Bulk Water Supply in Limpopo
Integrating Infrastructure Delivery towards 2030
Summit
Peter Mokaba Stadium
5 and 6 October 2010
A.M. Matukane
2
Contents
1. Growth Points
2. Water Resources - Dams, Transfers, Ground water
3. ORWRDP, MCWAP, GLEWAP, LRGWS
- Description, Purpose, Map, Schedule, Risks and Mitigation
4. Regional Bulk Infrastructure Grant (RBIG)
5. Funding
6. Challenges
3
Bulk Water Supply in Limpopo
Growth Points
1. Polokwane
2. Elias Motswaledi
3. Makhado
4. Lephalale
5. Greater Tubatse
6. Greater Tzaneen
Growth Points
7. Phalaborwa
8. Thabazimbi
9. Mogalakwena
10.Marble Hall
11.Musina
12.Lepelle Nkumpi
4
Bulk Water Supply in Limpopo
• The growth points in red are, apart from existing supplies, currently not addressed by either Implementation Ready Studies (IRS) or by constructing of a water resource/services project.
• The other growth points are covered with an IRS or a phase of a regional bulk water project is under construction to alleviate the water problem
• The water resources and transfer schemes are to support the development of the different growth points in the province.
5
Bulk Water Supply in Limpopo
All Growth Points must have water supply schemes:
• A water resource – surface and/or groundwater• A water treatment plant• Pump stations• Regional Bulk – from source to and including
bulk reservoir • Internal Bulk– from bulk reservoir outlet to
reticulation connection• Reticulation– from internal bulk end to
household meter
6
Bulk Water Supply in Limpopo
DWA has constructed many major dams in Limpopo in the past which supply water to people and other users, namely:
• Nzhelele, Vondo, Damani, Lupepe-Nwanedi in Vhembe
• Middle Letaba, Ebenezer, Tzaneen, Thabina, Tours, Blydepoort in Mopani
• Mokolo, Doorndraai, Glen Alpine in Waterberg• Houtrivier, Chuene, Molepo in Capricorn• Vergelegen, Nkadimeng, Piet Gouws, Flag
Boshielo in Sekhukhune
7
Bulk Water Supply in Limpopo
DWA is developing the major dams in Limpopo:• Inyaka (now in Mpumalanga)• Nandoni in Vhembe District• Flag Boshielo Raising, and• De Hoop in Sekhukhune District- construction
50% completed• Nwamitwa in Mopani District in planning• Possible dam in Olifants river under investigation
8
Bulk Water Supply in Limpopo
DWA is planning and developing major water transfer schemes in Limpopo from:
• Inyaka (now in Mpumalanga) to Acornhoek• Nandoni in Vhembe District to Makhado,
Matoks, Giyani, etc• Flag Boshielo to Pruissen at Mokopane• De Hoop in Sekhukhune District to Burgersfort,
Tubatse, Lebowakgomo and Polokwane (ORWRDP)
• Crocodile river to Lephalale (MCWAP)• Groblersdal to Moutse West
9
Bulk Water Supply in Limpopo
Major Schemes1. Olifants River Water Resources
Development Project (ORWRDP)2. Mokolo & Crocodile Water Augmentation
Project (MCWAP)3. Groot Letaba Water Augmentation Project
(GLeWAP)4. Luvuvhu River Government Water Scheme
(LRGWS) – Nandoni Distribution Scheme 5. Water Services
10
1. ORWRDP PHASE 2: DESCRIPTION & PURPOSE
• 88m high De Hoop Dam (R3 075 million) on Steelpoort River – Implementation by DWA
• Extensive bulk distribution systems (pump stations, balancing dams and pipelines) from De Hoop and Flag Boshielo Dams (R12 981 million)
• Implementation by TCTA• Primary water supply in Middle Olifants River
catchment area – Regional Bulk and Reticulation (R6 812 million)
• Industrial water for mining on eastern limb of
Bushveld Igneous complex
11
1. ORWRDP (DE HOOP)REGIONAL BULK AND PRIMARY RETICULATION TO HOUSEHOLD
FEASIBILITY STUDIES
Bulk and Internal Bulk (Rand million)
Reticulation (Rand million)
Total (Rand million)
MOOIHOEK TO TUBATSE AND BURGERSFORT
590 202 792
DE HOOP TO JANE FURSE AND NEBO PLATEAU
1110 422 1531
PRUISSEN TO MOKOPANE AND MOGALAKWENA LM
1141 184 1325
OLIFANTSPOORT TO CAPRICORN (LEPELLE-NKUMPI).
393 228 621
OLIFANTSPOORT TO POLOKWANE (OLIFANTS SAND)
1380 107 1487
OLIFANTSPOORT SOUTH (FETAKGOMO).
