UDOT STRUCTURES DESIGN AND DETAILING MANUAL GUIDELINES FOR STRUCTURAL DESIGN REVIEWS
Updated: 10/4/2012 Page 1-1
OVERVIEW
These guidelines provide directions for Structural Design Reviews and Oversight Reviews on projects. A
design reviewer and oversight reviewer are assigned to projects that involve structures. General
procedures are:
• The Structures Division assigns a design reviewer and oversight reviewer to each project.
• A task order (scope of work and cost estimate) is prepared and submitted to the Structures
Division by the reviewer for reviews performed by consultants. Specific responsibilities are
defined.
• The design reviewer evaluates the design deliverables and prepares comments on the Discipline
Review Comment Resolution Form as described in the UDOT Quality Control / Quality Assurance
(QC/QA) Procedures.
• The design reviewer submits the review comments to the oversight reviewer.
• The oversight reviewer examines the review comments for consensus, provides additional
comments if necessary, and returns the Discipline Review Comment Resolution Form to the
design reviewer.
• The design reviewer returns the completed Discipline Review Comment Resolution Form to the
structural designer for the project.
• The structural designer for the project responds to the review comments and returns the form
to the design reviewer.
• The structural designer and reviewers discuss comments and responses and agree upon a final
disposition.
• Once comments are addressed and incorporated, the final deliverables are provided by the
structural designer to the design reviewer and oversight reviewer for comment resolution
verification.
• The design reviewer will complete the Structural Review Completion Form and send the form to
the Structures Construction Manager for verification and final acceptance of the deliverables.
Activity requirements are described in the Project Delivery Network. All projects are required to use
ProjectWise to maintain a record of all structures submittals and to exchange comments and responses.
Local government projects are required to follow UDOT Structure’s plan presentation.
Review services are intended to provide a constructible set of plans that meet design requirements.
General instructions to reviewers:
• Conduct all reviews with professionalism and tact
UDOT STRUCTURES DESIGN AND DETAILING MANUAL GUIDELINES FOR STRUCTURAL DESIGN REVIEWS
Updated: 10/4/2012 Page 1-2
• Avoid comments that should have been/be discovered through the structural designer’s QC/QA
process
SCOPING (STAGE 1)
1S1 IDENTIFY PRELIMINARY STRUCTURE TYPE (MINOR & MAJOR)
UDOT Structures Project Manager reviews and accepts the Preliminary Structure Type Selection Report.
Design review and oversight review is not required at this stage.
GEOMETRY (STAGE 2)
3S1 DEVELOP TYPE SELECTION AND LAYOUT (TS&L) AND SEISMIC STRATEGY
3S2 DEVELOP S&L FOR MINOR STRUCTURES
3S3 DEVELOP S&L FOR REHABILITATION
3S4 DEVELOP S&L FOR RETAINING WALLS
3S5 DEVELOP S&L FOR BRIDGES
A status Structure Type Selection Report, Seismic Strategy and structural plan package is submitted for
the 2V1 Geometry Review Meeting by the structural designer for the project. A formal review is not
required at the geometry stage. A courtesy review can be implemented depending on the project.
PLAN-IN-HAND (STAGE 3)
3S1 DEVELOP TYPE SELECTION AND LAYOUT (TS&L) AND SEISMIC STRATEGY
3S2 DEVELOP S&L FOR MINOR STRUCTURES
3S3 DEVELOP S&L FOR REHABILITATION
3S4 DEVELOP S&L FOR RETAINING WALLS
3S5 DEVELOP S&L FOR BRIDGES
The structural designer prepares the following deliverables of the Structural Documentation Package
and submits the package to the design reviewer for comments. Design reviewer completes the
following:
UDOT STRUCTURES DESIGN AND DETAILING MANUAL GUIDELINES FOR STRUCTURAL DESIGN REVIEWS
Updated: 10/4/2012 Page 1-3
Structure Type Selection Report • Verify inclusion in package
• Review content for completeness
Preliminary Seismic Strategy Report
• Verify inclusion in package
• Review document and compare
description with design plans
Situation & Layout Plan Sheets
• Verify plan sheets meet all the
requirements of the Situation & Layout
Checklist
• Verify UDOT CADD Standards are followed
• Verify structures are constructible using
proven construction methods
• Spot check, cross reference, and look
through non-structural sheets to validate
information shown and impacts from non-
structural items are addressed
• Confirm plans represent acceptable UDOT
design practice and presentation
Railroad Company’s Review and Acceptance
(if applicable)
• Verify inclusion in package (if applicable)
Initial Design Exception, Design Waiver, or
Deviation from UDOT Standards Form
(if applicable)
• Verify inclusion in package (if applicable)
• Review information as it applies to the
plans
Responses to Previous Review Comments
• Verify comments on the Milestone Review
Comment Resolution Form (2V1 Geometry
Review Meeting) have been addressed
• Verify Structure Foundation Type Memo is complete
• Verify hydraulic data and requirements (if applicable) are complete and reflected properly in the
structures design
• Verify a review and comments from the UDOT Geotechnical Division for all retaining walls are
included
• Provide written comments on the Discipline Review Comment Resolution Form
• Post the form directly to ProjectWise
UDOT STRUCTURES DESIGN AND DETAILING MANUAL GUIDELINES FOR STRUCTURAL DESIGN REVIEWS
Updated: 10/4/2012 Page 1-4
REVIEW TIME REQUIREMENT (3 TO 5 WEEKS) – PRIOR TO PLAN-IN-HAND MEETING
Complete Design Review and Oversight Review 1 to 2 Weeks
Address Comments by Structural Designer 1 to 2 Weeks
Complete verification of comment dispositions,
verify QC/QA documentation is complete, and
send Structural Review Completion Form to UDOT
by Design Reviewer and Oversight Reviewer
1 Week
3S6 S&L ACCEPTANCE
REVIEW TIME REQUIREMENT (3 WEEKS) – PRIOR TO PLAN-IN-HAND MEETING
Once all comments have been addressed, the structural designer prepares the Structural
Documentation Package and submits the package to the UDOT Structures Construction Manager for
acceptance.
