Fiberglass Pipe
Bondstrand Bonder Training
Bondstrand Bonder Training for PTSC M&C - 2009 2
Contents
Part-1: General Part-2: AMERON’s Bondstrand Products Part-3: HSE & Product handling Part-4: Fabrication & Installation Part-5: Hydro-testing
Bondstrand Bonder Training for PTSC M&C - 2009 3
Part-1 : General
Training Purpose To provide knowledge of AMERON’s
Bondstrand Products To qualify bonder for bonding
certification required for fabrication and installation of AMERON’s Bondstrand Products
Bondstrand Bonder Training for PTSC M&C - 2009 4
Part-1 : General
Understanding AMERON’s Bondstrand Products
Understanding product data and QC form Pass hydrotest on practice
Achievements : Trainee must complete below points to get certificate
Bondstrand Bonder Training for PTSC M&C - 2009 5
Part-1 : General
Issued by AMERON to trainee who pass hydrotest on spool practice
2-year validity
Bonding certificate
Bondstrand Bonder Training for PTSC M&C - 2009 6
RTRP - Reinforced Thermosetting Resin Pipe FRP - Fiberglass Reinforced Pipe GRE - Glass Reinforced Epoxy GRV - Glass Reinforced Vinylester GRP - Glass Reinforced Polyester (in some
specifications it means Glass Reinforced Pipe)
Part-2 : AMERON’s Bondstrand Products
Abbreviations
Bondstrand Bonder Training for PTSC M&C - 2009 7
QLF - Quick Lock Female QLM - Quick Lock Male TF - Taper Female TM - Taper Male B&W - Butt & Wrap Spigot - Bondstrand Male Pipe End Bell - Bondstrand Female Pipe End
Part-2 : AMERON’s Bondstrand Products
Abbreviations
Bondstrand Bonder Training for PTSC M&C - 2009 8
Part-2 : AMERON’s Bondstrand Products
Epoxy (GRE) Vinylester (GRV)
Filament-wound pipe & fittings with advanced resins
Bondstrand Product Lines Bondstrand 2000/2000M Bondstrand 7000/7000M Bondstrand 2400/3400 series
Bondstrand Bonder Training for PTSC M&C - 2009 9
Bondstrand 2000
A lined epoxy system for applications where corrosion resistance and light weight are of paramount importance.
Part-2 : AMERON’s Bondstrand Products
Bondstrand Bonder Training for PTSC M&C - 2009 10
A lined epoxy system for applications where corrosion resistance and external pressure are of paramount importance.
Part-2 : AMERON’s Bondstrand Products
Bondstrand 2000M
Bondstrand Bonder Training for PTSC M&C - 2009 11
Bondstrand 7000/7000MAn epoxy system with conductive elements incorporated in the wall of the pipe to prevent accumulation of static electricity produced by the flow of liquids inside, and external effects outside the pipe.
Design equal to Bondstrand 2000/2000M
Unique patented pipe saddle drains off static charge build-up
Part-2 : AMERON’s Bondstrand Products
Bondstrand Bonder Training for PTSC M&C - 2009 12
Bondstrand Series 2400/3400 An epoxy system where corrosion
resistance and light weight are of paramount importance.
Pressure class determined by internal pressure requirements.
No external pressure requirements. Internal pressure class : 10, 12, 14,
16, 20 and 25 bar.* Also conductive
Part-2 : AMERON’s Bondstrand Products
Bondstrand Bonder Training for PTSC M&C - 2009 13
Part-2 : AMERON’s Bondstrand Products
Bondstrand Bonder Training for PTSC M&C - 2009 14
Joining SystemQuick-Lock Joint An adhesive-bonded joint with
straight spigot and tapered bell. The integral pipe stop in the Quick-Lock bell ensures accurate laying lengths in close tolerance piping.
Sizes : 25-400 mm (1”-16”) Sizes : 450-600 mm (18”-24”)
Part-2 : AMERON’s Bondstrand Products
Bondstrand Bonder Training for PTSC M&C - 2009 15
Taper/Taper Joint An adhesive-bonded joint with
matching tapered male and female ends offering superior strength by controlled adhesive thickness. Available in sizes : 50-1000 mm (2”- 40“).
