workstation is the best way to accomplish this. As noted in

Figure 3-6, 36% of the worker time observed during a random 2-hour period was waste. Much

of this wasted time was due to the fact that workers had to walk across the shop to get the tools

that they needed. This retrieval time is a waste of resources. Each work station should contain

every tool and supply that the worker will need for the job. This could mean that there are

"mobile" tools/supplies that move around to various stations depending on the type of work that

is to occur at each station on that particular day. Such a system would mean that some tools that

are only used occasionally could be traded between stations, rather than having to supply each

station with every tool only to have some of them sit there, not being used, for extended periods

of time. Any tools or supplies that are used regularly at a station should be kept there

permanently so that the worker always has it on hand whenever he needs it.

58

Page 59: Analysis of the Production System at ABB Combustion

The third FR in this sub-branch calls for minimizing "wasted motion in operators' work

tasks." The corresponding DP is the "ergonomic interface between the worker, machine, and

fixture." This means easy loading and unloading of parts and easy use of fixtures and jigs, which

were common improvements already being made during this internship.

The remaining segment of the Direct Labor branch requires "balanced work loops" as a

way to "eliminate operators' waiting on other operators." This functional requirement is an issue

that will have to be worked out in greater detail when the cells are actually formed.

4.7 Indirect Labor

Figure 4-11 shows the "Indirect Labor" branch of the MSDD. Both FRs and DPs of this

branch deal with decreasing the amount of indirect labor involved in running the production

system. This branch of the tree is a basic goal of any company and should always be improved

upon whenever possible.

Level IV FR-11 FR-12Improve effectiveness of Eliminate informationproduction managers disruptions

PM-11 PM-12Amount of indirect labor Amount of indirect laborrequired to manage system required to schedule system

DP-11 DP-12Self directed work teams Seamless information flow(horizontal organization) (visual factory)

Figure 4-11: Level IV of the "Indirect Labor" branch of the MSD Decomposition.

59

Page 60: Analysis of the Production System at ABB Combustion

5.0 CONCLUDING COMMENTS

5.1 Summary

By making the transition from job shop to lean manufacturing, ABB will see significant

improvements in their production system. If the improvements suggested in this thesis are

implemented, ABB will see a reduction in the floor space consumed, reduced scrap and re-work

levels, decreased production costs, decreased throughput time, and increased quality. The

production system will become more structured and systematic, which will provide a better

atmosphere for making continuous improvements.

5.2 Obstacles

The major obstacles that ABB will encounter in making the transition to the "lean"

system design are resistance to change, the challenge of mixing cellular manufacturing with

project shop manufacturing, and the quality regulations set forth in the ASME Code. The first

two obstacles can be dealt with over time and with some patience and persistence. The key to

overcoming resistance to change is to make sure that all change is a team effort. The transition

cannot be made by one or two extremely motivated individuals. Everyone, from upper

management on through the machine operators, must be involved with making decisions and

implementing change. Hopefully, as changes are made, people will see the results and be

encouraged to continue.

Dealing with the mix of cellular and project shop manufacturing will be a challenge

because there aren't many examples in existence to learn from. Much of the literature on "lean"

manufacturing and implementation of the Toyota Production System describe fast-paced, high

volume production, such as the automobile industry, where parts are in continuous motion. This

60

Page 61: Analysis of the Production System at ABB Combustion

is obviously not the case at ABB. Fortunately, some companies in the aerospace and ship

building industries have begun implementing cellular manufacturing systems that require some

parts/assemblies to remain stationary.

Working the ASME code regulations into a cellular manufacturing system, however, is

going to be very difficult. The Code prohibits self inspection and successive inspection since

inspection cannot be done by anyone involved in making the part, which means that separate

inspectors must be involved.

Quality in the nuclear industry takes on a slightly different meaning than most other

industries. Even the smallest defects can have devastating effects. Thus, it is understandable

that the nuclear industry is extra cautious about inspection. However, being cautious does not

mean that there must be specially designated inspectors. Dimensional inspection can be done

just as well by a worker in the cell as it can be done by a special inspector. If there is concern

that a worker may compromise judgement while inspecting parts that he, personally, made, then

successive inspection should be used. Of course, this means that the workers will have to be

properly trained to know exactly how to use the measuring devices, as well as how to read

drawings properly and understand tolerances.