Accept Structural Documentation Package by
UDOT 1 Week
Submit Situation & Layout Plan Sheets and
Preliminary Cost Estimate to Project Team for
Review by Structural Designer
2 Weeks (required)
INTERMEDIATE REVIEW (STAGE 4)
INTERMEDIATE REVIEW
An intermediate review is considered an over-the-shoulder review and will be included in projects as
deemed necessary during the Kickoff Meeting. Structure plan sets are reviewed to verify concept and
scope and identify design flaws that will significantly affect the design. This is not a detailed design or
UDOT STRUCTURES DESIGN AND DETAILING MANUAL GUIDELINES FOR STRUCTURAL DESIGN REVIEWS
Updated: 10/4/2012 Page 1-5
drawing check, but a review to validate the design direction and verify that the design scope and intent
and all project design criteria and requirements are being met. This review provides an opportunity to
make changes in the design before it progresses to the point where design changes become prohibitive.
PS&E (STAGE 4)
4SA DESIGN & DETAIL BRIDGE
4SM DESIGN & DETAIL MINOR STRUCTURE
4S1 DESIGN & DETAIL REHABILITATION
4S2 DESIGN & DETAIL OVERHEAD SIGN/VMS STRUCTURE
4S3 DESIGN & DETAIL RETAINING WALL
4S4 DEVELOP STRUCTURE PROJECT DOCUMENTS
The structural designer prepares the following deliverables of the Structure Project Documents and
submits the package to the design reviewer for comments. Design reviewer completes the following:
Structural Plans
• Verify plan sheets meet all the
requirements of UDOT Structures Design
and Detailing Manual
• Verify UDOT CADD Standards are followed
• Verify structures are constructible using
proven construction methods
• Spot check, cross reference, and look
through non-structural sheets to validate
information shown and impacts from non-
structural items are addressed
• Confirm plans represent acceptable UDOT
design practice and presentation
• Verify all appropriate structural details are
included
• Verify dimensions and callouts are clear
and complete
• Verify plan sheet notes use active voice
• Verify plans clearly communicate the
intended design
• Verify all structures are identified,
reviewed and have a structure number
assigned
UDOT STRUCTURES DESIGN AND DETAILING MANUAL GUIDELINES FOR STRUCTURAL DESIGN REVIEWS
Updated: 10/4/2012 Page 1-6
Calculations (upon request of Design Reviewer) • Compare design calculations with
information in the plan set (if applicable)
Structures Engineer’s Estimate • Verify quantities and unit costs for
structural items are reasonable
Specifications & Special Provisions
• Verify active voice is used
• Verify construction schedule is appropriate
• Verify specifications and special provisions
are clear and understandable
• Verify all required structural special
provisions are included
• Verify correlation between plans,
specifications, and special provisions are
complete
Measurement & Payment • Verify payment information for structural
items are complete and acceptable
Acceptance & Documentation • Verify structural items are complete
Responses to Previous Review Comments
• Verify comments on the Milestone Review
Comment Resolution Form (3V1 Plan-in-
Hand Review Meeting) have been
addressed
• Verify geotechnical report is complete and reflected properly in the structures design
• Verify hydraulic report (if applicable) is complete and reflected properly in the structures design
• Notify UDOT Structures Project Manager if final reports are not complete
• Verify a review and comments from the UDOT Geotechnical Division for all retaining wall
designs are included
• Verify consistency of items and quantities between the plans, specifications, special provisions,
engineer’s estimate, measurement and payment, and acceptance and documentation
documents
• Provide written comments on the Discipline Review Comment Resolution Form
• Post the form directly to ProjectWise
REVIEW TIME REQUIREMENT (5 TO 7 WEEKS) – PRIOR TO PS&E MEETING
UDOT STRUCTURES DESIGN AND DETAILING MANUAL GUIDELINES FOR STRUCTURAL DESIGN REVIEWS
Updated: 10/4/2012 Page 1-7
Complete Design Review and Oversight Review 1 to 2 Weeks
Address Comments by Structural Designer 1 to 2 Weeks
Complete verification of comment dispositions,
verify QC documentation is complete, and send
Structural Review Completion Form to UDOT by
Design Reviewer and Oversight Reviewer
1 Week
Submit PS&E documents to Project Team for
Review by Structural Designer 2 Weeks (required)
ADVERTISING (STAGE 5)
5S1 DELIVER FINAL STRUCTURE ACCEPTANCE
The structural designer addresses comments from the PS&E Meeting, prepares the Structural
Documentation Package, and submits the package to the UDOT Structures Construction Manager for
acceptance.
The UDOT Structures Construction Manager verifies completeness of package and provides Final
Structures Acceptance for advertising.
REVIEW TIME REQUIREMENT (3 TO 4 WEEKS) – PRIOR TO ADVERTISING
Address Comments by Structural Designer 1 to 2 Weeks
Review Structural Documentation Package by
UDOT and Provide Acceptance for Advertising 2 Weeks (required)