Initial Environmental Examination Document Stage: Draft Project Number: 42486-018 June 2021
India: Madhya Pradesh Urban Services Improvement Project – Additional Financing (Water Supply Scheme Subproject Town Bada Malhera) Package No. MPUSIP-6K
Prepared by the Project Management Unit, Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.
CURRENCY EQUIVALENTS
(As on 29 June 2021)
Currency unit – Indian rupee (₹) ₹1.00 = $0.013 $1.00 = ₹74.23
ABBREVIATIONS
ADB – Asian Development Bank ASO – Assistant Safeguards Officer BNP – Bada Malhera Nagar Parishad CFE – Consent for Establishment CFO – Consent for Operation CPCB – Central Pollution Control Board CWS – Clear Water Sump EA – Executing Agency EE – Executive Engineer EHS – Environmental Health & Safety EIA – Environmental Impact Assessment EMP – Environmental Management Plan; GOI – Government of India GOMP – Government of Madhya Pradesh HDPE – High Density Poly-ethylene HFL – Highest Flood Level IA – Implementing Agency IEE – Initial Environmental Examination; LPCD – Liters per Capita per Day MFF – Multi-tranche Financing Facility MLD – Million Liters per Day MOEF – Ministry of Environment and Forest MPPCB – Madhya Pradesh Pollution Control Board MPUDC – Madhya Pradesh Urban Development Company NOC – No Objection Certificate OHT – Over Head Tank PMC – Project Management Consultant PHED – Public Health Engineering Department PIU – Project Implementation Unit; PMU – Project Management Unit PO – Project Officer PWD – Public Works Department REA – Rapid Environmental Assessment Checklist ROW – right-of-way SEIAA – State Environmental Impact Assessment Authority SPS – Safeguard Policy Statement,2009 UDED – Urban Development & Environment Department ULB – Urban Local Body WTP – Water Treatment Plant
WRD – Water Resources Department WSS – Water Supply Scheme
NOTE
In this report, "$" refers to United States dollars.
This draft initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
WEIGHTS AND MEASURES
˚C km LPCDmm m MLD MCM No’s sq.km
Degree Celsius kilometer Liter per capita per day Mille meter meter Million liter per day Million Cubic Meter Number square kilometer
CONTENTS
I. INTRODUCTION 1
A. Background 1
B. Purpose of IEE Report 1
C. Report Structure 2
II. DESCRIPTION OF THE SUBPROJECT 3
A. Project Area 3
B. Existing Water Supply Situation 5
C. Components of the Subproject 8
D. Description of the Important Individual Components 11
E. Implementation Schedule 21
III. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK 29
A. ADB Policy 29
B. National Environmental Laws 29
IV. DESCRIPTION OF THE ENVIRONMENT (BASELINE DATA) 37
A. Methodology Used for Baseline Study 37
B. Physical Environment 38
C. Ecological Resources 41
D. Economic Development 42
E. Socio Cultural Resources 44
F. Subproject Site Environmental Features 44
V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 58
A. Pre-Construction Impacts – Design & Location 59
B. Environmental Audit of Existing Water Treatment Plant 87
C. Construction Impacts 90
D. Operation and Maintenance Impacts 102
E. Project benefits 104
VI. INFORMATION DISCLOSURE AND PUBLIC CONSULTATION 105
A. Overview 105
B. Public Consultation 105
C. Information Disclosure 107
VII. GRIEVANCE REDRESSMECHANISM 108
A. Project Specific Grievance Redress Mechanism 108
B. Purpose of the GRM Manual: 108
C. Principles: 108
D. Nature and scope of Grievance Redress Mechanism under MPUSIP 109
E. Structure of GRM and its Functions: 109
F. Process of Grievance Redress Mechanism 112
G. Monitoring and Evaluation Systems of GRM 115
H. Action Plan for the formation of the GRM 116
VIII. ENVIRONMENTAL MANAGEMENT PLAN 117
A. Environmental Management Plan 117
B. Implementation Arrangements 157
C. EMP Compliance Responsibilities 157
D. Training Needs 160
E. Monitoring and Reporting 161
F. EMP Implementation Cost 161
IX. CONCLUSIONS AND RECOMMENDATIONS 163
List of Tables
Table 1: Details of Existing Water Source & Water Supply System 7
Table 2: Project Water Demand 8
Table 3: Proposed Bada Malhera Town Water Supply Subproject Components 9
Table 4: Applicable Environmental Regulations 30
Table 5: WHO Ambient Air& Noise Quality Guidelines 37
Table 6: Existing Land Use Details 42
Table 7: Site Environmental Features of Proposed WSS Components of Bada Malhera Town 45
Table 8: Existing Weirs/ Check Dams across Kathan River and distance from Origin of river & proposed weir & Pick-up weir for Bada Malhera Town WSS 61
Table 9: Baseline Information and Flow Dynamics of River Kathan 69
Table 10: Details of Proposed Weir & Pick-up Weir across Kathan River 70
Table 11: Area Capacity Table of Proposed Weir for Bada Malhera Town WSS 71
Table 12: Evaporation Losses Table as per Central Water Commission 71
Table 13: Storage Capacity of Proposed Weir of Bada Malhera Town WSS at Contour 295 = 835.42 ML 72
Table 14: Storage Capacity of Pick-up Weir at Bada Malhera 113.38 ML at Contour 290 m 73
Table 15: Water Availability/ Yield Analysis based on Catchment area & Rainfall at Proposed Weir & Pick-up Weir Site – Bada Malhera Town WSS 74
Table 16: Salient Features of Bada Malhera Existing WTP 87
Table 17: Compliance with Applicable National and State Regulations 88
Table 18: Corrective Action Plan (CAP) for Environmental Compliance of Existing WTP 90
Table 19: Design Stage Environmental Management Plan 118
Table 20: Pre-Construction State Environmental Management Plan 121
Table 21: Construction Stage Environmental Management Plan 128
Table 22: Operation Stage Environmental Management Plan 151
Table 23: Pre-Construction and Construction Stage Environmental Monitoring Plan 154
Table 24: Operation Stage Environmental Monitoring Plan 155
Table 25: Outline Capacity Building Program on EMP Implementation 160
Table 26: Cost Estimates to Implement the EMP 161
List of Figures
Figure 1: Location of Bada Malhera Town in M.P. State Map 4
Figure 2: Location of Subproject Town Bada Malhera in District Map 5
Figure 3: Existing Water Abstraction Structure for Bada Malhera Town (to be used after Rehabilitation 12
Figure 4: Photographs of Existing Intake well located on the bank of River Kathan near Garkhuwan village 13
Figure 5: Existing WTP for Bada Malhera Town (to be used after Rehabilitation) 15
Figure 6: Google Earth Map Showing Existing WTP Located on Garkhuwan road in Ward No. 12, Bada Malhera 16
Figure 7: Photographs of Existing WTP located on Garkhuwan road in Ward No. 12, Bada Malhera 17
Figure 8: Photographs of Existing OHTs in Bada Malhera to be Utilized under MPUSIP 19
Figure 9: Key Plan Showing Proposed & Existing Components From Source to OHTs – Bada Malhera Town WSS 22
Figure 10: Google Earth Map Showing Source to OHTs - Proposed & Existing Components, Raw and Clear Water Alignment of Bada Malhera Town WSS 23
Figure 11: Zone plan details 24
Figure 12: Distribution Network Plan (Zone 1) 25
Figure 13: Distribution Network Plan (Zone 2) 26
Figure 14: Distribution Network Plan (Zone 3) 27
Figure 15: Distribution Network Plan (Zone 4) 28
Figure 16: Google Earth Map Showing Proposed Weir, Pick-up Weir & Existing Intake Well of Bada Malhera WSS 54
Figure 17: Google Earth Map Showing Proposed / Existing Components of Bada Malhera WSS55
Figure 18: Google Earth Map Showing Proposed OHT 160 KL - Bada Malhera Town WSS 56
Figure 19: Google Earth Map Showing Proposed OHT 330 KL - Bada Malhera Town WSS 57
Figure 20: Showing Origin & Destination Point and Location of Nearest Existing Weir (U18), Proposed weir & Pick-up weir, and existing Intake in Kathan River Near Garkhuwan village 64
Figure 21: Google Earth Map Showing Location of Existing Dams/Weirs w.r.t. Proposed Weir & Pick-up Weir across Kathan River 65
Figure 22: Google Earth Map Showing Location of Existing Weir/Check Dam (D1) on downstream of Proposed weir & Pick-up weir and existing Intake in Kathan River 66
Figure 23: Google Earth Map Showing Location of Existing weirs/check dams (U15 to U18) on Upstream of Proposed weir & Pick-up weir and existing Intake in Kathan River 67
Figure 24: Google Earth Map Showing Location of Existing weirs/check dams (U1 to U15) on Upstream of Proposed weir & Pick-up weir and existing Intake in Kathan River 68
Figure 25: Weir Capacity Curve 72
Figure 26: Pick-up Weir Capacity Curve 73
Figure 27: Catchment Area w.r.t. Proposed Weir & Pick-up Weir across Kathan River near Garkhuwan Village 75
Figure 28: Site Photographs of River Kathan Showing River Banks Height 76
Figure 29: Contour Map of Kathan River Superimposed on Google Earth Map showing Submergence area w.r.t. proposed Weir height and Location 80
Figure 30: Details of Plan, Cross-Section & Elevation of Proposed Weir Showing Sluice Gates for Bada Malhera Town WSS 83
Figure 31: Details of Plan, Cross-Section & Elevation of Proposed Pick-up Weir for Bada Malhera Town WSS 84
Figure 32 : Flowchart for Preparing an Asbestos Management Plan 99
Figure 33: Work Flow Diagram on GRM 112
Figure 34: Structure and Process of GRC 115
List of Appendices
Appendix 1: ADB Rapid Environmental Assessment (REA) Checklist 166
Appendix 2: National Ambient Air Quality Standards 171
Appendix 3: Vehicle Exhaust Emission Norms 172
Appendix 4: National Ambient Air Quality Standards In Respect Of Noise 173
Appendix 5: Comparison Between Indian Environmental Standards and IFC Standards 174
Appendix 6: Extract From Construction & Demolition Management Rules, 2016 178
Appendix 7: Salient Features Of Major Labor Laws Applicable To Establishments Engaged In Construction Of Civil Works 184
Appendix 8: Drinking Water Standards 185
Appendix 9: Sample Outline Traffic Management Plan 187
Appendix 10: Sample Outline Spoils (Construction Waste) Management Plan 194
Appendix 11: Application Submitted to WRD for Water Abstraction From Kathan River For Bada Malhera Town WSS 195
Appendix 12: Surface Water Quality Results – Kathan River 198
Appendix 13: Guidance on Siting and facilities in Contractors Camps 200
Appendix 14: Guideline for Construction Work about Safety from COVID-19 Pandemic 205
Appendix 15: Sample Grievance Registration Form 213
Appendix 16: Sample Environmental Site Inspection Report 214
Appendix 17: Quarterly Reporting Format for Assistant Safeguards Officer 217
Appendix 18: Stakeholder Consultation Details, Photographs of Consultations and List of Participants in Bada Malhera Nagar Parishad under Package 6K 223
Appendix 19: GPS Coordinates of Proposed/Existing WSS Components Sites of Subproject Towns – Bada Malhera Town under Package 6K 243
EXECUTIVE SUMMARY
Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project. The Project components are as follows:
(i) Component 1: Improvements to water supply and sewerage services in identified towns
• Continuous, pressurized, safe and sustainable drinking water through private household metered connections in sixty-four towns in the State of Madhya Pradesh in Central India; and
• Sewage collection and treatment services proposed in six (6) identified towns (Sanchi, Maihar, Dhamnod, Nagda, Khajuraho and Rajnagar) etc;
(ii) Component 2: Institutional Strengthening
• Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services;
• Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and
• Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.
(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.
The subproject: The subproject town Bada Malhera is located in the Chhattarpur district in the eastern part of Madhya Pradesh state. Bada Malhera is a small town, and population as per 2011 census was 18335. Improvement of water supply in the town will be implemented under a single Design-Build-Operate (DBO) contract package. The objective of the proposed improvements in town is to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The project proposals envisage providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes civil works, project implementation and management, and non-physical investments. The subproject includes the following civil works. Bada Malhera WSS project include following works: (i) Construction of a Weir of 192 length and 6m height across River Kathan, (ii) Construction of a Pick-up Weir of 94 length and 2m height across River Kathan; (iii) Repair and Rehabilitation of Existing Intake Well of 4.0m dia and 15.0m height on the bank of River Kathan; (iv) Repair and Rehabilitation of Existing Water Treatment Plant (WTP) of 3.0 MLD capacity (v)Laying of Clear Water Rising Main (CWRM) of length-3641m and dia 100-200mm DI K-9 pipes; (vi) 2 Nos.Over Head Tank (OHT) of capacity
ii
330 KL and 100 KL ; (vii) Distribution network 42417 m length having (110-250 mm dia) HDPE pipes; (viii) Bulk flow meter – 17 nos. and (viii) House connections with meters-(2156 no,s – Domestic and 50 no,s Non-domestic connections). Screening and assessment of potential impacts. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply. Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure. The subproject is unlikely to cause significant adverse impacts because: (i) the water abstraction for the project is very minimal in comparison with the river water flow/availability, there are already dams/weirs across the river both upstream and downstream and there are no notable sensitive environmental features; (ii) the components will involve straightforward construction and operation, so impacts will be mainly localized; (iii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements; and (iv) being located mainly in an existing built-up area, will not cause direct impact on terrestrial biodiversity values. Potential negative impacts mainly arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts, and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well-developed methods for mitigation of these impacts to acceptable levels. Categorization. Based on results of the assessment and ADB SPS, the subproject is classified as environmental Category B, i.e., the subproject is judged to be unlikely to have significant adverse environmental impacts. An initial environmental examination (IEE) is required to determine whether significant environmental impacts warranting an environmental impact assessment are likely. Aim of this IEE is to (i) provide critical facts, significant findings, and recommended actions; (ii) present the national and local legal and institutional framework within which the environmental assessment has been carried out; (iii) provide information on existing geographic, ecological, social and temporal context including associated facilities within the subproject’s area of influence; (iv) assess the subproject’s likely positive and negative direct and indirect impacts to physical, biological, socioeconomic and physical cultural resources in the subproject’s area of influence; (v) identify mitigation measures and any residual negative impacts that cannot be mitigated; (vi) describe the process undertaken during project design to engage stakeholders and the planned information disclosure measures and the process for carrying out consultation with affected people and facilitating their participation during project implementation; (vii) describe the subproject’s grievance redress mechanism for resolving complaints about environmental performance; (viii) present the set of mitigation measures to be undertaken to avoid, reduce, mitigate, or compensate for adverse environmental impacts; (ix) to describe the monitoring measures and reporting procedures to ensure early detection of conditions that necessitate particular mitigation measures; and (x) identify indicative costs and who is responsible for carrying out the mitigation and monitoring measures. Description of the Environment. The subproject components locations are in Bada Malhera town and its surroundings. Project area mostly comprises urban areas, agricultural areas of
iii
Bada Malhera town. The immediate surroundings were converted into urban use for many years ago, and there is no natural habitat left at the subproject sites. There is no ecological sensitive feature, such as forests, are present nearby. Project area experience a subtropical climate, typical to north India, hot summers, cold and dry winters and monsoon rains. While there is no natural habitat left within the town areas, the areas near river intake are comparatively intact though most of the lands there too converted into agricultural use. There are no protected areas, like wildlife sanctuaries, national parks, nor there are any historically, archeologically protected areas in the vicinity. There are no forest areas within the town or in the project area. None of the proposed components are located in any sensitive areas like forest. Town is densely populated in the core/old town areas with narrow lanes, and small and closely built houses, while most of the areas are undeveloped and are still under agricultural use. Commercial areas are along the main roads, which are mostly congested with activities, pedestrians and traffic. The existing intake well is located on the bank of Kathan River near village Garkhuwan, which is about 3.6 km away from Bada Malhera town. Proposed weir and pick-up weir will be constructed across River Kathan nearby existing intake well at Garkhuwan village. Proposed weir will be constructed on upstream of existing intake well (about 0.44 km away) & from Low bridge (about 0.135 km away from bridge to avoid the submergence of it.). Proposed pick-up weir will be constructed in the downstream of the proposed weir (about 1.47 km away) and from existing intake well (about 0.8 km away). Water will be released from weir and Pick-up weir will hold the water in the pool and then raw water will be abstracted from pick-up weir across Kathan River through existing intake and supply to WTP. Existing intake proposed weir and pick-up weir sites are located outside the town about 3.6 km away on north-western side of Bada Malhera town and are mostly surrounded by agricultural lands, and rivers/reservoirs. The Aquatic life in the river is limited to local common species of fishes and aquatic plants. There are no notable sensitive features. There is no forest area either in the downstream or in the upstream of the proposed intake site. The catchment area is mostly characterized by agricultural and barren lands. There are no polluting sources like industries or mining in the catchment areas. Habitations are limited to small villages. Rest of the components – existing WTP, water tanks, distribution lines, connections etc., will be located within the urban areas. existing WTP location is on a vacant government owned barren land within town, which is about a distance of 3.6 km away from intake site. All the locations of the OHT are government-owned barren land with no notable tree cover. The existing raw water rising mains (RWRM), connecting intake and WTP, is outside the town, and clear water rising mains (CWRM), from WTP to distribution reservoirs, is within the town. Existing RWRM will be utilized in this scheme which were laid by PHE department in 2015. CWRM will be laid along existing main road of ULB and in some part along NH-86 roads within ROW. The pipes will not traverse any private land across the entire length of the proposed alignment. Pipe will be laid underground. Distribution networks will be laid along the ULB roads/streets in the town within the road right of way (ROW). Distribution network/transmission lines will not be laid in forest areas, water bodies as there is no involvement of forest land nor comes along water bodies. There are no trees along the roads, except in some colonies in the outer areas. In old town areas pipes will be laid in the middle of the road, which may affect the traffic. Potential Environmental Impacts: Potential impacts were identified in relation to location, design, construction and operation of the improved infrastructure. The subproject area will not arise any significant adverse impacts due to: (i) small size population and their water demand, (ii) components proposed in the scheme are of comparatively is of small quantities & their effect will be locally which is manageable and controllable and (iii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements.
iv
Source Sustainability & Environmental Considerations: The proposed water supply scheme of Bada Malhera town include design of new surface source-based system with nearest surface water body i.e. River Kathan, which flows at about 3.6 km away from the town. The proposed water supply scheme includes construction of a Weir and a pick-up Weir across Kathan River near Garkhuwan village for storage of water to meet the demand of no flow / non-rainy period. Kathan river is not a perennial river. No flow data is available as there is no gauging station on the river. As per information gathered from the locally, river flows for about 4-5 months, from late June / early July to October and mid of November. Flow is normally very high during the peak monsoon months of July and August, and high to medium in the months of September and October. From November onwards, flow reduces significantly, and becomes very low from mid-November, and completely gets dry from the end of January to the onset of next monsoon in late June / July. ver without any storage structures will be able to provide water supply for about 4 months. Hence a weir is required to create water storage for remaining 8 months of the year, so that Ultimate demand of the town can be fulfilled. Considering the height of banks, it is assessed that to confine the water storage to the river course, a weir of maximum height 6 m can be constructed. River banks at this site is 8-10 m above bed level. On the basis of area basin survey, it is estimated that proposed weir of 6 m will have capacity of 0.835 MCM, which is less than annual requirement of 0.92 MCM. Therefore, it is proposed to construct an additional weir of 2 m high with capacity of 0.113 MCM. Together, the storage from both the weirs will be sufficient to meet the demand. It is proposed to utilize the existing river intake, which is at the upstream of proposed 2 m high weir site. The downstream weir (2m high) will act as a pick up weir, from where the water will be abstracted via intake, while the upstream weir (6 m high) will act as storage weir. Pick up weir will be filled from storage weir as and when required. The total water demand for Bada Malhera town is estimated to be 2.52 MLD. Considering evaporation losses from the storage, the estimated water requirement of 8 months low / no-flow season is 0.915 MCM. In the absence of flow records, catchment yield is estimated as 145.68 MCM based on the area (1,214 sq. km) and the rainfall. The requirement of the town is just about 0.63% of the total yield and therefore the source is sustainable, and also unlikely to have any notable impacts on the river flow regime. Also, the increase in overall storage volume across the river due construction new weir is will also not be significant. Although there are total 19 weirs/check dams/dams across the river, except Bila Dam, all are very small, and storage capacity is just around 0.5 MCM. Bila Dam is situated 60 km upstream of proposed weir site, and the capacity of Bila Dam is 56.37 MCM. In terms of water availability, the cumulative storage on the river is about 45% of total catchment yield. Creation of new storage for Bada Malhar with just 0.92 MCM of water is unlikely to alter the existing situation considerably. Water storage will be confined to river course, so therefore no impacts related to water impoundment or submergence. Given intermittent nature of river, there are no notable sensitive environmental features. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local common species and aquatic plants. Low level sluice gates will be opened prior to onset of heavy monsoon flows; this arrangement avoids silt accumulation and also prevents obstruction of heavy monsoon flows. River water quality is suitable for drinking water after conventional treatment and disinfection, and there are no notable pollution sources. Convention water treatment and disinfection which is proposed in the project is adequate to make the water usable for drinking purpose. Permission of water resources department (WRD) is a prerequisite for this project, and this will be obtained from WRD, GoMP, prior to start of works. WRD permission for abstraction from the
v
river is in process. PMU has already discussed with the WRD, and the permission is likely to be issued soon. It is proposed to utilize the existing intake, raw water main and WTP with necessary rehabilitation and repair works WTP do not have proper wastewater and sludge management system, and chlorine safety facilities. Therefore, these are included in the proposed subproject proposals to ensure compliance with the ADB SPS. Existing WTP also does not have the mandatory consent from the Madhya Pradesh Pollution Control Board (MPPCB), which needs to be obtained from the MPPCB for rehabilitation and further operation. During the construction phase, impacts mainly arise from the disturbance of residents, businesses, increase in traffic, increase in noise level and dusts and the need to dispose of moderate quantities of waste soil during construction phase. These are common temporary impacts of construction in urban areas, and there are well developed methods for their mitigation. Mitigation measures have been developed to reduce all negative impacts to acceptable level. Environmental Management Plan. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels. The EMP includes design measures such as (i) discontinuation of groundwater source, and shifting to a sustainable surface water source (Kathan River); (ii) design & construction of small weir & pick-up weir; (iii) wash water recovery for the WTP to reduce effluent to be discharged; (iv) beneficial use of treated sludge; and (v) quick leak detection and rectification to save the resources, etc. During construction, the EMP includes mitigation measures such as (i) selection of appropriate construction methodology and scheduling for intake works in river;(ii) implementation of traffic management plan in coordination with local traffic police to minimize traffic impacts; (iii) awareness campaigns and consultations to inform residents and businesses of potential disturbances; (iv) provision of walkways and planks over trenches to ensure access will not be impeded; (v) use of noise-dampening measures in areas with sensitive receptors such as hospitals, schools, places of worships and other silence-zones; (vi) use of dust-suppression methods such as watering and/or covering of stockpiles; and (vii) finding beneficial use of excavated materials to extent possible to reduce the quantity that will be disposed off. As for the O&M phase, facilities will need to be repaired from time to time, but environmental impacts will be much less than those of the construction period as the work will be infrequent, affecting small areas only. The design of the WTP includes dewatering and drying areas as part of sludge management. The EMP includes mitigation measures and monitoring plan to ensure compliance to environmental standards during O&M phase. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between Madhya Pradesh Urban Development Company (MPUDC), project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.
vi
The contractor will be required to submit to PMU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance. Consultation, disclosure and grievance redress mechanism. The stakeholders were involved in developing the IEE through discussions on-site and public consultation at several places in the town, after which views expressed were incorporated into the IEE and in the planning and development of the project. The IEE will be made available at public locations and will be disclosed to a wider audience via the ADB, MPUDC and PMU websites. The consultation process will be continued and expanded during project implementation to ensure that stakeholders are fully engaged in the project and have the opportunity to participate in its development and implementation. A grievance redress mechanism is described within the IEE to ensure any public grievances are addressed quickly. Implementation Arrangements. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh will be the Executing Agency. Implementing Agency will be Madhya Pradesh Urban Development (MPUDC), A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Project Implementation Units (PIUs). Several teams of Design Consultants, and a Project Management Consultant (PMC) centrally located in PMU and with field teams, will support PMU & PIUs. Infrastructure will be designed, built, and operated (DBO) by contractor for 10 years, after which it will be transferred to the ULB. Project Officer (Environment) at PMU and Assistant Safeguard Officer (ASO) at each of the PIU will be responsible for environment safeguards tasks, and will be supported by Environment Specialist of PMC Team. Contractor personnel will include an Environment, Health and Safety (EHS) supervisor. Monitoring and Reporting. The PMU and PMC will be responsible for monitoring. The PMDC will submit quarterly and semi-annual monitoring reports to PMU, and the PMU will review and send the semi-annual monitoring reports to ADB. ADB will post the environmental monitoring reports on its website. Conclusions and Recommendations. The proposed subproject is therefore unlikely to cause significant adverse impacts. The potential impacts that are associated with design, construction and operation can be mitigated to standard levels without difficulty through proper engineering design and the incorporation or application of recommended mitigation measures and procedures. Based on the findings of the IEE, there are no significant impacts and the classification of the project as Category “B” is confirmed. No further special study or detailed environmental impact assessment (EIA) needs to be undertaken to comply with ADB SPS (2009) or GoI EIA Notification (2006). Project will require following government permission/approvals: (i) permission of Water Resources Department (WRD), GoMP for water abstraction from River Kathan and construction of weir and pick-up weir; and (ii) consent to establish / operate for existing WTP from Madhya Pradesh Pollution Control Board. These permissions/approvals shall be obtained prior to start of civil works. This IEE will be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.
I. INTRODUCTION
A. Background
1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project. 2. The Project components are as follows:
(i) Component 1: Improvements to water supply and sewerage services in identified towns
• Continuous, pressurized, safe and sustainable drinking water through private household metered connections in sixty-four towns in the State of Madhya Pradesh in Central India; and
• Sewage collection and treatment services proposed in six (6) identified towns (Sanchi, Maihar, Dhamnod, Nagda, Khajuraho and Rajnagar) etc;
(ii) Component 2: Institutional Strengthening
• Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services;
• Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and
• Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.
(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.
3. The Subproject. Bada Malhera is located in Chhattarpur District in the eastern part of Madhya Pradesh state and improvement of water supply in the town is one of the subprojects proposed under MPUSIP. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The subproject envisages providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes civil works: two weirs across Kathan River, clear water transmission main, overhead tanks, distribution network, consumer connections and flow meters. Subproject also includes repairs and rehabilitation of exiting intake and WTP. A detailed description of the components is provided in Section III. B. Purpose of IEE Report
4. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguards Policy Statement (2009). The potential environmental impacts of the subproject
2
have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply (Refer Appendix 1). Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure, and results of the assessment show that the subproject is unlikely to cause significant adverse impacts. Thus, this initial environmental examination (IEE) has been prepared in accordance with ADB SPS’s requirements for environment category B projects. 5. This IEE is based on the preliminary engineering report prepared by the DPR Consultant “Shah & Pant Consulting Engineers (P) Ltd. Lucknow” team and will be finalized during implementation stage by DBO contractor to reflect any changes and latest subproject designs. The IEE was based mainly on field reconnaissance surveys and secondary sources of information. No field monitoring (environmental) survey was conducted however, the environmental monitoring program developed as part of the environmental management plan (EMP) will require the contractors to establish the baseline environmental conditions prior to commencement of civil works. The results will be reported as part of the environmental monitoring report and will be the basis to ensure no degradation will happen during subproject implementation. Stakeholder consultation was an integral part of the IEE. C. Report Structure
6. This report contains the following sections:
(i) Introduction (ii) Description of the Subproject (iii) Policy, Legal and Administrative framework (iv) Description of Environment (v) Anticipated Environmental Impact & Mitigation Measures (vi) Public Consultation and Information Disclosure (vii) Grievance Redress Mechanism (viii) Environmental Management Plan (ix) Conclusions and Recommendations
3
II. DESCRIPTION OF THE SUBPROJECT
A. Project Area
7. Bada Malhera is a town and a Nagar Parishad in Chhattarpur district in the state of Madhya Pradesh, India. It belongs to the Sagar division. It is located 54 KM towards Southwest from District headquarters Chhatarpur (Refer Figure 1 to Figure 2, below). Bada Malhera town is geographically situated at 24º 40' N and 79º 18' E and is 325 m above sea level. Bada Malhera is situated on NH - 86 connecting Sagar to Kanpur. National Highway (NH-86) passes through the town. The distance from Chhattarpur is about 54 Km, Tikamgarh is 60 km and Indore is 300 km and state capital Bhopal is 281 km from Bada Malhera town. Bada Malehara is bounded by Bijawar Tehsil towards East, Baldeogarh Tehsil towards North, Buxwaha and Shahgarh Tehsils towards South. Chhatarpur, Tikamgarh, Nowgaon and Damoh are the nearby Cities to Bada Malhera. 8. Bada Malhera town is established as Nagar Parishad in 1983. Bada Malhera Nagar Parishad (BNP) area comprises of 15 wards having the territorial jurisdiction of the Bada Malhera Nagar Parishad spans an area of 20.87 Sq.km. As per census 2011, Bada Malhera had a population of 18335. Bada Malhera is well connected via road. Bada Malhera is linked to other areas by road network only. Bada Malhera is situated on NH - 86 connecting Sagar to Kanpur. National Highway (NH-86) passes through the town. The nearest railway station is Chhatarpur railway station, which is nearly 54 km from the town and accessible via road network. Other nearest railway station is Teekamgarh (65km), Khajuraho (95km), Harpalpur (105km), Mauranipur (105km), Sagar (110km), Jhansi (175km) and Satna (190km) and is located on main Allahabad – Itarsi sector of Western Central Railways connect the main Jhansi - Bhopal sector of WCR from Bina. The nearest airport is also at Khajuraho, which has daily flights to and from the National Capital.
4
Figure 1: Location of Bada Malhera Town in M.P. State Map
5
Figure 2: Location of Subproject Town Bada Malhera in District Map
B. Existing Water Supply Situation
9. Source: The ground water is the main source of water for the Bada Malhera town. Presently, water is supplied through tube wells. There are 16 nos. of tube wells out of which only 10 are in working condition. In addition to this, hand pumps are other source of water in the town. A significant volume of ground water is also extracted through a network of hand pumps.
6
There are 26 nos. of hand pumps exists across the town. The water table in the area is going down years to years, due to which discharge of existing tube wells is going reduced. Mostly tube wells gets dry during summer. During summer, yield of the tube wells and hand pumps gets considerably reduced and thus town faces acute drinking water scarcity. 10. Apart from above mentioned, there is an existing intake well near village Garkhuwan in the natural pool on the bank of Kathan River, which is about 3.6 km from the town having dia. 4 m and height 15 m. There are 3 ports of 300 mm diameter. Also, there is an existing WTP having 3.00 MLD capacity and 01 no. of existing Elevated Service Reservoir in the town having 650 KL capacity. Intake well, WTP and 650 KL ESR have not been used since their construction in 2015. All these structures were built by the PHE department. Due to lack of maintenance, these structures are in poor condition and need some repairing work to meet their functional requirements. 11. Water Supply Coverage: Present water supply system is not sufficient to fulfill the water demand due to which town faces acute drinking water scarcity during summer season. The present water supply is 0.48 MLD @ 26 LPCD considering transmission losses. Due to scarcity, water is supplied on alternate days. The distribution network covers 30 percent of the developed area. At present, water is supplied to existing 160 kl ESR through tube wells and then distributed to certain areas of the town. In remaining parts of the town where pipe line is not laid, water is supplied through tractor tankers. 12. Treatment of water: Presently only primary informal treatment is being done. At present the entire water supply is being directly supplied from tube wells, without treatment except chlorination. Bada Malhera Nagar Parishad has adopted bleaching powder method for treatment of water. Before supply, bleaching powder is mixed for disinfection. As mentioned above, there is an existing water treatment plant having capacity of 3.00 MLD in the town constructed by PHE Department for surface water treatment for drinking purposes from Kathan River. Existing WTP have not been used since their construction in 2015. Due to lack of maintenance, WTP structures are in poor condition and need some rehabilitation and repairing work to meet their functional requirements. Existing WTP is taken into account for proposed system. 13. Water Storage Arrangement: Presently there are 02 nos. of existing overhead tanks (OHTs) of capacities 160 KL and 650 KL (staging height 20 m each) respectively. OHT 160 KL is located in ward no. 14, near Animal Hospital and OHT 650 KL is located in ward no. 07, near Government School in Bada Malhera town. OHT 650 KL were built by the PHE department and have not been used since their construction in 2015. At present, water is supplied to existing OHT 160 KL through tube wells and then distributed to certain areas of the town. OHT 160 KL is approximately 20 years old. Both the OHT are in working condition and structurally good and is taken into account for proposed system. 14. Water Distribution Arrangement: At present, the area of Bada Malhera town is not fully covered by distribution network. The distribution network covers 30 percent of the developed area and existing distribution covers about 23 km. About 18 km is covered by HDPE pipe line laid for distribution on both sides of NH-86 having dia. ranging from 90 mm – 160 mm. This pipe line was laid by National Highway Authority of India during construction of NH-86. These pipes are in good condition and have been considered in the proposed scheme. The remaining network of length 5.65 km is covered by AC pipes having dia. Ranging from 80 mm – 150 mm. These pipes are in dilapidated condition and cannot be used for distribution purpose. They are also buried approximately 10 to 12 feet (3-4 m) depth.
7
15. Service Connection: There are total of 1020 nos. water connection in Bada Malhera. All are domestic connections. There are no commercial connections. 16. Water Quality: The quality of water after the disinfection and distribution is considered Potable as per World Health Organization standards. In terms of quality standards, the quality of water in Bada Malhera town is quite satisfactory and suitable for domestic as well as other needs as told by the local people and officials of Bada Malhera Nagar Parishad. However, more sophisticated means of water treatment is necessary since common chlorination is the only method utilized.
Table 1: Details of Existing Water Source & Water Supply System
S. No. Particulars Details
1. No. of Tube wells 16 nos.; 10 are working
2. No. of Hand pumps 26 nos.
3. Per Capita Supply 0.48 @26 LPCD considering losses.
4. Intake Well
▪ Diameter – 4.00 m ▪ Height - 15.00 m ▪ Ports 3 nos. 300 mm dia.
5. RWRM
Length 3600 m, Dia. 200 mm (CI) considered for design in the proposal.
6. WTP 3.00 MLD Capacity
7. CW centrifugal pump
2 nos. pumps of having discharge 19.45 LPS & head 33 meter.
8. CWRM
Length 1152 m, Dia. 200 mm (CI) considered for design in the proposal.
9. ESR
2 nos. existing ESRs having capacity 650 kl & 160 kl (Staging 20 m each)
10. Distribution System
Length 18447 m, Dia. 90 mm – 160 mm HDPE pipe line considered for design in the proposal. Other lines length approximately 5065 m, Dia. 80 -150 mm Ac pipes, these pipes are dilapidated and below ground approximately 3-4 m m hence discarded.
Source: DPR Bada Malhera Town WSS
17. Issues in Present Water Supply System: After analyzing the existing situation of Bada Malhera Nagar Parishad, identified the following list of issues:
• Presently water supply is based on underground water sources which is inadequate to cater the demand of present population
• Water supply quantity is very low compared to per capita supply guidelines (70 lpcd); ground water through tube wells is not reliable and quality is also not appropriate for drinking
• Insufficient supply of water to all consumer ends in all parts of wards.
• Low residual heads at the end of Ferrule ends.
8
• Insufficient quantity of water supply, especially during summer season
• The water table in the area is going down years to years, due to which discharge of existing tube wells is going reduced. Mostly tube wells gets dry during summer. During summer, yield of the tube wells and hand pumps gets considerably reduced and thus town faces acute drinking water scarcity.
• Present water treatment procedure has outlived and is very old and would not purify water to cleanest extent/ to the required levels.
• There is an existing WTP on Garkhuwan road in ward no. 12 within the limit of Nagar Parishad Bada Malhera about 3.6 km away from existing intake site for surface water treatment. WTP have not been used since their construction in 2015. WTP structures were built by the PHE department and due to lack of maintenance; it is in poor condition and need some repairing and rehabilitation work to meet their functional requirements.
• The skill required for maintenance and implementation of proposed treatment method, a comprehensive and continuous training sessions and monitoring team should be appointed for appropriate maintenance of water treatment plant
• Lack of manpower has affected the operation and maintenance of water supply system including the revenue collection.
18. Overall, the current water supply systems in Bada Malhera town suffer from unreliable sources, low coverage, inadequate storage, poor network efficiency and low management capability. C. Components of the Subproject
19. Water Demand: The current (2018) gross water demand of Bada Malhera 1.70 is estimated, while the base year (2020), intermediate year (2035) and ultimate design year (2050) demands are projected at 1.75 MLD, 2.13 MLD and 2.52 MLD respectively.
Table 2: Project Water Demand Per Capita Demand – 70 LPCD + 15% Water Losses
Year 2018 2020 2035 2050
Projected Population
20493 21109 25733 30356
Bada Malhera
1.70 1.75 2.13 2.52
20. Water Source. An alternative source analysis has been conducted to select a feasible and sustainable source of water supply to meet the ultimate design demand. Two alternatives: (i) Ground water; (ii) Katha River were considered as source of water supply and techno-economic and environment studies carried out, indicated that Kathan River is the best possible source. Also, the government policy to utilize surface water source wherever it is feasible worked in favour of using Kathan River as the source of water by constructing a weir and a Pick-up Weir. 21. River Kathan flows in the Western side of the town, which is about at a distance 3.6 km away from the Bada Malhera town and it is the only surface source of water. No other source of water is available nearby. River Kathan is non-perennial River. It has sufficient flow up to month
9
of October and mid of November. Since flow finishes after the rains, therefore additional storage is required for remaining 8 months of the year so that Ultimate demand of the town can be fulfilled. Hence a weir and a Pick-up weir have been proposed in this scheme. The capacity of the proposed weir is 0.835 MCM and that of the Pick-up weir is 0.113 mcm. Pick-up weir will be constructed in the downstream of the proposed weir and existing intake well. There is a low level bridge approximately 300 u/s of intake well site. Hence a weir proposed 135m u/s of the bridge to avoid the submergence of it. Water will be released from weir and pick-up weir will hold the water in the pool.
