construction plan vs actuals after stage 2

1
Construction Plan Phase Description Date Days % Duration Delays in Days Work % Roughly Construction Start 24-Mar-14 1 Plith Level 12-Apr-14 19 10% 2 10% 20 2 Ground floor Roof 30-May-14 48 24% 12 15% 30 3 First floor Roof 28-Jun-14 29 15% 4 15% 30 4 Electrician Work 5% 10 5 Plumbing Work 5% 10 6 External Plastering 8% 16 7 Internal Plastering 8% 16 8 Elevation Work 5% 10 9 Compound Walls 2% 4 10 Flooring (Internal + Parking) 8% 16 11 Fixtures - Wood 3% 6 12 Fixtures - Plumbing 3% 6 13 Fixtures - Electical 3% 6 14 Painting 8% 16 15 Final Finishing 2% 4 16 Key Handover 10-Oct-14 200 100% 18 100% 200 218 Days adding the delay

Upload: kavitha

Post on 09-Jul-2016

213 views

Category:

Documents


0 download

DESCRIPTION

Construction Plan Actual Stages

TRANSCRIPT

Construction Plan

Phase Description Date Days % Duration Delays in Days Work % Roughly

Construction Start 24-Mar-14

1 Plith Level 12-Apr-14 19 10% 2 10% 20

2 Ground floor Roof 30-May-14 48 24% 12 15% 30

3 First floor Roof 28-Jun-14 29 15% 4 15% 30

4 Electrician Work 5% 10

5 Plumbing Work 5% 10

6 External Plastering 8% 16

7 Internal Plastering 8% 16

8 Elevation Work 5% 10

9 Compound Walls 2% 4

10 Flooring (Internal + Parking) 8% 16

11 Fixtures - Wood 3% 6

12 Fixtures - Plumbing 3% 6

13 Fixtures - Electical 3% 6

14 Painting 8% 16

15 Final Finishing 2% 4

16 Key Handover 10-Oct-14 200 100% 18 100% 200

218 Days adding the delay