williamsburg treatment plant - hrsd · williamsburg treatment plant j cit county offers much to...
Post on 16-Aug-2020
1 Views
Preview:
TRANSCRIPT
Williamsburg Treatment Plant
James City County offers much to area residents and visitors including opportunities to enjoy some of the best outdoor activities in the region.
Newport News City Center at Oyster Point is a business district thatfeatures retail shops, restaurants and offices as well as residential spacecentered around the fountain in the heart of the development.
Williamsburg Farmers Market, voted one of America's FavoriteMarkets, attracts residents and visitors alike to Merchants Square tobuy locally grown produce from local farmers.
York County Yorktown is most remembered as the site where BritishGeneral Lord Cornwallis surrendered to American and French forcesunder the command of General George Washington, bringing an endto the last major battle of the American Revolutionary War. But evenbefore the struggle for independence, the town was a bustling andprosperous 18th century seaport, having been established by the1691 Act of Ports. Yorktown also witnessed major Civil War activity.Its fortifications held off a Union army attack during the PeninsulaCampaign of 1862.
0 10,000 20,000 30,000 40,0005,000Feet
3Q±Williamsburg
WB012200
WB012600
WB012500
ÜCIP Location
Service Area
Legend
Treatment Plant Projects
Williamsburg Treatment Plant Service AreaCIP Projects
GN016342GN016350GN016351WB012400
WB012700WB012900
WilliamsburgTreatment Plant3Q±
_ CIP PumpStation Point
±
± CIP Interceptor LineCIP Abandonment
CIP Interceptor Point_̂
HRSD Interceptor Force MainHRSD Interceptor Gravity Main
3Q HRSD Treatment Plant
3SRP HRSD Pressure Reducing Station
3PS HRSD Pump Station
Treatment Plant Service Area
WB01
2200
DEPUE DR
LONGHILL RD
ASHB
URY
RD
FOSTER RD
TYLER BROOKS DR
LEWIS ROBERT LN
JOHN
WYT
HE PL
GOVERNOR BERKELEY RD
JOHN PINCKNEY LN
CARL
TON
CT
THOMAS NELSON LN
DOWNING CT
WB012200North Trunk Force Main Part BReplacement
CIP Location
Williamsburg
Legend
HRSD Interceptor Force MainHRSD Interceptor Gravity Main
3Q HRSD Treatment Plant
3SRP HRSD Pressure Reducing Station
3PS HRSD Pump Station
WB012200
/0 250 500 750 1,000125
Feet
Project Area
±
± Project Interceptor Line!]̂ Project Interceptor Point!]̂ Project Pump Station Point
CIP Project Area
_̂ CIP Interceptor Point_ CIP Pump Station Point
CIP Abandonment
±
± CIP Interceptor Line
North Trunk Force Main Part B Replacement PR_WB012200
System: WilliamsburgType: Pipelines
Driver Category: I&I Abatement-Rehabilitation PlanProject Status: ConstructionRegulatory: Rehab Plan Phase One
PROGRAM CASH FLOW PROJECTION ($,000)
Prog CostExp to
Previous Year FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29
$1,808 $1,333 $475 $0 $0 $0 $0 $0 $0 $0 $0 $0
PROJECT DESCRIPTION
This project is to replace approximately 1,700 linear feet (LF) of 24-inch Prestressed Concrete Cylinder Pipe (PCCP) along NF-001. The pipe to be addressed is located between existing branch valve W5016-2 and main line valve W5018A-4.
PROJECT JUSTIFICATION
Condition assessment activities indicate that these assets present a material risk of failure due to physical condition defects.