22. Proposed Project Components. As part of this project, it is proposed to develop a comprehensive water supply scheme based on River Kathan as a source for Bada Malhera town. Proposals include new reliable water source (Kathan River), weir, pick-up weir, utilization of existing intake, raw water abstraction, utilization of existing water treatment plant, energy efficient pumping machinery and clear water storage, Utilization of exiting raw & clear water transmission mains, overhead tanks and distribution network covering the whole town. Necessary rehabilitation and repair works will be carried out at the existing intake, WTP and ESRs. Project will also provide consumer connections with flow meters. Bulk flow meters are proposed at strategic locations to monitor the system performance efficiency. 23. Following Table 3 shows the proposed water supply systems along with nature and size of components in subproject towns. Figure 3 to Figure 15 show the proposed water systems, component layouts etc.
Table 3: Proposed Bada Malhera Town Water Supply Subproject Components Infrastructure Function Description Location
Weir facility
Creating storage in Kathan River by constructing a weir
• Construction of weir having total length of 192 m and height of 6.0 m
Weir will be Constructed across Kathan River in the upstream side of intake well & bridge near Garkhuwan village
Pick-up Weir facility
Creating storage in Kathan River by constructing a pick-up weir. Water after being released from the weir will get stored in the pick-up weir.
• Construction of pick-up wei having total length of 94 m and height of 2.0 m
Pick-up weir will be constructed across Kathan River in the downstream of the proposed weir and existing intake well near Garkhuwan village.
Rehabilitation & repairs of existing Intake Well
Raw water abstraction from Kathan River and supply to WTP
• Rehabilitation and repairs of existing intake well having diameter of 4.0 m and height of 15.0 m and Ports 3 nos. 300 mm dia.
Existing intake well cum pump house is located on the bank of Kathan River near Garkhuwan village, approximately 0.8km upstream of proposed pick-up weir and 0.67 km downstream of weir.
Raw water pumping station
To draw raw water from source for treatment and transmission of raw water up to WTP with adequate pressure
Providing and installation of 02 nos. Raw water Vertical Turbine pump sets (one working and one stand by) of 24.00 KW having motors of 31.67 HP each having discharge of 26.89 lps & pumping head of 61.82 m with 72.00 KVA transformer (for
Raw water pumps will be installed in the existing intake located on the bank of Kathan River.
10
Infrastructure Function Description Location
uninterrupted power supply to pumps and motors) with all other necessary electrical and mechanical installations
Rehabilitation and repairs of Existing Water Treatment Plant (WTP)
Treatment of raw water to meet the drinking water standards as per standard norms
Rehabilitation and repairs of existing WTP having 3.00 MLD capacity: Provision of back wash recirculation and sludge management system Chlorine safety system
Existing WTP is located on Garkhuwan road in ward no. 12, Bada Malhera town
Clear water pumping station
To provide adequate pressure to transmit water to overhead tanks
02 Nos. Centrifugal Horizontal Split Casing Pumps of 27.00 KW along with motors of 35.99 HP having pumping head of 73 m shall be provided with all necessary electrical and mechanical equipment. The discharge of pumps shall be 25.88 lps as required for intermediate phase.
Clear water pumps will be installed in the existing WTP campus near the clear water sump.
Clear water rising main (CWRM)
Treated water transmission to service reservoirs
• Proposed length - 3641 m having Diameter 100 - 200 mm (DI K-9) pipes.
Diameter (mm)
Length (m)
Material
100 1571 DI K-9
150 666 DI K-9
200 1404 DI K-9
Total 3641 DI K-9
• Clear water rising main pipelines will be mostly laid along the main public roads with ROW of Nagar Palika Parishad Bada Malhera, which are wider. Pipes will be laid underground.
OHTs
To distribute clear water from service reservoirs to consumers with standard pressure
Proposed to construct 02 nos. RCC OHT.
• OHT 330 KL having staging height 15 m,
• OHT 100 KL having staging height 18 m,
Utilization of 02 nos. existing OHT after rehabilitation and repairs works
• OHT 160 KL capacity having staging height 20 m,
• OHT 650 KL capacity having staging height 20 m,
• OHT 330 KL capacity located near Sarsawati public School in Ward No. 1, Bada Malhera
• OHT 100 KL capacity located in Kommodpur near Shiv Temple in Ward No. 12, Bada Malhera
Total area required for each OHT is (0.025 ha) site is owned by Revenue Department, GoMP
• OHT 160 KL capacity located near Animal Hospital in Ward no. 14, Bada Malhera.
• OHT 650 KL capacity located near
11
Infrastructure Function Description Location
government school in Ward no. 7, Bada Malhera.
Distribution network I
To distribute clear water from service reservoirs to consumers
• Proposed length - 42417 m having Diameter 110 - 250 mm HDPE PN 10, pipes.
Diameter (mm)
Length (m)
Material
110 38800 HDPE PN 10
140 1994 HDPE PN 10
160 558 HDPE PN 10
180 349 HDPE PN 10
200 536 HDPE PN 10
225 127 HDPE PN 10
250 180 HDPE PN 10
Total 42,417 HDPE PN 10
Pipes will be laid underground along the ULB Pasan roads; this work will cover entire area of the towns; in narrow roads, where there is no place, the pipeline will be laid within the tarmac; where the roads are very wide (15m or more), the pipelines will be laid on both sides of the road
Bulk Water Meters
Monitor water flow in the improved network
17 nos. Fixed at strategic locations at source, OHTs, DMA inlets etc., bulk meters will be fixed with the pipe section
Consumer connection with flow meters
Provide water to consumers and measure water usage
Domestic Connections - 2156 nos. Non-Domestic Connections - 50 nos.
Water delivery pipe (MPDE of dia 20 - 25 mm) will be connected to distribution lines and meters will be attached to the delivery pipe at each house with a meter chamber
D. Description of the Important Individual Components
24. Existing Intake Well: There is an existing intake well on the bank of Kathan River having dia. 4 m and height 15 m near village Garkhuwan in the natural pool about 3.6 km away from Bada Malhera town. There are 3 ports of 300 mm diameter. Intake well have not been used since their construction in 2015. Intake well structure was built by the PHE department and due to lack of maintenance; it is in poor condition and need some repairing and rehabilitation work to meet their functional requirements. The existing intake well will be used after augmentation / rehabilitation. Augmentation / rehabilitation of the old intake well will include repair of civil structures like repair of intake well platform, inlet port, repair of pump floor (supply, erection (installation), testing and commissioning replacement of pumps and machineries), door and windows, installation of Gantry, electrical panels, lightening & other miscellaneous work, fans, colouring and safety features etc. The existing structure as presented in Figure 3 to Figure 4 would be used.
12
Figure 3: Existing Water Abstraction Structure for Bada Malhera Town (to be used after Rehabilitation
13
Figure 4: Photographs of Existing Intake well located on the bank of River Kathan near Garkhuwan village
14
25. Transmission System: Existing raw water pipeline have been laid underground from the intake to WTP site along an existing PWD and ULB road within ROW by PHE Department in 2015. After withdrawal of raw water from existing intake well, it will be conveyed to existing WTP through raw water rising main (Existing: 3600 m long having 200 mm dia. CI Tyton class ‘LA’ pipe). Proposed clear water transmission pipelines of about 3641 m length of dia 100 – 200 mm DI K-9 pipes will be mostly laid along the ULB and NH-86 within ROW. The project also proposes to use and retained as clear water transmission main of about 1152 m having 200 mm dia, CI Tyton class LA from WTP to 650 KL OHT and from 650 KL OHT to main Sagar-Chhatarpur highway junction. Proposed clear water transmission pipelines will be mostly laid along the ULB road and some part along NH-86 roads within ROW. Pipes will be laid underground. The pipes will not traverse any private land across the entire length of the proposed alignment. The existing 18447 m (18.50 km) long HDPE distribution pipe line having diameter ranging from 90 mm-160 mm was laid for distribution on both sides of NH-86. This pipe line was laid by National Highway Authority of India (NHAI) during construction of NH-86. These pipes are in good condition and have been considered in the proposed scheme. Apart from this, it is proposed to have a new 42417 m long distribution pipe line having diameter ranging from 110 mm - 250 mm of HDPE pipes as part of the present program. 26. Existing WTP (3.00 MLD): There is an existing WTP on Garkhuwan road within the limit of Nagar Parishad Bada Malhera about 3.6 km away from existing intake site. WTP have not been used since their construction in 2015. WTP structures were built by the PHE department and due to lack of maintenance; it is in poor condition and need some repairing and rehabilitation work to meet their functional requirements. The existing WTP will be used after augmentation / rehabilitation. Augmentation / rehabilitation of the existing WTP will include repair of sedimentation tank, raw water channel, alum mixing plant, repair of filter bed, scraping of top lay of filter sand and refilling, repair of clear water pump house (supply, erection (installation), testing and commissioning replacement of pumps and machineries), colouring & other miscellaneous works and safety features etc. The existing WTP structure as presented in Figure 5 to Figure 7 would be used. During the design and planning process, the existing WTP at Bada Malhera was thoroughly inspected and audited for the environmental concerns. In addition to assess the structural integrity and physical condition a separate study have been carried out in the DPR. The detail findings of the environmental audit are described in Chapter VI.
15
Figure 5: Existing WTP for Bada Malhera Town (to be used after Rehabilitation)
27. Treatment of Waste/ Backwash Water of WTP: In the existing system it is proposed to use sludge collection sumps for collecting sludge from clarifiers and under drain backwash water tanks for collecting sludge from filtration units. The backwash water will be recycled to the flash mixer and the process will be continuous. All the collected sludge from WTP will be stored in a sludge tank 20mX 10 m. The dewatered sludge from centrifuge will be disposed in the low-lying areas within the campus or provided for brick kilns etc.
16
Figure 6: Google Earth Map Showing Existing WTP Located on Garkhuwan road in Ward No. 12, Bada Malhera
17
Figure 7: Photographs of Existing WTP located on Garkhuwan road in Ward No. 12, Bada Malhera
18
19
28. Audit of Existing OHTs: There are 02 nos. of existing overheat tanks (OHTs) having capacities 160 KL and 650 KL respectively. 160 KL OHT is approximately 20 years old constructed by Bada Malhera Nagar Parishad located in ward no. 14. Existing OHT 650 KL located in ward no. 7, constructed by PHE Department in 2015, since their construction in 2015, it has not been used and due to lack of maintenance; these structures are in poor condition and need some repairing work to meet their functional requirements. These existing OHT will be used after repair and rehabilitation works. Repair and rehabilitation of the existing OHTs will include construction of plinth and repairing of valve chamber, repairing of lightening conductor, Water level indicator, valves and Coloring etc. (apply for both OHT). repairing of office building adjacent to the tank (only for 160 KL OHT) and repairing of boundary wall and gate (only for 650 KL OHT). The existing OHTs structure as presented in Figure 8 would be used. During the design and planning process, the existing OHTs at Bada Malhera was thoroughly inspected and assess the structural integrity and physical condition a separate study have been carried out in the DPR.
Figure 8: Photographs of Existing OHTs in Bada Malhera to be Utilized under MPUSIP
Existing 650 KL Existing 650 KL
20
Existing 160 KL Office building near existing 160 kl ESR
Existing 160 KL
29. Construction works. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. The roads in the core city area of both the towns are very narrow and congested with pedestrians and vehicles, while the roads in outer areas are wide. Other civil works in the subproject include construction of water tanks at the identified sites. These works will be confined to sites, and construction will include general activities like excavation for foundation, construction of foundations, columns, walls and roof in cement concrete and masonry, and fixing of mechanical and electrical fixtures, etc. Weir and Pick-up Weir will involve construction within the water body. A temporary enclosed area (about 10 m dia) will be created using appropriate material and the water will be pumped out to make the area dry for construction. Once this is created, the rest of
21
the construction will follow the general construction procedures. Once the work is over, the temporary structure will be removed. 30. Project benefits. The subproject aims to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The subproject will provide continuous, pressurized and safe drinking water services to entire population of the towns (100% coverage). Besides achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency, the subproject will improve the overall environmental quality of the town. It will reduce the reduced time and costs of households in accessing alternative sources of water, and will lead to better public health particularly reduction in waterborne and infectious diseases.
E. Implementation Schedule
31. After the approval of the detailed project report, bid has been prepared and tenders are invited. Price bid has been opened and is under evaluation, and the contract likely to be awarded in December 2020. Construction is likely to start in March 2021 and will take about 36 months.
22
Figure 9: Key Plan Showing Proposed & Existing Components from Source to OHTs – Bada Malhera Town WSS
23
Figure 10: Google Earth Map Showing Source to OHTs - Proposed & Existing Components, Raw and Clear Water Alignment of Bada Malhera Town WSS
24
Figure 11: Zone plan details
25
Figure 12: Distribution Network Plan (Zone 1)
26
Figure 13: Distribution Network Plan (Zone 2)
27
Figure 14: Distribution Network Plan (Zone 3)
28
Figure 15: Distribution Network Plan (Zone 4)
29
III. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK
A. ADB Policy
32. ADB requires the consideration of environmental issues in all aspects of ADB’s operations, and the requirements for environmental assessment are described in ADB SPS, 2009. This states that ADB requires environmental assessment of all ADB investments. “MPUDC/PMU will adhere to necessary protocols in response to emerging infectious diseases such as the corona virus disease, 2019 (COVID-19) consistent with the guidelines of relevant government healthcare agencies and the World Health Organization. “ 33. Screening and categorization. The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories:
(i) Category A. Projects could have significant adverse environmental impacts. An EIA is required to address significant impacts.
(ii) Category B. Projects could have some adverse environmental impacts, but of lesser degree or significance than those in category A. An IEE is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report.
(iii) Category C. Projects are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed.
(iv) Category FI. Projects involve a credit line through a financial intermediary or an equity investment in a financial intermediary. The financial intermediary must apply an environmental management system, unless all projects will result in insignificant impacts.
34. Environmental management plan. An EMP, which addresses the potential impacts and risks identified by the environmental assessment, shall be prepared. The level of detail and complexity of the EMP and the priority of the identified measures and actions will be commensurate with the project’s impact and risks. 35. Public disclosure. ADB will post the safeguard documents on its website as well as disclose relevant information in accessible manner in local communities:
(i) for environmental category A projects, draft EIA report at least 120 days before Board consideration;
(ii) final or updated EIA and/or IEE upon receipt; and (iii) environmental monitoring reports submitted by the implementing agency during
project implementation upon receipt.
B. National Environmental Laws
36. Environmental assessment. The GoI EIA Notification of 2006 (replacing the EIA Notification of 1994), sets out the requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required for specified activities/projects, and EC must be obtained before any construction work or land preparation (except land acquisition)
30
may commence. Projects are categorized as A or B1 or B2 depending on the scale of the project and the nature of its impacts. None of the components of this water supply subproject falls under the ambit of the EIA Notification 2006, and, therefore no category assigned, and thus no EIA study and EC required for the subproject. 37. Applicable environmental regulations. Besides EIA Notification 2006, there are various other acts, rules, policies and regulations currently in force in India that deal with environmental issues that could apply to infrastructure development. The specific regulatory compliance requirements of the subproject are shown in Table 4.
Table 4: Applicable Environmental Regulations Law Description Requirement
The EIA
notification,
2006 (and its
subsequent
amendments in
2009) provides
for
categorization of
projects into
category A and
B, based on
extent of impact
This states that Environmental Clearance (EC) is
required for specified activities/projects, and this
must be obtained before any construction work or
land preparation (except land acquisition) may
commence. Projects are categorized as A or B
depending on the scale of the project and the
nature of its impacts. Categories A projects
require Environmental Clearance from the
National Ministry of Environment and Forests
(MoEF). Category B projects require
environmental clearance from the State
Environment Impact Assessment Authority
(SEIAA).
Sand borrow soil and aggregate used for road
construction has been classified as a minor
mineral and the quarry/borrow area require prior
environmental clearance
Not applicable.
The sub-project is not included in
schedule of environmental impact
assessment notification 2006 and
its subsequent amendments till
date, so it is not categories as
either Category A or Category B.
As a result, environmental
clearance is not required, either
from the state or the central
Government.
None of the project components
of the water supply system comes
under the provisions of the act
and would require environmental
clearance
However, the quarry or borrow
area from which the sand, soil
and aggregates are procured
need to have a valid
Environmental Clearance by the
District Environmental Appraisal
Committee/ State Environmental
Impact Assessment Authority.
Further as a contractual
obligation the Contractor is
required to submit the
Environmental Clearance
certificate, latest copy of the
latest Compliance Report
submitted to the Madhya Pradesh
State Pollution Control Board and
all other necessary permits to the
PIU before the procurement of
31
Law Description Requirement
the material.
Madhya
Pradesh State
Water Policy,
2003
Prepared in accordance with the National Water
Policy, it states that “for environmental balance, skillful and planned management of all types of
developmental activities, economic use on
equitable basis and in view of the prime
importance of water for all human and other living
beings, an effective and sound water policy is
necessary”.
Policy is detailed in 17 sections dealing with
different aspects of water resources. No. 7 deals
with Water Allocation Priorities, and according to
which drinking water supply shall have the
highest priority followed by irrigation, power,
tourism, etc.
Water Resource Department is nodal department
for permitting different uses of water resources.
Policy also states that “clear provision for reservation of drinking water shall be made in
irrigation projects”
Permission of WRD, GoMP:
• Water abstraction from Kathan River & construction of Weirs across Kathan River for Bada Malhera WSS.
Permission of water resources department (WRD) is a prerequisite for this project. Application already submitted to WRD and it is under process by WRD (Refer Appendix 11)
Water
(Prevention and
Control of
Pollution) Act of
1974, Rules of
1975, and
amendments
Act was enacted to provide for the prevention and
control of water pollution and the maintaining or
restoring of wholesomeness of water, by Central
and State Pollution Control Boards and for
conferring and assigning to CPCB/SPCBs powers
&functions relating to water pollution control.
Control of water pollution is achieved through
administering conditions imposed in consent
issued under to this Act. These conditions
regulate the quantity and quantity of effluent, the
location of discharge and the frequency of
monitoring of effluents. Any component of the
subproject having the potential to generate
sewage or trade effluent will come under its
purview. Such projects have to obtain Consent to
Establish (CTE) & Consent to Operate (CTO)
under Section 25 from Madhya Pradesh Pollution
Control Board (MPPCB)
WTP require CTE (prior to start of
construction) and CFO (prior to
start of operation) from MPPCB.
No consent from MPPCB obtained for the existing 3.00 MLD WTP. PIU/ULB to liaison with MPPCB and obtain valid consent. Application has to be submitted
online at
http://www.mppcb.nic.in/xgn.html
The application for CFO has to be
applied by PMU after the
completion of repair and
rehabilitation works of existing
WTP by the DBO Contractor on
behalf of the Nagar Parishad
Bada Malhera, prior to start of
operation,
Environment
(Protection) Act,
Emissions and discharges from the facilities to be
created or refurbished or augmented shall comply
Appendix 2: Emission and
Discharge Standards Applicable
32
Law Description Requirement
1986 and CPCB
Environmental
Standards.
with the notified standards
The Environment (Protection) Act is an umbrella
legislation seeking to supplement the existing
laws on the control of pollution (the Water Act and
the Air Act) by enacting a general legislation for
environment protection and to fill the gaps in
regulation of major environmental
hazards.
The act empowers central government to make
rules to regulate environmental pollution, such as-
The standards of quality of air, water, soil for
various areas etc.
Prohibits carrying out of any industry, operation or
process which discharges or emits environmental
pollution more than the standards
Regulates handling of hazardous substances.
The law and rule also states, the persons
responsible for discharges, bound to prevent or
mitigate environmental pollution and intimate the
any accidents due to any occurrences.
to The Project.: provides
applicable discharge standards
for ambient air quality,
Appendix 3: provides vehicular
emission norms
Contractor are required to ensure
all emissions and discharges
during civil works conform to all
applicable standards
A comparison of the
environmental standards to the
IFC environmental standards are
provided in Appendix: 5:
Comparison between Indian
Environmental Standards to IFC
Standards
Noise Pollution
(Regulation and
Control) Rules,
2000 amended
up to 2010.
Rule 3 of the Act specifies ambient air quality
standards in respect of noise for different
areas/zones.
Appendix 4: provides applicable
noise standards.
Contractor are required to ensure
all noise-producing activities
during civil works conform to
applicable standards
All equipment procured under the
Act should also conform to the
standards.
Municipal Solid
Wastes
Management
Rules, 2016
Rules to manage municipal solid waste
generated; provides rules for segregation,
storage, collection, processing and disposal.
Requires source segregation of degradable, non-
degradable wastes their treatment and disposal
Solid waste generated at
proposed facilities shall be
managed and disposed in
accordance with the MSWM
Rules
The municipal solid waste
generated from the labour camps
would have to comply with the
provisions of segregation of
waste and its treatment &
33
Law Description Requirement
disposal
Construction &
Demolition
Waste
Management
Rules, 2016
Rules to manage construction & to waste
resulting from construction, remodeling, repair
and demolition of any civil structure. Rules define
C&D waste as waste comprising of building
materials, debris resulting from construction, re-
modeling, repair and demolition of any civil
structure.
Construction & demolition waste
generated from the project
construction shall be managed
and disposed as per the rules
(Appendix 6)
Subprojects would generate
construction waste during the
dismantling of the pavement for
laying of pipeline. These
construction debris should be
used for backfilling as much as
possible and the wastes must be
segregated, stored and disposed
of separately as per the provision
of these rules. A Waste
Management Plan would also be
developed for the project.
Hazardous and
Other Wastes
(Management
and
Transboundary
Movement)
Rules, 2016
According to the Rules, hazardous wastes are
wastes having constituents specified in Schedule
II of the Rules if their concentration is equal to or
more than the limit indicated in the said schedule.
The hazardous waste generated
from the construction e.g. waste
oils, lubricants, and bitumen
would have to comply with the
provisions of the rules with
regards to storage and disposal.
The rules also make it mandatory
for maintaining records and
reporting the same to the
MPPCB.
The Contractor Would have to
obtain an authorization as a
generator of hazardous waste
from the Madhya Pradesh
Pollution Control boards. All the
waste oil, lubricants would have
to be disposed as per the
provisions of the act.
Any discarded asbestos pipes or
extracted asbestos cement pipes
would be considered as a
Hazardous waste as per the rules
and have to be disposed off as
indicated in the rules.
34
Law Description Requirement
Manufacture,
Storage, and
Import of
Hazardous
Chemical Rules,
1989
Defines hazardous chemicals and stipulates
rules, procedures to manufacture, storage and
import of hazardous chemicals requires
permission, authorization from the State Pollution
Control Boards for certain chemicals which have
hazardous property or if the total storage
exceeds specified quantity; requires emergency
management plan.
For storage of Chlorine
permission, authorization is
required from the Madhya
Pradesh State Pollution Control
Board before the operation of the
WTP. An on-site Emergency
Management Plan has to be
prepared for any incidence
related to Chlorine gas.
Regulation of
Polychlorinated
Biphenyls Order,
2016
The use of polychlorinated biphenyls or any
equipment containing PCB would be prohibited
entirely from 31st December 2025.
The technical specification would
clearly state that the transformer
oil should be free of PCBs or else
the Contractor / PMU should
provide a road map for ensuring
the phasing out of all PCB’s by 2025.
Ancient
Monuments and
Archaeological
Sites and
Remains Act,
1958 and
Ancient
Monuments and
Archaeological
Sites and
Remains
(Amendment
and Validation)
Act, 2010
The Act designates areas within 100 meters (m)
of the “protected monument/area” as “prohibited area” and beyond that up to 200 m as “regulated area” respectively. No “construction” is permitted in the “prohibited area” and any construction activity in the “regulated area” requires prior permission of the National Monuments Authority
(NMA).
There are no protected or notable
historical, cultural or tourism
places nor there are any
historically, archeologically
protected areas within the town or
in the project area.
None of the project components
comes under ASI.
Any construction carried out
without the permission under the
Ancient Monuments and
Archaeological Sites and
Remains Act, 1958 will be
considered as an “unauthorized ‘ Construction and would be liable
be removed.
Forest Act, 1927
and Forest
(Conservation)
Act, 1980,
amended 1988
Acts empower the government to declare forest
area (reserve, protected and village forest area)
and regulation of activities within the forests. Use
of forest land for any non- forest purpose and
forest land conservation will follow the guidelines
for “Diversion of forest lands for non-forest
purpose” under Forest (Conservation) Act 1980
None of the project components
comes under forest area.
Notification of
Eco Sensitive
Zones and
Central government notifies eco sensitive zones
Thereby to conserve and protect the natural
resources and living beings a notification under
Applicable to projects located
within core or buffer zone of
Protected Areas (Wildlife
35
Law Description Requirement
Indian Wildlife
(protection) Act,
1972 amended
1993 and Rules
1995 Wildlife
(Protection)
Amendment Act,
2002
the Environmental Protection A.
Provides for the comprehensive protection of
Wild animals, birds and plants .This would cover
matters concerning Appointment of forest
authorities, hunting of wild animals, protection of
specified plants, conservation of national parks
and sanctuaries, trade commerce in relation to
plants and animals and prevention of any
offences.
Sanctuaries, National parks,
biosphere reserves etc.)
There are no protected areas, like
wildlife sanctuaries, national
parks in the vicinity or in the
project areas.
None of the project located within
core or buffer zone of Protected
Areas (Wildlife Sanctuaries,
National parks, biosphere
reserves etc.)
The M.P. Transit
(Forest
Produce) Rules,
2000
As per the provisions of these rule for felling of
tree in non-forest rural areas transit pass is to be
issued by Forest Officer on recommendations of
Panchayat Level Committee. In respect of
Babool, Siris, Neem, Ber, Palas, Jamun,
Reunjha, Bamboo (except in the districts of
Khandwa, Betul, Hoshangabad, Harda,
Chhindwara, Seoni, Balaghat, Jabalpur, Katni,
Mandla, Dindori, Shahdol). Transit pass for the
species other than those mentioned above
Thus in this project for the
pipeline alignment or any other
infrastructure passing through
rural areas and requiring tree
felling would require permission
under this Act.
No felling would be allowed in the
project within the permission
under this act.
The M.P.
Vrikshon Ka
Parirakshan
(Nagariya
Kshetra)
Adhiniyam, 2001
As per the provisions of this act for felling of trees
in urban areas an application has to be made to
the concerned Tree Officer in the ULB for
permission providing details.
The Tree Officer shall provide for permission for
the felling of trees after adequate scrutiny
All trees within the jurisdiction of
the area of the ULB would require
permission from the ULB under
the rule.
No felling would be allowed in the
project within the permission
under this act.
The National
Green Tribunal
(NGT) Act, 2010
NGT provides an effective and expeditious
disposal of cases relating to environmental
protection and conservation of forests and other
natural resources including enforcement of any
legal right relating to environment and giving relief
and compensation for damages to persons and
property and for matters connected therewith.
NGT has jurisdiction over matters related to
Water Act, 1974; Water Cess Act, 1977; Forest
(Conservation) Act, 1980; Air Act, 1981;
Environment (Protection) Act, 1986; Public
Liability Insurance Act, 1991; and Biodiversity
Act, 2002. Consequently, no other court will have
jurisdiction over the matters related to
Stakeholders / affected persons
may approach NGT to resolve
project induced environmental
issues
36
Law Description Requirement
environment falling under the above referred
Acts. Being a dedicated tribunal for environmental
matters with the necessary expertise to handle
environmental disputes.
Labor Laws The contractor shall not make employment
decisions based upon personal characteristics
unrelated to job requirements. The contractor
shall base the employment relationship upon
equal opportunity and fair treatment, and shall not
discriminate with respect to aspects of the
employment relationship, including recruitment
and hiring, compensation (including wages and
benefits), working conditions and terms of
employment or retirement, and discipline. The
contractor shall provide equal wages and benefits
to men and women for work of equal value or
type.
Appendix 7, provides applicable
labor laws including amendments
issued from time to time
applicable to establishments
engaged in construction of civil
works.
Indian Drinking
Water
Standards
Gives details of the permissible and desirable
limits of various parameters in drinking water as
per the Bureau of Indian Standards
Appendix 8- provides drinking
water standards
38. ADB SPS Requirements. During the design, construction, and operation of the project the PMU and PIUs are required to apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines1 and Sector Specific (Water and Sanitation) Guidelines2). These standards contain performance levels and measures that are normally acceptable and applicable to projects. When Government of India regulations differ from these levels and measures, the PMU and PIUs will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the PMU and PIUs will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS. International acceptable air and noise quality guidelines are provided below:
1https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 2 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES
37
Table 5: WHO Ambient Air& Noise Quality Guidelines
IV. DESCRIPTION OF THE ENVIRONMENT (BASELINE DATA)
A. Methodology Used for Baseline Study
39. Data collection and stakeholder consultations: Data for this study has been primarily collected through comprehensive literature survey, discussion with stakeholder agencies, and field visits to the proposed subproject sites. 40. The literature survey broadly covered the following: (i) Project details, reports, maps, and other documents prepared by DPR consultant
(ii) Discussions with Technical experts, municipal authorities’ relevant government agencies like WRD, ULB etc.
(iii) Secondary data from previous project reports and published articles, and (iv) Literature on land use, soil, geology, hydrology, climate, socioeconomic profiles,
and other planning documents collected from Government agencies and websites.
41. Ocular inspection: Several visits to the project sites were made during IEE preparation period in 2019 to assess the existing environment (physical, biological, and socioeconomic) and gather information with regard to the proposed sites and scale of the proposed project. A separate socioeconomic study was conducted to determine the demographic information, existing service levels, stakeholder needs and priorities.
38
B. Physical Environment
1. Location, Area & Connectivity
42. Bada Malhera is a town and a Nagar Parishad in Chhattarpur district in the state of Madhya Pradesh, India. It belongs to the Sagar division. It is located 54 KM towards Southwest from District headquarters Chhatarpur. It is situated at 24º 40' N and 79º 18' E and is 325 m above sea level. Bada Malhera is situated on NH - 86 connecting Sagar to Kanpur. National Highway (NH-86) passes through the town. The distance form Chhattarpur is about 54 Km. Tikamgarh is 60 km and Indore is 300 km and state capital Bhopal is 281 km form Bada Malhera. Bada Malehara is bounded by Bijawar Tehsil towards East, Baldeogarh Tehsil towards North, Buxwaha and Shahgarh Tehsils towards South. Chhatarpur, Tikamgarh, Nowgaon and Damoh are the nearby Cities to Bada Malhera. 43. Bada Malhera town is established as Nagar Parishad in 1983. Bada Malhera Nagar Parishad (BNP) area comprises of 15 wards having the territorial jurisdiction of the Bada Malhera Nagar Parishad spans an area of 20.87 Sq.km. The study area covers only within the Bada Malhera Nagar Parishad limits. 44. Bada Malhera is situated on NH - 86 connecting Sagar to Kanpur. National Highway (NH-86) passes through the town. Bada Malhera is linked to other areas by road network only. The nearest railway station is Chhatarpur railway station, which is nearly 54 km from the town and accessible via road network. Other nearest railway station is Teekamgarh (65km), Khajuraho (95km), Harpalpur (105km), Mauranipur (105km), Sagar (110km), Jhansi (175km) and Satna (190km) and is located on main Allahabad – Itarsi sector of Western Central Railways connect the main Jhansi - Bhopal sector from Bina. The nearest airport is also at Khajuraho, which has daily flights to and from the National Capital.
2. Topography, Soils and Geology
45. The topography of the town is flat. The slope is towards South-western direction and the drainage from local Nalas reach Harijan Nala. The storm water and domestic waste water of the town is primarily channelized through a local drains known as Harijan nala which passes through the town in the north-west direction and ultimately discharges into the Kathan River (a tributary of Dhasan River) and finally discharges into the Dhasan River, a tributary of river Ganga. 46. The soils in Bada Malhera is mixed red and deep black soil. It supports the agriculture and some parts of hinterland are very fertile. The plateau area is either bare or stony on steep slopes or is covered with reddish soil or black cotton soil. The alkaline soil is grey, sticky on wetting and hard on drying acquiring a cloddy structure. Growth of crops or flora is difficult at places where undulating Kankar layer often comes up on the surface in any soil region. Due to alternate leaching and capillary rise of moisture the subordinate layer of calcium carbonate is also undesirable. 47. Physiographically the district has been divided broadly in to three main geomorphic units. The Panna range, the central plateau & northern plains range which traverses district in a south west north east direction. This range separates the upper Bundelkhand from lower bundelkhand plateau. Overlying the archeans is if formed by Bijawar and vindhyan beds which are highly folded and are also dissected by the superimposed drainage system.
39
3. Seismology
48. As per the seismic zoning map of India, project area falls under Zone II, which is the lowest earthquake risk zone in India. This zone is termed as “low damage risk zone”.
4. Climatic Conditions
49. Bada Malhera town can be classified into four seasons. Winter, Summer, Monsoon and post Monsoon or Transition period. Winter lasts from November till February, summer from March to Mid-June, Rains or southwest monsoon season from Mid-June to September, with the Maximum number of rainy days experienced during the months of July and August. October is generally transition month form monsoon to winter. 50. Temperature: The temperature starts rising from the middle of February and reaches maximum during the month of May. The daily maximum temperature during the month of May is around 42.7°C, while annual daily maximum normal temperature is around 32.6° C the day temperature on individual days during the summer season goes up to around 45°C. On the arrival of monsoon at the end of June there is a dip in temperature and weather becomes pleasant. After withdrawal of monsoon early in October, there is slight increase in day temperature. After October or from middle of November both the day and night temperature starts falling and lowest temperature recorded in the month of January. The minimum mean normal daily temperature is about 7.5"°C and the annual daily mean normal temperature is about 18.6') °C. Sometimes, the minimum temperature drops down to even as low as 1 & 2° C. 51. Relative Humidity: The summer season with the driest period of the year. Hence humidity is also very low during the summer season. The minimum humidity recorded during the month of April/May about 33%. May is the driest month of the year. On the arrival of Southwest monsoon, the humidity increases and highest recorded during the month of August i.e., 85%. and the rest of the year is drier. The humidity again decreases withdrawal of monsoon and due to high temperature. 52. Wind Velocity: The wind velocity is high during the pre-monsoon period as compared to post monsoon. The highest wind velocity is recorded during the month of June and minimum 1- 8 km/hr during the month of November. The mean monthly normal wind velocity during the month of June is around 8.2. The annual average normal wind velocity is around 4.1 to 4.5 Km/hr. 53. Rainfall: The normal annual rainfall of Bada Malhera town in Chhatrpur district is 1068.3 mm. Bada Malhera town receives maximum rainfall during the southwest monsoon period. The Southwest monsoon arrives at the end of June and last till end of September. About 91% of the annual rainfall received during monsoon season i.e between June to September. Only about 2% of the annual rainfall takes place during winter season from October to February and only about 7% of the annual rainfall takes place during the summer season i.e., between March to May. Hence only about 9% of the annual rainfall takes place from October to May. Thus, the surplus water is available only during the southwest monsoon. July is the wettest month of the year.
5. Surface Water
54. There are primarily two water bodies existing in the Nagar Parishad area is Harijan Nallah and Bada Malhera Talab is connected through natural drain system for carrying the storm water discharge. The water bodies mainly Bada Malhera Talab can be utilized not just as
40
environmental assets but also for recreation and improving the overall ambience of the Nagar Parishad. The present condition of the Bada Malhera Talab inhibits such a benefit which needs to be addressed. The flow of domestic sewerage into the open drain which leads this sewerage into the nearby water bodies is resulting in pollution of water in the Surface water bodies existing in the Nagar Parishad. This untreated sewerage is finding its way in to major water bodies and other natural streams creating a hygienic condition and detoriating the environment. Other major streams passing /covering the area which are Harijan Nala. The storm water and domestic waste water of the town is primarily channelized through Harijan Nallah which passes through the town and ultimately discharges into the Kathan River (a tributary of Dhasan River) and finally discharges into the Dhasan River, a tributary of river Ganga at the downstream of the river. Kathan River is non-perennial River. It flows in the Western side of the town. It has sufficient flow up to month of October and mid of November. Since flow finishes after the rains.
