SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
1
BIM PROJECT EXECUTION PLAN
FOR
BIMedical Providers Group
DEVELOPED BY
SOLVE Construction & Management
This BIM Project Execution Plan (PxP) was developed by Solve Design and
Construction to create an overall vision along with the implementation details of the
construction of CON 453 Healthcare clinic to be built in Northwest Corner Lot at
intersection of West University Drive and South Ash Avenue, Tempe, Arizona. This
proposed Health care facility, project number 1, will be a 27,600 square foot projected
area and 17- 32 foot high, two story building, and has prevision to begin the
construction in January of 2015, and to be completed in 24 months.
Team Members: Artur Feitosa
Fabricio Barbosa
Marco Torres
Priscilla Basto
December - 2014
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
2
BIM PROJECT EXECUTION PLAN
FOR
BIMedical Providers Group
DEVELOPED BY
SOLVE Design & Construction
TABLE OF CONTENTS
SECTION A: BIM PROJECT EXECUTION PLAN OVERVIEW ..................................................................................... 4
SECTION B: PROJECT INFORMATION ....................................................................................................................... 5
SECTION C: KEY PROJECT CONTACTS .................................................................................................................... 7
SECTION D: PROJECT GOALS / BIM USES ............................................................................................................... 8
1. Major BIM Goals / Objectives: ........................................................................................................................... 8
2. BIM USE ANALYSIS WORKSHEET: ATTACHMENT 1 .................................................................................................. 8
3. BIM Uses: ......................................................................................................................................................... 9
SECTION E: ORGANIZATIONAL ROLES / STAFFING .............................................................................................. 10
1. BIM Roles and Responsibilities: ...................................................................................................................... 10
2. BIM Use Staffing: ............................................................................................................................................ 10
SECTION F: BIM PROCESS DESIGN ........................................................................................................................ 11
1. Level One Process Overview Map: Attachment 2 ........................................................................................... 11
2. List of Level Two – Detailed BIM Use Process Map(s): Attachment 3 ............................................................ 11
SECTION G: BIM INFORMATION EXCHANGES ........................................................................................................ 12
1. List of Information Exchange Worksheet(s): Attachment 4 ............................................................................. 12
2. Model Definition Worksheet: Attachment 5 ..................................................................................................... 12
SECTION H: BIM AND FACILITY DATA REQUIREMENTS ........................................................................................ 13
SECTION I: COLLABORATION PROCEDURES ......................................................................................................... 14
1. Collaboration Strategy:.................................................................................................................................... 14
2. Meeting Procedures: ....................................................................................................................................... 14
3. Model Delivery Schedule of Information Exchange for Submission and Approval: ......................................... 15
4. Interactive Workspace..................................................................................................................................... 16
5. Electronic Communication Procedures ........................................................................................................... 16
SECTION J: QUALITY CONTROL ............................................................................................................................... 18
1. OVERALL STRATEGY FOR QUALITY CONTROL: ....................................................................................... 18
2. QUALITY CONTROL CHECKS: ..................................................................................................................... 18
3. Model Accuracy and Tolerances: .................................................................................................................... 19
SECTION K: TECHNOLOGICAL INFRASTRUCTURE NEEDS .................................................................................. 20
1. Software: ......................................................................................................................................................... 20
2. Computers / Hardware: ................................................................................................................................... 20
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
3
3. Modeling Content and Reference Information ................................................................................................. 21
SECTION L: MODEL STRUCTURE ............................................................................................................................ 22
1. File Naming Structure: .................................................................................................................................... 22
2. Model Structure: .............................................................................................................................................. 22
3. Measurement and Coordinate Systems: ......................................................................................................... 24
4. BIM and CAD Standards: ................................................................................................................................ 24
SECTION M: PROJECT DELIVERABLES ................................................................................................................... 24
SECTION O: ATTACHMENTS..................................................................................................................................... 26
1. BIM USE SELECTION WORKSHEET [FROM SECTION D] .......................................................................... 26
2. LEVEL 1 PROCESS OVERVIEW MAP [FROM SECTION F] ......................................................................... 27
................................................................................................................................................................................. 27
3. LEVEL 2 DETAILED BIM USE PROCESS MAP(S) [FROM SECTION F] ...................................................... 28
4. INFORMATION EXCHANGE REQUIREMENT WORKSHEET(S) [FROM SECTION G] ............................... 38
5. MODEL DEFINITION WORKSHEET [FROM SECTION G] ............................................................................ 41
TABLE OF FIGURES
FIGURE 1 - FIRST FLOOR ................................................................................................................... 23
FIGURE 2 - SECOND FLOOR ............................................................................................................... 23
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
4
SECTION A: BIM PROJECT EXECUTION PLAN OVERVIEW
To successfully implement Building Information Modeling (BIM) on a project, the project
team has developed this detailed BIM Project Execution Plan. The BIM Project
Execution Plan defines uses for BIM on the project (e.g. design authoring, cost
estimating, and design coordination), along with a detailed design of the process for
executing BIM throughout the project lifecycle.
The mission of this BIM Project Execution Plan is primarily to outline the implementation
of the BIM uses that are of high interest to BIMedical Providers Group (the owner) such
as:
● Design/Constructability Reviews;
● Cost Estimation;
● 3D Coordination;
● Site Utilization Planning;
● Phase Planning;
● Record Modeling.
We will also present the BIM uses that SOLVE Design & Construction has identified as
potential BIM uses that would bring value to this and future similar projects, which
include:
● Design Authoring;
● Lighting Analysis;
● Digital Fabrication;
● Energy Analysis.
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
5
SECTION B: PROJECT INFORMATION
i. Project Owner: BIMedical Providers Group (BPG);
ii. Project Name: CON 453 Healthcare Clinic;
iii. Project Location and Address: NW. Corner lot at intersection of W. University
Dr. and S. Ash Ave., Tempe, AZ;
iv. Contract Type / Delivery Method: Design-Bid-Build;
v. Brief Project Description: A 27,600 square foot projected area and 17- 32 foot
high, two story Healthcare facility in Tempe, Arizona, with medical and dental
offices;
vi. Additional Project Information: The BIM uses required for this project are:
Design/Constructability Reviews, Cost Estimation, 3D Coordination, Site
Utilization Planning, Phase Planning, and Record Modeling. The suggested BIM
Uses are: Design Authoring, Lighting Analysis, Digital Fabrication, and Energy
Analysis.
vii. Project Numbers:
PROJECT INFORMATION NUMBER
CONTRACT NUMBER: 453-2014
TASK ORDER: 001
PROJECT NUMBER: 001
BUILDING NUMBER 001
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
6
viii. Project Schedule / Phases / Milestones:
PROJECT PHASE / MILESTONE
