ER420-NEW ROAD LINK BETWEEN UPPER CHANGI
ROAD AND UPPER CHANGI ROAD EAST
METHOD STATEMENT
Bakau piling for 1500 RCU Drain along MC02
PREPARED BY : HARIRAM MANOHARAN
APPROVED BY : GOO KIANG TIONG, JIMMYSAFETY OFFICER : LEE SHANG KENGDATE OF SUBMISSION :REVISION : 0
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
2/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
TABLE OF CONTENTS:
1. Objective
2. Project Overview
3. Resources: Plant and Manpower 3.1. Hierarchy Chart for this Operation
3.2 Relevant certificates for manpower and Equipment
4. Method Statement
4.1. Service/ Utilities in the Vicinity of work 4.1.1. List of services
4.1.2. Protective Measures
4.2 Schedule of Works
5. Emergency Plan5.1 Evacuation Plan
5.2 Damage to services
5.3 Lists of essential Personnel
6. Safety and Environmental
6.1 Lists of personal protective equipment (PPE)
6.2 Permit to Work System
6.3 Risks Assessment and hazard Analysis
Appendix 1- Location Plan of Proposed Bakau piling works
Appendix 2- Relevant Certificates for Manpower & Equipment
Appendix 3-Services/Utilities in the Vicinity of Work
Appendix 4- Permit to Work Forms
Appendix 5- Risk Assessment and Hazard Analysis
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
3/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
1) OBJECTIVE:-The purpose of this document is to describe the methodology for the Installation of
Bakau piles for 1500 RCU drain works along Upper Changi road MC02.
2) PROJECT OVERVIEW:-The works under contract ER420: New road link between Upper Changi Road and
Upper Changi Road East mainly comprises of the following: Construction of new road between Upper Changi Road and Upper
Changi Road East Construction of New junctions in the Upper Changi Road and Upper
Changi Road East Construction of Rigid Pavements at the junctions Widening a Part of Upper Changi Road Milling and Patching works in Upper Changi Road and Upper Changi
Road East Construction of Drains, Box culverts and sumps Construction of Two Bus Bays and Bus Shelter Slabs Installation of railings
3) RESOURCES:PLANT & MANPOWER:-
Sl.No Item Qty
Machinery:
1 Excavator fitted with 3 meter long steeldolly( Excavator with valid LM certificate)
1
Manpower:
3 Site Engineer 1
4 Surveyor 1
5 Site Supervisor 1
6 Safety Supervisor 1
7 Banksman 1
7 General Worker 7
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
4/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
Project Manager
Site Engineer
Site SupervisorSafety Supervisor
Foreman
General Worker
Excavator operator
Surveyor
Banksman
3.1) HIERARCHY CHART FOR THE OPERATION:-
3.2) RELEVANT CERTIFICATES FOR MANPOWER AND EQUIPMENT:-
The relevant certificates for Manpower and Equipment are attached in Appendix 2.
Updated relevant certificates will be submitted before the commencement of work.
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
5/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
4) METHOD STATEMENT:-
4.1) SERVICES/UTILITIES IN THE VICINITY OF WORK:-
4.1.1)
List of services:-
There are no services running along the work area. The sheet piling works have been completed already. Trial trenches were done before the sheet piling works
to ensure the absence of any services within the work area.
4.1.2) Protective measures:-
Even though there are no services running exactly below the piling area, there isa 500mm AC Main at a distance of 7.5 meter from the bakau piling area. Care
is to be taken that no unsafe acts are carried out near the AC main. Regular
checks are to be carried out to look for any possible leakage in the 500 AC
Main.
4.2.2) SEQUENCE OF BAKAU PILING WORKS:
1) Set out the proposed 1500RCU drain alignment as per setting-out plan.2) Excavate the trenches to the required depth for the laying of precast RC U-drain.3) When the excavation reaches the required depth, Start the installation of Bakau
piles.
4) Bakau piles are installed with the help of the Steel Dolly attached to the teeth of the excavator bucket.
5) The length of the metal dolly is 3m. The depth of excavation is 2.5m whichmeans that the entire excavator bucket will be above the strut area when the
bakau piles are completely installed.
6) The work sequence is;
The bakau pile is placed in the required location and is pressed into the soil bythe workers up to possible depth.