6. Groundwater
55. Chhatarpur district is characterized by variety of geological formations representing vast period of geological time. The predominant geological formations are Recent Alluvium, Deccan Traps, Vindhyans, Bijawar & Bundelkhand Granite etc. Major water bearing formation are Recent Alluvium, Deccan Traps, Vindhyans, Bijawar & Bundelkhand Granite etc. 56. Bada Malhera comes under Bhundelkhand region. This region is covered by Bhundelkhand granite in northern part with thin soil cover. This region is very hard and compact with well-developed joints. These joints were open at the surface and persist to about 20m below the surface. Ground water in this region also occurs in weathered mantle in joints and fracture under water table condition and can sustain well having up to 2lps discharge. Ground water in the alluvium also occurs under water table conditions. 57. Ground water level in this region ranges from 2.1 to 23.63 mbbgl during pre-monsoon in the year 2015. Shallow water level in the district is less than 3m in north eastern and south eastern part of the district. Whereas in the post monsoon period the water level ranges from 0.89 mbgl to 12.8 mbgl with a shallow water level of less than 5m occurs in northern central & southern parts. est and pas. The deepest water level is 12.8 mbgl, observed in the north-west part. The long-term water level trend (1997-2015) shows declining trend ranges from 0.0015 to 0.64 m/year (Annual) water level fall is noticed in all block. 58. As per CGWB report Chhatarpur district- Dynamic ground water resources of the district have been estimated for base year -2008/09 on block-wise basis. There are eight number of assessment units (block) in the district which fall under non-command (96%) and command (3%) sub units. All blocks of the district in command area are categorized as safe blocks. Bijawar Gaurihar and Loundi blocks in non-command sub units are safe. Bada Malhera, Buxwaha, Chhatarpur, Nowgaon and Rajnagar are under semi critical and highest stage of ground water development is computed as 93 % for Chhatarpur Block. Bada Malhera town comes under Bada Malhera block is under semi critical zone. Ground water development for Bada Malhera block is computed as 75%. The net ground water availability in the Bada Malhera block is 8,382 ham and ground water draft for all uses is 5,118 ham, making stage of ground water development 61% as a whole for Bada Malhera block. After making allocation of 481 ham for future domestic and industrial supply for next 25 years, balance available ground water for future irrigation would be 3,131 ham. 59. Ground Water Quality: The quality of ground water for drinking purpose were analyzed for detailed chemical analysis. The pH value of water samples shows slight alkaline in nature
41
and within permissible limit (6.5 to 8.5) as described by BIS (1991). The salinity of the water is represented by the electrical conductivity. The electrical conductivity depends upon the concentration of dissolved inorganic salts in the water. The EC values in district were within BIS limit (1000 μS/cm2) and found to be in the ranges between 375 - 2160 μS/cm2 at 25°CThe concentration of NO3 The nitrate concentration in the district ranges 2 to 288 mg/l. The fluoride concentration in the district ranges between 0.14 to 1.78 mg/l. There is no problem of excess fluoride in the shallow ground water of the district. Source: Chhatarpur District Groundwater Information Booklet, CGWB - 2013 & Aquifer Mapping Report, Chhatarpur District 2018
7. Air Quality
60. There is no data on ambient air quality in Bada Malhera towns, which is not subject to monitoring by the Madhya Pradesh Pollution Control Board (MPPCB) as there are no major industries. Located in the semiarid drought prone Bundelkhand region, particulate matter is likely to be high, particularly during summer months. As the National Highway NH-86) passes through the town there are number of trucks, Buses and other Modes of Transport pass through the town. Traffic is the only significant pollutant, so levels of oxides of sulphur and nitrogen are likely to be well within the National Ambient Air Quality Standards (NAAQS). 61. No field monitoring (environmental) survey was conducted however, the environmental monitoring program developed as part of the environmental management plan (EMP) will require the contractors to establish the baseline environmental conditions prior to commencement of civil works. The results will be reported as part of the environmental monitoring report and will be the basis to ensure no degradation will happen during subproject implementation. C. Ecological Resources
62. Project area mostly comprises urban areas, agricultural areas and open areas of Bada Malhera, which are converted to human use many years back. There is no forest area within the limit of project area. None of the project components are located in the forest areas. Bada Malhera is dominated by open, dry barren and agricultural areas. The tree density is very less in the study area. As per studies in Bada Malhera Nagar Parishad area, the observed Flora are Neem (Azadirachta indica), Mango (Mangifera indica), Saja(Terminalia elliptica), Siris (Albizia lebbeck), Dhao (Dracontomelon dao), Shisham (Dalbergia sissoo) etc. The roadside vegetation is mostly thorny and dominated by different species of Prosopis and Zyzypus. Other tree species observed in the study area are Butea monosperma, Bombax ceiba mangifera indica Eucalyptus spp, Delonix regia, Ipomeas pp., Zyzypus zuzuba, Bamboo spp, Acacia catechu Acacia nilotica, prosopis juliflora, Calotropis procera, lantana camera, Azadirachta indica, Ficus benghalensis, Agave americana etc. The observed Fauna in the region is the Mammal species commonly observed are including Bat, Mongoose, Rabbit Jackal, fox, Squirrel, etc. Grazing activity mostly performed by domestic animals like cow, buffaloes, goat etc. Aquatic life in the project areas is not notable, given low rainfall semi-arid zone. Common and local species of fishes and aquatic plants are found in water bodies like Bada Malhera Talab and Kathan River in and around Bada Malhera Nagar Parishad area. 63. There is no forest land involved in the laying of clear water rising main, as there is no forest areas across the entire length of proposed clear water rising main alignment. The shoulder of the road would be used; No tree felling is involved as per the preliminary survey. No trees cutting will be required during laying of CWRM.
42
D. Economic Development
1. Land use
64. The total land area in Bada Malhera is 20.87 Sq.km. The area under agricultural use is 6.12 Sq.km, which is around 47.37% of the total area, rest of the area is around 6.80 Sq.km (52.63% of the total area) is existing under the total development area. The details of the existing land use is shown in the table 6, below.
Table 6: Existing Land Use Details
S. No. Land use Category Existing Land use (in Percentage)
1 Residential 42.12
2 Commercial 2.10
3 Public - semi public 6.50
4 Industrial 6.90
5 Roads 9.51
6 Green area/Open 28.37
7 Water bodies 4.50
Total 100.00
2. Industry & Agriculture
65. The economy of the town is mostly and mainly dependent / based on farming and agricultural products, trade & Commerce and administrative activities. Some of the locals are well-known grain merchants. As per the primary and secondary survey, primary sector is playing main role in the economy of the town. The economy of the town is based on the primary sector. Hence, it may be stated that Bada Malhera’s economy has an agricultural based economy. The main crop of the town and surrounding areas are sorghum, wheat, rice, millets, soybeans, pulses, oilseeds, cotton, sugar cane and medicinal crops. Bada Malhera has only some small household industries. Around 7% of working population is involved in household industrial activities.
66. Trade and Commerce: The village which has been very recently upgraded to town is predominantly agricultural in nature. The Nagar Parishad caters to the trading and other activities of the surrounding smaller villages. Weekly market is also held in the town.
67. Mandi: The city has class `C' mandi. The town provides a platform for wholesale of agricultural products. This is a very important activity for the economic growth of the town. Since there are no other major towns near Bada Malhera, the agricultural produce of the remote areas are brought into Bada Malhera for sale. Agricultural produce by small businessmen are also brought here for sale. At present the mandi and other government committees have undertaken the maintenance responsibility for the entire agricultural produce.
68. Tourism: The ancient Devangri Jain mandir is located in Bada Malhera. People of Jain Community from across the country & world visit this Temple. Every year a Jain mela is held at this place which attracts big crowd. Along with these there is the Hanuman Bagh holds a beautiful park with Hanuman Mandir.
43
69. Work Force participation: As per 2011 census, the total working population of main workers is 5929 which is 32.45% of the total population. The population percentage of main workers in Agriculture activities is 35.8 (which include Cultivators-22% & Agriculture Labour 14%), manufacturing activities is 7% and other services are 57%.
3. Infrastructure
70. Sewerage. There is no sewerage collection and treatment system in the towns. Households mainly depend on individual sanitation systems like pit latrines, septic tanks etc. Open defecation is also prevalent in the project area. Septage from septic tanks is collected by mobile tankers with suction arrangement. Disposal of the untreated sewerage in to Harijan Nala which is ultimately discharges in to Kathan River. This location is on the downstream of the proposed intake and weir. Sewerage and sanitation systems needs to be improved in the town to meet the increased wastewater generation due to improvement in water supply.
71. Solid Waste Management. There is no proper solid waste management system in the town. Bada Malhera Nagar Parishad is responsible for collection, transportation and disposal of Solid Waste of their areas. Waste generated in the towns are collected and disposed by crude open dumping method in the outskirts of the town. There is no engineered landfill site in Bada Malhera.
72. Storm Water Drainage. Open drainage system is provided in town for collection and conveyance of rain water from the town. Due to lack of sewerage system, the drains are presently carrying wastewater including sewage. Since rains are confined only to a short duration in monsoon, the drains mostly carry wastewater. Low discharge carrying capacity of the drains, encroachments and indiscriminate disposal of solid waste into drains is common, due to which drains are often chocked, creating unhygienic conditions.
73. Power Supply: The main source of electricity in DBada Malhera town is MPSEB which covers 65-70 percent of the Nagar Parishad area and it serves almost 100 percent of the population. The connection of electricity is good in terms of service reach. The town is provided 14 hours of supply per day. During summer season time of power cut off increases due to load shedding.
74. Transport. The old town areas of Badal Malhera are characterized by very narrow roads that are frequently congested with traffic and pedestrians. In contrast the remainder of the town has a relatively good road system, particularly in the outer areas, where streets are wide and not heavily used by traffic. Roads are surface either with bitumen or concrete, and roads in the outer areas are mostly unpaved. Most of the roads are maintained by Nagar Parishad Bada Malhera except the main roads connecting other towns and villages, which are maintained by the Public Works Department (PWD) and NHAI. The condition of the road is generally poor, with many roads in need of repairs and resurfacing. Bada Malhera Nagar Parishad is currently improving some of the important roads in the town.
75. The average width of road in Nagar Parishad area varies from 3.1 m to 14 m. The total length of Road Network in Bada Malhera including B.T. Roads, Cement Concrete Roads, W.B.M. Road & Earthen Roads is around 63 Km. Most of inner roads at present are narrow and some of them are paved with flagstone i.e., they are pedestrian in nature.
44
E. Socio Cultural Resources
1. Demography
76. According to the census, the population of Bada Malhera was 18335 in 2011, increased from 15,044 in 2001, which shows an increase of 21.88% over the decade. The previous decade of 1991-2001 experienced a very high growth of 34.98%, which is mainly due to inclusion of surrounding villages in the municipal limits. Overall literacy is 68.8% (which is lesser than the state average of 69.3%. The literacy figures are reported at 78.9% for males and 57.5% for females. The sex ratio is 914 females per 1000 males, less than the state average of 918. With an area of 20.87 sq. km under the municipal limits, gross population density is very low (879 persons/Sq.km), but this varies across the area, as most of this area is undeveloped, and in the core area of the town, population is dense. About 4.53% of the population are scheduled tribes (ST), but these are part of the mainstream population, and about 18.71% belong to scheduled castes (SC). Main language spoken the project areas is Hindi.
2. History, Culture and Tourism
77. Religious Importance and Tourism: The town was previously under the then Vindhya Pradesh. However, it became a part of Madhya Pradesh after its formation. There are no notable historical, archeological or tourism places in Bada Malhera. The ancient Devangri Jain mandir is located in Bada Malhera. People of Jain Community from across the country & world visit this Temple. Every year a Jain mela is held at this place which attracts big crowd. Along with these there is the Hanuman Bagh holds a beautiful park with Hanuman Mandir. Khajuraho, Panna, Ajaigarh, Deogarh & Orchha are the nearby Important tourist destinations. There are no protected monuments or places of archeological or historical importance in the project area.
F. Subproject Site Environmental Features
78. Site visits were carried out to the subproject component sites to identify the environmental sensitivities at the site. The environmental features at the selected subproject sites and site photographs for Bada Malhera town WSS are presented in the following Table 7. Site environmental features of Bada Malhera town w.r.t. water supply components are shown in the Google Earth Map in the Figure 6, Figure 10 and Figure 16 to Figure 19 respectively. Also Refer Appendix 19 - For GPS Coordinates of Proposed/Existing WSS Components Sites of Subproject Town – Bada Malhera under Package 6K respectively.
45
Table 7: Site Environmental Features of Proposed WSS Components of Bada Malhera Town S. No. Infrastructure Locations & Environmental Features Site Photographs
1.0 Proposed Weir (Latitude – 24°35'30.12"N Longitude - 79°16'26.15"E) & Pick-up Weir (Latitude – 24°36'16.52"N Longitude - 79°16'16.43"E)
Existing Intake Well (Latitude –24°35'51.86"N Longitude - 79°16'26.41"E)
A Weir and a Pick-up Weir has been proposed to
construct across Kathan River under the control of
Water Resources Department, GoMP near
Garkhuwan village about 3.6 km away on north-west
of Bada Malhera town to store water in the river
required for non-rainy season (8 months of the year)
so that ultimate demand of the town can be fulfilled.
The existing water supply scheme based on Kathan
river has become inadequate to meet the present
water demand of the town because there is no
storage structure for non-rainy season. Therefore,
additional storage is needed.
As there is a low level bridge approximately 300 u/s
of existing intake well site. Hence a weir is proposed
about 135m u/s of the low bridge to avoid the
submergence of it. Refer Figure 16, below.
There is an existing intake well in between proposed
weir, low level bridge and pick-up weir on the bank of
Kathan River having dia. 4 m and height 15 m near
village Garkhuwan in the natural pool.
Proposed weir will be constructed on upstream of
existing intake well (about 0.44 km away) & from Low
bridge (about 0.135 km away). Proposed pick-up
weir will be constructed in the downstream of the
proposed weir (about 1.47 km away) and from
existing intake well (about 0.8 km away). Water will
be released from weir and Pick-up weir will hold the
water in the pool and then raw water will be
abstracted from pick-up weir across Kathan River
Site Photographs of Proposed Pick-up Weir
46
S. No. Infrastructure Locations & Environmental Features Site Photographs
through existing intake and supply to WTP.
Kathan River originates from the hill near Tatarwara village, Shagarh Tehsil in Sagar district (Madhya Pradesh). It is tributary of Dhasan River. Prior merging with River Dhasan, the river navigates all through the area of Bundelkand. The river goes through the districts of Sagar, and Chhattarpur district in Madhya Pradesh. Kathan River flows towards North-East from South-West and passing throw Tatarwara, Luharra, Bilagram, Bagrohi, Karrai, Rampur, Rajpur Kalan, Patan, Barma, Garkhuwan, Kayan, Sijwaha, Silaro, Bamni, Morra village and enters into the Dhasan River at Devran village in Chhattarpur district (M.P.) as shown in Figure 20, below. The Dhasan River is a right bank tributary of the Betwa River. Kathan River has total length of around 91 km from origin to the meeting point of River Dhasan. Kathan River is non-perennial. Kathan River has not sufficient flow throughout the year. It has sufficient flow upto the month of October and mid of November. But Kathan River has sufficient width and bank to store the water required for the drinking needs. Kathan River having significant flow variations over the seasons. Kathan River flow is very high during monsoon period in the months of July to August and maintains high flow in the months of September to mid of November. By the mid of November flow reduces, and for the two months, flow is medium to low from mid of November to December. In January, river carries low to very flow, and River complete run dry during the months of March to June months, and up to the arrival of monsoon in late June as mentioned in Table 9. The 6m height of weir and 2m height of pick-up weir are proposed to meet the water storage requirement, and also to limit the water storage / submergence within river course. Considering the height of river
Site Photographs of Existing Intake Well
47
S. No. Infrastructure Locations & Environmental Features Site Photographs
banks which is about 8-10 m high from the bed of the River (Refer Figure 28 - Site Photographs of Kathan River), the proposed weir (6m height) and Pickup-up weir (2m height) is much below the river banks i.e. (proposed weir is about 2-4 m and pick-up weir is about 6-8 m below the river banks). River Kathan bed level is (289m) and HFL is 297.25m. As mentioned above, the height of weir in both the cases is less than the height of the river banks and HFL, and therefore the water storage is confined to river course / flood plain, and there is no submergence of lands outside the river. No negative impacts or acquisition of government of private or government lands anticipated. Therefore, there are no impacts due to submergence. The proposed weir and pick-up weir is located
approximately 78.27 km & 79.74 km respectively
from the river origin point and about 12.65 km and
11.18 km away from final destination point of Kathan
River (meeting point of Kathan River into Dhasan
River). Existing intake is located approximately 0.67
km downstream of proposed weir and 0.8 km
upstream of proposed pick-up weir. Except this there
is no other water intake either on upstream or
downstream of River Kathan from proposed
weir/pickup weir site. There are 18 no’s existing
weirs/check dams on u/s side w.r.t. proposed
weir/pick-up weir & 01 no. weir/ check dam on d/s
with respect to proposed weir/pick-up weir exist in
the Kathan river from origin to destination. Nearest
dam (U18) on the upstream is at 31.95 km from
proposed weir and about 33.42 from proposed pick-
up weir and nearest dam (D1) on downstream is at
about 2.15 km from proposed weir and 0.68 km from
48
S. No. Infrastructure Locations & Environmental Features Site Photographs
proposed pick-up weir. These existing weirs/ check
dams have been constructed by different
departments of Government of Madhya Pradesh
under various schemes. Information on these
structures is not readily available. Most of these
existing weirs/dams are very small in size and their
capacity is less than 0.5 MCM except Bila dam (56.7
MCM). Bila dam is located at about 56.89 and 58.36
km upstream of the proposed weir and pick-up wer.
Details of existing weirs/dams are given in the
Table 8. Apart from this, there are 51 natural
rivulets/streams join Kathan River from origin to
destination of river (Refer Figure 27). Out of 51
rivulets/streams, 27 streams join from left side and
24 streams join from right side to River Kathan.
Besides these, there are 43 natural rivulets/streams
join Kathanl River from upstream of proposed Weir.
Out of 43 rivulets/streams, 22 streams join from left
side and 21 streams join from right side to River
Kathan. All said streams are the natural drains that
carry runoff generated in the catchment area through
precipitation.
Weirs and intake facilities are located outside the
town and are mostly surrounded by agricultural and
barren land and rivers/reservoirs etc. There is no
notable, protected or unique aquatic plant/ creatures.
The Aquatic life in the river is limited to local common
species of fishes and aquatic plants. There is no
commercial fisherman activity take place in and
around the weir/intake sites. The aquatic plants in
river are floating plants Nelumbo Nucifera, Bispinosa,
Aponozeton etc. No notable sensitive features are
Site Photographs of Proposed Weir
49
S. No. Infrastructure Locations & Environmental Features Site Photographs
found. There is no forest area in the downstream of
the proposed intake.
There are trees, bushes and vegetation on both
sides of river banks across which Proposed weir is to
be constructed. Removal of trees and vegetation will
not require during implementation phase as the work
is confined to within river bank only. Trees found
along River banks are Acacia, Tamarind, kava,
Soapnut (Reetha), Palash, Mango, Chola, Mahua
and some other trees are commonly seen. There is
no polluting source like industry in the catchment
areas or town situated in this patch of river, only
agriculture fields are found. Habitations are limited to
small villages. Therefore, no significant impacts
envisaged.
2.0 Clear Water
Rising Main
(CWRM)
Proposed CWRM pipelines of about 3641 m length
of dia 100 – 200 mm DI K-9 pipes will be mostly laid
along the ULB road and some part along NH-86
roads within ROW. Pipes will be laid underground.
The pipes will not traverse any private land across
the entire length of the proposed alignment
There is no forest land involved in this as there is no
forest areas across the entire length of proposed
alignment. The shoulder of the road would be used;
No tree felling is involved as per the preliminary
survey. No trees cutting will be required during laying
of CWRM.
50
S. No. Infrastructure Locations & Environmental Features Site Photographs
51
S. No. Infrastructure Locations & Environmental Features Site Photographs
3.0 Proposed OHT (100 KL) Near temple (Latitude –24°34'20.42" N Longitude - 79°17'43.02"E)
One OHT of 100 KL capacity is proposed at Kommodpur in Ward No. 12 near Shiv Temple in Bada Malhera Nagar Parishad. Site is about 200 m away from temple as shown in site photograph. Site is located in the south-western side within the town. Site is currently vacant and barren land with no tree cover. There are trees on the periphery of the site. However, none of the activities are planned in this strip of land. No tree will be cut during construction of OHT. Rock outcrops are visible on the site. No environment impacts envisaged. Selected site is owned by Revenue Department, GoMP. Total area required for OHT is 0.025 ha. Available land area is 4.270 ha under Khasra no. 129.
4.0 Proposed OHT (330 KL) Near Sarswati Shishu high School (Latitude –24°33'23.67" N Longitude - 79°18'32.47"E)
OHT of 330 KL capacity is proposed nearby Sarsawati Public School in Ward No. 01, Bada Malhera Nagar Parishad. . Site is located in the south-eastern side within the town. Site is currently vacant, barren land and free of vegetation with no tree cover. There are no trees in the site. Site is covered with rock out crops, which is visible on the site. Selected site is owned by Revenue Department, GoMP. Total area required for OHT is 0.025 ha and available land area is 1.395 ha under Khasra no. 2441/1.
52
S. No. Infrastructure Locations & Environmental Features Site Photographs
5.0 Distribution
Network
Pipes will be laid along the roads/streets in the towns
within the road right of way (ROW). In wider roads
pipes will be laid in the road shoulder, and in narrow
roads, where there is no space, pipes will be laid in
the road carriage. Roads in the old part of the town
are quite narrow (~3m), and in the rest of the town
roads are wider. There are open drains on both sides
of the town road. There are no trees along the roads,
except in some new colonies in the outer areas. In
old town areas pipes will be laid in the middle of the
road, which may affect the traffic. In Bada Malhera
town it is proposed to have a new distribution
network, with HDPE pipes as part of the present
program. There are about 5.6 km length of AC pipes
underground laid many years back. These pipes are
about 3-4 m below groundlevel and are old. These
pipes will not be used or disturbed during
construction and would remain in-situ.
Distribution network pipe lines will not be laid in
forest areas or water bodies as there is no
involvement of forest land nor comes along water
bodies. Hence there is no environment impacts
envisaged.
53
S. No. Infrastructure Locations & Environmental Features Site Photographs
54
Figure 16: Google Earth Map Showing Proposed Weir, Pick-up Weir & Existing Intake Well of Bada Malhera WSS
55
Figure 17: Google Earth Map Showing Proposed / Existing Components of Bada Malhera WSS
56
Figure 18: Google Earth Map Showing Proposed OHT 160 KL - Bada Malhera Town WSS
57
Figure 19: Google Earth Map Showing Proposed OHT 330 KL - Bada Malhera Town WSS
58
V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
79. Potential environmental impacts of the proposed infrastructure components are presented in this section. Measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended. 81. Screening of potential environmental impacts are categorized into four categories considering subproject phases: location impacts and design impacts (pre-construction phase), construction phase impacts and operations and maintenance phase impacts.
a. Location impacts include impacts associated with site selection and include loss of on-site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site.
b. Design impacts include impacts arising from Investment Program design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services.
c. Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production.
d. O&M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.
82. Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent). 83. This section of the IEE reviews possible project-related impacts, in order to identify issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require that impacts and risks will be analyzed during pre-construction, construction, and operational stages in the context of the project’s area of influence. 84. The ADB Rapid Environmental Assessment Checklist in http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002.aspis used to screen project for environmental impacts and to determine the scope of the IEE. 85. In the case of this project (i) most of the individual elements are relatively small and involve straightforward construction and operation, so impacts will be mainly localized and not greatly significant;(ii) proposed water abstraction from the sources is very small compared to overall water availability, and the design of weir ensures that water impoundment is confined to river course itself; (iii) most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving excavation and earth movements; and some works are located in the reservoir and (iv) being mostly located in an urban area, will not cause direct impact on biodiversity values. The project will be in properties held by the local government and access to the project location is through public rights-of-way and existing roads hence, land acquisition and encroachment on private property will not occur.
59
A. Pre-Construction Impacts – Design & Location
86. Design of the Proposed Components. Technical design of the (i) Weir & Pick-up Weir; (ii) Repair & rehabilitation of existing intake facilities, (ii) Repair & rehabilitation of existing water treatment plant; (iii) clear water mains, (iv) storage reservoirs, and (v) distribution network, connections, flow meters, etc., follows the relevant national planning and design guidelines, focusing on providing a robust system which is easy to operate, sustainable, efficient and economically viable. Besides, the project also included the following environmental considerations:
(i) Discontinuation of current unsustainable groundwater source and developing a surface water source (Kathan River) based system by constructing a weir, pick-up weir for creating storage; duly utilizing the existing infrastructure like intakes and water treatment plant with necessary repairs and rehabilitation
(ii) Limiting the height of water impounding structures (weir and pick-up weir) well below the height of the river banks so that the water storage is confined to the river course
(iii) Design of apron to arrest erosion of the river bank of the downstream of weir and pick-up weir
(iv) Provision of low level sluice gates to allow heavy monsoon flow freely without any obstruction and to avoid dam silting.
(v) Recovering backwash water from treatment process (vi) Rehabilitation and repair of existing WTP and Treatment and reuse of sludge
from treatment process (vii) Improving the exiting WTP with wash water and sludge management and
chlorine safety measures (viii) Minimizing water losses from pipelines by perfect jointing and alignments using
appropriate techniques (HDPE pipes up to 150 mm diameter joined by electro fusion couplers using on-site electro fusion welding, and all higher diameter pipes by on site butt welding)
(ix) Designing the entire system to maintain optimal flow and terminal pressure, and optimising the overall energy usage
(x) Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies
(xi) Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor
(xii) Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections
(xiii) Using low-noise and energy efficient pumping systems 87. Identification and Selection of Water Source: An alternative source analysis has been conducted to select a feasible and sustainable source of water supply to meet the ultimate design demand of Bada Malhera town. Two alternatives: (i) Ground water, (ii) Kathan River; have been studied, and Kathan River is selected based on techno-economic and environment considerations as elucidated below.
(a) Ground Water Source: Ground water is the main source of water for the Bada Malhera town. Presently, water is supplied through tube wells. There are 16 nos. of tube wells out of which only 10 are in working condition. In addition to this,
60
hand pumps are other source of water in the town. A significant volume of ground water is also extracted through a network of hand pumps. There are 26 nos. of hand pumps exists across the town. The water table in the area is going down years to years, due to which discharge of existing tube wells has been reducing. Mostly tube wells get dry during summer. During summer, yield of the tube wells and hand pumps gets considerably reduced and thus town faces acute drinking water scarcity. Hence ground water source is not sustainable. Therefore, groundwater is not considered a sustainable source for meeting total projected demand. Since the water availability from tube well sources is neither dependable nor reliable against quantity and quality, so it has been discarded in this project.
(b) Kathan River: River Kathan flows in the western side of the town, which is about at a distance 3.6 km away from the Bada Malhera town and it is the only surface source of water nearby the town. There is no other alternatives and reliable source of water is available nearby other than Kathan River. Considering the proximity of good surface water source (Kathan River) and the techno-economic and environmental studies carried out indicated that Kathan River is the best possible source. Also, the government policy to utilize surface water source wherever it is feasible worked in favour of using Kathan River as the source of water. Hence it is proposed to develop Bada Malhera town water supply system based on Kathan River source.
88. Details of Kathan River: As mentioned above River Kathan flows in the western side of the town, which is about at a distance 3.6 km away from the Bada Malhera town and it is the only surface source of water nearby the Bada Makhera town. Kathan River originates from the hill near Tatarwara village, Shagarh Tehsil in Sagar district (Madhya Pradesh). It is tributary of Dhasan River. Prior merging with River Dhasan, the river navigates all through the area of Bundelkand. The river goes through the districts of Sagar, and Chhattarpur district in Madhya Pradesh. Kathan River flows towards North-East from South-West and passing throw Tatarwara, Luharra, Bilagram, Bagrohi, Karrai, Rampur, Rajpur Kalan, Patan, Barma, Garkhuwan, Kayan, Sijwaha, Silaro, Bamni, Morra village and enters into the Dhasan River at Devran village in Chhattarpur district (M.P.) as shown in Figure 20 to Figure 24, below. The Dhasan River is a right bank tributary of the Betwa River. Betwa river originates in Begumganj tehsil of Raisen district in Madhya Pradesh state, and meets Betwa River near Chandwari Danda village in Hamirpur district Uttar Pradesh. 89. Kathan River has total length of around 91 km from origin to the meeting point of River Dhasan. Kathan River is a non-perennial, and flows mainly during monsoon months. It carries significant flows during southwest monsoon, from end of June / beginning of July and up to the month of October and mid of November. Monsoon months demand can be directly met from the river as the flow is much higher than the demand, while storage is required to provide water supply for rest of the year. Kathan River has sufficient width and bank to store the water required for the drinking needs. Therefore, it is proposed to construction storage structure (weir), across the river to store water. 90. Considering the project water demand of the town, and to keep the water impoundment within the river course to avoid submergence of outside lands, it is proposed to keep the height of weir less than the height of river banks. Accordingly, it is assessed that, given the deep river banks, maximum of 6 m height weir can be constructed at the identified site. It is also assessed that weir with 6 m height will not be adequate to meet the demand, and therefore an additional weir of 2 m height is also proposed.
61
91. A Weir and an additional Pickup weir has been proposed across River Kathan near village Garkhuwan 3.36 km north-west of Bada Malhera town. Main weir (6m high) is proposed on the upstream and pick up weir (2 m high) on the downstream, about 1.5 km apart. Proposed location is approximately 78-79 km from the river origin point and about 12 km away from final destination point of Kathan River (meeting point of Dhasan River). 92. There is an existing water intake in River Kathan for Bada Marlhara water supply. This will be rehabilitated and utilized in the new system. Existing intake is about 800 m upstream of pick up weir, and it will pump water from the pick-up weir. Water from the main storage weir will be released into pick up weir as per the need, and from where it is abstracted via intake and pumped to the water treatment plant. 93. Except this intake, there is no other water intakes either on upstream or downstream of River Kathan from proposed weir/pickup weir site. In the river Kathan river course of about 90 km, there are 18 existing weirs/check dams on upstream and one on the downstream of proposed weir site. Nearest upstream weir/check dam (U18) is at about 32 km, and the nearest dam (D1) on downstream is at about 2 km from the proposed weir site. These existing weirs/ check dams have been constructed by different departments of Government of Madhya Pradesh under various schemes. Information on these structures is not readily available. Most of these existing weirs/dams are very small in size and their capacity is less than 0.5 MCM except Bila dam (56.7 MCM). Bila dam is located at about 60 km upstream of the proposed weir site. Details of existing weirs/dams are given in the Table 8, below. 94. River it is course is joined by 51 natural rivulets/streams (Refer Figure 27, below) - 27 streams join from left and 24 streams join from right . With reference to weir location, 43 rivulets/streams join Kathanl River on upstream of proposed Weir. Out of 43 rivulets/streams, 22 streams join from left side and 21 streams join from right side to River Kathan. All said streams are the natural drains that carry runoff generated in the catchment area through precipitation.
Table 8: Existing Weirs/ Check Dams across Kathan River and distance from Origin of
river & proposed weir & Pick-up weir for Bada Malhera Town WSS S.
No. Existing
Weirs/check dams across Kathan River
GPS Coordinates Distance from origin of Kathan River (in
Km)
Distance from proposed weir
(in km)
Distance from proposed pick-
up weir (in Km)
1. Origin point of Kathan River
Latitude – 24°08'25.77"N Longitude - 78°57'24.95"E
0
78.27
79.74
2. U1 Latitude – 24°09'01.50"N Longitude - 78°58'12.05"E
1.98
76.96
77.76
3. U2 Latitude – 24°09'10.20"N Longitude - 78°58'17.27"E
2.31
75.96
77.43
4. U3 Latitude – 24°09'22.15"N Longitude - 78°58'30.86"E
2.91
75.36
76.83
62
5. U4 Latitude – 24°09'26.90"N Longitude - 78°58'38.26"E
3.17
75.10
76.57
6. U5 Latitude – 24°09'52.68"N Longitude - 78°59'04.93"E
4.54
73.73
75.2
7. U6 Latitude – 24°10'02.86"N Longitude - 78°59'18.69"E
5.10
73.17
74.64
8. U7 Latitude – 24°10'11.67"N Longitude - 78°59'28.82"E
5.50 72.77
74.24
9. U8 Latitude – 24°10'39.71"N Longitude - 78°59'39.05"E
6.52 71.75 73.22
10. U9 Latitude – 24°10'50.60"N Longitude - 78°59'52.69"E
7.08 71.19 72.66
11. U10 Latitude – 24°11'03.92"N Longitude - 79°00'34.56"E
8.37 69.9 71.37
12. U11 Latitude – 24°11'46.20"N Longitude - 79°01'46.43"E
11.10 67.17 68.64
13. U12 Latitude – 24°11'58.15"N Longitude - 79°01'43.95"E
11.50 66.77 68.24
14. U13 Latitude – 24°12'42.07"N Longitude - 79°01'40.57"E
12.87 65.4 66.87
15. U14 Latitude – 24°13'21.79"N Longitude - 79°01'48.15"E
14.25 64.02 65.49
16. U15 (Bila Dam) Latitude – 24°15'41.07"N Longitude - 79°01'43.36"E
21.38 56.89 58.36
17. U16 Latitude – 24°18'37.45"N Longitude - 79°03'04.43"E
29.48 48.79 50.26
63
*U1 to U18 denotes upstream side weirs/check dams and; D1 denotes downstream side weirs/check dam
18 U17 Latitude – 24°21'48.28"N Longitude - 79°04'56.29"E
38.07 40.2 41.67
19 U18 Latitude – 24°24'02.38"N Longitude - 79°07'49.15"E
46.32 31.95 33.42
20 Proposed Weir Latitude – 24°35'30.12"N Longitude - 79°16'26.15"E
78.27 0 1.47
21 Existing intake well for Bada Malhera town WSS
Latitude – 24°35'51.86"N Longitude - 79°16'26.41"E
78.94 0.67 0.8
22 Proposed Pick-up Weir for Bada Malhera town WSS
Latitude – 24°36'16.52"N Longitude - 79°16'16.43"E
79.74 1.47 0
23. D1 Latitude – 24°36'36.59"N Longitude - 79°16'6.41"E
80.42 2.15 0.68
24 Destination point of Kathan River (Meeting with Dhasan River near Devran Village in Chhatarpur District in Madhya Pradesh)
Latitude – 24°41'24.00"N Longitude - 79°18'16.04"E
90.92 12.65 11.18
64
Figure 20: Showing Origin & Destination Point and Location of Nearest Existing Weir (U18), Proposed weir & Pick-up weir, and existing Intake in Kathan River Near Garkhuwan village
65
Figure 21: Google Earth Map Showing Location of Existing Dams/Weirs w.r.t. Proposed Weir & Pick-up Weir across Kathan River
66
Figure 22: Google Earth Map Showing Location of Existing Weir/Check Dam (D1) on downstream of Proposed weir & Pick-up weir and existing Intake in Kathan River
67
Figure 23: Google Earth Map Showing Location of Existing weirs/check dams (U15 to U18) on Upstream of Proposed weir & Pick-up weir and existing Intake in Kathan River
68
Figure 24: Google Earth Map Showing Location of Existing weirs/check dams (U1 to U15) on Upstream of Proposed weir & Pick-up weir and existing Intake in Kathan River
69
95. Kathan River Flow Dynamics: No flow data is available as there are no flow-gauging stations on Kathan River. It is a rain-fed and a non-perennial. River. As per the information collected from local people and water resource department officials, the river flows for about four to five months in a year; flow usually starts with the southwest monsoon rains in late June / July and continues throughout post monsoon, northeast monsoon season (October) and mid of November. River flow is very high during monsoon period in the months of July to August and maintains medium-high flow in the months of September to mid of November. Thereafter the flow reduces significantly, and flow is very low or insignificant from mid of November and up to February. River completely run dry from end of February / March to June months, and up to the arrival of monsoon in late June as mentioned in Table 9, below.
Table 9: Baseline Information and Flow Dynamics of River Kathan Locati
on
Na
me
of
Rive
r
Tot
al
len
gth
of
Riv
er
Lengt
h of
River
from
Origin
to
Propo
sed
weir
Site
Lengt
h of
River
from
propo
sed
weir
to
Final
dispo
sal
point
List
any
dams/
weirs
u/s of
propos
ed weir
site
River flow Characteristics
Ephem
eral /
Perenn
ial
Ver
y
hig
h
flow
peri
od
High
flow
period
Medi
um
flow
perio
d
Low
to
very
low
flow
period
with
shallo
w
depth,
not
navig
able
Comp
lete
dry
period
Garkhu
wan
Village
Kath
an
Rive
r
91
km 79 km 12 km
Yes,
there
are 18
existing
dams
Nearest
dam is
about
31.95
km
away
from
propose
d weir
site
Ephem
eral
July
&
Aug
ust
Septe
mber
Octo
ber
Nove
mber -
Febru
ary
March
to
June
end
and
upto
onset
of
monso
on
Source: DPR Consultant as well as Site visit observation by PMC, PIU PMC & PIU PMU Sagar Safeguard Team
70
96. Requirement of Weir and Pick-up Weir: The ephemeral nature of river necessitated creation of storage to meet the town water demand during low and no-flow season. As stated earlier, the river flows for about four to five months in a year and carries very high flows in the months of July and August and maintains medium-high flow in the months of September to mid of November. Thereafter the flow reduces significantly, and flow is very low or insignificant from mid of November and up to February. River completely run dry from end of February / March to June months, and up to the arrival of monsoon in late June as mentioned. Monsoon months demand can be directly met from the river as the flow is much higher than the demand, while storage is required to provide water supply for rest of the year. Kathan River has sufficient width and bank to store the water required for the drinking needs. Therefore, it is proposed to construction storage structures, weir, across the river store water. 97. Considering the project water demand of the town, and to keep the water impoundment within the river course to avoid submergence of outside lands, it is proposed to keep the height of weir less than the height of river banks. Accordingly, it is assessed that, given the deep river banks, maximum of 6 m height weir can be constructed at the identified site. It is also assessed that weir with 6 m height will not be adequate to meet the demand, and therefore an additional weir of 2 m height is also proposed. A Weir and an additional Pickup weir has been proposed across River Kathan near village Garkhuwan 3.36 km north-west of Bada Malhera town. Main weir (6m high) is proposed on the upstream and pick up weir (2 m high) on the downstream, about 1.5 km apart. Proposed location is approximately 78-79 km from the river origin point and about 12 km away from final destination point of Kathan River (meeting point of Dhasan River). 98. There is an existing water intake in River Kathan for Bada Marlhara water supply. This will be rehabilitated and utilized in the new system. Existing intake is about 800 m upstream of pick up weir, and it will pump water from the pick-up weir. Water from the main storage weir will be released into pick up weir as per the need, and from where it is abstracted via intake and pumped to the water treatment plant.