ESTIMATED START DATE ESTIMATED COMPLETION DATE
PROJECT STAKEHOLDERS INVOLVED
FEASIBILITY STUDIES 01/06/14 01/07/14 BPG, DesignCo
PRELIMINARY PLANNING 01/07/14 15/07/14 BPG, DesignCo
PROGRAMMING 15/07/14 01/08/14 BPG, DesignCo
DESIGN DOCUMENTS 01/08/14 01/09/14 BPG, DesignCo
STRUCTURAL ANALYSIS AND DESIGN 01/09/14 01/10/14 BPG, DesignCo,
CONSTRUCTION DOCUMENTS 01/10/14 01/11/14 BPG, DesignCo
COST ESTIMATION 01/11/14 10/11/14 BPG, DesignCo
BIDDING 10/11/14 10/12/14 BPG, DesignCo
NOTICE TO PROCEED 10/12/14 10/12/14 BPG, DesignCo, SOLVE
SITE UTILIZATION PLANNING
15/12/14 20/12/14 BPG, DesignCo, SOLVE
MECHANICAL CLASH DETECTION 15/12/14 20/12/14 BPG, DesignCo, SOLVE
CREW MOBILIZATION 20/12/14 01/01/15 BPG, DesignCo, SOLVE
CONSTRUCTION 01/01/15 01/01/17 BPG, DesignCo, SOLVE
RECORD MODELING 01/01/17 31/01/2017 BPG, DesignCo, SOLVE
ENERGY ANALYSIS 31/02/2017 31/03/2017 BPG, DesignCo, SOLVE
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
7
SECTION C: KEY PROJECT CONTACTS
ROLE ORGANIZATION CONTACT NAME LOCATION E-MAIL PHONE
Project Manager Solve Design and Construction Fabricio Barbosa
701 E Apache Blvd, Tempe-AZ Room 14
solve.asu@gmail.com (219)321-2714
BIM Manager Solve Design and Construction Artur Feitosa
701 E Apache Blvd, Tempe-AZ Room 13
solve.asu@gmail.com (480)738-6488
Structural Chief Engineer
The Terminal Engineering Viktor Navorski
101 Jamaica, New York-NY
victor.nav@terminal.com (646)287-3277
Energy and Lighting Chief Engineer
Dilbert Electrical Engineering Scott Adams
7501 Rural Rd, Tempe-AZ
scottadams@dilbert.com (215)322-2414
Architectural Leader How I Drew your House Ted Mosby
150 W. 85th Street, New York-NY
tedmosby@hidyh.com (260)838-6458
Contractor Representative
Solve Design and Construction Marco Torres
701 E Apache Blvd, Tempe-AZ Room 12
solve.asu@gmail.com (646)287-3277
Digital Fabrication Manager
Pixar Digital Fabrication Walt Disney
05 Lake Buena Vista,
Orlando-FL walt.pixar@digitalf.com (714)347-6539
Mechanical Sub Representative Stark Corporation Tony Stark
10880 Malibu Point, Malibu-CA
tonystark@stark.com (717)287-3374
Electrical Sub Representative Pikachu SA Ash Ketchum
543 Pokemon Street,
Pallet Town-NC ash@pikachu.com (123)356-5673
Plumbing Sub Representative Mario Brothers SA Mario Risotto
105 Yoshi Avenue, Italy Town-PA
mario@mariobro.com (223)321-2414
Legal Issues Manager Pearson Specter Harvey Specter
601 E 59th Street, New York-NY
harvey@pearsonspecter.com (480)772-5373
Facility Manager
Batman Butler SA
Alfred Pennyworth 1007 Mountain
Drive, Gothan-MI
alfred_pen@butler.com (347)652-7170
Site Logistics Coordinator
Solve Design and Construction Bob the Builder
701 E Apache Blvd, Tempe-AZ Room 10
solve.asu@gmail.com (460)345-5673
Materials Tracking Manager Agent 47 Tracking Hitman Codebar
007 Secret Street, Unknown City-NY
hitman.code@agent47.com (223)345-2774
Cost Estimation
Manager
Solve Design and Construction Priscilla Basto
701 E Apache Blvd, Tempe-AZ Room 13
solve.asu@gmail.com (646)287-3277
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
8
SECTION D: PROJECT GOALS / BIM USES
1. Major BIM Goals / Objectives:
PRIORIT (HIGH/ MED/
LOW) GOAL DESCRIPTION POTENTIAL BIM USES
Med Increase Field Productivity Design Reviews, 3D Coordination
Low Increase Sustainable Applications for the Project Energy Analysis
High Early Clash Detection 3D Coordination
Med Track Progress During Construction 4D Modeling
Med Increase Effectiveness of Site Utilization Site Utilization Planning
High Identify Cost Associated with Design Modifications Cost Estimation
High Incorporate Data for Future Facilities Record Modeling, Digital Fabrication
High Quickly Assess Design Performance Design Review, 3D Coordination
Med Increase Effectiveness of Building Performance Building System Analysis
High Accurate 3D Record Model for FM Team Record Model, 3D Coordination
Low Increase Energy Effectiveness of the Facility Energy Analysis, Lighting Analysis
Med Decrease Overall Maintenance Costs Record Modeling
2. BIM USE ANALYSIS WORKSHEET: ATTACHMENT 1
The BIM Use Analysis Worksheet is attached at Section O of this Report as Attachment 1.
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
9
3. BIM Uses:
X PLAN X DESIGN X CONSTRUCT X OPERATE
PROGRAMMING X DESIGN AUTHORING X SITE UTILIZATION PLANNING BUILDING MAINTENANCE
SCHEDULING
SITE ANALYSIS X DESIGN REVIEWS CONSTRUCTION SYSTEM DESIGN X ENERGY ANALYSIS
X 3D COORDINATION X 3D COORDINATION ASSET MANAGEMENT
STRUCTURAL ANALYSIS X DIGITAL FABRICATION SPACE MANAGEMENT / TRACKING
X LIGHTING ANALYSIS 3D CONTROL AND PLANNING DISASTER PLANNING
ENERGY ANALYSIS RECORD MODELING X RECORD MODELING
MECHANICAL ANALYSIS
OTHER ENG. ANALYSIS
SUSTAINABLITY (LEED) EVALUATION
CODE VALIDATION
PHASE PLANNING (4D MODELING) PHASE PLANNING
(4D MODELING) X PHASE PLANNING (4D MODELING) PHASE PLANNING
(4D MODELING)
COST ESTIMATION COST ESTIMATION X COST ESTIMATION COST ESTIMATION
EXISTING CONDITIONS MODELING EXISTING CONDITIONS
MODELING EXISTING CONDITIONS MODELING EXISTING CONDITIONS
MODELING
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
10
SECTION E: ORGANIZATIONAL ROLES / STAFFING
1. BIM Roles and Responsibilities:
BIM ROLE RESPONSIBILITIES
BIM Manager Manage the process of virtually constructing the facility and documenting the design contract documents accurately. In addition, he leads the BIM coordination meetings.
Client Facing Staff & Business Developers
Have a great experience with BIM in order to speak the language, show the vision of the company, make achievable promises and establish a great relationships\ with the client.
BIM Legal Team Update contracts and create contents that meet the BIM scope.
Initial Design Team Work in the first stages, making design collaboration meetings with the client to initiate the design within a BIM environment.
Project Production Staff
Performed by the BIM technicians who detail and materialize the design ideas produced by the Initial Design into the BIM models, designs, engineering, and construction documentation. They are BIM software modeling expert with solid understanding of their specific design discipline.
Estimators Adjust the BIM Models for the quantity take-off and the cost analysis and calculate the costs to obtain the cost estimation.
2. BIM Use Staffing:
BIM USE ORGANIZATION NUMBER OF
TOTAL STAFF FOR BIM USE
ESTIMATED WORKER HOURS LOCATION(S) LEAD CONTACT
Design Reviews How I Drew Your House 4 40 hours 150 W. 85th Street, New York-NY Ted Mosby
Cost Estimating Solve Engineering 3 20 hours 701 E Apache Blvd, Tempe-AZ Priscilla Basto
3D coordination How I Drew Your House, Solve Engineering, The Terminal Engineering
5 40 hours
150 W. 85th Street, New York-NY / 701 E
Apache Blvd, Tempe-AZ / 101 Jamaica, New York-NY
Ted Mosby, Priscilla Basto, Viktor Navorski
Site Utilization Planning Solve Engineering 2 20 hours
701 E Apache Blvd,
Tempe-AZ Fabricio Barbosa
Phase Planning Solve Engineering 3 30 hours 701 E Apache Blvd, Tempe-AZ Artur Feitosa
Record Modeling How I Drew Your House / Solve Engineering 4 40 hours
150 W. 85th Street, New York-NY /
701 E Apache Blvd, Tempe-AZ
Ted Mosby / Artur Feitosa
Design Authoring How I Drew Your House 5 50 hours
701 E Apache Blvd, Tempe-AZ Marco Torres
Lighting Analysis
The Terminal Engineering /
Dilbert Electrical Engineering
6 36 hours
101 Jamaica, New York-NY /
7501 Rural Rd, Tempe-AZ
Viktor Navorski / Scott Adams
Digital Fabrication Pixar Digital Fabrication 3 25 hours 701 E Apache Blvd, Tempe-AZ Walt Disney
Energy Analysis BIMedical Providers
Group 2 20 hours 701 E Apache Blvd,
Tempe-AZ Doctor House
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
11
SECTION F: BIM PROCESS DESIGN
1. Level One Process Overview Map: Attachment 2
The Level One Process Overview Map is attached at Section O of this Report as
Attachment 2.
2. List of Level Two – Detailed BIM Use Process Map(s): Attachment 3
The Detailed BIM Use Process Maps of the BIM Uses listed below are attached at
Section O of this Report as Attachment 3.
a. Design/Constructability Reviews
b. Cost Estimation
c. 3D Coordination
d. Site Utilization Planning
e. Phase Planning
f. Record Modeling
g. Design Authoring
h. Lighting Analysis
i. Digital Fabrication
j. Energy Analysis
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
12
SECTION G: BIM INFORMATION EXCHANGES
1. List of Information Exchange Worksheet(s): Attachment 4
The List of Information Exchange Worksheet is attached at Section O of this Report as
Attachment 4.
a. Design/Constructability Reviews
b. Cost Estimation
c. 3D Coordination
d. Site Utilization Planning
e. Phase Planning
f. Record Modeling
g. Design Authoring
h. Lighting Analysis
i. Digital Fabrication
j. Energy Analysis
2. Model Definition Worksheet: Attachment 5
The Model Definition Worksheet is attached at Section O of this Report as Attachment
5.
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
13
SECTION H: BIM AND FACILITY DATA REQUIREMENTS
For this project several BIM uses were previously listed by the owner, as show at
section A of this BIM Project Execution Plan. The BIMedical Providers Group will build a
new health-care clinic in Tempe, AZ, and they are particularly interested in investing
resources on planning this facility because they intent to eventually create additional,
similar health-care facilities throughout the Phoenix metropolitan area. The owner has
specifically identified several BIM uses – Design/Constructability Reviews, Cost
Estimation, 3D Coordination, Site Utilization Planning, Phase Planning and Record
Modeling – and also required Solve Design & Construction to define some additional
BIM uses that would add value for this particular project.
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
14
SECTION I: COLLABORATION PROCEDURES
1. Collaboration Strategy:
For a full coordination and collaboration of the team, the communication to the
development of the project will occur through weekly in-person meetings at Wednesday
afternoons. In addition, the company’s members will maintain a virtual communication
by Google Hangout and Gmail.