The workers are then to move away from the pile. The dolly attached to the excavator bucket is then lowered and the bakau pile is
inserted into the hollow part of the metal dolly. If necessary, worker will assist
in inserting the pile in to the dolly.
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
6/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
The metal dolly is the pressed down gradually until the whole length of the bakau pile is inserted into the ground.
The dolly is then lifted up with much care to prevent it from hitting the workersnear the work area.
The next bakau pile is placed 300mm from the previous pile and the same process is continued.
3m
300mm
Excavator Bucket
Metal Dolly
Bakau Pile
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
7/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
300mm
1900mm
1500mm RCU Drain
50mm Thick lean conc
3.5m x 75mm Bakau p
Sheet Pile
2.5m
300mm 300mm 300mm 300mm 300mm
Struts
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
8/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
SAFETY PRECAUTION
1) Work site shall be cordon off from public access.
2) Proper barricade and signage shall be provided to warn the workers to divert
away from deep excavation
3) Work area must be cleaned and stagnant water cleared daily.
4) All workers shall wear Personal Protective Equipment e.g. reflective safety vest,
safety helmet within the site.
5) Site supervisor shall supervise throughout the entire piling works; he is wholly
in-charge of safety, supervision and traffic control in work areas.
6) Where excavators are used, care shall be taken to ensure that no materials are
stacked within the swinging area of the excavator.
5) EMERGENCY PLAN:-
5.1) EVACUATION PLAN:-Upon the occurrence of work site accident, the emergency evacuation plan is as
follows: Site work in the vicinity will be stopped The reporting of the occurrence of accident will go up the company hierarchy
i.e. workers inform supervisors/engineers, who will inform the project manager,and then the RTO and LTA will be informed
Site and safety supervisors will be taking charge of securing the area Any hurt personnel will be carefully shifted to a secure location for first aid and
subsequent evacuation to nearby hospital Unhurt work personnel will be gathered at a safe with headcount accounted for.
They will receive further instructions Accident area to be investigated and subsequently cleared.
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
9/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
5.2) DAMAGE TO SERVICES:-In spite of all the precautionary measures taken, if there is any damage to the
existing service, the follow up action is as follows: Site work in the vicinity will be stopped
The reporting of the occurrence of accident will go up the hierarchy Site and safety supervisors will be taking charge of securing the area A report for services damage are be made immediately to the following hot-
line number; PUB-1800-284 6600 SPPG-1800-778 8888 SINGTEL-1800-288 4099
5.3) LIST OF ESSENTIAL PERSONNEL:-
Name Designation Contact numberJimmy Goo Project Manager 9695 7413Hariram Site Engineer 9447 7749Lee Shang Keng Safety Officer 9666 0582Soh Eng Soon Site Supervisor 9068 4578Fong Heng Wong Site Supervisor 8402 5141Solaiappan Subramanian Site Supervisor 8433 2276Velayutham Muniyandi Safety supervisor 8259 0048
6) SAFETY AND ENVIRONMENTAL:-
6.1) List of Personal Protective Equipment (PPE):-
S/No PPE
1 Safety Helmet
2 Safety boots
3 Reflective vest
4 Hand Gloves
5 Full Body Harness( If applicable)
6 Face Mask and Safety Goggles
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
10/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
6.2) Permit to Work System:-
All relevant Permit to Work forms would be submitted before the operation.
Refer to Appendix 6 for the relevant forms.
6.3) Risk Assessment and Hazard Analysis:-
Refer to Appendix 7 for the Risk assessment and Hazard analysis for the work.
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
11/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
APPENDIX 1LOCATION PLAN FOR BAKAU PILING WORKS
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
12/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
13/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
APPENDIX 2
Relevant Certificates for Manpower and Equipment
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
14/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
15/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
16/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
17/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
18/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
APPENDIX 3
Services/Utilities in the Vicinity of Work
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
19/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
20/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
APPENDIX 4
Permit to Work- Forms
-
7/28/2019 ER420_MS of Bakau Piling Works for 1500 RCU_r0
21/21
ER420_MS of Bakau Piling works for 1500 RCU_r0.doc
APPENDIX 5
Risk Assessment and Hazard Analysis