341 32 373
LEBALELO 552 130 681
TOTAL 5507 1305 6812
12
13
1. ORWRDP PHASE 2: SCHEDULE(Subject to availability of funding)
• 2A: June 2007 – Mar 2013• 2B: Jul 2011 – Dec 2013• 2C: Jul 2011 – June 2013 (Steel Bridge: July
2012)• 2D: Jul 2011 – June 2013• 2E: April 2012 – March 2014• 2F: April 2012 – March 2014• 2G: April 2012 – March 2014• 2H: Incorporated by March 2013
14
1. ORWRDP PHASE 2:PROJECT RISKS & MITIGATION
• Level of commitment by mines and municipalities due to effects of ongoing global recession
• High social demands• Affordability• High cost of scheme• Reliance on electricity for
pumping• Alignment of completion of
water resources & services infrastructure
• Implement GWW with government funding
• Implement WC & DM• Government funding• Step wise implementation
within funding constraints• Align with Eskom’s
developments• Aligned planning and water
supply agreements
15
2. MCWAP: DESCRIPTION & PURPOSE
• Augmented water supply in the Lephalale area to meet the water requirements of the Medupi Power Station, and the future water requirements related to the expected growth in the Lephalale Municipality
• Industrial water for possible CTL plant by Sasol• Phase 1 (R2 059 million) includes a new pump station at Mokolo
Dam and pipeline to Medupi and Matimba Power Station, Exxaro mine and Lephalale town
• Sub-phase 2A (R13 455 million): Abstraction works at Vlieëpoort and BDS to Steenbokpan and Lephalale areas
• Sub-phase 2B (R1 590 million): Duplication of BDS• Social/Commercial portion on/off-budget• TCTA implementing agent• Regional Bulk and Reticulation (R 330 million)
16
17
2. MCWAP: SCHEDULE(Subject to environmental authorisation and
Integrated Resource Plan (IRP) for electricity)
• MCWAP-1: July 2011 – July 2013• MCWAP-2A: Jan 2013 – Dec 2016• MCWAP-2B and further phases: Depends on
IRP and investment decisions by the private sector and other stakeholders
18
2. MCWAP-1 AND 2A:PROJECT RISKS & MITIGATION
• Likelihood of appeals against environmental authorisation high
• Very tight construction programme
• Affordability of water by social users
• Delayed IRP for electricity• High dependence on single
resource, i.e. Mokolo Dam
• Concerted efforts to deal swiftly with possible appeals
• Efficient implementation strategies and contract management
• Government funding• Co-operative governance• Investigate and implement
additional and alternatives sources
19
3. GLeWAP: DESCRIPTION & PURPOSE
• 36m high Nwamitwa Dam (R1 262 million) on Groot Letaba River – Implementation by DWA
• 3m raising of Tzaneen Dam (R84 million)• Regional Bulk Water supply (R410 million)• Provide primary water requirements in Mopani District• To implement the preliminary Reserve in compliance with the
National Water Act• To stabilise the assurance of supply to the existing irrigation
farming• To improve water availability for the establishment of resource-
poor irrigation farmers
20
21
3. GLeWAP: SCHEDULE(Subject to environmental authorisation and funding)
• Tzaneen Dam Raising: 2013/14• Nwamitwa Dam: 2016/17• Regional Bulk: 2015/2016
22
3. GLeWAP: PROJECT RISKS & MITIGATION
RISKS MITIGATION
Likelihood of appeals against environmental authorisation
Concerted efforts to deal swiftly with possible appeals
Very tight construction programme
Efficient implementation strategies and contract management
Affordability of water by social users
Government funding
Funding constraints Phased implementation & rescheduling
Skills shortage Training programmes
23
4. LRGWS – Nandoni Distribution Scheme: Description & Purpose
• The Nandoni Dam and Distribution scheme forms part of the larger Luvhuvhu River Government Water Scheme (LGWS) which also includes the Xikundu scheme
• The project was initiated to provide potable water to the area between Thohoyandou and Makhado after the completion of the Nandoni Dam
• The Nandoni Distribution projects were started in 2005 in conjunction with the Nandoni WTW after completion of the Nandoni Dam and includes:– 3 bulk pipelines takes water from Nandoni WTW to various reservoirs– NR6 and NN20B pipelines takes water in a northerly direction– 3 bulk pipelines takes water from Nandoni WTW to various reservoirs– NR5 pipeline takes water in a southern and western direction
• Estimated cost for the completion Nandoni Distribution Scheme is R701 million
24
25
4. LRGWS: SCHEDULE• DWA approved the accelerated plan to complete the Nandoni
Distribution Scheme’s bulk water pipelines up to the Valdezia Reservoir• Tender for PSPs to redesign the bulk water pipelines did close • Water delivery dates are as follows:
– Thohoyandou CBD (via NR6 Reservoir and Rising Main) by October 2011
– Mavambe to Gumbani and Mudabula (via Mavambe to Gumbani Rising Main, Gumbani Reservoir and Pump Station). Water was already being delivered as from 17 June 2010 Greater Vuwani Area(Vuwani (NR7) Reservoir and Rising Main) by August 2012
– Valdezia Area (Valdezia Reservoir and Rising Main) by November 2012
– Mushiri, Mahagala and Lambani (Lambani Gravity Main) by October 2011
– Peri-urban areas east of Thohoyandou (NN20B Reservoir and Rising Main) by October 2011
• The water from the bulk distribution systems will feed into the existing local reticulation systems
26
4. LRGWS: PROJECT RISKS & MITIGATION
RISKS MITIGATION
Quality control of construction Adequate site supervision including dedicated Resident Engineer
Productivity of local labour Implementing management controls to increase productivity
Condition of existing municipal water infrastructure
Municipal infrastructure refurbished or replaced by Municipalities where critical e.g. control valves at reservoirs
Extended lifespan of bulk water infrastructure (quality of materials and installation)
Independent 3rd party inspectors and warrantees
27
Bulk Water Supply in Limpopo - RBIG
Scheme
District Municipality (Water Services Authority)
Total Project Costs
RBIG Expenditure to date (2007/8/9/10)
RBIG Budget
2010/11 RBIG Budget
2011/12RBIG Budget
2012/13
Olifantspoort WTW Capricorn 303,527,528 173,000,000 23,000,000 20,000,000 0
Specon BWS Capricorn 74,316,000 39,500,000 19,000,000 0 0
Mametya Sekororo Mopani 214,000,000 10,000,000 7,000,000 48,000,000 51,789,000
Giyani BW Supply Drought Relief Mopani 252,000,000 0 54,000,000 0 0
Groblersdal Lukau BWSGreater
Sekhukhune 36,208,000 30,508,523 0 0 0
Nebo BWSGreater
Sekhukhune 1,379,480,000 53,934,769 28,000,000 60,000,000 77,000,000
Mooihoek/Tubatse BWSGreater
Sekhukhune 1,000,000,000 50,956,728 13,000,000 48,000,000 70,000,000
Sinthumule Kutama BWA Vhembe 454,979,475 34,314,595 16,000,000 51,000,000 44,500,000
Mogalakwena BWS Mogalakwena 1,530,000,000 66,571,832 27,000,000 60,000,000 82,700,000
5,244,511,003 458,786,447 187,000,000 287,000,000 325,989,000
Table 1: List of RBIG projects and funding for 2010/11, 2011/12 and 2012/13
28
Bulk Water Supply in Limpopo - RBIG
Estimated total cost of 9 projects
R 5 244 511 003
Minus RBIG expenditure 2007/8/9/10
R 458 786 447
Minus RBIG Budget 2010/11/12/13
R 799 989 000 R 1 258 775 447
Shortfall for 9 current projects to be completed
R 3 985 735 556
29
Bulk Water Supply in Limpopo - RBIG
• In addition to the projects being implemented, Table 2 illustrates projects at feasibility, or implementation ready study stage that were funded through the RBIG.
30
Bulk Water Supply in Limpopo - RBIG
Scheme
District Municipality
(Water Services Authority)
Total Project Costs
RBIG Expenditure
to date (2007/8/9/10)
RBIG Budget 2010/11
RBIG Budget2011/12
Ohrigstad Greater Sekhukhune
450 000 000 949 554 0 0
Lebalelo Central & North RWS
Greater Sekhukhune
600 000 000 2 397 573 0 0
Nwamitwa RWS Scheme(Great Letaba)
Mopani 644 000 000 3 122 166 0 0
Nzhelele Valley BWS Vhembe 600 000 000 1 983 685 0 0
Makhado West and Extension to Nandomi Dam
Vhembe 400 000 000 4 005 464 0 0
Matoks RWS Capricorn 1 000 000 000 2 335 362 0 0
Glen Alphine RWS Capricorn 345 000 000 2 897 726 0 0
Lephalale - Bulk Water Augmentation(Eskom)
Waterberg 330 000 000 5 049 991 1 000 000 0
Magalies Water to Waterberg
Waterberg 800 000 000 2 800 986 0 0
Sub Total 5 169 000 000 25 542 507 1 000 000 0
31
Bulk Water Supply in Limpopo - RBIG
Minus RBIG expenditure 2007/8/9/10
R 25 542 507
Minus RBIG Budget 2010/11/12/13
R 1 000 000 R 26 542 507
Estimated total cost of 9 IRS projects to implement
R 5 169 000 000
Shortfall for 9 current projects to be completed
R 3 985 735 556
Shortfall for 9 current IRS projects to be constructed
R 5 169 000 000
Total Shortfall R 9 154 735 556
32
Bulk Water Supply in Limpopo
FUNDING• The dams are funded by National Treasury• Funds not so easily available for RBIG and Reticulation
through MIGExample: • De Hoop is funded at R3 billion by National Treasury. • Bulk Distribution and reticulation to Households require R20
billion. • R1.2 billion is available from 2007 to 2013 through RBIG and
MIG. • Shortfall of R18.8 billion is needed to serve 2 million people
and mining.• Mines and Municipalities not in a position to sign off take
agreements with DWA.
