microsoft project - precast schedule

Upload: shabbir

Post on 26-Feb-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Microsoft Project - Precast Schedule

    1/1

    ID Task

    Mode

    Task Name Duration Start Finish Predecessors

    1 SCHEDULE OF WORKS PERTAINING

    TO PREACAST

    1 92 days May 2 '15 Dec 2 '15

    2 DESIGN 70 days May 2 '15 Jul 19 '15

    3 Receipt of Architectural

    drawings from AJEC

    3 days May 2 '15 May 4 '15

    4 Sending enquiries to Precast

    Subcontractors

    7 days May 4 '15 May 12 '15 3

    5 Reciept of Quotation from

    Subcontractor & Finalisation

    15 days May 12 '15 May 28 '15 4

    6 Issuance of PO to Precast

    Supplier

    7 days May 30 '15 Jun 6 '15 5

    7 Receipt of Load calculations

    from Precast subcontractors

    15 days Jun 6 '15 Jun 22 '15 6

    8 Finalisation of precast &

    architectural drawings

    4 days Jun 23 '15 Jun 27 '15 7

    9 Submission of Civil base design

    documens to SEC

    4 days Jun 27 '15 Jul 1 '15 8

    10 Approval of Civil Base design

    documents by SEC

    15 days Jul 1 '15 Jul 19 '15 9

    11 FABRICATION 32 days Sep 23 '15 Oct 29 '15

    12 Issuing Manufacturing clearance

    to the subcontractor

    2 days Sep 23 '15 Sep 26 '15 10FS+60 days

    13 Manufacuring 30 days Sep 26 '15 Oct 29 '15 12

    14 INSTALLATION 30 days Oct 29 '15 Dec 2 '15 13

    15 Erection of Precast 30 days Oct 29 '15 Dec 2 '15 13

    SCHEDULE

    OF WORKS PERTAINING TO PREAC

    DESIGN

    3 days

    7 days

    15 days

    7 days

    15 days

    4 days

    4 days

    15 days

    FABRICATION

    2 days

    30 days

    INSTALLATION

    30 days

    F S S M T W T F S S M T W T F S S M T W T F S S

    ar 29, '15 May 3, '15 Jun 7, '15 Jul 12, '15 Aug 16, '15 Sep 20, '15 Oct 25, '15 Nov 29, '15 Jan 3, '16 Feb 7, '16 Mar 1 '

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 1

    Project: msproj11

    Date: May 2 '15