Internal pressure class : 10, 12, 14, 16, 20, 25 bar.
Part-2 : AMERON’s Bondstrand Products
Joining System
Bondstrand Bonder Training for PTSC M&C - 2009 16
Flanged Joint A mechanical joint. Available
in sizes: 25-1000 mm (1”- 40“).
Various drilling patterns available (e.g. CL150, JIS 10K, DIN 10, etc.) - Compatible to Steel flanges.
Part-2 : AMERON’s Bondstrand Products
Joining System
Bondstrand Bonder Training for PTSC M&C - 2009 17
Joining System
Butt & Wrap Joint A lamination joint. Available
in sizes: 25-1000 mm (1”- 40“).
Time costly. Versatile. Most use on repair.
Part-2 : AMERON’s Bondstrand Products
Bondstrand Bonder Training for PTSC M&C - 2009 18
Adhesive System
RP-34C A two-part amine cured
epoxy resin system Non-conductive Use on Quick-Lock joint Available in 3 oz. kit and 6
oz. kit
Part-2 : AMERON’s Bondstrand Products
Bondstrand Bonder Training for PTSC M&C - 2009 19
Adhesive System
RP-60B A two-part thermosetting,
electrically conductive epoxy resin system
Conductive Use on Quick-Lock joint and
Taper/Taper joint Available in 3 oz. kit and 6
oz. kit
Part-2 : AMERON’s Bondstrand Products
Bondstrand Bonder Training for PTSC M&C - 2009 20
Adhesive System
RP-48 A two-part amine cured
epoxy resin system Non-conductive Use on Taper/Taper joint Available in 3 oz. kit and 6
oz. kit
Part-2 : AMERON’s Bondstrand Products
Bondstrand Bonder Training for PTSC M&C - 2009 21
Special Tools Pipe Shaver & Power Drive Heating Blanket
Other Accessories Band Clamp Lever Hoist Bore Polisher (Flapper Wheel)
Common Pipe Tools
Part-2 : AMERON’s Bondstrand Products
Tools & Equipment
Bondstrand Bonder Training for PTSC M&C - 2009 22
!!! Pipe Shaver: Machine of pipe end to obtain appropriate spigot end for bonding, shaver shall be selected based on type of joint, pipe diameter, with consideration of total project scope.
B-1F Shaver: ½”, ¾”, 1”, 1 ½”, 2”, 3”, 4”, 5” & 6”
Cutting Insert
For detail guide, See FP376F, ‘Ameron B-1F Pipe End Preparation Tool’
To individual size only; Straight Spigot (For Quick-
Lock Joint) only. Driven by common electrical
tools or air tools, such as hand drill.
Special Tools – Pipe Shaver & Power Drive
Bondstrand Bonder Training for PTSC M&C - 2009 23
M-74 Shaver
For detail guide, See FP696A, ‘M-74 Pipe Shaver’
For 2” – 16” pipes Use with arbor set Straight Spigot (For
Quick-Lock Joint) only. Driven by hand or
electrical tools (RIDGID-700).
Special Tools – Pipe Shaver & Power Drive
Bondstrand Bonder Training for PTSC M&C - 2009 24
Maintenance and Store Shall be kept in original tool box after use; Keep it in dry location, away from rain and
moisture; Do not use oil and/or grease as dust will
accumulate on oil and grease; Remove of dust/dirt using brush.