Table 10: Details of Proposed Weir & Pick-up Weir across Kathan River
S.
No.
Location Details Water
Requirement
During Non-
rainy period for
242 days (8
months)
Capacity
of Weir /
Pick-up
Weir in
MCM
Water Availability
based on Rainfall
and Catchment Area
Analysis
1. Weir on u/s side of
existing intake well &
low level bridge
192 M Long
& 6 M
Height
0.915 MCM 0.835 MCM 145.68 MCM
2. Pick-up Weir on d/s
side of existing intake
well & proposed weir
near Garkhuwan
Village
94 M Long
& 2 M
Height
0.113 MCM
99. Proposed Weir across River Kathan: The total water demand of the town is estimated 2.52 MLD in the ultimate year 2050. Annual raw water demand is estimated as 0.915 mcm for ultimate design year, considering evaporation losses from weir storage . The water demand of
71
the Bada Malhera town can be fulfilled by constructing a weir and a Pick-up weir and making drawl arrangement from the downstream of the Kathan river. Calculation shows that 6 m high and 192 m long main weir and 2 m high and 94 m long pick up weir will be required to fulfill the demand. Hence, it is proposed to construct 2 weirs across the River. There is a low level bridge approximately 300 u/s of existing intake well site. So, weir (6m height) proposed 135m u/s of the bridge to avoid the submergence of it. This arrangement will be sufficient to fulfill the drinking water demand for ultimate year of the Bada Malhera town. The capacity curve and table of weir are given in Table 11 to Table 13 & Figure 25, below:
Table 11: Area Capacity Table of Proposed Weir for Bada Malhera Town WSS
R.L. Area Volume cum Volume in
mcm
Cum Volume in
mcm
Cum Volume in ml
289 6800
290 25802 15282.63 0.0153 0.0153 15.28
291 65910 44316.82 0.0443 0.0596 59.60
292 108400 86278.67 0.0863 0.1459 145.88
293 213241 157892.75 0.1579 0.3038 303.77
294 268976 240569.87 0.2406 0.5443 544.34
295 313760 291080.77 0.2911 0.8354 835.42
296 392751 352517.22 0.3525 1.1879 1187.94
Table 12: Evaporation Losses Table as per Central Water Commission
Month Days Evaporation(mm/day) Total Evaporation(mm) Total Evaporation(m)
Jan 31 3 93 0.09
Feb 28 4 112 0.11
Mar 31 7 217 0.22
Apr 30 9 270 0.27
may 31 11 341 0.34
June 30 10 200 0.20
July 31 5 155 0.16
Aug 31 4 124 0.12
Sep 30 5 150 0.15
Oct 31 4 124 0.12
Nov 30 3 90 0.09
Dec 31 3 93 0.09
2059 2.059
72
Table 13: Storage Capacity of Proposed Weir of Bada Malhera Town WSS at Contour 295 = 835.42 ML
S.
No.
Month Drinking water
demand in
MLD for
Ultimate year
(in MLD)
Days Total
Consump
tion
Net
Capacity
(in ML) at
the end of
month
RL of
Conto
ur
Evaporat
ion
Losses
(in M)
RL of
the
contou
r at the
end of
month
Balance
Capacity
(in ML) at
the end of
month
1. Nov. 2.52 30 75.6 759.82 294.75 0.09 294.66 732
2. Dec. 2.52 31 78.1 653.88 294.37 0.09 294.28 620
3. Jan. 2.52 31 78.1 541.88 294.00 0.09 293.91 515
4. Feb. 2.52 28 70.6 444.44 293.60 0.11 293.49 418
5. March 2.52 31 78.1 339.88 293.17 0.22 292.95 295
6. April 2.52 30 75.6 219.40 292.47 0.27 292.20 175
7. May 2.52 31 78.1 96.88 291.45 0.34 291.11 67
8 June 2.52 30 75.6 16.60 290.00 0.20 289.80 12
Figure 25: Weir Capacity Curve
100. Proposed Pick-up weir: A Pick-up weir will be constructed in the downstream of
the proposed weir. Water after being released from the proposed weir will get stored in
73
the Pick-up weir. Length of the proposed Pick-up weir is 94 m, height is 2 m and capacity is 0.113 mcm (Refer Table 14 & Figure 26, below). This arrangement will be sufficient to store water released from proposed weir to fulfill the water demand of the town at ultimate stage.
Table 14: Storage Capacity of Pick-up Weir at Bada Malhera 113.38 ML at Contour 290 m
S.
No.
Month Drinking
Water
Demand
for
Ultimate
Yr. (in
MLD)
Days Total
Consumptio
n
Net
capacit
y at the
end of
Month
(in ML)
RL of
contour
Evaporation
loss (m)
RL of
the
contour
at the
end of
month
Balance
Capacity
(ML) at the
end of
Month
1 June 2.52 10 25.2 88.18 289.67 0.10 289.57 77
2 July 2.52 20 50.4 26.6 288.75 0.16 288.60 21
Figure 26: Pick-up Weir Capacity Curve
74
101. Water Availability/Yield Assessment: In the absence of flow records, an engineer’s estimate of volume of water availability / catchment yield based on rainfall and catchment area with respect to proposed weir site has been prepared. The river catchment area up to the proposed weir point is 1214 sq. km (Refer Figure 27). With the annual average rainfall of 800 mm (minimum) and taking coefficient of runoff as 0.15 (poor catchment and no continuous downpour), the yield at weir point is estimated as 145.68 MCM. Proposed storage volume of both the weirs, to meet the water demand of Bada Malhara for a period 8 months annually, is 0.915 MCM per year including evaporation losses. This is just about 0.63% of total catchment yield. Hence on the basis of above analysis it is concluded that source is sustainable, and capacity of weir is sufficient to fulfill the ultimate demand. (For details water availability analysis based on catchment area & rainfall - see Table 15, below).
Table 15: Water Availability/ Yield Analysis based on Catchment area & Rainfall at Proposed Weir & Pick-up Weir Site – Bada Malhera Town WSS
Calculation for Total Runoff w.r.t Proposed Weir & Pickup Weir across Kathan River Near
Garkhuwan Village for Bada Malhera Town WSS
S. No. Description Value Parameter
1 Catchment area (A) = 1214 Sq. Km
2 Average rain fall (Maximum) (I) = 950 Mm
3 Average rain fall (Minimum)(I) = 800 Mm
4 Run off coefficient (R) =
0.15
=
5 Formula = AIR
i Maximum rainfall
= 1214X1000X1000X0.95X0.15 cum
= 172995000 cum
= 172.99 MCM
ii
Minimum rainfall
= 1214X1000X1000X0.8X0.15 cum
145680000 cum
145.68 MCM
Total Available water = 145.68 MCM
Ultimate Year Water Demand for
Bada Malhera Town = 0.92 MCM
75
Figure 27: Catchment Area w.r.t. Proposed Weir & Pick-up Weir across Kathan River near Garkhuwan Village
76
102. Source Sustainability for the water supply scheme (WSS) of Bada Malhera town: The total water demand for Bada Malhera town is estimated to be 2.52 MLD at ultimate stage for year 2050. Considering evaporation losses from the storage, the estimated water requirement of 242 days (8 months), low / no-flow season is 0.915 MCM. Capacity of the proposed weir and pick-up weir is 0.835 MCM and 0.113 MCM i.e. (Total = 0.948 MCM) respectively, which is sufficient to meet the required ultimate year demand. The catchment area up to the weir point are 1214 km2 (Refer Fig 27) and based on the catchment area and rainfall analysis, river catchment yield with respect to the proposed weir and pick-up weir is estimated as 145.68 MCM (Refer Table 15). Looking to the yield, the gross capacity of proposed weir and pick-up weir is (0.835+0.113) MCM = 0.948 MCM, which is just about 0.63% of total yield, hence the source is 100% assured. 103. Submergence of land / Impact on Upstream due to Weir & Pick-up Weir Construction: The 6m height of weir and 2m height of pick-up weir are proposed to meet the water storage requirement, and also to limit the water storage / submergence within river course. Considering the height of river banks, about 8-10 m high from the bed of the River (Refer Figure 28 - Site Photographs of Kathan River), the proposed weir (6m height) and Pickup-up weir (2m height) is much below the river banks i.e. (proposed weir is about 2-4 m and pick-up weir is about 6-8 m below the river banks). The height of the weir (6m) and pick-up weir (2m), to store required water is fixed in such way that top level (295m) of structure is well below the High Flood Level (297.25 m) of the river. HFL of the river is 8.25m above from the bed level of river (289m). It is also considered that the weir height should be as low as possible so that the submergence is limited to the river course when the height of weir is kept at 6 m and 2m at proposed sites. Refer Map annexed as Figure 29 shows the weir storage / contour plan and submergence area of proposed weir and pick-up weir. The height of weir in both the cases is less than the height of the river banks and HFL, and therefore the water storage is confined to river course / flood plain, and there is no submergence of lands outside the river. No negative impacts or acquisition of government of private or government lands anticipated. Therefore, there are no impacts due to submergence.
Figure 28: Site Photographs of River Kathan Showing Riverbanks Height
77
U/s and D/s side of Proposed Pick-up Weir
78
Showing Low bridge (on d/s of weir) and Upstream & Downstream of Proposed Weir
Downstream of Weir (Low bridge is on downstream of Weir)
Kathan River (intake upstream side) Kathan River (intake downstream side)
79
Kathan River (intake d/s & Pick-up weir u/s side) Kathan River (intake d/s & Pick-up weir u/s side)
80
Figure 29: Contour Map of Kathan River Superimposed on Google Earth Map showing Submergence area w.r.t. proposed Weir height and Location
81
104. Impacts due to weir & pick-up weir on downstream users and River ecosystem: Based on the river catchment yield estimate it is assessed that the proposed weir is storage is just about 0.63% of total yield, therefore this marginal abstraction is unlikely to have any notable impacts on existing users or river ecosystem. River is ephemeral, and has large flow variations, and completely gets dry for about 4-5 months from March through June. Given that there are already existing weirs / dams across the river throughout its course, both on upstream and downstream of proposed weir, there is unlikely to be any notable change or impact on the river ecosystem or aquatic life. There are no notable sensitive environmental features or protected or unique aquatic plant/ creatures. The Aquatic life in the river is limited to local common species of fishes and aquatic plants. There is no commercial fishing activity take place in this stretch of the river and on downstream up to the meeting point of Dhasan River. The aquatic plants in river are floating plants Nelumbo Nucifera, Bispinosa, Aponozeton etc. There are trees, bushes and vegetation on both sides of river banks across which proposed weir and pick-up weir are to be constructed. Removal of trees and vegetation will not require during implementation phase as the work is confined to within river bank only. Trees found along River banks are Acacia, Tamarind, kava, Soapnut (Reetha), Palash, Mango, Chola, Mahua and some other trees are commonly seen. 105. Also, the increase in overall storage volume across the river due construction new weir is will also not be significant. Although there are total 19 weirs/check dams/dams across the river, except Bila Dam, all are very small, and storage capacity is just around 0.5 MCM. Bila Dam is situated 60 km upstream of proposed weir site, and the capacity of Bila Dam is 56.37 MCM. The total capacity of the impounding structures across the river at present may be appropriately 66 MCM (based on rough estimate as no data available), and with the construction of new weir for Bada Malhara this will increase very marginally to about 67 MCM, about 1.5% increase. In terms of water availability, the cumulative storage on the river is about 45% of total catchment yield. Creation of new storage for Bada Malhar with just 0.92 MCM of water is unlikely to alter the existing situation considerably. 106. Height of proposed weirs are 6m and 2m from the bed level of the river. Weir will be of solid concrete structure, and will be provided with low level sluice gates (just above the dam sill level at the river bed) to allow release of water as and when required. Sluice gates will be closed prior to end of monsoon flows and opened prior to onset of heavy monsoon flows; this arrangement avoids silt accumulation and also prevents obstruction of heavy monsoon flows as shown in drawings annexed as Figure 30 to Figure 31, below. There are already existing dams on the upstream and downstream of the proposed weir site, across River Kathan (Details are provided above). Therefore, the change in flow regime due to this small weir will be negligible. Hence no notable impacts envisaged on the downstream. The proposed impoundment, in fact, is likely to benefit the environment through groundwater recharge and propagating aquatic life, therefore no further impacts envisaged due to proposed weir. Hence no impact envisaged on downstream side. As the package is implemented under DBO mode, the detailed design of weir will be conducted by the contractor after award of the contract. 107. Weir Operation and Safety of Downstream Structures: There is a low-level road bridge, approximately 300 u/s of existing intake well site (see Figure 28). During very heavy flows, water flows over the bridge. To avoid submergence of this bridge, weir (6m height) is proposed 135 m up stream of bridge, while the pick-up weir (2 m height) will be on the downstream of bridge at about 1.35 km. During the operation phase, water from the main weir will be released periodically into pick up weir for abstraction via intake and supply to the town. As the existing bridge is located close on the downstream, the aspects of structural stability of bridge, and also risk of water releases on the bridge way and traffic movement, need to be
82
considered during the detailed design. There may be a risk due to release of water from the sluice gates, and in the events of overflow of weir. This needs to be properly studied, and necessary precautions to be included for safety of structures, and road users.
83
Figure 30: Details of Plan, Cross-Section & Elevation of Proposed Weir Showing Sluice Gates for Bada Malhera Town WSS
84
Figure 31: Details of Plan, Cross-Section & Elevation of Proposed Pick-up Weir for Bada Malhera Town WSS
85
108. Water Quality of Kathan River: Catchment area of the proposed weir site is spread over 1214 sq. km, and is mostly characterized by agricultural and barren lands, and forest areas. Water Quality Test Report of Kathan River is given in Appendix 12. All the parameters of water quality in comparison with drinking water standards are well within the limits, except for turbidity and bacteriological contamination. hence conventional water treatment and disinfection which is proposed in the project is adequate to make the water usable for drinking purposes. A regular water quality regime needs to be established for checking the raw water quality. The water supplied to the consumers at all-time must meet the drinking water standards (Appendix 8). 109. Use of Chlorine as disinfectant. Given the risk of bacteriological contamination in the river water souce, it is proposed to have disinfection of the water. Thus it is proposed to use chlorine at WTP to disinfect the water prior to supply to consumers. There is invariably a safety risk when chlorine is handled. Although facilities are not located close to habitations, safety precautions are necessary to ensure the safety of workers and citizens. An offsite emergency management plan will be prepared during detailed design stage by DBO Contractor. For the existing WTP for Bada Malhera town WSS, all the facilities that are required including chlorine safety are included in the subproject proposals/designs under rehabilitation and repair works. The EMP (Refer EMP Table 19 & Table 22) includes mitigation measures to ensure the compliance of environmental standards during O&M phase. To avoid any risk, the chlorination facility will be provided with the following:
(i) Chlorine neutralization pit with a lime slurry feeder (ii) Proper ventilation, lighting, entry and exit facilities (iii) Facility for isolation in the event of major chlorine leakage (iv) Continuous monitoring and detection of leaks (v) Visible and auditable alarms in the event of chlorine leakage (vi) Personal protection and safety equipment for the operators in the chlorine plant (vii) Provide training to the staff in safe handling and application of chlorine; this shall
be included in the contract of Chlorinator supplier (viii) Supplier of Chlorinator equipment shall provide standard operating manual for
safe operation and as well as maintenance and repairs; preferably these shall be provided both in English and Hindi Languages
(ix) Develop procedures for handling of emergencies and provide training to the employees.
110. Utilities. Telephone lines, electric poles and wires, water lines within the proposed project locations may require to be shifted in few cases. To mitigate the adverse impacts due to relocation of the utilities, the contractor, in collaboration with ULB will (i) identify the locations and operators of these utilities to prevent unnecessary disruption of services during construction phase; and (ii) instruct construction contractors to prepare a contingency plan to include actions to be done in case of unintentional interruption of services. 111. Site selection of construction work camps, stockpile areas, storage areas and disposal areas. Priority would be to locate these facilities near the project components. However, if it is deemed necessary to locate elsewhere, sites to be considered will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems. However, it would be necessary to ensure that the facilities are located in areas such that it does not cause any harm to the environment; cause any conflict with the local population, results in destruction of property, vegetation, irrigation, and common resources.
86
112. To prevent any inconvenience to local population and prevent harm to the environment siting guidelines have been developed for setting up of construction camps:
• Residential areas will not be considered for setting up camps to protect the human environment (i.e., curb accident, health risks due to air and water pollution and dust, and noise, and to prevent social conflicts, shortages of amenities, and crime). A minimum buffer distance of 200 m would be maintained.
• Sensitive environmental receptors forest, schools’ hospitals, religious places, water bodies, swamps, riverbeds/banks or in areas which will inconvenience the community will be avoided; and
• A detailed guidance for siting of construction camps is provided in Appendix 13: Guidance for Siting and Facilities at Construction Camp.
113. Site selection of sources of materials. Significant quantities of coarse aggregate and fine aggregate will be required for construction works. Requirement of gravel is limited. Contractor should procure these materials only from the quarries permitted/licensed by Mines and Geology Department. Contractor should, to the maximum extent possible, procure material from existing quarries, and creation of new quarry areas should be avoid as far as possible. Improper extraction of materials can disrupt natural land contours and vegetation resulting in accelerated erosion, disturbance in natural drainage patterns, ponding and water logging, and water pollution. It will be the construction contractor’s responsibility to verify the suitability of all material sources and to obtain the approval of Department of Mines & Geology and local revenue administration. 114. To prevent the adverse effect from the sourcing of quarry material required i.e. sand and stone aggregate, the following measures will be adopted in MPUSIP.
• The material will be procured from existing quarries which have valid Environmental Clearance by the State Environmental Appraisal Committee/ State Environmental Appraisal Authority/ District Environmental Committee.
• Further as a contractual obligation the Contractor is required to submit the Environmental Clearance certificate and the latest copy of the six-monthly Compliance Report submitted by the Quarry to MPPCB to the PIU before the procurement of the material. Contractor to submit to PIU on a monthly basis documentation on material obtained from each source (quarry/ borrow pit).
• However, if the Contractor opens a new quarry, he has to obtain the environmental clearance and submit the same to the PIU before extracting any material from the quarry/sand mine.
• Submit to MPUDC on a monthly basis report of the quantity of material procured/extracted from each quarry.
115. Impact due to presence of Hazardous Material (Asbestos Cement Pipes): As discussed earlier asbestos cement pipes had been used in part of the pipeline network developed during the 1970’s. There is acute health risk of workers getting exposed to asbestos containing material if these pipes are uncovered in the course of the work. These, pipeline were laid at a depth of 1.5 m from the ground level. And also, ground level of the roads increased considerable due to road improvements over last many years. At present these pipes are very old and are laying about 3-4 m below the ground level. Under this project the maximum depth of laying of pipeline would be 1.2 m. Thus, there would be no possibility of the workers getting
87
exposed to the pipelines. These pipes will not be used in future, and will be left as it is in the ground, without any disturbance. 116. Considering the health and safety risk associated with asbestos the following precautions have been proposed to safeguard workers and the community around:
• A detailed survey with the assistance of PHED and /NP on the presence of existing AC pipes in the distribution network or on areas which involve pipe laying activities. In the final IEE, a map showing the exact location of the AC pipes should be provided.
• Locate the new pipes carefully to avoid encountering AC pipes
• All AC pipes will be left in situ and untouched. New pipes will be placed next to AC pipes.
• In the event, that the asbestos fibers from AC pipes were accidentally disturbed/ exposed, the contractor should also prepare SOP for handling the AC pipes.
• Safe disposal and precaution will be taken as per the USEPA https://www.epa.gov/asbestos/safe-work-practices.
117. Impacts from Procurement of Material: The Regulation of Polychlorinated Biphenyls Order, 2016 states that all equipment containing biphenyl should be phased out by 31st December 2025. In such cases both the oil and the equipment would be considered as a hazardous waste and disposed as per the relevant legislations. To prevent this scenario No transformer procured under the project should contain PCBs. B. Environmental Audit of Existing Water Treatment Plant
118. There is an existing WTP in Bada Malhera having capacity 3.00 MLD, which will be used for the project with necessary improvements. As per the ADB SPS 2009, this is an associated facility and therefore the component operation shall comply with the ADB and applicable environmental laws of India. A preliminary environmental audit is conducted to (i) assess the compliance of the existing WTP with environmental legislations; (ii) improve environmental performance; and (iii) increase Bada Malhera Nagar Parishad’s knowledge, thus increasing its ability to continually improve and minimize future potential liabilities. A more detailed environmental audit and risk assessment shall be carried out during detailed design stage by DBO Contractor.
Table 16: Salient Features of Bada Malhera Existing WTP Description Bada Malhera Existing WTP
Location In Ward No. 12, on Garkhuwan road, Bada Malhera. Latitude – 24°34'44.58"N Longitude - 79°17'58.12"E
Start of Operation (Year) WTP have not been used since their construction in 2015.
Owned by WTP were built by the PHE department, GoMP.
Capacity 3.00 MLD (1000 sq m @ average 0.125 m3/m2/ hr filter rate slow sand filter bed).
Water Supply Source & Distance from WTP Kathan river, 3.36 km away from the WTP
88
Description Bada Malhera Existing WTP
Water Treatment process Treatment process: The treatment process is conventional, and has following units: Coagulation flocculation, chemical dosing, filtration, and disinfection with chlorine. There are 02 slow sand filters. Materials: All civil structures are made of reinforced cement concrete,
Treated water quality N.A. WTP have not been used since their construction in 2015 by PHE Department.
Backwash Water and Sludge Management None
Chlorination System Chlorine dosage system is not proper; there are no safety precautions in place. Chlorine cylinders are not working, and other water electro chlorinator is also not in working condition. No safety systems like leak detection or emergency alarm or lime slurry pit available in the facility. Safety equipment like masks and oxygen cylinders are not provided at the facility.
Overall condition of WTP WTP was built by the PHE department, however, this is not put into operation. Due to lack of maintenance, WTP structures are in poor condition and need some repairing work to meet their functional requirements.
Table 17: Compliance with Applicable National and State Regulations
Act/Rule Clearance Requirement Compliance Status of Existing WTP at
Bada Malhera Town
EIA Notification The EIA Notification of 2006 and
2009 (replacing the EIA Notification
of 1994) states that environmental
clearance is required for certain
defined activities/projects
N.A.
Environmental clearance is not required
as WTPs are not listed in the EIA
Notification’s “Schedule of Projects Requiring Prior Environmental Clearance”
Manufacture,
Storage, and Import
of Hazardous
Chemical Rules, 1989
Storage of chlorine (threshold
quantity greater than 10 tons will
require clearance from Madhya
Pradesh Pollution Control Board
(MPPCB). However, PMU needs to
liaise with the MPPCB if there are
any changed to this statute
requirement
NA
WTP have not been used since
construction in 2015.
Water (Prevention
and Control of
Consent to operate from MPPCB Non-compliant
89
Act/Rule Clearance Requirement Compliance Status of Existing WTP at
Bada Malhera Town
Pollution) Act of 1974,
Rules of 1975, and
amendments
Air (Prevention and
Control of Pollution)
Act of 1981, Rules of
1982 and
amendments.
At present there is no Consent obtained
from the MPPCB for this plant. This is
mandatory and needs to be obtained.
Environment
(Protection) Act, 1986
and CPCB
Environmental
Standards
Emissions and discharges from the
facilities to be created, refurbished,
or augmented shall comply with the
notified standards.
a. Air emissions No significant air emissions.
b. Effluent N.A.
WTP have not been used since their
construction in 2015.
Forest (Conservation)
Act, 1980 and Forest
Conservation Rules,
2003 as amended
As per Rule 6, every user agency,
who wants to use any forest land for
non-forest purposes shall seek
approval of the central government
N/A
WTP is not located in notified forest
lands.
Ancient Monuments
and Archaeological
Sites and Remains
Rules of 1959
No development activity is permitted
in the “protected area,” and all development activities likely to
damage the protected property are
not permitted in the “controlled area” without prior permission of the
Archaeological Survey of India
(ASI). Protected property includes
the site, remains, and monuments
protected by ASI or the State
Department of Archaeology.
N/A WTP is not located near any protected monument
119. Compliance & Corrective Actions. The existing WTP structure as presented in Figure 5 to Figure 7 would be used. Existing WTP have not been used since its construction in 2015. WTP structures were built by the PHE department and due to lack of maintenance; it is in poor condition and need some repairing and rehabilitation work to meet their functional requirements.
90
The existing WTP will be used after rehabilitation. Rehabilitation of the existing WTP will include repair of sedimentation tank, raw water channel, alum mixing plant, repair of filter bed, scraping of top lay of filter sand and refilling, repair of clear water pump house (supply, erection (installation), testing and commissioning replacement of pumps and machineries), colouring & other miscellaneous works and chlorine safety features etc. Backwash recirculation and sludge management facilities will also be constructed. During the design and planning process, the existing WTP at Bada Malhera was thoroughly inspected and audited for the environmental concerns. In addition to assess the structural integrity and physical condition a separate study have been carried out in the DPR.
Table 18: Corrective Action Plan (CAP) for Environmental Compliance of Existing WTP Concern Action Required Time line Responsible Agency
and Funding Source
Non-compliance with
statutory regulations ?
Obtain consent (CTE /
CTO) from MPPCB.
CTE prior start of
rehabilitation work
CTO prior to start of
operation of
rehabilitated WTP
Nagar Parishad Bada
Malhera (for Bada
Malhera WTP)
Poor backwash
wastewater and sludge
management.
- Provision of
backwash recirculation
system – to avoid
discharge and also to
recover raw water.
-Provision of sludge
collection, thickening,
drying and
reuse/disposal system..
Issues of concerns to
be addressed by the
start of operation of
Rehabilitated WTP (i.e.
February 2023).
MPUDC (components are
included in the subproject
under MPUSIP)
Lack of safety
measures for chlorine
handlings.
-Improvements to
chlorination system
including provision all
necessary safety
measures, PPEs and
provide training to staff.
Issues of concerns to
be addressed by the
start of operation of
Rehabilitated WTP (i.e.
February 2023)
MPUDC
(components are included
in the subproject under
MPUSIP)
C. Construction Impacts
120. The construction work is expected not to cause major negative impacts, mainly because:
• Most of the activities will be on the built-up areas of town and/or existing RoW, thus could be constructed without causing impacts to biodiversity.
• All the sites are located on government-owned land which is not occupied or used for any other purpose.
• Pipelines will be mainly located on unused ground alongside existing roads and can be constructed without causing major disruption to road users and adjacent houses, shops and other businesses;
91
• Most pipeline construction will be conducted by small teams working on short lengths at a time so most impacts will be localized and short in duration;
• Most of the individual elements of the subproject are relatively small and involve straight forward construction and operation, so impacts will be mainly localized and not greatly significant;
• Most of the predicted impacts associated with the construction process are produced because the process is invasive, such as involving excavation. However, the routine nature of the impacts means that most can be easily mitigated, and the impacts are clearly a result of the construction process rather than the design or location, as impacts will not occur if excavation or other ground disturbance is not involved.
• As a result, there are several aspects of the environment which are not expected to be affected by the construction process and these can be screened out of the assessment at this stage as required by ADB procedure. These environmental factors are screened out presently but will be assessed again before starting the construction activities.
• Overall construction program will be relatively short and is expected to be completed in 36 months with activities to be conducted by small teams and specified location so most.
121. Pipe Laying Works. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. Pipeline laying work will be taken up in section-wise by DBO contractor daily; trench excavation, pipe laying, jointing, will be refilled, consolidated with a plate vibrator/ roller and levelled by the end of the day; this limits the public disturbance to a minimum time. The mitigation measures are discussed in the EMP (Refer EMP Table 20 - 21). The roads in the core city area of all the towns are very narrow and congested with pedestrians and vehicles (mainly 2-wheelers), while the roads in outer areas are wide. 122. Earth work excavation will be undertaken by machine (backhoe excavator) or manually and include danger lighting and using barricades at every 100 m. Sufficient care will be taken while laying so that existing utilities and cables are not damaged and pipes are not thrown into the trenches or dragged, but carefully laid in the trenches. As trenches are a maximum of 1.2 m, there is no risk of collapse of trenches or risk to surrounding buildings. Once they are laid, pipes will be joined as per specification and then tested for any cracks of leakages. The minimum working hours will be 8 hours daily, the total duration of each stage depends on the soil condition and other local features. About 95% of the excavated soil will be used for refilling the trench after placing the pipe and therefore residual soil after pipe laying and refilling is not significant. 123. Other construction works. Other civil works in the subproject include construction of a weir, pick-up weir across River Kathan, repair and rehabilitation of existing intake and water treatment plant, construction of water tanks at the identified sites. These works will be confined to sites, and construction will include general activities like excavation for foundation, construction of foundations, columns, walls and roof in cement concrete and masonry, and fixing of mechanical and electrical fixtures, etc. Weir and pick-up weir structures has been proposed for creating storage of raw water in Kathan River and water after being released from the weir will get stored in the pick-up weir to collect and lift water up to treatment works via
92
existing intake. Weir and pick-up weir will be constructed within the water body across the River Kathan. An enclosed area will be created at the selected site using temporary barriers like sand bags or sheet piles and the water will be pumped out only after settling & clarified to make the area dry for construction. Once this is created, the rest of the construction will follow the general construction procedures. Once the work is over, the temporary structure/barrier will be removed. 124. Although construction of these project components involves quite simple techniques of civil work, the invasive nature of excavation and the project locations in the built-up areas of the town where there are a variety of human activities, will result in impacts to the environment and sensitive receptors such as residents, businesses, and the community in general. Water lines will be laid on either side of the roads/streets. These anticipated impacts are temporary and for short duration. Physical impacts will be reduced by the method of working and scheduling of work, whereby the project components will be (i) constructed by small teams working at a time; (ii) any excavation done near sensitive area like school, religious places and house will be protected as per standard norms. (iii) Busy street and bazaar area will require night work. For night work Contractor will ensure lights not focusing on houses, (iv) Use of low noise generator. (v) Proper signage’ sand barricades. (vi) Prior noticed before construction work of a particular stretch to residences/shops etc. 125. Sources of Materials. Significant amount of sand and coarse aggregate will be required for this project. The construction contractor will be required to:
(i) Use material sources permitted by government; (ii) Verify suitability of all material sources and obtain approval of PIU; and (iii) Submit to PIU on a monthly basis documentation of sources of materials.
126. Air Quality. It is most certain that work will be conducted during the dry season, so there is potential for creating dust from the excavation of dry soil, backfilling, transportation to disposal, and from the import and storage of sand/gravel for bedding. Emissions from construction vehicles, equipment, and machinery used for excavation and construction will induce impacts on the air quality in the construction sites. Anticipated impacts include dusts and increase in concentration of vehicle-related pollutants such as carbon monoxide, sulfur oxides, particulate matter, nitrous oxides, and hydrocarbons. These however will be temporary, limiting to construction activities only. Specific areas of concern have been observed in case of laying of clear water rising main and distribution line. Dust generation from construction work in individual and confined work sites, will be mainly during the initial construction phase of earthwork, as the site is confined, dust can be effectively controlled with common measures. Dust generation will be significant during distribution line laying along the roads. Increase in dust/ particulate matter in ambient air have adverse impacts on people’s health and environment. Potential impact is negative but short-term and reversible by mitigation measures. To mitigate the impacts, for all construction works contractor will be required to:
(i) Barricade the construction area using hard barricades (of 2m height) on both sides and provide dust/wind screen (such as geo textile fabric) up to 3m height (1 m above the hard barricading
(ii) Initiate site clearance and excavation work only after barricading of the site is done
(iii) Confine all the material, excavated soil, debris, equipment, machinery (excavators, backhoe, etc.) to the barricaded area
(iv) Limit the stocking of excavated material at the site; remove the excess soil from the site immediately to the designated disposal area
93
(v) Undertake the work section-wise: 100-200 m section should be demarcated and barricaded
(vi) Conduct work sequentially – excavation, pipe laying, backfilling; conduct pipe testing section-wise (for a minimum length as possible) so that backfilling, stabilization of soil can be done
(vii) Damp down exposed soil and any stockpiled material on site by water sprinkling; (viii) Stabilize surface soils where loaders, support equipment and vehicles will
operate by using water and maintain surface soils in a stabilized condition (ix) Apply water prior to levelling or any other earth moving activity to keep the soil
moist throughout the process (x) Cover the soil stocked at the sites with tarpaulins (xi) Backfilled trend at any completed section after removal of barricading will be the
main source of dust pollution. The traffic, pedestrian movement and wind will generate dust from backfilled section. Road restoration shall be undertaken immediately.
(xii) Control access to work area, prevent unnecessary movement of vehicle, public trespassing into work areas; limiting soil disturbance will minimize dust generation
(xiii) Use tarpaulins to cover sand and other loose material when transported by trucks;
(xiv) Control dust generation while unloading the loose material (particularly aggregate, sand, soil) at the site by sprinkling water and unloading inside the barricaded area
(xv) Clean wheels and undercarriage of haul trucks prior to leaving construction site (xvi) Disallow access in the work area except workers to limit soil disturbance and
prevent access by barricading and security personnel (xvii) Fit all heavy equipment and machinery with air pollution control devices which
are operating correctly (xviii) Ensure that all the construction equipment, machinery is fitted with pollution
control devises, which are operating correctly, and have a valid pollution under control (PUC) certificate
(xix) Limit the speed of construction vehicles on access roads and work sites to a maximum of 30 km/h
(xx) Prohibit burning firewood in work and labor camps (xxi) Prohibit burning of solid wastes.
127. Surface Water Quality. Run-off from stockpiled materials and chemical contamination from fuels and lubricants during construction works can contaminate downstream surface water quality of the streams. As the rainfall in the project areas is mostly confined to monsoon, these potential impacts are short-term and temporary. However, to ensure that these are mitigated, construction contractor will be required to:
(i) No earthwork will be conducted during rainy season (ii) All earth works be conducted during the dry season to prevent the problem of soil
run-off during monsoon season; (iii) Avoid stock piling of earth fill especially during the monsoon season unless
covered by tarpaulins or plastic sheets; (iv) Prioritize-use of excess spoil sand materials in the construction works. If spoils
will be disposed, only designated disposal areas shall be used; (v) Disposal sites will be selected prior to start of construction following the EMP
guidelines
94
(vi) Install temporary silt traps or sedimentation basins along the drainage leading to the water bodies;
(vii) Place storage areas for fuel sand lubricants away from any drainage leading to water bodies;
(viii) Dispose any wastes generated by construction activities in designated sites; (ix) Temporary drains or bunds will be created around the periphery of work area to
avoid flooding, and entry of runoff (x) Accumulated water in work areas / excavated pits will be pumped to a temporary
ponds / sedimentation basins; only clarified water will be disposed into drains (xi) Safety measures will be undertaken to avoid any risk of collapse due to water
entry (xii) Conduct surface water quality inspection according to the Environmental
Management Plan (EMP).
128. Construction of weir and pick-up weir across the River Kathan may lead to degradation of water quality due to increase in turbidity and chemical contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life, silting/chocking of spill ways/ canals etc. Kathan River is a non-perennial river and almost run dry during summer season. Though there are no notable aquatic life, to ensure that any negative impacts are mitigation, the contractor will be required to:
(i) Select a construction methodology that is least disturbing, and appropriate for the in-situ soil condition, and able to complete the construction work prior to onset of monsoon
(ii) Schedule the construction works in river bed during summer where there is no flow / low water level period – late winter months to pre monsoon (February – June/July); ensure that works are completed during the same period to prior to onset of monsoon; coordinate with upstream dam authorities on release of water; avoid scheduling the works during water release period.
(iii) Do not disturb riverbed except the actual work area; no equipment, machinery shall be operated outside the work area
(iv) Erect temporary barriers to form enclosed construction area with least disturbance
(v) Allow adequate time to settle the distributed solids to prior to pumping out water; only clear/clarified water shall be pumped back into the reservoir; any silt laden water should be pumped to a silt pond
(vi) Avoid/minimize use of fuels, chemicals and lubricants; ensure no spillage (vii) Clean up the area after the completion & prior to the onset of monsoon flow
129. Generation of Construction Wastes. Solid wastes generated from the construction activities are excess excavated earth (spoils), discarded construction materials, cement bags, wood, steel, oils, fuels and other similar items. Domestic solid wastes may also be generated from the workers’ camp. Improper waste management could cause odor and vermin problems, pollution and flow obstruction of nearby watercourses and could negatively impact the landscape. The following mitigation measures to minimize impacts from waste generation shall be implemented by the contractor:
(i) Prepare and implement a Construction Waste Management Plan (ii) Stockpiles, lubricants, fuels, and other materials should be located away from
steep slopes and water bodies;
95
(iii) Avoid stock piling any excess spoils. Excess excavated soils should be dispose to approved designated areas;
(iv) Domestic solid wastes should be properly segregated in biodegradable and non- (v) Biodegradable for collection and disposal to designated solid waste disposal site (vi) Residual and hazardous wastes such a soils, fuels, and lubricants shall bed is
posed in disposal sites approved by local authorities; (vii) Prohibit burning of construction and domestic waste; (viii) Ensure that wastes are not hap hazard dumped with in the project site and
adjacent areas. (ix) Get approval of PIU in writing that the necessary environmental restoration work
has been adequately performed before acceptance 130. Noise and Vibration Levels: Except weir, pick-up weir and water tanks, all the construction work will be conducted at selected sites and along the roads in Bada Malhera urban areas, where there are houses, schools and hospitals, religious & historical places and small- scale businesses. The sensitive receptors are the general population in these areas. Increase in noise level may be caused by excavation, particularly breaking of cement concrete or bitumen roads, operation of construction equipment like concrete mixers, and the transportation of equipment, materials, and people. Vibration generated from construction activity, for instance from the use of pneumatic drills, will have impact on nearby buildings and monuments. This impact is negative but short-term, and reversible by mitigation measures. The construction contractor will be required to:
(i) Plan activities in consultation with PIU so that activities with the greatest potential to generate noise are conducted during periods of the day which will result in least disturbance;
(ii) Horns should not be used unless it is necessary toward other road users or animals of the vehicle’s approach;
(iii) Minimize noise from construction equipment by using vehicles silencers, fitting jackhammers with noise-reducing mufflers, and use portable street barriers to minimize sound impact to surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels (dBA) when measured at a distance of 10m or more from the vehicle/s.
