PROJECTMANAGEMENT

Pre-reads1) Intro to projects2) Design-Build exercise

DesignBuild

3) Gantt exercise 1Exercise

4) Gantt exercise 25) PM theory 16) PM theory 2

40’15’10’ ~1 hr15’15’17’20’12’ ~1.5 hr16’23’

1

2

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

Challenges in Project Management

• Communication

• Coordination

• Dependencies/ order

• Change/ risk

3

5/15/20

2

‘Only those who attempt the absurd will achieve the impossible.’ — M. C. Escher

“The real measure of success is the number of experiments that can becrowded into 24 hours.” — Thomas Alva Edison

“It is only through failure and through experiment that we learn andgrow.” — Isaac Stern

4

5

6

5/15/20

3

7

8

9

5/15/20

4

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

E1 Lessons Learned

• Communication

• Time/cost/quality/scope and tradeoffs

• Plan/ Execute

• Contingency/ Disaster recovery

• Competition/ CI

10

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

Top 10 Causes of Project Failure

• Poor preparation• Inadequate documentation and tracking• Bad leadership• Failure to define parameters and enforce them• Inexperienced project managers• Inaccurate cost estimates• Little communication at every level of management• Culture or ethical misalignment• Competing priorities• Disregarding project warning signs

By Rosanne Lim (2016) https://project-management.com/top-10-main-causes-of-project-failure/

11

12

5/15/20

5

13

MBiotech Project Management (Gantt Chart) Agenda

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

Spaghetti

14

15

5/15/20

6

PERT Chart/ Network Diagram 2

16

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

Rock’n Bands

Designed by: Ken Klaassen, Brock University© 2014 Keith Willoughby, Bucknell University

12

17

Original

38 person-weeks= $7,600 min.

Cost000000000000_0Staff

Admin

18

5/15/20

7

1 22

2001 2 5

400 1100

100100

17003002000

Example Costing

Up to 4 workers @$200 eachplus 1 additional @$300 for overtime

Normally 1 worker/weekbut 1 extra costs $100 for admin

21

100

2

Staff

Admin

19

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

20

Light Crash

BEST+$400 for crash

21

5/15/20

8

22

Good Solution

+$1,200 (+$800 for 1 extra week

23

My Crash

+$1,100for 1 extra week

24

5/15/20

9

25

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

Rock’n Bands Learnings• Precedence/dependencies

• Critical path

• Expediting/ crashing

• Resource allocation/ scarcity

• Time/cost

• Coordination

• Uncertainty

26

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

27

5/15/20

10

28

Supporting Processes

Core Processes

Project Life Cycle

TeamMgmt.

StakeholderMgmt.

InformationMgmt.

RiskMgmt.

ContractMgmt.

ScopeMgmt.

ScheduleMgmt.

BudgetMgmt.

QualityMgmt.

Initiate Plan

Adapt

Implement

Monitor CloseControl/Check

Do/Execute

Input Output

29

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

30

5/15/20

11

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

31

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

32

33

5/15/20

12

Initiate Plan

Adapt

Implement

Monitor Close

34

Work Breakdown Structure

PERT Chart/ Network Diagram

Responsibility Assignment Matrix (RACI)

RESPONSIBLEACCOUNTABLECONSULTEDINFORMED

35

36

5/15/20

13

S-Curve

37

Strategy:Project Charter- Objectives- Business Case- Scope- Stakeholders- Assumptions- Statement of

Work

Execution:Progress Reports- vs. Baselines- Issue Log- Change Log- Plan Revisions- Stage-Gates- Lessons Learned

Planning:Project Plan- Time, Cost,

Quality Baselines- Stage-Gates- Risk

Management- Communication

Plan Change:Change Request

38

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

39

5/15/20

14

PLAN/MANAGEPMP www.pmi.org

PMBOK

REQUIREMENTSBA www.iiba.org

BABOK

COMMUNICATIONSChange Mgmt.

40

41

Milestones & Stage-gates

42

5/15/20

15

43

44

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

45

5/15/20

16

46

47

48

5/15/20

17

49

© Duncan Jones @ Hexagon-Innovating.com (2016) All rights reserved

Communication

Plan Your WorkWork Your Plan

Documentation