Special Tools – Pipe Shaver & Power Drive
Bondstrand Bonder Training for PTSC M&C - 2009 25
!!! Heating Blanket: For accelerating joint curing, as well as preheat of jointing surface
Available in 115V and 230V, to be specified; Size depends on pipe size; Equipped with thermostat;
For 1” to 28” Pipe For 30” to 40” Pipe
Special Tools – Heating Blanket
Bondstrand Bonder Training for PTSC M&C - 2009 26
Description of Heating Blanket
Special Tools – Heating Blanket
Bondstrand Bonder Training for PTSC M&C - 2009 27
Using Heating Blanket Wrap the pipe using the
end with thermostat; Tie down accessory
shall be used; Do NOT pull the cable;
Special Tools – Heating Blanket
Bondstrand Bonder Training for PTSC M&C - 2009 28
Packing, Storage and Transporting Always roll up the heating blanket when not in used; Do NOT pack and transport heating blanket in
folded form; Any heavy object fall on it may damage the heating
blanket;
Special Tools – Heating Blanket
Bondstrand Bonder Training for PTSC M&C - 2009 29
Band Clamp with D-Rings Shall be used when making joints, Quick-Lock,
Taper, Mechanical O-Ring, … Available in 2” width x 6’ length, and Available in 2” width x 13’ length, and Available in 3” width x 13’ length
Other Accessories
Bondstrand Bonder Training for PTSC M&C - 2009 30
Lever Hoist Shall be used when making joints,
Quick-Lock, Taper, Mechanical O-Ring, ……
Available in ½ Ton and 1 Ton, ……
Alternatively, ratchet puller (chain block) can be used
Bore Polisher (Flapper Wheel) Sanding bonding surface Grid 40~60 Driven by electrical drill or air tool
Other Accessories
Bondstrand Bonder Training for PTSC M&C - 2009 31
Hacksaw or abrasive wheel; Paint marker; Pipe wraparound; Baby grinder; Electric or Air drill; Level Gauge; Paint Brush; Nylon/Rubber Mallet;
Cotton Roller; Adjustable Pipe Stands; Sanding Disc; Screw Driver; Scissors; Air Release Roller; ……
There are many other common piping tools might be required for fiberglass piping fabrication and installation work, such as:
Common Piping Tools
Bondstrand Bonder Training for PTSC M&C - 2009 32
Part-3 : HSE & Product handling
!!! To prevent injuries & occupational diseases, property damages through needless industrial accidents and inefficient environment via waste management.
Personal Protection Equipment (PPE) Chemical and Dust Hazards
Bondstrand Bonder Training for PTSC M&C - 2009 33
Personal Protection Equipment (PPE)
!!! PPE is any device or appliance designed to be worn by an individual when exposed to one or more health and safety hazards.
Overall Safety Helmet Safety Boots Safety Glasses Gloves Dust Mask Etc
Bondstrand Bonder Training for PTSC M&C - 2009 34
!!! Resin, curing agent, catalyst, adhesive and other chemical products could cause irritation, some could be harmful to eyes.
Quick access to water in case of chemical contact !! No eating, drinking and smoking during handling of
above products; Maintain personal hygiene at all time; Safe glasses during handling above products; Dust mask to prevent inhalation of glass-fiber dust; Long sleeve shirts with long pants, or overall to
prevent skin irritation due to fiber dust;
Chemical and Dust Hazards
Bondstrand Bonder Training for PTSC M&C - 2009 35
Maintain personal hygiene at all time; Do not rub or scratch irritated area if occurred; Shower in lukewarm water with soap and a
washcloth at day’s end to remove loose fiber; Wash work clothes separately; Good ventilation in workplace to keep dust
concentration below the MAC value (10mg/m3); Rinsing workplace with water or sweeping with
brushes or brooms; Refer to relevant MSDS and product literature for
unfamiliar products.
Chemical and Dust Hazards
Bondstrand Bonder Training for PTSC M&C - 2009 36
!!! GRP piping components can be susceptible to mechanical damage from impact, sharp edges or scratching. Special consideration should be given to protecting components and to ensuring that all personnel involved are given training in the relevant procedures. ISO14692-4:2002
Goods Receiving Inspection Handling and Transportation Storage
Receiving and Handling
Bondstrand Bonder Training for PTSC M&C - 2009 37
Verify goods receiving conform to shipping and packing document and compliance to purchase order.
Packing condition. Spools and components condition. Adhesive Kits condition including shelf life, visible
damage and/or leaking, completeness of kit packing. Reporting of any deviation and/or issue. FP167D, Shipping, Handling, Storage and Inspection
of Bondstrand Fiberglass Pipe.