(v) Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity;
131. Surface and Groundwater Quality. Another physical impact that is often associated with excavation is the effect on drainage and the local water table if groundwater and surface water collect in the voids. In Bada Malhera groundwater is deeper than the proposed excavation depths, and rains are limited to short duration during monsoon. However, to ensure that water will not pond in pits and voids near project location, the construction contractor will be required to conduct excavation works in non-monsoon season to the maximum extent possible. 132. Accessibility. Excavation along the roads, hauling of construction materials and operation of equipment on-site can cause traffic problems. Roads in the core/old town area of Bada Malhera is very narrow. However, most of the roads are used by pedestrians and two wheelers, and four wheelers vehicles are very limited. Potential impact is negative but short term and reversible by mitigation measures. The construction contractor will be required to:
(i) Confine work areas along the roads to the minimum possible extent; all the activities, including material & waste/surplus soil stocking should be confined to
96
this area. Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately removed from site/ or brought to the as and when required
(ii) Leave spaces for access between mounds of soil; (iii) Provide walkways and metal sheets where required to maintain access across
for people and vehicles; (iv) Plan transportation routes so that heavy vehicles do not use narrow local roads,
except in the immediate vicinity of delivery sites; (v) MS Trench Bridges3 should be provided with proper handrails so that it can
elderly and children not fall. (vi) Motor able access will be provided in front of the Hospital and school during the
construction period. In front of school or hospital MS Trench Bridges of adequate capacity should be provided with proper handrails so it can withstand the pedestrian loads at these institutions.
(vii) Schedule transport and hauling activities during non-peak hours; (viii) Locate entry and exit points in areas where there is low potential for traffic
congestion; (ix) Keep the site free from all unnecessary obstructions; (x) Drive vehicles in a considerate manner; (xi) Coordinate with Traffic Police for temporary road diversions, where necessary,
and for provision of traffic aids if transportation activities cannot be avoided during peak hours
(xii) Notify affected public by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints.
133. Wherever road width is minimal, there will be temporary loss of access to pedestrians and vehicular traffic including 2 wheelers during the laying of pipes. Under those circumstances, contractor shall adopt following measures:
o Inform the affected local population 1-week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of
access is minimum. o Provide pedestrian access in all the locations until normalcy is restored. Provide
wooden/metal planks over the open trenches at each house to maintain the access.
134. Socio-Economic – Income. The project components will be located in government land and there is no requirement for land acquisition or any resettlement. Construction works will impede the access of residents to specific site in limited cases. The potential impacts are
3 MS Trench Bridge or wwalkways must be provided for pedestrian traffic. These structures shall: i) have a safety
factor of 4; shall have a minimum clear width of 0.51 m; iii) be fitted with hand rails (between 39-in and 45-in from top of deck);and •Mid Rail: centre at 20-in to 22-in from top of deck iv) extend a minimum of 24 in (.61 m) past the surface edge of the trench and v) the deck should be made of slip resistant material and completely drained. The structural requirements of the bridge are as follows; i) Bridge Allowable Loading: distributed load minimum of 50 pounds per square foot (PSF) ; ii) •Point Loading: One (1) 300 pound person including tools per 2-ft of bridge length iii) Handrail Strength: 200 pound point load directed in vertical direction and horizontal direction not simultaneously, applied at any point between support posts; iv) Middle Rail: 150 pound point load directed in vertical direction and horizontal direction not simultaneously, applied at any point between support posts; v) Toe Kick: 50 pound point load directed in horizontal direction, applied at any point between support posts (https://www.osha.gov/dts/osta/otm/otm_v/otm_v_2.html /https://www.ntsafety.com/2016/07/21/temporary-bridges-used-for-worker-access-in-excavation-work/)
97
negative and moderate but short-term and temporary. The construction contractor will be required to:
o Leave spaces for access between mounds of soil; o Provide walkways and metal sheets where required to maintain access across
for people and vehicles; o Increase workforce in the areas with predominantly institutions, place of worship,
business establishment, hospitals, and schools; o Consult businesses and institutions regarding operating hours and factoring this
in work schedules; and o Consult affected business people to inform them in advance when work will
occur. o Provide sign boards for pedestrians to inform nature and duration of construction
works and contact numbers for concerns/complaints. o Notify community/ water users in advance about likely interruptions in water
supply. o Provide alternate sources of clean water until water supply is restored.
135. Socio-Economic – Employment. Manpower will be required during the 24-months construction stage. This can result in generation of temporary employment and increase in local revenue. Thus, potential impact is positive and long-term. The construction contractor will be required to:
o Employ local labour force to the maximum extent; o Secure construction materials from local market.
136. Occupational Health and Safety. Workers need to be mindful of the occupational hazards which can arise from working in height and excavation works. Potential impacts are negative and long-term but reversible by mitigation measures. The construction contractor will be required to:
o Comply with all national, state and local labour laws (see Appendix 7); o IFC’s General EHS Guidelines4 and Sector Specific (Water and Sanitation)
Guidelines5 o A detailed guidance for Safety from COVID-19 Pandemic during construction
works is provided in Appendix 14 - Guideline for Construction work about safety from COVID-19, Pandemic (SOP – Health & Safety Plan).
o Develop and implement site-specific occupational health and safety (OH&S) Plan which will include measures such as: (a) excluding public from the site; (b) ensuring all workers are provided with and use personal protective equipment; (c) OH&S Training6 for all site personnel; (d) documented procedures to be
4 https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-
%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 5 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-
%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES 6 Some of the key areas that may be covered during training as they relate to the primary causes of accidents
include (i) slips, trips and falls; (ii) personal protective equipment; (iii) ergonomics, repetitive motion, and manual handling; (iv) workplace transport; and (v) legislation and responsibilities. Training can provide the foundations of competence but it does not necessarily result in a competent worker. Therefore, it is essential to assess staff competence to ensure that the training provided is relevant and effective. Supervision and monitoring arrangements shall be in place to ensure that training has been effective and the worker is competent at their job. The level of supervision and monitoring required is a management decision that shall be based on the risks
98
followed for all site activities; and (e) documentation of work-related accidents; o Ensure that qualified first-aid is provided at all times. Equipped first-aid stations
shall be easily accessible throughout the site; o Provide medical insurance coverage for workers; o Secure all installations from unauthorized intrusion and accident risks; o Provide supplies of potable drinking water; o Provide clean eating areas where workers are not exposed to hazardous or
noxious substances; o Provide H&S orientation training to all new workers to ensure that they are
apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers;
o Provide visitor orientation if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted;
o Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas;
o Ensure moving equipment is outfitted with audible back-up alarms; o Mark and provide sign boards for hazardous areas such as energized electrical
devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and
o Disallow worker exposure to noise level greater than 85 dBA for duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.
137. Asbestos Materials. Existing AC pipes are laid long back and are presently buried 3-4 m below ground level. Considering the proposed depth of 1-1.2 m below ground level for the new pipes, therefore there is no likely risk of encountering AC pipes during trench excavation works. However, if during implementation if any AC pipes found, because of the health risks these will be left in situ. As part of the project careful planning shall be carried out to prevent any interference with the AC pipes during the construction. Plan pipeline alignments carefully to avoid any conflict or damage. However, as a chance if such pipes are encountered during the construction, exposures of workers to asbestos containing material possess a grave risk. In such cases the following precautions should be taken:
o Workers should be made aware to identify AC pipes. o Work in such area should be immediately stopped and the excavations backfilled
so that it does not expose others to asbestos risk, o The Contractor should prepare an Asbestos Management Plan as illustrated in
the flow chart in Figure 32. o Application of a detailed H&S procedure by the contractor such that equipment
and workers who might have been accidentally exposed to asbestos dust are protected (as per international protocols for exposure to protocol.
associated with the job, the level of competence required, the experience of the individual and whether the worker works as part of a team or is a lone worker.
99
Figure 32 : Flowchart for Preparing an Asbestos Management Plan
100
138. Community Health and Safety. Hazards posed to the public, specifically in high-pedestrian areas may include traffic accidents and vehicle collision with pedestrians. Specific areas of concern have been observed in case of laying of Clear water rising main and distribution networks. Potential impact is negative but short-term and reversible by mitigation measures. The construction contractor will be required to:
o Motorable access is to be provided in front of the Hospital during the construction period. In front of school or hospital MS Trench Bridges7 of adequate capacity should be provided with proper handrails so it can withstand the pedestrian loads at these institutions.
o All excavation, work areas within 500 m of the hospital and education area need to be closed with hard barricading 2.0 m high. The contractor should also provide cross over point where necessary with MS Trench Bridge.
o At sensitive locations particularly where there are schools and markets close to the road, awareness of safety issues will be raised through neighborhood awareness meetings. Conduct noise-generating activities in daytime only and intermittently so that excessive noise may not cause health impact to people.
o In other areas confine work areas, prevent public access to all areas where construction works are on-going using hard barricading and security personnel.
o Provide warning signs, blinkers to the barricading to caution the public about the hazards associated with the works, and presence of deep excavation.
o Minimize the duration of time when the trench is left open through careful planning; plan the work properly from excavation to refilling and road relaying.
o Do not allow any stagnant water during rains at site to prevent mosquito breeding.
o Ensure appropriate and safe passage for pedestrians along the work sites. o Provide temporary traffic control (e.g. flagmen) and signs where necessary to
improve safety and smooth traffic flow. o Where traffic is diverted around crossings, traffic control or careful selection of
the exit from the working areas will be provided with the aim of ensuring that vehicles join the road in a safe manner.
o All drivers and equipment operators will undergo safety training. o Plan routes to avoid times of peak-pedestrian activities. o Liaise with PIU in identifying risk areas on route cards/maps. o Maintain regularly the vehicles and use of manufacturer-approved parts to
minimize potentially serious accidents caused by equipment malfunction or premature failure.
o Provide road signs and flag persons to warn of on-going trenching activities.
7 MS Trench Bridge or wwalkways must be provided for pedestrian traffic. These structures shall: i) have a safety
factor of 4; shall have a minimum clear width of 0.51 m; iii) be fitted with hand rails (between 39-in and 45-in from top of deck);and •Mid Rail: centre at 20-in to 22-in from top of deck iv) extend a minimum of 24 in (.61 m) past the surface edge of the trench and v) the deck should be made of slip resistant material and completely drained. The structural requirements of the bridge are as follows; i) Bridge Allowable Loading: distributed load minimum of 50 pounds per square foot (PSF) ; ii) •Point Loading: One (1) 300 pound person including tools per 2-ft of bridge length iii) Handrail Strength: 200 pound point load directed in vertical direction and horizontal direction not simultaneously, applied at any point between support posts; iv) Middle Rail: 150 pound point load directed in vertical direction and horizontal direction not simultaneously, applied at any point between support posts; v) Toe Kick: 50 pound point load directed in horizontal direction, applied at any point between support posts (https://www.osha.gov/dts/osta/otm/otm_v/otm_v_2.html /https://www.ntsafety.com/2016/07/21/temporary-bridges-used-for-worker-access-in-excavation-work/)
101
139. Road in the old part / Central parts of both the towns are characterized by narrow roads and some of which are accessible only by foot/two wheelers. Congested area have been identified in Bada Malhera town. Besides impeding the access, the trench excavation and pipe laying will pose safety risks to pedestrians, and the people living in these areas. Though the width (~400 mm) and depth (~700 mm) of trench is minimal, it will pose safety risk, especially for sensitive groups i.e., children and elders etc. and the other pedestrian in narrow streets. Trench excavation in narrow street will pose high risk to children and elders in the locality and precautions will thus be needed to ensure the safety of both workers and citizens especially sensitive groups. The construction contractor will be required to produce and implement a site Health and Safety (H&S) plan and this should include such measures as:
o Provide prior information to the local people about the nature and duration of work
o Excluding the public from site o Ensuring that all workers are provided with and use of appropriate personnel
protective equipment (PPE) o Health and safety training for all site personnel o Documented procedures to be followed for all site activities. o Accidents reports and records etc. o Conduct awareness program on safety during the construction work o Undertake the construction work stretch-wise; excavation, pipe laying and trench
refilling should be completed on the same day o Provide barricades, and deploy security personnel to ensure safe movement of
people and also to prevent unnecessary entry and to avoid accidental fall into open trenches
140. Work Camps. Operation of work camps can cause temporary air and noise pollution from machine operation, water pollution from storage and use of fuels, oils, solvents, and lubricants. Potential impacts are negative but short-term and reversible by mitigation measures. The construction contractor will be required to:
o Consult PIU before locating project offices, sheds, and construction plants; o Minimize removal of vegetation and disallow cutting of trees; o Ensure conditions of liveability at work camps are maintained at the highest
standards possible at all times (For details Refer Appendix 13- Guidance for siting and facilities in construction camps);
o Guidelines to be followed for establishing construction camps / labour camps etc. o Camp sites shall be away from residential areas (100 m), sensitive areas
(schools, hospitals, etc. 250 m,) water bodies (500 m) and forests (more than 1 km)
o Use unused, vacant lands; no trees shall be cut o Provide a proper fencing/compound wall o Prepare a site layout plan & display at the site; uniformly label (name boards) all
the places in the facility o Entire site/facility area shall be provided with hard levelled surface as
appropriate; no loose soil, slush, water logging etc., o Living quarters and construction camps shall be provided with standard
materials; no shacks or huts o Provide cooking fuel (cooking gas); and a separate safe place to cook; fire wood
not allowed o Adequate lighting and ventilation
102
o Provide drinking water, water for other uses, and sanitation facilities for employees; drinking water should be regularly tested
o Construct septic tanks and soak pit arrangement for wastewater disposal o Wash area, toilets (separate for women); mobile toilets for linear work o Provide clear pathways (for workers/staff) and roads (for vehicles) for safe
movement in the work site. o A temporary rest area for workers (for resting in break time, protection against
rain/sun, eating etc.) o First Aid o Prohibit employees from poaching wildlife and cutting of trees for firewood; o Train employees in the storage and handling of materials which can potentially
cause soil contamination; o Recover used oil and lubricants and reuse or remove from the site; o Manage solid waste according to the following preference hierarchy: reuse,
recycling and disposal to designated areas; o Solid waste shall be properly manager – provide separate bins, compost
biodegradable waste; sell recyclable waste o Camp sites shall be cleared and restored to original after completion of work, all
debris, wreckage cleared o Remove all wreckage, rubbish, or temporary structures which are no longer
required; and o Confirm to PMU report in writing that the camp has been vacated and restored to
pre-project conditions before acceptance of work.
141. Debris disposal. Prior to the commencement of works, contractor shall identify a debris disposal site in consultation with the PIU and adhering to following criteria:
o The site shall be selected preferably from barren, infertile lands. In case agricultural land needs to be selected, top-soil stripping, stacking and preservation should be undertaken prior to initiation of any activities.
o Debris disposal site shall be at least 200 m away from surface water bodies8. o No residential areas shall be located within 100 m downwind side of the site. o The site is minimum 250 m. away from sensitive locations like hospitals, religious
places, ponds/lakes or other water bodies. o The local governing body and community shall be consulted while selecting the
site.
142. The above impacts are typical for construction in urban areas, and therefore are common to the subproject town. These are negative but short-term and reversible by mitigation measures. There are well-developed and proven measures and construction practices to avoid, mitigate and/or minimize these impacts to acceptable levels. These measures are given in the construction phase EMP applicable to town. D. Operation and Maintenance Impacts
143. Operation and Maintenance of the water supply system will be carried out by DBO contractor for 10 years (including construction period), after which it will be the responsibility of
8 In the absence of site meeting the stipulated criteria, an alternate site can be selected specifying the reasons. In
such a case, the construction camp management plan should incorporate additional measures specific to the site as suggested by the Construction Manager.
103
Bada Malhera Nagar Parishad. During the system design life (15/30 years for mechanical/civil components) it shall not require major repairs or refurbishments and should operate with little maintenance beyond routine actions required to keep the equipment in working order. The stability and integrity of the system will be monitored periodically to detect any problems and allow remedial action if required. Any repairs will be small-scale involving manual, temporary, and short-term works involving regular checking and recording of performance for signs of deterioration, servicing and replacement of parts. 144. Operation and Maintenance of Pipes: Recurrence of pipe bursting and leakage problems can be managed by the leak detection and water auditing surveys. The ULBs will be required to ensure that the leak detection and rectification time is minimized. Repair works could cause some temporary disruption of activities at locations of social and cultural importance such as schools, hospitals, churches, tourist sites etc., so the same precautions as employed during the construction period should be adopted. 145. Exposure to Asbestos during the repair of Pipes: Since the new network would not have any AC pipes there are no risk of exposure to asbestos during the Operation and Maintenance. 146. Water Treatment Plant. The potential impacts for the operation and maintenance of the water treatment plant are: (i) contamination and/or pollution of the water source; (ii) blockage of the intake structure; (iii) contaminated and/or poor quality of drinking/treated water; (iv) generation of sludge; (v) pollution on the receiving body of water for the filter backwash water; and (vi) risks and hazards to the workers in the operation and maintenance of the WTP (i.e. exposure to chlorine gas, fire incidents, accidents during O&M). The preventive and mitigation measures that the contractor should implement are:
o Develop and implement an O& M Manual of the WTP. Basic information that should be included in the O&M plan are: (a) standard operating procedure of all the equipment and unit operations in the treatment plant; (ii) cleaning procedures and frequency; (iii) responsible personnel; maintenance and repairs schedule; (iv) sludge management; and (v) forms and checklist for routine inspection.
o The O&M of the intake structure will include: (a) regular checking of blockage and breakage of intake conduit and pumps; (b) cleaning of screenings and side channels, and (c) monitoring of the water level and flow velocity. For the water quantity, a flow meter should be included in the design to ensure that the environmental/ecological flow of the river is maintained.
o Regular monitoring of the treated water quality to ensure that the parameters are within the applicable standards for drinking water quality (IS 10500:2012). Online analyzers for pH (as per International Union for Pure and Applied Chemistry), Turbidity (as per ISO 7027) and Residual Chlorine shall be installed and linked to the operation control system.
o For the sludge management, the contractor will be responsible for the final disposal of the sludge – For temporary storage a Sludge Storage Tank of 10m X 20 m has been proposed in the DPR.
o For the filter backwash water, the design of WTP has already incorporated recirculation of water and no wastewater will be discharged in the receiving body of water
o To avoid risks and hazards to workers, the contractors should prepare OHS plan during O&M, including emergency response procedures for chemical spill, fire, earthquake, etc. Handling and storage chemicals should be in accordance with
104
the Material Safety Data Sheet. Also, prepare and implement the safety procedures of handling chlorine based on national and international standards such as the World Bank’s Group General EHS Guidelines and EHS Guidelines for Water and Sanitation.
o For the precautions regarding the accidental discharge of chlorine the precautions mentioned in Chapter 8 of the CPHEEO Manual on Water Supply and Treatment must be followed.
147. Since back water is recovered and recirculated in the WTP, no wastewater will be generated from water treatment process. The sludge generated from the wash water storage tank, and sedimentation tanks. 148. Water treatment process will generate sludge from sedimentation of particulate matter in raw water, flocculated and precipitated material resulting from chemical coagulation, residuals of excess chemical dosage, plankton etc; and waste from rinsing and back washing of filter media containing debris, chemical precipitates, straining of organic debris and plankton. Following are included in the subproject design to dispose the sludge and back wash:
(i) Provision for recirculation system for filter backwash – backwash water from filter beds will be sent to a storage tank, and after allowing adequate time for settlement of solids, clarified water will be pumped to WTP inlet. This arrangement will avoid pollution and also minimize wastage of water.
(ii) Accumulated sludge from Tube Settler, filter backwash etc., will be disposed-off at sludge drying beds for natural drying. Dried sludge will be disposed off in a land fill or used as soil conditioner if it is suitable.
E. Project benefits
149. During the construction phase, there are likely to be positive impacts through employment generation, increase in local revenue from the project activities. During the operation phase also, there is potential for employment generation, though limited, as the improved and expanded water infrastructure requires additional workforce. 150. The citizens of the Bada Malhera Nagar Parishad will be the major beneficiaries of the improved water supply system, as they will be provided with a constant supply of better-quality water, piped into their homes at an appropriate pressure. The project will improve the over-all health condition of the town as water borne diseases will be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health. This should also improve the environment of these areas, should deliver major improvements in individual and community health and well-being.
105
VI. INFORMATION DISCLOSURE AND PUBLIC CONSULTATION
A. Overview
151. The active participation of stakeholders including local community, NGOs/CBOs, and the media in all stages of project preparation and implementation is essential for successful implementation of the project. It will ensure that the subprojects are designed, constructed, and operated with utmost consideration to local needs, ensures community acceptance, and will bring maximum benefits to the people. Public consultation and information disclosure is a must as per the ADB policy. 152. Most of the main stakeholders have already been identified and consulted during preparation of this IEE, and any others that are identified during project implementation will be brought into the process in the future. Primary stakeholders of the subproject are: residents, shopkeepers and businesspeople who live and work alongside the roads in which network improvements will be provided and near sites where facilities will be built (WTP and water tanks), and government and utility agencies responsible for provision of services in Bada Malhera PWD, WRD and Madhya Pradesh Pollution Control Board. Secondary stakeholder are: NGOs and CBOs working in the area, community representatives, beneficiary community in general, government agencies, the executing and implementing agencies (MPUDC, PMU and PIUs), Government of India and the ADB. B. Public Consultation
153. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction. Project planning and design stage consultation was conducted at Bada Malhera Nagar Parishad office with elected public representative and people of Bada Malhera town on 19th February 2019 and 12th December 2019 (Refer Appendix 18).
1. Consultation during Project Preparation
154. Institutional consultations were conducted with the Governmental Departments such as PMU, Pollution Control Board, Public Health Engineering Department, Water Resourced Department, and ULB. The project proposal is formulated in consultation with Bada Malhera Nagar Parishad and suits the requirements of the town. 155. Focus-group discussions with affected persons and other stakeholders were conducted to learn their views and concerns. A socio-economic household survey has been conducted in the town, covering sample households, to understand the household characteristics, health status, and the infrastructure service levels, and also the demand for infrastructure services. General public and the people residing along the project activity areas were also consulted during visits to the project sites. At the same time, the communities were informed about the MPUSIP project in detailed along with proposed water supply infrastructure in their town. During consultations, community enquired about the perceived benefits of water supply scheme. During project planning period, there has been consultations on project design, features, implementation procedures, water supply scheme, health and sanitation, formation of GRC, land transfer, rehabilitation of affected households, Possible positive & negative impacts of the project and other environment and social safeguard issues. There is great acceptance of the project as there is only positive impact on the life of community.
106
156. Formal town-level consultation meetings were conducted in February and December 2019 in the subproject town Bada Malhera. Besides, other meetings also conducted at ward-level with communities. The details of consultation are provided in Appendix 18. In all 188 stakeholders participated in the consultations (male = 92, female = 96) 108. Summary of Stakeholder Consultation in Bada Malhera Nagar Parishad: During the consultation/s the following queries were raised by the local communities and it was responded by the Concerned PIU and DPR Consultant.
• All stakeholders were very supporting of the project, and promises to extend full cooperation during the construction phase as the activities are proposed to improve the water supply service levels and the living standards.
• Stakeholder expressed their concern regarding water charges, affordability, disturbance and loss of business due to the work in market areas, dust, road closure etc.).
• Local people should be employed by the contractor during construction work;
• Water logging during rains, damage to existing utilities during excavation, disturbance to shops, traffic etc.,
• Stakeholders also indicated that a public notice on works, and awareness programs to be conducted
• Traffic management should be planned and informed to people well in advance of implementation of the works
• Excavation work should be carried out in the stretches, so as to cause least disturbance to the local public
• Adequate safety measures should be taken during construction work;
• Safety of citizen shall be the top priority during network laying.
• Physical relocation and resettlement should be minimized.
• Utility shifting should be properly planned before execution of the work;
• Road restoration should be carried out properly;
• Special care is needed in case of any structure comes in the alignment like removal or shifting the sacred trees, temples, mosques and other places of cultural and historical significance (by following the rituals and customs of community concerned).
• Septic tanks coming under road ROW or in encroached part, tanks, and other traditional sources of surface water may get affected during excavation which has to be restored timely.
• The project team explained the proposed mitigation measures to mitigate / minimize such issues. Attention of stakeholders drawn to the EMP, and explained to them how the construction phase issues by avoided, minimized or mitigated and managed.
157. It was observed that people are willing to extend their cooperation as the proposed activities are proposed to improve the water supply service levels and the living standards. Stakeholder expressed their concern regarding water charges, affordability, disturbance and loss of business due to the work in market area (dust, road closure etc.). The project team explained the proposed mitigation measures to mitigate / minimize such issues.
2. Consultation during Construction
107
158. Prior to start of construction, ULB and PIU with the assistance of PDMC will conduct information dissemination sessions at various places and solicit the help of the local community, leaders/prominent for the project work. At each ward/neighborhood level, focus group meetings will be conducted to discuss and plan construction work with local communities to reduce disturbance and other impacts. 159. A constant communication will be established with the affected communities to redress the environmental issues likely to surface during construction phases and also regarding the grievance redress mechanism. ULB/PIU and PDMC will organize public meetings and will appraise the communities about the progress on the implementation of EMP. Meeting will also be organized at the potential hotspots/sensitive locations before and during the construction. C. Information Disclosure
160. Executive summary of the IEE will be translated in Hindi and made available at the offices of PMU, PIU, Nagar Parishad offices, and also displayed on their notice boards. Hard copies of the IEE will be accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. Electronic version of the IEE in English and Executive Summary in Hindi will be placed in the official website of the MPUDC, PMU after approval of the IEE by Government and ADB. Stakeholders will also be made aware of grievance register and redress mechanism. 161. Public information campaigns to explain the project details to a wider population will be conducted. Public disclosure meetings will be conducted at key project stages to inform the public of progress and future plans. Prior to start of construction, the PMU/PIU will issue Notification on the start date of implementation in local newspapers A board showing the details of the project will be displayed at the construction site for the information of general public. 162. Local communities will be continuously consulted regarding location of construction camps, access and hauling routes and other likely disturbances during construction. The road closure together with the proposed detours will be communicated via advertising, pamphlets, radio broadcasts, road signage, etc.
108
VII. GRIEVANCE REDRESSMECHANISM
A. Project Specific Grievance Redress Mechanism
163. Grievance Redress Mechanism (GRM) is a part of project management that is likely to increase accountability and responsiveness among service providers and provide a friendly environment to the beneficiaries of the project. GRM is considered a tool to measure efficiency and effectiveness of the project as it provides important feedback on the project management. Effectively addressing public grievances is a core component of managing risks under Asian Development Bank (ADB) projects according to the Safeguard Policy Statement (Safeguard Requirement 2: Involuntary Resettlement, Social safeguard and Environmental Safeguard; Pages 49-50, June 2009) – “The borrower/client will establish a mechanism to receive and facilitate the resolution of affected persons’ concerns and grievances about physical and economic displacement and other project impacts, paying particular attention to the impacts on vulnerable groups. The grievance redress mechanism should be scaled to the risks and adverse impacts of the project. It should address affected persons’ concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to the affected persons at no costs and without retribution. The mechanism should not impede access to the country’s judicial or administrative remedies. The borrower/client will inform affected persons about the mechanism”. The statement allows the formation of grievance redress committee in the project areas to facilitate the concerns of affected people under the project areas. B. Purpose of the GRM Manual:
164. This document describes the procedure that shall be followed by the Madhya Pradesh Urban Development Company Limited (MPUDCL) under Madhya Pradesh Urban Services Improvement project (MPUSIP) to address complaints or concerns shared by people affected due to project related interventions. 165. The present document intends to provide clarity to project stakeholders on the grievance redress mechanism procedures to be followed under the project. The document provides clarity on how the complaint shall be received, registered, sorted, assessed, resolved and monitored under MPUSIP. This also includes action plans to be followed for effective implementation. C. Principles:
166. The GRM is based on the following principles and the same shall be used to assess the GRM performance:
1. Accessibility
167. The GRM shall be accessible to all people residing in the project area. It shall be available and provide assistance to all project affected people irrespective of language, literacy level, or cost. Project affected people shall access the GRM without fear of reprisal. Information on the GRM will be disseminated using various means to ensure people know about GRC, its members and procedures.
2. Predictability
109
168. The GRM shall offer clear procedures with time frames for each stage and clarity on the type of results it can and cannot deliver.
3. Transparency
169. The GRM shall operate in such a way that it is easy for others to see what actions are being performed. This will be undertaken through disclosure of all information to the public and affected people.
4. Credibility
170. The performance of the GRM shall enable affected people to accept and believe that the mechanism works, delivers results and is trustworthy.
5. Fairness
171. The GRM procedures shall be perceived as fair, especially in terms of access to information, and opportunities for meaningful participation in the final decision. Its outcome should be consistent with applicable national standards and should not restrict access to other redress mechanisms.
6. Feedback
172. The GRM shall serve as a means to channel citizen feedback to improve project outcomes for the people. 173. It is difficult to avoid Grievances totally but much can be done to minimize and manage complaints in order to reduce impacts. D. Nature and scope of Grievance Redress Mechanism under MPUSIP
174. GRM aims to address complaints of local affected people because of project interventions in the selected towns (64 towns) of MPUSIP during the project period. 175. MPUSIP predicts public complaints because of the nature of the project during the design, implementation and operation & maintenance stage of the project. In the design phase, people are expected to raise inconveniences with regards to land acquisition, compensation amount, compensation procedure and environmental issues. During project implementation, grievances may come from individuals or a particular group of people in relation to construction related inconveniences such as dust, noise, blocking drainage, damage roads, walls/boundaries of property and its impact on their daily lives in addition to land acquisition, and compensation. Issues related to corruption shall not be considered by the Grievance Redress Committee (GRC). Corruption related issues shall be forwarded to the State GRC (PMU) directly by the Chairperson of town level GRC at the time of sorting of grievances. The structure, functions of GRC, monitoring & evaluation systems and action plan of its implementation is described below: E. Structure of GRM and its Functions:
176. The GRM will have a three- tier decision making process. The first tier which is at the town level aims to resolve all construction related grievances which require quick and efficient action. The second tier which is at the project implementation unit (PIU) will handle complaints
110
that could not be resolved by the first- tier level and/or grievances related to land acquisition and compensation. The third tier which is at the project management unit (PMU) or state level will handle complaints which are over and above the scope for the first and second tier and/or complaints which could not be resolved by the first and second tier levels. 177. Contact numbers of GRC Chair-person and members, CDO and contractor’s focal person will be placed at appropriate locations like construction sites, ULB office etc. 178. The three-tier Grievance Redress Mechanism under MPUSIP is described below: 1st tier (At Town Level): composition of the Grievance Redress Committee (GRC):
• A representative of Chief Municipal Officer associated with Urban Local Body, Chairperson;
• CDO of ULB designated/nominated by ULB. • Field Engineer of Project Management Consultants; • Focal person (GRC Person) of DBO contractor of respective town; • Field Engineer of concerned ULB designated by the respective PIU, Secretary;
Major Functions: The major functions of town level GRC is as follows:
• Registration of Grievances by the Local person (GRC Person) of DBO contractor of respective town Sorting of Grievances by Focal person (GRC Person) of DBO contractor of respective town and Chairperson;
• Forwarding grievances to concerned authorities i.e. Site Engineer for resolution; • Information to the complainant on the decision taken to address registered
complaint and expected time to resolve issue; • Resolution of issues emerged due to construction; • Feedback to the complainant on action completed against registered complaint
and seeking complainant feedback on level of satisfaction; • Closure of grievances by CDO-ULB or forwarding of complaint to PIU GRC if
grievance remains unresolved. 2nd Tier {At PIU Level}: Composition of the PIU level GRC:
• Project Manager, associated with Project Implementation Unit (PIU) of Madhya Pradesh
• Urban Development Company Limited - Chairperson • An elected member nominated by Mayor in Council/ President in Council of
associated • Urban Local Body (ULB). • A Social Worker nominated by Mayor in Council/ President in Council of
associated Urban • Local Body • Commissioner of associated Urban Local Body/Chief Municipal Officer or
Community • Development Officer/Community Organizer of Urban Local Body. • Community Development Officer CDO-PIU - Secretary
Major Functions: The following functions will be performed by the PIU level GRC:
• Registration of complaints by CDO-PIU from the 1st tier GRC and/or affected people;
111
• Eligibility assessment of grievances by the GRC Chairperson; • Information to the complainant about eligibility of the complaint; • Grievance Redress Committee meetings to discuss grievances and action
required; • Ensuring collection of detailed information about the eligible complaint; • Assessment of complaint, draw conclusion from discussions and make
recommendations; • Develop action plan outlining activities required to implement the
recommendations; • Ensuring implementation of recommendations by stakeholders or concerned
authorities; • Monitoring actions of the recommendations in view of timeline; • Feedback to the complainant on action completed against registered complaint
and seeking complainant feedback on level of satisfaction; • Closure of grievances by CDO-PIU or forwarding of complaint to PMU GRC if
grievance remains unresolved. 3rd Tier {At PMU-State Level} Composition of State Level GRC:
• Engineer in Chief, MPUDC – Chairperson • Deputy Project Director (T) • Deputy Project Director (A) (Secretary) • Project Officer • Community Development Officer CDO-PMU • PMC TL or representative Advisor
Major Functions: The state level GRC will be responsible to perform the following functions:
• Registration of complaints received from GRC PIU and/or affected people; • Information to the complainant about eligibility of the complaint; • Eligibility assessment of grievances by the GRC PMU chairperson with support
of the • Secretary of state GRC- – whether grievance is eligible for consideration or not at
the state level; • Ensuring collection of required information about the eligible complaint; • Assessment of complaint to draw conclusion from discussions and make
recommendations; • Develop action plan outlining activities required to implement the
recommendations; • Ensuring implementation of recommendations by stakeholders or concerned
authorities; • Monitoring actions of the recommendations in view of timeline; • Closing complaint after all actions taken as per recommendations and feedback
to the complainant. • Advise to complainants about approach /appeal to the concerned department in
case the complainant is not satisfied or complaint is beyond the scope of the GRC PMU.
112
Figure 33: Work Flow Diagram on GRM
F. Process of Grievance Redress Mechanism
179. The following process shall be adopted for receiving complaints and addressing received complaints: Step 1: Receiving Grievances/ Complaints and its Registration at town Level:
• All grievances, complaints, concerns shall be submitted verbally or in writing to CDO contractor’s focal person or any GRC members – by filling the Complaint Registration Slip and putting into the complaint box placed at construction sites or ULB office.
• Received complaints shall be recorded, compiled and Registered (Grievance Number) in a register (database) placed at the ULB by CDO with support of the
Grievance
Redress
Mechanism
Step 1: Receiving Grievances /
Complaints and its Registration at
Step 2: Review
of Grievances,
Sorting,
Information and
Ste
p 3
: E
lig
ibil
ity a
nd
Pre
pa
rati
on
fo
r
GR
C M
ee
tin
g (
3 D
ay
s)
Step 4: Assessment of the
Grievance, Meeting and Plan of
Step 5: Implementation of
Action
Ste
p 6
: M
on
ito
rin
g a
nd
Re
po
rtin
g
(Mo
nth
ly)
Ste
p 7
: C
losu
re o
f th
e
Co
mp
lain
t
Step 8: Appeal to the
State Level GRC
113
contractor’s focal person on a daily basis (24 hours). Each grievance shall be given a number to track status.
Step 2: Review of Grievances, Sorting, Information and Forwarding (24 hours):
• Registered grievances shall be reviewed by the CDO with support of the contractor’s focal person.
• Based on type of grievances, CDO shall sort out grievances with support of the contractor’s focal person.
• CDO (ULB) shall inform the GRC Chairperson about all grievances either by phone or in writing. At that time, CDO may suggest grievances can be managed by the site engineer to the GRC Chairperson;
• GRC Chairperson will determine eligibility of the complaints. Inconveniences caused by minor construction related issues shall be referred to the site engineer to resolve immediately or within 24 hours. For example -site engineer shall be instructed to resolve grievances associated with construction at the town such as restoration of road, obstruction in accessing house/shop or any place due to dumping of construction materials, dust etc. Site engineer will be responsible to respond to the complaints immediately. On the other hand, issues which cannot be resolved by the site engineer and if it is complex in nature shall be referred to GRC.
• CDO shall receive acknowledgement from concerned authorities (site engineer) on receipt of the grievances shared with them. CDO shall inform complainants regarding eligibility of their complaint and action to be taken by the concerned authority (site engineer/ GRC) within (24 hours). If the grievance is ineligible, complainants should be informed of the reasons;
Step 3: Eligibility and Preparation for GRC meeting (3 days):
• GRC Chairperson shall receive eligible complaints (copy of written complaint document or verbally recorded messages) from the CDO (ULB) and review details; GRC Chairperson may ask to collect baseline information about the grievances registered, if required.
• GRC Chairperson shall share list of documents with the GRC Secretary to collect baseline information on selected grievances to be addressed.
• The GRC Secretary shall arrange all documents with the help of CDO-ULB, CDO-PIU or the contractor’s focal person in a proper way to present in front of GRC.
• GRC Chairperson shall call a meeting as per convenient date and time of the committee members.
Step 4: Assessment of the Grievance, Meeting and Plan of Action (7 days):
• If necessary, the GRC shall consult and seek relevant information about complaint from the concerned parties.
• On basis of the collected evidences, GRC shall draw conclusions and make recommendations for a solution.
• GRC Secretary shall keep record of the proceedings and decisions taken by GRC members to further track the status as per decided time line.
114
• The GRC shall agree on the action plan required to be implemented according to the recommendations made. The action plan shall include detailed activities along with timeline.
