Bond Construction Bond Construction UpdateUpdate
Citizen’s Oversight Citizen’s Oversight CommitteeCommittee
Bond Construction Bond Construction UpdateUpdate
Citizen’s Oversight Citizen’s Oversight CommitteeCommittee
Long Beach Community College District April 26, 2010
EDUCATE ENGAGE EMPOWER 1
Agenda Latest Completed Construction Projects
PCC Industrial Tech Phase 1 (January 2010) Bldg. Z – Warehouse Retrofit (April 2010)
Current & Upcoming Construction Projects LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements LAC Building I (Bookstore)LAC Building I (Bookstore) PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit District Wide – Electronic Signage Plan LAC South Walkway Extension LAC Building P FPP Upcoming Projects
Planned Phasing of Future Projects
Q & A
2
Latest CompletedConstruction Projects
Modern facility houses Welding Department and other trade programs
Ribbon Cutting Ceremony April 2, 2010 New Northern face of the campus Buildings UU & VV demolition will be
completed April 2010 Exterior Lighting & Landscape
completion anticipated Summer 2010
PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1
Measure E 2002Measure E 2002
3
Facilities Department building retrofit from warehouse and classrooms to shop areas
Exterior car wash structure
Charging station for electrical powered vehicles
Additional Visitor’s Parking lot
Completed April 2010
Latest CompletedConstruction Projects
LAC Building Z – Warehouse RetrofitLAC Building Z – Warehouse Retrofit
Measure E 2002Measure E 2002
4
Current and UpcomingConstruction Projects
LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit
Measure E 2008Measure E 2008
5
Plans submitted to DSA September 2009 Adds 6,500 Sq. Ft. to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction end of Fall 2010
Current and UpcomingConstruction Projects
Completed Schematic Design Will house Math and Culinary Arts instructional
program as well as Reprographics Estimated start of construction Fall 2012
LAC Math Technology Building – Measure E 2008LAC Math Technology Building – Measure E 2008
6
Current and UpcomingConstruction Projects
LAC Parking Structure – Measure E 2008LAC Parking Structure – Measure E 2008
7
Spaces for 900 Vehicles Photovoltaic Electrical Generation Array on top level To be located Southeast corner of Lot J adjacent to the Verizon building Outfitted with single-axis tracking system Minimum 450 KW+ output Curriculum building opportunity Exhibit classroom Groundbreaking anticipated Summer 2010
Current and UpcomingConstruction Projects
LAC Building O Complex – Measure E 2008LAC Building O Complex – Measure E 2008
8
Two structures totaling 87,000 square feet
Current Occupants: ERD, Foundation, Warehouse
Facility, and one leasee Future Occupants:
IITS and BMT Potential rental spaces being
assessed Start of construction of
Building O1 began April 2010
9
LAC Infrastructure Improvement ProjectsLAC Infrastructure Improvement Projects
Measure E 2008Measure E 2008
Current and UpcomingConstruction Projects
Project to be completed in a phased construction schedule
Total annual estimated savings of 1.5 million Kwh
Project started Fall 2009. Anticipated completion Summer 2011; in Phase 3 and 3A currently
Upgrades include; Reclaimed Water, Domestic Water, Data, etc.
Majority of existing building HVAC systems to be connected to new infrastructure
Landscaping upgrades to be implemented in conjunction with infrastructure project phasing
Current and UpcomingConstruction Projects
10
Add additional 4,000 square feet to existing building
Architecture to match LAC Mediterranean Theme
Submitted for DSA review
Construction scheduled for Summer 2010
Bookstore Swing Space installation began April 2010
LAC Building I - Measure E 2008LAC Building I - Measure E 2008
Current and UpcomingConstruction Projects
PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002(Multi-Disciplinary Academic Building) - Measure E 2002
11
Currently out for bid Install portables for swing space Summer 2010 Anticipated start of MDAB construction Fall 2010 Project to be completed in two phases
Current and UpcomingConstruction Projects
PCC Building CC Retrofit - Measure E 2008PCC Building CC Retrofit - Measure E 2008
12
Currently in DSA for plan check Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices Swing space to be located on PCC Campus (Bldg. GG) To be completed concurrently with MDAB project phase 2 Anticipated start of construction 2012
Current and UpcomingConstruction Projects
District Wide – Electronic Signage PlanDistrict Wide – Electronic Signage Plan Measure E 2008Measure E 2008
13
District Wide Signage Plan complete for LAC & PCC Construction anticipated to start May 2010 Anticipated construction completion of Marquee Signs
Fall 2010
l i b
e r
a l
a r
t s
Liberal Arts CampusSite Plan
p a
c i f
i c
c
o a
s t
Pacific Coast CampusSite Plan
Current and UpcomingConstruction Projects
16
LAC Relocate Bond Management Team Offices to O Building and
remove W Trailers (Fall 2010) Increase parking at Faculty and Lew Davis St.