When it comes to inspecting welds and performing NDE tests, however, specially trained

inspectors may still be needed. To train each worker to perform each NDE test would be more

time consuming and costly than employing a few specially trained inspectors.

5.3 The Next Steps

The very first step in a lean implementation process is forming a team of people, ranging

from top-level management, to engineers, to shop workers, who will be the heart and soul of the

61

Page 62: Analysis of the Production System at ABB Combustion

changing process. At ABB-CE Newington Operations, that team would involve a wide variety

of people including the general manager, project manager, plant manager, union steward,

manufacturing engineer(s), design engineer, maintenance foreman, quality engineering, NDE

level III supervisor, production control, and shop workers.

Because Newington is so tight-staffed, it would be most beneficial if this team designated

a few people as the core of the group, the central cluster that would dedicate much of their time

to making this cellular implementation work and constantly working to improve the current

system. The rest of the larger team must also be involved in terms of keeping up to date on the

progress being made, giving their input whenever something new is implemented or whenever

they have an idea for improvement, and as support for the central core. Without the support and

backing of the entire team, the cellular implementation will not be successful.

Another step that needs to be taken early on is to improve the accounting system at ABB.

Having an accurate count of exactly how much time each operation takes is vital to making

improvements. Without this information, ABB won't know which operations are holding up

production and delaying throughput time.

First of all, the MPSs need to be more detailed and each process needs to be distinctly

separated. Currently, multiples tasks are included in the same "sequence" on the MPS, which

means that the times to perform each separate task are lumped into one total amount on the

accounting sheet. Another problem is that times for each sequence of the MPS often get

jumbled. For example, suppose a worker spends 6 hours of his day on one particular sequence

but then works on the next sequence for the last 45 minutes of his shift. Usually, the worker will

simply put all 6 hours 45 minutes down as the first sequence, rather than distinctly separating the

last 45 minutes. This results in inaccurate records of time requirements. Also, if a machine

62

Page 63: Analysis of the Production System at ABB Combustion

breaks down, the downtime is recorded as time for the sequence that was currently being worked

on at the time of the breakdown. Thus, something that only takes 4 hours to complete, may

actually say that it took 8 hours to complete, when 4 hours of that time was spent repairing a

machine. Similarly, time spent retrieving tools and supplies is recorded as time spent on the

particular machining/welding/assembly sequence. All of the above misrepresentations of time

snowball into one large time chunk for each sequence that no one can completely explain. As a

result, the accounting records are of no use to anyone in the future. The records can't be used to

improve time estimates for bidding purposes, or as a means to pinpoint true critical paths and

improve processes.

In order for a truly smooth cellular manufacturing system to be designed and worked out,

the accounting system (time recording system) needs to be revamped. Accurate time logging

needs to be done for each sequence of each MPS, where each sequence consists of one operation.

Activities such as machine breakdowns, tool searching, lunch breaks need to be clearly

differentiated from actual production.

As mentioned in Chapter 4, ABB also needs to begin keeping track of the amount of

scrap produced, the amount of work-in-process, the amount of inventory, and the amount of

rework done. These performance measures will help provide motivation for making changes and

will also help gauge the level of improvement over time.

5.4 Final Comments

The main point of this thesis was to show how the MSD Decomposition, based on the

philosophies of the Toyota Production System, can be applied to the current production system at

ABB in order to make improvements to the system as a whole, while coping with the constraints

63

Page 64: Analysis of the Production System at ABB Combustion

and speed bumps of the nuclear industry. The recommendations put forth in this thesis are only

starting points. Continuous improvement efforts must be made through kaizen teams.

This thesis has discussed each branch of the MSD Decomposition separately as related to

the production system at ABB. Certain FRs and DPs were emphasized over others because of

their relevance to the current system at ABB, though every single one is important to the system

as a whole. Making the transition to lean isn't easy or cheap, but is worth the investment in the

end when the money that the new system is saving over the old system begins to add up and

customers are more satisfied because they're receiving better quality products faster than before.