• GRC Secretary shall inform to the complainant about the decisions taken by the committee members and expected date of resolution of the grievance.
• If the complaint is complex, the GRC may request for additional time and resolution after proper assessment or refer the complaint to the GRC-PMU Level.
Step 5: Implementation of Action (30 days)
• The concerned parties shall be responsible to implement action plan according to recommendations of the GRC.
• The GRC members may arrange field trip and interact with the concerned persons, if needed before reaching the conclusion.
Step 6: Monitoring and Reporting (Monthly)
• CDO (ULB) shall be responsible to track and record status of all complaints -whether forwarded to site engineer or GRC in the database as follows – Grievance registered, Grievance in process to be resolved, Grievance addressed and closed, and Grievance forwarded to concerned authorities.
• CDO (ULB) shall be responsible to report/inform status of the complaints (received, addressed and forwarded) to the contractor for further reporting to respective PIU.
• Overall GRC chairperson shall be responsible for effective management of complaints at the town level.
Step 7: Closure of the Complaint
• GRC Secretary shall prepare a summary of the findings and share with GRC members.
• On agreement of all GRC members, GRC Secretary shall provide information to the complainant about decisions taken in writing/verbal on the registered complaint and seek feedback of the complainant about the decisions taken. A copy of the letter shall be kept as record with GRC Secretary and CDO (ULB).
• Complaint shall be considered closed if all actions have been taken and the complainant satisfied with the resolution.
• GRC Secretary shall prepare a closure report of the grievances handled by GRC members and the closure shall be documented by the CDO (ULB) in his register.
Step 8: Appeal to the State level GRC
• In the event that GRC PIU cannot make a decision on how to resolve the complaint, or if a complainant is not satisfied with the actions taken to resolve the complaint by the GRC (PIU), an appeal can be made to state level GRC (PMU) either by the GRC Chairperson (PIU) or complainant directly.
• GRC Chairperson (PIU) or complainant shall submit an appeal in writing to the state level GRC established at PMU.
• The state GRC Secretary shall register the case in consultation with Chairperson and provide a number of the grievances to be tracked.
115
• The state GRC Secretary shall acknowledge the registration of the grievance to the complainant in writing.
• The Secretary of the GRC shall review the registered grievances and collect required evidences from relevant parties to present case to the GRC.
• The state GRC Chairperson shall call a GRC meeting to review the complaint. GRC members shall get information about the meeting in advance to ensure their availability in the meeting.
• The state GRC shall draw conclusions and recommendations based on the evidence in the meeting. At the same time an action plan shall be developed for implementation with a timeline.
• The state GRC Secretary shall communicate decisions of the State GRC to the complainant in writing. The copy of the communication shall be kept with the state GRC Secretary as record.
• The recommendations shall be implemented immediately
• Upon completion of the recommended actions, the state GRC Secretary shall prepare a report on the closure of the complaint which will be signed by the complainant and state GRC Chairperson. A copy of the same shall be kept for record.
180. The structure and process of GRM is presented below for detailed understanding.
Figure 34: Structure and Process of GRC
G. Monitoring and Evaluation Systems of GRM
116
181. All grievances, concerns and complaints received shall be recorded by concerned authorities to be tracked. The status of the grievances shall be discussed in the review meetings organized at PIU and PMU level. The following indicators shall be monitored and recorded:
- Number and type of complaints received;
- Number and % of complaints that have been resolved;
- Number and % of complaints that are unresolved;
182. The State GRC shall review grievance related data on monthly basis to evaluate the functionality of the system, as well as to note the followings:
• Failures to follow GRM procedures;
• Delays in complaint resolution, particularly those that can affect project construction;
• Most frequent types of grievances and complaints;
• Location(s) producing the most grievances and complaints;
H. Action Plan for the formation of the GRM
S. No Action Plan Time Line
A Action required at PMU/PMC
A1 Letter for formation of GRC and follow up Pre -construction
A2 Development of GRM Manual Pre -construction
A3 Orientation of GRC members by integrating with training/workshops/meetings
Construction
A4 Integration of GRC topic in BCC – like availability of GRC and its procedure
Construction
A5 Review of functioning of GRC by integrating with meetings and visits
Construction
B Action at Town level
B1 Formation of GRC at town level and inform to the PMU/PMC Pre -construction
B2 Information to All ULB Officials/Public about existence of GRC, its committee members and their function
Construction
B3 Orientation of all GRC members during visit of PMU and PMC officials
Construction
B4 Tracking of complaint registered and its status Construction
B5 Sharing status of grievances with PIUs with the help of GRC person
Construction
B6 Training of selected women to maintain grievances at customer service center (Educated Prerak (Motivator) may be considered)
Construction
B7 Complaint management Operation and maintenance phase
117
VIII. ENVIRONMENTAL MANAGEMENT PLAN
A. Environmental Management Plan
183. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels.
184. The EMP will guide the environmentally-sound construction of the subproject and ensure
efficient lines of communication between MPUDC, project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.
185. The contractor will be required to submit to PIU, for review and approval, a site
environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.
186. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.
187. For civil works, the contractor will be required to (i) carry out all of the mitigation and
monitoring measures set forth in the approved SEP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and SEP. The contractor shall allocate budget for compliance with these SEP measures, requirements and actions.
188. The following tables 19-24, show the potential environmental impacts, proposed
mitigation measures and responsible agencies for implementation and monitoring.
118
Page | 118
Table 19: Design Stage Environmental Management Plan Field Anticipated
Impact
Mitigation Measures Responsible for
Implementation
Cost and
Source of
Funds
Design of
water supply
system
Unsustainable
source;
resource
conservation
& energy use
• Discontinuation of current unsustainable groundwater source and developing a surface water source (Kathan River) based system by constructing weir, pick-up weir for creating storage and rehabilitation/augmentation of existing intake well
• duly utilizing the existing infrastructure like intakes and water treatment plant with necessary repairs and rehabilitation
• Limiting the height of water impounding structures (weir and pick-up weir) well below the height of the river banks so that the storage is limited to the river course.
• Design of apron to arrest erosion of the river bank of the downstream of weir and pick-up weir.
• Provision of low level sluice gates to allow heavy monsoon flow freely without any obstruction and to avoid dam silting.
• Recovering wash water from treatment process • Rehabilitation and repair of existing WTP and Treatment and reuse of
sludge from treatment process
• Improving the exiting WTP with wash water and sludge management and chlorine safety measures
• Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (HDPE pipes up to 150 mm dia joined by electro fusion couplers using on-site electro fusion welding, and all higher dia pipes by on site butt welding)
• Designing the entire system to maintain optimal flow and terminal pressure, and optimizing the overall energy usage
• Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies
• Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor
• Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections
• Using low-noise and energy efficient pumping systems
• During the design, construction, and operation of the project, apply
These measures
are already
included in the
preliminary
designs.
DBO Contractor
(DBOC) to follow,
enhance where
possible.
PMU to ensure
compliance.
Part of
project
costs
119
Field Anticipated
Impact
Mitigation Measures Responsible for
Implementation
Cost and
Source of
Funds
pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines9 and Sector Specific (Water and Sanitation) Guidelines10).
Water
abstraction
from Kathan
River for
Bada
Malhera town
WSS
Project
sustainability
& water use
conflicts
• Obtain permission from Water resources department, GoMP for water abstraction and construction of weir and pick-up weir across Kathan River prior to start of works.
PMU & Bada
Malhera Nagar
Parishad,
No costs;
scope of
IA
Construction
and operation
of weir
Safety of
existing road
bridge on the
downstream
side (135 m
away) and
safety of road
users
• Assess the stability and safety of the low level road bridges located in the downstream, and take necessary precautions to ensure safety of due to release of water from weir during operation
• Rik of bridge submergence due to water impoundment of downstream weir, and water releases from upstream weir should be assessed, and necessary measures should be incorporated in the detailed design, and operation
• Coordinate with respective road agency (PWD)
PMU and DBO
Contractor
No costs;
scope of
IA
Waste
generation
from WTP
operations
Environmental
pollution
• Obtain consent from MPPCB for existing WTP at Bada Malhera prior to start of repair and rehabilitation works
PMU / Nagar
Parishad; DBOC
to prepare
application, and
assist as required
No costs;
scope of
IA & DBO
Chlorine Chlorine o Provide the following measure at the chlorine application unit: These measures Project
9https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 10 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES
120
Field Anticipated
Impact
Mitigation Measures Responsible for
Implementation
Cost and
Source of
Funds
usage as
disinfectant at
WTP
handling &
application
risk – health &
safety risk to
workers and
general public
o Chlorine neutralization pit with a lime slurry feeder o Proper ventilation, lighting, entry and exit facilities o Facility for isolation in the event of major chlorine leakage (if needed) o Continuous monitoring and detection of leaks o Personal protection and safety equipment for the operators in the
chlorine plant o Provide training to the staff in safe handling and application of
chlorine; this shall be included in the contract of Chlorinator supplier o Supplier of Chlorinator equipment shall provide standard operating
manual for safe operation and as well as maintenance and repairs; preferably these shall be provided both in English and Hindi Languages
o Develop procedures for handling of emergencies and provide training to the employees.
are already
included in the
preliminary
designs.
DBOC to follow,
enhance where
possible.
PMU to ensure
compliance.
Costs
Corrective actions at the existing WTP to ensure compliance with ADB SPS 2009 and GoI regulatory framework
Non-compliance
• Provide backwash recirculation facility – this will not only improve environmental performance but also minimizes raw water intake
• If the above is not feasible for technical reasons, then a simple sedimentation pond/tank of adequate capacity will be developed within the WTP campus; back will be sent this tank, where the impurities will be settled, and only clarified water will be disposed. The sludge from this tank will be periodically removed and dried in sludge drying beds, and disposed off.
• Creation of sludge collection, drying and disposal system
• Proper & safe facility for handling and storing chemicals used in treatment process (alum, bleaching powder, chlorine etc.,) including provision of personal protection equipment
• Training for the workers in safe operation of WTP
These measures are already included in the preliminary designs. DBOC to follow, enhance where possible.
PMU to ensure
compliance.
Project
Costs
Procurement
of Material
Procurement
of Hazardous
material
(Biphenyl)
• No transformer shall be procured under MPUSIP which contains biphenyl
• The Bid Document should clearly state this condition.
DBO Contractor /
PMU
Project
Costs
121
Table 20: Pre-Construction State Environmental Management Plan Field Anticipated
Impact Mitigation Measures Responsible for
Implementation Monitoring of Mitigation
Cost and Source of Funds
EMP Implementation & reporting
Unsatisfactory compliance to EMP
• Appoint EHS supervisor and designate site safety steward (among the technical staff) at each site to take care of EHS issues on site on day-to-day basis under the guidance of EHS supervisor.
• Ensure that all pre-construction activities are complete prior to start of construction work
• Updated IEE / site specific EMP will be submitted
• Ensure timely submission of monitoring reports
• “Works cannot be commenced until the contractor submits Site-specific Health and Safety Plan including Health and Safety COVID-19 Plan (HSCOVID 19) and PIU/PMU approves”
DBO contractor in collaboration with PIU and with approval of PMU
• Ensure that all pre-construction activities are complete prior to start of construction work
• Ensure timely submission of monitoring reports
Cost for
implementation
of mitigation
measures
responsibility
of contractor.
Utilities Telephone lines, electric poles and wires, water lines within proposed project area
• Identify and include locations and operators of these utilities in the detailed design documents to prevent unnecessary disruption of services during construction phase; and
• Require construction contractors to prepare a contingency plan to include actions to be taken in case of unintentional interruption of services.
• Require contractors to prepare
DBO Contractor in
collaboration with
PIU and with
approval of PMU
• List of affected utilities and operators;
• Bid document to include requirement for a contingency plan for service interruptions (example provision of water if disruption is more than 24 hours), waste management
Project costs – general construction practice
122
Field Anticipated Impact
Mitigation Measures Responsible for Implementation
Monitoring of Mitigation
Cost and Source of Funds
spoils (waste) management plan (Appendix 10) and traffic management plan (Appendix 9)
plan and traffic management plan
Construction work camps, stockpile areas, storage areas, and disposal areas.
Conflicts with local community; disruption to traffic flow and sensitive receptors
• The Guidelines of Construction Camps mentions guidelines for siting of Construction Camp. This should be strictly maintained.
• Prioritize barren, waste, infertile, vacant lands within the area,
• Shall not be located in productive agricultural lands, water bodies, natural drainage channels, flood plains & groundwater recharge areas, forests, vegetative lands, etc.
• Prioritize areas within or nearest possible vacant space in the project location;
• If it is deemed necessary to locate elsewhere, consider sites that will not promote instability flooding and result in destruction of property, natural drainage, vegetation, irrigation, and drinking water supply systems;
• For private lands, obtain land owner’s (not lessees) written consent; indicate the requirement for reinstatement to original
• Do not consider residential areas;
• Take extreme care in selecting sites to avoid direct disposal to
DBO Contractor to
finalize locations in
consultation and
approval of PIU
• List of selected sites for construction work camps, hot mix plants, stockpile areas, storage areas, and disposal areas.
• Written consent of landowner/s (not lessee/s)
Project costs – general construction practice
123
Field Anticipated Impact
Mitigation Measures Responsible for Implementation
Monitoring of Mitigation
Cost and Source of Funds
water body which will inconvenience the community.
• For excess spoil disposal, ensure (a) site shall be selected preferably from barren, infertile lands. In case agricultural land needs to be selected, written consent from landowners (not lessees) will be obtained; (b) debris disposal site shall be at least 200 m away from surface water bodies; (c) no residential areas shall be located within 50 m downwind side of the site; and (d) site is minimum 250 m away from sensitive locations like settlements, ponds/lakes or other water bodies.
• Document site’s pre-project conditions
Sources of
Materials
Extraction of
materials can
disrupt natural
land contours
and vegetation
resulting in
accelerated
erosion,
disturbance in
natural
drainage
patterns,
ponding and
water logging,
and water
• To prevent the adverse effect from the sourcing of quarry material required i.e. sand and stone aggregate, the following measures will be adopted in MPUSIP:
• Prioritize sites already permitted by the Department of Mines and Geology
• The material will be procured from existing quarries which have valid Environmental Clearance by the State Environmental Appraisal Committee/ State Environmental Appraisal Authority.
DBO Contractor to
prepare list of
approved quarry
sites and sources
of materials with
the approval of PIU
• List of approved quarry sites and sources of materials;
Part of project costs
124
Field Anticipated Impact
Mitigation Measures Responsible for Implementation
Monitoring of Mitigation
Cost and Source of Funds
pollution. • Further as a contractual obligation the Contractor is required to submit the Environmental Clearance certificate and the latest copy of the six-monthly Compliance Report submitted by the Quarry to MPPCB to the PIU before the procurement of the material. Contractor to submit to PIU on a monthly basis documentation on material obtained from each source (quarry/ borrow pit).
• However, if the Contractor opens a new quarry he has to obtain the environmental clearance and submit the same to the PIU before extracting any material from the quarry/sand mine.
• Submit to MPUDC on a monthly basis report of the quantity of material procured/extracted from each quarry
• If additional quarries will be required after construction is started, inform construction contractor to obtain a written approval from PIU.
• Maintain a construction material register at the site
• A monthly report will be submitted to PIU on construction material quantity (sources-wise)
• All clearance/license copies of quarries / borrow areas are
125
Field Anticipated Impact
Mitigation Measures Responsible for Implementation
Monitoring of Mitigation
Cost and Source of Funds
provided to PIU for prior approval
Consents,
permits,
clearances,
NOCs, etc.
Failure to
obtain
necessary
consents,
permits, NOCs,
etc. can result
to design
revisions and/or
stoppage of
works
• Obtain all necessary consents, permits, clearance, NOCs, etc. prior to award of civil works.
• Ensure that all necessary approvals for construction to be obtained by contractor are in place including in compliance with labour laws, before start of construction
• Contractor to acknowledge in writing to PIU and provide report on compliance all obtained consents, permits, clearance, NOCs, etc.
• Copies of all permission / approvals are submitted to PIU prior to start of work
• Include in detailed design drawings and documents all conditions and provisions if necessary
PIU and PMU • Incorporated in final design and communicated to contractors.
No cost required. Cost of obtaining all consents, permits, clearance, NOCs, etc. prior to start of civil works responsibility of PIU.
Asbestos
Cement Pipes
Health risk due
to exposure to
asbestos
materials
• Obtain details from PHED/NPs on location of underground AC pipes
• Contractor should prepare a detailed survey with the assistance of PHED and /NP on the presence of existing AC pipes in the distribution network or on areas which involve pipe laying activities. In the final IEE, a map showing the exact location of the AC pipes should be provided.
DBO Contractor in
coordination with
PIU and PMC
• Detailed construction drawings showing alignment of AC pipes
No cost
required.
Mitigation
measures are
part of TOR of
PIU and
PMDSC
126
Field Anticipated Impact
Mitigation Measures Responsible for Implementation
Monitoring of Mitigation
Cost and Source of Funds
• Locate the new pipe/sewer carefully to avoid encountering AC pipes
• All AC pipes will be left in situ and untouched. New pipes will be placed next to AC pipes.
• In the event, that the asbestos fibers from AC pipes were accidentally disturbed/ exposed, the contractor should also prepare SOP for handling the AC pipes.
• Safe disposal and precaution will be taken as per the USEPA https://www.epa.gov/asbestos/safe-work-practices
Guidelines to be followed for establishing construction camps / labour camps
Establishing construction camps / labour camps
• Camp sites shall be away from residential areas (100 m), sensitive areas (schools, hospitals, etc. 250 m,) water bodies (500 m) and forests (more than 1 km)
• Use unused, vacant lands; no trees shall be cut
• Provide a proper fencing/compound wall
• Prepare a site layout plan & display at the site; uniformly label (name boards) all the places in the facility
• Entire site/facility area shall be provided with hard leveled surface as appropriate; no loose soil, slush, water logging etc.,
DBO Contractor to
finalize locations in
consultation and
approval of PIU
• List of selected sites for construction work camps/labour camps
Project costs – general construction practice
127
Field Anticipated Impact
Mitigation Measures Responsible for Implementation
Monitoring of Mitigation
Cost and Source of Funds
• Living quarters and construction camps shall be provided with standard materials; no shacks or huts
• Adequate lighting and ventilation
• Provide drinking water, water for other uses, and sanitation facilities; drinking water should be regularly tested
• Provide clear pathways for safe movement
• Provide cooking fuel (cooking gas); and a separate safe place to cook; fire wood not allowed
• Construct septic tanks and soak pit arrangement for wastewater disposal
• Solid waste shall be properly manager – provide separate bins, compost biodegradable waste; sell recyclable waste
• Camp sites shall be cleared and restored to original after completion of work, all debris, wreckage cleared
Work site
management
• Provide a proper fencing/compound wall
• Prepare a site layout plan & display at the site; uniformly label (name boards) all the places in the facility
• Entire site/facility area shall be provided with hard leveled surface as appropriate; no loose soil, slush, water logging
DBO Contractor • Provide a proper fencing/compound wall
Project costs – general construction practice
128
Field Anticipated Impact
Mitigation Measures Responsible for Implementation
Monitoring of Mitigation
Cost and Source of Funds
etc.,
• Provide clear pathways (for workers/staff) and roads (for vehicles) for safe movement in the work site
Worker
amenities at all
work sites
• A temporary rest area for workers (for resting in break time, protection against rain/sun, eating etc.)
• Drinking water
• Wash area, toilets (separate for women); mobile toilets for linear work
• Septic tank and soak pits for waste disposal
• First aid
DBO Contractor • Provide basic facilities for site worker
Project costs – general construction practice
Table 21: Construction Stage Environmental Management Plan
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
EMP
Implementation
Training
Irreversible
impact to the
environment,
workers, and
community
• Project manager, staff and all key workers will be required to undergo training on EMP implementation including spoils/waste management, Standard operating procedures (SOP) for construction works; occupational health and safety (OH&S), core labor laws, applicable environmental laws, etc. prior to start of work
DBO
Contractor
Certificate of Completion
(Safeguards
Compliance Orientation)
Posting of EMP at
worksites
Cost of EMP
Implementation
Orientation
Training to
contractor is
responsibility of
PMU.
Other costs
responsibility of
contractor.
Air Quality Emissions from
construction
Vehicle emissions;
• Fit all heavy equipment, and
DBO • Location of stockpiles;
Cost for
implementation
129
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
vehicles,
equipment, and
machinery used
for installation of
pipelines
resulting to
dusts and
increase in
concentration of
vehicle-related
pollutants such
as carbon
monoxide, sulfur
oxides,
particulate
matter, nitrous
oxides, and
hydrocarbons.
machinery with air pollution control devices which are operating correctly; all the vehicle shall meet the emission norms and shall have valid pollution under control (PUC) certificate (Appendix 3)
• Pollution under control (PUC) certificate will be obtained for all vehicles, equipment, and records maintained
Dust Control;
• Dust screen will be provided around work sites (OHT and WTP, intake etc.)
• Loose soil on work sites, vehicle and worker movement areas will be properly rammed and stabilized to minimize dust generation; it will be ensured that no loose soil surface at working places
• Access to work area will be controlled; unnecessary movement of vehicles, workers and public in work areas will be controlled to minimize soil disturbance
• Prior to any leveling or earth moving activity, water will be sprinkled to avoid dust
• Damp down exposed soil and any stockpiled material on site by water sprinkling;
• Water will be sprinkled adequately (at least daily 3 times in dry weather) to maintain surface in stabilized and damp condition
• Material stocks will be covered with tarpaulins/covers at the sites
Contractor • Complaints from sensitive receptors;
• Heavy equipment and machinery with air pollution control devices;
• Pollution under control certificate
of mitigation
measures
responsibility of
contractor.
130
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
• Use tarpaulins to cover sand and other loose material when transported by trucks;
• Loose material from trucks will be unloaded in a barricaded area and with water sprinkling
• Clean wheels and undercarriage of haul trucks prior to leaving construction site
• Disallow access in the work area except workers to limit soil disturbance and prevent access by barricading and security personnel
Dust control from pipeline works;
• Construction area will be barricaded on both sides using hard barricades of 2m height
• Site clearance and excavation work will be commenced only after barricading the site
• Works and all associated activities (material, soil, debris, equipment, machinery) will be confined to barricaded area
• Excavated soil storage will be removed from the site immediately & stored/disposed at identified site
• Work will be undertaken section wise (100-500 m) at various places; these sections will be demarcated and barricaded and trench filled
• Work will be conducted work sequentially - excavation, pipe laying, backfilling; testing section-wise (for a minimum length as
131
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
possible) so that backfilling, stabilization of soil can be done
• Excavated soil will be removed section-wise, and used for filling the previous section, this is to avoid stocking of excavated soil
• Road restoration will be taken up immediately after backfilling by proper consolidation
• Conduct air quality monitoring as per the monitoring plan
Surface water
quality
Water pollution /
works in rainy
season,
Mobilization of
settled silt
materials, and
chemical
contamination
from fuels and
lubricants during
installation of
pipelines can
contaminate
nearby surface
water quality.
• No earthwork will be conducted during rainy season
• All earthworks be conducted during the dry season to prevent the problem of soil run-off during monsoon season;
• Avoid stockpiling of earth fill especially during the monsoon season unless covered by tarpaulins or plastic sheets;
• Prioritize re-use of excess spoils and materials in the construction works. If spoils will be disposed, only designated disposal areas shall be used;
• Disposal sites will be selected prior to start of construction following the EMP guidelines
• Dispose any wastes generated by construction activities in designated sites; and
• Install temporary silt traps or sedimentation basins along the drainage leading to the water bodies to control water pollution;
DBO
Contractor
• Areas for stockpiles, storage of fuels and lubricants and waste materials;
• Records of surface water quality inspection;
• Effectiveness of water management measures;
• No visible degradation to nearby drainages, nallahs or water bodies due to civil works
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
132
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
• Place storage areas for fuels and lubricants away from any drainage leading to water bodies;
• Temporary drains or bunds will be created around the periphery of work area to avoid flooding, and entry of runoff
• Accumulated water in work areas / excavated pits will be pumped to a temporary ponds / sedimentation basins; only clarified water will be disposed into drains
• Safety measures will be undertaken to avoid any risk of collapse due to water entry
• Install Bio-Toilets in all worksites especially in Urban Areas and Conduct surface quality inspection according to the Environmental Management Plan (EMP).
Weir & Pick-up
Weir setup
works in
Kathan River
Pollution of
River/dams due
to weir and Pick-
up weir
construction
• Select a construction methodology that is least disturbing, and appropriate for the in-situ soil condition, and able to complete the construction work prior to onset of monsoon
• Schedule the construction works in river bed during summer where there is no flow / low water level period – late winter months to pre monsoon (February – June/July); ensure that works are completed during the same period to prior to onset of monsoon; confirm with dam authorities on release of water; avoid scheduling the works during water release period.
DBO
contractor
• No visible degradation to nearby drainages, nallahs or water bodies due to civil works
• water quality monitoring results
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
133
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
• Do not disturb river bed except the actual work area; no equipment, machinery shall be operated outside the work area
• Erect temporary barriers to form enclosed construction area with least disturbance
• Allow adequate time settle the distributed solids to prior to pumping out water; only clear/clarified water shall be pumped back into the reservoir; any silt laden water should be pumped to a silt pond
• Avoid/minimize use of fuels, chemicals and lubricants; ensure no spillage
• Clean up the area after the completion & prior to the onset of monsoon flow
Noise Levels Increase in
noise level due
to earth-moving
and excavation
equipment, and
the
transportation of
equipment,
materials, and
people
• Noisy works will be avoided in the night
• Plan activities in consultation with PIU so that activities with the greatest potential to generate noise are conducted during periods of the day which will result in least disturbance;
• Horns should not be used unless it is necessary to warn other road users or animals of the vehicle’s approach;
• Drivers will be trained to avoid usage of horns unnecessarily
• Minimize noise from construction equipment by using vehicle
DBO
Contractor
• Complaints from sensitive receptors;
• Use of silencers in noise-producing equipment and sound barriers;
• Equivalent day and night time noise levels
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
134
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
silencers, fitting jackhammers with noise-reducing mufflers, and use portable street barriers to minimize sound impact to surrounding sensitive receptor; and
• Maintain maximum sound levels not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s.
• Before undertaking work with heavy noise/vibration, surrounding area / buildings will be surveyed to identify any old / sensitive buildings at risk, and necessary precautions will be taken to avoid any risk
• Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity;
• Noisy works will not be conducted near sensitive places (hospitals, schools, etc.,) and at sensitive times (festivals etc.,); works will be scheduled accordingly
Landscape and
aesthetics
Impacts due to
excess
excavated earth,
excess
construction
materials, and
solid waste such
as removed
concrete, wood,
packaging
• Prepare and implement a Construction Waste Management Plan
• All the cut and open surfaces shall be properly consolidated and protected with surface pitching /grass turfing etc. as appropriate to avoid any surface erosion
• Excess soil / debris will be utilized in construction / useful purposes to avoid disposal
• Excess soils/debris will be
DBO
Contractor
• Complaints from sensitive receptors;
• Worksite clear of hazardous wastes such as oil/fuel
• Worksite clear of any excess excavated earth, excess construction materials, and solid waste such as removed concrete,
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
135
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
materials, empty
containers,
spoils, oils,
lubricants, and
other similar
items.
removed from site on regular basis to avoid stockpiling at site
• Disposal site will be identified prior to start of work following EMP guidelines
• Stockpiles, lubricants, fuels, and other materials should be located away from steep slopes and water bodies;
• Avoid stockpiling any excess spoils. Excess excavated soils should be dispose to approved designated areas;
• Domestic waste generated at camp sites will be properly segregated in biodegradable and non-biodegradable for collection and disposal to designated solid waste disposal site; biodegradable waste composted in impervious pit at site; recyclable waste will be sold in market
• Residual and hazardous wastes such as oils, fuels, and lubricants will be disposed via licensed agencies by MPPCB
• Burning of construction and domestic waste will not be allowed
• Ensure that wastes are not haphazardly dumped within the project site and adjacent areas.
• Sites will be managed neatly; waste collection bins will be provided, awareness will be created among workers, staff in site cleanliness
• All camp/work sites will be
wood, packaging materials, empty containers
136
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
restored to original condition after the completion of work
• Get approval of PIU in writing that the necessary environmental restoration work has been adequately performed before acceptance of work.
Existing
Infrastructure
and Facilities
Disruption of
service and
damage to
existing
infrastructure at
specified project
location
• Obtain from PIU the list of affected utilities and operators if any;
• Prepare a contingency plan to include actions to be done in case of unintentional interruption of service
DBO
Contractor
• Existing Utilities Contingency Plan
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
Ecological
Resources –
Terrestrial
Loss of
vegetation and
tree cover
• Avoid removal of trees and vegetation along the roads best pipeline alignments and layout planning of reservoirs and facilities, however, if this cannot be avoided fully, undertake compensatory tree plantation (5 trees to 1 tree removed)
• Minimize removal of vegetation and disallow cutting of trees;
• If tree-removal will be required, obtain tree-cutting permit and (iii) Plant 5 native trees for every one that is removed.
DBO
Contractor
• PIU to report in writing the no of trees cut and planted.
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
Land use Environmental
Issues due to
land use change
• The impact due to change in land use will be negligible due to this project.
Not applicable • Not applicable Not applicable
Accessibility Traffic problems
and conflicts
Traffic management / access during pipeline works;
Construction • Traffic route during construction works
Cost for
implementation
137
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
near project
locations and
haul road
• Pipeline work implementation plan will be prepared for each road; works will not be conducted in all roads at once in a locality; alternative roads for traffic movement will be ensured
• A simple traffic management plan will be prepared in consultation with traffic police for each road, and displayed on site; one-week prior notice will be provided
• Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours
• Temporary diversions will be provided as required, with prior public information
• Confine work areas along the roads to the minimum possible extent; all the activities, including material & waste/surplus soil stocking should be confined to this area. Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately removed from site/ or brought to the as and when required
• Work area will be properly defined, barricaded; minimum strip of land will be used
• Material / waste / soil will not be stocked obstructing the traffic, pedestrian etc.,
Contractor including number of permanent signages, barricades and flagmen on worksite (Appendix 9);
• Complaints from sensitive receptors;
• Number of signages placed at project location.
of mitigation
measures
responsibility of
contractor.
138
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
• Trench width will be minimized as much as possible by adopting best construction methods with proper shoring/bracing
• Work site will be kept free from all unnecessary obstructions
• Public information boards, sign boards, caution boards will be provided along with contact numbers
• Notify affected public by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints.
• Prior to start of pipeline work, information will be provide to the public through media – newspapers and local cable television (TV) services
Access to houses/business during pipeline works;
• Access to any house, business or property will not be blocked completely, at least safe pedestrian access will be maintained
• Leave spaces for access between mounds of soil;
• Provide walkways, wooden and metal sheets/planks on excavated trenches where required to maintain access across for people and vehicles;
Material transport using heavy trucks;
139
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
• Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites;
• Material haulage vehicles will main/wide roads as far as possible
• Transportation / hauling activities will be conducted during non-peak hours (6:30 am to 8:00 am)
• Locate entry and exit points in areas where there is low potential for traffic congestion;
• Proper entry and exits facilities will be provided at low traffic places
• Keep the site free from all unnecessary obstructions;
• Drivers will be trained to drive vehicles in a considerate manner and following all traffic rules
For works in very narrow roads;
• Inform the local / affected local population / business, 1-week in advance about the work schedule and access restrictions
• Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum.
• Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access.
Socio-
Economic –
Impede the
access of
• Leave spaces for access between mounds of soil;
DBO • Complaints from sensitive receptors;
Cost for
implementation
140
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
Income. residents and
customers to
nearby shops
• Provide walkways and metal sheets where required to maintain access across for people and vehicles;
• Increase workforce in the areas with predominantly institutions, place of worship, business establishment, hospitals, and schools;
• Consult businesses and institutions regarding operating hours and factoring this in work schedules; and
• Provide sign boards for pedestrians to inform nature and duration of construction works and contact numbers for concerns/complaints.
• Notify community/ water users in advance about likely interruptions in water supply.
• Provide alternate sources of clean water until water supply is restored.
Contractor • Spoils management plan
• Number of walkways, signages, and metal sheets placed at project location.
of mitigation
measures
responsibility of
contractor.
Socio-
Economic –
Employment
Generation of
temporary
employment and
increase in local
revenue
• Employ at least 50% of the labour force, or to the maximum extent, local persons within the 2-km immediate area if manpower is available;
• Comply with labor laws
DBO
Contractor
• Employment records;
• Compliance to labor laws (see Appendix 7 of this IEE)
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
Occupational
Health and
Safety
Occupational
hazards which
can arise during
• Comply with all national, state and local core labor laws (see Appendix 7 of this IEE)
• Following internationally recognized health and safety
DBO
Contractor
• Site-specific OH&S Plan;
• Equipped first-aid stations;
• Medical insurance
Cost for
implementation
of mitigation
measures
141
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
work standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines11 and Sector Specific (Water and Sanitation) Guidelines12).
• Develop and implement site-specific occupational health and safety (OH&S) Plan which will include measures such as: (a) excluding public from the site; (b) ensuring all workers are provided with and use personal protective equipment like helmet, gumboot, safety belt, gloves, nose musk and ear plugs; (c) OH&S Training for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents;
• A detailed guidance for Safety from COVID-19 Pandemic during construction works is provided in Appendix 14 - Guideline for Construction work about safety from COVID-19 Pandemic (SOP – Health & Safety Plan).
• Site will be prepared and maintained to create safe working conditions; workers will be provided with safe work areas, elevated platforms, steps, ladders,
coverage for workers;
• Number of accidents;
• Supplies of potable drinking water;
• Clean eating areas where workers are not exposed to hazardous or noxious substances;
• record of H&S orientation trainings
• personal protective equipment;
• % of moving equipment outfitted with audible back-up alarms;
• permanent sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal.
• Compliance to core labor laws (see Appendix 7 of this
responsibility of
contractor.
11https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 12 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES
142
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
walkways /access to work areas and amenities
• Deep excavations (more than 1 m) will be properly protected to avoid collapse (safety measures such as / shoring / safe slopes)
• Hard barricading will be provided around deep trenches / pits of more than 1.5 m deep
• All necessary precautions will be taken to avoid collapse of trench/pit, and damage to surrounding structures
• Proper personnel protection equipment will be provided to all workers / staff; and its use will be ensured
• Ensure that qualified first-aid can be provided at all times. Equipped first-aid stations shall be easily accessible throughout the site;
• Provide medical insurance coverage for workers;
• All installations will be properly secured from unauthorized intrusion and accident risks; hazardous locations will be properly marked
• All work sites will be properly secured, barricaded to avoid unauthorized public/traffic entry
• Provide road signs and flagman to regulate traffic / pedestrians / road users of on-going trenching activities
• Site safety orientation will be
IEE)
143
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
provided to all visitors to the site
• Drinking water, sanitation, washing and resting facilities will be provided at all sites; separate sanitation facilities for women
• Provide clean eating areas where workers are not exposed to hazardous or noxious substances;
• Provide H&S orientation training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers;
• Provide visitor orientation if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted;
• Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas;
• Proper audible back-up alarms will be ensured for all moving equipment/machinery
• Provide safety sign, caution, information boards on site for workers and staff awareness, follow up
• Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high
144
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and
• Emergency procedures and contact information will be provided on all sites
• Accidents will be promptly registered and reported; register will be maintained at every work site
• Public compliant box and compliant register will be provided at every work site
• Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.
COVID 19
Response
Spread of
infection,
adverse impact
on health of
workers, staff
and community
• In view of the prevailing COVID-19 pandemic, the contractors and workers shall need to take additional measures to avoid the spread of the disease and shall follow various guidelines/guidance notes issued by the national/state governments and international organizations such as WHO, ILO, etc., from time to time.
• Contractor shall prepare a site-specific Health and Safety COVID-19 Pan (HS COVID-19 Plan) in accordance with the government
DBO
Contractor
• PIU Contractor costs
145
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
policy, legislation and regulatory requirements on COVID-19 prevention and control. In the absence thereof, the HS COVID-19 Plan should be updated in accordance with international good practice guidelines issues by agencies like World health organization (WHO), International Labour Organization, etc.,
• The HS COVID-19 Plan must be approved by the PMU prior to commencement of works. Appendix 14 provides a basic COVID-19 health and safety plan.
• The contractor shall submit a fortnightly monitoring and progress report to PIU on implementation of HS COVID-19 Plan.
Asbestos
Cement (AC)
Materials
Health risks
associated with
AC pipes
• Location of existing/old AC pipes will be identified prior to excavation for new pipes
• Underground AC pipes will be left as it is in the ground without disturbing / touching
• Awareness will be created among workers and supervisors on AC pipes
• Workers should be made aware to identify AC pipes.
• Work in such area should be immediately stopped and the excavations backfilled so that it does not expose others to asbestos risk.
• The Contractor Should prepare an Asbestos Management Plan as
DBO
Contractor
• on site observations & records
• Asbestos management Plan
• Reporting of Incidence by DBO Contractor
• Supervision report of Asbestos management in SEMR
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
146
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
illustrated in the flow chart for Asbestos Management
• Application of a detailed H&S procedure by the contractor such that equipment and workers who might have been accidentally exposed to asbestos dust are protected (as per international protocols for exposure to protocol.
• Report the incident to the PIU and PMU
• Additional supervision to be provided by PIU/PMU/PMC to ensure works are done as per protocol
• Report the incidence of asbestos and its management to ADB as part of the SEMR.
Community
Health and
Safety.
Traffic accidents
and vehicle
collision with
pedestrians
during material
and waste
transportation
• Plan routes to avoid times of peak-pedestrian activities.
• Liaise with PIU/ULB in identifying high-risk areas on route cards/maps.
• Maintain regularly the vehicles and use of manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure.
• Provide road signs and flag persons to warn of on-going trenching activities.