FUNDING TYPE CONTACTS
Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-InterceptorsContacts-Dept Contacts: Jeremiah BurfordContacts-Managing Dept: Engineering
PROPOSED SCHEDULE START DATE COST ESTIMATE
PrePlanning 09/01/2015PER 10/01/2016Design Delay 02/01/2017Design 02/01/2017Bid Delay 11/01/2018PreConstruction 11/01/2018Construction 02/01/2019Closeout 09/01/2019
Cost Estimate Class: Class 1 PrePlanning $0PER $21,629Design $132,943PreConstruction $3,000Construction $1,645,419Closeout $5,000 Est. Program Cost $1,807,991Contingency Budget $180,000
Est. Project Costs $1,987,991
WB012400WB012400
WB012900
WB012400Williamsburg Treatment PlantGenerator and SwitchgearReplacement
CIP Location
Williamsburg
Legend
HRSD Interceptor Force MainHRSD Interceptor Gravity Main
3Q HRSD Treatment Plant
3SRP HRSD Pressure Reducing Station
3PS HRSD Pump Station
WB012400
/0 130 260 390 52065
Feet
Project Area
±
± Project Interceptor Line!]̂ Project Interceptor Point!]̂ Project Pump Station Point
CIP Project Area
_̂ CIP Interceptor Point_ CIP Pump Station Point
CIP Abandonment
±
± CIP Interceptor Line
Williamsburg Treatment Plant Generator and SwitchgearReplacement
PR_WB012400
System: WilliamsburgType: Electrical
Driver Category: Aging Infrastructure/RehabilitationProject Status: DesignRegulatory: None
PROGRAM CASH FLOW PROJECTION ($,000)
Prog CostExp to
Previous Year FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29
$16,098 $905 $6,216 $8,277 $700 $0 $0 $0 $0 $0 $0 $0
PROJECT DESCRIPTION
The project is to design and construct needed replacement of the treatment plant main switchgear, generator, generator switchgear, controls and appurtenances. The replacement of the switchgear will require the construction of a new switchgear building. The project also includes the replacement of three sub-stations (transformer, switch, distribution panel) and electrical provisions to accommodate the future SWIFT Facility.
PROJECT JUSTIFICATION
This project will replace 43 year old switchgear and transformers nearing the end of its useful life. The switchgear is starting to become unreliable, switchgear breakers have failed to open and experienced nuisance tripping, and many of the component parts are difficult to obtain. An independent engineering evaluation has concluded a new building is required to house the switchgear due to the limited available space in the existing building and the need to maintain plant operations during construction. The SWIFT project requires additional generator capacity thus making it appropriate to replace the generator at this time.
FUNDING TYPE CONTACTS
Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-TreatmentContacts-Dept Contacts: Eddie AbisaabContacts-Managing Dept: Engineering
PROPOSED SCHEDULE START DATE COST ESTIMATE
PrePlanning 10/01/2017PER 07/01/2018Design Delay 07/01/2018Design 07/01/2018Bid Delay 06/01/2019PreConstruction 06/01/2019Construction 10/01/2019Closeout 08/01/2021
Cost Estimate Class: Class 3 PrePlanning $74,681PER $0Design $828,240PreConstruction $10,000Construction $15,175,234Closeout $10,000 Est. Program Cost $16,098,155Contingency Budget $1,500,000
Est. Project Costs $17,598,155
WB012500LODGE ROAD
HUMELSINE PKWY
HUMELSINE PKWYLODGE RD
BLUFFS CIR
PAYNES RD
WB012500Lodge Road Pump Station Upgrades
CIP Location
York County
Legend
HRSD Interceptor Force MainHRSD Interceptor Gravity Main
3Q HRSD Treatment Plant
3SRP HRSD Pressure Reducing Station
3PS HRSD Pump Station
WB012500
/0 110 220 330 44055
Feet
Project Area
±
± Project Interceptor Line!]̂ Project Interceptor Point!]̂ Project Pump Station Point
CIP Project Area
_̂ CIP Interceptor Point_ CIP Pump Station Point
CIP Abandonment
±
± CIP Interceptor Line
Lodge Road Pump Station Upgrades PR_WB012500
System: WilliamsburgType: Pump Stations
Driver Category: Capacity ImprovementsProject Status: ProposedRegulatory: None
PROGRAM CASH FLOW PROJECTION ($,000)
Prog CostExp to
Previous Year FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29
$1,516 $0 $8 $156 $528 $824 $0 $0 $0 $0 $0 $0
PROJECT DESCRIPTION
The project will upgrade the existing Lodge Road Pump Station (PS) including all station pumps, controls, pipe, valves, and electrical infrastructure.
PROJECT JUSTIFICATION
This project will address needed capacity improvements within York County in an area that has current wet weather capacity challenges and newly proposed additional development flows. Lodge Road PS requires pumping upgrades to provide additional capacity. These improvements will require an electrical service upgrade and will drive replacement of the pumps, electrical equipment, generator, and controls. Lodge Road PS receives flow from Rolling Hills PS, several York County Pump Stations, and a local collection system. During wet weather periods, the upstream collection system has experienced Sanitary Sewer Overflows (SSOs) related to pumping capacity. An interconnect was installed by North Shore Interceptors to allow Rolling Hills PS to discharge into the Lodge Road PS. The activation of the Route 199 Interim Pressure Reducing Station (PRS) along with the development projections in the service area require capacity enhancement due to increased flow and discharge pressure.
