PROJECT SCOPE OVERVIEW

SR 60/E Kennedy Blvd From N Nebraska Ave To N Ashley

StFPN 436491-1-32-01

PRESENTER:LIYANAGE INDIKE RATNAYAKE

SEPTEMBER 04, 2015

Florida Department ofTRANSPORTATION

Florida Department of Transportation

• Preserve existing pavement and improve ride quality through Milling and Resurfacing• Enhance Safety and Mobility of the project corridor while

accommodating all modes of transportation• Minimize inconvenience to travelling public • Achieve efficient design through application of Practical

Design Guidelines

PROJECT INFORMATION

Florida Department of Transportation

Project Objectives

• Milling and Resurfacing• Work Types

• 3.1- Minor Highway Design• 4.1.1 – Miscellaneous Structures• 6.3.1 – ITS Analysis & Design • 7.1 – Signing and Pavement Marking• 7.3 - Signalization

• Total project length: 0.580 Miles• From MP 0.010 (west radius return of Nebraska Ave) to 0.590

(east radius return of Ashley St)• Ties into project FPID 434841-1 (in-house, March 2017 Letting)

PROJECT INFORMATION

Florida Department of Transportation

Project Overview

• Current Design Schedule: 18 Months• Letting Date: 12/26/2017• Funded for Design and Construction (Federal)• Some Improvements under Federal Safety Funds• Current PPR Estimate: $ 742,472.00• Designated as BDI (Business Development Initiative) for design

PROJECT INFORMATION

Florida Department of Transportation

Project Overview

END PROJECT

BEGIN PROJECT

PROJECT INFORMATION

Florida Department of Transportation

Project Location

• Urban multi-lane, One-way, variable width, curb and gutter with parking • Sidewalks on both sides• No designated Bike Lanes• Mid-block crosswalks• Several signalized intersections• Patterned pavements and sidewalks• Granite curbs• Access Management Classification: 7

PROJECT INFORMATION

Florida Department of Transportation

Existing Conditions

Traffic Data

PROJECT INFORMATION

Florida Department of Transportation

Pavement Data

• Base Materials: Limerock, shell, concrete, and brick.• Average asphalt thickness: 4.5 inches (2.9 inches minimum

and 4.5 inches maximum)• Pavement Condition Survey results:

PROJECT INFORMATION

Florida Department of Transportation

PROJECT INFORMATION

Florida Department of Transportation

Typical Section

Crash Data• Total 24 crashes

between 2011 and 2013• No Fatalities• 30% Injury Crashes • No Pedestrian and

Bicyclist crashes

PROJECT INFORMATION

Florida Department of Transportation

• Milling and Resurfacing• Cross slope corrections• ADA improvements to sidewalks and curb ramps• Address Sight Distance issues at intersections

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Roadway

• Bulb-outs at Signalized Intersections• Enhance pedestrian safety • Tampa St, Franklin St, Florida Ave, Marion St, Morgan St, Pierce

St• Drainage and utility impacts

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Roadway

Parking

SidewalkCurb Ramps

X-Walks

• Improvements at Lee Roy Selmon Expressway Off Ramp• Existing flexible delineators damaged by vehicles crossing over• Alternative Analysis to make recommendations

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Roadway

• No major flooding complaints• Minor Drainage improvements as needed• Address ponding along walkways and curb returns• Potential impacts due to proposed bulb-outs

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Drainage

• Deficiencies in Bicyclist Accommodations• Deficiencies in Cross Slope• Deficiencies in Gutter Grade

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Anticipated Variations & Exceptions

• Project located in Downtown Tampa• Several stakeholders

• City of Tampa, Hillsborough County, HART, several UOA’s, Several Businesses

• Community Awareness Plan• Project Fact sheet, Project

Brochure, Elected Official Notifications

• Design Open House

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Public Involvement

• High pedestrian volumes• Major Transit Route• Consideration to Special Events

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Temporary Traffic Control Plan

• Update S&M throughout the corridor including parking areas and bus stops• Update signal clearance

timings• Overhead sign panel

modifications

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Signing and Markings/Signalization

• Upgrade signing for mid-block crossings • Advance warning signs including RRFB’s

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Signing and Markings/Signalization

• Upgrade signing and markings on Lee Roy Selmon Expressway off Ramp• Wrong Way Traffic Control features• Speed Feedback Signs

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Signing and Markings/Signalization

• Coordination with several UAO’s • Fiberlight LLC, Deltacom, FPL Fibernet LLC, Verizon,

Hillsborough County ITS, Hillsborough County Clerck of Circuit CO, Hillsborough County Traffic Service, Level 3 Communications LLC, MCI, TECO Peoples Gas, City of Tampa Water Department, City of Tampa Transportation, City of Tampa Water (Sewer), Tampa Electric Company, Bright House Networks, Sprint Nextel, XO Communications.

• FDOT and COT ITS (Fiber Optic Cables) in the vicinity• No ITS work anticipated (Optional Services if needed)

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Utilities

• Minor structures involvement• Overhead sign structure evaluation

PROPOSED SCOPE OF WORK

Florida Department of Transportation

Structures

• Provided by the Department

Surveying & Mapping, SUE, Geotechnical

• Project information available in Department’s Publicly-Accessible websites

• DRAFT Scope: ftp://ftp.dot.state.fl.us/LTS/D7/Procurement/PSU/Scopes/Drafts/

• Project Intelligence:ftp://ftp.dot.state.fl.us/LTS/D7/Development/ProjMgmt/ProjectIntelligence/

OTHER INFORMATION

Florida Department of Transportation

• FDOT Project Manager: Liyanage “Indike” Ratnayake• FDOT Technical Review Committee Members:• Rochelle Garrett• Daniel Lauricello• Lilliam Escalera

• Professional Services Contract Administrator• Nikitra King

OTHER INFORMATION

Florida Department of Transportation

• Selection Procedure• Letter of Response and Interview

• Important Dates• Marketing Meeting Date: September 08th, 2015; 08:30 AM to 12:00PM• Advertisement Date: 14SEP2015• Longlist (TRC) Date: 19OCT2015• Shortlist Selection Date: 27OCT2015 • TRC Meeting Date: 19NOV2015• Final Selection Meeting Date: 08DEC2015 • 1st Negotiations Meeting Date: 21DEC2015