DBO
Contractor
• Traffic Management Plan;
• Complaints from sensitive receptors
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
Safety of
sensitive
groups
(children,
Trench
excavation in in
narrow streets
will pose high
• Provide prior information to the local people about the nature and duration of work
• Conduct awareness program on
DBO
Contractor
• Complaints from neighbourhood and monitoring of accidents
Cost for
implementation
of mitigation
measures
147
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
elders etc.)
and others
pedestrians in
narrow streets
risk to children
and elders in the
locality
safety during the construction work
• Undertake the construction work stretch-wise; excavation, pipe laying and trench refilling should be completed on the same day
• Provide barricades, and deploy security personnel to ensure safe movement of people and also to prevent unnecessary entry and to avoid accidental fall into open trenches
responsibility of
contractor.
Work Camps
and worksites
Temporary air
and noise
pollution from
machine
operation, water
pollution from
storage and use
of fuels, oils,
solvents, and
lubricants
Unsanitary and
poor living
conditions for
workers
• Consult with PIU before locating project offices, sheds, and construction plants;
• Minimize removal of vegetation and disallow cutting of trees;
• Provide drinking water, water for other uses, and sanitation facilities for employees;
• Ensure conditions of livability at work camps are maintained at the highest standards possible at all times;
• Prohibit employees from poaching wildlife and cutting of trees for firewood;
• Train employees in the storage and handling of materials which can potentially cause soil contamination;
• Recover used oil and lubricants and reuse or remove from the site;
• Manage solid waste according to the preference hierarchy: reuse, recycling and disposal to designated areas;
DBO
Contractor
• Complaints from sensitive receptors;
• Drinking water and sanitation facilities for employees
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
148
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
• Ensure unauthorized persons specially children are not allowed in any worksite at any given time.
Establishing
construction
camps / labour
camps
Guidelines to be
followed for
establishing
construction
camps / labour
camps
• Camp sites shall be away from residential areas (100 m), sensitive areas (schools, hospitals, etc. 250 m,), water bodies (500 m) and forests (more than 1 km)
• Use unused, vacant lands; no trees shall be cut
• Provide a proper fencing/compound wall
• Prepare a site layout plan & display at the site; uniformly label (name boards) all the places in the facility
• Entire site/facility area shall be provided with hard leveled surface as appropriate; no loose soil, slush, water logging etc.,
• Living quarters and construction camps shall be provided with standard materials; no shacks or huts
• Adequate lighting and ventilation
• Provide drinking water, water for other uses, and sanitation facilities; drinking water should be regularly tested
• Provide clear pathways for safe movement
• Provide cooking fuel (cooking gas); and a separate safe place to cook; fire wood not allowed
• Construct septic tanks and soak pit arrangement for wastewater
DBO
Contractor
• Complaints from sensitive receptors;
• Drinking water and sanitation facilities for employees
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
149
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
disposal
• Solid waste shall be properly manager – provide separate bins, compost biodegradable waste; sell recyclable waste
• Camp sites shall be cleared and restored to original after completion of work, all debris, wreckage cleared
Work site
management
• Provide a proper fencing/compound wall
• Prepare a site layout plan & display at the site; uniformly label (name boards) all the places in the facility
• Entire site/facility area shall be provided with hard leveled surface as appropriate; no loose soil, slush, water logging etc.,
• Provide clear pathways (for workers/staff) and roads (for vehicles) for safe movement in the work site
DBO
Contractor
• Complaints from sensitive receptors;
• Provide a proper fencing/compound wall
• Provide clear pathways (for workers/staff) and roads (for vehicles) for safe movement in the work site
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
Worker
amenities at all
work sites
• A temporary rest area for workers (for resting in break time, protection against rain/sun, eating etc.,)
• Drinking water
• Wash area, toilets (separate for women); mobile toilets for linear work
• Septic tank and soak pits for waste disposal
• First aid
DBO
Contractor
• Drinking water and sanitation facilities for employees
• First aid
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
Social and
Cultural
Risk of
archaeological
• Excavation work shall be supervised by a person with
DBO • mobilization of archaeologist
Cost for
implementation
150
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
Resources chance finds archaeological training
• If any chance find is suspected during excavation/works, work will be immediately stopped, and report to PIU/PMU and PMC
• Stop work immediately to allow further investigation if any finds are suspected;
• Necessary action as suggested by concerned authorities will be undertaken
• Ensure that construction activities follows all precaution mentioned in the Plan are followed
Contractor • Records of chance finds
of mitigation
measures
responsibility of
contractor.
Submission of
EMP
implementation
report
Unsatisfactory
compliance to
EMP
• Appointment of (I) EHS Supervisor and Archeological supervisor to ensure EMP implementation
• Timely submission of monitoring reports including pictures
DBO
contractor
• Availability and competency of appointed supervisor
• Monthly report
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
Post-
construction
clean-up
Damage due to
debris, spoils,
excess
construction
materials
• All spoils wreckage, rubbish, or temporary structures (such as buildings, shelters, and latrines) which are no longer required will be removed; and
• All excavated roads shall be reinstated to original condition.
• All disrupted utilities will be restored
• All affected structures rehabilitated / compensated
• The area that previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these
DBO
Contractor
• PIU/PDMC report in writing that (i) worksite is restored to original conditions; (ii) camp has been vacated and restored to pre-project conditions; (iii) all construction related structures not relevant to O&M are removed; and (iv) worksite clean-up is satisfactory.
Cost for
implementation
of mitigation
measures
responsibility of
contractor.
151
Field Anticipated Impact
Mitigation Measures Responsible for Mitigation
Monitoring of Mitigation
Cost and Source of Funds
will be cleaned up.
• All hardened surfaces within the construction camp area will be ripped, all imported materials removed, and the area will be top soiled and regrassed using the guidelines set out in the revegetation specification that forms part of this document.
• The contractor must arrange the cancellation of all temporary services
• Restoration to original will be documented and reported to PIU
• Request PIU to report in writing that worksites and camps have been vacated and restored to pre-project conditions before acceptance of work.
Table 22: Operation Stage Environmental Management Plan
Field Anticipated Impact Mitigation Measures Responsible for
Mitigation
Monitoring of
Mitigation
Cost and
Source of
Funds
Check for
blockage and
leakage problems
reducing the
water losses
Loss of water,
increased demand
and inconvenience to
consumers & general
public
• Effective leak detection and water auditing to reduce the water losses
DBO Contractor PIU and Bada
Malhera Nagar
Parishad
Operating
costs
152
Field Anticipated Impact Mitigation Measures Responsible for
Mitigation
Monitoring of
Mitigation
Cost and
Source of
Funds
Water
contamination –
raw water
contamination at
source and
treated water
during
transmission
Impacts on public
health
• Ensure protection of water source quality, any entry of wastewater into the river upstream of stop dam sites should be prevented.
• Contamination of treated water during transmission and distribution should be prevented by quickly identifying, isolating and repairing the leak section. Develop a system of leak detection and rectification.
• Conduct regular monitoring of raw & treated water and ensure that water supplied at all times meets the drinking water standards (Appendix 8)
Bada Malhera
Nagar Parishad
DBO Contractor
PMU in
coordination with
WRD
PIU and Bada
Malhera Nagar
Parishad
Operating
costs
Discharge the
impurities and
other solids
collected due to
filtration and back
wash
Pollution of streams
/drains
• Backwash water will be recirculating so no wastewater generated from WTPs
• Maintain the mechanical parts as per the maintenance plan to avoid any hazards
DBO Contractor PIU and Bada
Malhera Nagar
Parishad
Operating
costs
Sludge
generation
Land and water
pollution, impacts on
health & environment
• Collect the sludge from WTP units, dry in sludge drying beds, and reuse / dispose safely as per the design
DBO Contractor PIU and Bada
Malhera Nagar
Parishad
Operating
costs
Increased in
sewage
generation
Water pollution, and
impacts on public
health and
environment
• Sanitation facilities needs to be improved at community level and at the town level to meet the increased sewage demand
Bada Malhera
Nagar Parishad
PMU To be
identified -
respective
NPs
Generation of
waste materials
Impacts on public
health and
environment
• Collect solid wastes and dispose to approved disposal yards
DBO Contractor PIU and Bada
Malhera Nagar
Parishad
Operating
costs
153
Field Anticipated Impact Mitigation Measures Responsible for
Mitigation
Monitoring of
Mitigation
Cost and
Source of
Funds
Occupational
health and safety
Health, social and
economic impacts on
the workers
• Provide appropriate PPE to workers & training on its proper use
• Use fall protection equipment when working at heights.
• Maintain work areas to minimize slipping and tripping hazards.
• Implement a training program for operators who work with chlorine regarding safe handling practices and emergency response procedures.
• Prepare escape plans from areas where there might be a chlorine emission.
• Install safety showers and eye wash stations near the chlorine equipment and other areas where hazardous chemicals are stored or used.
• Prohibit eating, smoking, and drinking except in designated areas.
• Comply with all national, state and local core labor laws (see Appendix 7 of this IEE)
• Following internationally recognized health and safety standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines13 and Sector Specific (Water and Sanitation) Guidelines14).
• Develop and Implement site-specific occupational health and safety (OH&S) plan which will include measures, such as the following
DBO Contractor PIU and Bada
Malhera Nagar
Parishad
Operating
costs
13https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 14 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES
154
Field Anticipated Impact Mitigation Measures Responsible for
Mitigation
Monitoring of
Mitigation
Cost and
Source of
Funds
• A detailed guidance for Safety from COVID-19 Pandemic during construction works is provided in Appendix 14 - Guideline for Construction work about safety from COVID-19 Pandemic (SOP – Health & Safety Plan).
• Excluding public from the site;
Table 23: Pre-Construction and Construction Stage Environmental Monitoring Plan
Monitoring field Monitoring location Monitoring parameters Frequency Responsibility Cost & Source of
Funds
Construction
disturbances,
nuisances, public &
worker safety,
All work sites Implementation of dust
control, noise control,
traffic management, &
safety measures.
Site inspection checklist to
review implementation is
appended at Appendix
16
Regularly as required
during construction;
checklist to be filled
monthly once
Supervising
staff and
safeguards
specialists
Part of TOR of PIU,
PMC and PMU
Ambient air quality 03 locations
(at weir/pick-up weir
site, at OHT & WTP
sites and at
distribution work
sites for Bada
Malhera town WSS)
• PM10, PM2.5 NO2, SO2, CO
Once before start of
construction
Quarterly (yearly 4-times)
during construction (2
year period considered)
DBO Contractor Cost for
implementation of
monitoring measures
responsibility of
contractor
(27 samples x 5000
per sample = 135,000)
Ambient noise 03 locations • Day time and night time noise levels (24 hours)
Once before start of DBO Contractor Cost for
155
(at weir site, at OHT
/ WTP sites and at
distribution work
sites for Bada
Malhera town WSS)
construction
Quarterly (yearly 4-times)
during construction (2
year period considered)
implementation of
monitoring measures
responsibility of
contractor
(27 samples x 1500
per sample = 40,500)
Surface water
quality
02 locations
(upstream & down
Stream of Weir
works in Kathan
river)
• pH, Oil & grease, Cl, F, NO3, TC, FC, Hardness, Turbidity BOD, COD, DO, Total Alkalnity
Once before start of
construction & monthly
during construction (12
months period
considered) in river
DBO Contractor Cost for
implementation of
monitoring measures
responsibility of
contractor
(26 samples x 4000
per sample =
1,08,000)
Table 24: Operation Stage Environmental Monitoring Plan
Monitoring field Monitoring
location
Monitoring parameters Frequency Responsibility Cost & Source
of Funds
Source water quality Near intake point in
River Kathan
pH, Cl, F, NO3, TC, FC, Hardness, Turbidity
BOD, COD, DO, Total Alkalnity
heavy metals & pesticides
Yearly twice
(pre & post
monsoon)
DBO
Contractor
O&M costs
Monitoring of quality
of water supplied to
consumers
Consumer end-
random sampling in
all zones
pH, Nitrite, Nitrate, Turbidity BOD, Total
Alkalnity, Total coliform and Feacal coliform
Monthly
once
DBO
Contractor
O&M costs
Sludge quality and WTP Analysis for concentration of heavy metals
and confirm that value are within the following
Yearly once DBO O&M costs
156
Monitoring field Monitoring
location
Monitoring parameters Frequency Responsibility Cost & Source
of Funds
suitability as manure limits (all units are in mg/kg dry, except pH)
• Arsenic - 10.00,
• Cadmium - 5.00
• Chromium - 50.00
• Copper - 300.00
• Lead - 100.00
• Mercury - 0.15
• Nickel - 50.00
• Zinc - 1000.00
• PH - 5.5-8.5
Contractor
Sludge Disposal
Management
WTP As per Fertilizer Control Order 2006 so that it
can be used as Soil Conditioner
Yearly once ULB Operating costs of Bada Malhera Nagar Parishad
157
B. Implementation Arrangements
189. Urban Development and Environment Department (UDED) of Government of Madhya Pradesh will be the Executing Agency for the Program, responsible for management, coordination and execution of all activities funded under the loan. Implementing Agency will be the recently established Madhya Pradesh Urban Development Company (MPUDC), a wholly owned subsidiary of GoMP. A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs) with a flexibility to redeployment depending upon the implementation requirements. 190. The PMU and PIUs will be supported by several teams of Design Consultants in preparation of preliminary engineering designs. 191. Water Resource Review Committee (WRRC) is constituted to undertake a thorough review of the source when recommended by the Design Consultant in regard to techno-economic feasibility and sustainability especially ensuring climate change resilience, and Technical Review Committee (TRC) to review and approve the preliminary designs developed by the Design Consultants. 174. Program Management Consultant (PMC) centrally located in PMU and with field teams located in PIUs shall be responsible for implementation of the Program. All infrastructure contracts will be procured through performance-based contracts (PBCs) and include build-operate (BO) framework. Based on the preliminary designs prepared by Design Consultants, the DBO (design-build-operate) Contractor will design, construct, commission and operate for 10 years, after which it will be transferred to the respective ULB. 175. Two Committees - an Empowered Committee cum Executive Committee and a Technical Clearance and Tender Committee have been constituted by the Government to be responsible for effective and timely implementation of the Program. 176. Safeguards. At PMU, there will be two safeguard specialists: (i) Project Officer (Environment) and (ii) Social & Gender Offer, who will responsible for compliance with the environmental and social safeguards in program implementation. PO (Environment) will have overall responsibility in implementation of the investment program as per the Environmental Assessment & Review Framework (EARF) agreed between ADB and the government. At individual subproject level, PO will ensure that environmental assessment is conducted, and a project-specific is prepared and implemented, and the compliance, and corrective actions, if any are reported as required.
C. EMP Compliance Responsibilities
177. PMU Responsibilities. PO (Environment) will be supported by PMC, which will be staffed with an Environmental Specialist, and Environmental Coordinators. Key tasks and responsibilities of the PO (Environment) for this sub project include the following: Bidding stage:
(i) Prior to invitation of bids for civil works contract, ensure that
158
a. Water Resources Department (WRD) permission is obtained for sourcing water Kathan river and to construct weir and pick-up weir
b. Consent for establishment (CFE) is obtained from MPPCB for WTP construction
(ii) Ensure that EMP is included in bidding documents and civil works contracts (iii) Ensure that the bid/contract documents include specific provisions requiring
contractors to comply with all applicable labour laws and core labour standards including: a. Labour welfare measures and provision of amenities b. prohibition of child labour as defined in national legislation for construction
and maintenance activities; c. equal pay for equal work of equal value regardless of gender, ethnicity, or
caste; d. elimination of forced labour; e. The requirement to disseminate information on sexually transmitted
diseases, including HIV/AIDS, to employees and local communities surrounding the project sites.
(iv) Ensure that staff required for implementation of EMP (EHS officer) is included in the bid requirements
(v) Ensure that EMP cost is included in the project cost (vi) In the pre-bid meeting, provide insight into the EARF requirements, IEE update,
EMP measures, and overall compliance requirements to the bidders
Construction stage:
(i) Facilitate and ensure that all necessary environmental clearances/permissions, including that of contractor’s are in place prior to start of construction
(ii) Organize an induction course for the training of contractors, preparing them on EMP implementation, environmental monitoring, and on taking immediate action to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation.
(iii) provide oversight on environmental management aspects of subprojects and ensure EMPs are implemented by PIU and contractors
(iv) Supervise and provide guidance to the PIUs to properly carry out the environmental monitoring as per the EMP
(v) Oversee grievance redress mechanism to address any grievances brought about in a timely manner; ensure that records are properly maintained
(vi) Consolidate monthly environmental monitoring reports from PIU and submit semi-annual monitoring reports to ADB
(vii) Oversee site closures to ensure that all work / facility sites are restored properly prior to issuing work completion certificate to the contractor
Operation stage:
(i) Ensure and consent for operation (CFO) is obtained from MPPCB for WTP prior to start of operation.
178. PIU Responsibilities. PIU will be headed by a Project Manager and supported by PMC. An Assistant Project Manager of PIU will be given additional responsibilities of safeguard tasks and will be designated as Assistant Environmental Officer (ASO). ASO will be supported by
159
PDMC Environmental Specialist and Environmental Engineer. Key tasks and responsibilities of the ASO for this subproject include the following:
(i) Provide necessary support to PIU and Nagar Parishad in obtaining permission from WRD and MPPCB; liaison with PMU and regulatory agencies
(ii) Oversee day-to-day implementation of EMPs by contractors, including compliance with all government rules and regulations, take necessary action for obtaining rights of way
(iii) Oversee environmental monitoring by contractors (iv) Take corrective actions when necessary to ensure no environmental impacts (v) Submit monthly environmental monitoring reports to PMU (vi) Conduct continuous public consultation and awareness (vii) Address any grievances brought about through the grievance redress
mechanism in a timely manner as per the EMP 179. Contractor’s responsibilities. Bidding stage:
(i) Understand the EMP requirements and allocate necessary resources (budget, staff, etc.,)
(ii) Understand the regulatory compliance requirements related to labour welfare, safety, environment etc.,
Design stage:
(i) Review the IEE Report including the REA checklist, category and the EMP, and conduct site visits to understand the environmental sensitivity of the project sites.
(ii) Update the REA checklist, confirm the category, and update/revise the IEE Report of the project reflecting the changes /amendments /additions that are effected in the project during the detailed design
(iii) Update / revise and finalize the EMP (iv) Provide all necessary technical assistance to PIU / ULB in obtaining regulatory
clearances/approvals. (v) Ensure that all design-related measures of the EMP, and conditions, if any, of
government regulatory agencies (like MPPCB consent conditions) are duly included in the final designs.
Construction stage:
(i) Ensure that all regulatory clearances (both project related and contractor related) are in place before start of the construction work.
(ii) Mobilize EHS supervisor prior to start of work (iii) Confirm with PIU availability of rights of way at all project sites prior to start of
work. (iv) Prepare and submit:
a. Construction waste management (CWM) plan b. Traffic management (TM) plan
(v) Implement the mitigation measures as per the EMP including CWM & TM Plans (vi) Follow the EMP measures/guidelines for establishment of temporary construction
camps, construction waste disposal sites, and material borrow areas, etc.,
160
(vii) Implement EMP and ensure compliance with all the mitigation and enhancement measures
(viii) Conduct environmental monitoring (air, noise, water etc.,) as per the EMP (ix) Undertake immediate action as suggested by PIU / PMU / PMC to remedy
unexpected adverse impacts or ineffective mitigation measures found during the course of implementation
(x) Submit monthly compliance reports on EMP implementation (xi) Act promptly on public complaints and grievances related to construction work
and redress in a timely manner in coordination with PIU (xii) Comply with applicable government rules and regulations
Operation stage:
(i) Obtain CFO from MPPCB in coordination with the ULB, and comply with MPPCB conditions, if any, during the operation phase
(ii) Implement the operation phase EMP including the monitoring plan (iii) Submit quarterly EMP implementation report
D. Training Needs
180. The following Table 25 presents the outline of capacity building program to ensure EMP implementation. The detailed and specific modules will be customized for the available skill set after assessing the capabilities of the target participants and the requirements of the project by the ES of PMC.
Table 25: Outline Capacity Building Program on EMP Implementation Description Target Participants &
Venue Cost and Source of Funds
1. Introduction and Sensitization to Environmental Issues (1 day) - ADB Safeguards Policy Statement - Government of India and Madhya Pradesh applicable safeguard laws, regulations and policies including but not limited to core labor standards, OH&S, etc. - Incorporation of EMP into the project design and contracts - Monitoring, reporting and corrective action planning
All staff and consultants involved in the project At PMU, Bhopal (combined program for all subprojects)
Included in the overall program cost
2. EMP implementation (1/2 day) - EMP mitigation & monitoring measures -Roles and responsibilities - Public relations, - Consultations - Grievance redress - Monitoring and corrective action planning - Reporting and disclosure - Construction site standard operating procedures (SOP) - AC pipe protocol - Traffic management plan - Waste management plan - Site clean-up & restoration
All PIU staff, contractor staff and consultants involved in the Bada Malhera subproject At PIU
Part of overall program costs – PMC will conduct at PIU office Part of scope of work of PMU, PIU, PMC & DBOC
161
Description Target Participants & Venue
Cost and Source of Funds
3. Contractors Orientation to Workers (1/2 day) - Environment, health and safety in project construction
Once before start of work, and thereafter regular briefing every month once. Daily briefing on safety prior to start of work All workers (including unskilled laborers)
Contractors cost
E. Monitoring and Reporting
181. During the detailed design stage, DBO Contractor should confirm PMU the mobilization of Environmental Expert for IEE update and integrating design stage EMP into designs. 182. Prior to commencement of the works, the contractor will submit a compliance report to PIU that all identified pre-construction mitigation measures as detailed in the EMP are undertaken. Contractor should confirm EHS supervisor is mobilized and EHS coordinators are designated for each town for effective implementation of the EMU. PMU with the assistance of the PMC will review the report and permit commencement of works. 183. During construction, results from internal monitoring by the contractor will be reflected in their monthly EMP implementation reports to the PIU. PMU will review and advise contractors for corrective actions if necessary. Quarterly report summarizing compliance and corrective measures taken will be prepared by PMC field team at PIU and submitted to PMU (Appendix 17). During operation, the contractor will conduct management and monitoring actions as per the operation stage EMP, and submit to PMU and ULB a quarterly report on EMP implementation and compliance. 184. Based on monthly & quarterly reports and measurements, PMU will submit to ADB, semi-annual (6-monthly) Environmental Monitoring Reports (EMR). Once concurrence from the ADB is received the report will be disclosed on the MPUDC and PMU websites. 185. ADB will review project performance against the MPUSIP commitments as agreed in the legal documents. The extent of ADB’s monitoring and supervision activities will be commensurate with the project’s risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system F. EMP Implementation Cost
186. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. The costs which are specific to EMP implementation and are not covered elsewhere in the projects are given below. The total costs are estimated at INR 2.35 million, which are to be covered by contractor costs.
Table 26: Cost Estimates to Implement the EMP Particulars Stages Unit Total
Number
Rate (INR)
Cost (INR)
Costs Covered By
A. Implementation staff
162
Particulars Stages Unit Total Number
Rate (INR)
Cost (INR)
Costs Covered By
1 EHS Supervisor Construction per month
24 50,000 1,200,000 DBO contract
Subtotal (A) 1,200,000
B. Mitigation Measures
1 Consent for establishments & consent for operation from MPPCB
Pre-construction
Lump sum
100,000 Project costs
2 Provision for tree cutting & compensatory plantation measures
Construction Per tree 100 1,000 100,000 DBO contract
3 Traffic management at work sites (Pavement Markings, Channelizing Devices, Arrow Panels and Warning Lights)
Construction Lump sum
- - 100,000 DBO contract
Subtotal (B) 300,000
C. Monitoring Measures
1 Air quality monitoring Construction / sample 27 5,000 135,000 DBOC
2 Noise levels monitoring Construction / sample 27 1,500 40,500 DBOC
3 Surface water monitoring
Construction / sample 26 4,000 104,000 DBOC
4 Water and sludge Operation LS / yr - - 100,000 DBO
Subtotal (C) 379,500
D Capacity Building
1 Training on EMP implementation
Pre-construction
Lump Sum
100,000
2 Preparation of plans and protocols (traffic management plan, waste (spoils) management plan etc., chance find protocol
Pre-construction
Lump Sum
50,000
3 Contractors Orientation to Workers on EMP implementation
Prior to dispatch to worksite
Lump Sum
25,000
Subtotal (D) 1,75,000
Total (A+B+C+D) INR 2,054,500
163
IX. CONCLUSIONS AND RECOMMENDATIONS
187. The process described in this document has assessed the environmental impacts of all elements of the Bada Malhera water supply improvement subproject. All potential impacts were identified in relation to pre-construction, construction, and operation phases. Planning principles and design considerations have been reviewed and incorporated into the site planning and design process wherever possible; thus, environmental impacts as being due to the project design or location were not significant. 188. Project area mostly comprises urban areas, agricultural areas of Bada Malhera, which are converted to human use many years back. Existing WTP, CWRM, and proposed/existing OHT components are located within the urban area of Bada Malhera Nagar Parishad. Proposed weir, pick-up weir, existing intake (which was built on the bank of River Kathan exclusively for Bada Malhera town water supply), and existing raw water rising main alignment is located outside the town, and surrounded by agricultural areas. There are no forest areas within the town or in the project area. There are no protected areas like national parks, wildlife sanctuaries or archeologically important monuments or historical or heritage places in and near the project area and none of the project components are located in the forest areas. 189. The proposed water supply scheme of Bada Malhera town include design of new surface source based system with nearest surface water body i.e. River Kathan, which flows at about 3.6 km away from the town. The proposed water supply scheme includes construction of a Weir and a pick-up Weir across Kathan River near Garkhuwan village for storage of water to meet the demand of no flow / non-rainy period. Kathan river is not a perennial river. No flow data is available as there is no gauging station on the river. As per information gathered from the locally, river flows for about 4-5 months, from late June / early July to October and mid of November. Flow is normally very high during the peak monsoon months of July and August, and high to medium in the months of September and October. From November onwards, flow reduces significantly, and becomes very low from mid-November, and completely gets dry from the end of January to the onset of next monsoon in late June / July. ver without any storage structures will be able to provide water supply for about 4 months. Hence a weir is required to create water storage for remaining 8 months of the year, so that Ultimate demand of the town can be fulfilled. 190. Considering the height of banks, it is assessed that to confine the water storage to the river course, a weir of maximum height 6 m can be constructed. River banks at this site is 8-10 m above bed level. On the basis of area basin survey, it is estimated that proposed weir of 6 m will have capacity of 0.835 MCM, which is less than annual requirement of 0.92 MCM. Therefore it is proposed to construct an additional weir of 2 m high with capacity of 0.113 MCM. Together, the storage from both the weirs will be sufficient to meet the demand. It is proposed to utilize the existing river intake, which is at the upstream of proposed 2 m high weir site. The downstream weir (2m high) will act as a pick up weir, from where the water will be abstracted via intake, while the upstream weir (6 m high) will act as storage weir. Pick up weir will be filled from storage weir as and when required. 191. The total water demand for Bada Malhera town is estimated to be 2.52 MLD. Considering evaporation losses from the storage, the estimated water requirement of 8 months low / no-flow season is 0.915 MCM. In the absence of flow records, catchment yield is estimated as 145.68 MCM based on the area (1,214 sq. km) and the rainfall. The requirement of the town is just about 0.63% of the total yield and therefore the source is sustainable, and also unlikely to have any notable impacts on the river flow regime. Also, the increase in overall storage
164
volume across the river due construction new weir is will also not be significant. Although there are total 19 weirs/check dams/dams across the river, except Bila Dam, all are very small, and storage capacity is just around 0.5 MCM. Bila Dam is situated 60 km upstream of proposed weir site, and the capacity of Bila Dam is 56.37 MCM. In terms of water availability, the cumulative storage on the river is about 45% of total catchment yield. Creation of new storage for Bada Malhar with just 0.92 MCM of water is unlikely to alter the existing situation considerably. Water storage will be confined to river course, so therefore no impacts related to water impoundment or submergence. Given intermittent nature of river, there are no notable sensitive environmental features. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local common species and aquatic plants.. Low level sluice gates will be opened prior to onset of heavy monsoon flows; this arrangement avoids silt accumulation and also prevents obstruction of heavy monsoon flows. 192. River water quality is suitable for drinking water after conventional treatment and disinfection, and there are no notable pollution sources. Convention water treatment and disinfection which is proposed in the project is adequate to make the water usable for drinking purpose. Permission of water resources department(WRD) is a prerequisite for this project, and this will be obtained from WRD, GoMP, prior to start of works. WRD permission for abstraction from the river is in process. PMU has already discussed with the WRD, and the permission is likely to be issued soon. 193. It is proposed to utilize the existing intake, raw water main and WTP with necessary rehabilitation and repair works WTP do not have proper wastewater and sludge management system, and chlorine safety facilities. Therefore these are included in the proposed subproject proposals to ensure compliance with the ADB SPS. Existing WTP also does not have the mandatory consent from the Madhya Pradesh Pollution Control Board (MPPCB), which needs to be obtained from the MPPCB for rehabilitation and further operation. 194. During the construction phase, impacts mainly arise from the construction dust and noise, the need to dispose of large quantities of waste soil and import of construction material, and from the disturbance of residents, businesses, traffic and important buildings by the construction work. The social impacts (access disruptions) due to construction activities are unavoidable, as the residential and commercial establishments exist along the roads where pipes will be laid. As some of the works are conducted in river, there is a risk of water contamination, river bed damage, etc. Appropriate measures are suggested. 195. Anticipated impacts of water supply during operation and maintenance will be related to detection and repair of leaks, pipe bursts. These are, however, likely to be minimal, as proper design and selection of good quality pipe material shall mean that leaks are minimal. Leak repair work will be similar to the pipe-laying work. Since the new network would not have any AC pipes there are no risk of exposure to asbestos during the Operation and Maintenance. Appropriate measures to deal with backwash water and sludge from WTP is included in the project design. Application and handling of chlorine gas will involve certain risks, and appropriate measures are suggested for safe application. The DBO Contractor will implement the operation stage EMP during contract period. 196. The public participation processes undertaken during project design ensured stakeholders are engaged during the preparation of the IEE. The planned information disclosure measures and process for carrying out consultation with affected people will facilitate their participation during project implementation.
165
197. The project’s grievance redress mechanism will provide the citizens with a platform to redress of their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance. 198. The EMP will assist the PMU, PIU, PMC and DBO contractor in mitigating the environmental impacts, and guide them in the environmentally sound execution of the proposed project. 199. A copy of the EMP/approved SEP shall be kept on-site during the construction period at all times. The EMP shall be made binding on all contractors operating on the site, and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance. 200. The project will benefit the general public by contributing to the long-term improvement of water supply systems and community liveability in Bada Malhera. 201. Therefore, as per ADB SPS, the project is classified as environmental category B and does not require further environmental impact assessment. However, to conform to government guidelines, the project requires (i) permission of WRD, GoMP for water abstraction from Kathan river and construction of a weir and a pick-up weir- it under process and (iii) Consent to establish and operate for existing WTP from MPPCB. These permissions/approvals shall be obtained prior to start of civil works. 202. This IEE shall be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.
166
Appendix 1: ADB Rapid Environmental Assessment (REA) Checklist
Country/Project: India/Madhya Pradesh Urban Services Improvement project- Bada Malhera- Water Supply project Sector/Division: Urban Development & Environment Department/MPUDC
SCREEINING QUESTION YES NO REMARKS
A. Project Siting Is the project area
• Densely populated? √ Subproject activities extend to the entire town including the densely populated areas. There are no major negative impacts envisaged, because pipeline will be located in unused government lands alongside the existing roads and can be constructed without causing disturbance to, houses, and commercial establishments. In narrow streets, disruption to road users is likely, and measure like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. As per census 2011, density of Bada Malhera is found 879 Person / Sq.km, that is considered average. Only during construction phase, population would be affected adversely due to excavation, construction. But the impact would be very low. During operation, local of town would be more beneficiary
• Heavy with development activities?
√ No
• Adjacent to or within any environmentally sensitive areas?
√ No
• Cultural heritage site √ No
• Protected Area √ No
• Wetland √ No
• Mangrove √ No
• Estuarine √ No
• Buffer zone of protected area √ No
• Special area for protecting biodiversity
√ No
167
• Bay √ No
B. Potential Environmental Impacts Will the Project cause…
• Pollution of raw water supply from upstream wastewater discharge from communities, industries, agriculture, and soil erosion runoff?
√ There are no significant water pollution sources in the catchment. Raw water quality is tested and found that it is suitable for domestic use
• Impairment of historical/cultural monuments/areas and loss/damage to these sites?
√ Not applicable
• Hazard of land subsidence caused by excessive ground water pumping?
√ Not applicable; subproject does not involve groundwater abstraction
• Social conflicts arising from displacement of communities?
√ Project does not involve land acquisition /displacement. No social conflicts envisaged
• Conflicts in abstraction of raw water for water supply with other beneficial water uses for surface and ground waters?
√ No; the water will be abstracted only with due permission of government and allocation of water from Kathan River for water supply of Bada Malhera. Drinking water is priority as per the MP water policy.
• Unsatisfactory raw water supply (e.g. excessive pathogens or mineral constituents)?
√ Raw water quality is tested and found that it is suitable for domestic use. Bacteriological contamination is noticed, and water will be subjected for treatment prior to supply
• Delivery of unsafe water to distribution system?
√ Water will be treated and disinfected prior to supply
• Inadequate protection of intake works or wells, leading to pollution of water supply?
√ Not applicable
• Over pumping of ground water, leading to salinization and ground subsidence?
√ No
• Excessive algal growth in storage reservoir?
√ Regular cleaning of storage tanks will be conducted during operation
• Increase in production of sewage beyond capabilities of community facilities?
√ As per CPHEEO manual the rate of water supply is 70 lpcd for the town where sewerage scheme is not anticipated
• Inadequate disposal of sludge from water treatment plants?
√ Not applicable
• Inadequate buffer zone around √ No
168
pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?
• Impairments associated with transmission lines and access roads?
√ No
• Health hazards arising from inadequate design of facilities for receiving, storing, and handling of chlorine and other hazardous chemicals.
√ Measures for safe handling of chlorine are included
• Health and safety hazards to workers from the management of chlorine used for disinfection and other contaminants?
√ Measures for safe handling of chlorine are included
• Dislocation or involuntary resettlement of people
√ There is no resettlement of people for project implementation.
• Social conflicts between construction workers from other areas and community workers?
√ The contractor will be utilizing the local labour force as far as possible; in case if it is unavoidable, labour camps and facilities will be provided appropriately. No conflicts envisaged
• Noise and dust from construction activities?
√ All the construction machineries employed will comply with noise emission standards of Central Pollution Control Board. Dust suppression measures such as water sprinkling will be employed
• Increased road traffic due to interference of construction activities?
√ Excavation and laying pipelines along public roads will interfere with the traffic. Construction material transport will increase traffic within city. Proper traffic management and construction planning will be ensured to minimize the interference
• Continuing soil erosion/silt runoff from construction operations?
√ Construction work during monsoon shall be carried out with due care so that silt run off due to construction operation is prevented. No construction will be allowed during rains.
• Delivery of unsafe water due to poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine
√ No; appropriate O&M will conducted
169
residuals in distribution systems?
• Delivery of water to distribution system, which is corrosive due to inadequate attention to feeding of corrective chemicals?
√ Not envisaged
• Accidental leakage of chlorine gas?
√ Measures for safe handling of chlorine are included
• Excessive abstraction of water affecting downstream water users?
√ Water abstraction will be limited to the allocated quantity for Bada Malhera
• Competing uses of water?
√ Water abstraction will be limited to the allocated quantity for Bada Malhera
• Increased sewage flow due to increased water supply
√ As per CPHEEO manual the rate of water supply is 70 lpcd for the town where sewerage scheme is not anticipated
• Increased volume of sullage (wastewater from cooking and washing) and sludge from wastewater treatment plant
√ As per CPHEEO manual the rate of water supply is 70 lpcd for the town where sewerage scheme is not anticipated
• Large population influx during project construction and operation that causes increased burden on social infrastructure and services (such as water supply and sanitation systems)?
√ Minimum influx of population during the construction and operation period.
• Risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel, and other chemicals during operation and construction?
√ No such materials are used in project so no risk to community health & safety
• Community safety risks due to both accidental and natural hazards, especially where the structural elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning?
√ Proper safety measures would be ensured during the construction & operation and decommissioning.
Climate Change and Disaster Risk Questions The following questions are not for environmental categorization. They are included in this checklist to help identify
Yes
No
Remarks
170
potential climate and disaster risks. Is the Project area subject to hazards such as earthquakes, floods, landslides, tropical cyclone winds, storm surges, tsunami or volcanic eruptions and climate changes?
√
Semi-arid zone, unreliable rainfall, less vegetation cover. Promote more efficient use of water by reducing losses and wastage to counter increased demands due to higher temperatures.
Could changes in temperature, precipitation, or extreme events patterns over the Project lifespan affect technical or financial sustainability (e.g., changes in rainfall patterns disrupt reliability of water supply; sea level rise creates salinity intrusion into proposed water supply source)?
√
Reduction in rainfall may affect the water availability from dam. Given the priority for drinking water supply, dead storage will be utilized in case of low rain fall years .
Are there any demographic or socio-economic aspects of the Project area that are already vulnerable (e.g.,high incidence of marginalized populations, rural-urban migrants, illegal settlements, ethnic minorities, women or children)?
√
No
Could the Project potentially increase the climate or disaster vulnerability of the surrounding area (e.g., by using water from a vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?