IITS relocation to O building Bldg. K – Roof extension over Kiln area Bldg. J – Theater lighting control panel replacement Bldg. E – Renovation upgrades CDC – new carpet installation Installation of Monument Signs at Conant/Clark and Bldg. O
(Summer 2010) PCC
Bldg. JJ – Add new landscaping around perimeter MDAB swing space preparation Installation of Monument Signs PCH/Walnut and 20th/Walnut
(Summer 2010)
Upcoming ProjectsUpcoming Projects
Planned Phasing of Future Projects
17
2009-10 Began infrastructure construction – Fall 2009
Master landscaping implementation will follow this project
Parking Structure – groundbreaking anticipated May 2010
Install portables for swing space at PCC – Summer 2010
Anticipating swing space move for Building A at LAC – Summer 2010
Planned Phasing of Future Projects
18
2010-11 Begin construction of Buildings DD and EE at PCC – Fall 2010
Marquees complete – Fall 2010
Begin construction of Building I (Bookstore) and move to portable swing space – Summer 2010
Building O2 occupancy scheduled
BMT and IITS – Fall 2010
Begin construction of Building A at LAC – Fall 2010
Begin schematic design of Math/Technology Building at LAC – Winter 2011
Begin Building R (Gym) HVAC and ADA upgrades – Winter 2011
Planned Phasing of Future Projects
19
2011-12 Infrastructure project complete at LAC – Summer 2011 Begin Schematic Design for Buildings C and F at LAC –
Summer 2011 Submit plans to DSA for Math/Technology Building at LAC –
Fall 2011 Anticipated construction completion of Parking Structure at
LAC – Fall 2011 Anticipated construction completion of Building I (Bookstore)
at LAC – Winter 2012 Anticipating construction completion of Building R (Gym)
HVAC and ADA upgrades - Winter 2012 Submit plans to DSA for Buildings C and F at LAC - Spring
2012 Begin schematic design for Building GG at PCC – Spring 2012
Planned Phasing of Future Projects
20
2012-13 Begin Schematic Design for Building M/N – Summer 2012
Construction completion of Buildings DD and EE at PCC – Summer 2012
Anticipated Construction completion of Building A at LAC – Summer 2012
Begin construction of Math/Technology Building at LAC – Fall 2012
Begin construction of Buildings AA, BB and CC at PCC – Fall 2012
Begin Schematic Design for Building GG at PCC – Fall 2012
Begin Schematic Design for Buildings J and P at LAC – Winter 2013
Begin Schematic Design for Building MM (Phase 1) at PCC – Winter 2013
Planned Phasing of Future Projects
21
2012-13 (continued) Move Buildings C and F programs into Swing Space (M/N
Building) and begin construction – Spring 2013
Submit plans to DSA for M/N Building at LAC – Spring 2013
Planned Phasing of Future Projects
22
2013-14 Submit plans to DSA for Building P at LAC and Building MM
(Phase 1) at PCC – Fall 2013
Begin schematic design for Building FF at PCC – Fall 2013
Submit plans to DSA for Building J at LAC – Fall 2013
Begin Schematic Design for Building D at LAC and Building MM (Phase 2) at PCC – Winter 2014
Anticipated Construction completion of Building CC at PCC – Winter 2014
Begin construction on Building GG at PCC – Winter 2014
Anticipated Construction completion of Buildings AA and BB at PCC – Spring 2014
Planned Phasing of Future Projects
23
2014-15 Submit plans to DSA for Building FF at PCC – Summer 2014
Begin construction on Building P at LAC and Building MM at PCC (Phase 2) – Fall 2014
Anticipated construction completion of Math/Technology Building at LAC – Summer 2014
Begin construction of Building M/N at LAC – Fall 2014
Anticipated construction completion of Buildings C and F at LAC – Fall 2014
Begin construction on Building J at LAC –Fall 2014
Submit plans to DSA for Buildings D at LAC and MM (Phase 2) at PCC – Winter 2015
Begin schematic design for Performing Arts Building (G & H) LAC – Winter 2015
Begin schematic design for Building E at LAC – Spring 2015
Planned Phasing of Future Projects
24
2015-16 Anticipated construction completion of Building GG at PCC –
Summer 2015
Anticipated start of construction of Building FF at PCC – Summer 2015
Submit plans to DSA for Performing Arts Building at LAC – Fall 2015
Begin construction on Building D at LAC and Building MM (Phase 2) at PCC – Winter 2016
Submit plans to DSA for Building E at LAC – Winter 2016
Anticipated construction completion of Building P at LAC – Spring 2016
Anticipated construction completion of Building J at LAC – Spring 2016
Planned Phasing of Future Projects
25
2016-17 Anticipated construction completion of Building FF at PCC – Fall
2016
Anticipated start of construction of Building E at LAC – Spring 2017
Anticipated construction completion – Spring 2019
Anticipated construction completion of Building M/N at LAC – Fall 2016
Anticipated construction completion of Building MM (Phase 1) at PCC – Winter 2016
Anticipated start of construction for Performing Art Building at LAC – Fall 2016
Anticipated construction completion – Fall 2018
Anticipated construction completion of Building D at LAC – Winter 2017
Begin schematic design for Building K at LAC – Winter 2017
Planned Phasing of Future Projects
26
2017-18
Anticipated construction completion of Building MM (Phase 2) at PCC – Summer 2017
Submit plans to DSA for Building K at LAC – Fall 2017 Anticipated start of construction Fall 2018
Anticipated completion Spring 2020