The project data and information sharing will be established using Google Drive online
storage. All members will have access to the company’s Google account and they will
update the project files periodically.
In case of disagreement between team members, all members should gather to analyze
each side and find a solution that better achieve the project goals. If some member
starts to have lack of performance, participation, or attendance, the rest of the team will
talk with him/her to understand the situation. Thus, a way to compensate this will be
established.
2. Meeting Procedures:
MEETING TYPE PROJECT STAGE FREQUENCY PARTICIPANTS LOCATION
BIM REQUIREMENTS KICK-OFF Planning One Time Solve Engineering and stakeholders
Villas at Vista Front Desk - 701 E Apache
Blvd. Tempe, AZ.
BIM EXECUTION PLAN DEMONSTRATION
Planning
Monthly Solve Engineering and stakeholders
Villas at Vista Front Desk - 701 E Apache
Blvd. Tempe, AZ.
DESIGN COORDINATION Construction Weekly or as-needed Solve Engineering and
stakeholders
Villas at Vista Front Desk - 701 E Apache
Blvd. Tempe, AZ.
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
15
MEETING TYPE PROJECT STAGE FREQUENCY PARTICIPANTS LOCATION
CONSTRUCTION OVER-THE-SHOULDER PROGRESS REVIEWS Construction Weekly or as-needed
Solve Engineering and stakeholders
Villas at Vista Front Desk - 701 E Apache
Blvd. Tempe, AZ.
ANY OTHER BIM MEETINGS THAT OCCURS WITH MULTIPLE
PARTIES Any Stage As-needed Solve Engineering and
stakeholders
Villas at Vista Front Desk - 701 E Apache
Blvd. Tempe, AZ.
3. Model Delivery Schedule of Information Exchange for Submission
and Approval:
Below are some information exchanges that are going to be handled within Google
Drive between project team members and stakeholders. The most common software
used in this project are listed below:
● Revit 2014 (Design Build Suite - Autodesk);
● Navisworks Manage 2014 (Autodesk);
● Sketch UP Make 2014 (Google);
● Bluebeam Revu (Bluebeam Software);
● etc.
INFORMATION EXCHANGE
FILE SENDER
FILE RECEIVER
ONE-TIME or FREQUENCY
DUE DATE or START DATE
MODEL FILE
MODEL SOFTWARE
NATIVE FILE TYPE
FILE EXCHANGE
TYPE
Design Exchange
Architect (Ted Mosby)
Google Drive (stakeholders)
One Time or as-needed 01/09/14 Arch
Revit 2014 Bluebeam
Revu
.rvt .pdf
.rvt
.ifc .pdf
3D Coordination models
Solve Engineering
Google Drive (stakeholders)
Weekly or as-needed 20/12/14 Constr
Navisworks Manage
2014 Bluebeam
Revu
.nwd .pdf
.nwd .ifc .rvt
Fabrication Coordination
Model
Mechanical Engineer
Google Drive (stakeholders)
Weekly or as-needed 20/12/14 Constr
Revit 2014 Bluebeam
Revu
.rvt .pdf
.rvt
.ifc .pdf
Design Intent Models
Architect (Ted Mosby)
Google Drive (stakeholders)
Weekly 01/11/14 Design Revit 2014 Bluebeam
Revu
.rvt .pdf
.rvt
.ifc .pdf
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
16
4. Interactive Workspace The headquarter of Solve Design & Construction is located at 701 E Apache Blvd.,
Tempe, AZ. The initial phases of planning and design of the facility will be executed at
this location, as well as the regular meetings with the other parties involved in the
project. All the organizations involved in the project, such as the Design Company –How
I Drew Your House, the Engineering Company –The Terminal Engineering, and legal
Issues Firm –Pearson Specter, have also their own facilities. Solve Design &
Construction will also have a temporary facility installed at the construction site to
facilitate a proper execution of the BIM uses during construction phases.
5. Electronic Communication Procedures All electronic communication is going to be performed through Google Drive and Google
Hangout. The email of the company has enough capacity to store all data required for
this project. The file location and file structure name for our project files are defined at
the following table.
FILE LOCATION FILE STRUCTURE / NAME FILE TYPE PASSWORD PROTECT
FILE MAINTAINER
UPDATED
Google Drive server PROJECT FOLDER FOLDER YES Solve Engineering
ONCE
Google Drive server>PROJECT FOLDER
CONSTRUCTION_DOCUMENTS FOLDER
FOLDER No Solve Engineering
ONCE
Google Drive server>PROJECT FOLDER>CONSTRUCTION_DOCUMENTS
ARCH FOLDER FOLDER No Solve Engineering
ONCE
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
17
FILE LOCATION FILE STRUCTURE / NAME FILE TYPE PASSWORD PROTECT
FILE MAINTAINER
UPDATED
Google Drive server>PROJECT FOLDER>CONSTRUCTION_DOCUMENTS
MECH FOLDER FOLDER No Solve Engineering
ONCE
Google Drive server>PROJECT FOLDER>CONSTRUCTION_DOCUMENTS
STRUCT FOLDER FOLDER No Solve Engineering
ONCE
Google Drive server>PROJECT FOLDER>CONSTRUCTION_DOCUMENTS>(ARCH/MECH/PROJECT FILES)
PROJECT FILES
.NWD
.RVT
.SKP
No Solve Engineering
DAILY
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
18
SECTION J: QUALITY CONTROL
1. OVERALL STRATEGY FOR QUALITY CONTROL:
The quality inspections will be implemented during the execution of each activity, during
the equipment and material delivery, and by the development of a virtual mock up. For
each activity, inspection will occur at the beginning of the work, permitting the early
identification of issues. In the case of equipment and material delivery, the inspection
will be executed when they arrive in the construction site, identifying non-conformity
before they be used, such as defects in equipment, broken material or wrong material
model. Finally, the virtual mock up permits an early agreement between the project
stakeholders about the design intent, function and look.
2. QUALITY CONTROL CHECKS:
The following checks should be performed to assure quality.
CHECKS DEFINITION RESPONSIBLE PARTY
SOFTWARE PROGRAM(S) FREQUENCY
VISUAL CHECK Ensure there are no unintended model components and the design intent has been followed
Contractor NAVISWORKS
MANAGE Sampling Prior to
Model Delivery
INTERFERENCE CHECK Detect problems in the model where two building components are clashing including soft and hard
BIM Manager NAVISWORKS
MANAGE Prior to Model
Delivery
STANDARDS CHECK Ensure that the BIM and AEC CADD Standard have been followed (fonts, dimensions, line styles, levels/layers, etc)
BIM techinicias
NAVISWORKS MANAGE
REVIT
Prior to Model
Delivery
MODEL INTEGRITY CHECKS
Describe the QC validation process used to ensure that the Project Facility Data set has no undefined, incorrectly defined or duplicated elements and the reporting process on non-compliant elements and corrective action plans
BIM Manager NAVISWORKS
MANAGE THROUGHOUT DEVELOPMENT
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
19
3. Model Accuracy and Tolerances:
The accuracy of the models is going to be the greatest degree of accuracy possible.
Tolerances are going to be based on team expertise, experience, and field
observations. Also, surveys and construction drawings are going to be used as
reference. Note: Conditions shall be verified by the contractor in-loco prior to fabrication.
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
20
SECTION K: TECHNOLOGICAL INFRASTRUCTURE NEEDS
1. Software:
BIM USE DISCIPLINE (if applicable) SOFTWARE VERSION
❏ Design/Constructability Reviews
All Disciplines Bluebeam Revu
CAD, Navisworks 2014,
Manage - 2014
❏ Phase Planning Construction Revit, MS Project, Navisworks
2014, 2014, Manage - 2014
❏ Cost Estimation ❏ Digital Fabrication ❏ Record Modeling ❏ Design Authoring ❏ Lighting Analysis ❏ Energy Analysis
All Disciplines Revit 2014
❏ Site Utilization Planning
Construction Google Sketch UP Make - 2014
❏ 3D Coordination
Construction Navisworks Manage - 2014
2. Computers / Hardware: Solve Design & Construction members shall utilize computer hardware that is sufficient
to efficiently handle single model files in Revit 2014 and Navisworks Manage 2014, the
following hardware was chosen to perform the job.
BIM USE HARDWARE OWNER OF HARDWARE SPECIFICATIONS
❏ Design/Constructability Reviews
❏ Design Authoring ❏ Cost Estimation ❏ 3D Coordination ❏ Site Utilization Planning ❏ Phase Planning ❏ Record Modeling ❏ Lighting Analysis ❏ Digital Fabrication ❏ Energy Analysis
Lenovo Yoga 2 Pro-
Windows 8.1 (2013) 64bits -
Computer System
Solve Design & Construction
Intel(R) Core(™) i7-4500U CPU @ 1.80GHz 2.39 GHz., 8.00GB, Intel(R) HD Graphics Family (1792MB), Intel(R) Wireless-N 7260.
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
21
3. Modeling Content and Reference Information
Identify items such as families, work spaces, and databases.
