decommissioning subsea abrasive water jet cutting case studymcedd.com/wp-content/uploads/03_paul...

Post on 28-Jul-2020

4 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

MCE Deepwater Development 2016

PAU, FRANCE • 5-7 APRIL 2016

Decommissioning

Subsea Abrasive Water Jet Cutting

Case Study

Paul Yeats

Oceaneering

MCE Deepwater Development 2016

Project Description

• Multi Operators approached Oceaneering to review well schematics of 8 subsea

wells in UKCS and propose a solution for the safe and efficient recovery.

• Upon review of information for each well, each recovery would face its own

challenge (access / Non H4 profile / Cement Patio’s / unknowns – lack of cement in

annulus etc).

• Oceaneering proposed a methodology for each well including contingency options

for each.

• Project took place October/November 2015.

• Customer also indicated that pricing was to be submitted as a lump sum campaign.

MCE Deepwater Development 2016

Primary Equipment: Internal Multi-string Cutting Tool (IMCT)

MCE Deepwater Development 2016

Challenging Wells

MCE Deepwater Development 2016

Cement Patio Break Up Tools

MCE Deepwater Development 2016

Challenges: Lack of Cement in Annulus

MCE Deepwater Development 2016

Challenges: Recovery/Non H4

MCE Deepwater Development 2016

Dredging for Access

MCE Deepwater Development 2016

Pile Dredging

MCE Deepwater Development 2016

External Wellhead Cutting

MCE Deepwater Development 2016

Wellhead Recovery

MCE Deepwater Development 2016

Wellhead Protection Structure

MCE Deepwater Development 2016

Recovered Structure

MCE Deepwater Development 2016

• Through the extensive time spent up-front prior to mobilisation, we were able to

ensure the correct equipment including all contingency equipment was onboard

to cover all eventualities.

• With the correct equipment onboard, we were able to complete these 8

challenging wells within budget, on time (1 day on WOW) and without any

requirement to sail to port for further equipment mobilisations.

• Successful completion of this project using this pricing strategy shows a step

change in how these work scopes can be completed and favour all parties.

• Currently bidding further work for client based on success of operation.

Conclusion

MCE Deepwater Development 2016

Day Rate v Lump Sum:

• High amount of wells to be Decommissioned in the UKCS – next 5 years account for

large % of decommissioning activity.

• Decommissioning is here and now.

• Risk v Reward.

• Is it feasible to bid the final (or other) stages of decommissioning on a lump sum basis?

• Do you fully know & understand your risk?

• Known knowns, known unknowns, unknown unknowns.

• Weather Risk – W.O.W

Driving Efficiencies in Decommissioning

top related