Good Receiving Inspection
Bondstrand Bonder Training for PTSC M&C - 2009 38
Handling and Transportation Proper support and protection with protection pad. Securely fastened. Forklifts should have at least a 6-foot carriage,
spacer of at least 2-inch thickness are located. Fittings shall be loaded onto pallets, crates or
baskets with sufficient protection. 3m or less pipe and spool could be lifted by single
4” wide canvas or suitable plastic. Pipe and spool greater than 3m (in length) shall be
lifted in using two or more canvas or suitable plastic.
Handling and Transportation
Bondstrand Bonder Training for PTSC M&C - 2009 39
Prohibitions Being thrown or dropped from any height. Using chains, wire ropes or clamps for lifting
Handling and Transportation
Bondstrand Bonder Training for PTSC M&C - 2009 40
!!! Carrying out inspection for good storage preparation and carrying out periodical inspection.
Fiberglass Pipe Well supported (side support and spacer support), not more
than 10-ft Interval, 6-ft from each end, the support should have 4-in wide bearing surface.
Side supports; not exceed 5-ft height; proper tie down. Protective end cover must be in place.
Storage
Bondstrand Bonder Training for PTSC M&C - 2009 41
Fiberglass Fitting and Accessories Shall be kept in shipping box/pallet. Protective end cover must be in placed. Accessories such as Nylon Key and O-Ring, shall be kept
in shed store. Fiberglass Fabricated Spools
Shall be kept in shipping pallet or skid. End cover / protection shall not be removed until
installation. Adhesive Kit, Resin and Curing Agent
Shall be kept in original packing. Shall be kept in specified control condition. Shall be used before expiry date.
Storage
Bondstrand Bonder Training for PTSC M&C - 2009 42
Drawings Product data & Pipe length calculation QC form : Log sheet Fabrication and Installation Tolerances Hook-up to Equipment / Other Material
Part-4 : Fabrication and Installation
Bondstrand Bonder Training for PTSC M&C - 2009 43
Spool Drawing Contain detail dimensions, fabrication materials, and
erection materials. Isometric Drawing
Contain all details of design (Pressure, fluid, system, temperature,…..), fabrication and erection (Materials), installation (Coordinates, connections) and testing.
Layout Drawing Background, surrounding, piping routing, supporting,
interface, equipment, etc. Piping and Instrument Diagram
Principle such as size, flow direction, design information, materials specification.
Drawings
Bondstrand Bonder Training for PTSC M&C - 2009 44
Sample Drawing – Spool 1
Bondstrand Bonder Training for PTSC M&C - 2009 45
Sample Drawing – Spool 2
Bondstrand Bonder Training for PTSC M&C - 2009 46
Sample Drawing – Spool 3
Bondstrand Bonder Training for PTSC M&C - 2009 47
Sample Drawing – ISO
Bondstrand Bonder Training for PTSC M&C - 2009 48
Sample Drawing – Layout
Bondstrand Bonder Training for PTSC M&C - 2009 49
Product data Assembling dimension of fittings
Pipe length calculation To produce pipe cutting table To calculate pipe length for spool adjustment To verify installation
Product data & Pipe length Calculation
Exercise : calculate pipe length.
Bondstrand Bonder Training for PTSC M&C - 2009 50
To record bonding history for fabrication and site installation
Part of QC documentation
QC Form : Log sheet
Bondstrand Bonder Training for PTSC M&C - 2009 51
Good tolerances control could ensure success in installation; reduce the possibility of leak at field joint; reduce the possibility of damage due to force on mismatched pipes; reduce/eliminate modification work, …
Recommended Fabrication Tolerances Installation Dimensional Tolerances
Refer to tolerance of different type of joints such as flange joint, mechanical o-ring joint.