BIM USE DISCIPLINE (if applicable)
MODELING CONTENT / REFERENCE INFORMATION
Design/Constructability Reviews All Disciplines N/A
Phase Planning Construction Crew and Productivity information; Lead
Times and Scheduling Patterns
Cost Estimation All Disciplines Cost Reports from previous works; Cost Data Base
Digital Fabrication All Disciplines N/A
Record Modeling All Disciplines Equipment Information; Project Submittal Information
Design Authoring All Disciplines Parametric Modeling Content
Lighting Analysis All Disciplines Construction Type library; Energy
Takeoff; Weather Data; Soil Data; Solar Data
Energy Analysis All Disciplines Sensor Data; Performance targets; Performance Costs, Weather Data.
Site Utilization Planning Construction Schedule; Existing Site Conditions
Information; Construction Equipment libraries
3D Coordination Construction Company Implementation Standards; Contract Requirements; Information
Exchange Requirements
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
22
SECTION L: MODEL STRUCTURE
1. File Naming Structure: The following table shows how our files shall be formatted:
FILE NAMES FOR MODELS SHOULD BE FORMATTED AS:
ARCHITECTURAL MODEL ARCH-001-BLDG001.RVT
CIVIL MODEL CIVIL-001-BLDG001.RVT
MECHANICAL MODEL MECH-001-BLDG001.RVT
PLUMBING MODEL PLUMB-001-BLDG001.RVT
ELECTRICAL MODEL ELEC-001-BLDG001.RVT
STRUCTURAL MODEL STRUCT-001-BLDG001.RVT
ENERGY MODEL ENERGY-001-BLDG001.RVT
CONSTRUCTION MODEL CONST-001-BLDG001.RVT
COORDINATION MODEL COORD-001-BLDG001.RVT
2. Model Structure:
Since we just have one simple building, it is going to be separated by floors (First Floor, Second
Floor, Roof - Main, Roof - High, and TOF Footing) and disciplines (architecture; mechanical,
electrical and plumbing; structural). Also, zones and areas might be specified during the BIM
project execution planning.
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
23
Figure 1 - First Floor
Figure 2 - Second Floor
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
24
3. Measurement and Coordinate Systems:
Our standard measurement system is the Imperial and our referenced coordinated
system is the Cartesian.
4. BIM and CAD Standards:
Identify items such as the BIM and CAD standards, content reference information, and
the version of IFC, etc.
Standard Version BIM Uses Applicable Organizations Applicable
National BIM Standard Version 2.0 ALL Solve Design & Construction
IFC VERSION/MVD(s) Record Modeling
As-Built Modeling
Solve Design & Construction
National CAD Standard Version 5.0 Drawing Production Solve Design & Construction
COBie Version 2.4 Record Modeling Solve Design & Construction
SECTION M: PROJECT DELIVERABLES
In this section, the BIM deliverables for the project and the format in which the
information will be delivered are shown.
BIM SUBMITTAL ITEM STAGE APPROXIMATE DUE DATE FORMAT NOTES
STRUCT-01-BL001.rvt Construction Documents
01/11/14 Revit (.rvt)
MEP-01-BL001.rvt Construction Documents
01/11/14 Revit (.rvt)
ARCH-01-BL001.rvt Construction Documents
01/11/14 Revit (.rvt)
SiteUtilizationPlanning_BL001.skp Construction 20/12/14 SketchUP(.skp)
3D_Coordination_BL001.nwd Construction 20/12/14 Naviswork Manage 2014 (.nwd)
Cost_Estimation_BL001.xls Design 10/11/14 Microsoft Excel (.xls)
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
25
BIM SUBMITTAL ITEM STAGE APPROXIMATE DUE DATE FORMAT NOTES
Lighting _Analysis_01_BL001.pdf Design 01/10/14 Bluebeam Revu (.pdf)
Lighting _Analysis_02_BL001.pdf Design 01/10/14 Bluebeam Revu (.pdf)
Lighting _Analysis_03_BL001.pdf Design 01/10/14 Bluebeam Revu (.pdf)
Lighting_Analysis_04_BL001.pdf Design 01/10/14 Bluebeam Revu (.pdf)
Record_Model_BL001.rvt Close out 31/01/2017 Revit (.rvt)
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
26
SECTION O: ATTACHMENTS
1. BIM USE SELECTION WORKSHEET [FROM SECTION D]
High / Med / Low
High / Med / Low
YES / NO / MAYBE
Res
ourc
es
Com
pete
ncy
Exp
erie
nce
Design/Constructability Reviews MED Architect MED 2 2 3 YesFacility Manager HIGH 2 2 2Contractor HIGH 1 3 2 Need training on latest software
Cost Estimation (Planning) MED Engineer LOW 1 2 2 Requires training and basic software Overall Cost Estimation Yes
Cost Estimation (Construction) HIGH Contractor HIGH 3 2 2 Yes
3D Coordination (Design) HIGH Architect HIGH 3 3 2 YesEngineer HIGH 2 2 2 Coordination software required
3D Coordination (Construction) HIGH Architect MED 3 2 2 YesContractor HIGH 2 3 2Subcontractor HIGH 1 2 2 Need training on latest software Modeling learning curve possible
Site Utilization Planning MED Contractor HIGH 3 2 3 Yes
Phase Planning (4D Modeling) HIGH Contractor HIGH 2 2 2 Use for Phasing & Construction Yes
Record Modeling HIGH Contractor LOW 2 2 2 YesArchitect MED 2 3 3Facility Manager HIGH 2 2 3
Building Maintenance Schedule LOW Facility Manager LOW 1 2 1 Large learning curve No
Design Authoring HIGH Architect HIGH 3 2 3 YesEngineer HIGH 2 3 2
Engineering Analysis HIGH Engineer MED 2 3 2 Yes
Digital Fabrication HIGH Digital Fabricator HIGH 3 2 3 Yes
Sustainability (LEED) Analysis MED Architect MED 1 2 2 Requires training and software NoEngineer LOW 2 1 2
Building System Analysis MED Facility Manager MED 2 2 3 Yes
Disaster Planning LOW Engineer LOW 2 2 1 No
Proceed with Use
Scale 1-3 (1 = Low)
Responsible Party
Additional Resources / Competencies Required to
Implement
High value to owner due to intention of future similar facility construction
Local is not susceptible to force majeur disaster
BIM Use* NotesCapability
Rating
Value to Resp Party
Value to Project
High value to owner due to intention of future similar facility construction
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
27
2. LEVEL 1 PROCESS OVERVIEW MAP [FROM SECTION F]
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
28
3. LEVEL 2 DETAILED BIM USE PROCESS MAP(S) [FROM SECTION F]
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
29
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
30
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
31
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
32
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
33
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
34
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
35
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
36
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
37
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
38
4. INFORMATION EXCHANGE REQUIREMENT WORKSHEET(S) [FROM SECTION G]
InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes Info Resp Party Notes Info Resp Party Notes Info Resp Party Notes Info Resp Party Notes