√
No
171
Appendix 2: National Ambient Air Quality Standards
172
Appendix 3: Vehicle Exhaust Emission Norms
173
Appendix 4: National Ambient Air Quality Standards In Respect Of Noise
174
Appendix 5: Comparison Between Indian Environmental Standards and IFC Standards A. Ambient Air Quality Standards
Parameter Location a
India Ambient
Air Quality
Standard
(µg/m3) b
WHO Air Quality
Guidelines (µg/m3) Applicable
Per ADB SPSe
(µg/m3)
Global
Update c
2005
Second
Edition
2000
PM10
Industrial
Residential, Rural
and Other Areas
60 (Annual)
100 (24-hr)
20
(Annual)
50 (24-hr)
- 20 (Annual)
50 (24-hr)
Sensitive Area 60 (Annual)
100 (24-hr)
20
(Annual)
50 (24-hr)
- 20 (Annual)
50 (24-hr)
PM25
Industrial
Residential, Rural
and Other Areas
40 (Annual)
60 (24-hr)
10
(Annual)
25 (24-hr)
- 10 (Annual)
25 (24-hr)
Sensitive Area 40 (Annual)
60 (24-hr)
10
(Annual)
25 (24-hr)
- 10 (Annual)
25 (24-hr)
SO2
Industrial
Residential, Rural
and Other Areas
50 (Annual)
80 (24-hr)
20 (24-hr)
500 (10-
min)
-
50 (Annual)
20 (24-hr)
500 (10-min)
Sensitive Area 20 (Annual)
80 (24-hr)
20 (24-hr)
500 (10-
min)
-
20 (Annual)
20 (24-hr)
500 (10-min)
NO2
Industrial
Residential, Rural
and Other Areas
40 (Annual)
80 (24-hr)
40
(Annual)
200 (1-hr)
-
40 (Annual)
80 (24-hr)
200 (1-hr)
Sensitive Area 30 (Annual)
80 (24-hr)
40
(Annual) -
30 (Annual)
80 (24-hr)
175
Parameter Location a
India Ambient
Air Quality
Standard
(µg/m3) b
WHO Air Quality
Guidelines (µg/m3) Applicable
Per ADB SPSe
(µg/m3)
Global
Update c
2005
Second
Edition
2000
200 (1-hr) 200 (1-hr)
CO
Industrial
Residential, Rural
and Other Areas
2,000 (8-hr)
4,000 (1-hr) -
10,000 (8-
hr) 100,000
(15-min)
2,000 (8-hr)
4,000 (1-hr)
100,000 (15-
min)
Sensitive Area 2,000 (8-hr)
4,000 (1-hr) -
10,000 (8-
hr)
100,000
(15-min)
2,000 (8-hr)
4,000 (1-hr)
100,000 (15-
min)
Ozone (O3)
Industrial
Residential, Rural
and Other Areas
100 (8-hr)
180 (1-hr) 100 (8-hr)
100 (8-hr)
180 (1-hr)
Sensitive Area 100 (8-hr)
180 (1-hr) 100 (8-hr)
100 (8-hr)
180 (1-hr)
Lead (Pb)
Industrial,
Residential, Rural
and Other Areas
0.5 (Annual)
1.0 (24-hr)
0.5
(Annual)
0.5 (Annual)
1.0 (24-hr)
Sensitive Area 0.5 (Annual)
1.0 (24-hr)
0.5
(Annual)
0.5 (Annual)
1.0 (24-hr)
Ammonia
(NH3)
Industrial
Residential, Rural
and Other Areas
100 (Annual)
400 (24-hr)
100 (Annual)
400 (24-hr)
Sensitive Area 100 (Annual)
400 (24-hr)
100 (Annual)
400 (24-hr)
Benzene
(C6H6)
Industrial
Residential, Rural
and Other Areas
5 (Annual) 5 (Annual)
176
Parameter Location a
India Ambient
Air Quality
Standard
(µg/m3) b
WHO Air Quality
Guidelines (µg/m3) Applicable
Per ADB SPSe
(µg/m3)
Global
Update c
2005
Second
Edition
2000
Sensitive Area 5 (Annual) 5 (Annual)
Benzo(o)py
rene (BaP)
particulate
phase only
Industrial
Residential, Rural
and Other Areas
0.001 (Annual) 0.001 (Annual)
Sensitive Area 0.001 (Annual) 0.001 (Annual)
Arsenic
(As)
Industrial
Residential, Rural
and Other Areas
0.006 (Annual) 0.006 (Annual)
Sensitive Area 0.006 (Annual) 0.006 (Annual)
Nickel (Ni)
Industrial
Residential, Rural
and Other Areas
0.02 (Annual) 0.02 (Annual)
Sensitive Area 0.02 (Annual) 0.02 (Annual)
B. Ambient Noise Quality Standards
Receptor/
Source
India National
Noise Level
Standardsa
(dBA)
WHO Guidelines Value
For Noise Levels
Measured Out of Doorsb
(One Hour LAq in dBA)
Applicable Per IFC
(dBA)
Day Night 07:00 –
22:00
22:00 –
07:00 Day time
Night
time
Industrial area 75 70 70 70 70 70
Commercial
area 65 55 70 70 65 55
Residential
Area 55 45 55 45 55 45
Silent Zone 50 40 55 45 50 40
177
C. Treated Wastewater Quality Standard
Parameters No discharge
standard for WTP
under national laws
Parameters IFC Sanitary
Wastewater
Quality- 2007
pH pH 6-9
BOD (mg/l) BOD (mg/l) 30
COD (mg/l) COD (mg/l) 125
TSS (mg/l) TSS (mg/l) 50
Total N (mg/l) Total N (mg/l) 10
NH4-N (mg/l) Total P (mg/l) 2
Fecal coliform
(MPN/100ml)
Total coliform bacteria
(MPN/100ml)
400
Oil &grease (mg/l) 10
178
Appendix 6: Extract From Construction & Demolition Management Rules, 2016
179
180
181
182
183
184
Appendix 7: Salient Features Of Major Labor Laws Applicable To Establishments Engaged In Construction Of Civil Works
185
Appendix 8: Drinking Water Standards
186
187
Appendix 9: Sample Outline Traffic Management Plan
188
189
190
.
191
Figure A2 & A3: Work on shoulder or parking lane & Shoulder or parking lane closed on divided road
192
Figure A4 & A5: Work in Travel lane & Lane closure on road with low volume
193
Figure A6: Street closure with detour
194
Appendix 10: Sample Outline Spoils (Construction Waste) Management Plan
195
Appendix 11: Application Submitted to WRD for Water Abstraction from Kathan River For Bada Malhera Town WSS
1. Copy of Letter Submitted to WRD along with Application Form 199 for Water Allocation
from Kathan River
196
2. Water Allocation Form-199 Submitted to WRD For Bada Malhera Town WSS
197
198
Appendix 12: Surface Water Quality Results – Kathan River
199
200
Appendix 13: Guidance on Siting and facilities in Contractors Camps
Siting of Contractor’s Camp
Sites / land types to be avoided:
• Lands close to habitations
• Irrigated agricultural lands
• Lands belonging to small farmers
• Lands under village forests
• Lands within 100m of community water bodies and water sources as rivers
• Lands supporting dense vegetation and Forest with/without conservations status
• Low lying lands
• Lands within 100m of watercourses
• Grazing lands and lands with or without tenure rights Community land ((Gochars,Thans) which is traditionally used as conservation areas
• Lands where there is no willingness of the landowner to permit its use
• 2km from Class A and above towns
• 500m from any villages
Land Types Preferred:
• Waste lands.
• Waste Lands belonging to owners who look upon the temporary use as a source of income.
• Community lands or government land not used for beneficial purposes.
• non-irrigated lands where the owner is willing.
• Lands with an existing access road.
Living Arrangements:
Ensure conditions of livability at work camps are maintained at the highest standards possible at
all times; living quarters and construction camps shall be provided with standard materials (as
far as possible to use portable ready to fit-in reusable cabins with proper ventilation); thatched
huts, and facilities constructed with materials like GI sheets, tarpaulins, etc., shall not be used
as accommodation for workers
Security:
The contractor shall put in place the following security measures to ensure the safety of the
workers. The following measures shall be incorporated:
• The contractor/sub-contractor shall provide Identity cards to all the employees/workers.
• Access to the campsite shall be limited to the residing workforce.
201
• The contractor shall be responsible for deploying adequate number of guards. However, guards shall not carry any firearms unless authorized by the Client or his representative.
• Adequate, d/ night-time lighting shall be provided at all the facilities in the camp.
• The security personnel shall be provided with training to respect the community traditions and in dealing with, use of force etc.; and
• The rental accommodation shall be provided with firefighting equipment and portable fire extinguishers.
Provision of Drinking Water:
• Access to an adequate and convenient supply of free potable water is a necessity for workers. The domestic water supply shall be made available by the contractor.
• Safe drinking water conforming to the IS 10500:2012 for drinking water shall be provided.
• Bottled Potable drinking water would be provided to all the employee/workers both at the worksite and at the construction camps.
• Every water supply or storage shall be at a distance not less than 15m from any wastewater / sewage drain or other source of pollution. Water sources within 15m proximity of toilet, drain or any source of pollution will not be used for any consumption purpose in the project
• The Contractor should regularly monitor (every quarter) the quality of drinking water available. In case of non-compliance with the Drinking Water Specifications, additional treatment shall be provided, or alternative sources of water supply shall be arranged; and
• All tanks used for the storage of drinking water shall covered as to prevent water stored therein from becoming polluted or contaminated.
• The tanks shall be cleaned at regular interval (minimum every 3 months) to ensure hygiene conditions are maintained.
Cooking Arrangement:
The construction phase will involve engagement of large number of migrant people in the
project area for a limited time. Hence, there shall be requirement of provision of cooking
facilities (kitchen) as listed below:
• The cooking area shall be separate from the Living quarters.
• Places for food preparation are designed to permit good hygiene practices, including protection against contamination between and during food preparation.
• The cooking area should be provided with water connections which is fit for consumption.
• Adequate personal hygiene including designated areas for cleaning hands and cleaning of utensils.
• All kitchen floors, ceiling and wall surfaces adjacent to or above food preparation and cooking areas are built using durable, non-absorbent, easily cleanable, non-toxic materials.
• Food preparation area to be durable, easily cleanable, non-corrosive surface made of non-toxic materials; and
202
• To ensure that the fuel need of labour in the project area does not interfere with the local requirements, necessary arrangements for supply of cooking fuel to the labour shall be done by the contractor. Clean fuels shall be used in no circumstance fuel wood shall be used for cooking or heating.
Washing and Bathing Facilities
In every site, adequate and suitable facilities for washing clothes and utensils shall be provided
and maintained for the use of contract labour employed therein. Separate and adequate bathing
shall be provided for the use of male and female workers. Such facilities shall be conveniently
accessible and shall be kept in clean and hygienic conditions.
Toilets Facilities:
Sanitary arrangements, latrines and urinals shall be provided in every workplace separately for
male and female workers. The arrangements shall include:
• A latrine for every 15 females or part thereof (where female workers are employed).
• A latrine for every 10 males.
• Every latrine shall be under cover and so partitioned as to secure privacy and shall have a proper door and fastenings.
• Where workers of both sexes are employed, there shall be displayed outside each block of latrine and urinal, a notice in the language understood by most of the workers ―” For Men Only” or ―” For Women Only” as the case may be. Pictographic signages can also be used.
• The latrines and urinals shall be adequately lighted and shall be maintained in a clean sanitary condition at all times and should have a proper drainage system; and
• Water shall be provided in (preferably) or near the latrines and urinals by storage in suitable containers.
Wastewater Generation:
There will of generation of wastewater from the campsite. About 80% of water used shall be
generated as sewage/wastewater. Contractor shall ensure that the campsite/s is/are equipped
with:
• Septic tank and soak pit for disposal of sewage or with mobile bio-toilets. The toilets and the septic tank and soak pit should not be located near any drinking water sources either within or outside the camp.
• The storm water and sewage system should be separate. The surface water drainage shall include all necessary gutters, down pipes, gullies, traps, catch pits, manholes etc. An Oil water separator should be in the drains leading out of the maintenance area. Water passing out of the camp should be passed through a sedimentation tank of at-least 3hrs holding capacity; and
• Sanitary and toilet facilities are constructed of materials that are easily cleanable. Sanitary and toilet facilities are required to be cleaned frequently and kept in working condition.
203
Solid Waste Management:
The solid waste generated from campsite will mostly comprise of compostable wastes like
vegetable residues (kitchen waste) and combustible waste like paper, cans, plastic and some
non-degradable waste like glass/glass bottles. Improper disposal of solid waste will lead to
environmental degradation and health hazards to labour as well as nearby community.
The following measures shall be adopted by contractors for ensuring effective management of
solid waste:
• The solid wastes of domestic nature (especially food waste, waste from canteen) shall be collected and stored separately in appropriate containers with proper covers on them so that they are not littered.
• Separate bins with proper markings in terms of recyclable or non-recyclable waste shall be provided in the houses and kitchen premises in sufficient numbers for collection of garbage.
• Food waste and other refuse are to be removed from the kitchen frequently to avoid accumulation; and
• The contractor shall ensure that the all food waste generated is composed within the camp premises. All recyclables except for the waste which are covered by any other act/rules other than the Municipal Solid Waste Rules 2016.
• Roads
All the internal roads shall be paved. The concrete slurry from the batching plant shall be used
for paving the roads
Medical Facility:
Effective health management is necessary for preventing spread of communicable diseases
among labour and within the adjoining community. The following medical facilities shall be
provided by contractors for the construction workers:
• A first aid centre shall be provided for the labour within the construction site equipped with medicines and other basic facilities.
• Adequate first aid kits shall be provided in the campsite in accessible place. The kit shall contain all type of medicines and dressing material.
• Contractor shall identify and train an adequate number of workers to provide first aid during medical emergencies.
• Regular health check-ups shall be carried out for the construction labour every six month and health records shall be maintained.
• Labours should have easy access to medical facilities and first aid; where possible, nurses should be available for female workers.
• First Aid Box will be provided at every construction campsite and under the charge of a responsible person who shall always be readily available during working hours. He shall be adequately trained in administering first aid-treatment. Formal arrangement shall be prescribed to carry injured person or person suddenly taken ill to the nearest hospital. The first aid box shall contain the following.
204
• In case, the number of labour exceeds 50, the items in the first aid box shall be doubled. All the vehicles and equipment shall be provided with a fir-aid box with all the above. The medicines should be regularly checked for the expiry of the medicines.
• Information and awareness of communicable diseases, AIDS etc. shall be provided to workers; and
• Basic collective social/rest spaces are provided to workers.
Fire-fighting arrangement
• The contractor shall carry out demarcation of area susceptible to fires and put in precautionary signages as specified in IS 9457.
• Portable fire extinguishers and/or sand baskets shall be provided at easily accessible locations in the event of fire as per the provisions of IS 2190; and
• The contractor shall carry out fire safety drill every quarter and Workers shall be trained on the usage of such equipment/s.
Fuel and Chemical Storage
• License is required for storage and transport of any such product (i.e. petroleum class B) if the total quantity in in possession does exceed 2500 liters in non-bulk (i.e. drums) or 1000litres in a receptacle / tank (i.e. bulk).
• Fuel Storage in HDPE drums shall be prohibited because the static energy is stored in the drum as there no conducting media. This can lead to fires int oil storage areas.
• All fuel and chemical storage area should be made impermeable either by concrete flooring or by placing an HDPE liner.
• The storage area shall be provided with a bunded. The capacity of the bund shall be 110% of the volume of the maximum storage tank
• The area shall be covered and secured under lock and key.
• In no condition shall the fuel be decanted by tilting of drums. An approved fuel pump manual or energy driven shall be used.
• In case of spills Emergency Spill care procedures as presented in Appendix 15 shall be used.
Vehicle Maintenance and Repairs
• Equipment maintenance and refueling sites will be located at least 500 m from rivers and irrigation canal/ponds
The wastewater/ runoff from the vehicle maintenance area shall be passed through an Oil water
separation system to prevent any oil and grease into the natural system
205
Appendix 14: Guideline for Construction Work about Safety from COVID-19 Pandemic (SOP – Health & Safety Plan)
206
207
208
209
210
211
212
213
Appendix 15: Sample Grievance Registration Form
214
Appendix 16: Sample Environmental Site Inspection Report
Project Name
Contract Number
NAME: __________________________________ DATE: __________________________
TITLE: ___________________________________ DMA: ___________________________
LOCATION: _______________________________GROUP: ________________________
WEATHER:
Project
Activity
Stage
Survey
Design
Implementation
Pre-Commissioning
Guarantee Period
Monitoring Items Compliance
Compliance marked as Yes / No / Not applicable (NA) / Partially Implemented (PI)
EHS supervisor appointed by contractor and available on site
Archaeological Supervisor appointed by contractor and available on site
Construction site management plan (spoils, safety, schedule, equipment etc.,) prepared
Traffic management plan prepared
Dust is under control
Excavated soil properly placed within minimum space
Construction area is confined; no traffic/pedestrian entry observed
Surplus soil/debris/waste is disposed without delay
Construction material (sand/gravel/aggregate) brought to site as & when required only
Tarpaulins used to cover sand & other loose material when transported by vehicles
After unloading, wheels & undercarriage of vehicles cleaned prior to leaving the site
No AC pipes disturbed/removed during excavation
215
No chance finds encountered during excavation
Work is planned in consultation with traffic police
Work is not being conducted during heavy traffic
Work at a stretch is completed within a day (excavation, pipe laying & backfilling)
Pipe trenches are not kept open unduly
Road is not completely closed; work is conducted on edge; at least one line is kept open
Road is closed; alternative route provided & public informed, information board provided
Pedestrian access to houses is not blocked due to pipe laying
Spaces left in between trenches for access
Wooden planks/metal sheets provided across trench for pedestrian
No public/unauthorized entry observed in work site
Children safety measures (barricades, security) in place at works in residential areas
Prior public information provided about the work, schedule and disturbances
Caution/warning board provided on site
Guards with red flag provided during work at busy roads
Workers using appropriate PPE (boots, gloves, helmets, ear muffs etc)
Workers conducting or near heavy noise work is provided with ear muffs
Contractor is following standard & safe construction practices
Deep excavation is conducted with land slip/protection measures
First aid facilities are available on site and workers informed
Drinking water provided at the site
Toilet facility provided at the site
Separate toilet facility is provided for women workers
Workers camps are maintained cleanly
Adequate toilet & bath facilities provided
Contractor employed local workers as far as possible
Workers camp set up with the permission of PIU
216
Adequate housing provided
Sufficient water provided for drinking/washing/bath
No noisy work is conducted in the nights
Local people informed of noisy work
No blasting activity conducted
Pneumatic drills or other equipment creating vibration is not used near old/risky buildings
Signature
_______________________________________
Sign off
_______________________________ ________________________________
Name Name
Position Position
217
Appendix 17: Quarterly Reporting Format for Assistant Safeguards Officer 1. Introduction
• Overall project description and objectives
• Description of sub-projects
• Environmental category of the sub-projects
• Details of site personnel and/or consultants responsible for environmental monitoring
• Overall project and sub-project progress and status
No. Sub-Project
Name
Status of Sub-Project List of
Works
Progress
of Works Design Pre-
Construction
Construction Operational
Phase
2. Compliance status with National/ State/ Local statutory environmental requirements
No. Sub-Project Name Statutory Environmental
Requirements
Status of
Compliance
Action Required
3. Compliance status with environmental loan covenants
No. (List schedule and
paragraph number of
Loan Agreement)
Covenant Status of Compliance Action Required
218
4. Compliance status with the environmental management and monitoring plan
• Provide the monitoring results as per the parameters outlined in the EMP. Append supporting documents where applicable, including Environmental Site Inspection Reports.
• There should be reporting on the following items which can be incorporated in the checklist of routine Environmental Site Inspection Report followed with a summary in the semi-annual report send to ADB. Visual assessment and review of relevant site documentation during routine site inspection needs to note and record the following:
o What are the dust suppression techniques followed for site and if any dust was noted to escape the site boundaries;
o If muddy water was escaping site boundaries or muddy tracks were seen on adjacent roads;
o adequacy of type of erosion and sediment control measures installed on site, condition of erosion and sediment control measures including if these were intact following heavy rain;
o Are their designated areas for concrete works, and refuelling; o Are their spill kits on site and if there are site procedure for handling emergencies; o Is there any chemical stored on site and what is the storage condition? o Is there any dewatering activities if yes, where is the water being discharged; o How are the stockpiles being managed; o How is solid and liquid waste being handled on site; o Review of the complaint management system; Checking if there are any activities being under taken out of working hours and how
that is being managed
219
Summary Monitoring Table
Impacts
(List from
IEE)
Mitigation
Measures
(List from
IEE)
Parameters
Monitored (As a
minimum those
identified in the IEE
should be
monitored)
Method of
Monitoring
Location
of
Monitoring
Date of
Monitoring
Conducted
Name of
Person
Who
Conducted
the
Monitoring
Design Phase
Pre-Construction Phase
Construction Phase
Operational Phase
220
Overall Compliance with CEMP/ EMP
No. Sub-Project
Name
EMP/ CEMP
Part of
Contract
Documents
(Y/N)
CEMP/ EMP
Being
Implemented
(Y/N)
Status of
Implementation
(Excellent/ Satisfactory/
Partially Satisfactory/
Below Satisfactory)
Action Proposed
and Additional
Measures
Required
5. Approach and methodology for environmental monitoring of the project
• Brief description on the approach and methodology used for environmental monitoring of each sub-project
6. Monitoring of environmental impacts on project surroundings (ambient air, water
quality and noise levels)
• Brief discussion on the basis for monitoring
• Indicate type and location of environmental parameters to be monitored
• Indicate the method of monitoring and equipment to be used
• Provide monitoring results and an analysis of results in relation to baseline data and statutory requirements
As a minimum the results should be presented as per the tables below.
221
Air Quality Results
Site No. Date of Testing Site Location
Parameters (Government
Standards)
PM10
µg/m3
SO2
µg/m3
NO2
µg/m3
Site No. Date of Testing Site Location
Parameters (Monitoring
Results)
PM10
µg/m3
SO2
µg/m3
NO2
µg/m3
Water Quality Results
Site No. Date of Sampling Site Location
Parameters (Government Standards)
pH Conductivity
µS/cm
BOD
mg/L
TSS
mg/L
TN
mg/L
TP
mg/L
Site No. Date of Sampling Site Location
Parameters (Monitoring Results)
pH Conductivity
µS/cm
BOD
mg/L
TSS
mg/L
TN
mg/L
TP
mg/L
222
Noise Quality Results
Site No. Date of Testing Site Location LAeq (dBA) (Government Standard)
Day Time Night Time
Site No. Date of Testing Site Location LAeq (dBA) (Monitoring Results)
Day Time Night Time
7. Summary of key issues and remedial actions
• Summary of follow up time-bound actions to be taken within a set timeframe.
8. Appendixes
• Photos
• Summary of consultations
• Copies of environmental clearances and permits
• Sample of environmental site inspection report
• Other
223
Appendix 18: Stakeholder Consultation Details, Photographs of Consultations and List of Participants in Bada Malhera Nagar Parishad under Package 6K
Date Location No. of Participants
Participants Topics Discussion Issues/ Concern and Mitigation Measures
20/02/19
Bada Malhera
Nagar
Parishad
Meeting Hall
Total = 20 Male = 16, Female = 04
Elected
representatives,
officials of Bada
Malhera
• Background of water supply subproject, Environmental, Social, GRM, traffic safety issue, Temporary disruption of accesses and benefits from the project were explained to the Stakeholders.
• Status of Existing Water Supply at town.
• Proposed subproject components.
• Environment, Social and community impact during operation work
• Impact on health by proposed project
• Willing to take new Water connection
• Location of components of proposed water Supply scheme has been finalized with identification of government land.
• Potential positive and negative impacts due to project implementation Ensuring no income loss
• Present water supply quantity is not sufficient in town.
• Some ward does not get the municipal water supply
• Quality of water is not good.
• The prime concern and apprehension of the ULB Chairman regarding the project was whether it will be a financial burden on the Nagar Parishad.
• Hope local people support the upcoming water supply project as it will be beneficial to the community in all aspects.
• All stakeholders were very supporting of the project, and extended full cooperation during the works
• People are ready to take new water connection in place of old one
• People will pay proposed water tariff.
• There should not be any water supply interruption during laying new pipe line.
• Try to avoid negative impact on the livelihood of local businessman as disturbance due to road excavation
• Prevent entry of traffic, public in construction area
• Hard barricading shall be provided in construction area.
• Control dust during construction by water sprinkling on exposed soil, stock stockpiled material on site
224
• Employ local persons in construction work and
• Use of personal protective equipment (PPE) to workers (like helmet, gumboot, safety belt, gloves, nose musk and ear plugs) for his/her safety
• Attention of stakeholders drawn to the EMP, and explained to them how dust, and other construction issues will be managed. It was informed that night work will be explored during construction but may not be possible, however all measures will be taken by contractor to avoid/minimize construction disturbances.
19/02/19 Office of NGO
J.V Sangthan
Total = 3 Male = 2 Female = 1
Officials from
NGO • Briefing on project objectives
probable implementation procedures
• Present drinking water supply source and its condition
• Potential positive and negative
impacts due to project
implementation
• Land use and area to be covered under the project
• Consultant representatives visited Bada Malhera Parishad for explaining concept report and site visit for finalization of source and land availability details for preparation of Detailed Project Report of Water Supply Scheme
• The Officials of MPUDC explained in details regarding the project and its necessity to the Town
. The officials of MPUDC explained the
officials from NGO JV Sangthan in
details regarding the project
subcomponent and Route from which
the Clear Water Feeder mains will
pass and there will be no damage to
the Environment and to any forest
land due to the Project.
• The Officials of JV Sangthan welcomed the project and expressed need for it.
•
19/02/19 Galla Market War No. 6
Total = 13 Male = 8 Female = 5
Local Shop Keepers of Ward No 6 Bada Malhera
• Background of water supply subproject, Environmental, Social, GRM, traffic safety issue, Temporary disruption of
• Assured full support during implementation.
• During excavation, dust and traffic management assurance given to
225
accesses and benefits from the project were explained to the Stakeholders.
• Briefing on project objectives probable implementation procedures
• Present drinking water supply source and its condition
• Potential positive and negative impacts due to project implementation
• Potential positive and negative impacts due to project implementation
• Land use and area to be covered under the project
• Relevant information of the upcoming project and benefits of the project.
• Ensuring no income loss
• Proposed subproject components
• Grievance Redressal Mechanism (GRM)
the Shopkeepers with the help from local police and local shopkeepers.
• Prior consultation / intimation before the start of civil works in market area.
• Road restoration must be in timely manner.
• Shop keepers assured their full support to the Project and assured full cooperation during the construction phase
• Street vendors and small shop owners got agreed on temporary shifting of Haats (to other road side were alignment is not proposed) during excavation
• It should be ensured that their business is not closed for the civil works ensuring no income loss
• The shop owners indicated that they are willing to accept the project which is ultimately for the benefit of the community people;
• GRC will be formed at town level to address the local complaints and briefed about other levels under GRM
12/12/19 Local Market & Hatt, Near Bus Stand, Bada Malhera
Total = 14 Male = 7 Female = 7
Local Shop Keepers of Ward No 6 Bada Malhera
• Background of water supply subproject, Environmental, Social, GRM, traffic safety issue, Temporary disruption of accesses and benefits from the project were explained to the Stakeholders.
• Briefing on project objectives probable implementation procedures
• Assured full support during implementation.
• During excavation, dust and traffic management assurance given to the Shopkeepers with the help from local police and local shopkeepers.
• Prior consultation / intimation before the start of civil works in market area.
226
• Present drinking water supply source and its condition
• Potential positive and negative impacts due to project implementation
• Potential positive and negative impacts due to project implementation
• Land use and area to be covered under the project
• Relevant information of the upcoming project and benefits of the project.
• Ensuring no income loss
• Proposed subproject components
• Grievance Redressal Mechanism (GRM)
• Road restoration must be in timely manner.
• Shop keepers assured their full support to the Project and assured full cooperation during the construction phase
• Street vendors and small shop owners got agreed on temporary shifting of Haats (to other road side were alignment is not proposed) during excavation
• It should be ensured that their business is not closed for the civil works ensuring no income loss
• The shop owners indicated that they are willing to accept the project which is ultimately for the benefit of the community people;
• GRC will be formed at town level to address the local complaints and briefed about other levels under GRM
19/02/19 Ward No. 5, Soni Muhalla
Total =34 Male = 14 Female = 20
Community Members
• Status of existing drinking water supply system;
• Need for improvements to present system;
• Background of water supply subproject, Environmental, Social, GRM, traffic safety issue, Temporary disruption of accesses and benefits from the project were explained to the Stakeholders.
• Relevant information of the upcoming project and benefits of the project.
• Potential positive and negative impacts due to project implementation
• The area has insufficient and inadequate drinking water resource.
• The community willingly accepted the project.
• Majority were very excited about the scheme as either they are fetching water from far, or the quality is not good, children also suffer as they also are required to help.
• Assured full support during implementation.
• Some people are ready to take new water connection in place of old one
• Demand for free water stand post
• People were agreeing to pay
227
• Ensuring no income loss
• The Water Supply Scheme, SHG (Self Help Group) Environmental, Social, GRM, traffic safety issue and benefit from the project were explained to the Stakeholders.
• Briefing on project objectives probable implementation procedures.
proposed water tariff.
• There should not be any water supply interruption during laying new pipe line.
• Raised the issue about their business disturbance due to road excavation.
• Control dust during construction by water sprinkling on exposed soil, stock stockpiled material on site
• Employ local persons in construction work.
25/09/19 Ward No. 1 Total = 27 Male = 07 Female = 20
Community Members
• Background of water supply subproject, Environmental, Social, GRM, traffic safety issue, Temporary disruption of accesses and benefits from the project were explained to the Stakeholders.
• Status of existing drinking water supply system;
• Need for improvements to present system;
• Relevant information of the upcoming project and benefits of the project.
• Potential positive and negative impacts due to project implementation
• Ensuring no income loss
• The Water Supply Scheme, SHG (Self Help Group) Environmental, Social, GRM, traffic safety issue and benefit from the project were explained to the Stakeholders.
• Briefing on project objectives probable implementation procedures.
• The area has insufficient and inadequate drinking water resource.
• The community willingly accepted the project.
• Majority were very excited about the scheme as either they are fetching water from far, or the quality is not good, children also suffer as they also are required to help.
• Assured full support during implementation.
• Some people are ready to take new water connection in place of old one
• Demand for free water stand post
• People were agreeing to pay proposed water tariff.
• There should not be any water supply interruption during laying new pipe line.
• Raised the issue about their business disturbance due to road excavation.
• Control dust during construction by water sprinkling on exposed soil, stock stockpiled material on site
228
• Employ local persons in construction work.
229
19/02/2019 Ward No. 2 Total = 19 Male = 11 Female = 08
Scheduled Tribes (ST) Community members
• Background of water supply subproject, Environmental, Social, GRM, traffic safety issue, Temporary disruption of accesses and benefits from the project were explained to the Stakeholders
• Status of existing drinking water supply system;
• Need for improvements to present system;
• Relevant information of the upcoming project and benefits of the project.
• Potential positive and negative impacts due to project implementation
• Ensuring no income loss
• The Water Supply Scheme, SHG (Self Help Group) Environmental, Social, GRM, traffic safety issue and benefit from the project were explained to the Stakeholders.
• Briefing on project objectives probable implementation procedures.
• The area has insufficient and inadequate drinking water resource.
• The community willingly accepted the project.
• Majority were very excited about the scheme as either they are fetching water from far, or the quality is not good, children also suffer as they also are required to help.
• Assured full support during implementation.
• Some people are ready to take new water connection in place of old one
• Demand for free water stand post
• People were agreeing to pay proposed water tariff.
• There should not be any water supply interruption during laying new pipe line.
• Raised the issue about their business disturbance due to road excavation.
• Control dust during construction by water sprinkling on exposed soil, stock stockpiled material on site
• Employ local persons in construction work.
230
12/12/2019 Ward No.2 & 3 near OHT 330 KL
Total = 15, Female = 07, Male = 08
Scheduled Tribes (ST) Community members
• Background of water supply subproject, Environmental, Social, GRM, traffic safety issue, Temporary disruption of accesses and benefits from the project were explained to the Stakeholders
• Status of existing drinking water supply system;
• Need for improvements to present system;
• Relevant information of the upcoming project and benefits of the project.
• Potential positive and negative impacts due to project implementation
• Ensuring no income loss
• The Water Supply Scheme, SHG (Self Help Group) Environmental, Social, GRM, traffic safety issue and benefit from the project were explained to the Stakeholders.
• Briefing on project objectives probable implementation procedures.
• The area has insufficient and inadequate drinking water resource.
• The community willingly accepted the project.
• Majority were very excited about the scheme as either they are fetching water from far, or the quality is not good, children also suffer as they also are required to help.
• Assured full support during implementation.
• Some people are ready to take new water connection in place of old one
• Demand for free water stand post
• People were agreeing to pay proposed water tariff.
• There should not be any water supply interruption during laying new pipe line.
• Raised the issue about their business disturbance due to road excavation.
• Control dust during construction by water sprinkling on exposed soil, stock stockpiled material on site
• Employ local persons in construction work.
231
12/12/2019 Ward No 12 Total = 21 Male = 14 Female = 07
Scheduled Cast (SC) Community members
• Background of water supply subproject, Environmental, Social, GRM, traffic safety issue, Temporary disruption of accesses and benefits from the project were explained to the Stakeholders
• Status of existing drinking water supply system;
• Need for improvements to present system;
• Relevant information of the upcoming project and benefits of the project.
• Potential positive and negative impacts due to project implementation
• Ensuring no income loss
• The Water Supply Scheme, SHG (Self Help Group) Environmental, Social, GRM, traffic safety issue and benefit from the project were explained to the Stakeholders.
• Briefing on project objectives probable implementation procedures.
• The area has insufficient and inadequate drinking water resource.
• The community willingly accepted the project.
• Majority were very excited about the scheme as either they are fetching water from far, or the quality is not good, children also suffer as they also are required to help.
• Assured full support during implementation.
• Some people are ready to take new water connection in place of old one
• Demand for free water stand post
• People were agreeing to pay proposed water tariff.
• There should not be any water supply interruption during laying new pipe line.
• Raised the issue about their business disturbance due to road excavation.
• Control dust during construction by water sprinkling on exposed soil, stock stockpiled material on site
• Employ local persons in construction work.
232
12/12/2019 Ward No. 15 Total = 22 Male = 06 Female = 16
Scheduled Cast (SC) Community members
• Background of water supply subproject, Environmental, Social, GRM, traffic safety issue, Temporary disruption of accesses and benefits from the project were explained to the Stakeholders
• Status of existing drinking water supply system;
• Need for improvements to present system;
• Relevant information of the upcoming project and benefits of the project.
• Potential positive and negative impacts due to project implementation
• Ensuring no income loss
• The Water Supply Scheme, SHG (Self Help Group) Environmental, Social, GRM, traffic safety issue and benefit from the project were explained to the Stakeholders.
• Briefing on project objectives probable implementation procedures.
• The area has insufficient and inadequate drinking water resource.
• The community willingly accepted the project.
• Majority were very excited about the scheme as either they are fetching water from far, or the quality is not good, children also suffer as they also are required to help.
• Assured full support during implementation.
• Some people are ready to take new water connection in place of old one
• Demand for free water stand post
• People were agreeing to pay proposed water tariff.
• There should not be any water supply interruption during laying new pipe line.
• Raised the issue about their business disturbance due to road excavation.
• Control dust during construction by water sprinkling on exposed soil, stock stockpiled material on site
• Employ local persons in construction work.
233
Photographs of Consultation and List of Participants of Elected Representative and ULB Officials Bada Malhera Nagar Parishad
234
Photograph of consultation and List of Participants during
consultation with Jay Vardhan Sangthan NGO, Bada Malhera Nagar
Parishad
235
Photograph of consultation and List of Participants during consultation with Shopkeepers, in Galla Market Ward No. 06, Bada Malhera Nagar Parishad
236
Photographs of Consultation and List of Participants during consultation with Shopkeepers of Main Market & Hatt, Near Bus Stand, Bada Malahera, Bada Malhera
Nagar Parishad
237
Photograph of consultation and List of Participants during consultation with Genral Public in Soni Muhalla, ward No.- 05, Bada Malhera Nagar Parishad
238
Photograph of consultation and List of Participants during consultation with Communty & Locail residents, Ward No-1, Sarswati Shishu Mandir (OHT- 330 KL),
Bada Malhera Nagar Parishad
239
Photograph of consultation and List of Participants during consultation with ST Community in ward no 2, Bada Malhera Nagar Parishad
240
Photograph of consultation and List of Participants during consultation with S.T Community of Ward No 2 and 3, Bada Malhera Nagar Parishad
241
Photograph of consultation and List of Participants during consultation with SC Communty, Ward No-12, Kammod Pura, ( OHT-100 KL), Bada Malhera Nagar
Parishad
242
Photograph of consultation and List of Participants during consultation with SC Community in Ambedkar, ward No.- 15, Bada Malhera Nagar Parishad
243
Appendix 19: GPS Coordinates of Proposed/Existing WSS Components Sites of Subproject Towns – Bada Malhera Town under Package 6K
S. No. Proposed / Existing WSS Components GPS Coordinates
1. Proposed Weir Latitude – 24°35'30.12"N Longitude - 79°16'26.15"E
2. Proposed Pick-up Weir Latitude – 24°36'16.52"N Longitude - 79°16'16.43"E
3. Existing Intake well Latitude – 24°35'51.86"N Longitude - 79°16'26.41"E
4. Existing WTP Latitude – 24°34'44.58"N Longitude - 79°17'58.12"E
5. Proposed OHT: 100 KL Latitude – 24°34'20.42"N Longitude - 79°17'43.02"E
6. Proposed OHT: 330 KL Latitude – 24°33'23.67"N Longitude - 79°18'32.47"E
7. Existing OHT: 160 KL Latitude – 24°33'35.00"N Longitude - 79°18'13.52"E
8. Existing OHT: 650 KL Latitude – 24°34'30.02"N Longitude - 79°18'18.11"E