SADARA Polyethylene Project PC-0251

Facts Project DescriptionCivil, Structural & Architectural Works for a new Polyethylene Plant Train 02 and 04 inSADARA Refinery in Jubail.Major Volume of works are 21,500 m3 of Concrete, 1,910 tons of Rebar, 15,448 m3 ofExcavation, 86,600 m3 of Filling.

City/Country

Jubail / Saudi Arabia

Client

Saudi Aramco & DOW Chemical (SADARA), -

Contract Value

€ 18,86 Mio.

Construction Period

02/2013 - 07/2015 (29 Months)

.