FUNDING TYPE CONTACTS
Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-InterceptorsContacts-Dept Contacts: Sam McAdooContacts-Managing Dept: Engineering
PROPOSED SCHEDULE START DATE COST ESTIMATE
PrePlanning 01/01/2020PER 06/01/2020Design Delay 11/01/2020Design 11/01/2020Bid Delay 09/01/2021PreConstruction 09/01/2021Construction 01/01/2022Closeout 05/01/2023
Cost Estimate Class: Class 5 PrePlanning $0PER $39,303Design $155,434PreConstruction $5,552Construction $1,310,092Closeout $5,552 Est. Program Cost $1,515,932Contingency Budget $327,524
Est. Project Costs $1,843,456
WB012600KINGSMILL
WB012600Kingsmill Pump Station PipingReplacement and Wet WellRehabilitation
CIP Location
Williamsburg
Legend
HRSD Interceptor Force MainHRSD Interceptor Gravity Main
3Q HRSD Treatment Plant
3SRP HRSD Pressure Reducing Station
3PS HRSD Pump Station
WB012600
/0 110 220 330 44055
Feet
Project Area
±
± Project Interceptor Line!]̂ Project Interceptor Point!]̂ Project Pump Station Point
CIP Project Area
_̂ CIP Interceptor Point_ CIP Pump Station Point
CIP Abandonment
±
± CIP Interceptor Line
Kingsmill PS Piping Replacement and Wet Well Rehabilitation
PR_WB012600
System: WilliamsburgType: Pump Stations
Driver Category: Aging Infrastructure/RehabilitationProject Status: PERRegulatory: None
PROGRAM CASH FLOW PROJECTION ($,000)
Prog CostExp to
Previous Year FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29
$2,664 $243 $1,453 $967 $0 $0 $0 $0 $0 $0 $0 $0
PROJECT DESCRIPTION
This project involves the rehabilitation of the Kingsmill Pump Station wet well and will require complete bypass of the pump station. Additionally, yard piping, interior and exterior/buried valves, and a portion of the interceptor force main upstream and downstream of the pump station will be replaced as part of this project.
PROJECT JUSTIFICATION
The existing wet well at the Kingsmill Pump Station is showing signs of significant deterioration, evident by the exposed aggregate documented during wet well inspections. The wet well is also not configured to easily allow for bypass pumping, as there is no slide gate or permanently-mounted suction line currently installed. Inthe dry well, pump suction valves have been showing signs of significant wear. Recently, one of these valves was replaced because it was determined to be inoperable. Outside the pump station, valves and force main piping need replacement. Three of the eight diversion/isolation valves are inoperable and another three valves are horizontally installed gate valves – valves that have proven to fail prematurely. The reinforced concrete force main in the area where the pump station connects is unnecessarily deep, adding safety risk and potential for delayed repairs in the event of a pipe failure. Since the early 1970's when this pipe was originally installed, 15 to 20 feet of fill has been placed on top of this line, adding a static load onto the pipeline that has already resulted in one failure.