64

Page 65: Analysis of the Production System at ABB Combustion

REFERENCES

American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section III,Division 1, Nuclear Power Plant Components.

American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section III,Division 3, Nuclear Power Plant Components (Containment Systems and TransportPackagings for Spent Nuclear Fuel and High Level of Radioactive Waste.

Black, J.T., The Design of the Factory with a Future. McGraw-Hill, Inc., New York, NY,1991.

Cochran, David S., "2.82/2.812 Design and Control of Manufacturing Systems Course Notes",Massachusetts Institute of Technology, Cambridge, MA, 1999.

Cochran, David S. and Paulo C. Lima, "Manufacturing System Design Decomposition, version5.1". Production System Design Laboratory, Massachusetts Institute of Technology,2000.

DeVor, Richard, Tsong-how Chang, and John W. Sutherland, Statistical Quality Design andControl: Contemporary Concepts and Methods. Prentice Hall, Upper Saddle River,NJ, 1992.

Interviews with Richard Brillon, Gerry Dopp, Ken Fortin, Dave Kelley, Richard Talbot, RobertThompson, Scott Vallimont, and Carl Waterhouse, all of ABB Combustion EngineeringNuclear Power Newington Operations.

Interview (via telephone) with Dr. J.T. Black, June 2, 2000.

Ohno, Taiichi, Toyota Production System: Beyond Large-Scale Production. ProductivityPress, Cambridge, MA, 1988.

Shingo, Shigeo, A Study of the Toyota Production System From an Industrial EngineeringViewpoint. Productivity Press, Portland, OR, 1989.

Storch, Richard Lee, Cohn P. Hammon, Howard M. Bunch, and Richard C. Moore, ShipProduction, Second Edition. The Society of Naval Architects and Marine Engineers,Jersey City, NJ, 1995.

Suh, Nam P., The Principles of Design. Oxford University Press, New York, NY, 1990.

65

Page 66: Analysis of the Production System at ABB Combustion

Appendix A

The following standardized work combination sheets are for the tube steel arms in the sample machining cell presented in

Chapter 4. Similar sheets were done for all parts going through the cell. All operations are completely manual.

Page 1 of 1 pages

Part no. 17 Date: Manual operation -

Standard OperationsRoutine Sheet Machine Processing - - - - - -

Part name 5x2 Tube Steel Arm Main Takt Time: 15.96Cell # Cross min. Walking

Assy

Work Work content Time (seconds) Operations Time (minutes)

sequence Manual Machine Walk 5 10 15 20 25

02 Cut to length on cut off saw I0s 120s 3s -

04 Inspect length 30s

06 Mark P/N, S/N 20s 90s 2s -

08 Deburr & clean ID 60s 4s

10 Punch holes 10s 16s 3s

12 Inspect holes 60s 5s

20 Deburr all edges (after milling) 360s 4s

14 Mill chamfers 30s 120s

16 Mill weld preps 30s 240s 3s

18 Inspect chamfers & weld preps 240s 2s

TOTAL 850s 586s 26s

1462s (24.4 min) Takt lime

66

Page 67: Analysis of the Production System at ABB Combustion

Page 1 of 1 pages

Part no. 19 Date: Manual operation

Standard OperationsRoutine Sheet ______________________Machine

Processing- - --- -

Part name 2x2 Tube Steel Arm Main Takt Time: 15.96

Cell # Cross min. Walking

Assy

Work Work content Time (seconds) Operations Time (minutes)

sequence Manual Machine Walk 5 10 15 20 25

02 Cut to length on cut off saw I0s 120s 3s -

04 Inspect length 30s

06 Mark P/N, S/N

08 Deburr & clean ID 60s 2s

10 Mill holes 20s 2O0s 3s

12 Inspect holes 60s 5s

20 Deburr all edges (after milling) 360s 4s

14 Mill chamfers 30s 120s

16 Mill weld preps 30s 240s 3s

18 Inspect chamfers & weld preps 240s 2s

TOTAL 860s 670s 24s

1 ~CA. ~ A ...... T kdt Ti,1554s k2j.9 11n.)

67

a me,