Unit 5 AssignmentProject Changes
Charles W. Jansen, IIKaplan University
IT499-01 Bachelors Capstone in Information TechnologyInstructor: Allison Selby
June 14, 2012
(Fictitious network consultant)
6838 Old Banyan WayNaples, FL 34109(239) 273-8604
chuckamania@chuckamania.net
Project Client (fictitious)
Patch Productions1066 Big Picture BlvdNaples, FL 34104(239) 555-1066
Current company profileCompany Produces:• Video Games• Commercials• DocumentariesVideo Restoration & Transfer Service• 70mm• 35mm• 16mm• 8mm
• Currently employs several hundred people
• Will add over one hundred new hires
Project Goal Add new department for developing theatrical film production offices. Chuckamania Productions will install network equipment in the building. Equipment will include:
Routers Switches Wiring Closet New IP addressing scheme
Servers, computers and printers will be provided by separate firms. IPS and Firewall services will be provided by Corero Network Security
ChangesChange Order One
Reduce Budget by 10%Possible Solutions
Reduce Staffing Reduce Functionality Modify Schedule
Change Order TwoLoss of Project Team MemberPossible Solutions
Staff picks up extra tasks Bring in new member
Change One: Reduced BudgetBudget reduced by 10%
Reduce the budget for the switches. Replace the Cisco Catalyst WS-C3750X-48T-L switches Use the Cisco Catalyst C2960S-48TS-L switches
Effect Will lose some advanced capabilities
Power over Ethernet Reduced QoS Lose 10GB uplinks between switches
Maintains Gigabit Ethernet capabilities Scalability IP Phone capable (will require AC power to be supplied by outlet to each IP
Phone Adjusted team costs
Project Manager hours adjusted – reduced time for meetings
Change TwoLoss of team member
Gloria Howard has been assigned as Project Manager to another project
Replaced by another of Chuckamania Productions fine staffRaiko Nakamura
CCNA certified Specialized field setup Two years with company Same rate of pay
Net hours reducedMinor savings
New Switch SpecificationsCisco Catalyst Switch 2960 S-48TS-L
48 Ethernet Ports10/100/1000 Ports4 One Gigabit Ethernet SFP Ports (Modular) uplinksSmart operationsAutoQoSVLAN
Separate VoIP VLAN VTP (VLAN Trunking Protocol)
Advanced Intelligent Network Management ToolsBorderless securityThreat defense
Old BudgetResource Standar
d RateHours/
QtyUOM Extended
CostChuck Jansen II $50.00 307 Hourly $15,350.00Herman Pinder $20.00 212 Hourly $4,240.00Gloria Howard $20.00 246 Hourly $4,920.00Pepé Yamichi $20.00 196 Hourly $3,920.00Haruko Jones $20.00 236 Hourly $4,720.00Cisco Router (PC Rush, 2012)
$1,200.00
1 Each $1,200.00
Cisco HSWIC (PC Rush, 2012)
$550.00 1 Each $550.00
Cisco Switches (PC Rush, 2012)
$5,500.00
4 Each $22,000.00
APC UPS (PC Rush, 2012) $1,140.00
6 Each $6840.00
CAT 6 Ethernet Cables (50ct) (C2G, 2012)
$410.00 6 Bundle $2,460.00
Total Budget $66,650.00 Add 10% Reserve $6,665.00Total with Reserve $73,315.00
New BudgetResource Standar
d RateHours/
QtyUOM Extended
CostChuck Jansen II $50.00 316 Hourly $15,250.00Herman Pinder $20.00 212 Hourly $4,240.00Gloria Howard $20.00 84 Hourly $1,880.00Pepé Yamichi $20.00 196 Hourly $3,920.00Haruko Jones $20.00 236 Hourly $4,720.00Raiko Nakamura $20.00 112 Hourly $2,240.00Cisco Router (PC Rush, 2012)
$1,200.00
1 Each $1,200.00
Cisco HSWIC (PC Rush, 2012)
$550.00 1 Each $550.00
Cisco Switches (PC Rush, 2012)
$3,500.00
4 Each $14,000.00
Cisco MGBT1 SFP (Cisco, 2012)
$130.00 4 Each $520.00
APC UPS (PC Rush, 2012) $1,140.00
6 Each $6840.00
CAT 6 Ethernet Cables (50ct) (C2G, 2012)
$410.00 6 Bundle $2,460.00
Total Budget $57,820.00 Add 15% Reserve $5,782.00Total with Reserve $63,602.00
Effect on ScheduleOrdering of Material
No effectChange made before equipment was orderedConfiguration for switches not started yet
ScheduleSchedule stays on deadlineProject manager C W Jansen II picks up slack in work
Reduce time for meetings with Patch Productions Will be more active in configuration and installation This will reduce cost slightly
New team member Raiko Nakamura will only be scheduled where necessary Net cost slightly reduced Takes over some WBS tasks
ProgressCabling
Inspected and certifiedCat 6 UTP Ethernet cable with RJ-45 connectorsPlenum cable exists in crawl spacesPatch panel numbering
Matches in All floors building 2 and 3 Floors 1-3 in building 1
Does not match in Fourth floor building 1 This will be rectified during wiring closet management
portion of installation
SummaryChanges will effect feature set of switches. Switches will
still be functional. Uplinks (links between switches or switches and router) will be reduced from 10GB to 1GB. Switches will perform required tasks and still provide scalability at reduced cost.
Replacement of team member reduces overall cost as new member will not be available until after configurations are finished. Project manager will pick up this slack without increasing time worked. This means a change from a primarily supervisory role to that of a participatory role.
Project manager hours decreased by reducing meeting times with client as per conversation with Natalie Kalmus and Cecil B. Miller.
References APC by Schneider Electric. (2012). APC Smart-UPS 2000VA RM 2U LCD 120V. Retrieved June
9, 2012, from American Power Conversion: http://www.apc.com/products/resource/include/techspec_index.cfm?base_sku=SMT2200RM2U&total_watts=50
C2G. (2012). 5 ft. Cat6 550 MHz Snagless Patch Cable - Blue 50pk. Retrieved June 9, 2012, from Cables 2 Go: http://www.cablestogo.com/product.asp?cat%5Fid=3521&sku=31372
Cisco. (2012). Gigabit Ethernet 1000 Base-T Mini-GBIC SFP Transceiver . Retrieved June 14, 2012, from Cisco: http://cisco.links.channelintelligence.com/pages/prices.asp?sSKU=MGBT1&nRGID=2422
Cisco Systems. (2012). Cisco 2901 Integrated Services Router. Retrieved June 12, 2012, from Cisco: http://www.cisco.com/en/US/products/ps10539/index.html
Cisco Systems. (2012). Cisco Catalyst WS-C2960S-48TS-L Series Switches (Data Sheet. Retrieved June 10, 2012, from Cisco: http://www.cisco.com/en/US/prod/collateral/switches/ps5718/ps6406/product_data_sheet0900aecd80322c0c.html
PC Rush. (2012). Cisco 2901 ISR; Cisco Catalyst Switch; Cisco HSWIC; APC UPS. Retrieved June 12, 2012, from PC Rush: http://www.pcrush.com
PC Rush. (2012). Cisco High-Speed WAN Interface Card. Retrieved June 11, 2012, from PC Rush: http://www.pcrush.com/product/Network-and-Interface-Modules/767067/Cisco-Ehwic-1-Port-Dual-Mode-SFP-100M-1G-OR-GBE-10M-100M-1G-for-3900
QuestionsAddress questions to Chuck Jansen II chuckamania@chuckamania.net