FUNDING TYPE CONTACTS
Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-InterceptorsContacts-Dept Contacts: Matt PoeContacts-Managing Dept: Engineering
PROPOSED SCHEDULE START DATE COST ESTIMATE
PrePlanning 07/01/2018PER 11/01/2018Design Delay 03/01/2019Design 03/01/2019Bid Delay 10/01/2019PreConstruction 10/01/2019Construction 12/01/2019Closeout 12/01/2020
Cost Estimate Class: Class 4 PrePlanning $0PER $99,400Design $252,000PreConstruction $5,000Construction $2,297,225Closeout $10,000 Est. Program Cost $2,663,625Contingency Budget $459,445
Est. Project Costs $3,123,070
WB012700
WB012900WB012400WB012400
WB012700Williamsburg Treatment PlantAdvanced Nutrient ReductionImprovements Phase I
CIP Location
Williamsburg
Legend
HRSD Interceptor Force MainHRSD Interceptor Gravity Main
3Q HRSD Treatment Plant
3SRP HRSD Pressure Reducing Station
3PS HRSD Pump Station
WB012700
/0 110 220 330 44055
Feet
Project Area
±
± Project Interceptor Line!]̂ Project Interceptor Point!]̂ Project Pump Station Point
CIP Project Area
_̂ CIP Interceptor Point_ CIP Pump Station Point
CIP Abandonment
±
± CIP Interceptor Line
WBTP Advanced Nutrient Reduction Improvements Ph I PR_WB012700
System: WilliamsburgType: Nutrient Reduction
Driver Category: Performance UpgradesProject Status: ProposedRegulatory: Integrated Plan-SWIFT
PROGRAM CASH FLOW PROJECTION ($,000)
Prog CostExp to
Previous Year FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29
$450 $141 $309 $0 $0 $0 $0 $0 $0 $0 $0 $0
PROJECT DESCRIPTION
This project is for the design and construction of improvements to the secondary treatment process at the Williamsburg Treatment Plant. Based on performance of thecurrent secondary treatment configuration and recent process modeling, the initial improvements will include installation of ammonia based aeration control, nitrate-based recycle flow control, equipment to release excess air, and all required appurtenances. This initial effort is intended to significantly delay, and may potentially eliminate, the need for design and construction of a supplemental carbon addition system, which was the basis for the original total project estimate.
PROJECT JUSTIFICATION
Advanced secondary treatment improvements, including nutrient reduction measures, will be required to provide stable source water quality that meets the influent requirements of the full scale SWIFT facility at Williamsburg Treatment Plant.
FUNDING TYPE CONTACTS
Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-TreatmentContacts-Dept Contacts: Lauren ZuravnskyContacts-Managing Dept: Engineering
PROPOSED SCHEDULE START DATE COST ESTIMATE
PrePlanning 01/01/2019PER 01/01/2019Design Delay 01/01/2019Design 01/01/2019Bid Delay 01/01/2019PreConstruction 01/01/2019Construction 01/01/2019Closeout 06/01/2020
Cost Estimate Class: Class 1 PrePlanning $0PER $0Design $0PreConstruction $0Construction $450,000Closeout $0 Est. Program Cost $450,000Contingency Budget $8,136,000
Est. Project Costs $8,586,000
WB012900WB012400WB012400
WB012900Williamsburg Treatment PlantAdministration Building Renovation
CIP Location
Williamsburg
Legend
HRSD Interceptor Force MainHRSD Interceptor Gravity Main
3Q HRSD Treatment Plant
3SRP HRSD Pressure Reducing Station
3PS HRSD Pump Station
WB012900
/0 125 250 375 50062.5
Feet
Project Area
±
± Project Interceptor Line!]̂ Project Interceptor Point!]̂ Project Pump Station Point
CIP Project Area
_̂ CIP Interceptor Point_ CIP Pump Station Point
CIP Abandonment
±
± CIP Interceptor Line
Williamsburg Treatment Plant Administration Building Renovation
PR_WB012900
System: WilliamsburgType: Facilities, Buildings and Capital Equipment
Driver Category: Aging Infrastructure/RehabilitationProject Status: ProposedRegulatory: None
PROGRAM CASH FLOW PROJECTION ($,000)
Prog CostExp to
Previous Year FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29
$1,120 $0 $25 $399 $696 $0 $0 $0 $0 $0 $0 $0
PROJECT DESCRIPTION
This project is to renovate the existing 1960s Administration Building at the Williamsburg Treatment Plant.
PROJECT JUSTIFICATION
This project will replace the 1960s toilets, sinks, showers and lockers and allow for more space in both the men's and women's restrooms; provide much needed office space for plant staff; refurbish the conference room; and create additional work shop space. This project will also provide for an operations control room in the hurricane category 2 rated administration building. The existing operations control room is in the incinerator building which must be abandoned during tropical storm force winds.
FUNDING TYPE CONTACTS
Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-TreatmentContacts-Dept Contacts: Robert RutherfordContacts-Managing Dept: Engineering
PROPOSED SCHEDULE START DATE COST ESTIMATE
PrePlanning 01/01/2020PER 02/01/2020Design Delay 05/01/2020Design 06/01/2020Bid Delay 12/01/2020PreConstruction 02/01/2021Construction 04/01/2021Closeout 01/01/2022
Cost Estimate Class: Class 5 PrePlanning $0PER $10,000Design $90,000PreConstruction $22,500Construction $904,100Closeout $93,000 Est. Program Cost $1,119,600Contingency Budget $200,000
Est. Project Costs $1,319,600