edvard grieg anders henriksson, lundin petroleum prosjektleder
Post on 01-Jan-2017
225 Views
Preview:
TRANSCRIPT
www.lundin-norway.no
Edvard Grieg Anders Henriksson, Lundin Petroleum Prosjektleder
www.lundin-norway.no
Lundin Petroleum – Asset overview
www.lundin-norway.no
Lundin Norway AS • Established on the NCS in 2004 by the
purchase of the DNO portfolio in Norway
• ”Core staff” from previous Saga Petroleum and DNO
• 40 licences in total, 22 as operator
• Daily NCS production of approximately 30 000 boe from the Alvheim and Volund fields
• Several development projects in the planning phase as operator
– Brynhild – startup 2014 – Luno– startup 2015
www.lundin-norway.no
Utsirahøyden
Utsirahøyden is an area where Lundin has focus Exploration has been on and off
in almost 40 years in this area Several ongoing development
projects in this area Edvard Grieg Ivar Aasen Johan Sverdrup Infrastructure: oil, gas, power
www.lundin-norway.no
Edvard Grieg
PL338 is located in block 16/1, about 180 km west of Stavanger Water depth at platform location is 109 m
By January 2011 the license consisted of: Lundin Norway AS (operat0r): 50% Wintershall Norge AS: 30% RWE Dea Norge AS: 20%
Todays owners: Lundin Norway AS (operatør): 50% OMV Norge AS: 20% Wintershall Norge AS: 15% Statoil Petroleum AS: 15%
www.lundin-norway.no
Edvard Grieg
www.lundin-norway.no
Edvard Grieg - Capacities
Kapasitet PL338 Kapasitet PL338 + tie-ins
Olje (Sm3/d) 14 300 20 000
Gassprosessering (MSm3/d) 2.5 5
Prod. vann (Sm3/d) 13 000 13 000
Vanninjeksjon (Sm3/d) 24 000 24 000
www.lundin-norway.no
Edvard Grieg - Mainlifts
P00 5338 T
C00 10645 T
F00 268 T
N FORBORINGSDEKK
H00 + L00 + U00 6665 T
TOTAL TOPSIDE TØRRVEKT 22668 T
Weightreport rev. 14
www.lundin-norway.no
Jacket EPC – Some key data
Jacket Contract value 1.2 BN Jacket weight: 13.400 ton Pile weight: 6.500 ton Bouyancy tanks: 1.500 tonnes Temporary drill deck for 20 slots Appurtenances
7 Risers for pipeline connection 10 caissons (7 pump caissons and 3 dump caissons) 16 J –tubes 8 for future cables 8 for future risers
Delivery date: 01.04.14
www.lundin-norway.no
Edvard Grieg – Pre-drilling
www.lundin-norway.no
Edvard Grieg – UHGP Installeres 2014
www.lundin-norway.no
Edvard Grieg – EGOP «Grane Y» Installation on going
www.lundin-norway.no
EG platform: High complexity
EG platform designed as a Field Centre from day #1 in-license tie-ins: discoveries & prospects final processing + export of oil & gas from Ivar Aasen Specific design challenges Significant differences between reservoirs to be produced
Incompatible formation waters
Area solutions for oil & gas export + future power from shore
www.lundin-norway.no
EG main process 3 separators to limit recycle of intermediate components 1x coalescer to reduce water-in-oil to ~0.3% due to salt content
2-stage recompression w/VSD & 2-casing design w/space for extra impellers
HP gas compression train 1x 100% train ... with «spare» compressors «high» and «low» design flow for gas processing
www.lundin-norway.no
EG inlet separators Parallel inlet separators primary / secondary / test segregated water treatment Inlet routing flexibility valves: primary/test valves: secondary/test spools: primary/secondary Significant impact on layout
Space for future manifolds
www.lundin-norway.no
Jacket EPC – Construction at Verdal Yard
Load-Out 1-2 of April
www.lundin-norway.no
Jacket EPC – Construction at Verdal Yard
Status 9th. of April
www.lundin-norway.no
Verdal, April 15th, 1430 hours
www.lundin-norway.no
The Launch moment! Well testing and by the way, Launch, May 3rd.
www.lundin-norway.no
Saturday evening, May 3rd.
www.lundin-norway.no
Sunday morning, May 4th.
www.lundin-norway.no
Pile stabbing
www.lundin-norway.no
Pile hammer
www.lundin-norway.no
Bouyancy tanks Removal, May 10th.
www.lundin-norway.no
PDD installation
www.lundin-norway.no
Finished, May 13th. 0500 hours
www.lundin-norway.no
Edvard Grieg Topside EPC Contract
www.lundin-norway.no
Topside EPC Contract – May Bi-weekly cut-off
www.lundin-norway.no
Engineering April 2014
Karl-Petter Løken
www.lundin-norway.no
Detail Engineering finished
Construction and Follow-on Engineering on-going
Engineering manning reduced every month
Engineering
www.lundin-norway.no
Edvard Grieg Topside EPC Contract
Equipment
www.lundin-norway.no
Duisburg 29.07.2013
www.lundin-norway.no
Hengelo 2.08.2013
www.lundin-norway.no
Hengelo 13.02.2014 Final Inspection Re-compressor and Injection Compressor
www.lundin-norway.no
www.lundin-norway.no
ATV
www.lundin-norway.no
Edvard Grieg Topside EPC Contract
Construction
www.lundin-norway.no
Process Module - Assembly status Three of total four deck floors are installed.
The first section for the fourth deck (P40) has arrived from Poland (in the hook)
www.lundin-norway.no
Process Module – Current status of erection program in Egersund.
Installation of equipments on P30 deck has commenced.
Gas Injection Compressor 1 and 2 Stg. Recompressor
www.lundin-norway.no
Process Module
1 & 2 stage recompressor and Gas Inj. Compressor skids are installed incl. Noise hoods.
El. Cabinets in LER and the framework for Raised Access Floor are installed.
www.lundin-norway.no
C00 Installation dates
www.lundin-norway.no
www.lundin-norway.no
www.lundin-norway.no
www.lundin-norway.no
www.lundin-norway.no
Installation of C32 Mod Section
www.lundin-norway.no
Installation of C32 Mod Section
www.lundin-norway.no
Currency connection
The light is on!
www.lundin-norway.no
Lifting of Helideck, May 27th.
www.lundin-norway.no
EDVARD GRIEG – FLOTEL STATUS - MARCH 2014
www.lundin-norway.no
www.lundin-norway.no
www.lundin-norway.no
www.lundin-norway.no