0101 1001 10 10 Standard Foundations A-300 Eng A-300 Eng A-300 Eng B-200 Eng B-200 Eng A-300 Eng N/A A-350 Eng A-350 Eng A-500 CM A-500 Owner01 10 20 Special Foundations A-300 Eng A-300 Eng A-300 Eng B-200 Eng B-200 Eng A-300 Eng N/A A-350 Eng A-350 Eng A-500 CM A-500 Owner01 2001 20 10 Walls for Subgrade Enclosures A-300 Eng A-200 Eng A-300 Eng B-200 Eng B-200 Eng N/A A-350 Eng A-350 Eng A-500 Owner01 4001 40 10 Standard Slabs-On-Grade A-300 Eng A-200 Eng A-300 Eng A-300 Eng B-200 Eng A-300 Eng N/A A-200 Eng A-350 Eng A-500 CM A-500 Owner01 40 20 Structural Slabs-On-Grade A-300 Eng A-300 Eng A-300 Eng A-300 Eng B-200 Eng A-300 Eng N/A A-200 Eng A-350 Eng A-500 CM A-500 Owner01 40 30 Slab Trenches C-100 Eng C-100 Eng C-100 Eng A-300 Eng B-200 Eng A-300 Eng N/A A-300 Eng B-200 Eng A-500 CM A-500 Owner01 40 40 Pits and Bases C-100 Eng C-100 Eng C-100 Eng A-300 Eng B-200 Eng A-300 Eng N/A A-300 Eng B-200 Eng A-500 CM A-500 Owner01 40 50 Slab-On-Grade Supplementary Components C-100 Eng C-100 Eng C-100 Eng A-300 Eng B-200 Eng A-300 Eng N/A A-300 Eng B-200 Eng A-500 CM A-500 Owner01 6001 60 10 Building Subdrainage A-400 Eng A-200 Eng A-300 Eng B-200 Eng C-100 Eng A-300 Eng A-400 N/A A-350 Eng A-500 CM A-500 Owner01 60 20 Off-Gassing Mitigation A-400 Eng A-200 Eng A-300 Eng B-200 Eng C-100 Eng A-300 Eng A-400 N/A A-350 Eng A-500 CM A-500 Owner01 9001 90 10 Substructure Excavation N/A C-300 Eng N/A C-200 Eng N/A C-100 Eng N/A A-350 Eng N/A C-100 CM B-200 Owner01 90 20 Construction Dewatering N/A C-300 Eng N/A C-200 Eng N/A C-100 Eng N/A A-350 Eng N/A C-100 CM B-200 Owner01 90 30 Excavation Support N/A C-200 Eng N/A C-200 Eng N/A C-100 Eng N/A A-400 Eng N/A C-100 CM B-200 Owner01 90 40 Soil Treatment N/A C-300 Eng N/A C-100 Eng N/A C-100 Eng N/A A-200 Eng N/A C-100 CM B-200 Owner0202 1002 10 10 Floor Construction B-200 Eng B-200 Eng A-350 Eng A-400 Eng B-200 Eng A-300 Eng N/A A-350 Contractor A-400 Eng A-400 CM A-500 Owner02 10 20 Roof Construction B-200 Eng B-300 Eng A-350 Eng A-400 Eng B-200 Eng A-300 Eng N/A A-300 Contractor A-400 Eng A-400 CM A-500 Owner02 10 30 Stairs A-400 Eng A-400 Eng A-350 Eng A-400 Eng B-200 Eng A-300 Eng N/A A-300 Contractor A-400 Eng A-400 CM A-500 Owner02 2002 20 10 Exterior Walls B-200 Eng A-500 Eng B-200 Arch A-300 Arch B-200 Eng A-400 Eng A-400 Dig Fab A-200 Contractor A-300 Arch A-500 CM A-500 Owner02 20 20 Exterior Windows B-200 Eng A-350 Eng B-200 Arch A-300 Arch B-200 Eng A-400 Eng A-350 Dig Fab A-200 Contractor A-300 Arch A-500 CM A-500 Owner02 20 50 Exterior Doors and Grilles B-200 Eng A-350 Eng B-200 Arch A-300 Arch B-200 Eng A-400 Eng A-350 Dig Fab A-200 Contractor A-300 Arch A-500 CM A-500 Owner02 20 70 Exterior Louvers and Vents B-200 Eng B-200 Eng B-200 Arch A-300 Arch B-200 Eng A-400 Eng A-350 Dig Fab A-200 Contractor A-300 Arch A-500 CM A-500 Owner02 20 80 Exterior Wall Appurtenances B-200 Eng A-200 Eng B-200 Arch A-300 Arch B-200 Eng A-400 Eng A-350 Dig Fab A-200 Contractor A-300 Arch A-500 CM A-500 Owner02 20 90 Exterior Wall Specialties B-200 Eng A-300 Eng B-200 Arch A-300 Arch B-200 Eng A-400 Eng A-350 Dig Fab A-200 Contractor A-300 Arch A-500 CM A-500 Owner02 3002 30 10 Roofing B-200 Eng B-200 Eng A-300 Arch A-400 Arch B-200 Eng A-400 Eng A-400 Dig Fab C-300 Contractor A-350 Arch A-500 CM A-500 Owner02 30 20 Roof Appurtenances B-200 Eng B-200 Eng B-200 Arch A-350 Arch B-200 Eng A-400 Eng A-350 Dig Fab C-300 Contractor A-300 Arch A-500 CM A-500 Owner02 30 40 Traffic Bearing Horizontal Enclosures B-200 Eng B-200 Eng B-200 Arch A-300 Arch B-200 Eng A-400 Eng A-350 Dig Fab C-300 Contractor A-300 Arch A-500 CM A-500 Owner02 30 60 Horizontal Openings B-200 Eng B-200 Eng B-200 Arch A-300 Arch B-200 Eng A-400 Eng A-350 Dig Fab C-300 Contractor A-300 Arch A-500 CM A-500 Owner02 30 80 Overhead Exterior Enclosures B-200 Eng B-300 Eng B-200 Arch A-300 Arch B-200 Eng A-400 Eng A-350 Dig Fab C-300 Contractor A-300 Arch A-500 CM A-500 Owner0303 1003 10 10 Interior Partitions A-300 Eng A-500 Eng A-200 Arch A-350 Arch B-200 Eng A-400 Arch A-400 Dig Fab C-200 Contractor A-350 Arch A-400 CM A-500 Owner03 10 20 Interior Windows A-300 Eng A-300 Eng A-300 Arch A-350 Arch B-200 Eng A-400 Arch A-350 Dig Fab C-200 Contractor A-350 Arch A-400 CM A-500 Owner03 10 30 Interior Doors A-300 Eng A-300 Eng A-300 Arch A-350 Arch B-200 Eng A-400 Arch A-350 Dig Fab C-200 Contractor A-350 Arch A-400 CM A-500 Owner03 10 40 Interior Grilles and Gates A-300 Eng B-300 Eng A-300 Arch A-350 Arch B-200 Eng A-400 Arch N/A C-200 Contractor A-350 Arch A-400 CM A-500 Owner03 10 60 Raised Floor Construction A-300 Eng B-300 Eng A-300 Arch A-350 Arch B-200 Eng A-400 Arch N/A C-200 Contractor A-350 Arch A-400 CM A-500 Owner03 10 70 Suspended Ceiling Construction A-300 Eng A-300 Eng A-300 Arch A-350 Arch B-200 Eng A-400 Arch N/A C-200 Contractor A-350 Arch A-400 CM A-500 Owner03 10 90 Interior Specialties A-300 Eng B-300 Eng A-300 Arch A-300 Arch B-200 Eng A-400 Arch N/A C-200 Contractor A-350 Arch A-400 CM A-500 Owner03 2003 20 10 Wall Finishes A-300 Arch N/A Arch B-200 Arch A-300 Arch B-200 Arch A-400 Arch N/A A-200 Contractor A-350 Arch A-400 CM A-500 Owner03 20 20 Interior Fabrications A-300 Arch B-200 Arch B-200 Arch A-400 Arch A-300 Arch A-400 Arch N/A A-200 Contractor A-400 Arch A-400 CM A-500 Owner03 20 30 Flooring A-300 Arch N/A Arch B-200 Arch A-400 Arch B-200 Arch A-400 Arch N/A A-200 Contractor A-350 Arch A-400 CM A-500 Owner03 20 40 Stair Finishes A-300 Arch N/A Arch B-200 Arch A-350 Arch B-200 Arch A-400 Arch N/A A-200 Contractor A-350 Arch A-400 CM A-500 Owner03 20 50 Ceiling Finishes A-300 Arch N/A Arch B-200 Arch A-350 Arch B-200 Arch A-400 Arch N/A A-200 Contractor A-350 Arch A-400 CM A-500 Owner0404 1004 10 10 Vertical Conveying Systems N/A C-200 Eng N/A N/A N/A N/A N/A A-300 Contractor N/A N/A A-400 Owner04 10 30 Horizontal Conveying Systems N/A C-200 Eng N/A N/A N/A N/A N/A A-301 Contractor N/A N/A A-400 Owner04 10 50 Material Handling N/A N/A N/A N/A N/A N/A N/A A-302 Contractor N/A N/A A-400 Owner04 10 80 Operable Access Systems N/A N/A N/A N/A N/A N/A N/A A-303 Contractor N/A N/A A-400 Owner04 2004 20 10 Domestic Water Distribution A-400 Eng N/A A-350 Eng A-400 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner04 20 20 Sanitary Drainage A-400 Eng N/A A-350 Eng A-400 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner04 20 30 Building Support Plumbing Systems A-400 Eng N/A A-350 Eng A-350 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner04 20 50 General Service Compressed-Air A-400 Eng N/A A-350 Eng A-350 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner04 20 60 Process Support Plumbing Systems A-400 Eng N/A A-350 Eng A-350 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner
Building Systems Analysis
Design
OperationsFacility Manager/Owner
.RVTRevit 2014
Time of Exchange (SD, DD, CD, Construction) SD,DD
Engineering Analysis
Project Stage Design Design Design Design Operations
INTERIORS
SERVICES
Plumbing
Subgrade Enclosures
.PDF and .NWD
Contractor, Facility Manager
Revit 2014
Model Element Breakdown
SUBSTRUCTURE
Bluebeam Revu CAD 2014 and Navisworks
Manage 2014
Revit 2014Revit 2014
Application & Version
Revit 2014 Google SketchUP make-2014
Revit 2014, MS Project 2014, Navisworks
Manage 2014
Revit 2014Revit 2014 and Navisworks Manage
2014
Revit 2014 and Navisworks Manage 2014
Foundations
Slabs-On-Grade
Water and Gas Mitigation
Substructure Related Activities
Superstructure
Exterior Vertical Enclosers
Interior Finishes
Conveying
.SKP
ConstructionSD DD
.RVT
Architect
.RVT
Contractor Facility Manager/OwnerDigital Fabricator
.RVT
CD CDCM/Trade Contractors
.RVT and .NWD.RVT.RVT, .MSP and .NWD
CM/Trade Contractors
.RVT and .NWD
DD
Site Utilization Planning
CD
Phase Planning (4D Modeling)
DD
Construction
Record Modeling
Contractor
Digital Fabrication
ConstructionDesign Construction
Cost Estimation
CM/Trade Contractors
Design Reviews 3D Coordination
Construction
CDCM/Trade Contractors
3D Coordination
BIM Use Title
Design Authoring
Responsible Party (Information Receiver)Receiver File Format .RVT
SHELL
Exterior Horizontal Encloses
Interior Construction
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
39
