construction plan vs actuals after stage 2

Post on 09-Jul-2016

213 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

DESCRIPTION

Construction Plan Actual Stages

TRANSCRIPT

Construction Plan

Phase Description Date Days % Duration Delays in Days Work % Roughly

Construction Start 24-Mar-14

1 Plith Level 12-Apr-14 19 10% 2 10% 20

2 Ground floor Roof 30-May-14 48 24% 12 15% 30

3 First floor Roof 28-Jun-14 29 15% 4 15% 30

4 Electrician Work 5% 10

5 Plumbing Work 5% 10

6 External Plastering 8% 16

7 Internal Plastering 8% 16

8 Elevation Work 5% 10

9 Compound Walls 2% 4

10 Flooring (Internal + Parking) 8% 16

11 Fixtures - Wood 3% 6

12 Fixtures - Plumbing 3% 6

13 Fixtures - Electical 3% 6

14 Painting 8% 16

15 Final Finishing 2% 4

16 Key Handover 10-Oct-14 200 100% 18 100% 200

218 Days adding the delay