33
Bulk Water Supply in Limpopo
Example:• RBIG is funding a pipe line from Steelbridge to
Jane Furse – 70% completed• Sekhukhune DM with MIG is on tender for WTW
at Steelbridge and 10 Megaliter reservoir at Jane Furse for completion July 2012.
• DWA has to do Phase 2C pipe from De Hoop Dam to Steelbridge for completion July 2012 depending on funding from National Treasury.
34
Life cycle planning Cost of the Business
Planning Design Procure Construct Operate Maintain Refurb.
0,2% 2% 17% 44%
Typical % of Total Cost over the Life of Water Supply InfrastructureTypical % of Total Cost over the Life of Water Supply Infrastructure
37% Financing Cost
Based on actual local government case study (Paul le Roux)Based on actual local government case study (Paul le Roux)
35
Limpopo PictureRand (bil)
Identified Projects including: 59.3
•ORWRDP (De Hoop)
•MCWAP (Lephalale)
•GLeWAP (Nwamitwa)
•Waste Water Treatment Works
Capital = 20% 60.0
O&M 20 years = 40% 120.0
Financing 20 years = 40% 120.0
Total 300.0
36
Needs Classification/Definition – Water Services
Community with no
water services at all
ExtensionU
pgrade
Infrastru
cture
needs
O&M needs
Resource needs
Ma
na
ge
me
nt
Refurbishm
ent Deman
d
man
agem
ent
Local s
ource
development
Regional Bulk
Internal Bulk
Sew
erag
e w
orks
Pur
ifica
tion
plan
ts
Interim
Permanent
Illegal settlement
Formal rural Housing ProgramBackyard dwelling
Shared services
37
Needs Classification/Definition - Sanitation
Households with no
sanitation services at
all
RDP – Pit/less
than VIP
Basic but not
appropriate
Infrastru
cture
needs
O&M needs
Existing Services that
needs to be replaced
Ma
na
ge
me
nt
Refurbishm
ent Bucke
ts
Other
Other
Programmes
Health Sanitation
needs
Sch
ools
S
anita
tion
need
s
Interim
Permanent
Illegal settlement
Formal rural Housing ProgramBackyard dwelling
Shared services
38
Backlog on Water: Households
Priority (Infrastructure Status)PriorityAdequate 0No Water Services 1Inadequate Infrastructure: Need Extensions 2Inadequate Infrastructure: Need Upgrade 3Inadequate Resources 4Inadequate Management: O & M 5Inadequate Management: Refurbishment 6Inadequate Housing: Interim 7Inadequate Housing: Permanent 8
39
LIMPOPO WATER CHALLENGES
EQUITABLE SHARES
• Currently R5 / kiloliter (1000 liters)
• ORWRDP at Nebo estimated R25 / kiloliter (1000 liters)
• 85% indigents to get 6 kiloliter free
• 200 000 households (4 people / hh) x 6kl x 12months x R20 = R288 mil per year
40
STRATEGIC TARGETS / BACKLOG ERADICATION PROGRESS AND
CHALLENGES• Total Water Business – Industry, Agriculture, Tourism and
People• Single Purpose Dams• Water Services Provider – Cross Border Issues• WSDP requirements – Water Resource Planning & Internal
Strategic Perspective• Priorities of backlogs• Eradicate per priority• Water Resource shortfall (De Hoop)• Funding shortfall – RBIG, MIG, ACIP• Water Services Reference Framework - MIG Projects
outstanding• Redesign EQUITTABLE SHARE formula
41
STRATEGIC TARGETS / BACKLOG ERADICATION PROGRESS AND
CHALLENGES Cont…..
• Materials availability• Manpower• Inexperienced PSPs and Contractors• Supply Chain• Not enough resources to support Population
Growth• Population development require higher water
needs
42
THANK YOU