04 3004 30 10 Facility Fuel Systems A-400 Eng N/A A-350 Eng A-400 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner04 30 20 Heating Systems A-400 Eng N/A A-350 Eng A-400 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner04 30 30 Cooling Systems A-400 Eng N/A A-350 Eng A-400 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner04 30 50 Facility HVAC Distribution Systems A-400 Eng N/A A-350 Eng A-400 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner04 30 60 Ventilation A-400 Eng C-300 Eng A-350 Eng A-400 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner04 30 70 Special Purpose HVAC Systems A-400 Eng N/A A-350 Eng A-400 Eng B-100 Eng A-400 Eng A-400 Dig Fab N/A A-400 Eng A-500 CM A-500 Owner04 4004 40 10 Fire Suppression A-400 Eng N/A A-350 Eng A-350 Eng B-100 Eng A-400 Eng N/A C-300 Contractor A-400 Eng A-500 CM A-500 Owner04 40 30 Fire Protection Specialties A-400 Eng N/A A-350 Eng A-350 Eng B-100 Eng A-400 Eng N/A A-200 Contractor A-400 Eng A-500 CM A-500 Owner04 5004 50 10 Facility Power Generation A-400 Eng A-400 Eng A-350 Eng A-350 Eng B-100 Eng A-400 Eng N/A A-350 Contractor A-400 Eng A-500 CM A-500 Owner04 50 20 Electrical Service and Distribution A-400 Eng A-500 Eng A-350 Eng A-400 Eng B-100 Eng A-400 Eng N/A A-350 Contractor A-400 Eng A-500 CM A-500 Owner04 50 30 General Purpose Electrical Power A-400 Eng A-500 Eng A-350 Eng A-400 Eng B-100 Eng A-400 Eng N/A A-350 Contractor A-400 Eng A-500 CM A-500 Owner04 50 40 Lighting A-400 Eng A-500 Eng A-350 Eng A-400 Eng B-100 Eng A-400 Eng N/A A-350 Contractor A-400 Eng A-500 CM A-500 Owner04 50 50 Miscellaneous Electrical Systems A-400 Eng A-400 Eng A-350 Eng A-350 Eng B-100 Eng A-400 Eng N/A A-350 Contractor A-400 Eng A-500 CM A-500 Owner04 6004 60 10 Data Communications A-400 Eng N/A A-350 Eng N/A B-100 Eng A-400 Eng N/A N/A A-400 Eng A-500 CM A-500 Owner04 60 20 Voice Communications A-400 Eng N/A A-350 Eng N/A B-100 Eng A-400 Eng N/A N/A A-400 Eng A-500 CM A-500 Owner04 60 30 Audio-Video Communication A-400 Eng N/A A-350 Eng N/A B-100 Eng A-400 Eng N/A N/A A-400 Eng A-500 CM A-500 Owner04 60 60 Distributed Communications and Monitoring A-400 Eng N/A A-350 Eng N/A B-100 Eng A-400 Eng N/A N/A A-400 Eng A-500 CM A-500 Owner04 60 90 Communications Supplementary Components A-400 Eng N/A A-350 Eng N/A B-100 Eng A-400 Eng N/A N/A A-400 Eng A-500 CM A-500 Owner04 7004 70 10 Access Control and Intrusion Detection A-400 Eng N/A A-350 Eng B-200 Eng B-100 Eng A-400 Eng N/A B-300 Contractor A-400 Eng A-500 CM A-500 Owner04 70 30 Electronic Surveillance A-400 Eng N/A A-350 Eng B-200 Eng B-100 Eng A-400 Eng N/A B-300 Contractor A-400 Eng A-500 CM A-500 Owner04 70 50 Detection and Alarm A-400 Eng N/A A-350 Eng B-200 Eng B-100 Eng A-400 Eng N/A B-300 Contractor A-400 Eng A-500 CM A-500 Owner04 70 70 Electronic Monitoring and Control A-400 Eng N/A A-350 Eng C-200 Eng B-100 Eng A-400 Eng N/A B-300 Contractor A-400 Eng A-500 CM A-500 Owner04 70 90 Electronic Safety and Security Supplementary Compoenents A-400 Eng N/A A-350 Eng C-200 Eng B-100 Eng A-400 Eng N/A B-300 Contractor A-400 Eng A-500 CM A-500 Owner04 8004 80 10 Integrated Automation Facility Controls A-400 Eng C-300 Eng A-350 Eng C-200 Eng B-100 Eng N/A B-300 Contractor A-400 A-400
0505 1005 10 10 Vehicle and Pedestrian Equipment C-100 Owner N/A B-200 Owner N/A B-100 Owner B-200 Owner N/A A-200 Contractor A-300 Owner A-300 Owner A-400 Owner05 10 30 Commercial Equipment C-100 Owner N/A B-200 Owner N/A B-100 Owner B-200 Owner N/A A-200 Contractor A-300 Owner A-300 Owner A-400 Owner05 10 40 Institutional Equipment C-100 Owner N/A B-200 Owner N/A B-100 Owner B-200 Owner N/A A-200 Contractor A-300 Owner A-300 Owner A-400 Owner05 10 60 Residential Equipment C-100 Owner N/A B-200 Owner N/A B-100 Owner B-200 Owner N/A A-200 Contractor A-300 Owner A-300 Owner A-400 Owner05 10 70 Entertainment and Recreational Equipment C-100 Owner N/A B-200 Owner N/A B-100 Owner B-200 Owner N/A A-200 Contractor A-300 Owner A-300 Owner A-400 Owner05 10 90 Other Equipment C-100 Owner N/A C-100 Owner N/A B-100 Owner B-200 Owner N/A A-200 Contractor A-300 Owner A-300 Owner A-400 Owner05 2005 20 10 Fixed Furnishings C-100 Owner C-300 Owner B-200 Arch B-300 Arch B-100 Owner B-200 Owner A-400 Dig Fab N/A A-200 Owner A-300 Owner A-500 Owner05 20 50 Movable Furnishings C-100 Owner N/A C-100 Arch B-300 Arch B-100 Owner B-200 Owner A-350 Dig Fab N/A A-200 Owner A-300 Owner A-500 Owner0606 1006 10 10 Integrated Construction N/A A-350 Eng N/A A-400 Eng N/A N/A N/A A-350 Contractor N/A N/A A-350 Owner06 10 20 Special Structures N/A A-300 Eng N/A A-400 Eng N/A N/A N/A A-350 Contractor N/A N/A A-350 Owner06 10 30 Special Function Construction N/A A-350 Eng N/A A-400 Eng N/A N/A N/A A-350 Contractor N/A N/A A-350 Owner06 10 50 Special Facility Components N/A A-200 Eng N/A A-400 Eng N/A N/A N/A A-350 Contractor N/A N/A A-350 Owner06 10 60 Athletic and Recreational Special Construction N/A A-200 Eng N/A A-350 Eng N/A N/A N/A A-200 Contractor N/A N/A A-350 Owner06 10 80 Special Instrumentation N/A C-200 Eng N/A A-200 Eng N/A N/A N/A A-200 Contractor N/A N/A A-350 Owner06 2006 20 10 Hazardous Materials Remediation N/A N/A N/A N/A N/A N/A N/A A-200 Contractor N/A N/A A-350 Owner06 3006 30 10 Structure Demolition N/A A-300 Eng N/A N/A N/A N/A N/A A-200 Contractor N/A N/A N/A Owner06 30 30 Selective Demolition N/A A-300 Eng N/A N/A N/A N/A N/A A-200 Contractor N/A N/A N/A Owner06 30 50 Structure Moving N/A A-300 Eng N/A N/A N/A N/A N/A A-200 Contractor N/A N/A N/A Owner0707 1007 10 10 Site Clearing C-100 CM N/A C-100 Arch N/A C-100 CM A-400 CM N/A A-400 Contractor B-200 Contractor C-200 CM N/A Owner07 10 20 Site Elements Demolition C-100 CM B-300 CM C-100 Arch N/A C-100 CM A-400 CM N/A A-400 Contractor B-200 Contractor C-200 CM N/A Owner07 10 30 Site Element Relocation C-100 CM C-200 CM C-100 Arch N/A C-100 CM A-400 CM N/A A-400 Contractor B-200 Contractor C-200 CM N/A Owner07 10 50 Site Remediation C-100 CM N/A C-100 Arch N/A C-100 CM A-400 CM N/A A-350 Contractor B-200 Contractor C-200 CM N/A Owner07 10 70 Site Earthwork C-100 CM B-300 CM C-100 Arch N/A C-100 CM A-400 CM N/A A-500 Contractor B-200 Contractor C-200 CM N/A Owner07 2007 20 10 Roadways C-100 CM C-100 CM B-100 Arch A-400 Eng B-100 CM A-400 CM N/A A-300 Contractor B-200 Arch C-200 CM N/A Owner07 20 20 Parking Lots C-100 CM C-100 CM B-100 Arch A-400 Eng B-100 CM A-400 CM N/A A-300 Contractor B-200 Arch C-200 CM N/A Owner07 20 30 Pedestrian Plazas and Walkways C-100 CM C-100 CM B-100 Arch A-350 Eng B-100 CM A-400 CM N/A A--300 Contractor B-200 Arch C-200 CM N/A Owner07 20 40 Airfields C-100 CM C-100 CM B-100 Arch A-300 Eng B-100 CM A-400 CM N/A A-300 Contractor B-200 Arch C-200 CM N/A Owner07 20 50 Athletic, Recreational, and Playfield Areas C-100 CM C-100 CM B-100 Arch A-400 Eng B-100 CM A-400 CM N/A A-200 Contractor B-200 Arch C-200 CM N/A Owner07 20 60 Site Development C-100 CM N/A B-100 Arch A-300 Eng B-100 CM A-400 CM N/A A-350 Contractor B-200 Arch C-200 CM N/A Owner07 20 80 Landscaping C-100 CM N/A B-100 Arch A-300 Eng B-100 CM A-400 CM N/A C-200 Contractor B-200 Arch C-200 CM N/A Owner
SPECIAL CONSTRUCATION AND DEMOLITION
Heating, Ventilation and Air Conditioning (HVAC)
Fire Protection
Electrical
Equipment
SITEWORKSite Preparation
Site Improvements
Demolition
Furnishings
Special Construction
Communications
EQUPMENT AND FURNISHINGS
Electronic Safety and Security
Integrated Automation
Facility Remediation
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
40
07 3007 30 10 Water Utilities A-300 CM N/A A-350 Eng A-300 Eng B-200 CM A-400 Eng A-400 A-300 Contractor A-400 Eng C-200 Eng N/A Owner07 30 20 Sanitary Sewerage Utilities A-300 CM N/A A-350 Eng A-300 Eng B-200 CM A-400 Eng A-400 A-300 Contractor A-400 Eng C-200 Eng N/A Owner07 30 30 Storm Drainage Utilities A-300 CM C-100 CM A-350 Eng A-200 Eng B-200 CM A-400 Eng A-400 A-100 Contractor A-400 Eng C-200 Eng N/A Owner07 30 50 Site Energy Distribution A-300 CM A-200 CM A-350 Eng A-200 Eng B-200 CM A-400 Eng N/A A-300 Contractor A-400 Eng C-200 Eng N/A Owner07 30 60 Site Fuel Distribution A-300 CM C-100 CM A-350 Eng A-200 Eng B-200 CM A-400 Eng N/A A-300 Contractor A-400 Eng C-200 Eng N/A Owner07 30 90 Liquid and Gas Site Utilites Supplementary Components A-300 CM C-100 CM A-350 Eng A-200 Eng B-200 CM A-400 Eng N/A A-300 Contractor A-400 Eng C-200 Eng N/A Owner07 4007 40 10 Site Electric Distribution Systems C-100 CM C-300 CM A-350 Eng A-200 Eng B-200 CM A-400 Eng N/A A-350 Contractor A-400 Eng C-200 Eng N/A Owner07 40 50 Site Lighting C-100 CM C-300 CM A-350 Eng A-300 Eng B-200 CM A-400 Eng N/A A-400 Contractor A-400 Eng C-200 Eng N/A Owner07 5007 50 10 Site Communications Systems C-100 CM N/A A-350 Eng N/A B-200 CM A-400 Eng N/A A-400 Contractor A-400 Eng C-200 Eng N/A Owner07 6007 60 10 Tunnels N/A A-200 A-350 Eng A-350 Eng B-200 N/A N/A A-400 Contractor A-400 Eng N/A N/A OwnerA
