microsoft project - precast schedule
Post on 26-Feb-2018
216 Views
Preview:
TRANSCRIPT
-
7/25/2019 Microsoft Project - Precast Schedule
1/1
ID Task
Mode
Task Name Duration Start Finish Predecessors
1 SCHEDULE OF WORKS PERTAINING
TO PREACAST
1 92 days May 2 '15 Dec 2 '15
2 DESIGN 70 days May 2 '15 Jul 19 '15
3 Receipt of Architectural
drawings from AJEC
3 days May 2 '15 May 4 '15
4 Sending enquiries to Precast
Subcontractors
7 days May 4 '15 May 12 '15 3
5 Reciept of Quotation from
Subcontractor & Finalisation
15 days May 12 '15 May 28 '15 4
6 Issuance of PO to Precast
Supplier
7 days May 30 '15 Jun 6 '15 5
7 Receipt of Load calculations
from Precast subcontractors
15 days Jun 6 '15 Jun 22 '15 6
8 Finalisation of precast &
architectural drawings
4 days Jun 23 '15 Jun 27 '15 7
9 Submission of Civil base design
documens to SEC
4 days Jun 27 '15 Jul 1 '15 8
10 Approval of Civil Base design
documents by SEC
15 days Jul 1 '15 Jul 19 '15 9
11 FABRICATION 32 days Sep 23 '15 Oct 29 '15
12 Issuing Manufacturing clearance
to the subcontractor
2 days Sep 23 '15 Sep 26 '15 10FS+60 days
13 Manufacuring 30 days Sep 26 '15 Oct 29 '15 12
14 INSTALLATION 30 days Oct 29 '15 Dec 2 '15 13
15 Erection of Precast 30 days Oct 29 '15 Dec 2 '15 13
SCHEDULE
OF WORKS PERTAINING TO PREAC
DESIGN
3 days
7 days
15 days
7 days
15 days
4 days
4 days
15 days
FABRICATION
2 days
30 days
INSTALLATION
30 days
F S S M T W T F S S M T W T F S S M T W T F S S
ar 29, '15 May 3, '15 Jun 7, '15 Jul 12, '15 Aug 16, '15 Sep 20, '15 Oct 25, '15 Nov 29, '15 Jan 3, '16 Feb 7, '16 Mar 1 '
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 1
Project: msproj11
Date: May 2 '15
top related