Project specification
Fabrication and Installation Tolerances
Bondstrand Bonder Training for PTSC M&C - 2009 52
1. Face/center to face/center dimension, or location of attachment
2. Lateral translation of branch or connection
3. Rotation of flange
4. End preparation
5. Alignment of flange face
6. Angular deflection
7. Reference: ISO14692-4:2002
Recommended Fabrication Tolerances
Bondstrand Bonder Training for PTSC M&C - 2009 53
DN (Inch)
Tolerances / Dimension Number
1 (mm) 2 (mm) 3 (Degree) 4 (mm) 5 (mm) 6 (Degree)
½”-8” ±5 ±3 ±0.5 ±3 ±1 ±0.5
10”-12” ±5 ±3 ±0.3 ±3 ±1 ±0.5
14”-16” ±5 ±3 ±0.3 ±3 ±1.6 ±0.5
18”-24” ±6 ±5 ±0.3 ±3 ±2.0 ±0.5
26”-36” ±6 ±5 ±0.2 ±4 ±2.4 ±0.5
40”-48” ±6 ±5 ±0.15 ±5 ±2.4 ±0.5
Reference: ISO 14692-4:2002 and Ameron PF-01.
Recommended Fabrication Tolerances
Bondstrand Bonder Training for PTSC M&C - 2009 54
To prevent damage to both equipment and fiberglass piping system, attention shall be given when fiberglass piping is hooked up to equipment and other piping materials.
Hook-up to Equipment Equipment (Including fire hydrant, ballast eductor,
….) shall be independently anchored, Allowable alignment to avoid excessive stress, Control torque value strictly if equipment connection
is cast iron material, Dismantle piece is recommended for testing and
equipment maintenance.
Hook-up to Equipment / Other Material
Bondstrand Bonder Training for PTSC M&C - 2009 55
Fabricated Spool Testing System Hydro-testing
Part-5 : Hydro-testing
Bondstrand Bonder Training for PTSC M&C - 2009 56
Spool Testing is normally used to verify quality of fabrication joints (if applicable). Test pressure determination: 1.5 times of design pressure of
the weakest component on the spool. Recommended Test Duration: 10 minutes Special end blind/plug required for variety of spool end
configuration Limitation: Some fabricated spools could not be tested due
to end configuration and size : Spool with “Taper Male” end, Spool with QL Female and Taper Female and greater than 16” …….
Fabricated Spool Testing
Bondstrand Bonder Training for PTSC M&C - 2009 57
System Hydrotesting is carried out on installed piping system to verify fabricated joints, site joints, as well as the integrity of the installed piping system.
Prior to Hydro-Testing All piping supports must be completed; For underground piping, sufficient partial backfill and
temporary block must be in place to prevent excessive movement;
High point vents / low point drains in place; Removing/isolating components that shall be
excluded from hydro-testing;
System Hydro-testing
Bondstrand Bonder Training for PTSC M&C - 2009 58
Test Pressure 1.5 times of design pressure 1 hour holding minimum, or sufficient time to carry out
line check, or project specification whichever is longer Testing Equipment
Quick closing valve and booster pump without suitable control shall not be used, to avoid surge;
Pressure gauges and instrument must be calibrated; Appropriate pressure gauges shall be selected, the test
pressure shall be between 30% to 75% of reading range If possible, pressure recorder shall be used;
System Hydro-testing
Bondstrand Bonder Training for PTSC M&C - 2009 59
Hydro-Testing Pressure build up process:
The test pressure shall be raised over a period of 30minutes of longer.
Slowly and gradually to allow for equalizing for strain, and also in stages to allow for inspection.
Inspection Instrument reading Visual inspection of joints, pipes and fittings
24 hour holding @ 1.1 design pressure (ISO14692:4) Acceptance criteria
No sign of leaking or weeping No significant pressure lost
System Hydro-testing
Bondstrand Bonder Training for PTSC M&C - 2009 60
Possible causes of pressure change Effect of joint expansion and material creep; Effect of temperature (Morning, afternoon, night, under
sun, and so on), take precaution to prevent over-pressure Other Concerns
Glycol antifreeze shall be added when test is carry out in subzero temperature.
Instrument to prevent from buckling in case of sudden depressurization
Safety aspects, such as qualified operator, signs and notices, operation procedures …. Shall be in placed.
Reference: AME/INS-004 – “Hydro-Testing Procedure for Bondstrand GRE / GRV Pipe”