AA Construction Equipment N/A N/A N/A N/A N/A N/A N/A A-400 Contractor N/A N/A N/AB Temporary Safety N/A N/A N/A N/A N/A N/A N/A A-400 Contractor N/A N/A N/AC Temporary Security N/A N/A N/A N/A N/A N/A N/A A-350 Contractor N/A N/A N/AD Temporary Facilities N/A N/A N/A N/A N/A N/A N/A A-500 Contractor N/A N/A N/AE Weather Protection N/A N/A N/A N/A N/A N/A N/A A-200 Contractor N/A N/A A-500 Owner
BA Construction Activity Space N/A N/A N/A N/A N/A N/A N/A A-200 Contractor N/A N/A A-500 OwnerB Analysis Space N/A N/A N/A N/A N/A N/A N/A A-300 Contractor N/A N/A A-500 Owner
CA Construction Information A-300 CM A-300 Eng N/A A-300 CM N/A A-400 CM N/A A-300 Contractor N/A C-200 CM A-400 OwnerB Engineering Information A-300 Eng A-300 Eng A-300 Eng A-400 Eng N/A A-300 Eng N/A C-200 Eng A-400 OwnerC Record Information A-300 CM A-300 Eng A-300 Arch A-400 CM N/A A-300 Eng/Arch/CM N/A C-200 CM A-500 Owner
CA Grid A-300 Eng/CM A-300 Eng A-350 Eng/Arch B-300 Eng B-300 Eng/CM A-400 Eng/CM N/A N/A A-400 Eng/Arch C-200 Eng/CM A-400 OwnerB Levels A-300 Eng/CM A-300 Eng A-350 Eng/Arch B-300 Eng B-300 Eng/CM A-400 Eng/CM N/A N/A A-400 Eng/Arch C-200 Eng/CM A-400 OwnerC Orgin A-300 Eng/CM A-300 Eng A-350 Eng/Arch A-300 Eng B-300 Eng/CM A-400 Eng/CM N/A N/A A-400 Eng/Arch C-200 Eng/CM A-400 Owner
Datum
Additional InformationConstruction Systements
Miscellaneous Site Construction
Liquid and Gas Site Utilities
Electrical Site Improvements
Site Communications
Space
Information
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
41
5. MODEL DEFINITION WORKSHEET [FROM SECTION G]
10 15 20 25 30 40 50 60
InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes InfoResp Party
Notes
0101 1001 10 10 Standard Foundations C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 10 20 Special Foundations C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 2001 20 10 Walls for Subgrade Enclosures C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 4001 40 10 Standard Slabs-On-Grade C-100 Arch C-100 Arch B-200 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 40 20 Structural Slabs-On-Grade C-100 Arch C-100 Arch B-200 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 40 30 Slab Trenches C-100 Arch C-100 Arch B-200 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 40 40 Pits and Bases C-100 Arch C-100 Arch B-200 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 40 50 Slab-On-Grade Supplementary Components C-100 Arch C-100 Arch B-200 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 6001 60 10 Building Subdrainage C-100 Arch C-100 Arch B-200 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 60 20 Off-Gassing Mitigation C-100 Arch C-100 Arch B-200 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 9001 90 10 Substructure Excavation C-100 Arch C-100 Arch B-200 Eng A-300 Arch/Eng A-300 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 90 20 Construction Dewatering C-100 Arch C-100 Arch B-200 Eng A-300 Arch/Eng A-300 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 90 30 Excavation Support C-100 Arch C-100 Arch B-200 Eng A-300 Arch/Eng A-300 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors01 90 40 Soil Treatment C-100 Arch C-100 Arch B-200 Eng A-300 Arch/Eng A-300 CM A-500 CM/Trade Contractor B-200 Eng A-300 Eng/CM/Trade Contractors0202 1002 10 10 Floor Construction C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 10 20 Roof Construction C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 10 30 Stairs C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 2002 20 10 Exterior Walls C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 20 20 Exterior Windows C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 20 50 Exterior Doors and Grilles C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 20 70 Exterior Louvers and Vents C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 20 80 Exterior Wall Appurtenances C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 20 90 Exterior Wall Specialties C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 3002 30 10 Roofing C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors
02 30 20 Roof Appurtenances C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 30 40 Traffic Bearing Horizontal Enclosures C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 30 60 Horizontal Openings C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors02 30 80 Overhead Exterior Enclosures C-100 Arch C-100 Arch A-300 Eng A-400 Arch/Eng A-400 CM A-500 CM/Trade Contractor A-300 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors0303 1003 10 10 Interior Partitions C-100 Arch C-100 Arch B-200 Arch A-400 Arch/Eng A-400 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 10 20 Interior Windows C-100 Arch C-100 Arch B-200 Arch A-400 Arch/Eng A-400 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 10 30 Interior Doors C-100 Arch C-100 Arch B-200 Arch A-400 Arch/Eng A-400 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 10 40 Interior Grilles and Gates C-100 Arch C-100 Arch B-200 Arch A-400 Arch/Eng A-400 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 10 60 Raised Floor Construction C-100 Arch C-100 Arch B-200 Arch A-400 Arch/Eng A-400 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 10 70 Suspended Ceiling Construction C-100 Arch C-100 Arch B-200 Arch A-400 Arch/Eng A-400 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 10 90 Interior Specialties C-100 Arch C-100 Arch B-200 Arch A-400 Arch/Eng A-400 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 2003 20 10 Wall Finishes C-100 Arch C-100 Arch B-200 Arch A-300 Arch/Eng A-300 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 20 20 Interior Fabrications C-100 Arch C-100 Arch B-200 Arch A-300 Arch/Eng A-300 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 20 30 Flooring C-100 Arch C-100 Arch B-200 Arch A-300 Arch/Eng A-300 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 20 40 Stair Finishes C-100 Arch C-100 Arch B-200 Arch A-300 Arch/Eng A-300 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor03 20 50 Ceiling Finishes C-100 Arch C-100 Arch B-200 Arch A-300 Arch/Eng A-300 CM A-400 CM/Trade Contractor B-200 Arch/CM/Trade Contractor A-300 Arch/CM/Trade Contractor0404 1004 10 10 Vertical Conveying Systems N/A N/A N/A N/A N/A N/A N/A N/A04 10 50 Material Handling N/A N/A N/A N/A N/A N/A N/A N/A04 10 80 Operable Access Systems N/A N/A N/A N/A N/A N/A N/A N/A04 2004 20 10 Domestic Water Distribution C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-300 Eng/CM/Trade Contractors04 20 20 Sanitary Drainage C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-300 Eng/CM/Trade Contractors04 20 30 Building Support Plumbing Systems C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-300 Eng/CM/Trade Contractors04 20 50 General Service Compressed-Air C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-300 Eng/CM/Trade Contractors04 20 60 Process Support Plumbing Systems C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-300 Eng/CM/Trade Contractors04 3004 30 10 Facility Fuel Systems C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors04 30 20 Heating Systems C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors04 30 30 Cooling Systems C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors04 30 50 Facility HVAC Distribution Systems C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors04 30 60 Ventilation C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors04 30 70 Special Purpose HVAC Systems C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-400 Eng/CM/Trade Contractors
Plumbing
Interior Finishes
SERVICESConveying
Interior Construction
Slabs-On-Grade
Application & Version
Subgrade Enclosures
INTERIORS
Exterior Vertical Enclosers
Foundations
Design StageConstruction
Document StageProject Stage Deliverable
Author File Format (if varies, specify in notes)
Conception StageProject Delivery Selection Stage
Model Element Breakdown
SUBSTRUCTURE
Water and Gas Mitigation
Substructure Related Activities
SHELLSuperstructure
Exterior Horizontal Encloses
Heating, Ventilation and Air Conditioning (HVAC)
Utilization StageExecution Stage Closure StageProcument Stage
SOLVE Design & Construction - CON 453 Healthcare Clinic Date: 27 October 2014
BUILDING INFORMATION MODELING PROJECT EXECUTION PLAN
42
04 4004 40 10 Fire Suppression C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 40 30 Fire Protection Specialties C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 5004 50 20 Electrical Service and Distribution C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 50 30 General Purpose Electrical Power C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 50 40 Lighting C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 50 50 Miscellaneous Electrical Systems C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 6004 60 10 Data Communications C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-300 Eng/CM/Trade Contractors04 60 20 Voice Communications C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-300 Eng/CM/Trade Contractors04 60 30 Audio-Video Communication C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-300 Eng/CM/Trade Contractors04 60 60 Distributed Communications and Monitoring C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-300 Eng/CM/Trade Contractors04 60 90 Communications Supplementary Components C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-300 Eng/CM/Trade Contractors04 7004 70 10 Access Control and Intrusion Detection C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 70 30 Electronic Surveillance C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 70 50 Detection and Alarm C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 70 70 Electronic Monitoring and Control C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 70 90 Electronic Safety and Security Supplementary C-100 Arch C-100 Arch A-300 Eng A-400 Eng A-400 CM A-500 CM/Trade Contractor A-500 Eng/CM/Trade Contractors A-500 Eng/CM/Trade Contractors04 8004 80 10 Integrated Automation Facility Controls C-100 Arch N/A Arch N/A N/A N/A N/A N/A N/A0505 1005 10 10 Vehicle and Pedestrian Equipment N/A N/A N/A N/A N/A N/A N/A N/A05 10 30 Commercial Equipment N/A N/A N/A N/A N/A N/A N/A N/A05 10 40 Institutional Equipment N/A N/A N/A N/A N/A N/A N/A N/A05 10 60 Residential Equipment N/A N/A N/A N/A N/A N/A N/A N/A05 10 70 Entertainment and Recreational Equipment N/A N/A N/A N/A N/A N/A N/A N/A05 10 90 Other Equipment N/A N/A N/A N/A N/A N/A N/A N/A05 2005 20 10 Fixed Furnishings N/A N/A N/A N/A N/A N/A N/A N/A05 20 50 Movable Furnishings N/A N/A N/A N/A N/A N/A N/A N/A0606 1006 10 10 Integrated Construction N/A N/A N/A N/A N/A N/A N/A N/A06 10 20 Special Structures N/A N/A N/A N/A N/A N/A N/A N/A06 10 30 Special Function Construction N/A N/A N/A N/A N/A N/A N/A N/A06 10 50 Special Facility Components N/A N/A N/A N/A N/A N/A N/A N/A06 10 60 Athletic and Recreational Special Construction N/A N/A N/A N/A N/A N/A N/A N/A06 10 80 Special Instrumentation N/A N/A N/A N/A N/A N/A N/A N/A06 2006 20 10 Hazardous Materials Remediation N/A N/A N/A N/A N/A N/A N/A N/A06 3006 30 10 Structure Demolition N/A N/A N/A N/A N/A N/A N/A N/A06 30 30 Selective Demolition N/A N/A N/A N/A N/A N/A N/A N/A06 30 50 Structure Moving N/A N/A N/A N/A N/A N/A N/A N/A0707 1007 10 10 Site Clearing C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 10 20 Site Elements Demolition C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 10 30 Site Element Relocation C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 10 50 Site Remediation C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 10 70 Site Earthwork C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM
Site Preparation
Facility Remediation
Fire Protection
Electrical
Communications
EQUPMENT AND FURNISHINGSEquipment
Electronic Safety and Security
Integrated Automation
Furnishings
SPECIAL CONSTRUCATION AND DEMOLITION
Special Construction
Demolition
SITEWORK
07 2007 20 10 Roadways C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 20 20 Parking Lots C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 20 30 Pedestrian Plazas and Walkways C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 20 40 Airfields C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 20 50 Athletic, Recreational, and Playfield Areas C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 20 60 Site Development C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 20 80 Landscaping C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Arch/CM C-100 Arch/CM07 3007 30 10 Water Utilities C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Eng/CM A-300 Eng/CM07 30 20 Sanitary Sewerage Utilities C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Eng/CM A-300 Eng/CM07 30 30 Storm Drainage Utilities C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Eng/CM A-300 Eng/CM07 30 50 Site Energy Distribution C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Eng/CM A-300 Eng/CM07 30 60 Site Fuel Distribution C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Eng/CM A-300 Eng/CM07 30 90 Liquid and Gas Site Utilites Supplementary ComponentsC-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Eng/CM A-300 Eng/CM07 4007 40 10 Site Electric Distribution Systems C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Eng/CM A-300 Eng/CM07 40 50 Site Lighting C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Eng/CM A-300 Eng/CM07 5007 50 10 Site Communications Systems C-100 Arch C-100 Arch A-400 Eng A-300 Eng/Arch A-300 CM A-400 CM/Trade Contractor C-100 Eng/CM A-300 Eng/CM07 6007 60 10 Tunnels N/A N/A N/A N/A N/A N/A N/A N/AA
AA Construction Equipment N/A N/A N/A N/A N/A N/A N/A N/AB Temporary Safety N/A N/A N/A N/A N/A N/A N/A N/AC Temporary Security N/A N/A N/A N/A N/A N/A N/A N/AD Temporary Facilities N/A N/A N/A N/A N/A N/A N/A N/AE Weather Protection N/A N/A N/A N/A N/A N/A N/A N/A
BA Construction Activity Space N/A N/A N/A N/A N/A N/A N/A N/AB Analysis Space N/A N/A N/A N/A N/A N/A N/A N/A
CA Construction Information C-100 Arch C-100 Arch A-300 Eng A400 Eng N/A A-400 CM/Trade Contractor C-100 Arch/CM N/AB Engineering Information C-100 Arch C-100 Arch A-300 Eng A400 Eng N/A A-400 CM/Trade Contractor C-100 Arch/CM N/AC Record Information C-100 Arch C-100 Arch A-300 Eng A400 Eng N/A A-400 CM/Trade Contractor C-100 Arch/CM N/A
CA Grid C-100 Arch C-100 Arch A-300 Eng A-500 Eng N/A A-400 CM/Trade Contractor C-100 Arch/CM C-100 Eng/CMB Levels C-100 Arch C-100 Arch A-300 Eng A-500 Eng N/A A-400 CM/Trade Contractor C-100 Arch/CM C-100 Eng/CMC Orgin C-100 Arch C-100 Arch A-300 Eng A-500 Eng N/A A-400 CM/Trade Contractor C-100 Arch/CM C-100 Eng/CM
Site Improvements
Space
Information
Datum
Liquid and Gas Site Utilities
Electrical Site Improvements
Site Communications
Miscellaneous Site Construction
Additional InformationConstruction Systements